Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam i
IMPROVING THE DECISION-MAKING
PROCESS OF DEMOLITION WASTE
MANAGEMENT IN URBAN
REDEVELOPMENT PROJECTS
IN VIETNAM
Diep Thi BUI
Master of Science
Dr. Timothy Rose
Prof. Martin Skitmore
Submitted in fulfilment of the requirements for the degree of
Doctor of Philosophy
School of Civil Engineering and Built Environment
Science and Engineering Faculty
Queensland University of Technology
2018
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Keywords
Decision-making framework
Decision support system
Demolition waste
Framework for demolition waste management
GIS-based model
Supporting database
Urban redevelopment
Urban renewal
Waste management
Vietnam
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam iii
Abstract
Over the last three decades, rising population and increasing urbanisation have
significantly impacted on aging urban infrastructure in developed and developing
countries. Thus, sustainable urban redevelopment has become an important strategy in
many cities around the world. Although urban redevelopment benefits communities
by upgrading housing conditions and infrastructure, it can be a source of conflict
resulting from the imbalance among economic, environmental and social objectives.
A particularly significant problem is the massive waste stream that is produced as a
result of the demolition process of aging buildings in urban redevelopment projects.
Effectively planning for demolition waste management practice, therefore, has become
a priority for policy makers. In Vietnam, urban redevelopment projects are now
required to be delivered in a sustainable way due to the rising awareness of sustainable
construction processes. However, the management of demolition waste has not been
effective yet due to the confusion of how a sustainability policy is implemented in
practice and the insufficient knowledge and the lack of information available to
project’s stakeholders on demolition waste management. Within this context, this
research develops a decision-making framework consisting of key decision-making
factors and a database to support the decision-making process of demolition waste
management in Vietnamese urban redevelopment projects.
Firstly, this research develops a preliminary conceptual framework that encapsulates
19 themes under five categories including technical, environmental, economic, social,
and institutional factors. This framework forms 53 factors in total that are regarded as
important influencing elements in demolition waste management decision-making
process. Twenty-four critical factors were then identified through a questionnaire
survey of 216 stakeholders in Vietnamese urban redevelopment projects, allowing the
revision and refinement of the conceptual framework. Twenty-two semi-structured
interviews were then conducted with a focus on the in-depth understanding of the
importance of each critical factor and the development of action plans aiming at
improving demolition waste management decision-making process in Vietnam.
Further, a GIS-based data model is proposed as a decision support tool for demolition
waste management at district level. This model is designed for the case study in
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Vietnam in which spatial information of urban redevelopment projects and information
of demolition waste management are integrated. Finally, a meaningful decision-
making framework is proposed for improving demolition waste management in
Vietnamese urban redevelopment projects.
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam v
Table of Contents
Keywords ................................................................................................................................. ii
Abstract ................................................................................................................................... iii
Table of Contents ...................................................................................................................... v
List of Figures ......................................................................................................................... xi
List of Tables ........................................................................................................................ xiii
List of Abbreviations .............................................................................................................. xv
Statement of Original Authorship ......................................................................................... xvi
Acknowledgements .............................................................................................................. xvii
Chapter 1: Introduction ...................................................................................... 1
1.1 INTRODUCTION .......................................................................................................... 1
1.2 RESEARCH BACKGROUND ...................................................................................... 1
1.3 RESEARCH PROBLEM................................................................................................ 3
1.4 RESEARCH QUESTIONS ............................................................................................ 4
1.5 RESEARCH AIM AND OBJECTIVES ........................................................................ 5
1.6 RESEARCH SIGNIFICANCE ....................................................................................... 6
1.7 OVERVIEW OF RESEARCH METHODOLOGY ....................................................... 7
1.8 SCOPE AND LIMITATIONS OF THE RESEARCH ................................................... 9
1.9 OUTLINE OF THE THESIS .......................................................................................... 9
1.10 SUMMARY .................................................................................................................. 11
Chapter 2: Literature Review ........................................................................... 12
2.1 INTRODUCTION ........................................................................................................ 12
2.2 URBAN REDEVELOPMENT ..................................................................................... 12
2.2.1 Definitions .......................................................................................................... 12
2.2.2 Global trend in urban redevelopment ................................................................. 15
2.3 THE LINK BETWEEN URBAN REDEVELOPMENT AND SUSTAINABILITY .. 20
2.4 DEMOLITION WASTE MANAGEMENT ................................................................. 23
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
2.4.1 The lifecycle of the built environment ............................................................... 23
2.4.2 Integrated approach to waste management in construction industry ................. 25
2.4.3 Current status of demolition waste .................................................................... 28
2.5 DEMOLITION WASTE MANAGEMENT IN URBAN REDEVELOPMENT
PROJECTS ............................................................................................................................. 32
2.5.1 Overview of demolition waste in urban redevelopment projects ...................... 32
2.5.2 Current research trend in urban redevelopment demolition waste
management ....................................................................................................... 34
2.6 URBAN REDEVELOPMENT DEMOLITION WASTE MANAGEMENT IN
VIETNAM ............................................................................................................................. 41
2.6.1 Urban redevelopment in Vietnam ...................................................................... 41
2.6.2 Demolition waste management in Vietnamese urban redevelopment
projects ............................................................................................................... 45
2.7 RESEARCH GAP ........................................................................................................ 48
2.8 RESEARCH CONCEPTUAL FRAMEWORK .......................................................... 50
2.8.1 Organisational decision-making ........................................................................ 50
2.8.2 Research factors influencing demolition waste management in urban
redevelopment projects ...................................................................................... 53
2.9 SUMMARY ................................................................................................................. 62
Chapter 3: Research Design .............................................................................. 63
3.1 INTRODUCTION ....................................................................................................... 63
3.2 RESEARCH PROPOSITION ...................................................................................... 63
3.3 RESEARCH PHILOSOPHY ....................................................................................... 64
3.4 RESEARCH DESIGN ................................................................................................. 67
3.4.1 Research approach ............................................................................................. 67
3.4.2 Selection of research methods ........................................................................... 69
3.5 RESEARCH PROCESS .............................................................................................. 71
3.5.1 Establishing conceptual framework ................................................................... 71
3.5.2 Development of the framework ......................................................................... 71
3.5.3 Development of supporting database ................................................................. 73
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam vii
3.6 RESEARCH METHODS ............................................................................................. 73
3.6.1 Literature review ................................................................................................ 73
3.6.2 Questionnaire survey .......................................................................................... 75
3.6.3 Interview ............................................................................................................. 79
3.6.4 Case study........................................................................................................... 81
3.7 ETHICAL CONSIDERATIONs .................................................................................. 83
3.8 SUMMARY .................................................................................................................. 84
Chapter 4: Survey Study ................................................................................... 85
4.1 INTRODUCTION ........................................................................................................ 85
4.2 QUESTIONNAIRE DESIGN ...................................................................................... 85
4.3 SURVEY INSTRUMENT............................................................................................ 87
4.4 SURVEY RESPONSE RATE AND VALIDITY ........................................................ 88
4.5 QUESTIONNAIRE RESULTS AND ANALYSES .................................................... 89
4.5.1 Respondents’ profiles ......................................................................................... 89
4.5.2 Reliability of the questionnaire .......................................................................... 92
4.5.3 Respondents’ perspectives ................................................................................. 92
4.5.4 Comparison of rankings among five groups of respondents .............................. 98
4.5.5 Critical decision-making factors for demolition waste management in
Vietnamese urban redevelopment projects ....................................................... 103
4.5.6 Agreement on critical decision-making factors ................................................ 107
4.6 MAIN FINDINGS OF THE QUESTIONNAIRE SURVEY ..................................... 117
4.6.1 Main findings ................................................................................................... 117
4.6.2 Revised conceptual framework ........................................................................ 118
4.7 SUMMARY ................................................................................................................ 119
Chapter 5: Interview ........................................................................................ 121
5.1 INTRODUCTION ...................................................................................................... 121
5.2 INTERVIEWEES’ SELECTION AND THEIR BACKGROUND ........................... 121
5.2.1 Selection of interviewees .................................................................................. 121
5.2.2 Interviewee background ................................................................................... 122
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
5.3 INTERVIEW INSTRUMENTS................................................................................. 124
5.4 INTERVIEW FORMAT AND STRUCTURE .......................................................... 124
5.5 INTERVIEW RESULTS AND DISCUSSION ......................................................... 126
5.5.1 Choosing demolition methods ......................................................................... 126
5.5.2 Demolition waste management procedures ..................................................... 127
5.5.3 Waste classification and estimation ................................................................. 128
5.5.4 Planning for landfill, sorting area, and storage ................................................ 129
5.5.5 Training ............................................................................................................ 131
5.5.6 Stakeholder awareness ..................................................................................... 132
5.5.7 The uniqueness of demolition waste ................................................................ 133
5.5.8 “3R” strategies and recovery ........................................................................... 134
5.5.9 Environmental impact assessment ................................................................... 135
5.5.10 Cost estimation and cost-effectiveness .......................................................... 136
5.5.11 Preservation .................................................................................................... 137
5.5.12 Reduction of disturbance on the community .................................................. 138
5.5.13 Regulations/guidelines ................................................................................... 139
5.5.14 Stakeholder engagement ................................................................................ 139
5.5.15 Information and communication .................................................................... 140
5.6 IMPROVING DEMOLITION WASTE MANAGEMENT IN VIETNAMESE
URBAN REDEVELOPMENT PROJECTS ........................................................................ 141
5.7 SUMMARY ............................................................................................................... 144
Chapter 6: Case study ...................................................................................... 145
6.1 INTRODUCTION ..................................................................................................... 145
6.2 CASE STUDY PURPOSE ......................................................................................... 145
6.3 case STUDY SITE CONTEXT ................................................................................. 146
6.4 case study DATA COLLECTION METHOD ........................................................... 149
6.4.1 The spatial data ................................................................................................ 150
6.4.2 The attribute information ................................................................................. 153
6.5 DEVELOPMENT OF DEMOLITION WASTE DATABASE ................................. 153
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam ix
6.6 CASE STUDY RESULTS AND DISCUSSION ....................................................... 154
6.6.1 Demolition waste estimation ............................................................................ 154
6.6.2 Demolition waste classification ........................................................................ 158
6.6.3 Demolition waste transport .............................................................................. 160
6.6.4 Selection of landfill sites .................................................................................. 162
6.7 SUMMARY ................................................................................................................ 164
Chapter 7: Discussion and Findings ............................................................... 165
7.1 INTRODUCTION ...................................................................................................... 165
7.2 CONCEPTUAL FRAMEWORK ............................................................................... 165
7.3 REVISED CONCEPTUAL FRAMEWORK ............................................................. 167
7.3.1 Technical factors .............................................................................................. 168
7.3.2 Environmental factors ...................................................................................... 171
7.3.3 Economic factors .............................................................................................. 173
7.3.4 Social factors .................................................................................................... 173
7.3.5 Institutional factors ........................................................................................... 174
7.4 GIS-BASED DECISION SUPPORT SYSTEM ......................................................... 176
7.5 FINALISED DECISION-MAKING FRAMEWORK ............................................... 178
7.6 FINDINGS RELATED TO THE EXTANT LITERATURE ..................................... 181
7.7 SUMMARY ................................................................................................................ 182
Chapter 8: Conclusion ..................................................................................... 183
8.1 INTRODUCTION ...................................................................................................... 183
8.2 REVIEW OF RESEARCH OBJECTIVES AND DEVELOPMENT PROCESSES . 183
8.3 DECISION-MAKING FRAMEWORK FOR IMPROVING DEMOLITION WASTE
MANAGEMENT IN VIETNAMESE URBAN REDEVELOPMENT PROJECTS ........... 185
8.3.1 The factors influencing demolition waste management in Vietnamese
urban redevelopment projects........................................................................... 185
8.3.2 Action plans for improving demolition waste management in Vietnamese
urban redevelopment projects........................................................................... 188
8.3.3 Supporting database for urban redevelopment demolition waste
management decision-making process ............................................................. 191
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
8.4 RESEARCH CONTRIBUTIONS .............................................................................. 192
8.4.1 Contribution to academic knowledge .............................................................. 193
8.4.2 Contribution to the industry practice ............................................................... 194
8.5 RESEARCH LIMITATIONS .................................................................................... 195
8.6 RECOMMENDATIONS FOR FUTURE RESEARCH ............................................ 196
Bibliography ........................................................................................................... 199
Appendices .............................................................................................................. 219
Appendix A. Questionnaire survey ...................................................................................... 219
Appendix B. Survey Analysis results ................................................................................... 233
Appendix C. Invitation letter – Interview............................................................................. 251
Appendix D. Data collection and analysis for case study .................................................... 253
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam xi
List of Figures
Figure 1-1: Research focus ......................................................................................... 3
Figure 2-1: Triple bottom line of sustainable urban redevelopment ......................... 22
Figure 2-2: A C&D waste management framework. ................................................ 24
Figure 2-3: Environmental effects as a function of time. ......................................... 25
Figure 2-4: Conceptual model for sustainable construction waste management
(Manowong, 2012) ....................................................................................... 26
Figure 2-5: System for integrated demolition waste management ........................... 27
Figure 2-6: Hierarchy of construction and demolition waste management
(Peng, Scorpio, & Kibert, 1997) .................................................................. 28
Figure 2-7: The aging blocks in Ba Dinh district, Hanoi .......................................... 42
Figure 2-8: The aging buildings in District 10, Ho Chi Minh City .......................... 43
Figure 2-9: Aging building in Le Chan district, Hai Phong ..................................... 44
Figure 2-10: Steps of a sustainable decision-making model for waste
management. ................................................................................................ 52
Figure 2-11: Conceptual framework of effective DW management in urban
redevelopment projects ................................................................................ 56
Figure 3-1: Research proposition .............................................................................. 64
Figure 3-2: Philosophical Positions (Creswell, 2013) .............................................. 65
Figure 3-3: Research process .................................................................................... 72
Figure 3-4: Process of GIS-based model for the development of supporting
database ........................................................................................................ 83
Figure 4-1: Distribution of the respondents by the places in which they
implemented the urban redevelopment projects .......................................... 91
Figure 4-2: Revised conceptual framework for improving decision-making in
DW management for urban redevelopment projects ................................. 119
Figure 6-1: Location of Ba Dinh district ................................................................. 148
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Figure 6-2: Locations of four urban redevelopment projects in Ba Dinh district ... 152
Figure 6-3: The total volume of DW generation in four urban redevelopment
projects ....................................................................................................... 156
Figure 6-4: The DW volume generation in four projects presented in GIS
model .......................................................................................................... 157
Figure 6-5: Demolition waste generation divided by materials in four urban
redevelopment projects .............................................................................. 158
Figure 6-6: Demolition waste generation divided by materials in four urban
redevelopment projects presented in GIS model ....................................... 159
Figure 6-7: Estimation of the number of pick-up trucks per project for non-
inert waste .................................................................................................. 161
Figure 6-8: The information of C&D waste landfill sites in Hanoi ........................ 163
Figure 7-1: Finalised decision-making framework for improving DW
management in urban redevelopment projects at district level .................. 180
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam xiii
List of Tables
Table 1-1: Research methods are used to address the research objectives ................. 8
Table 2-1: Key reviewed themes ............................................................................... 34
Table 2-2: Research factors influencing DW management in urban
redevelopment project .................................................................................. 55
Table 3-1: Quantitative, qualitative, and mixed methods approach analyses by
Creswell (2009) ............................................................................................ 69
Table 3-2: Summary of selection of research methods ............................................. 70
Table 3-3: Methods of statistical analysis ................................................................. 76
Table 4-1: Structure of the questionnaire .................................................................. 87
Table 4-2: Respondents’ information ........................................................................ 90
Table 4-3: Academics’ ratings of decision-making factors of demolition waste
management ................................................................................................. 93
Table 4-4: Planners’ ratings of decision-making factors of demolition waste
management ................................................................................................. 94
Table 4-5: Consultants’ ratings of decision-making factors of demolition waste
management ................................................................................................. 95
Table 4-6: Engineers’ rating of decision-making factors of demolition waste
management ................................................................................................. 97
Table 4-7: Policy Makers’ rating of decision-making factors of demolition
waste management ....................................................................................... 98
Table 4-8: A comparison of ratings of decision-making factors for urban
redevelopment DW management among key stakeholders ....................... 100
Table 4-9: Factors rated by the respondents as important and very important
(mean >4) ................................................................................................... 104
Table 4-10: Kendall’s coefficient of concordance .................................................. 106
Table 4-11: Comparison of rating of critical decision-making factors for
improving urban redevelopment DW management among key
stakeholders ................................................................................................ 109
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Table 4-12: One-Way ANOVA statistic for log-transformed data of critical
decision-making factors for improving urban redevelopment DW
management ............................................................................................... 111
Table 4-13: Adjusted differences based on p-value generated in Kruskal-
Wallis test ................................................................................................... 112
Table 4-14: Probability values in Mann-Whitney test on three critical factors ...... 114
Table 4-15: Probability values in 2-sample t test on three critical factors .............. 115
Table 4-16: Adjusted differences based on p-value generated in Mann-
Whitney test ............................................................................................... 116
Table 5-1: Statistical Breakdown of Interviewees .................................................. 122
Table 5-2: Interviewee Profiles ............................................................................... 123
Table 5-3: Interview questions ................................................................................ 125
Table 5-4: Major findings of the interview study .................................................... 141
Table 6-1: The project information of the case study ............................................. 149
Table 8-1: The research design related to research objectives ................................ 184
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam xv
List of Abbreviations
ArcGIS GIS software made by ESRI
DW Demolition waste
C&D Construction and demolition
GIS Geographic Information System
MSWM Municipal solid waste management
SPSS Statistical Package for the Social Sciences
FDR False Discovery Rate
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Statement of Original Authorship
The work contained in this thesis has not been previously submitted to meet
requirements for an award at this or any other higher education institution. To the best
of my knowledge and belief, the thesis contains no material previously published or
written by another person except where due reference is made.
