Upload
kogi3075
View
223
Download
0
Embed Size (px)
Citation preview
8/17/2019 Ind Presentation CSRH Intro Rule Updates
1/37
Gary Horn, Chair of IACS Hull PanelPhilippe Baumans and Åge Bøe,
IACS Project Management Team
Hasan Ocakli, PM of Consequence Assessment team
HarmonisedCommon Structural Rules
Project Status
Industry Presentation
June 2013
8/17/2019 Ind Presentation CSRH Intro Rule Updates
2/37
IACS Harmonised CSRIndustry Presentations
• Welcome, and thank you forattending
• Safety First
http://www.eagle.org/eagleExternalPortalWEB/appmanager/absEagle/absEagleDesktop?_nfpb=true&_pageLabel=abs_eagle_portal_directory_pagehttp://www.rs-class.org/en/directory/index_rs_directory.phphttp://www.rina.org/EN/istituzionale/dovesiamo.aspxhttp://www.prs.pl/dir21.htmlhttp://www.classnk.or.jp/hp/directory/dir_top.asphttp://www.lr.org/contact_us/office_directory/index.aspxhttp://www.krs.co.kr/eng/intro/organ/I_organ_dir.aspxhttp://www.irclass.org/IRS_directory.pdfhttp://www.gl-group.com/http://www.dnv.com/findus/http://www.crs.hr/en-us/directory.aspxhttp://www.ccs.org.cn/en/CCS_Brief/CCS_Brief2.htmhttp://www.veristar.com/wps/portal/marinedirectory
8/17/2019 Ind Presentation CSRH Intro Rule Updates
3/37
Agenda
Topic Presenter
Welcome & Introduction G. Horn
Status1. Schedule2. Industry feedback and rule changes
G. Horn
Changes to the CSR-H since 1-Jul-20121. General Principles
2. Loads3. Hull Girder & Local Prescriptive Reqts4. Direct Strength Analysis5. Buckling Criteria6. Fatigue Strength7. Discussions (Q/A)
P. Baumans Å. Bøe
Consequence Assessment
1. General, scope and method2. Oil Tankers, prescriptive and FEM3. Discussions (Q/A)4. Bulk Carriers, prescriptive and FEM5. Discussions (Q/A)
H. Ocakli
General Discussion (Q/A) All
WelcomeJune 2013 3
8/17/2019 Ind Presentation CSRH Intro Rule Updates
4/37
Goal based standards & Harmonised CSR
2010 2011 2012 2013 2014 2015 2016
CSR-OT
CSR-BC
21 Harmonised CSR
External review period
Technical Committee review
IACS adoption
Entry into force
GBS to startapplication tooil tanker andbulker
(1 July 2016)
1July 1Apr.
30 Jun.
CSR-H1st Draft Rules
CSR-H2nd Draft Rules
Deadline of submission to IMO for GBS
verification
( 31 December 2013)
(RCN1 of the 2010 CSRs)
Welcome 4June 2013 4
8/17/2019 Ind Presentation CSRH Intro Rule Updates
5/37
CSR-H Schedule
C66 Approved
Schedule
First draft (External) 1 Jul 2012
1st Industry Review 1 Jul – 31 Dec 2012
(6 months)
Feedback/Re-work1 Jan – 31 Mar 2013
(3 months)
Second draft 1 Apr 2013
2nd Industry Review 1 Apr – 31 Aug 2013
(5 months)
Feedback/Re-work1 Sep – 31 Oct 2013
(2 months)
Third (TC) draft 1 Nov 2013
TC Review 1 Nov – 15 Dec 2013 (1.5 months)
IACS Adoption December 2013
Final clean-up 15 Dec – 1 Feb 2014
Release Rules 1 Feb 2014
5
8/17/2019 Ind Presentation CSRH Intro Rule Updates
6/37
2nd Draft of CSR-H Released
Released 1 April 2013 (Website: www.iacs.org.uk) CSR-H Rule Text.
Technical Background.
Consequence Assessment (based on 31-Dec-2012 internal version).
IACS Press Release.
IACS web site modified to suit.
• A working draft showing “track changes” from 1st external release of1-Jul-2012 is available upon request.
“In Progress” items from 1st draft of 1-Jul-2012 addressed as necessaryand labels removed.
