Upload
truongkhuong
View
220
Download
0
Embed Size (px)
Citation preview
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Index
1
INDEX
1 EXECUTIVE SUMMARY ......................................................................................... 4
2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION ...... 6
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT ........................................ 6
2.2 NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY/ REGION ........... 7
2.3 DEMAND – SUPPLY GAP ...................................................................................................... 8
2.4 IMPORTS VS. INDIGENOUS PRODUCTION ....................................................................... 8
2.5 EXPORT POSSIBILITY ........................................................................................................... 8
2.6 DOMESTIC/EXPORT MARKETS .......................................................................................... 8
2.7 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT .... 9
3 PROJECT DESCRIPTION ........................................................................................ 9
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT PROJECTS, IF
ANY ........................................................................................................................................... 9
3.2 LOCATION ............................................................................................................................... 9
3.3 DETAILS OF ALTERNATE SITES ......................................................................................... 4
3.4 SIZE OR MAGNITUDE OF OPERATION .............................................................................. 4
3.4.1 REGIONAL GEOLOGY………………………………………………………………….4
3.4.2 LOCAL GEOLOGY:- …………………………………………………………………… 6
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS ........................................................ 7
3.5.1 YEARWISE PRODUCTION DETAILS ………………………………………………….7
3.5.2 PROPOSED METHOD OF MINING: …………………………..……………………….7
3.5.3 EXTENT OF MECHANIZATION……………………………………………………….8
3.5.4 CONCEPTUAL MINING PLAN………………………………………………………… 9
3.5.5 DRILLING…………………………………………………………………………………. 1 0
3.5.6 BLASTING………………………………………………………………………………… 1 0
3.6 RAW MATERIAL REQUIRMENT ....................................................................................... 11
3.7 RESOURCES OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN THE
PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED .................................................. 11
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Index
2
3.8 AVAILABILITY OF WATER& ITS SOURCE, ENERGY /POWER REQUIREMENT AND
SOURCE .................................................................................................................................. 11
3.9 QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND SCHEME
FOR THEIR MANAGEMENT/DISPOSAL ........................................................................... 12
4 SITE ANALYSIS ....................................................................................................... 12
4.1 CONNECTIVITY (Mine Site) ................................................................................................ 12
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP ...................................................... 12
4.3 TOPOGRAPHY ....................................................................................................................... 13
4.4 EXISTING LAND USE PATTERN ....................................................................................... 13
4.5 EXISTING INFRASTRUCTURE ........................................................................................... 14
4.5.1 WATER ………………………………………………………………………………14
4.6 CLIMATE ................................................................................................................................ 15
4.7 SOCIAL INFRASTRUCTURE AVAILABLE ....................................................................... 15
5 PLANNING BRIEF ................................................................................................... 15
5.1 PLANNING CONCEPT .......................................................................................................... 15
5.2 POPULATION PROJECTION ............................................................................................... 15
5.3 LAND USE PLANNING ........................................................................................................ 17
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND ........................................................... 18
5.5 AMENITIES/FACILITIES ...................................................................................................... 18
6 PROPOSED INFRASTRUCTURE ......................................................................... 19
6.1 INDUSTRIAL AREA (PROCESSING AREA) ...................................................................... 19
6.2 RESIDENTIAL AREA (NON PROCESSING AREA) .......................................................... 19
6.3 GREEN BELT ......................................................................................................................... 19
6.4 SOCIAL INFRASTRUCTURE ............................................................................................... 19
6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL / METRO
/WATER WAYS ETC)............................................................................................................ 19
6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER) .................... 19
6.7 SEWAGE SYSTEM ................................................................................................................ 19
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Index
3
6.8 INDUSTRIAL WASTE MANAGEMENT ............................................................................. 20
6.9 SOLID WASTE MANAGEMENT ......................................................................................... 20
6.10 POWER REQUIREMENT & SUPPLY/SOURCE ................................................................. 20
7 REHABILITATION AND RESETTLEMENT (R & R PLAN) ........................... 20
7.1 POLICY TO BE ADOPTED. .................................................................................................. 20
8 PROJECT SCHEDULE AND COST ESTIMATES .............................................. 20
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF
COMPLETION ........................................................................................................................ 20
8.2 ESTIMATED PROJECT COST AND ALONG WITH ANALYSIS IN TERMS OF
ECONOMIC VIABILITY OF THE PROJECT ...................................................................... 20
9 ANALYSIS OF PROPOSAL .................................................................................... 21
10 ENVIRONMENT MANAGEMENT PLAN .................................................................. 22
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
4
1 EXECUTIVE SUMMARY
The Miragpur Manganese Ore Deposit of M/s. Anik Industries Limited is
situated Near Village Miragpur, Tehsil Katangi, District Balaghat (Madhya
Pradesh)over an area of 130.0hainforest land of compartment No. 551 A& B. Letter
of Intent (LOI) issued from Mineral Resource Department of M.P vide their order no.
F-2-173/2008/12-2 dated 31.10.2015 for a period of fifty years from the date of
execution of lease deed and require consent for Manganese Ore under section (5)of
the Mines & Minerals (Development & Regulation) Act 1957 is given by Central
Government vide their letter no. 5/291/2008-M-IV dated 13.08.2009.
The Mining Plan with PMCP has been approved by Indian Bureau of Mines &
Geology, Department of Mines Jabalpur vide letter No.BGT/MN/MPLN-
1168/NGP/2015/2265 dated25/07/2016.
The mining will be carried out by fully mechanized method as per the approved
Mining Plan only. The entire mining area is Forest Land falls in Forest Compartment
No. 551 A& B. As per MCR 1960 & MCDR 1988, validity of mining is 50 years
from the date of execution of lease deed. The proposed production is 26460 Tonne.
The estimated cost of project will be Rs. 5, 01, 00,000 /-.
Manganese mines of Madhya Pradesh and Maharashtra have good quality high grade
manganese which is used in metallurgical industry as ferro-alloys and manganese
metals. Manganese ore is used in the manufacture of porcelain, enamel, dry battery,
building bricks, glazed pottery, floor tile, plastics, welding rods, chemicals, varnish
and electric bulbs etc. Manganese sulphate is used in fertilizer industry. Large
proportion of manganese is required in the metallurgy of iron and steel. The ore grade
of the mine is most suitable for Ferro- Silico-Manganese manufacturing. Most of the
ore is sold to Ferro-Silico Manufacturers.