Signature: QUT Verified Signature
Date: November 2018
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam xvii
Acknowledgements
I am close to accomplishing the greatest challenge of my life thus far. This journey has
been accompanied by unforgettably sweet and bitter moments. I would like to take this
opportunity to thank those whose support, assistance, and favour have been stepping
stones in completing my PhD journey.
First and foremost, I would like to express my sincerest appreciation to my previous
principal supervisor, Professor Jay Yang, who originally suggested and guided the
research in the first milestone of my PhD study. My deepest appreciation goes to my
current principal supervisor, Dr. Timothy Rose, who has always been actively engaged
throughout my PhD project. There is no way I could have completed this thesis without
extensive support from my principal supervisor. Special thanks are also extended to
Professor Martin Skitmore, my associate supervisor, who supported and shared
knowledge and experience in data analysis. Thank you, my supervisory team; you have
kindly opened up the doors and guided me to academia.
I gratefully acknowledge the School of Civil Engineering and Built Environment,
Science and Engineering Faculty, Queensland University and Technology (QUT) and
Institute of Strategy and Policy on Natural resources and Environment (ISPONRE) in
Vietnam for supporting me in the PhD journey. My special thanks go to Ms. Sascha
Mitchell, a fantastic English teacher in the EAP course sponsored by QUT, who helped
me in improving my academic writing skills. I also acknowledge the services of
professional editor, Diane Kolomeitz, who provided copyediting and proofreading
services, according to the guidelines laid out in the university-endorsed national
‘Guidelines for editing research theses’.
My love and deep gratitude go to my parents and my parents-in-law, who have always
provided me with their unconditional love, encourage and support throughout my PhD
journey and my academic career. My enduring appreciation and deep love are due to
my husband, Bich, my son, Khai, and my daughter, Phuong, who understand,
spiritually support and are the source of my motivation, whether my mood is up or
down. This dissertation would not have been possible without you; I give you all my
love.
improving the decision-making process of demolition waste management in urban redevelopment projects in vietnam
Last but not least, many thanks to my sisters and brothers, and my dearest friends in
Vietnam, at QUT, and in Brisbane who are always beside me, encouraging and
inspiring me to overcome the challenges in my life.
Chapter 1: Introduction 1
Chapter 1: Introduction
1.1 INTRODUCTION
This chapter discusses the research background and the research problem statement of
the study. Research questions, research objectives, and research methodology are
formulated to achieve the research aims and figure out the significance of the research.
This is followed by a discussion on the scope and limitations of the research. The final
section of the chapter provides the outline of the thesis and the summary of the study.
1.2 RESEARCH BACKGROUND
Throughout the last century, rapid population growth and increasing urbanisation have
had a profound influence on urban infrastructure. Urban redevelopment has become
inevitable in the process of urban change, which is one of the important concerns in
both theory and practice. Large-scale housing and urban redevelopment activities are
taking place in many cities all over the world, in order to upgrade housing conditions
and urban infrastructure. Urban redevelopment is considered a complex issue because
of the large number of stakeholders, the financial commitment needed, and the impact
on society and the environment (Roussat, Dujet, & Mehu, 2009b; Zheng, Shen, &
Wang, 2014). More recently, urban redevelopment issues have become the focus of
attention in both developed and developing countries, resulting in several studies on
pertinent topics (Couch & Dennemann, 2000; Munoth, Jain, Raheja, & Brar, 2013;
Yau & Ling Chan, 2008). Researchers have been paying increasing attention to
sustainable urban redevelopment to balance the economic, social and environmental
issues resulting from redevelopment processes (Leigh & Patterson, 2006; Munoth, et
al., 2013; Yau & Ling Chan, 2008; Zheng, et al., 2014). According to Zheng et al.
(2014), despite the benefits of a holistic perspective of urban sustainable
redevelopment, most researchers in this discipline have concentrated exclusively on
such aspects as heritage conservation, housing development and resident relocation,
while other urban redevelopment issues, such as demolition waste and resource
management, also need to be taken into consideration (Fang & Zhang, 2003; Yeoh &
Huang, 1996).
2 Chapter 1: Introduction
Despite the increase in global research into construction waste management (Yuan &
Shen, 2011), demolition waste (DW) management has received little attention,
particularly from an urban redevelopment perspective at both project and regional
levels (Yuan, Shen, & Wang, 2011). To date, critical reviews of construction and
demolition (C&D) waste management research have been conducted by Wu, Yu, Shen
and Liu (2014) and Yuan & Shen (2011). However, while such reviews provide a
broader coverage of C&D waste management in the construction industry, they do not
focus specifically on DW management, especially in the field of urban redevelopment.
Many countries, such as Hong Kong, the USA, and the UK, have associated with the
problems of DW with urban redevelopment (Couch & Dennemann, 2000; Farfel et al.,
2005; Poon, Ann, & Ng, 2001). For example, due to the rapid of urban redevelopment,
Hong Kong is facing the threat of overflowing landfills (Poon, Yu, See, & Cheung,
2004). It is estimated that about 1.8 million US housing units were demolished in the
2000s (Farfel, et al., 2005) that resulted in a massive amount of DW. However, for
developing countries in particular, the issue of urban redevelopment DW management
has received less attention from both the academic community and practitioners.
Vietnam has also encountered the issues of urban redevelopment. Many cities in
Vietnam have experienced decades of exponential population growth and
urbanisation. In addition, the demand for improving the quality of urban life has been
conducive to the redevelopment of many old parts of cities. In fact, Vietnam urban
redevelopment programs have announced a large-scale demolition of old buildings,
planning to make way for new constructions. This gives rise to the need for
management of DW, which is generated in the demolition process.
This study will focus on the processes of DW management for the urban
redevelopment projects (Figure 1-1). It also analyses the decision-making process of
DW management at the district level and explores the tool of Geographic Information
System (GIS) to assist stakeholders in improving the decision-making process.
Urban changes ‐ Population ‐ Urbanisation
Urban decay/dilapidation
Urban redevelopment
Economic issues Environmental issues Social issues
Chapter 1: Introduction 3
This research is also necessary for the practitioners and researchers in the decision-
making process of integrated DW management, as it will assist them to increase the
recovery rate, to ameliorate the environmental impacts and to guarantee the
sustainability of the urban redevelopment.
1.3 RESEARCH PROBLEM
According to Yau and Ling Chan (2008) and Munoth et al. (2013), the concept of
sustainability corresponds to urban redevelopment in terms of environmental,
economic and social aspects. Nevertheless, Zheng et al. (2014) conclude that most
research focused narrowly on one or two aspects of sustainable urban renewal at a
time. While other urban redevelopment issues are seriously considered, such as
heritage conservation, housing development and resident relocation (Fang & Zhang,
2003; Yeoh & Huang, 1996), waste management was not managed in a comprehensive
manner. DW management has received much attention over the last two decades as
one of the main indicators of sustainable urban redevelopment. However, DW
management knowledge and experience in urban redevelopment projects are still
limited.
DW management in urban redevelopment project requires the effective engagement
of a wide range of stakeholders, such as planners, policy makers, constructors, sub-
constructors and the members of wider communities (Poon, et al., 2001). A successful
strategy to integrate the DW management process is to incorporate all key stakeholders
into the demolition process (del Río Merino, Azevedo, & Gracia, 2009; Poon, et al.,
2001; Poon, et al., 2004). This requires an application combining the information and
knowledge of waste management in order to provide a decision-making framework
Figure 1-1: Research focus
4 Chapter 1: Introduction
throughout the process. This will ensure that the responsibilities are clearly defined,
assigned and allocated to the right stakeholders, which will save time and the cost of
the DW management process.
Despite the negative influences of the DW stream, there is still a dearth of accurate
information compared to construction waste data, especially in developing countries
(Wu, Ann, Shen, & Liu, 2014). This is because DW is often studied under the term of
“C&D waste” or is even mixed up with municipal solid waste. This has led to limited
understanding of DW management, especially DW as a result of urban redevelopment
projects.
In addition, there is a lack of stakeholders’ interest in dealing with DW, since it costs
money and time. There is the need to identify how decisions are made, who could be
involved in this process and their relationships in effective DW management. A clearly
planned DW management is advisable for stakeholders. Thus, it is significant to
identify the decision-making factors affecting DW management and develop a
decision support system to facilitate the DW management process.
Through a case study in Hanoi, the framework of the decision-making process and
decision support system is proposed with a view to closing the substantial gap as
mentioned above. The research results would assist the decision-makers in identifying
the most effective approach of DW management with respect to different criteria.
The mixed-method research comprised a large sample of key industry stakeholders
involved in the DW management process. As an empirical contribution, this work
provides a greater insight into how to improve DW management processes and support
decision-making, particularly considering the unique challenges faced in urban
redevelopment across developing nations.
1.4 RESEARCH QUESTIONS
In view of the research background and research problems outlined in the previous
sections, three research questions are raised to direct the researcher in achieving the
research aim. The research examined the following questions:
(1) What are the key decision-making factors influencing demolition waste
management in Vietnamese urban redevelopment projects?
Chapter 1: Introduction 5
The selection of appropriate solutions and tools towards making decisions for DW
management in urban redevelopment projects depends largely on the perspectives and
consideration of key stakeholders with regards to integrated waste management.
Therefore, considered decisions made from the key stakeholders’ perspectives are
investigated via the first stage of the research – the large scale survey.
(2) How do the key decision-making factors influence demolition waste management
in Vietnamese urban redevelopment projects?
It is essential to understand how the key decision-making factors influence the
improvement of DW management in Vietnamese urban redevelopment projects. There
is limited existing research on DW management, especially in developing countries,
in the context of urban redevelopment that identifies and investigates the critical
decision-making factors and various decision support tools to provide a valid platform
for this research. This research question is investigated via the second stage of the
research: the interview program.
(3) What is the necessary information to support key stakeholders in demolition waste
management in Vietnamese urban redevelopment projects at the district level?
To facilitate effective DW management in urban redevelopment projects, key
stakeholders require requisite information to support their making decisions on DW
management. This is necessary in terms of guiding decision makers to implement
appropriate strategies and actions. The information system should be able to be
assessed and analysed by every stakeholder in different projects at the district level.
1.5 RESEARCH AIM AND OBJECTIVES
The aim of this research is to establish a comprehensive decision-making framework
for improving DW management in Vietnamese urban redevelopment projects at the
district level. The research will explore the key factors that need to be taken into
account and identify the necessary information to support the decision-making process
of DW management with respect to balancing the environmental, economic and social
targets.
In order to achieve the research aim and address the research questions above, three
main objectives are identified:
6 Chapter 1: Introduction
(1) To explore the current DW management in urban redevelopment projects and in
the context of Vietnam.
‐ Establishing the link between urban redevelopment and sustainability;
‐ Exploring the status of DW management in urban redevelopment projects;
‐ Revealing the existing research and decision tools on DW management;
‐ Examining the context of DW management in Vietnam urban redevelopment
projects;
‐ Investigating the key influencing factors of DW management.
(2) To identify critical decision-making factors of DW management in urban
redevelopment projects.
‐ Investigating the different concerns and expectations of key stakeholders in
making decisions on Vietnamese urban redevelopment DW management;
‐ Identifying the critical decision-making factors in achieving effective DW
management;
‐ Investigating the action plans for each critical factor to enhance urban
redevelopment DW management in Vietnam.
(3) To develop a decision-making framework and critical supporting information to
assist decision makers in improving demolition waste management in Vietnamese
urban redevelopment projects at the district level.
‐ Identifying the necessary information to support decision makers in the
decision-making process of urban redevelopment demolition waste
management;
‐ Developing the supporting database of DW management at district level in
GIS-based model for an applied case study in Vietnam
‐ Integrating a decision-making framework with a GIS-based system for
improving DW management in Vietnamese urban redevelopment projects
with respect to sustainability at district level;
1.6 RESEARCH SIGNIFICANCE
Along with the overall growth of the world's population and continuing urbanisation
process, large-scale housing and urban redevelopment activities are taking place in
many cities throughout the world in order to upgrade housing conditions and urban
Chapter 1: Introduction 7
infrastructure. As a result of the growth of urban redevelopment, DW volumes are
predicted to keep rising. This poses challenges for many urban areas facing a shortage
of capacity landfill and a potentially severe environmental impact.
The demolition of existing buildings is a predominant feature of urban redevelopment,
therefore its waste management is particularly important. DW management has
received much attention over the last two decades as one of the main indicators of
sustainable construction (Munoth, et al., 2013; Qualharini & Flemming, 2009; Yau &
Ling Chan, 2008). However, there has been limited research on DW management in
the context of urban redevelopment. Although developing countries have experienced
problems of DW caused by urban redevelopment, they seem to be comparatively less
active in DW management research.
This study will investigate the research trend and existing decision tools of DW
management in urban redevelopment projects. This study subsequently uncovers the
list of key stakeholders’ considerations of urban redevelopment DW management with
respect to technical, environmental, social, economic and institutional aspects. The
critical decision-making factors are discussed to provide valuable information for
decision makers in urban redevelopment of DW management. The decision-making
framework in urban redevelopment of DW management is the outcome of the research.
In addition, the decision support system is developed by GIS-based model will
facilitate stakeholders making decision of DW management.
This study will further contribute by offering the framework for other developing
countries that have similar circumstances of urban redevelopment of DW
management, such as China, Thailand, India and Brazil.
1.7 OVERVIEW OF RESEARCH METHODOLOGY
Research design is a plan for undertaking research to answer the research questions by
adopting appropriate and feasible methods (Sproull, 2002). Fellow & Liu (2015) stated
that choosing the research methods requires the logic and relationship between data
collection analysis and the research questions. The body of knowledge can be
developed with confidence only when proper methodologies are employed with
thoroughness (Fellows & Liu, 2015)..
In this study, a decision-making framework is established to support the process of
DW management in the urban redevelopment practice. Therefore, a mixed method is
8 Chapter 1: Introduction
employed to enable the researcher to review the current situation, identify the critical
decision-making factors and develop the decision support system in order to achieve
the research objectives. Qualitative and quantitative approaches can be applied in
different forms according to different research stages. Four main research methods are
adopted in this study, including literature reviews, questionnaires, semi-structured
interviews, and case study. Table 1-1 presents how the research methods were used to
address the research objectives.
Table 1-1: Research methods are used to address the research objectives
Research objectives
Research methods
To explore the current DW management in
urban redevelopment projects and in the context of Vietnam
To identify critical decision-making factors of DW
management in urban redevelopment projects
To develop a decision-making framework and
critical supporting information in improving demolition waste management in Vietnamese urban redevelopment projects at the district level
Literature review X
Questionnaire X X
Semi-structured
interview X X
Case study X
In the preliminary stage, the interdisciplinary literature associated with urban
redevelopment, DW management and sustainability was reviewed to identify the
research gaps and establish the theoretical framework. The questionnaire survey was
employed to determine the concerns and expectations of key stakeholders in making
decisions about DW management in urban redevelopment projects. With the aid of the
quantitative analysis of questionnaire survey results, critical decision-making factors
were formulated to develop a conceptual framework. In this research, the semi-
structured interview approach was subsequently employed in the qualitative analysis
for more in-depth understanding of the critical decision-making factors.
Chapter 1: Introduction 9
The supporting database was developed by GIS-based solutions for an applied case
study to practically formulate the DW management database and to illustrate the
feasibility of the framework. This database is based on the critical factors and action
plans revealed in previous stages and is integrated into the decision-making framework
of DW management for the case study of urban redevelopment projects in Hanoi,
Vietnam.
1.8 SCOPE AND LIMITATIONS OF THE RESEARCH
This research was designed to develop a decision-making framework targeted at DW
management for Vietnam’s urban redevelopment projects. Particular emphasis is
placed upon DW in the redevelopment projects of aging buildings, which are
demolished because of urban decay.
The research first explores the research gaps and theoretical framework based on
existing international studies on urban redevelopment DW management. This research
then focuses on investigating key stakeholders’ perspectives about decision-making
factors that influence urban redevelopment DW management with respect to
sustainability. The key stakeholders participating in this research are categorised into
five main groups: academics/researchers, planners, consultants, engineers and policy
makers. The respondents of the questionnaire survey and interviews are from different
backgrounds and play various roles of DW management in the urban redevelopment
projects.
Research data was collected in three main cites in Vietnam, namely Hanoi, Hai Phong
and Ho Chi Minh city, which have witnessed the process of urban redevelopment. Four
urban redevelopment projects in Hanoi are chosen as a case study to develop DW
management database. The research results are, therefore, applicable in Vietnam only
because the case study is limited to a particular set of decision-making factors.
1.9 OUTLINE OF THE THESIS
This thesis consists of eight chapters. A brief summary of each chapter is outlined as
follows. Chapter 1 begins with the introduction section, which describes the direction
of the research. It also explains the research background and research problems. Then,
research questions are raised before the research aim and objectives are formulated.
10 Chapter 1: Introduction
Finally, Chapter 1 discusses the research significance, research methodology, research
scope and limitations.
Chapter 2 reviews the current theory and former studies relating to the research topic.
The topics covered include the concept of urban redevelopment and sustainable urban
redevelopment, DW management in urban redevelopment projects, and the theory of
decision-making. The theoretical factors that influence the decision-making process of
urban redevelopment DW management are subsequently identified in this chapter.
Chapter 3 delivers the methodology of the research. It presents the research design
before describing the selected research methods. Research development is composed
of qualitative and quantitative analysis, including a literature review, questionnaires,
interviews, and case study. Ethical considerations are also provided at the end of the
chapter.
Chapter 4 presents the quantitative analysis of the survey data and the findings of the
questionnaire survey. It discusses the questionnaire design, the survey instrument, the
survey response rate and the respondents’ profiles. The key stakeholders’ perspectives
of decision-making factors influencing urban redevelopment DW management are
then identified. The main findings from the questionnaire survey are outlined and the
conceptual framework is also revised.
Chapter 5 illustrates the qualitative analysis of the interview data and the findings of
the interviews. The selection of interviewees and their profiles are briefly introduced.
The interview instruments and structures are then presented before findings and action
plans based on the interview are outlined.