6
8/17/2019 Ind Presentation CSRH Intro Rule Updates
7/37
2nd Draft of CSR-H Released
2nd
Industry Review Period 1 April 2013 ~ 31 August 2013
Industry invited to review and comment during the review period,and further advised:
• This period constitutes the last opportunity for "substantive"
review of the draft harmonized CSR.
• There will be a final Technical Committee review of the draftharmonized Common Structural Rules during the period of1 Nov 2013 thru 15 Dec 2013, however, this final review isplanned as a non-substantive confirmation of the Rules.
the reason being the schedule for the submission of the CSR-H toIMO for verification of compliance with the IMO Goal BasedStandards.
7
8/17/2019 Ind Presentation CSRH Intro Rule Updates
8/37
Technical Documentation Package to IMO
CSR-Hdocuments
IACS Common Package, 2nd Part
Other IACSdocuments
(UR, PR, UI, etc.)
IACS Common Package, 1st Part
ABS
BV
CCS
RS
… A letter +
Individual Tech.
Doc. Package
to IMO
R e f e r e n c e s
Note: IACS is working closely with the IMO Secretariat to
coordinate scope and schedule of the GBS
submiss ion package.
WelcomeJune 2013 8
8/17/2019 Ind Presentation CSRH Intro Rule Updates
9/37
Detailed Technical Presentations
2nd
round of Industry Presentations:18 June 2013 – Athens
20 June 2013 – London
24 June 2013 – Shanghai
26 June 2013 – Busan
28 June 2013 – Tokyo
9
8/17/2019 Ind Presentation CSRH Intro Rule Updates
10/37
TC Review
Current 2nd
Industry Review Period Now ~ 31 August 2013.
Final TC and Industry Review Period
1 ~ 15 December 2013.
Final review as a non-substantive confirmation of the Rules.
Final adoption by IACS Council during mid-December 2013.
Ready for the submission of the CSR to IMO for verification of
compliance with the IMO Goal Based Standards.
10
8/17/2019 Ind Presentation CSRH Intro Rule Updates
11/37
Time schedule
• Schedule
• Knowledge Centre
• IACS Organisation
8/17/2019 Ind Presentation CSRH Intro Rule Updates
12/37
Harmonised CSR - Time Schedule
June 2013 12
8/17/2019 Ind Presentation CSRH Intro Rule Updates
13/37
IACS Knowledge Centre
June 2013
IACS knowledge centre address: http://www.iacs-csrkc.org.uk
Industry contact through: [email protected]
►Accessible by anyone
►Comments and questions received from
Industry
►Answers provided by IACS groups
(HPTs, PMTs, Hull panel, etc )
0
20
40
60
80
100
120
J u l 2 0 1 2
A u g 2 0 1 2
S e p 2 0 1 2
O c t 2 0 1 2
N o v 2 0 1 2
D e c 2 0 1 2
J a n 2 0 1 3
F e b 2 0 1 3
M a r 2 0 1 3
A p r 2 0 1 3
M a y 2 0 1 3
J u n 2 0 1 3
Questions Received
Total 300 Q
13
8/17/2019 Ind Presentation CSRH Intro Rule Updates
14/37
IACS CSR Organisation
June 2013
IACS Council
SG/CSR(ABS, BV, LR, NK, Rina)
GPG
Hull Panel(13 members)
CSRMaintenance
Project Management TeamCSR Harmonization
(BV, DNV)
11 Project TeamsCSR-H
CSRSecretariat
EG/GBS
PT/GBS
14
8/17/2019 Ind Presentation CSRH Intro Rule Updates
15/37
Harmonisation of CSR-OT & CSR-BC
CSR-H Deliverables
1. Common part
2. Part for specific shiptypes (oil tanker andbulk carrier)
Apr il
2006
CSR EIF
Harmonization
Detail Plan
Submission to
IMO
for GBS(Dec 2013)
PMT Project Management Team(BV, DNV)
1 - Wave Load (BV)
2 – Buckling (CCS)
3 - Finite Element Analysis (KR)
4 - Corrosion additions (ABS)
5 – Welding (RS)
7 - Ship in operation (Rina)
8 – Fatigue (DNV)
9 - Prescriptive Requirements (BV/DNV)
10 – Consequence Assessment (LR)
2007 2008 2009 2010 2011 2012 20132006
Total staff: 71
June 2013 15
8/17/2019 Ind Presentation CSRH Intro Rule Updates
16/37
Technical issues solved in ER April 2013
Number of LC for FE assessmentLC for FE•Governing Load Cases identified per ship type for
•Midship region
•Outside Midship
•Work in progress for foremost and
aftmost cargo hold
Fatigue• Improvement for prescriptive and FE fatigue assessment
Buckling• Improvement of Ch 8, Sec 5, Tab 2 case 2 (Simple support with σy)
• Improvement of plate buckling - side shell in single side bulk carriers
June 2013 16
8/17/2019 Ind Presentation CSRH Intro Rule Updates
17/37
Goal Based Standards
Residual strength after collision or grounding
• Introduced in Pt 1, Ch 5, Sec 3
Structural redundancy
•
Technical background is under development•Conclusion: Ship structure, i.e. stiffened panels with scantlings in
accordance with CSR have inherent redundancy and do not needreinforcement for this purpose
Fatigue Vibration due to whipping / springing• Implicitly covered for a very large part of ships as it is included in
the experience from operation
•Technical background Report is under development
June 2013 17
8/17/2019 Ind Presentation CSRH Intro Rule Updates
18/37
Goal based standards
Reference to IACSGuidelines
June 2013
No. Functional Req.