Manganese is one of the most widely used metals next to iron, Aluminum and
Copper. Majority of the industrial quality of Manganese in India was exported to
other countries of the world till late sixties. With gradual growth of indigenous
industry, the domestic consumption of Manganese ore has increased to almost total
consumption.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
5
Table1: Salient Features of the project site
S.NO. Particulars Details
A. Nature of the Project Miragpur Manganese Ore Deposit
B. Size of the Project
1. Mine Area 130.0ha
2. Proposed Production capacity 26,460 MT
C Location Details
1. Village Miragpur
2. Tehsil Katangi
3. District Balaghat
4. State Madhya Pradesh
5. Latitude & Longitude Pillars Latitude (N) Longitude (E)
1 21°38'28.85" 79°46'16.13"
2 21°38'28.90" 79°46'19.20"
3 21°38'22.63" 79°46'36.11"
4 21°38'13.78" 79°46'52.14"
5 21°38'10.58" 79°47'03.10"
6 21°38'03.95" 79°47'18.23"
7 21°38'01.30" 79°47'15.8"
8 21°38'04.31" 79°47'09.42"
9 21°37'53.8" 79°47'07.92"
10 21°37'49.2" 79°47'2.51"
11 21°37'47.74" 79°47'04.21"
12 21°37'46.46" 79°46'41.00"
13 21°37'48.1" 79°46'38.6"
14 21°37'48.42" 79°46'28.64"
15 21°37'48.54" 79°46'23.80"
16 21°37'53.96" 79°46'25.63"
17 21°38'03.45" 79°46'21.14"
18 21°38'10.13" 79°46'20.70"
19 21°38'17.87" 79°46'18.18"
20 21°38'24.59" 79°46'18.07"
21 21°38'27.90" 79°46'16.32"
6. Toposheet No. 55 O/9, 55 O/10, 55 O/13, 55 O/14
D Environmental Settings of the Area
1. Ecological Sensitive Areas The following Protected & Reserved Forests fall within
15 km radius of Buffer zone:
S. No. P.F./R.F. Distance Direction
1. KHAPUR WIHARI R.F 2.0 KM SE
2. P.F 2.0 KM NE
3. GARRA GHAT R.F 1.0 KM NORTH
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
6
S.NO. Particulars Details
4. R.F 2.50 KM WEST
5. MOHAGOANGHAT R.F 7.05 KM SE
6. PHULCHUR R.F 8.66 KM SE
7. CHANDPUR FOREST 5.0 KM SOUTH
2. River / water body Available water bodies and rivers falls within 15 Km
radius Buffer zone as follows:
S. No. Water bodies/River Distance Direction
1. BILONI NADI 1.42 KM SW
2. BHAWANTHARI
RIVER
4.57 KM SW
3. DHORIYA NALLH 5.0 KM WEST
3. Nearest Town / City Katangi-14.90 km, NNE
4. Nearest Railway Station The nearest railway station is Katangiwhich is about
14.90KmsNNEfrom mine site.
5. Nearest Airport Nagpur Airportis about 89.43 Km in SW direction.
6. State Boundary Interstate Boundary of Madhya Pradesh and Maharashtra lies
at a distance of 4.22 km from the site.
7. Seismic Zone Zone – III [as per IS 1893 (Part-I): 2002]
D Cost Details
1.
Total Project Cost
Fixed Cost: Rs. 5,01,00,000 /-
Operating Cost: Rs. 2,90,28,000/-
E Requirements of The Project
1. Proposed Water Requirement 10.0KLD
2. Fuel requirement 150 LPD
3. Man Power Requirement 31 (Skilled and unskilled persons)
2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
2.1 IDENTIFICATION OF PROJECT AND PROJECT PROPONENT
The Miragpur Manganese Ore Deposit of M/s. Anik Industries Limited is situated
Near Village Miragpur, Tehsil Katangi, District Balaghat (Madhya Pradesh) over an
area of 130.0 ha in forest land of compartment No. 551 A& B. Letter of Intent (LOI)
issued from Mineral Resource Department of M.P vide their order no. F-2-
173/2008/12-2 dated 31.10.2015 for a period of fifty years from the date of execution
of lease deed and require consent for Manganese Ore under section (5) of the Mines
& Minerals (Development & Regulation) Act 1957 is given by Central Government
vide their letter no. 5/291/2008-M-IV dated 13.08.2009.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
7
2.2 BRIEF DESCRIPTION OF THE NATURE OF PROJECT
As per EIA Notification dated 14th Sep, 2006 and as amended till date, the project
falls under, Category “A”. It has been proposed to excavate approximately 26460TPA
of Manganese Ore from forest Compartment No. 551 A& B by fully mechanized
method. The lease area is 130.00 ha. Total mineable reserve available is 1, 18,857 MT
of Manganese Ore Mineral. The expected life of mine is 11 years. O.B. and waste/
sub-grade generated during the five year plan period will be 7515 m3&4536
m3respectively. The Manganese ore will be transported through trucks/dumper.
At the end of lease period (130.00 ha), the total excavated area will be 5.5878 ha out
of which 3.9778 hect area will be converted into water reservoir & 1.6100 hect will be
backfilled & covered by plantation. Water reservoir will ultimately help in recharging
the ground water table and also used for irrigation purpose. The depth of water table is
30m (Pre-Monsoon) to 25 m (Post-Monsoon) below the general ground level. The
depth of water table is 18 m BGL. Thus ground water table will not be encountered
during working in the mine.
2.2 NEED FOR THE PROJECT & ITS IMPORTANCE TO THE COUNTRY/
REGION
Mining of manganese ore has been practiced since ancient times in central India, as
high grade manganese occurs in this region. Manganese mines of Madhya Pradesh
and Maharashtra have good quality high grade manganese which is used in
metallurgical industry as ferro-alloys and manganese metals. Manganese ore is used
in the manufacture of porcelain, enamel, dry battery, building bricks, glazed pottery,
floor tile, plastics, welding rods, chemicals, varnish and electric bulbs etc. Manganese
sulphate is used in fertilizer industry. Large proportion of manganese is required in
the metallurgy of iron and steel. The ore grade of the mine is most suitable for Ferro-
Silico-Manganese manufacturing. Most of the ore is sold to Ferro-Silico
Manufacturers.
Besides this, the project will prove beneficial in terms of socio-economic
development as it will provide employment to locals. Further, the average income
level, which is the indicator of socio – economic status of households is expected to
increase, which will ultimately result in better standard of living of the local people.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
8
2.3 DEMAND – SUPPLY GAP
Manganese is one of the most widely used metals next to iron, Aluminium and
Copper. Majority of the industrial quality of Manganese in India was exported to
other countries of the world till late sixties. With gradual growth of indigenous
industry, the domestic consumption of Manganese ore has increased to almost total
consumption.