Chapter 6 introduces the GIS-based approach for an applied case study to practically
formulate the supporting database of DW management in Vietnamese urban
redevelopment projects.
Chapter 7 discusses the findings from the data analysis of the questionnaire survey and
interviews, which encapsulates the decision-making framework. The results of
supporting database of DW management are then discussed. Accordingly, the
decision-making framework is finalised.
Chapter 8 sketches the research findings in relation to the research objectives and
research questions. The research contributions and limitations of the research are also
highlighted before future directions are recommended.
Chapter 1: Introduction 11
1.10 SUMMARY
This chapter provides an overview of the research. It first reveals the research
background and research problems regarding urban redevelopment DW management.
The research aim and objectives are clearly defined to address the research questions.
This is followed by an explanation of research significance and the introduction of
research methods to be adopted to achieve the research objectives. The scope and
limitations of the research are subsequently defined to ensure the focus of the research.
The chapter concludes by providing a summary of the thesis structure and outline.
12 Chapter 2: Literature Review
Chapter 2: Literature Review
2.1 INTRODUCTION
This chapter presents an overview of previous work on related literature and studies
done by the researchers that provide the fundamental background for the research
questions. The first section presents an overview of urban redevelopment on the global
scale and the linkage between urban redevelopment and sustainability. It then reviews
the current DW waste management practices. This is followed by the status of DW
management in urban redevelopment projects, including the current research trend of
urban redevelopment DW management. In this chapter, the need of urban
redevelopment in Vietnam is described based on both the documents and policy
analysis, followed by the review of C&D waste management in Vietnam so that the
main obstacles of DW management implement are revealed. As a result, a decision-
making framework of improving DW management is developed for Vietnam as the
primary purpose of this study. In the following section, a summary of contextual gaps
is discussed to fill the research aims and objectives. On the basis of these discussions,
the identified factors and conceptual framework for improving urban redevelopment
DW management are proposed, after a thorough review of organisational decision-
making is presented.
2.2 URBAN REDEVELOPMENT
2.2.1 Definitions
Urban redevelopment is an inevitable part of modern urban planning (Thomas &
Hwang, 2003), because it is an imperative step for cities to tackle the issues of social
and economic developments. Urban redevelopment projects began to emerge in the
United States in the second half of the nineteenth century (Gotham, 2001) but a
normative concept originated in the British urban policy (Imrie, Lees, & Raco, 2009).
Many studies have pinpointed two main reasons behind urban redevelopment.
Firstly, increasing population in the city centres coupled with poor living conditions
in aging neighbourhoods have called for urban redevelopment (Bernt, 2009; Couch,
1990; Zielenbach, 2000). There are a number of countries that have experienced
economic and population growth, pressurising the need for urban redevelopment.
Chapter 2: Literature Review 13
Secondly, disinvestment and population loss have led to abandoned and dilapidated
infrastructure; redevelopment is therefore required to tackle these shrinking cities
(Couch, 1990). In the early 20th century, this problem exclusively occurred in Europe,
where about 30% of all cities in this continent experienced population declines (Turok
& Mykhnenko, 2007). For example, Germany has been facing dramatic losses of
inhabitants that dramatically has increased the vacancies in housing stock (Deilmann,
Effenberger, & Banse, 2009) and this has led to an increase 0.5% per year of
demolition rate for redevelopment projects.
No consensus yet exists regarding the definition of urban redevelopment in the
literature. Many countries and regions have discussed this concept in such different
terms as “neighbourhood rehabilitation”, “urban improvement scheme”, “in-situ
redevelopment” and “urban regeneration” (Holcomb, 1981). More recently, Zheng, et
al. (2014) indicated that the terms closely related to the concept of urban
redevelopment are ‘urban regeneration’, ‘urban renewal’ and ‘urban rehabilitation’.
Couch, Sykes, and Börstinghaus (2011) indicate that urban renewal and urban
regeneration are similar in meaning and their works are on a relatively large scale.
While urban renewal is considered to be the activities of slum clearance and physical
redevelopment, urban regeneration involves resolving multi-faceted issues in deprived
urban areas to upgrade the economic, social, physical and environmental conditions
(Ercan, 2011). De Sousa (2008) compares that urban redevelopment is more specific
and is conducted on a smaller scale and this term refers to constructing new buildings
on the same site with the demolished, aging buildings. Urban rehabilitation is
refurbishing to a good function (Zuckerman, 1991). Zheng, et al. (2014) conclude that
urban renewal aims to improve the physical, social, economic and ecological
conditions of urban areas by different plans of redevelopment, rehabilitation and
heritage preservation. Although these activities may vary in form and process, the
mutual aims are to promote land-use value and improve the environmental conditions
(Adams & Hastings, 2001); to address the urban decline and urban decay problems
and meet a number of socioeconomic modern goals (Lee & Chan, 2008a).
Urban redevelopment is a construction process wherein the existing aging buildings
are removed and the cleared sites for the construction of new buildings are reused
(Miller, 1959). This approach to the concept of urban redevelopment is applicable to
buildings in seriously dilapidated condition and ones that have no preservation value,
14 Chapter 2: Literature Review
or the design of buildings have poor living conditions (Miller, 1959). In the urban
redevelopment process, developers can make profits by selling the new centrally-
located apartments, and the local government can maximum the land-use value and
enhance the building’s functions, such as in higher living conditions and more
commercial activities in the inner-city (Broudehoux, 1994).
Fong (1985) defines urban redevelopment as a continuous process of physically
restructuring the old part of the city via planned or unplanned programs in both private
and public sectors. De Sousa (2008) indicates that urban redevelopment is new
construction, rebuilt on a site of aging buildings on a small scale and more specific
than others. For example, in the 1980s, in the large-scale urban renewal projects
conducted by the US government, the term of urban redevelopment was used for many
small-scale projects focusing on the improvement of old neighbourhoods and
transportation infrastructure (Ho, 2012). Yeh (1990) elaborates urban redevelopment
as ‘an important process in changing land use and improving the building stock and
environment of a city’ (Page 361). Ng (1998) specifies that urban redevelopment is
one of the strategies of urban renewal, which involves reshaping the older section of
the city in terms of both physical and social fabric.
Based on the definitions mentioned above and the context of this study, urban
redevelopment is understood as a process that involves demolitions of aging buildings
to upgrade the physical and socio-economic conditions in order to meet the modern
standard and constructions of new buildings on the same site, including resident and
non-resident buildings. It highlights the fact that aging buildings are dilapidated blocks
scattered in a city core with high density of population.
In summary, urban redevelopment is highly desirable for modernising an old city core
in achieving a number of goals, such as slum clearance, provision of accommodation,
reform of population mix, encouragement of economic growth, effective land-use,
rectification of construction shortages and improvement of neighbourhood (Chan &
Lee, 2008b). However, Kazemian (1991) indicates that dismantling the structure of the
old building is the most serious concern of the urban redevelopment process, triggering
problems such as the ruin of cultural heritage, the destruction of the neighbourhood
regarding social and psychological loses, and the impact on other functionary social
systems. Therefore, the issues of social, environmental and economic impacts should
be wisely considered in the urban redevelopment process.
Chapter 2: Literature Review 15
2.2.2 Global trend in urban redevelopment
As the world population grows and urbanisation increases, massive housing and urban
redevelopment activities take place in many cities over the world. The World Bank (as
cited in Dowall, 1994) reported that there are over 30% of urban households living in
poorly equipped accommodation with a low living standard, with less than 4 square
metres per person, and approximately 28% are classified as those living with no
sanitary facilities. There were almost one billion people living in urban slums, which
are overcrowded, polluted, insecure and lack basic necessities such as clean water and
sanitation (Habitat, 2006). According to the United Nations Human Settlement
Program (Habitat, 2006), these urban slums are projected to double by 2030, placing
pressures on cities around the world. These require the redevelopment projects to
provide more living space and improve the living conditions, both of which help
transform urban space into high-rise building or reshape the purpose of land-use
(Dowall, 1994; Ercan, 2011).
In addition, the dilapidation in most cities has been significant to the extent that it has
urged cities to improve their performance to meet the urbanisation criteria (Steinberg,
1996). For example, Steinberg (1996) indicates that the large quantity of aging
buildings in cities of developing countries that were built before the 1970s have been
considered the housing problems that need to be addressed. At the same time, the
desire for urbanisation has led to the change of the cities in socio-economic respects
by the elimination of the aging buildings in the city core. Wu and He (2005) indicate
that urban redevelopment has often been carried out in the most dilapidated areas and
the oldest part of the city, because the high population density and building density
hinder the extensive redevelopment of the whole city. Recently, the governments of
many countries have paid more attention to urban redevelopment, which is reshaped
on a large scale in order to upgrade housing conditions and urban infrastructures.
The earliest urban redevelopment projects were implemented in the United States in
the late 19th century and increased in quantity in the 1950s in developed nations after
World War II (Demberel, 2010). The first urban redevelopment efforts in the United
States instigated the American Park movement and the City Beautiful movement,
which focused on the transformation of city cores by the incorporation of public parks
and monumental buildings (Holcomb, 1981). In the 1930s, the programs of Public
Works and Public Housing was conducted to transform the slums, blighted areas and
16 Chapter 2: Literature Review
low-income housing to modern complex apartments (Nelson, 1988). In the 1960s, the
small-scale urban redevelopment programs were promoted in order to improve urban
conditions (Holcomb, 1981). According to America’s national report in 1992, 86,000
housing units accounting for 6% of public housing were dilapidated and in need of
redevelopment (Leigh & Patterson, 2006). It is estimated that about 1.8 million US
housing units were demolished in the 2000s (Farfel, et al., 2005). From 2000 to 2004,
about 6,000 buildings were razed in the city of Philadelphia and many industrial cities
in the US faced the problems of demolishing thousands of abandoned buildings, such
as Baltimore, Michigan and Detroit (Leigh & Patterson, 2006).
In Europe, Grebler (1964) argues that the modernisation of the old city cores emerged
in the industrial revolution in Europe, which was later than that in the United States.
In the late 1960s, the renewal policies were formulated to implement slum clearance
and action plans placed emphasis on rehabilitation (Couch, 1990). After the Second
World War, the quality of most of the housing stock in Europe did not meet the
requirements of contemporary society (Itard & Klunder, 2007). For example, old
buildings in most urban districts in the Netherlands failed to meet the living standard
in size and divergent usages, leading to massive demolition and reconstruction.
In Eastern Germany, due to shrinking population, the demolition rate increased to
0.5% of the existing stock per year in the early 2000s and this figure is expected to rise
more noticeably in the next 40 years (Deilmann, et al., 2009). According to Deilmann,
et al. (2009), western Germany will paint a similar development scenario in another
25 years. In the program launched by the German Federal Government in 2007, there
are about 30 million pre-1984 units in Germany that will be upgraded by 2020 (Power,
2008).
In the middle of the 20th century, the UK faced the physical problems of replacing the
old sections of cities to improve housing and living conditions from the low level to
the approved higher regional levels (Couch, 1990; Ho, 2012). The UK government
offered the guidelines for urban redevelopment plans in the city cores (Couch, 1990).
This presented the physical problems of the old areas in improving housing and living
standards. From 1930 to 1980, the slum clearance programme was conducted with
massive demolitions in Britain, and in the late 1960s this culminated in about 80,000
demolitions per year (Power, 2008). According to Power (2008), a maximum of two
million London homes are forecast to be demolished by 2050 and about 10% of current
Chapter 2: Literature Review 17
stock is estimated to be razed by then. In Ankara, Turkey, urban redevelopment
projects were the main solutions to address the issues of squatter settlements since the
1980s, which were shelter to 75% of Ankara’s residents (Uzun, 2005).
The strategy of urban renewal was also adopted in Hong Kong, China and Singapore,
with a focus on tackling poor housing conditions and urban decay in the city cores. In
the early 1970s in Hong Kong, a huge programme of urban redevelopment was
implemented in order to remove resettlement buildings by modern city infrastructure
and the urban redevelopment was conducted to replace the dilapidated buildings in the
old districts with new apartments (Yeh, 1990). In the late 1990s, it was estimated that
about 80 hectares of land-use in the inner-city needed redevelopment (Hui, Wong, &
Wan, 2008). According to an assessment by The Planning and Lands Bureau of Hong
Kong in 1999, roughly 2,200 of the total 8,500 buildings aged over 30 years needed to
be redeveloped or intensively repaired and another 3,900 buildings required repair on
varying scales (Poon, et al., 2004).
In Hong Kong, it is also estimated that the number of buildings constructed over 30
years will reach by 50% in the following 10 years. These issues can be found in many
districts where many dilapidated buildings awaited improvement or redevelopment
(Yau & Ling Chan, 2008). In 2001, the Hong Kong Government set up the Urban
Renewal Authority to implement 225 urban redevelopment projects, which cost more
than US$38 billion (Mui & Sankaran, 2004). The number of buildings that were
redeveloped in the early 2010s was recorded at 879, including both residential and
non-residential buildings (Hui, et al., 2008). It is reported that 10,000 buildings aged
over 30 years and 7,500 aged over 40 years were in need of urban redevelopment
efforts in 2006 (Hui, et al., 2008). Hui, et al. (2008) pointed out that the large number
of existing ageing buildings in Hong Kong can be a major issue to urban decay and
will take hundreds of years to be redeveloped.
Furthermore, in China, the scale of urban redevelopment and residential relocations
has been extensive (Li & Song, 2009). There were 8.5 million households relocated in
the 1980s and the pace of urban redevelopment began to accelerate in the 1990s (as
cited in Li & Song, 2009). A study by Fang and Zhang (2003) also indicate that
growing population in the inner city led to a redevelopment program of about 4.2
million square metres in four districts located in Beijing in 1998. In the 10-year period
between 1995 and 2004, over 33 million square metres of housing were redeveloped
18 Chapter 2: Literature Review
in Shanghai, a project which is larger in scale than urban renewal projects in cities of
the USA (He & Wu, 2007).
In the Ninth Five Year Plan from 1996 to 2000, it is reported that about 330 million
square metres of housing were demolished throughout the whole of China (Li & Song,
2009). This urban redevelopment program in China covered most of the traditional old
houses aged up to 100 years old or lane housing with simple structures (Fang & Zhang,
2003; Li & Song, 2009). However, studies on urban redevelopment in China are more
focused on the preservation of historical buildings, the relocation of populations and
the resolution of political-economic problems (Li & Song, 2009). In line with that, the
environmental issues associated with urban redevelopment programs have also been
recognised in Beijing (Fang & Zhang, 2003).
The Land Title Act was introduced in Singapore in the year 1999, with the aim to
encourage private sector engagement in urban renewal (Hui, et al., 2008). This decree
has made vital contributions to the redevelopment of aged buildings and the provision
of new housing apartments. There were over half a million square metres redeveloped,
which covered about 7,400 residential apartments. In 2000, the Singapore’s Urban
Redevelopment Authority was established to enhance redevelopment activities and
motivate housing development (Hui, et al., 2008). By doing this, Singapore has
improved the conditions of living and physical environment, and has conserved
landscapes and built modern infrastructure.
Similarly, Seoul experienced significant population growth, which reached
approximately 9.64 million after the Second World War in 1985, requiring a huge
demand for housing and urban development (Ho, 2012). The urban redevelopment was
adopted in the early 1960s, aiming to provide commercial and office uses, particularly
in Seoul (Ha, 2001). The very first urban redevelopment activity was to deal with the
problems of the clearance of squatters and improve housing conditions (Sohn, 2003).
According to Ha (2001), a Joint Redevelopment project was introduced to Korea in
1983, which heightened housing standards by building high-rise flats, with height
varying from 15 to25 stories. In 1984, the Seoul government established the guidelines
for Joint Redevelopment to facilitate the urban redevelopment process led by
stakeholders of the corporation (Ho, 2012).
However, Ho (2012) states that this program lacked comprehensive planning and the
focus was on a small scale, rather than on a district level. Moreover, apart from the
Chapter 2: Literature Review 19
first Seoul Comprehensive Plan introduced in 1990, the Seoul government has
improved the urban redevelopment program to upgrade living conditions in the old
districts and improve the residential environment (Ho, 2012). According to the
Ministry of Land, Transport and Marine Affairs, South Korea, the project of urban
redevelopment has led to a replacement of 67,000 housing units that had been located
in over 200 districts (Ho, 2012). Of those urban redevelopments in Seoul, most of the
houses had been in very poor condition in terms of structure, materials and facilities
(Ha, 2001).
Australia witnessed intensive urban redevelopment after the Second World War
(Arthurson, 1998). Arthurson (1998) states that the majority of public housing was
aging and had poor design. In addition, the demographic change and the economic
development have put pressures on urban redevelopment. As a result, many urban
redevelopment projects have been operating on a large scale in Sydney, Melbourne,
and other cities, since the 1990s.
The pace of urban redevelopment in other developing countries, such as Brazil, India,
Vietnam and Thailand, is still slower than in developed countries. In the 1970s and
1980s, the major goals of urban redevelopment in developing countries are addressing
the issues of urban slum and squatter eradication (Broudehoux, 1994). There are
numerous problems of aging buildings in the city cores such as misusing land, lacking
community facilities, poor living conditions and high residential density (Ng, 1998).
Thus, these problems can be addressed through urban redevelopment programs,
focusing on upgrading the old buildings in the city cores to modern buildings.
The rate of urban redevelopment in many countries is a natural development in
urbanisation and economic growth. Consequently, urban redevelopment plans need to
be embedded in a long-term scenario of urban development in the modern city. The
redevelopment activities must be undertaken with the combination of economic,
environmental and social targets aiming to achieve sustainability. Fang and Zhang
(2003) indicate that urban redevelopment is a profound value-laden process involving
societal engagement. Therefore, the issues related to the environment, economy and
society should be considered by all concerned in the public domain, with respect to
sustainable development.