CSR-H
Text
Survey
Panel
PT/GBS-
GAPS
1 Design Life Yes - -
………
8 Watertight & Weathertight integrity Yes - -
9 Human element consideration (Yes) - Yes
10 Design transparency (Yes) - Yes
11 Construct ion quali ty procedures (Yes) Yes -
12 Survey during construct ion (Yes) Yes -
13 Survey and maintenance - Yes -
14 Structural accessibil ity Yes - -
15 Recycl ing - - Yes
18
8/17/2019 Ind Presentation CSRH Intro Rule Updates
19/37
Main Rule Updates between July 2012 andApril 2013
8/17/2019 Ind Presentation CSRH Intro Rule Updates
20/37
June 2013
Table of content – ER April 2013 - 1/2
Part 1: General Hull Requirements
Main Modifications :
Grab 20, 30, 35t
Removal of
IMO PSPC
Reduction offatigue loads
Reduction of
FE LC
Envelop
method
removal
SSS BC
modification
20
8/17/2019 Ind Presentation CSRH Intro Rule Updates
21/37
Table of content – ER April 2013 - 2/2
June 2013
Part 1: General Hull Requirements Part 2: Ship Type Requirements
ImprovementProtection
against
wire rope
21
8/17/2019 Ind Presentation CSRH Intro Rule Updates
22/37
Main Rule updates – Pt 1 – Ch 1 to 3
June 2013
Ch 1: Rule General
Principles
Ch 3: Structural
Design Principles
►Sec 1, [3.2.2]: Grab notation 35, 30, 20t►Sec 2: Many minor editorial corrections
►Sec 4: Corros ion protection: removal of IMO PSPC for ballast tanks►Sec 6: Structural detail principles
►[5.2] Connection of stiffener to PSM :Detail calculation when spacings are different
►[7.5] Bilge strake: Removed as duplicated in Ch 6 Sec 4►Sec 7:Structural idealisation
►[1.3.2] Effective breadth PSM: new formula but similar results►[1.4.2] Bulb section equivalency to Inverted Angle in net►[1.4.6] Z plastic: error correction with sin( w)
Ch 2: General
Arrangement Design
►Sec 4, [1]: Closed spaces must be accessible for easy inspection
22
8/17/2019 Ind Presentation CSRH Intro Rule Updates
23/37
Main Rule updates – Pt 1 Ch 4 - 1/2Loads
June 2013
• Sec 2: Dynamic load cases
– Table 5: CWH increased by 10% except for OST/OSA cases instrength assessment
• Sec 3: Ship motions & accelerations
– Coeficient f fa = 0.9 for fatigue, introduced in f p factor (Mwv)
• Sec 4: Hull girder loads
– Cv and Ch removed and replaced by a 0.9 coefficient forfatigue analysis (Mwv , Mwh and Mwt)
– f nlh = 0.9 for strength & f nlh = 1 for fatigue :Mwh reduced for OST/OSA in strength assessment
• Sec 5:External loads
– Tab 14 : Editorial correction ( fxl =0.7 )
– f fa = 0.9 for fatigue introduced in f p factor (Pressure)
– [2.2.3] Green see loads: P D-min = 0 for FE analysis
– [3.2.1] Bottom slamming pressure case 2: (ztop-z) instead of ztop in formula and fSL coefficient
Ch 4: Loads
23
8/17/2019 Ind Presentation CSRH Intro Rule Updates
24/37
Main Rule updates – Pt 1 Ch 4 - 2/2Loads
June 2013
• Sec 6 Internal loads
– fdc: new coefficient for dry cargo in fatigue f dc = 0.5 used in Pbd in[2.4.3]– MH and MHD defined for 50% consumables– Steel coils: correction of loads on hopper side by cos h :
• [4.2.2] & [4.3.2]: correction of F sc-hs and F sc-hs-s
• Sec 8 Loading conditions
– Identification of loading condition with “Max SFLC”– Cleaning of the large number of footnotes in tables (already
mentioned in the rule text)
– Midship tables: clerical error– Outside midship: introduction of governing LC in tables– Foremost and aftmost CH: reduction of LC but work still in
progress
– Introduction of missing check existing in the CSR-BC, URS25 andCSR-H text in line with the hold mass curves.
– Additional tables for fatigue analysis outside midship.
• App 1: Hold mass curves
– Re-analysis and presentation by ship type for seagoing andharbour in same table.
Ch 4: Loads
24
l d h 6
8/17/2019 Ind Presentation CSRH Intro Rule Updates
25/37
Main Rule updates – Pt 1 – Ch 5 & 6Prescriptive Requirements
June 2013
• Sec 1 HG Yielding
– [3.4.6] Equivalent thickness of corrugated bhd provided for oil Tanker
• Sec 2 HG Ultimate strength
– Clarification of the Msw for the different design load scenarios
• App 2 HG Ultimate capacity
– Incremental method only - Single Step Ultimate Capacity method removed.
Ch 5:
Hull Girder Strength
• Sec 1 General
– Scope: clarification of scope in [1.1.1] including SS above FB deck, exposed deckof superstructure and internal decks except inside superstructure and deckhouse.
• Sec 2 Load application
– Tab 1, DL-1 draught = T BAL instead of T SC
• Sec 3 Minimum thickness
– Rearrangement of Tab 1 and add a row for other plates
• Sec 4 Plating
– Use of a and b instead of and s
– [2.2] Correction for bilge plate
• Sec 6 Primary supporting members and pillars
– PSM to be calculated in flooded conditions
Ch 6:
Hull Local Scantling
25
M i R l d P 1 Ch 7
8/17/2019 Ind Presentation CSRH Intro Rule Updates
26/37
Main Rule updates – Pt 1 – Ch 7Direct Strength Analysis
June 2013
• Sec 2 Cargo hold structural strength analysis
–Envelop method removed. Only individual method to be used.
– [2.2.2] Simplification for modelling the structure fwd theforemost CH
– [2.4.4] Corrugation: dummy rod elements to be modelled atintersection between flange and web
– [2.5.3] Boundary condition of aftmost CH: same as for midship– [2.5.4] End constraint beam characteristics: Area modified
– [4.2] Green sea loads on hatch cover to be considered– [4.3.3] Qtarg aft and fwd redefined– [4.4.5] HG Shear force adjustment procedure revisited.
Introduction of Method 1 and Method 2 using SFLC
– [4.4.9] Procedure to adjust vertical and horizontal bendingmoments outside midship
– [5.2.3] Tab 12 harmonised with tab for buckling, for the vertical
corrugated bhd with and w/o lower stool• Sec 3 Local structural strength analysis
– Fine mesh - Mandatory details
• Connections between deck and double bottomlongitudinal stiffeners and adjoining structures oftransverse bhd:
Clarification of the required fine mesh to be analysed
Ch 7: Direct Strength Analysis
26
M i R l d P 1 Ch 8 1/3
8/17/2019 Ind Presentation CSRH Intro Rule Updates
27/37
Main Rule updates – Pt 1 Ch 8 - 1/3Buckling
June 2013
• Sec 2: Slenderness requirements
– Geometry of the stiffener in Net thickness
– Plate panel: ReH can be based on mild steel provided the bucklngrequirements for prescriptive/ FE buckling comply with mild steel.
• Sec 3 Prescriptive requirements
– [3.2.1] Vertically stiffened side shell plating of Single Side Shell BCbetween hopper and top side tanks: Cases of Table 2 (Sec 5)corresponding to the shorter edge clamped to be considered togetherwith a mean σy stress and ψy = 1.
– [3.3.1] Side frame of single side shell of BC considered as stiffenerfor buckling assessment
• Sec 4 Buckling requirements for FE
– [2.3.3] d) Clerical correction in definition of “a”
– [2.4] Reference stress using stress based reference stress only (App 1)Displacement based reference stress removed.
– [4.1.1] Side shell of single side shell of BC: shorter edge of EPPconsidered clamped and ψ x = ψy = 1
– [4.1.2] Side frame of single side shell of BC considered as stiffenerfor the buckling assessment
Ch 8: Buckl ing
27
M i R l d P 1 Ch 8 2/3
8/17/2019 Ind Presentation CSRH Intro Rule Updates
28/37
Main Rule updates – Pt 1 Ch 8 - 2/3Buckling
June 2013
• Sec 5: Buckling capacity
– [2.2.5] F tran = 1.15 for single side shell of BC– [2.2.7] Applied stresses: stresses from beam/grillage analysis to be
corrected for Poisson effects ( ).
– Tab 2: Plane plate panels
• Case 2 (Simple support with y)
• New case 7 (long edge clamped with y)
• Corrections for case 8 (Short edge clamped with x)
• New case 9 (Short edge clamped with y)
• Corrections for case 10 (4 edges clamped with x)
• New case 12 (4 edges clamped with τ)
– Tab 3 Curved plate panels:
•
Editorial corrections• C value needs not to be taken less than expanded plane panel
– [2.3.4] Stiffener capacity: yw modified for angle and bulb profile.
– [2.3.5] Effective breadth modified.
– Tab 6 Clerical modification for Cwarp of the 4th Case
Ch 8: Buckl ing
28
M i R l d t Pt 1 Ch 8 3/3
8/17/2019 Ind Presentation CSRH Intro Rule Updates
29/37
Main Rule updates – Pt 1 Ch 8 - 3/3FE Buckling
June 2013
• App1 Stress based Reference Stress
– Regular panel• Longitudinal stress: a) quadratic distribution for plate buckling
b) weighted average for stiffener buckling
• Transverse stress: no modification (linear distribution)
– Irregular panel
• Weighted average approach with ψx = ψy = 1
Ch 8: Buckl ing
x
σ x
a
El. 1 El. 2 El. 3 El. 4 El. 5
Average =>
Stiff. buckling
Max => Plate buckling
29
M i R l d t Pt 1 Ch 9
8/17/2019 Ind Presentation CSRH Intro Rule Updates
30/37
Main Rule updates – Pt 1 Ch 9Fatigue
June 2013
• Re-arrangement of the sections.
• Sec 1 General considerations
– Material with ReH > 390 MPa or with fatigue performance: S-N Curves to beconsidered on a case-by-case basis.
• Sec 2 Structural details to be assessed
– Improvement of the figures for hot spots in Tables 4 through 18.
• Sec 3: Fatigue evaluation
– [3.2.1] Mean stress effect: σmCor , i( j) , σmax , ReEq– [3.3.1] Thickness effect: improvement for cruciform joint and clarification
between welded and non welded details for the n value
• Sec 4: Simplified stress analysis
– [4.1.1] Non linear factor introduced i.w.o. the water surface fNL and effectivebreadth modified.
– [4.2.6] Clarification for relative displacement in stress range.– Tab 4 stress concentration factors revised.– [5.3] Clarification for the methodology to apply in case of alternative design.
• Sec 5: FE Stress analysis– [3.1.2] and [4.2.3] Read out stress
• Average from each side of AA line and linear interpolation at xshift.
– [4.3.1] Hot spot in the web: σ HS = σshift – Tab 2 Stress magnification factor for Screening is revised.
• Sec 6: Design standards for details
– Distance to knuckle < 50mm
Ch 9: Fatigue
30
8/17/2019 Ind Presentation CSRH Intro Rule Updates
31/37
Main Rule updates – Pt 1 Ch11 & Ch12
June 2013
• Sec 1: Superstructures, deckhouses and companionways
– [1.1.1] Scope clarified.– [3.1] Superstructure sides and decks
– [3.2.1] Plating instead of deck plating of exposed decks
– [3.2.3] Beams and stiffeners instead of deck beams & longdeck stiff.
Ch 11:Superstructure,
Deckhouses and Hull
Outfitting
Ch 12: Construction
and Welding
• Sec 1: Construction and fabrication
– [3.3.1] bent plates: scope changed. 2 bullets apply only forcorrugated bhd subject to lateral liquid pressure.
• Sec 3: Design of weld joints
– [2.2.2] clarification of a few items
31
8/17/2019 Ind Presentation CSRH Intro Rule Updates
32/37
Main Rule updates – Pt 2 – Ch 1 & 2
June 2013
• Sec 2: Structural design principles
– [3.3.4] Hatchways: added requirements for protection againstwire rope.
• Sec 3: Hull local scantling
– [1.1.1] Side frame area: 1.1 coefficient was missing.
– [2.3.1], [2.3.2], [2.4.1] and [2.4.2] Steel coils, correction due to unitmodification of “ F ” in Ch 4
• Sec 5: Hatch covers
– Tab 3: consistency with Ch. 8
– [4.1.7]: Self weight to be considered for hatch cover analysis.
•
Sec 3: Hull local scantling– [1.5.4] Deck transverse adjacent to transverse bhd: missing with
regard to CSR-OT.
Ch 1: Bulk Carriers
Ch 2: Oil Tankers
32
8/17/2019 Ind Presentation CSRH Intro Rule Updates
33/37
What Next?
Consequence assessment
Schedule
8/17/2019 Ind Presentation CSRH Intro Rule Updates
34/37
Consequence assessment ships
ID Type Lpp B Tsc D Dwt
BC-1 Capesize 1 285 46 18 25 180200
BC-2 Capesize 2 284 45 18 25 180000
BC-3 Capesize 3 293 50 18 25 205000BC-4 Baby Cape 1 240 43 15 21 114500
BC-5 Baby Cape 2 248 43 15 20 115000
BC-6 Panamax 1 225 32 14 20 82000
BC-7 Panamax 2 223 32 15 20 81000
BC-8 Handymax 1 183 32 13 18 53000
BC-9 Handymax 2 185 32 13 18 57000
BC-10 Handymax 3 185 32 14 18 48000
June 2013
ID Type Lpp B Tsc D Dwt
OT-1 VLCC 1 319 60 23 30 318000
OT-2 VLCC 2 324 60 21 29 330000
OT-3 Suezmax1 264 48 17 24 158000OT-4 Suezmax2 264 50 17 23 163000
OT-5 Aframax 1 240 42 15 22 97000
OT-6 Aframax 2 240 44 15 21 103000
OT-7 Aframax 3 234 42 15 21 105000
OT-8 Panamax1 220 32 15 21 76000
OT-9 Panamax2 219 32 15 21 74000
OT-10 Handymax1 176 32 13 18 51000
Bulk carriers Oil tankers
CA Report based on ER April 2013 version available (1200 pages)
CA updates at each Rule Release
34
8/17/2019 Ind Presentation CSRH Intro Rule Updates
35/37
June 2013
Harmonised CSR - Time Schedule
2011 2012 2013 2014
Submission
1st External draft
1st Hearing
Industry
2nd HearingIndustry
Technical Committee
Review
IACS Council
Adoption
Final CSRH
Final draft
2nd External draft
2012-07-01
2013-12-31
External review period
Technical Committee review
IACS adoption
Entry into force (T.B.D.)
?
2013-04-01
2013-11-01
2013-12-18
35
Overall situation:
8/17/2019 Ind Presentation CSRH Intro Rule Updates
36/37
Overall situation:IMO & Harmonised CSR
June 2013
Jul
2012
Jan
2013
Jul
2013Jan
2014
Jul
2014
Industry Review FeedbackReworkIndustry
Review
FeedbackRework TC
Ext. Release CSR-H
IACSCouncil
AdoptionText of CSR-H and TB available onIACS web site:http://www.iacs.org.uk/
2nd Presentation to Industry,
June 2013: Athens, London: 18 & 20 Asia: 24, 26 & 28 Submission
1st Presentation
to Industry,Sept. 2012
36
8/17/2019 Ind Presentation CSRH Intro Rule Updates
37/37