About 96% of manganese ore is used in the metallurgical industry as ferro-alloys and
manganese metals. Manganese ore is used in the manufacture of porcelain, enamel,
dry battery, building bricks, glazed pottery, floor tile, plastics, welding rods,
chemicals, varnish and electric bulbs etc. Manganese sulphate is used in fertilizer
industry. Large proportion of manganese is required in the metallurgy of iron and
steel. It acts as a deoxidizer in the manufacture of nickel and other non-ferrous metals.
It is also used in the manufacture of special electrodes. The use of electrolytic
manganese in metal industries can be justified only if its price difference over that of
other alloys is maintained. Approximately half of the electrolytic manganese is
utilized in the ferrous production and the other half in non-ferrous production such as
copper, nickel, aluminium and magnesium alloys.
2.4 IMPORTS VS. INDIGENOUS PRODUCTION
Manganese produced from the proposed Manganese ore mine will be used in
metallurgical industry such as ferro-alloys and manganese metals.
2.5 EXPORT POSSIBILITY
Not applicable as the manganese production from the mine will be for domestic use.
2.6 DOMESTIC/EXPORT MARKETS
Domestic demand is one of the chief reasons for the rapid growth of Manganese Ore
business in India. Thus, domestic market for Manganese Ore for metallurgical
industry is well established. Manganese ore is used in the manufacture of porcelain,
enamel, dry battery, building bricks, glazed pottery, floor tile, plastics, welding rods,
chemicals, varnish and electric bulbs etc. No export will be done.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
9
2.7 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE
PROJECT
The total number of manpower is required for the mining activity is 31people.
Priority for employment will be given to local workers. Following staff & workers are
proposed to be employed:-
Table 2: Manpower requirement
1. Supervisory Staff 1
2. Mining Engineer 1
3. Geologist 1
4. Excavator Operator 1
5. Time Keeper/ Store Keeper
cum first aider
1
6. Gardener/ Watchman/ Pump
Operator
1
7. Labour 25
Total 31
3 PROJECT DESCRIPTION
3.1 TYPE OF PROJECT INCLUDING INTERLINKED AND INDEPENDENT
PROJECTS, IF ANY
The mining of Manganese Ore is carried out by fully mechanized method.
This is an independent project. No interlinked project is proposed.
3.2 LOCATION
The Miragpur Manganese Ore Deposit mine area falls in forest compartment
No. 551 A& B of, village Miragpur, Tehsil -Katangi, District -Balaghat, State Madhya
Pradesh over an area of 130.00 ha. The project site falls in Survey of India Toposheet
No. 55 O/9, 55 O/10, 55 O/13, 55 O/14.
The geographical location with respect to boundary pillars of the proposed
Manganese Ore area are:-
Table 3: The geographical location with respect to boundary pillars
Pillars Latitude (N) Longitude (E)
1 21°38'28.85" 79°46'16.13"
2 21°38'28.90" 79°46'19.20"
3 21°38'22.63" 79°46'36.11"
4 21°38'13.78" 79°46'52.14"
5 21°38'10.58" 79°47'03.10"
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
10
6 21°38'03.95" 79°47'18.23"
7 21°38'01.30" 79°47'15.8"
8 21°38'04.31" 79°47'09.42"
9 21°37'53.8" 79°47'07.92"
10 21°37'49.2" 79°47'2.51"
11 21°37'47.74" 79°47'04.21"
12 21°37'46.46" 79°46'41.00"
13 21°37'48.1" 79°46'38.6"
14 21°37'48.42" 79°46'28.64"
15 21°37'48.54" 79°46'23.80"
16 21°37'53.96" 79°46'25.63"
17 21°38'03.45" 79°46'21.14"
18 21°38'10.13" 79°46'20.70"
19 21°38'17.87" 79°46'18.18"
20 21°38'24.59" 79°46'18.07"
21 21°38'27.90" 79°46'16.32"
The location map is given below: -
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
4
Figure-1: Location Map
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
4
3.3 DETAILS OF ALTERNATE SITES
Mining activity is site specific hence no alternative sites examined.
3.4 SIZE OR MAGNITUDE OF OPERATION
Mine area for the Manganese Ore Deposit mine is 130.00 ha and production
capacity is 26,460 TPA.
3.4.1 REGIONAL GEOLOGY
Regionally the area belongs to Mesoproterozoic age. In Nagpur District rock
formation ranges in age from Archaean to Recent. Tirodi Gneissic Complex of
Archaean to Palaeozoic age (2500-2200 my) comprising Migmatite, Orthogneiss and
Granulites occupies the eastern and northeastern part. Sakoli group of meso
Proterozoic age (2000 – 16000 my) occupies the southern part and comprises Mica
Schist, Phyllite and Carbonaceous PhylliteMetabasalt with associated tuff,
Metarhyolite and felsic volcanics with associated tuff. Sausar Group of Meso
Proterozoic age occupies the northern part and comprises Quartz Muscovite Schist,
Feldspar Muscovite Schist and Intercalated Quartzite (Sitasawangi Formation), Calc
Gneiss and ManganiferrousMarble with pockets of Manganese Ore (Lohangi
Formation) Muscovite Biotite Schist with Manganese Ore (Mansar Formation),
Quartzite and Quartz Muscovite Schist (chorbaoli Formation), Muscovite Biotite
Schist and Quartz Biotite Granite (Junewani Formation) and crystalline Limestone
and Dolomite (Bichua Formation) area is repeatedly tight folded. The Saunsar Group
is a store house of Manganese Ore Deposit. Talchir formation of Carboniferous to
Permian age (345 – 230 my) and Kamthi Formation of Permian to Triassic age (280 -
195 my) of Gondwana Super Group are exposed around Umrer, Savner and Kamthi.
Almost half of the district in its western and southern parts is occupied by the Deccan
Trap comprising 6 km thick pile of basaltic flows of Cretaceous to Palaeogene age
(60-62 my). At some places Intertrappeans (sedimentary) beds separate the individual
flows. Isolated laterite cappings are found around Kondhali. Alluvial deposits of
Pleistocene to Recent age are found along Kanhan, Jam Wine and Sur rivers.
The Precambrian manganiferrous ENE-WSW trending Sausar Group of rocks occur
in the northern parts of the Maharashtra and southern parts of the Madhya Pradesh.
SynsedimentarySrtatiform Manganese Ore Deposit of this area mainly associated with
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
5
the Psammo-pelitic Rocks of the Saunsar Group. The Saunsar Group comprises
mainly Quartz Mica Schist, Quartzite, Calc Granulite and Gneiss with Calcite and
Dolomite marble. The basement for this group of rock is Trirodi Gneiss.
The entire saunsar belt is intensively deformed and metamorphosed. The basement
gneiss has also participated in all the deformational episodes of Saunsar origin along
with the rock of Saunsar Group. Tectonic slices of narrow dismembered
manganiferrousSaunsar Rock are also seen within the Tirodi Gneiss indicating
thrusting of the overlying rock within the gneisses. The gneisses, Migmatite son and
post tectonic Granite Plutons, Vein Quartz also occur within sausar supra crustal rock.
The lower most rock is a lensoidal Calcareous Quartzite overlain by thick Dolomite
marble. It is overlain by Calc Silicate rock inner banded by Calcitic Marble, hosting
Gonditic Manganese Ore. Linear bands of Lohangi formation are observed within
Gneissic terrain between Torni, Bodalbhana and Bichhwa. Around Mogra and south
Bichhwa Gneissic rocks interleave the sediments.
The geological succession is as follows.
Table 4: Geological Succession of the area
AGE GROUP FORMATIN LITHOLOGY
Quaternary
Cretaceous-
Palaeogene
-
Sahyadri Group
(Deccan Trap)
KaranjaFm
ChikhliFm
Alluvium
Laterite
18 simple flows of Basalt
6 flows of Basalt
Intertrappean beds
Undifferentiated Basalt
Cretaceous Lameta Group - Conglomerate Sandstone
Shale Limestone
Permian -Triassic
Carboniferous –
Permian
KamthiFm
TalchiFm
BichuaFm
Sandstone and Ferruginous
Sandstone Boulder bed
Sandstone, Shale granite
pegmatite crystalline limestone
dolomite
S
A
U
S
A
R
JunewaniFm
ChorbaoliFm
MansarFm
Muscovite biotite schist, quartz
biotite and granulites
Quartzite and quartz muscovite
schist Muscovite biotite schist
with manganese ore
MESO PROEROZO
IC
GROUP LohangiFm
Kasbdikhera
Formation
SitasawangiFm
Calc gneiss and manganiferrous
marble with Manganese Ore
pocket Dolomitic Marbles and
calc silicates quartz biotite
granulitesFelspathic schist and
quartzites Silicified zone, quartz
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
6
reef
S
A
K
O
L
I GROUP
Metarhyolite, tuff felsic
volcanics and associated tuff
Mica schist Phyllite carbonaceous
PhylliteTourmalinite, coticule
Metabasalt with associated tuff
Archaean PalaeoTirodi Gneissic
complex
Amgaon Gneissic
complex
Amphibolites Ultramafic rock
quartz (+/- kyanite, sillmanite)
Calsilicate rock granite gneiss
with migmatite gneiss
3.4.2 LOCAL GEOLOGY:-
Lithology:
The lithological succession of the area as follows:
1. Soil
2. Mica Schist along with quartzite
3. Manganese Ore with Gondite
The above litho sequence will be confirmed after the results of proposed exploration.
Characteristics of Mn Ore within the lease area:
Formation: Disseminated pebble form (size is varying from 2 cm to 8 cm)
Association: Associated with murum
Streak: Greyish Black
Hardness: 5-6
Soiling Property: Its Soils
MINERAL RESERVES
Table 5: Mineral Reserve
LIFE OF MINE
Table 6: Life of Mine
Classification Code Quantity (tonnes)
Mineral Reserve
Probable Mineral Reserve
(Manganese Ore)
122 118857
Remaining Resources
Prefeasibility Mineral Resource
(Manganese Ore)
222 5906
Inferred Mineral Resource
(Manganese Ore)
333 55440
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
7
3.5 PROJECT DESCRIPTION WITH PROCESS DETAILS
3.5.1 YEARWISE PRODUCTION DETAILS
In this area the mining of Manganese Ore involves blasting. The O.B. will be
removed with the help of JCB/ excavator. The Applicant has proposed to produce
Manganese Ore working for a period of 5 years with a production of 26,460 TPA as
per the mine plan. The details of year wise production for the five years period are
given below.
Table7: Year wise Production of Manganese Ore for the five years period
Year Overburden in m3
(waste)
ROM Ore-
T
Total Saleable
Manganese Ore
Production - T
Mineral
Reject / Sub
– Grade
Ore - T
Ore to
Overburden
Ratio
I 307.00 4070.00 2688.00 Nil 1:0.15
II 614.00 8140.00 5376.00 Nil 1:0.15
III 1037.00 13738.00 9072.00 Nil 1:0.15
IV 1728.00 22896.00 15120.00 Nil 1:0.15
V 3024.00 40068.00 26460.00 Nil 1:0.15
3.5.2 PROPOSED METHOD OF MINING:
The proposed Manganese Ore Mine shall be developed by fully open –cast mining which
Include excavating, manual sorting, loading, transport and dispatch of mineral to end users.
3.5.2.1 OPEN CAST MINING
The mining will be done by fully open- cast manual method of mining. In mineral the bench
height will be maintained 4m and the width will be maintained more than bench height. The
ultimate depth of the workings is estimated to reach up to 18.0 m from the surface level.
3.5.2.2 SALIENT FEATURES OF MINING METHOD
The salient features of proposed mining method are:-
1. Bench or Bank or high wall height 4 meter.
2. Bench width not less than the bench height.
3. Bench slope angle from horizontal, about 770 – 80
0 from horizontal.
4. Ultimate Pit slope 450.
5. All benches to be equipped with road edge barrier.
Life of mine
Mineable reserve/ Average annual production
118857/11743 =10.2 say 11 years
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
8
6. Transportation of the mineral from mine to end users will be done by
trucks/dumpers.
3.5.3 EXTENT OF MECHANIZATION
The mining machineries to be used in proposed mining operation are as below:-
Table-8: List of Machineries
S. No. Machine Type No. of Items
1. Hydraulic Excavator (Backhoe system)
TATA HITACHI 200 1
2. Dumpers -24 Tonnes Capacity 1
3. Tractor & Water Tank 1
4 Tractor (Hindustan) Compressor (Atlas
Copco) 1
5 Jack Hammer 1
6 Wagon Drill 1
7 Rock Breaker 1
8 Pumps (Diesel)10 HP -
9 Drill, other Tools & Spares As per
requirement
10 Mining Safety Equipment’s as Safety Shoes,
Helmets, Hand Gloves, Leg Guard etc.
As per
requirement
11 Mining Equipment’s such as Crowbar, Pick
– Axe, Spade, Chisel etc.
As per
requirement
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
9
3.5.4 CONCEPTUAL MINING PLAN
The Manganese Ore is occurring throughout the area. The mineable reserves are estimated
to 1, 18,857MT. The annual Production is proposed to be 26,460TPA. Life of the mine is
11Years.
3.5.4.1 LAND USE PATTERN
The land use for mining and allied purposes is given below:-
Table 9: STAGE WISE LAND USE AND RECLAMATION AREA (Ha.)