For several decades up to now, the environmental consideration in urban
redevelopment and urban renewal has been waste implication. Although large-scale
20 Chapter 2: Literature Review
urban redevelopments may drive profit, they have also profound impact on the
neighbourhoods and the historic environment (Wu & He, 2005). The consensus
between researchers is that urban redevelopment practices have been conducted with
too much attention on economic objectives and have neglected the environmental and
social issues, which evidently violates the global trend of sustainable urban
development (Chan & Lee, 2008b; Wu & He, 2005). Thus, there is a need for emphasis
on DW in urban redevelopment activities, which poses environmental pressure on
sustainable urban development. The next section will provide the discussion on the
link between urban redevelopment and sustainability.
2.3 THE LINK BETWEEN URBAN REDEVELOPMENT AND SUSTAINABILITY
In a well-known statement of the Brundtland Report (WCED, 1987, p. 16), sustainable
development is defined as ‘development that meets the needs of the present without
compromising the ability of the future generation to meet their own needs’ (Page 16).
This perception can be understood as improving the quality of life to provide people
with a healthy environment and enhance the social, economic and environmental
conditions for present and future generations (Ortiz, Castells, & Sonnemann, 2009).
There is a growing body of literature that has strongly attempted to conceptualise
sustainable construction in different contexts. The construction industry is considered
as a major contributor to the environmental issues due to the extraction of raw
materials and generation of waste in its manufacturing process. Zimmermann, Althaus,
and Haas (2005) give evidence that the construction sector is a source that consumes
a large amount of energy, generates waste, increases global greenhouse gas emission,
creates different types of pollution, and triggers environmental problems and natural
resource depletion.
As the challenge of sustainability was associated to the construction industry in the
early 1990s, the new disciplines of ‘sustainable construction’ of ‘green construction’
were discussed at The First International Conference on Sustainable Construction in
Florida, the United States of America in 1994 (as cited in Hill & Bowen, 1997). The
term of ‘sustainable construction’ refers to ‘cradle to grave’ assessment, which
comprises managing the serviceability of a building and recycling of building
Chapter 2: Literature Review 21
materials to reduce demolition waste (Wyatt & Gilleard, 1994). Manowong (2012)
argues that environmental sustainability is essential to construction management,
which includes construction waste management and pollution control. While social
sustainability provides a better living condition, the issues of construction waste are
addressed. In addition, in terms of economics, sustainability can be only achieved
when the living conditions are improved and the environment is enhanced.
Accordingly, urban redevelopment has a substantial impact on all three aspects of
sustainability: the society, the economy and the environment, which requires a
significant consideration of achieving a more sustainable society (Lombardi, Porter,
Barber, & Rogers, 2011). Urban redevelopment is consistent with the goals of
sustainability, because it helps encourage compact development, reuse existing
infrastructure, and support local businesses and employment (Leigh & Patterson,
2006).
The concept of sustainable development was first integrated in the UK urban
redevelopment plans in the 1990s (Ho, 2012). In sustainable development: the UK
strategy in 1994, the government realised the significant contribution of urban
regeneration to sustainability that uses developed areas in the effective way, while
creating them more attractive places of living and working (Couch & Dennemann,
2000).
According to Couch and Dennemann (2000), urban regeneration contributes to
sustainability by recycling dilapidated areas, reducing the demand for peripheral
development and facilitating the development of modern cities; however, it still needs
to fully tackle the requirement for other aspects of sustainability, such as community
participation, pollution issues, employment for inhabitants, and waste and resources.
In 2001, the Hong Kong government had considered the concept of sustainable
development in planning and executing urban renewal programs, however such a
concept still needs to be improved in terms of balancing the social aspects (Chan &
Lee, 2008a).
Recently, academic scholars have endeavoured to pay more attention to sustainable
urban redevelopment to balance economic, social and environmental issues (Leigh &
Patterson, 2006; Munoth, et al., 2013; Yau & Ling Chan, 2008; Zheng, et al., 2014).
22 Chapter 2: Literature Review
According to the studies by Yau and Ling Chan (2008) and Munoth et al. (2013), the
indicators of urban sustainable redevelopment have been recognised based on three
dimensions of sustainability, as shown in Figure 2-1. Thus, urban redevelopment
mainly aims at solving the urban decay, and it also needs to meet socioeconomic
targets and resolve environmental problems (Zheng, et al., 2014).
Figure 2-1: Triple bottom line of sustainable urban redevelopment
Social sustainability is to improve the living conditions, to conserve the urban heritage,
to enhance the urban facilities and to relocate successfully the housing residents.
Economic sustainability is to implement cost-effective urban redevelopment projects,
to promote job creation, to design efficient infrastructure systems and to increase land-
use values. Environmental sustainability is to efficiently consume the energy in
conducting urban redevelopment projects, to comprehensively manage C&D waste, to
significantly reduce the noise and air pollution and to create more public space.
With respect to the three pillars of sustainability, urban redevelopment can vitally
contribute to sustainable urban development. However, most urban redevelopment
policies have placed much emphasis on economic targets rather than social and
environmental aspects (Couch & Dennemann, 2000; Zheng, et al., 2014), and the
concept of sustainable urban redevelopment is poorly conceptualised. Therefore,
Environment target- Energy efficiency supply
- C&D waste management
- Noise and air pollution management
- Creation public spaces
Social target- Better living conditions
- Conservation of urban heritages
- Better urban facilities
- Sactifaction for relocation
Economic target- Cost effective UR project
- Job creation
- Efficient infrastructure system
- Promote land-use values
Sustainable urban
redevelopment
Chapter 2: Literature Review 23
sustainability needs to be integrated in urban redevelopment policy with greater
accentuation given to environmental considerations, particularly DW management.
2.4 DEMOLITION WASTE MANAGEMENT
2.4.1 The lifecycle of the built environment
The concept of closed-loop in the field of construction industry is rooted in nature’s
ecology (van Dijk, Tenpierik, & van den Dobbelsteen, 2014). As buildings are
constructed by the complexity of natural materials that have their own life spans, such
as wood, steel, concrete, plastics and ceramic, building development is deemed as a
cyclical process that consumes a large amount of energy and materials. Whether the
life span of buildings lasts for long or not depends on different factors, such as the
components’ quality, the purpose of use, the climate and the circumstance of socio-
economy.
Construction lifecycle is described in the study of Kibert (1994) as a process of
planning, development, design, use, maintenance and deconstruction. According to the
framework of C&D waste management, there are six different stages in a project
lifecycle, from the concept to design, construction and operation, to maintenance and
demolition, as shown in Figure 2-2 (Lu & Yuan, 2011). As is illustrated, there is a link
between the demolition stage and the redevelopment stage, and the building’s life
cycle is completed at the demolition stage. It is perceived that at the end of the building
life span, demolition produces a larger amount of waste than other stages (Shen, Li
Hao, Tam, & Yao, 2007).
In the field of construction, researchers and practitioners are trying to find the
alternatives to extend the life of buildings in order to avoid demolition and
environmental impacts, such as maintenance or deconstruction of the old buildings
(Kibert & Chini, 2000; Leigh & Patterson, 2006; Wyatt & Gilleard, 1994). Leigh and
Petterson (2006) argue that deconstruction is a more sustainable approach instead of
the demolition of dilapidated structures and construction of new buildings. This
approach can reduce the amount of waste produced during the demolition process and
through the reuse of the existing buildings.
24 Chapter 2: Literature Review
Figure 2-2: A C&D waste management framework.
Adapted from ‘A framework for understanding waste management studies in
construction’ by (Lu & Yuan, 2011), page 1255.
However, most of the buildings aged over 30 years old have not been designed with
sustainability in mind (Poon, et al., 2004). In addition, overcrowded, dilapidated and
aging buildings in the city cores have become targets for demolition in pursuing
modernity (Liu, Pun, & Langston, 2005a). For instance, the history cityscape of
American cities changed from the late nineteenth century with the urban
redevelopment programmes for slums and blight clearance, and housing development
(Gotham, 2001). In the 1970s and 1980s, Singapore launched urban redevelopment
and renewal projects that encompassed the demolition of blighted and dilapidated
areas to make way for modern high-rise buildings (Lee, 1996). These issues have
occurred in many cities all over the world and have involved not only socio-economic
but also environmental problems.
Shen, et al. (2007) state that the demolition of a structure is considered as the
completion stage of the project lifecycle, which normally generates different wastes
such as wood, concrete, metal, bricks, plastic, gypsum, roofing shingles and glass. It
is suggested that the volume of waste in demolition work is far greater than that from
a new construction project. In addition, research by Itard and Klunder (2007) indicates
that compared with other options, such as maintenance, consolidation and
transformation, demolition and rebuilding (redevelopment option) lead to more
impacts on the environment due to more energy consumption, raw material extraction,
Chapter 2: Literature Review 25
and waste generation. The assessment of environmental effects of a building’s
lifecycle is presented in Figure 2-3 (Itard & Klunder, 2007).
Figure 2-3: Environmental effects as a function of time.
Adapted from ‘Comparing environmental impacts of renovated housing stock with
new construction’ by (Itard & Klunder, 2007), page 255.
According to Liu, Pun, and Langston (2005b), the previous efforts in addressing the
impact caused by DW were mainly focused on the disposal of DW, not the demolition
process itself and full consideration should be given to the last lifecycle stage of
demolition. Thus, an effective approach to DW management is urgently needed to
minimise the environmental effects, by recovering as many of the dismantled materials
as possible.
2.4.2 Integrated approach to waste management in construction industry
The term of ‘integrated’ was first coined in the field of waste management during the
1970s and became standardised by the mid-2000s (Wilson, Velis, & Rodic, 2013).
Wilson et al. (2013) also indicate that integrated waste management are mainly
technical, focusing on how to combine different technical elements into a system, and
the computer-aided tools are used to support with that integration. From the
perspective of sustainability, the research undertaken by Diaz, Savage, and Golueke
(1996) shows that the three objectives of triple bottom lines indicating sustainability
are economic, environmental and social aspects that need to be emphasised in an
approach of integrated solid waste management.
In addition, the government and local authority also need to be taken into account in
those dimensions, such as political, economic, socio and environmental aspects. In the
26 Chapter 2: Literature Review
literature and practice, integrated waste management is understood as an approach to
achieve the goals of sustainability. This is integrated in all fields, and C&D waste
management is no exception. The conceptual model of construction waste
management in achieving sustainability is suggested by Manowong (2012), as
demonstrated in Figure 2-4.
Thus, the integrated DW management could only be achieved when a comprehensive
strategy and solution are proposed based on the interactions between the above three
pillars. The complexity of the system to recognise integrated DW management is
illustrated in Figure 2-5.
Environment
Economic
InstitutionalTechnical
Society
Integrated DW management
Environmental Sustainability
Social Sustainability
Economic Sustainability
Construction waste management
Green and sustainable
i
Figure 2-4: Conceptual model for sustainable construction waste management (Manowong, 2012)
Chapter 2: Literature Review 27
Figure 2-5: System for integrated demolition waste management
Generally, the ‘3R principles’ has been a key concept in C&D waste management,
including DW management, which refers to reduction, reuse, and recycling (Yuan &
Shen, 2011). This guideline has helped researchers and practitioners develop effective
strategies through waste reduction, reuse, and recycling instead of dumping the C&D
waste. Peng, et al. (1997) also suggest a hierarchical classification of waste
management strategies and their environmental impacts from low to high (Figure 2-
6).
‘Reduce’ means measures used, before a building structure or component becomes
waste, that reduce: (a) the quantity of waste, (b) the adverse influences of the waste
generation on the environment and human health, or (c) the content of hazardous
substances. Reduction is the most desirable strategy for controlling C&D waste in
terms of saving natural resources and remedying environmental pollution (Yuan &
Shen, 2011).
‘Reuse’ means any building structures, or components that are not waste, reusing for
the same purpose or other purposes. Reuse also denotes less energy consumption and
the process is not complicated compared to other principles (Peng, et al., 1997). The
C&D waste is usually reused as aggregate in road construction (Hendriks & Janssen,
2001). For example, in the Netherlands, a large portion of C&D waste is reused as raw
materials in road construction, accounting for more than 95% of the total (Mulder, de
Jong, & Feenstra, 2007).
Reduce
Reuse
Recycle
Compost
Incinerate
Landfill
Env
iron
men
tal i
mpa
cts
Low
High
28 Chapter 2: Literature Review
‘Recycle’ means any recovery of waste, whether for the original or other purposes.
Recycle has been widely used as an alternative approach when the waste is hardly ever
reduced and reused. This creates recycled production that can be used in other
constructions (Yuan & Shen, 2011), which reduces the amount of landfilling waste as
well as the effects on natural resources (del Río Merino, et al., 2009). South Korea, as
a salient example of recycling, recorded the recycling rate at 98.1% (Somasundaram
et al., 2015).
2.4.3 Current status of demolition waste
The term of construction and demolition (C&D) waste has been used to refer to the
solid waste resulting from construction, renovation and demolition activities of
structures (Lu et al., 2011). These structures include buildings of all types in residential
and non-residential households as well as roads and bridges. Depending on its
generation phases, C&D waste can be classified into three major categories:
construction waste, renovation waste and demolition waste (Wu & Ann, 2014).
A typical component of C&D waste contains a mixture of inert and non-inert materials.
Inert substances mainly include sand, bricks, and concrete, making up 40% to 85% of
the total (Eurostat, Environment and Energy, 2009). C&D waste, representing one of
the major waste streams, varies significantly from country to country according to the
differences in the economy, culture, perspectives of C&D waste and the way of data
collection (Kourmpanis, Papadopoulos, Moustakas, Stylianou, et al., 2008). It has been
reported that the proportion of C&D waste amounts to 25 to 30% of the total municipal
solid waste in the EU, as opposed to 40% in China, 29% in the USA, 44% in Australia,
and 36% in Japan (Hendriks & Pietersen, 2000; Wang & Yuan, 2008).
In recent decades, the construction industry has been globally considered as the major
producer of solid waste (Marzouk & Azab, 2014; Poon, et al., 2004) and DW is
commonly managed together under the term ‘C&D waste’. However, the
characteristics of waste, resulting from demolition processes, are quite different. The
Figure 2-6: Hierarchy of construction and demolition waste
Chapter 2: Literature Review 29
DW signifies the materials from demolition and clear sites and which structures are to
be dismantled before the erection of new ones (Fatta et al., 2003). DW is composed
of ‘metals (steel, aluminium, copper and zinc), inert wastes (titles, concrete, bricks,
ceramic materials, stones, clinker), wood, plaster, plastic (PVC), flat glass, glass wool,
and hazardous waste (bituminous roof and fluorestives lamps containing mercury)’
(Roussat, et al., 2009b). The DW composition varies according to the type, age, shape,
use, and size of the structure, while the historical, cultural and economic values of the
buildings are very important factors that influence the DW components (Fatta, et al.,
2003). In addition, demolition work generates typically more waste than the
construction one, which requires more attention on effective DW management (Chen
& Lu, 2017; Yuan & Shen, 2011).
Furthermore, the DW characteristics depend on the demolition technologies and
methodologies. For example, the demolition work with heavy equipment generates a
commingled pile of waste that makes classification of reusable waste difficult. (Poon,
et al., 2001). The research of Poon, et al. (2001) also indicates that the recovery rate of
reusable waste is enhanced by using mechanical hand tools, such as ‘piece-by-piece’
wrecking. Therefore, the success of DW management is highly dependent on the
selection of demolition methods.
In general, DW is mostly inert materials (Poon, et al., 2004), though it is likely that the
DW poses less threat to the environment than other types of municipal solid waste
(Wang, Touran, Christoforou, & Fadlalla, 2004). However, from the environmental
perspective, growing evidence has suggested the effects of DW in terms of damaging
natural resources and cityscape by expansion of the landfill spaces, leaching
contaminated substances into soil and water, and increasing air and noise pollution
levels (Yuan, 2011). In addition, construction waste treatments consume large amounts
of energy in transportation and manufacturing (Marzouk & Azab, 2014). For the
reasons above, DW can cause more issues than construction waste, such as
environmental pollution, low rate of recovery, difficulties in waste sorting, and higher
energy consumption for DW treatment. Thus, it is required that a specific study of DW
management should be conducted.
Globally, an average of 28% of municipal solid waste is C&D waste, meanwhile, 10%
that of is reused, and over 60% is recycled and the remaining 30% is disposed of in
landfill (Reddrop et al., 1999; Graham et al., 2003). In Germany, the annual volume
30 Chapter 2: Literature Review
of waste is calculated for DW and construction waste, accounting for 22.6 million
tonnes and 10 million tonnes respectively (Brooks, Adams, & Demsetz, 1994). The
construction industry in Hong Kong accounts for 44% of all municipal solid waste
disposed daily in the landfill (Poon, et al., 2004). Leigh & Patterson (2006) also note
that C&D waste accounts for 25-40% of the US waste stream, 92% of which is from
demolition and renovation activities.
According to Eurostat, Environment and Energy (2009), the European Union generates
an annual average of over 500 million tonnes of C&D waste , accounting for 25 to
30% of all waste streams (Mália, de Brito, Pinheiro, & Bravo, 2013). In Western
Europe, about 175-250 million tons of DW are generated each year, with France
generating explicitly 17 million tons (Roussat, Méhu, Abdelghafour, & Brula, 2008).
The study by Kleemann, Lederer, Aschenbrenner, Rechberger, and Fellner (2014)
indicates that in Austria, there were about 6.5 million tonnes of DW management
generated in comparison to only 3.9 million tonnes of municipal solid waste.
In Australia, C&D waste contributes up to 30-40% of solid waste that goes to landfills
(Liu, et al., 2005b). According to the report by Hyder Consulting (2011) in 2008-09,
C&D waste accounted for about 19.7 million, which corresponded to approximately
42% of the national waste. Further, 49.9% of the solid waste stream in South Korea
was derived from C&D waste (Somasundaram, et al., 2015), while in China, Zhao,
Leeftink et al. (2010) reported that C&D waste constituted more than 30% of
municipal solid waste and Lu (2014) figured out that DW is the largest proportion,
constituting 62.3% of the total C&D waste produced in the year 2011.
In the past, landfilling was the main approach for construction waste management,
including illegal disposal, and this put pressure on landfill sites that could be exhausted
in the short term (Tam, 2008). Río Merino, Azevedo et al. (2009) indicate that in Spain,
the rate of growth in C&D waste was 8.7% yearly in the 2000s and 90% of this waste
went directly to landfill. Facing the large proportion of waste generated from the
construction industry, many countries such as Hong Kong, Australia, China and EU
countries, promoted legislation aiming to minimise the amount of C&D waste in the
landfill (Mália, et al., 2013; Mcdonald & Smithers, 1998; Poon, et al., 2004; Wong &
Yip, 2004; Yuan, et al., 2011).
Reduction is the most desirable strategy for controlling C&D waste in terms of saving
natural resources and remedying environmental pollution (Yuan & Shen, 2011). While
Chapter 2: Literature Review 31
Denmark, the Netherlands, Germany, and The United States have succeeded in the
reduction strategies in C&D waste management, countries such as Hong Kong, China,
India, Greece and Thailand are facing challenges in waste reduction (BIO Intelligence
Service, 2011). As the later countries continue to redevelop, more and more C&D
waste that puts high pressure on the landfill will be generated. Therefore, the need of
creating waste management plans could minimise the amount of waste in construction
projects.
Reuse consumes less energy and its process is not complicated compared to other
principles (Peng, et al., 1997). The C&D waste is usually reused as aggregate in road
construction (Hendriks & Janssen, 2001). For example, in the Netherlands, a large
portion of C&D waste is reused as raw materials in road construction, accounting for
more than 95% of the total (Mulder, et al., 2007).
Recycling has been widely used as an alternative approach when waste is rarely
reduced and reused (Yuan & Shen, 2011). This creates recycled production that can
be used in other constructions (Yuan & Shen, 2011), reducing the amount of landfilling
waste as well as the effects on natural resources (del Río Merino, et al., 2009). Many
studies have indicated that only 25-30% of C&D waste is currently recycled and about
75% of C&D waste dumping in the landfills can be diverted (Biddle, 2001). South
Korea serves as a successful example of recycling with the rate observed at about
98.1% (Somasundaram, et al., 2015).
According to The European Union’s Waste Framework Directive, the requirement for
the average of C&D waste to be recycled and reused in European countries is 70% by
2020 (BIO Intelligence Service, 2011). It is evident that Denmark, Germany, and the
Netherlands have successfully achieved the targets with the level of recovery of C&D
waste accounting for over 80% (Nisbet, Venta, & Foo, 2012), while Spain and Greece
have a recovery rate of below 20% (Brodersen, Juul, Jacobsen, & Tsotsos, 2002).
Some developing economies have contributed noticeably in C&D waste treatment; for
example, Malaysia and China have promoted research efforts in C&D waste
management (Yuan & Shen, 2011), while other developing countries are making
relatively slow progress in recovering, such as India and Vietnam.
Facing the large proportion of waste generated by the construction industry, many
countries such as Hong Kong, Australia, China, Japan and EU countries have
introduced legislation directed at promoting the use of recycled materials and
32 Chapter 2: Literature Review
minimising the amount of C&D landfill waste (Mália, et al., 2013; Mcdonald &
Smithers, 1998; Poon, et al., 2004; Wong & Yip, 2004; Yuan, et al., 2011). The rate
of waste recovery has been improving over the last two decades by means of national
efforts to reduce its impacts on natural resources and the environment. For example,
Denmark, Belgium, and Netherlands have a high level of C&D waste recovery, each
accounting for over 80% of all C&D waste (Brodersen, et al., 2002). Similarly, South
Korea has been successful in recycling C&D waste, with a recovery rate of around
98.1% (Somasundaram, et al., 2015). Despite increased research into C&D waste
management strategies in developing countries (Yuan & Shen, 2011), other nations
such as India and Vietnam are making relatively slow progress (Huy, 2015).
Along with the popularity of urban redevelopment, DW volumes are predicted to
continue increasing that poses challenges for many urban areas which are facing
capacity landfill and potentially severe environmental impacts (Poon, et al., 2004). In
addition, Chen and Lu (2017) argue that demolition work in both developed and
developing countries is considered as an uneconomical activity if the waste is not
properly handled In response to these concerns, more effective DW management is
critically important for ensuring sustainability outcomes.
2.5 DEMOLITION WASTE MANAGEMENT IN URBAN REDEVELOPMENT PROJECTS
2.5.1 Overview of demolition waste in urban redevelopment projects
According to Liu et al. (2005b), ‘building demolition represents the process in which
an erected structure is purposely destroyed to form a diversity of components and
fragments of mixed materials’. Roussat, et al. (2008) indicate that DW occupies a
major proportion of industrial waste of most countries and the majority of this waste,
including concrete, brick, sand, and gravel, is inert. In addition, Yuan & Shen (2011)
point out that demolition produces typically 10-20 times more waste than the
construction process because the nature of each process is different.
Many studies contend that DW is recyclable materials (Fatta, et al., 2003; Huang, Lin,
Chang, & Lin, 2002; Kourmpanis, Papadopoulos, Moustakas, Kourmoussis, et al.,
2008; Poon, et al., 2001; Wong & Yip, 2004). It is also worth noting that some
developed countries, such as Austria, Germany, and The Netherlands, hold a high
recycling rate of C&D waste in targets of reducing waste to landfill, whilst developing
Chapter 2: Literature Review 33
countries that have different socio-economic circumstances might have difficulties in
management of waste from redevelopment projects.
The reason is that dismantled materials from old structures aged over 30 years are less
modern (Poon, 1997). For example, asbestos used to be commonly used as insulation
material, but now is considered as hazardous waste. Materials such as metal, which is
rarely generated in the construction process, make up a significant proportion of the
total dismantled waste from old structures. Masonry, wood, concrete and brick
typically produced more than half of DW management (Poon, 1997). Finally, Poon
(1997) states that DW often contains hazardous waste resulting from paints, fasteners,
adhesives, insulation and bituminous roof and fluorestive lamps. This hazardous
waste, for example, in France, represents a tiny minority at merely 2% of DW, but it
can give rise to environmental risks when it is not properly managed (Roussat, et al.,
2008). These contaminants can be a hindrance to waste recovery because separation
of this waste at source is not easy compared to construction waste, which is normally
new and segregated (Liu, et al., 2005b; Roussat, et al., 2008).
In urban redevelopment projects, demolition of old buildings can generate a massive
waste, in which all materials are mixed together (Poon, et al., 2001). These create a
waste stream that is more expensive and more time-consuming in waste recovery than
construction waste because of the complexity of its components (Lu, Lau, & Poon,
2009). In addition, it may imply that demolition generates more waste that goes to
landfills than construction, although accurate data of DW from landfills or projects are
unavailable (Liu, et al., 2005b).
Therefore, waste streams resulting from the demolition processes of urban
redevelopment projects should be processed separately for the following reasons.
Firstly, the volume and characteristics of DW in dismantling older structures in urban
redevelopment projects is quite different from construction waste. Secondly, DW
potentially contains hazardous materials, such as paint, bitumen and fluorescent lamps
containing mercury (Roussat, Dujet, & Mehu, 2009a), which can be more difficult to
reclaim, reuse or recycle. In addition, urban redevelopment projects consist of many
stages involving different activities, of which the demolition process seems to be
separate and waste management is the responsibility of different stakeholders. Thus,
an integrated approach that can possibly encompass all activities in the process is
desired to meet the waste management target (Yuan, 2011).
34 Chapter 2: Literature Review
The fact that DW information is not well documented in projects or regional level can
be one of the main contributing factors in the DW management decision-making.
Therefore, implementing a comprehensive waste management strategy requires
effectively sharing the knowledge and information of DW between stakeholders, such
as the waste volume and compositions.
2.5.2 Current research trend in urban redevelopment demolition waste management
As mentioned above, DW is a critical environmental issue in the construction industry.
Both developed and developing countries are facing challenges in the form of urban
redevelopments that generate large amounts of DW (Ding & Xiao, 2014). In response,
researchers are attaching more significance to a variety of aspects of urban
redevelopment waste management. The demolition of existing buildings is a
predominant feature of urban redevelopment and therefore its waste management is
particularly important. Research to date, however, has been piece-meal with no
systematic review of the literature. The effort to identify possible solutions towards
DW begins with the review of urban redevelopment DW management in general.
Five major categories of the literature demonstrated the concerns of urban
redevelopment DW management in both the practice and academic discipline: strategy
and solution, decision support, environmental challenges, stakeholder engagement,
and evaluation. The themes generated under each category are shown in Table 2-1.
The contribution of the literature is discussed in the following sections.
Table 2-1: Key reviewed themes
Category Themes
(1) Decision support
Estimation of C&D waste generation; categorisation of building materials; statistical and geographical analysis of demolished buildings; multi-criteria decision analysis for choosing a sustainable DW management strategy.
(2) Environmental challenges
Leaching behaviour of hazardous demolition waste; air pollution; environmental impacts
(3) Stakeholder engagement
Participants’ attitude to on-site waste sorting; residents’ concerns about environmental issues related to urban redevelopment.
Chapter 2: Literature Review 35
(4) Strategy and solutions
Reduction, reuse and recycling DW; on-site sorting of C&D waste; improving C&D waste management; a C&D waste management tool; legislation for DW management; sustainable redevelopment.
(5) Performance evaluation
Cost efficiency of DW management; assessment of the impact of C&D waste disposal.
2.5.2.1 Strategy and solutions
Researchers since 1997 have been occupied with the strategy and solutions for DW
management, covering different sub-topics, namely sustainable redevelopment, and
strategy and solution.
Sustainable redevelopment is the most prevalent topic in the field of urban
redevelopment DW management. Many studies have realised the importance of C&D
waste management to sustainable urban redevelopment, which is perceived as a
sustainable decision-making factor (Couch & Dennemann, 2000; Leigh & Patterson,
2006; Munoth, et al., 2013; Qualharini & Flemming, 2009; Yau & Ling Chan, 2008).
According to (Andersen, 2003), a sustainable redevelopment scheme should
endeavour to reduce social exclusion and increase economic value of urban areas. In
addition, urban redevelopment should contribute to the conservation of architectural
merits and heritage (Jim, 1994) and the protection of natural resources by taking into
account the environmental issues such as waste and pollution management (Yau &
Ling Chan, 2008). Sustainable redevelopment can provide a paradigm shift in
encouraging reuse and recycling of DW, which leads to reducing the use of natural
resources (Qualharini & Flemming, 2009).
The environmental issue associated with C&D waste derives not only from the
increased quantity, but also from the treatment process (Marrero, Solis-Guzman,
Molero-Alonso, Osuna-Rodriguez, & Ramirez-de-Arellano, 2011). In the particular
case of the demolition project, DW management requires an effective strategy to
minimise the volume, and to reuse and recycle materials in order to alleviate the
impacts on the environment and natural resources.
Of all the countries facing urban redevelopment issues, China, Spain, and the United
Kingdom have studied legislation aiming at improving DW management in the context
of sustainability (Marrero, et al., 2011; Petersen, 2004; Rao & Zhang, 2015). The
36 Chapter 2: Literature Review
study by Rao and Zhang (2015) analysed the construction waste issues in an urban
renewal program and proposes the strategy and policies to improve waste
management. In order to encourage the use of recycling materials, Rao and Zhang
(2015) suggest that the recycling market should be developed. In addition, construction
waste treatment should be regulated, such as initiating charging schemes, establishing
a certification system for recycling materials and introducing government green
purchasing catalogues.
In Spain, a legislation of C&D waste management was established in 2008, covering
waste hierarchy from prevention, reuse, recycling, energy recovery and proper waste
disposal (del Río Merino, et al., 2009). However, the issues arising in demolition
projects, such as a low technical demolition process and no special measures for waste
classification in a demolition project, limit the frame implementation. In order to fulfil
the legal frame, del Río Merino, et al. (2009) suggest a DW management plan, which
includes waste estimation, hazardous waste identification, waste classification,
disposal plan, and so forth.
In the UK, despite the optimal practice guideline for sustainable development in the
construction industry, there is still the need for integration of sustainability into urban
renewal, which seeks environmental benefits, financial cost and community
involvement (Petersen, 2004). By this approach, sustainable DW management is a key
component of sustainable urban renewal projects. Accordingly, Petersen (2004)
proposes a tool of strategic C&D waste management to improve the sustainable
development performance of the renewal project, which is based on three main
parameters, namely social, economic, and environmental dimensions. The tool assists
the local authorities, planners, developers, and contractors in achieving cost benefits
by increasing community engagement and cushioning environmental impacts in urban
renewal projects.
Due to the speed of urban redevelopment and the depletion of landfill space in Hong
Kong, Poon, et al. (2004) suggest the strategy of minimising DW generation and
increasing waste recovery rate by implementing on-site waste sorting and selective
demolition. Although these solutions have been applied successfully in the
construction industry, especially in developed countries, there is a need for further
research specifically devoted to the urban redevelopment DW management. This is
Chapter 2: Literature Review 37
because of the dissimilarities in the quality and quantity of waste from the demolition
of aging buildings.
2.5.2.2 Decision support
The second commonly occurring topic is decision support. This research direction has
provided methods for selecting sustainable DW management strategies, applying
computer-based solutions in estimating the amount of DW generation, identifying
demolition materials, and managing DW.
With respect to sustainability, the DW management can be a difficult task, because
many aspects regarding economic, environmental and social issues, which are often in
conflict, must be considered (Roussat, et al., 2009b). In order to clarify the decision,
Roussat, et al. (2009b) employ an application of the ELECTRE III decision-aid method
to choose a sustainable DW management strategy. This method takes into account the
sustainable development, which is relative to economic, environmental and social
issues. Nine options for DW management were analysed based on eight criteria,
namely energy consumption, depletion of abiotic resources, global warming,
dispersion of hazardous substances in the environment, economic activities,
employment, and the quality of residents’ life. Roussat, et al. (2009b) conclude that
the local authorities can develop the demolition building guidelines based on the
choice of DW management strategies.
According to Lu (2014), C&D waste estimation has been significantly highlighted by
policy makers, academics, practitioners, and pertinent parties. For example, the U.S.
Environmental Protection Agency (USEPA, 2009) asserted that one of the main
purposes of the estimation of the amount of C&D waste generated is targeting to
reduce, reuse and recycle waste as part of the waste recovery challenge by managing
waste more efficiently. In essence, scrutinising theory and knowledge about C&D
waste generation is a prerequisite to establishing a proper solution for waste
management (Li, Ding, Mi, & Wang, 2013), which is the most useful approach to
understand waste management in the construction industry (Lu, et al., 2011). However,
the data of C&D waste generation have been collected and only the aggregate figure
was released in certain regions. For example, in 2014, the total construction waste
generated in 27 European countries was 61.8 million tons (EUROSTAT, 2017). The
generation of C&D waste in Vietnam was 28 million tons in 2008 (MONRE, 2011).
Thus, there is the need of waste estimation generated in the demolition works.
38 Chapter 2: Literature Review
Recently, estimating DW generation on urban redevelopment projects has attracted
increasing attention from academics. Poon (1997) states that it is significant to estimate
the average of DW generation daily. Poon proposed a method for quantifying DW
generation from demolition work in Hong Kong based on the existing total floor areas,
measured site areas and the number of stories of the different aging buildings.
Seo and Hwang (1999) estimate C&D waste in Seoul, Korea, using a four-step method.
The first involves calculating the life span of buildings. In the second step, the floor
area of building including construction and demolition is estimated. Subsequently, the
individual intensity units of C&D waste are calculated and in the final step, the future
C&D generation is projected. Of the total amount of C&D waste, Seo and Hwang
(1999) reported that 98% was produced by demolition work, and concrete and brick
are the main components. Ding and Xiao (2014) conducted a study into C&D waste
estimation for the urban redevelopment activities in Shanghai. Meanwhile, the regional
DW generation can be calculated based on the demolished floor area of resident and
non-resident buildings, structure types and waste intensities. The number of DW types
such as steel, concrete, brick, and gypsum were taken into account in the study by Ding
and Xiao (2014).
In line with the studies of determining DW components, Kleemann, et al. (2014)
proposed a method for investigating the waste composition prior to demolition,
composed of four steps. The first step is to collect and analyse all relevant documents
for the materials used to construct the building. In the second step, on-site inspection
is conducted before the demolition of the building. This step comprises the inspections
of building components, such as windows, doors, floor and roof construction, wires,
pipes, etc. Based on the results drawn from documents and on-site inspection, the
database of built-in materials is aggregated. Finally, the collected data are compared
with the given information, which is reported by the demolition contractors to verify
the proposed method.
Research in waste estimation has been increasing, reflecting the potential benefits of
computer-based systems in the identification quantity of DW. For example, Al-Saggaf
and Jrade (2015) develop a model of BIM and GIS to estimate waste generation in
urban redevelopment projects, which are the total volume of DW, the volume of
reusable and recyclable materials, and total loss waste. The estimation of the total
volume of DW is based on the building area and the height of buildings. According to
Chapter 2: Literature Review 39
the statistics of the demolished buildings in Finland between the years 2000 and 2012,
Huuhka and Lahdensivu (2014) calculated the volume of DW for 50 different building
types based on the floor areas and the number of demolished buildings. In addition,
Huuhka & Lahdensivu (2014) developed a GIS-based model to demonstrate the
characteristics, the waste volume, and location of demolished buildings to assist in the
planning of waste recovery in Finland.
The studies of waste estimation open a new door, through which DW generation
volume can possibly be estimated and the feasibility of using computer-based solution
for DW management can be identified. For example, Kleemann, et al. (2014) suggest
that the database about building age, building categories, and specific material
intensities can be gathered with GIS data as a prerequisite for the management of
demolition projects.
2.5.2.3 Environmental challenges
The results indicate that little research has been conducted on the environmental
challenges topic, with several papers involved having discussed such issues as air
pollution and hazardous DW (Farfel, et al., 2005; Power, 2008; Roussat, et al., 2008).
According to Farfel, et al. (2005), demolition work in urban redevelopment projects
can be a large source of Pb pollution, which poses a potential risk for residents and
workers. Farfel found an acute increase in Pb dust fall during residential demolition
works in urban redevelopment projects in East Baltimore. This finding highlights the
need to control and minimise the level of Pb poisoning and heightens the awareness of
demolition-related public health issues for developers, contractors, planners, and
public health agencies.
Regarding the hazardous DW, Roussat, et al. (2008) also report that DW contains the
substances that, after being mixed with inert waste, such as lead-based paint, mercury-
contained in fluorescent lamps, can adversely impact human health and environment.
These hazardous components represent only 2% of the DW in France, but they can be
a high risk for the environment. Roussat, et al. (2008) conduct leaching tests and found
out that some elements exceed the limit value set by European regulations. These
studies demonstrate that it is of paramount importance to classify and remove
hazardous substances before demolition work, in order to limit the risks of pollution
to the environment.
40 Chapter 2: Literature Review
2.5.2.4 Stakeholder engagement
Only two papers are relevant to stakeholder engagement in DW management. Poon,
et al. (2001) conducted a survey to identify the factors affecting the implementation of
on-site waste sorting and analysed the current views of stakeholders in carrying out
on-site waste sorting. According to Poon, et al. (2001), on-site C&D waste sorting
requires less effort and results in a better classification of inert and non-inert waste in
comparison with off-site sorting. However, the result of Poon’s study showed that the
stakeholders are reluctant to implement on-site sorting because of time and labour
demands. With regards to community experiences and perceptions of urban
redevelopment, Bowie et al. (2005) found out that there is a need for earlier anecdotal
reports of community concerns and that there is a vital role of community in addressing
environmental and psychosocial issues. Since the last study of Bowie et al. (2005),
little importance has been attached to stakeholder roles. The responsibilities and
attitudes of stakeholders in the demolition process in promoting integrated DW
management are in need of further study.
2.5.2.5 Performance evaluation
Research into the performance evaluation - vital for improving integrated DW
management - has received hardly any attention from academia apart from two
relevant studies (Lu, et al., 2009; Marzouk & Azab, 2014). One of these focused on
the environmental and economic impacts from the disposal of C&D waste, including
waste from demolition work and rebuilding. Marzouk and Azab (2014) argue that
C&D waste has increasingly serious impacts on the environment, the economy, and
society. Two alternatives for C&D waste management, namely recycling and disposal,
are evaluated by a dynamic model with the aid of STELLA software in the four
following steps (Marzouk & Azab, 2014). The first step is to quantify the total cost of
mitigating the impacts of C&D waste on the environment and human health. Then, the
study quantifies the total emissions avoided and energy saved by recycling waste. The
third step is to estimate the cost saved by recycling waste. Finally, a decision support
tool is provided to assist the re-thinking of waste disposal. Marzouk and Azab (2014)
conclude that recycling C&D waste can significantly reduce the emission, energy use,
global warming potential, and converse landfill area when compared with the disposal
alternative. In addition, the study concluded that the cost of addressing the impact of
waste disposal is tremendously high.
Chapter 2: Literature Review 41
The other study developed simulation modeling to evaluate the cost efficiency of DW
management on the demolition project in Hong Kong (Lu, et al., 2009). This model
includes raw DW collecting and sorting, broken concrete sieving and stockpiling, steel
bar recycling, and waste disposal at the landfill. Whereas the time and cost parameters
of a given waste management method (selective demolition) were evaluated. Lu, et al.
(2009) reveal that the on-site DW management was operated smoothly and efficiently
with higher recovery rate for resources of different types. In addition, cost and time
can be reduced by doubling the resource provision on-site. In order to address the need
of sustainable development, a greater emphasis of cost efficiency is expected to be
placed on this topic in the future, due to the increasing need for sustainability
assessment that includes social, environmental and economic considerations.
2.6 URBAN REDEVELOPMENT DEMOLITION WASTE MANAGEMENT IN VIETNAM
2.6.1 Urban redevelopment in Vietnam
In the past 30 years, major cities in Vietnam have undergone tremendous population
growth and a rapid urban modernisation. In such cities, urban housing areas have high
population density, with more than 2,000 persons per one square kilometre. In
addition, the population of the city core is predicted to continue to increase and people
have started to express more concern about their quality of life. Whilst many
neighbourhoods were built around 30-40 years ago, which cannot satisfy the
requirements of natural disaster performance, as well as living conditions. As a result,
serious housing shortages and decay in the inner city have underpinned the need for
the city authorities to carry out large-scale redevelopment. In line with the economic
development and the high population density in Vietnam’s city cores, redevelopment
and new construction activities have become an essential part of contemporary urban
planning.
According to a report by the Ministry of Construction in Hanoi and Ho Chi Minh cities,
there were about 90% of low-rise blocks that were dilapidated, 25% of which were at
high risk to the residents (Bao Anh, 2011). Additionally, Hanoi is the second largest
city in Vietnam. According to the national census conducted in 2009, the
Hanoi’s population is estimated to be 6,451,909, with the average density of
approximately 1,979 people per km2. In addition, with the massive wave of immigrants
from other provinces flocking to Hanoi, the actual population in Hanoi is increasing at
42 Chapter 2: Literature Review
an accelerated speed and this upward trend seems not to be going to cease in the
foreseeable future. Accordingly, the landscape in Hanoi city has gone through
spectacular changes. Despite the rapid urban development, there are about 1,500
dilapidated buildings in the old districts of Hanoi, mainly positioned in Ba Dinh, Dong
Da, Hoan Kiem, Hai Ba Trung, and Thanh Xuan districts, which are located in city
core (Figure 2-7).
According to the survey of Hanoi Construction Department, these old buildings were
built in the 1960s, 1970s and the later 1980s, with low-rise blocks from two to five
floors (Gia Huy, 2015). Constructed with out-dated technology, many of these earlier
buildings were improperly structured or environmentally obsolete, which not only
jeopardised the safety of residents, but also put the public’s safety at risk. Particularly,
the residents have refurbished through generations, which has, in part, accelerated the
deterioration. Moreover, the existing buildings are in possession of their own unique
characteristics, although such infrastructure did not meet the modern standards due to
a lack of community facilities. In addition, the old buildings aged about 50 years do
not have a private kitchen and toilets; especially the old neighbourhoods seem to be
overloaded because the density of residents has increased to almost twice, in
proportion to their initial capacity. A fact worth noting is that many old blocks have
sunk about 1.2 metres and could collapse at any time.
Figure 2-7: The aging blocks in Ba Dinh district, Hanoi
Chapter 2: Literature Review 43
With the rapid deterioration rate and mounting public concern about living conditions,
in 2005, Hanoi Authorities announced a decree 07/2005/NQ-HĐND on urban
redevelopment, stating that the high-risk buildings should be the top priority. In 2008,
The Hanoi Authorities continuously issued a program 06 of urban redevelopment to
motivate the improvement of the dilapidated buildings by replacing complex buildings
with high-rise flats, commercial buildings, and green public spaces. However, in spite
of the city’s attempts, the pace of urban redevelopment after 10 years has been
comparatively low. To date, only 14 old blocks, located in the wards of Thanh Cong,
Kim Lien, and Giang Vo, have been redeveloped, accounting for 1% of buildings that
are labeled as those that need to be redeveloped in Hanoi City. If the urban
redevelopment pace remains static as of now, it might take about 100 years or more to
replace all the old buildings in Hanoi.
According to Ho Chi Minh City Construction Department, there are 474 dilapidated
buildings with 27,208 units, which were constructed before 1975 (Dieu, 2017). It is
estimated that 55% of those aging buildings that need to be redeveloped are at the
highest risk level (Figure 2-8). Similarly, Ho Chi Minh City has similar low pace to
Hanoi in implementing urban redevelopment.
Figure 2-8: The aging buildings in District 10, Ho Chi Minh City
44 Chapter 2: Literature Review
Likewise, in Hai Phong City, there are marginally over 200 dilapidated buildings with
about 8000 inhabitants (Do, 2017). These buildings were built in the 1970s, which put
the residents at high risk (Figure 2-9). In 2017, Hai Phong issued an urban
redevelopment plan to construct new high-rise buildings in the next five years.
Urban redevelopment and housing problems in the city core have emerged as such
major challenges regarding to long-term economic, national security and societal
damage. The Government has announced that the aging buildings in the city core
should be demolished rather than refurbished. The earliest attempt of urban
redevelopment was in 2007 when the Vietnamese government enacted Decree
34/2007/NQ-CP on an urban renewal program focusing on the redevelopment of aging
buildings located within inner city areas. However, starting in 2007, the urban
redevelopment projects have been implemented at a low level across Vietnam for a
number of reasons pertaining to economic, social and environmental aspects. In fact,
the policy makers, planners, and contractors of this program have focused on technical,
land-use, and economic aspects to avoid social and environmental impacts.
Figure 2-9: Aging building in Le Chan district, Hai Phong
As discussed above, a large number of aging buildings in some main cities in Vietnam
have reached the end of their life span and are targets for demolition and
redevelopment. Accordingly, the Vietnamese government has announced the Decree
101/2015/NĐ-CP on the redevelopment of aging buildings, which are likely to be
Chapter 2: Literature Review 45
dilapidated based on Vietnam housing law of 2014. The redevelopment project is
supposed to be undertaken on a large scale, not dealing with single dilapidated
buildings. Consequently, the demand of urban redevelopment leads to massive DW
generation, which can be a huge challenge to sustainable development in many cities
in Vietnam.
2.6.2 Demolition waste management in Vietnamese urban redevelopment projects
According to the national environmental reports, the amount of solid waste generated
in the country was 28 million tons in 2008, of which urban solid waste accounted for
46%, solid waste from industrial activities accounted for 17%, and the rest was solid
waste from construction, craft villages, health and rural activities (MONRE, 2011). It
is estimated that in Hanoi and Ho Chi Minh cities, about 1,000 to 2,000 tonnes of the
C&D waste have been landfilled daily.
The DW is normally dealt with in individual redevelopment sites, which is claimed to
be ineffective and insecure without technical and financial resources. Whilst DW in
many of the developed countries is managed properly with high levels of recovery
(Leigh & Patterson, 2006), there is no coherent framework for DW management in
Vietnam. According to the National report (2011), C&D waste is most often disposed
of in the nearest available open spaces or landfills either legally or illegally. These
seemingly distant threats can metastasise into immediate problems, leading to growing
public concerns about the impacts on the ecology, cityscapes and people’s health, such
as resource degradation, environmental pollution, and land value reduction. In
addition, the open space and landfill are overflowing rapidly to the extent that there
may be inadequate space for waste disposal, demanding a set of actions and strategies
for reduction, reuse, and recycling to remedy the environmental impacts and conserve
natural resources for the future.
According to the Vietnamese Ministry of Construction, in Hanoi City, over 1.7 million
square metres of aging buildings built from the 1960s to 1980s are being planned for
redevelopment, which is expected to produce a huge amount of DW (Gia Huy, 2015).
The redevelopment progress in Hanoi and other cities in Vietnam is behind schedule
because of the conflicts of economic, social and environmental objectives, ranging
from the issues of relocation, the cost of project implementation to the struggle with
environmental problems. The challenges facing the government are how to effectively
46 Chapter 2: Literature Review
manage the volume of DW in the absence of a comprehensive framework that can
minimise the time and cost of DW management and its environmental impacts. In
addition, the duties and responsibilities of all stakeholders involved in the demolition
process are not clearly assigned. In fact, redeveloping the aging and dilapidated
buildings in Hanoi has garnered less attention from developers because it is very time-
consuming and costly. There is the need of improving the DW management
performance in Vietnamese urban redevelopment projects. At present, implementing
urban redevelopment DW management, Vietnam is confronted with four major
obstacles, including insufficient regulations, unavailability of data, absence of a
comprehensive framework, and low of environmental awareness.
‐ Insufficient regulation:
Recently, the Vietnamese government has increasingly promoted sustainable
development in the construction industry in which sustainability should be considered
when planning and executing construction projects (Huy, 2015). However, urban
redevelopment projects in Vietnam have been under scrutiny for failing to achieve the
environmental objectives, including poor DW management (Nguyen, 2015).
Currently, urban redevelopment policy in Vietnam has not provided a roadmap for
sustainable urban redevelopment. In addition, both of its generation and treatment
solutions are not taken into consideration, and there is an increasing concern about the
volume of waste generated by the redevelopment program and the consequences of
waste disposal. Therefore, there is a need for a comprehensive approach in the research
of DW management in Vietnam.
Integrated DW management is considered a feasible solution in order to reduce DW,
to maximise the reuse and recycling and proper disposal of DW. However, there is a
lack of tools to enable the communications of all stakeholders and support decision-
making regarding DW management in urban redevelopment projects at the district
level, offering decision makers a concise view of the critical challenges with a broader
and longer-term perspective. In fact, low tipping fees at landfills and illegal disposal
have suppressed interest in recovering DW in urban redevelopment projects.
Therefore, constructors have mainly focused on building demolition with little
attention to waste minimisation.
Chapter 2: Literature Review 47
There is minimal regulation supporting DW management in the construction industry
in Vietnam, especially in urban redevelopment projects. In fact, DW management is
regulated jointly with municipal waste and most of the measures are aimed at the
improvement of municipal waste management. For example, The Vietnamese
Environmental Law is mainly concentrated on municipal solid waste management and
provides little environment-related legislative and policy framework for C&D waste
management.
‐ Unavailability of data
Obtaining reliable data on waste from the construction industry in Vietnam is not easy,
as data in this field is often managed together with the municipal waste one. This
makes it difficult to precisely estimate the amount of DW in urban redevelopment
projects. Whereas, the information of the DW, such as the amount of waste, the waste
compositions, and the rate of reusable and recycling waste, is essential for planning
and making decisions that support effective management.
‐ Absence of comprehensive framework:
A comprehensive framework and plans are essential; however, urban redevelopment
projects still lack clear guidance as to how to manage DW effectively. There is a need
of framework development to guide waste classification, reduction, reuse, recycling
and disposal of DW.
‐ Lack of environmental awareness:
Although sustainability is perceived widely in Vietnam, stakeholders have still
considered environmental issues as a low priority, especially DW management. In
addition, the practice of DW management and the adaptation of sustainable urban
redevelopment in Vietnam are still at a lower level compared to regional and
developed countries. This is because a DW management process is costly and time-
consuming for them to carry on in practice. Therefore, improving DW management
process can bring about a significant change to stakeholders’ awareness of
environmental protection in urban redevelopment projects.
In line with the need for effective urban redevelopment in Vietnam as stated in the
Decree 101/2015/NĐ-CP, the improvement of DW management should be considered
by addressing the obstacles faced in implementing DW management in Vietnam. This
study, therefore, aims to identify the key decision-making factors that influence DW
48 Chapter 2: Literature Review
management in urban redevelopment projects in Vietnam. The GIS-based model is
applied to develop the database of DW. Subsequently, a decision-making framework
is proposed in order to improve DW management in Vietnamese urban redevelopment
projects. This framework may apply to other developing countries, which have similar
circumstances in urban redevelopment, such as China, Brazil, and India.
2.7 RESEARCH GAP
As discussed above, DW management has captured much attention over the last two
decades, focusing on five main areas: (1) strategy and solution, (2) decision support,
(3) environmental challenges, (4) stakeholder engagement, and (5) evaluation. This
has enriched the body of knowledge of DW management, as well as presented the
current status quo of DW management practices throughout the world. However, the
review indicates that knowledge and experience of DW management in an urban
redevelopment context is limited. Accordingly, research gaps can be identified and are
discussed as follows.
According to Roussat, et al. (2009b), effective DW management requires an integrated
stakeholder approach to include all the stakeholders involved in the demolition
process. However, stakeholder involvement has been limited to date because of cost
and time constraints (Lu, Lau, & Poon, 2009). It is, therefore, indispensable to consider
how communication and information exchange between different stakeholders can be
improved. In addition, there is urgency for a focus on the practice guidelines of
stakeholders’ responsibility in DW management in order to encourage improved
stakeholder buy-in and involvement.
There are a number of computer-based solutions, such as Building Information
Modeling (BIM) and Geographic Information Systems (GIS) that can support
decision-making; from the design to construction or building demolition stages. These
solutions offer useful and versatile tools for academics and professionals in
understanding the characteristics and amounts of waste in order to devise
comprehensive waste handling plans and strategies (Harrison et al., 2001; Najm & El-
Fadel, 2004; Sumathi, Natesan, & Sarkar, 2008). However, there is still a lack of
accurate construction waste data, especially in developing countries (Wu, et al., 2014).
This may be due to the fact that the focus of previous research on both C&D waste has
led to a gap in the understanding of DW, particularly that of urban redevelopment
Chapter 2: Literature Review 49
projects. Therefore, further studies are needed about the impact of a wide range of
information technology systems on the management of DW in urban redevelopment
projects at the regional level.
Furthermore, there is a multitude of challenges in urban redevelopment DW
management due to the complexities involved, such as poor waste management
planning, the overlapping of responsibilities and ineffective time and cost management
(Lu, Lau, & Poon, 2009; Wu, Yu, Shen, & Liu, 2014). Therefore, effective waste
management requires a clear decision-making process with the inclusion of key
stakeholders, which involves project performances towards sustainability covering
different aspects such as economic, environmental, social, technical and institutional
ones. Therefore, more research needs to be conducted to investigate the important
factors influencing effective urban redevelopment DW management and to develop a
framework for improving DW management process, particularly in the context of
Vietnamese urban redevelopment.
Existing academic research underscores the integration of sustainability and DW
management, waste minimisation, environmental issues, waste estimation, and
evaluation. In recognition of those contributions to the knowledge of urban
redevelopment DW management, it should be noted that knowledge and experience of
DW management in an urban redevelopment context is limited. It is also discerned
that less attention has been given to the identification of important decision-making
factors influencing DW management in urban redevelopment projects. There is a
potential for developing knowledge in these areas further, particularly in consideration
of the complexities and challenges involved in delivering urban redevelopment
projects in Vietnam. The knowledge, insights and recommendations provided,
establish a theory framework that can critically address the issues associated with
urban redevelopment DW management to further promote sustainable urban
redevelopment. This framework will be applied in the investigation of the important
decision-making factors in the context of Vietnamese urban redevelopment DW
management. The following section presents the background of decision-making that
applies in the urban redevelopment DW management process.
50 Chapter 2: Literature Review
2.8 RESEARCH CONCEPTUAL FRAMEWORK
2.8.1 Organisational decision-making
Decision-making has become one of the most active strategies in the management
research field (Papadakis, Lioukas, & Chambers, 1998). Decision-making is a process
whereby people gather information, propose and assess alternative resolutions, and
implement those decisions that influence their lives (Hain, 1980). Decision-making is
a process that is implemented over a period of time (Cooke & Slack, 1991) and is the
responsibility of key managers (Elbanna, 2006). This process reflects the interaction
between an organisation and its environment, which is embedded in both the internal
context and external context of the organisation (as cited in Elbanna, 2006). The
decision-making process combines certain steps in the particular order of identifying
existing problems, interpreting and diagnosing those problems and determining the
appropriate solutions (Cooke & Slack, 1991).
Papadakis, et al. (1998) indicate that a decision-making process is multidimensional
in nature and must be integrated over at least four basic perceptions: individual
decision opinion, strategic or management option, environmental determinism, firm
characteristics, and resource availability perception. Many studies have argued that a
decision that is categorised and labeled in the early stages of the decision-making
process can strongly impact the organisation’s subsequent response (Dutton, 1993;
Fredrickson, 1985). Papadakis, et al. (1998) state that the role of decision makers is
vital in determining the strategy content and process. However, their influences on the
decision-making process need to further underline the characteristics that are
important.
Regarding environmental determinism, the decision-making process is presenting the
adaptation to opportunities, threats, constraints and other environmental aspects
(Papadakis, et al., 1998). This adaptation is facilitated by top decision makers, and
answers the question of how environmental factors affect the decision-making process.
The research by Papadakis, et al. (1998) also indicates that the perspective of firm
characteristics and resource availability emphasises internal factors, such as internal
system, organisation performance, size and corporate control and also relates to
profitability and slack resources.
Chapter 2: Literature Review 51
Elbanna (2006) concludes that both academia and executives have paid increased
attention to strategic decision-making, which are grouped into two categories, namely
content research and process research. Content research addresses the issues of the
strategy content such as portfolio management, diversification, mergers and the
alignment of organisational strategies with its environmental features. Meanwhile,
research tackled with the process in which a decision is made and carried out, followed
by figuring out and dealing with the resulting factors. It is noteworthy that these two
categories are not alternative choices (Mintzberg & Waters, 1985).
However, in comparison with content issues, process research has received less
attention from researchers (as cited in Elbanna, 2006). Many studies have advocated
integrating various perspectives of the decision-making process to develop strategic
decision-making process (Bryson & Bromiley, 1993; Chan, Scott, & Chan, 2004;
Elbanna, 2006; Lu & Yuan, 2010). It is of significance to combine the different
elements of decision-making, which would provide a better understanding of the
decision-making process (Hitt & Tyler, 1991).
In the field of waste management, the model of a decision-making process for
municipal solid waste management (MSWM) has integrated factors from various
aspects, such as economic, environmental and technical (Hung, Ma, & Yang, 2007).
The study by Hung, et al. (2007) also indicates that in recent years, sustainability has
been integrated into the models of MSWM. Morrissey and Browne (2004) suggest that
a sustainable decision-making model of MSWM should consider the environmental
effects, the consequences on the economy, and social acceptance.
Furthermore, Wilson (2001) proposes that combining different public groups’
perspectives in the early stages of the decision-making process is to find a
compromised solution. The novel sustainable decision-making model for MSWM is
proposed by Hung, et al. (2007), as shown in Figure 2-10. This model presents various
steps to develop the decision-making process for MSWM. Firstly, there is the
consideration of numerous contributing factors with respect to aspects of
environmental, economic, social, and so forth. Multiple stakeholders’ criteria are also
identified. Secondly, there are a number of methods of waste management that can be
used to prioritise alternatives.
As the waste management decision-making process involves different stakeholders
with different perspectives, it is essential to perform in-depth analysis to select the
52 Chapter 2: Literature Review
viable alternative. The analyses are conducted on the basis of five steps of constructing
the hierarchical structure of waste problems, calculating the criteria weights,
determining the performance of the alternatives for each factor, aggregating the fuzzy
performance and rating the score of the alternatives. In addition, measuring the
agreement between stakeholders regarding the alternatives is needed. Finally, decision
makers can make decisions on waste management based on not only the compromise
solution, but also on the stakeholders’ agreement over all alternatives. This approach
can help decision makers avoid the likely conflicts in making decisions.
Figure 2-10: Steps of a sustainable decision-making model for waste management.
Adapted from ‘A novel sustainable decision-making model for municipal solid waste management’ by (Hung, et al., 2007), page 213.
Chapter 2: Literature Review 53
In line with the study by Hung, et al. (2007), Mayer, van Bueren, Bots, van der Voort,
and Seijdel (2005) integrate the ‘sustainability’ element in the decision-making
process of urban renewal projects by addressing the complexity of perspectives from
various stakeholders. There is the need of collaboration in planning and decision-
making among different stakeholders in order to ensure that all stakeholders’
perspectives are included in the decision-making process. In addition, Mayer, et al.
(2005) also state that the decision support system (DSS) would facilitate sharing of
knowledge and information concerning the project between decision-makers. This
indicates that in sustainable urban redevelopment projects, stakeholders from different
areas, such as construction contractors, waste management contractors, planners, and
policy makers, must be able to communicate and share information effectively. Mayer,
et al. (2005) (Page 406) conclude that there is a need of methodologies and tools to
implement sustainable urban renewal projects, which ‘are able to support the
substantive (that is, content), as well as the political (that is, the context), dimensions
of decision-making’.
In addition, more recently, integrated assessment is more concerned with the
dimensions of the decision-making process and the use of participatory tools for both
environmental issues and other socio-technological systems (Ravetz, 2000; Rotmans,
van Asselt, & Vellinga, 2000). Besides the application of the decision-making theory
into urban redevelopment DW management, it is vital to integrate and to incorporate
sustainability in the decision-making process. As DW management in urban
redevelopment projects is complex, a compromising approach can facilitate the
confrontation of DW management issues among the stakeholders.
2.8.2 Research factors influencing demolition waste management in urban
redevelopment projects
Strategic decision-making plays a significant role in the field of management. Using
multi-criterion analysis is supportive for decision makers to make decisions in the
management process (Yau & Ling Chan, 2008). According to Walker (2015),
considerations that should be taken into account in the early stage of a construction
project are political, legal, economic, institutional, sociological and technical aspects.
Ng, Cook, and Chui (2001) add that the key issues of an urban regeneration project
planning are the project’s impacts on the society, economy, environment, and traffic.
In urban redevelopment projects, DW management encompasses environmental and
54 Chapter 2: Literature Review
socio-economic issues and involves different stakeholders, which makes the
management process more complicated (Yau & Ling Chan, 2008). In order to achieve
integrated DW management, the contributory factors of the decision-making process
need to be fully perceived.
In fact, based on the three pillars of sustainability, scholars have different views
regarding which factors should be examined in the decision-making process. Research
by Yau and Ling Chan (2008) concludes that a sustainable urban regeneration plan is
demanded to mitigate the social impacts, enhance the economic targets, and take
environmental issues into account. Kum et al. (2005) give a simple decision-making
process for integrated waste management that influences can be categorised into seven
factors, including political, legal, technical, social, environmental and economic
factors, and available resources. Zhang and Li (2012) point out that the consideration
of sustainable construction waste management should be based on the evaluation of
sustainable attributes that can balance the environmental, economic and social
objectives. Therefore, assessing the environmental impacts of specific waste
management approaches, evaluating the cost of dealing with construction waste and
identifying social impacts can be factors that influence the decision-making process.
In this study, considering DW management at the district level, the DW issue is
complex and dependent on various factors specific to the region. Therefore, it is crucial
to analyse the information related to integrated DW management thoroughly to help
decision makers make the right decisions. Due to the growing complexity of the urban
redevelopment projects, the technical and institutional aspects are considered in order
to ensure the appropriate allocation of stakeholders’ responsibility and availability of
technical information. In addition, the performance metrics of DW management
should be in line with the three pillars of sustainable urban redevelopment including
economic, social, and environmental considerations.
Therefore, in this study, the decision-making factors which influence DW management
were encompassed under technical, environmental, social, economic and institutional
goals that can be achieved through integrated DW management in sustainable urban
redevelopment. Based on the analysis of related literature, the decision-making factors
are grouped under five categories including technical, environmental, economic,
economic, social and institutional. Table 2-2 shows the details of references to
literature from which potential factors have been developed. As a result, fifty-three
Chapter 2: Literature Review 55
potential factors were obtained from the comprehensive literature review. These
factors were analysed and classified into 19 main themes, which represent the five
categories of DW management performance. This finding formed the main basis for
the questionnaire design used in the survey study.
Table 2-2: Research factors influencing DW management in urban redevelopment project
Category Theme Relevant literature
Technical (1) Demolition techniques
Poon, et al. (2001), Poon, et al. (2004), Lombardi, et al. (2011), Lu and Yuan (2010), Petersen (2004), Roussat, et al. (2009b), Lombardi, et al. (2011)
(2) DW management processes
Poon, et al. (2001), Poon, et al. (2004), Ding and Xiao (2014) Blengini (2009), del Río Merino, et al. (2009), Lu (2014), Seo and Hwang (1999), Qualharini and Flemming (2009), Marrero, et al. (2011)
(3) ICT-based solutions
Huuhka and Lahdensivu (2014), Kleemann, et al. (2014), Al-Saggaf and Jrade (2015)
(4) Time and risk management
Roussat, et al. (2009b), Chan, et al. (2004), , Akintoye and MacLeod (1997)
(5) Life cycle assessment
Blengini (2009)
Environmental (1) Stakeholder awareness
Rao and Zhang (2015), (Yuan, et al., 2011), Poon (1997)
(2) Environmental issues
Huuhka and Lahdensivu (2014), Yuan & Shen (2011), del Río Merino, et al. (2009), Blengini (2009), Marzouk and Azab (2014), Tam (2008) Marrero, et al. (2011)
(3) 3R strategies Poon, et al. (2001), (Yuan & Shen, 2011), del Río Merino, et al. (2009), Marrero, et al. (2011)
(4) Disposal control Poon (1997)
Economic (1) Cost-effectiveness Lu, et al. (2009), Yau and Ling Chan (2008), Vego, Kučar-Dragičević, and Koprivanac (2008), Mcdonald and Smithers (1998), Lu, et al. (2009), Roussat, et al. (2009b), Al-Saggaf and Jrade (2015)
(2) Recycled market Blengini (2009), Petersen (2004), Mcdonald and Smithers (1998), Roussat, et al. (2009b), del Río Merino, et al. (2009)
(3) Disposal costs Mcdonald and Smithers (1998), Roussat, et al. (2009b), del Río Merino, et al. (2009), Poon (1997)
Social (1) Community involvement
Zheng, et al. (2014), Bowie, et al. (2005)
(2) Safety implication Petersen (2004), Roussat, et al. (2009b), Yau and Ling Chan (2008)
(3) Preservation Yau and Ling Chan (2008), Zheng, et al. (2014), Petersen (2004), Lee and Chan (2008b)
(4) Job creation Roussat, et al. (2009b), Yau and Ling Chan (2008), Petersen (2004)
Institutional (1) Stakeholder engagement
Zheng, et al. (2014), Delmas and Toffel (2004), del Río Merino, et al. (2009), Marrero, et al. (2011), Lu and Yuan (2010), (Lam, Chan, Poon, Chau, & Chun, 2010), Liu, et al. (2005b), Roussat, et al. (2009b)
56 Chapter 2: Literature Review
(2) Policy and guidelines
del Río Merino, et al. (2009), Rao and Zhang (2015), Marrero, et al. (2011), Bjerregaard (2008), Bjerregaard (2008), Poon (1997)
(3) Information and communication
Huuhka and Lahdensivu (2014), Kleemann, et al. (2014), Lombardi, et al. (2011), Chan, et al. (2004)
Based on the background literature covering C&D waste management, particularly
DW management in urban redevelopment projects, a conceptual framework for
improving DW management in urban redevelopment projects is developed, as shown
in Figure 2-11.
Figure 2-11: Conceptual framework of effective DW management in urban redevelopment projects
As illustrated in Figure 2-11, the research factors identified to influence DW
management in urban redevelopment projects are categorised as 1)Technical,
2)Environmental, 3)Economic, 4)Social, and 5)Institutional. These factors are
discussed as follows.
2.8.2.1 Technical factors
This category includes five main themes, covering 16 sub-factors that are summarised
from the relevant literature, namely demolition techniques, DW management
processes, ICT-based solutions, time and risk management, and life cycle assessment.
Influencing factors in urban redevelopment DW
management
Technical
Demolition techniques
DWM processes
ICT-Based solutions
Time & risk management
LCA
Environmental
Stakeholder awareness
Environmental issues
3R strategies
Disposal control
Economic
Cost -effectiveness
Recycled market
Disposal costs
Social
Community Involvement
Safety implication
Preservation
Job creation
Institutional
Stakeholder engagement
Policy guidelines
Information& Communication
Chapter 2: Literature Review 57
The theme of demolition techniques refers to choosing the demolition method,
applying the selective demolition method, demolition skills and training, and
demolition equipment. According to Yau and Ling Chan (2008), an urban regeneration
project can be a source of conflict if it is poorly planned. In light of that, demolition
technique consideration should be taken into account so that demolition work can
facilitate the urban redevelopment DW management process. For example, Poon, et
al. (2004) state that choosing a proper demolition method can ease on-site waste
sorting and increase the waste recovery rate. In addition, the selective demolition
technique is adopted to dismantle the selected material in different demolition stages.
This method helps retrieve the recyclable and reusable waste in an easy and systematic
way (Poon, et al., 2004). In addition, the C&D waste generation is substantially
affected by how skilful construction workers are (Lu & Yuan, 2010). If workers are
incompetent, the implementation of the construction or demolition works will result in
large amount of waste (Wang, Kang, & Wing-Yan Tam, 2008). Therefore, ‘demolition
skill and training’ is considered an influencing factor in implementing waste
management in construction projects. Furthermore, the stakeholders may reluctant to
invest in demolition equipment, particularly low waste technology, which capital cost
may initially outweigh return on investment. This results in the difficulty in on-site
waste classification and low rate of waste recovery (Poon, et al., 2001).
A DW management process theme consists of DW management procedures, onsite-
waste sorting, waste estimation, planning of waste sorting space and landfills. These
are all important stages of the DW management process. For example, Roussat, et al.
(2009b) argue that a strategy of DW management could not be effective without an
appropriate classification of waste types that can be recovered for different purposes,
such as road engineering and concrete block production. Poon, et al. (2001) add that
effective waste management on the construction site usually involves scheduling for
waste clearance, waste collection, and waste disposal, which should be developed
before construction activities. According to Poon, et al. (2001) off-site waste
classification can be more cost-effective than that of on-site classification because it
does require less workers and less cost expenditure on a construction site. However,
from the perspective of environmental protection, off-site waste classification is not
recommended for C&D waste management. This is because the waste is more easily
classified directly from the source than that in case of mixing and then separating it.
58 Chapter 2: Literature Review
Thus, the contractors can increase the value of recyclable waste and avoid the pollution
caused by mixed materials (Wu & Ann, 2014). In addition, Formoso, Soibelman, De
Cesare, and Isatto (2002) indicate that waste estimation, such as the amount of waste
and the waste components, provides stakeholders crucial information for achieving
cost and plan effectiveness in DW management.
ICT-based solutions denote the application of ICT-based in improving DW
management in urban redevelopment projects. There is an increasing trend of ICT-
based applications in the construction industry due to their various individual features
and capabilities (Al-Saggaf & Jrade, 2015). Recently, ICT-based solutions have been
applied in the field of waste management as a decision support tool (Al-Saggaf &
Jrade, 2015; Chalkias & Lasaridi, 2011). For example, Karadimas and Loumos (2008)
state that an integrated GIS-based model has been considered as one of the most
powerful platforms to computerise the process of waste planning and management.
The theme of time and risk management comprises the duration of demolition work
and identifying the risks associated with demolition work. The time factor is an
important concern that stakeholders need to consider prior to implementing DW
management. According to Poon, et al. (2001) and Lu, et al. (2009), stakeholders are
reluctant to conduct on-site sorting because of time constraints. Therefore, there is a
need for proper time management in DW management.
The theme of life cycle assessment refers to a methodology that emphasises the
evaluation of specific elements of a product system to investigate its environmental
impacts (De Benedetto & Klemeš, 2009). By this approach, Blengini (2009) states that
a comprehensive energetic and environmental picture regarding demolition and final
disposal of a building can be investigated. Accordingly, the recycling potential of DW
can be estimated. Thus, consideration of life cycle assessment should be a rudimentary
fundamental for sustainability.
2.8.2.2 Environmental factors
According to (del Río Merino, et al., 2009), all construction projects have impact on
the environment through the use of raw materials, energy consumption, and waste
generation. For example, the hazardous components of DW sent to landfill can pose a
potential risk to the groundwater by leaching chemical hazardous waste (Roussat, et
al., 2008). In addition, it is indisputable that the lack of full awareness of and
knowledge about demolition results in demolition failures (Liu, et al., 2005b).
Chapter 2: Literature Review 59
Therefore, considering and understanding environmental factors in formulating plans
of DW management could diminish the environmental impacts. The environmental
category consists of four main themes covering 11 sub-factors, namely stakeholder
awareness, environmental issues, and 3R strategies.
The theme of stakeholder awareness refers to the willingness of DW management by
stakeholders, and training in integrated waste management. Insufficiency of interest
and understanding by stakeholders could hinder the improvement of DW management
in urban redevelopment projects. Meanwhile, the uniqueness of DW and hazardous
DW, emission of greenhouse gases, disposal control, environmentally could impact
the assessment of DW and cause the environmental problems associated with DW
management, which are grouped in the theme of environmental issues. The problems
associated with DW management include environmental impacts, low rate of recovery,
difficulties in waste sorting, and higher energy consumption for DW treatment.
Therefore, understanding DW’s uniqueness in the early stage of the demolition work
is vital for effective DW management. In addition, the hazardous waste, such as metal,
paints and bituminous, make up a significant component of DW. The audit of these
components should be done properly in demolition work. Construction activities, such
as manufacturing, transporting of materials, and disposal waste, can consume primary
energy, which results in a large amount of greenhouse gas emission (Yan, Shen, Fan,
Wang, & Zhang, 2010). Balancing greenhouse gas in construction projects,
particularly in the process of waste disposal, can reduce environmental impacts.
Furthermore, disposal control implies the consideration of disposal fee and landfill
sites in DW management. Hendriks and Jansen (2001) affirm that high disposal fees
of C&D waste should be imposed by the authorities and the construction industry that
may help raise stakeholders’ awareness of waste management.
The 3R strategies theme takes into consideration 3R promotion in DW management,
the use of recycled materials, and rate of waste recovery. These strategies should be
expedited in the process of choosing waste management measures (Peng, et al., 1997),
which could increase the waste recovery rate and remedy the environmental impacts
as well as soothing the pressure on the landfills.
2.8.2.3 Economic factors
The economic category is composed of eight factors under three main themes
regarding cost-effectiveness, recycled market, and disposal cost. The theme of cost-
60 Chapter 2: Literature Review
effectiveness takes into consideration the cost of demolition, waste transport, and waste
treatment; the cost-effective demolition plan; and energy saving during DW
management process. From an economic viewpoint, ineffective urban redevelopment
DW management could result in tremendous losses in the process of waste treatment
and waste recycling. Therefore, cost-effective plans would assist stakeholders in saving
energy and the cost of DW management. It is of valuable to determine which economic
factor should be important to be considered. For example, it is crucial to identify the
demolition plan that can be implemented with reasonable efforts at an affordable cost
and involve the use of recycled materials. Accordingly, this can enhance the
stakeholders’ willingness to conduct the DW management or recycle DW.
Recycled market refers to the development of the recycled market in order to encourage
the use of recycled materials. The development of the recycling market is reckoned as
one of the effective strategies of C&D waste management (Wu & Ann, 2014).
Disposal cost signifies the issue of proposing an appropriate fee for DW disposal. del
Río Merino, et al. (2009) indicate that poor on-site waste sorting results in not only
extra waste processing but also higher disposal fees. The disposal fees should be
properly imposed for different types of DW.
2.8.2.4 Social factors
In order to achieve sustainable development through urban redevelopment projects, it
is also important to identify the social factors in the preparation for the DW
management plan. This category consists of nine sub-factors under four main themes:
community involvement, safety implication, preservation, and job creation.
The theme of community involvement takes into consideration the role, supportive
actions, monitoring and feedback by community, and public awareness of urban
redevelopment DW management. The theme of safety implication is divided into two
sub-factors, which are safety at work and the reduction of community disturbance.
Safety is an important aspect for society. Considering security at the workplace and
the reduction of environmental impacts on the community will ensure public health
and quality of life in urban redevelopment neighbourhoods. Preservation reflects the
conservation of natural resources, and historical structures and local cultures. It is
witnessed that heritage should be conserved properly for the enjoyment of society
through different generations (Fung, 2004). Job creation is one of the major indicators
of social sustainability (Omann & Spangenberg, 2002). In this sense, this study
Chapter 2: Literature Review 61
considers job creation as the primary factor in urban redevelopment DW management.
This factor emphasises the number of jobs created due to DW management regarding
demolition work and waste processing.
2.8.2.5 Institutional factors
In order to ensure that the right decision can be made, the institutional factors that
contribute to effective DW management should be considered. This category includes
nine factors, which are grouped into three main themes: stakeholder engagement,
policy and guidelines, and information and communication.
Stakeholder engagement refers to the involvement of key stakeholders in DW
management, including the roles and responsibilities of stakeholders; control and
feedback by stakeholders; and stakeholders’ perspectives on the DW management
process. Identifying who needs to be specifically engaged in DW management process
is vital to making an effective DW management plan. The theme of policy and
guidelines embodies the development of the best practice guidelines for urban
redevelopment DW management and the accomplishment of policies and strategies
related to DW management in urban redevelopment projects. According to Lu and
Yuan (2010), stakeholders may be reluctant to implement C&D waste management in
their construction projects if there is a lack of guidelines and government’s
supervision. This results in poor DW management planning and the overlap of
stakeholders’ responsibilities. Specifically, (Lu & Yuan, 2010), a good policy system
is considered as the most important factor to the success of waste management in
construction projects in China (Lu & Yuan, 2010). Therefore, accomplishing policies
and strategies will help address the problems for implementing effective DW
management in urban redevelopment projects. ‘Information and communication’
reflects the reports or database in the urban redevelopment DW management process
which can help stakeholders design an effective waste management plan and avoid
miscommunication. Shen, et al. (2007) state that the more crucial information and
knowledge the stakeholders share, the better projects’ performance is. Thus, this factor
was identified as an important theme in improving DW management in urban
redevelopment projects.
62 Chapter 2: Literature Review
2.9 SUMMARY
Through the literature analysis, a holistic view of DW management in urban
redevelopment activities is examined. It is highlighted that urban redevelopment is an
inevitable stage of the modern urban development process. This is occurring in many
cities all over the world, especially in developing countries that are facing dilapidation
in the city core. However, as the urban redevelopment activities are increasing, DW
management is receiving less attention.
In Vietnam, there is a lack of regulation and information to assist stakeholders in
implementing effective urban redevelopment DW management. Therefore, it is crucial
to develop knowledge in these areas further, particularly in view of the complexities
and challenges involved in delivering urban redevelopment projects. The knowledge,
insights, and recommendations lend urgency for practitioners and academics to
construct a conceptual framework to critically address the issues associated with urban
redevelopment DW management, to further promote the sustainability of urban
redevelopment. This research provides a better understanding of the important
decision-making factors that influence the implementation of effective DW
management in Vietnamese urban redevelopment projects.
In order to establish a decision-making framework, a thorough and extensive
understanding of factors affecting the decision-making process of DW management is
investigated. A number of issues have been raised to identify the factors relevant to
the technical, economic, environmental, social, and institutional aspects.
Although the 53 decision-making factors under five categories in this study are
regarded as important influences in urban redevelopment DW management, people
may have different perceptions towards their relative importance. Wang and Yuan
(2011) argue that the perspectives of decision-making factors can be affected by
stakeholders’ experience, background, personal beliefs, and social culture. Hence, this
study aims to address the significant research gap by identifying the decision-making
factors based on the perspectives of different groups of stakeholders, academics,
planners, consultants, engineers and policy makers in the context of Vietnamese urban
redevelopment through questionnaire surveys and interviews. The research design is
presented in detail in the next chapter.
Chapter 3: Research Design 63
Chapter 3: Research Design
3.1 INTRODUCTION
A proper research design before embarking on research actions is necessary to
facilitate effective data collection and reliable results. The research design is a plan for
undertaking research in order to achieve the research questions and objectives by
adopting appropriate and feasible methods (Sproull, 2002). Fellow and Liu (2015)
state that choosing the research methods requires the logic and relationship between
data collection analysis and the research questions. This research adopted the research
strategy of social science.
This chapter first explores the research proposition and the philosophical basis of the
research methodology that is used in this study. It then presents the research design
with the explanation of the research approach and the selection of research methods
adopted in the study: questionnaire surveys, interviews, and a case study. This is
followed by the research process, including the three main stages. Four main
approaches in the research development stage were then discussed and finally, the
consideration of research ethics is drawn.
3.2 RESEARCH PROPOSITION
There are a variety of methods in designing a research plan in terms of data collection,
analysis and modelling. Underlying the weaknesses and strengths of various methods
can help select the most appropriate methods and tools for the research.
The intent of this study is to explore the factors affecting the decision-making process
and develop a decision support model for DW management in urban redevelopment
projects. In this study, several research methods are applied to answer the research
questions. As can be observed, the research proposition is drawn based on the research
questions, aim and objectives, which will stimulate new approaches to reach the aim
of the research (Figure 3-1).
64 Chapter 3: Research Design
3.3 RESEARCH PHILOSOPHY
Research philosophy has a significant influence on the link between the targeted set of
terms and concepts that define an academic discipline and its process (Johnson &
Clark, 2006). According to Fellows and Liu (2015), a research paradigm can be
considered from a theoretical framework perspective. This perspective represents how
a researcher views the world (Creswell, 2013). It is crucial to identify what views and
approaches are applied in developing a conceptual framework regarding the selected
topic (Fellows & Liu, 2015). The paradigm of the study should be established as the
set of concepts and beliefs upon which a scientific field can be understood. In addition,
according to Creswell (2013), the philosophical position need to be understood before
the design of the whole research. The study by Mark, Philip, and Adrian (2009)
Research questions 1. What are the key decision-making factors influencing demolition
waste management in Vietnamese urban redevelopment projects? 2. How do the key decision-making factors influence demolition waste
management in Vietnamese urban redevelopment projects? 3. What is the necessary information to support key stakeholders in
demolition waste management in Vietnamese urban redevelopment projects at the district level?
Research aim The aim of this research is to develop a comprehensive decision-making framework for improving demolition waste management in Vietnamese urban redevelopment projects at the district level.
Research objectives 1. To explore the current DW management in urban redevelopment
projects and in the context of Vietnam. 2. To identify critical decision-making factors of DW management in
urban redevelopment projects. 3. To develop a decision-making framework and critical supporting
information to assist decision makers in improving demolition waste management in Vietnamese urban redevelopment projects at the district level.
Figure 3-1: Research proposition
Chapter 3: Research Design 65
indicated that the research design decision should be developed based on the research
questions, objectives and research philosophy.
Creswell (2013) contended that there are four approaches in identifying the best
methods for research including postpositivism, constructivism, advocacy, and
pragmatism. The main elements of these philosophies are shown in Figure 3-2.
Figure 3-2: Philosophical Positions (Creswell, 2013)
Postpositivism is known as positivism or postpositivism research or empirical science.
This philosophy is an approach of natural sciences (Neuman, 2000). Fellows and Liu
(2015) claimed that postpositivism which is related to rationalism, empiricism and
objectivity represents a conventional research philosophy based on facts including
non-metaphysical and phenomena that can be observed. It is assumed that since
postpositivism fits quantitative research better than qualitative ones, this philosophy
is usualy applied in experiments, surveys and statistical analysis (Creswell, 2009).
Constructivism reflects an interpretive research approach in which the researcher uses
his or her individual experience to conceptualise facts and phenomena rather than the
researcher’s objective and observation (Creswell, 2009). According to Neuman
66 Chapter 3: Research Design
(2000), constructivism is ‘the systematic analysis of socially meaningful action
through the direct detailed observation of people in natural settings in order to arrive
at understandings and interpretations of how people create and maintain social worlds’.
This is particularly suitable for research that has a complexity of views and multiple
meanings. Fellows and Liu (2015) stated that constructivism is a typical approach to
qualitative analysis.
Advocacy is known as a participatory paradigm, in which research should be
integrated with politics and political agenda (Creswell, 2009). This can combine
various perspectives and the experiences of people from different backgrounds
(Morris, 2006). Advocacy research normally deals with the need of person or groups
of people that may be disenfranchised or trivialised. The type of research that applies
this approach is normally qualitative research.
Pragmatism is an approach that combines different methodologies to identify the
research problems resulting from consequences, circumstances and activities
(Creswell, 2009). Patton (2002) stated that the application of pragmatism research can
help identify the research problems and figure out the solutions. This approach support
research which uses mixture of methodologies and deals with not only qualitative but
also quantitative database that can help the researcher find the best answers to research
questions.
According to research’s concerns and objectives (as discussed in section 1.3 and 1.5,
Chapter 1), this study aims to explore and investigate the critical decision-making
factors that help improve the urban redevelopment DW management and then develop
a decision-making framework. Therefore, pragmatism is the most appropriate
approach for this research. Pragmatism adopts to mixed methods, different
assumptions, and various forms of data collection and analysis (Creswell, 2013). This
philosophy is possible in conducting a study with variations in epistemology and
ontology, to answer the research questions. This proves the legitimacy of mixed
methods in solely study, which has been widely applied in urban sustainability (van
Bueren & ten Heuvelhof, 2005; Williams & Dair, 2007).
Chapter 3: Research Design 67
In this research, the methods were adopted separately. The quantitative analysis was
first employed to deal with the questionnaire survey results. Then, the qualitative
analysis was used to improve the proposed framework based on the interview results.
A case study was conducted to develop a decision support system by using a GIS-
based solution. Finally, a comprehensive decision-making framework of urban
redevelopment DW management was finalised. The details of the research
methodology will be presented in the next sections.
3.4 RESEARCH DESIGN
According to Mark, et al. (2009), the research design is defined as an overall
framework aiming at answering the research question in sequence. This is developed
based on both research concept and research contribution. The research design
provides a scheme according to which the research can be conducted including data
collection and analysis so that all research questions are addressed (Bryman & Bell,
2015). Fellows and Liu (2015) state that consideration of the appropriate methods
needs to be logically linked with how the data can be analysed in order to answer
research questions and achieve research objectives.
3.4.1 Research approach
This research is designed as a pragmatist approach. This approach is credited for
bringing flexibility and simplicity to the research process. This involves different
methods in finding appropriate solutions to deal with the research questions. Specially,
the research approach discovers how to approach data collection and analysis to
develop or test the theory for a research (Mark, et al., 2009). This research combines
both inductive and deductive approaches at different steps of the research process.
While inductive research formulates a theory from different observations, deductive
research develops a theory aiming at a rigorous test (Yin, 2013).
The deductive approach is applied in identifying theoretical decision-making factors
of urban redevelopment DW management, which are extracted from the literature. In
addition, these theoretical factors are formulated in the process of analyses of
stakeholders’ perspectives to develop a decision-making framework, which is an
inductive approach in nature.
68 Chapter 3: Research Design
In this study, the research approach adopted both qualitative and quantitative methods
to address the research questions and seek to attain the research objectives. Once the
quantitative methods are employed, accordingly, data are collected and analysed in
numeric form (Fellows & Liu, 2015). At the same time, qualitative methods are
adopted based on the constructivist approach. Qualitative research can help identify
and understand the issues behind any phenomenon and can also provide intricate
details (Corbin, Strauss, & Strauss, 2014). This method is employed to analyse the data
from different sources, while seeking information regarding stakeholders’ perspectives
and identifying the action plans for improving the decision-making process. Thus,
interpreting the entire analysis requires a combination of both quantitative and
qualitative data.
In this study, the sequential strategy is employed the mixed methods design of
Creswell and Plano Clark (2011), which analyses both quantitative data and qualitative
data, in order to interpret the research problems. The mixed methods strategy is
adopted based on knowledge claims of the pragmatic paradigm. Creswell (2009) states
that the usage of both a quantitative and qualitative analysis can help the researcher
incorporate strategies of enquiry in collecting data.
The distinctions of the selection of quantitative, qualitative, or mixed methods are
described in Table 3-1. Gephart Jr (1991) adds that the analysis of quantitative and
qualitative data helps to provide a more complete picture of the phenomenon.
Therefore, by adopting the mixed methods, the researcher could gain insight into the
research problems and deal effectively with the research questions. Therefore, an in-
depth identification of the factors influencing the decision-making process is vital. The
use of quantitative methods to explore the stakeholders’ perspectives, identify critical
decision-making factors, and develop a supporting database is necessary. In addition,
the qualitative approach is adopted to elaborate and validate the results from the
quantitative process. Three main research methods were selected and are described in
the next section.
Chapter 3: Research Design 69
Table 3-1: Quantitative, qualitative, and mixed methods approach analyses by Creswell (2009)
Items Qualitative
Approach Quantitative
Approach Mixed-Method
Approach
Philosophical assumptions Strategies of
inquiry
Constructivist/ Advocacy Participatory Phenomenology,
grounded theory, ethnography, case study, and narrative
Post positivist Surveys and
experiments
Pragmatic Sequential,
concurrent and transformative
Data collection methods
Open-ended questions, emerging approaches, text or image data
Close-ended questions, predetermined approaches, numeric data
Both open- and close-ended questions
Data analysis strategies
Focus on a single concept or phenomenon Validate the
accuracy of research results Provide
explanations of the data Create a plan for
the changes or reform Interact with
participants
Verify theories Identify variables
data Link the variables
in questions Identify the
reliable and valid data Observe and
compute the data numerically Use unbiased
approaches Adopt statistical
procedures
Collect both quantitative and qualitative data Establish a
rationale for mixed data Incorporate the
data at different research stages Present visual
pictures of the research process Employ both
qualitative and quantitative analysis
3.4.2 Selection of research methods
As the research aim is to develop a decision-making framework in improving DW
management in urban redevelopment projects, this requires a mixed method of both
qualitative and quantitative approaches to collect and analyse data to identify the
important factors influencing DW management. In addition, in the decision-making
process, a decision support system based on GIS tools is proposed to provide a
supporting database. Qualitative and quantitative approaches can be combined in
70 Chapter 3: Research Design
different forms according to varied research targets. The research questions are solved
by integrating quantitative and qualitative methodologies, selecting appropriate
research methods, and formalising a logical research process. Four main research
methods are adopted in this study, including literature reviews, questionnaire surveys,
interviews, and case studies. The key features and objectives of each method are
described in Table 3-2.
Table 3-2: Summary of selection of research methods
Methods Key features Objectives
Questionnaire survey
Allowing an approach to a large survey sample. Allowing quantitative
analysis of a large number of variables Not restricted to the physical
locations of the participants.
Identifying the important factors influencing the decision-making process in improving urban redevelopment DW management. