INABENSA 1 Overhead Contact Line Installation on Spain´s High Speed Network

INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

  • Upload
    buinhu

  • View
    224

  • Download
    1

Embed Size (px)

Citation preview

Page 1: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA

1

Overhead Contact Line Installation on Spain´s High Speed Network

Page 2: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Abengoa and Inabensa. Railway Sector.

2

Abengoa (MCE: ABG) is an international company that applies innovative technology solutions for sustainability in the energy and environment sectors, generating energy from the sun, producing

biofuels, desalinating sea water and recycling industrial waste

Inabensa is the company of Abengoa developing Energy Construction and Concession Business.

•  Strategic partner of Adif –Spanish Rail- for 60 years.

•  Export to global markets:

  TCDD of Turkey

  FS of México

  SNCF of France

  CORE of India

Railway Sector

•  Exportation experience to Mecca-Medina high speed line.

•  Leading contractor in development of Spanish conventional and high speed rail.

Page 3: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA

3

Conventional Line Network

Inabensa works

-  Renewals & Upgrades

-  New works

-  Maintenance

-  Incidents resolutions

Over 23.000 STK

70% electrified

Page 4: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA

Spanish – High Speed Line Network

Feeding subst.

OHE Construction

Maintenance

4

Over 4.000 STK

Page 5: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Our activity in railways sector includes detailed design, procurement, installation, commissioning and maintenance.

Autotransformers

2

Rectifier substations

Catenary (new lines)

Catenary Upgrade

Auxiliary installations

We construct substations, both open air and GIS, for high speed lines with 1x25 kV and 2x25 kV feeding systems.

We install transformer centers and energy distribution systems to feed installations around a railway facility.

For DC electrified railways, we build rectifier substations.

We provide EPC turnkey projects for the installation of catenary system in new lines or existing lines to be electrified.

We build and install autotranformer centers for high speed lines with 2x25 kV feeding system.

When existing catenary systems may require, we renew and upgrade existing installation without service interruption.

Substations

1

3

4

5

6

Our activities

5

Page 6: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Cost Reduction on OHLE Contracts

6

Efficiency Savings Delivered…

By means of:

- Detailed engineering

- Investment in plant & machinery

- Planning & Programing

- Quality control

Page 7: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Foundations construction: From digging to drilling

  Excavator works for a long time

  Big surface affecting other systems

  Difficulties on mast adjustment

  High costs on concrete, labuor & shuttering

Gravity foundations…

  Faster drilling works

  Smaller surface

  Easy reference for mast location & adjustment

  Investment in plant and machinery

  Quality control

Cylindrical foundations…

7

Page 8: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Pole Erection

  Detailed engineering

  Material procurement

8

Pole erection is optimised work if all fittings have been pre-assembled

Assembly of all fittings prior to pole erection

  Safer work

  Cost optimisation

  Execution period improvement

Page 9: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Cantilever assembly and transportation to site

Key factors for a successful cantilever assembly

Cantilever design

 Actual position from mast to track

 Design and design quality control

9

Cantilever assembly

 Manufacturing jig design

 Assembly and assembly quality control

Page 10: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Cantilever assembly and transportation to site

Cantilever installation: marking and transportation

Ordered transportation to site

 Unique labeling of each cantilever identifying mast number and location.

 Cantilevers must be stacked in correct order to avoid time wasting looking for the right one and transported in “goal post” cradles to prevent damage.

10

Page 11: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Catenary wiring: the quality factor

 Performance

  1st step: Laying messenger wire on pulleys

  2nd step: Tensioning MW

  3rd step: Midpoint anchor installation

  4th step: Laying contact wire

  5th step: Tensioning CW

  6th step: Pulleys removal

 Quality

  Variable wiring speed: Micro undulations might

appear

 Risks

  Copper wires on pulleys are easily stolen

Catenary wiring: the old system

11

Page 12: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA Catenary wiring: the quality factor

Catenary wiring: the current system

12

Page 13: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA

13

Key Messages

  Working Safely   Working Collaboratively   Innovation and Continual Improvement

  Reduced Unit Cost   Shorter Construction Period

  An Improved Efficient Sustainable Solution

Lead to…

Page 14: INABENSA - Cost | Optimisation | Electrification | … Pole Erection Detailed engineering Material procurement 8 Pole erection is optimised work if all fittings have been pre-assembled

INABENSA

UK Strategy:

14