S. No. Land use Category Present 5th Year End of life of mine
1 Top Soil Dump Nil Nil Nil
2 Dump/Stacks of Mineral Nil 0.9328 0.7694
3 Excavation (Voids Only) 2.3133 3.7664 5.5878 (3.9778 hect area will be
converted into water reservoir &
1.6100 hect will be backfilled)
4 Road Nil 0.05 0.05
5 Infrastructure Nil 0.01 0.01
6 Afforestation Nil 0.045 0.1350
7 Reclamation (Backfilled) Nil Nil 1.6100*
8 Mineral Storage Nil Nil Nil
9 Processing (Crushing) Nil Nil Nil
10 Tailing Ponds/Dam 4.50 4.595 4.595
11 Others Toe Wall etc. Nil 0.05 0.10
12 Undisturbed Area 123.1867 120.5508 118.7528
Total 130.00 130.00 130.00
Table 10: POST MINING LAND USE OF CORE ZONE WITH ENVIRONMENT
MANAGEMENT
S. No. Description Land Use (In Ha)
Plantation Water Body Public Use Undisturbed Total
1 Top Soil Dump Nil Nil Nil Nil Nil
2 Dump/Stacks of Mineral 0.7694 Nil Nil Nil 0.7694
3 (a)Excavation (Voids) Nil 3.9778 Nil Nil 3.9778
(b)Excavation (backfilled) 1.6100 Nil Nil Nil 1.6100
4 Road Nil Nil 0.05 Nil 0.05
5 Infrastructure Nil Nil 0.01 Nil 0.01
6 Afforestation 0.1350 Nil Nil Nil 0.1350
7 Mineral Storage Nil Nil Nil Nil Nil
8 Processing (Crushing) Nil Nil Nil Nil Nil
9 Tailing Ponds/Dam Nil 4.595 Nil Nil 4.595
10 Others Toe Wall etc. Nil Nil Nil 0.10 0.10
11 Undisturbed Area Nil Nil Nil 118.7528 118.7528
Total 2.5144 8.5728 0.06 118.8528 130.00
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
10
3.5.5 DRILLING
The deposit is proposed to be mined by fully Opencast mining by adopting a system of small
hole/deep hole blasting and /or working with the help of machinery for digging, excavation
and removal of ore, overburden etc. Drilling of the blast holes is proposed to be done by
compressed air fed jack hammers and wagon drills. Height of the bench is proposed to be kept
at 4 m where drill will make 1.5 m deep bore hole. Wet drilling is to be done in hand holes as
well as jack hammer drilling/ wagon drill.
3.5.6 BLASTING
Blasting is required only for removing OB, waste rock and mineral. The controlled blasting
technique is to be adopted, so that is does not damage the Manganese Ore. The Manganese
Ore is capped by OB of siliceous nature and it is fine to medium grained and compact.
Heaving and breaking of the OB will be required that can be achieved by effective blasting
economically. About 80% of the siliceous OB and Manganese Ore will be required to be
blasted, while the rest will be generated by impact. Drilling of blast holes is proposed to be
done by compressed air fed wagon drills. Secondary Blasting will not be needed. Muffle
blasting will be done to prevent flying fragments, which may cause injury to local inhabitants
within danger zone. Muffle blasting will be carried out by keeping sand filled bags on wire
net placed on holes.
Broad Blasting Parameters
Table 11: Blasting Parameters
Parameters Jack Hammer Wagon Drill
Spacing 1 2
Burden 1.2 3
Depth of Hole 1.5 5
Powder Factor 8 t/kg 8 t/kg
Dia. of hole: 32 mm 32 mm 100 mm
TYPE OF EXPLOSIVE TO BE USED
Gunpowder with safety fuse or special gelatine having 80% strength will be used for
blasting.
Powder factor in ore & waste will be 8 tonnes per kg of explosive.
STORAGE OF EXPLOSIVE
As this is a fresh grant case, after the mine open consent, the applicant will initially
purchase explosives from the authorized agency holding the license from the
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
11
controller of explosives Agra or Nagpur. In the meantime after getting possession, the
applicant will apply for explosive license.
MINERAL TRANSPORTATION
Loading of mineral will be done by excavator & dumper/trucks of 24 T will be used
for transportation of mineral &waste. The Manganese ore will be used for captive
plant for Ferro Mn.
3.6 RAW MATERIAL REQUIRMENT
No raw material will be required. The final product will be sent to consumer
industries based on their demand. The mode of transportation of raw material will be
road. Trucks/Dumpers will be used for transportation of Manganese Ore.
3.7 RESOURCES OPTIMIZATION/ RECYCLING AND REUSE ENVISAGED IN
THE PROJECT, IF ANY, SHOULD BE BRIEFLY OUTLINED
The Manganese Ore will be mined in the form of lump so there will be no recycling
and reuse envisaged.
3.8 AVAILABILITY OF WATER& ITS SOURCE, ENERGY /POWER
REQUIREMENT AND SOURCE
WATER:
The daily water demand for the proposed project is 10.00 KLD which will be
procured from near Village- Miragpur & from Biloni Nalla and rain harvested water
stored in tank after and during monsoon. The pond desiltation and impoundment will
be done by the project proponent. The detailed breakup of the water requirement is
given below.
Table 12: Water Demand
S. No. Particulars Quantity (KLD)
1. Domestic Purpose 2.00
2. Dust Suppression / Water Sprinkling 4.00
3. Green belt / Plantation 4.00
Total 10.00
Power Supply: There is no electricity proposed as the mining will be done during the
day time and the machinery proposed will be operated by the use of diesel.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
12
3.9 QUANTITY OF WASTE TO BE GENERATED (LIQUID AND SOLID) AND
SCHEME FOR THEIR MANAGEMENT/DISPOSAL
Siliceous material as waste (OB).About 7515 m3 OB and 4536 m
3 Sub Grade will be
the end of first five year’s period. The generated OB/ interburden will be dumped in the
south of the lease area and these dumps will be temporary& sub grade dump will be used
as per changing norms from industry users. The dump will be protected by retaining wall
with garland drain, compacted and temporarily rehabilitated by sowing fast growing grass
seeds.
PARTICULARS MANAGEMENT
O.B./Mineral
Waste
About 7515 m3OB and 4536 m
3Sub Grade will be the end of firstfive year’s period. The
generated OB/ interburden will be dumped in the south of the lease area and these
dumps will be temporary. No mineral reject are likely to be generated.
4 SITE ANALYSIS
4.1 CONNECTIVITY (Mine Site)
Table No.13: Connectivity
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
LAND FORM
The Mining area is low undulating area.
LAND USE
The present land use pattern is as below:-
Table 14: Land Use Pattern
S. No. Particulars Present Land-use (ha.)
1. Top Soil Dump Nil
2. Dump/Stacks of Mineral Nil
PARTICULARS DISTANCE & DIRECTION
Nearest Railway Station Katangi Railway Station – 14.90 Km, NNE
Nearest Airport Nagpur Airport, – 89.43 Km, SW
Nearest Highway SH-54, (0.18 Km, East)
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
13
S. No. Particulars Present Land-use (ha.)
3. Excavation (Voids Only) 2.3133
4. Road Nil
5. Infrastructure Nil
6. Afforestation Nil
7. Reclamation (Backfilled) Nil
8. Mineral Storage Nil
9. Processing (Crushing) Nil
10. Tailing Ponds/Dam 4.50
11. Others Toe Wall etc. Nil
12. Undisturbed Area 123.1867
Total 130.00
LAND OWNERSHIP
The land as per revenue records is Govt. forest land of 130.00 hectare falls in forest
compartment No. 551 A & B. In first stage of forest clearance out of 130.0 ha only
39.0 ha will be applied for prior approval under Forest (Conservation) Act, 1980 will
be submitted separately. Map for the same is enclosed as Plate No.-II of mining plan.
4.3 TOPOGRAPHY
Topographically, the Mining area has moderate rolling topography which is covered
with forest having the density less than 0.3 & highest elevation of335.00mRL and
lowest elevation of 306.00mRL.
4.4 EXISTING LAND USE PATTERN
Table 15: Existing Land Use Pattern (In Ha.)
S. No. Particulars Forest
Land
Govt.
Grazin
g Land
Govt./
Private
waste
land
Private land
Total
Ag. Non Ag.
1. Top Soil Dump Nil -- - -- -- Nil
2. Dump/Stacks of Mineral Nil -- - -- -- Nil
3. Excavation (Voids Only) 2.3133 -- - -- -- 2.3133
4. Road Nil -- - -- -- Nil
5. Infrastructure Nil -- - -- -- Nil
6. Afforestation Nil -- - -- -- Nil
7. Reclamation (Backfilled) Nil -- - -- -- Nil
8. Mineral Storage Nil -- - -- -- Nil
9. Processing (Crushing) Nil -- - -- -- Nil
10. Tailing Ponds/Dam 4.50 -- - -- -- 4.50
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
14
11. Others Toe Wall etc. Nil -- - -- -- Nil
12. Undisturbed Area 123.1867 -- -- -- 123.1867
Total 130.00 -- -- -- --- 80.94
Table No.-16: Environmental Settings
S. No. Particulars Details
1. National Park, Wild Life
Sanctuary, Biosphere
Reserve, Tiger Reserve,
Wildlife Corridor,
Reserved Forest
2 Protected &5 Reserved Forests falls within 15 km radius
of Buffer zone.
S.
No.
Name Distance Direction
1. KHAPUR WIHARI
R.F
2.0 KM SE
2. P.F 2.0 KM NE
3. GARRA GHAT R.F 1.0 KM NORTH
4. R.F 2.50 KM WEST
5. MOHAGOANGHAT
R.F
7.05 KM SE
6. PHULCHUR R.F 8.66 KM SE
7. CHANDPUR
FOREST
5.0 KM SOUTH
2. River / water body Available water bodies and rivers falls within 15 Km
radius Buffer zone as follows: -
Water bodies/River Distance Direction
BILONI NADI 1.42 KM SW
BHAWANTHARI
RIVER
4.57 KM SW
DHORIYA NALLH 5.0 KM WEST
4.5 EXISTING INFRASTRUCTURE
Refer the Para no. 4.1 of section 4.0
4.5.1 WATER
The total water demand will be as follows:
Daily Water Demand 10.0 KLD
Domestic
2.0 KLD
Dust Suppression
4.0 KLD
Plantation
4.0 KLD
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
15
4.6 CLIMATE
The area witnesses subtropical climate and receives an average rainfall of 1600-1800 mm
annually. They are – i) Winter ranging from November to February ii) Summer ranging from
March to mid- June iii) South west monsoon ranging from mid – June to mid- September iv)
Post monsoon ranging from mid – September to October in the cold weather, The variation in
temperature is from 250 C to 46
0 C in summers and 4
0 C to 22
0 C during winter. From
November to February the area experiences winter, while April to June the region experiences
summer. The monsoon sets in by June and retreats by September. Relative humidity averages
from 18% to 80% in a year.
4.7 SOCIAL INFRASTRUCTURE AVAILABLE
Table 17: Infrastructure in the Study Area
Particulars Name Distance (Km) Direction
(From MineArea)
Nearest Habitation Chitewani 2.70 kms SW
Nearest Towns Katangi 14.90 Km NNE
Nearest Airport Nagpur airport 89.43 Km SW
Nearest Highway SH-54 0.18 Km East
NH- 7 36.92 km West
Nearest Railway Station Katangi 14.90 Km NNE
Nearest Hospital Katangi 14.90 Km NNE
Educational Facility Katangi 14.90 Km NNE
5 PLANNING BRIEF
5.1 PLANNING CONCEPT
It is a mining Industry using fully mechanized method will be adopted. The
proposed mine will produce manganese ore with capacity of 26,460TPA. It will be used
in metallurgical industry and will be transported by trucks to end users.
5.2 POPULATION PROJECTION
In the Buffer zone, total household is 27102. Total population is 109267 out of which,
53922 are males and 55345 are females. The total literate person in the surrounding
area is 74811 and total worker’s population is 59285. The detailed demographic
profile of villages located in the study area is given below:-
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
16
Table No. -18: DEMOGRAPHIC PROFILE
SR.NO Name No_HH TOT_
P
TOT_M TOT_F P_LIT P_IL TOT_
WOR
K_P
NON_
WOR
K_P
1. Kodbi 270 1306 654 652 865 441 620 686
2. Laxmipur
Hamesha
39 150 77 73 93 57 91 59
3. Digdha 416 1605 782 823 1038 567 857 748
4. Pandhari 9 31 17 14 18 13 20 11
5. AnjanBihari 660 2849 1422 1427 1774 1075 1726 1123
6. Bamhani 580 2330 1176 1154 1514 816 1136 1194
7. Bonkatta 852 3403 1741 1662 2205 1198 1919 1484
8. Chichgaon 10 38 15 23 21 17 22 16
9. Gusaitola 22 93 42 51 57 36 49 44
10. Sadabodi 181 721 354 367 450 271 392 329
11. Chakaheti 631 2734 1377 1357 1581 1153 1441 1293
12. Sukali 314 1051 537 514 646 405 605 446
13. Siwanheti 90 321 172 149 180 141 192 129
14. Sitapathar 180 642 303 339 371 271 345 297
15. Chandadoh 152 716 359 357 441 275 472 244
16. BichhwaRyt. 236 865 443 422 612 253 488 377
17. Kharpadiya 219 837 431 406 565 272 499 338
18. Hirapur 134 507 241 266 366 141 236 271
19. Jamrapani 131 524 258 266 356 168 191 333
20. Boldongari 208 783 377 406 572 211 393 390
21. Dhankosa 330 1421 715 706 1025 396 659 762
22. Dongargaon 94 379 190 189 273 106 179 200
23. Pauniya 605 2496 1230 1266 1752 744 1113 1383
24. Katedara 319 1445 733 712 998 447 721 724
25. Bothwa 497 2135 1027 1108 1528 607 1162 973
26. Pipriya 150 625 298 327 406 219 383 242
27. Sonegaon 177 790 366 424 530 260 341 449
28. Sawri 510 2312 1152 1160 1645 667 1073 1239
29. Kohka 280 1269 635 634 977 292 644 625
30. Jhanjhagi 195 907 443 464 679 228 529 378
31. Nawegaon 322 1340 659 681 976 364 750 590
32. Sundar 222 976 485 491 727 249 567 409
33. Birsula 186 925 442 483 709 216 524 401
34. Nandi 426 1848 923 925 1313 535 972 876
35. Mohgaon 409 1621 808 813 1100 521 895 726
36. Paraswadaghat 662 2583 1230 1353 1853 730 1381 1202
37. Hatoda 328 1333 664 669 984 349 674 659
38. Gurragusai 119 488 242 246 299 189 271 217
39. KapoorBihari 13 59 24 35 29 30 34 25
40. Chitewani 26 102 59 43 59 43 66 36
41. Nawegaon
(Hamesha)
38 149 63 86 58 91 79 70
42. Hardoli 732 3126 1523 1603 1935 1191 1669 1457
43. Bori(Hamesha) 14 51 26 25 16 35 29 22
44. Tirodi (CT) 2078 8451 4154 4297 6008 2443 2976 5475
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
17
45. Bitodi 615 2516 1231 1285 1675 841 1416 1100
46. Kothurna 462 1774 914 860 1222 552 1041 733
47. Nawegaon 661 2731 1342 1389 1799 932 1525 1206
48. Pipariya 452 1559 776 783 1123 436 894 665
49. Bakodi 526 2198 1060 1138 1565 633 1302 896
50. Chicholi 199 792 391 401 507 285 441 351
51. Kanhadgaon 179 698 350 348 532 166 455 243
52. Katangi 84 349 161 188 262 87 209 140
53. Kharkhadi 691 2734 1358 1376 1991 743 1582 1152
54. Khapa 158 594 307 287 431 163 251 343
55. Nawegaon
Khurd
537 2257 1116 1141 1597 660 1290 967
56. Pindkepar 460 1927 949 978 1295 632 1138 789
57. Amai 762 3048 1497 1551 2113 935 1638 1410
58. Chikhla 607 2316 1166 1150 1640 676 1332 984
59. Salebardi 771 2839 1375 1464 1869 970 1604 1235
60. Yerwaghat 685 2696 1311 1385 1863 833 1489 1207
61. GorraBodi 239 761 392 369 516 245 427 334
62. Manglegaon 260 991 482 509 766 225 687 304
63. Sukdighat 295 1207 606 601 821 386 670 537
64. Sabargaon 434 1533 748 785 1059 474 933 600
65. Gudrughat 452 1732 830 902 1217 515 1025 707
66. Tekadighat 409 1594 768 826 1045 549 919 675
67. Miragpur 389 1418 712 706 993 425 806 612
68. JaitpurKhapa 30 130 64 66 91 39 89 41
69. Pandharwani 190 711 332 379 463 248 441 270
70. MohgaonGhat 337 1220 598 622 859 361 806 414
71. Pulputta 613 2691 1332 1359 1826 865 1911 780
72. Chorpindkepar 249 960 484 476 651 309 565 395
73. Tuiyapar 425 1620 790 830 1112 508 987 633
74. Fulchur 489 1858 891 967 1348 510 1165 693
75. Chicholi 376 1476 720 756 956 520 862 614
TOTAL 27102 109267 53922 55345 74811 34456 59285 109267
(Source: Census Data, 2011)
5.3 LAND USE PLANNING
The sapling for plantation will be selected on less water according to climatic condition and
hence it is proposed to plant 8580 saplings per year. The plantation will be done at the lease
boundary.Year- wise programme of green belt development for five years, about saplings
42,900 will be planted in an area of 42.9 ha. Up to the conceptual phase 42,900 saplings will
be planted. By the green development it will improve the eco-systems and aesthetic beauty of
the area. Post plantation cares including provision for watering, soil mulching manure supply
to plants will be done. The list of the species to be planted in the green is provided below:-
Table 19: Green belt Programme
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
18
Year No. of
Saplings
Area
(ha.)
Species Place of Plantation
I 8.58 8580 Neem, Banyan,
Peepal, Ber,
Tamarind etc.
Boundary of the
lease, both side of the
road, schools II 8.58 8580
III 8.58 8580
IV 8.58 8580
V 8.58 8580
After
VthYear
8.58 8580
At the end of
Lease period
42.9 42,900
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
The mine area is easily accessible from the state highway by SH-54(0.18 km, East)
will be helpful to approach workers to the mine site as well as transportation of
mineral to the nearby areas and end user. KatangiRailway Stationis 14.90 Km far
towards NNE form the mine site. The infrastructure demand in the villages will be
evaluate on the basis of necessity and priority. Job opportunities are inadequate and
new possibility for income generation is required.
5.5 AMENITIES/FACILITIES
� Mine Office: It is proposed to have a temporary mine office with First Aid Facility.
� Rest Shelter: Temporary Rest Shelter will be made available.
� Drinking Water Facility: The drinking water will be made available from the
nearby pond &from Biloni Nalla and rain harvested water stored in tank after and during
monsoon. The quality of water is reportedly potable.
� Adequate lighting arrangements: Single shift working during day time is proposed,
yet adequate lighting arrangements will be made at quarry face and haulage roads as
per statutory norms.
� Toilets: The toilet facility is proposed for the better sanitary condition of the workers
employed in Mining area.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
19
6 PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (PROCESSING AREA)
The area is well connected by road network to the mines, District headquarter etc. The
area is self-sufficient to supply the needs of the project. Hence no, infrastructure is
proposed.
6.2 RESIDENTIAL AREA (NON PROCESSING AREA)
The local people will be employed, hence no residential area/ housing is proposed.
6.3 GREEN BELT
Refer point no. 5.3.
6.4 SOCIAL INFRASTRUCTURE
The proposed project is situated at Village Miragpur, Tehsil Katangi, District
Balaghat (Madhya Pradesh). As local people will be employed for excavation
activities, no permanent infrastructure is required. The workers will come to the site
by company’s vehicle. By this project, indirect means of earnings in the area will be
developed, which will bring a positive impact on the adjacent habitation.
6.5 CONNECTIVITY (TRAFFIC AND TRANSPORTATION ROAD / RAIL /
METRO /WATER WAYS ETC)
Given in ParaNo. 4.0.
6.6 DRINKING WATER MANAGEMENT (SOURCE & SUPPLY OF WATER)
The total water requirement for the proposed activity is 10.0KLD. The
drinking water (0.090 KLD) will be met from the nearby village water source through
mobile tanker supply while other water requirement for mining activities will be made
available from the pond desiltation and impounded by the project proponent. The
proposed indigenous water source created by the project proponent will fulfill the
water demand of local habitants.
6.7 SEWAGE SYSTEM
Not applicable.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
20
6.8 INDUSTRIAL WASTE MANAGEMENT
No industrial waste will be generated.
6.9 SOLID WASTE MANAGEMENT
Given in point no. 3.9
6.10 POWER REQUIREMENT & SUPPLY/SOURCE
No Power requirement is proposed for Miragpur Manganese ore mine as the diesel
operated machineries are proposed and mining will be done during the day time only.
7 REHABILITATION AND RESETTLEMENT (R & R PLAN)
7.1 POLICY TO BE ADOPTED.
No Rehabilitation and Resettlement plan is required because there is no infrastructure
to affect the persons or to any landless labour.
8 PROJECT SCHEDULE AND COST ESTIMATES
8.1 LIKELY DATE OF START OF CONSTRUCTION AND LIKELY DATE OF
COMPLETION
The project will be started immediately after Environmental Clearance and other
necessary approvals from concerning authorities of State Government.
8.2 ESTIMATED PROJECT COST AND ALONG WITH ANALYSIS IN TERMS
OF ECONOMIC VIABILITY OF THE PROJECT
Project cost
a) Capital Cost
a Cost of constructing and maintenance of the site service office
& etc. (0.01) ha
Rs. 1,00,000/-
b Lease registration, lease agreement and mine development
cost other incidental expenses (including interest) cost of
mining plan and Financial Assurance. Cost EIA/ EC clearance
& forest clearance (10 ha area @ 10000.00 per hectare)
Rs. 5,00,00,000/-
Total Capital Investment is Rs. 5,01,00,000/-
b) Investment Cost
i) Interest on Capital Investment of Rs. 5,01,00,000/- year interest = @12% = 60,12,000/-
ii) Depreciation of cost of building/ site services/land per year = 1,00,000/50 = 2,000/
iii) Depreciation of cost of mining plan preparation, lease agreement, financial assurance
etc. per year = 50000000/50 = Rs. 10,00,000/-
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
21
c) Per year cost incurred on fixed investment = 6012000+2000+1000000 = Rs.
70,14,000/-
d) Operating Cost:
Wages Hire Machinery Miscellaneous
Planting, settling tank, garland,
air water monitoring, road
making, De-watering etc. (e),
out of pocket expenses
STAFF SALARY
450.00 650.00 80.00
Total Cost Will be Rs. 1180/- per tonne
Production 24600 t per year
(The average production of five year when the mine is fully developed)
e) Total Operating Cost production/ yr = 24600 x 1180 = Rs. 2,90,28,000/-
f) Sensitivity Studies: The area does not require any such study.
g) Closure Cost: Cost incurred on fencing, parapet wall, warning board, gate,
decommissioning, rehabilitation of people etc. = Rs. 5,00,000/-
h) Total closure cost: Rs. 5,00,000/-
i) Rehabilitation cost: PMCP/FMCP implementation cost (including pit/ dump
management / backfilling, afforestation and other measures etc.) = Rs. 5,00,000/-
j) Total Reclamation & Rehabilitation Cost: Rs. 5,00,000/-
k) Total cost of productivity/yr = (2+3+4+5) = 7014000 + 29022800 + 5,00,000 +
5,00,000 = Rs. 3,70,42,000.00
Total Cost of production per T = 37042000/24600 = 1505.00/-
9 ANALYSIS OF PROPOSAL
Miragpur Manganese Ore mine project will result in growth of the surrounding areas.
Direct and indirect employment will be created in nearby village. Special emphasis on
Financial and Social benefits will be given to the local People. No major adverse
effect on environment is envisaged as the required mitigation measures are inbuilt in
the project.
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
22
10 ENVIRONMENT MANAGEMENT PLAN
PARTICULARS MANAGEMENT
Air Quality Excavation, Loading
and Transportation
� Dust generated due to excavation and
vehicular movements will be suppressed by
water spraying on haul road.
� To avoid the dust generation from the
drilling operations Wet drilling method
will be practiced.
� Drill machines will be fitted with dust
collectors.
� Use of appropriate explosives for blasting.
� Controlled blasting techniques will be
practiced.
� Dust mask will be provided to the workers.
� Proper maintenance of vehicles &
machineries will be done.
� Water sprinkling on the haul road and other
road at regular intervals will be done.
� Speed of the vehicles will be kept within
the prescribed limits.
� Trucks will not be over loaded.
Water Quality
� No waste water or any effluence as solid or
gas there will be generated from mining
operation
� Garland drains will be made around the
mining area to channelize surface run off
into natural drainage pit so that it can be
utilized for dust suppression.
� Mining operations will be at higher levels;
therefore there will be no effect on ground
water condition due to mining.
Noise Quality Drilling, Blasting, � Adequate silencers in all the diesel engines
Miragpur Manganese Ore Mine, Production Capacity – 26,460 TPA, M.L. Area-130.0 ha., Near Village-
Miragpur, Tehsil – Katangi, District - Balaghat (Madhya Pradesh)
Pre-Feasibility Report
23
Loading and
unloading of Mineral
and movement of
Trucks.
will be used.
� Personal protective equipment will be
provided to the workers.
� Proper maintenance of machines at regular
intervals will be done.
� Green belt development and plantation
Solid Waste
� There is no top soil available in the lease
area
� The generated OB/ interburden will be
dumped in the south of the lease area and
these dumps will be temporary.
Land Reclamation
The area has moderate rolling topography
which is covered with forest having the density
index less than 0.3. At the conceptual stage,
out of total mined out area (5.5878 ha) 3.9778
ha will be converted into water reservoir &
1.6100 ha will be backfilled & covered with
plantation.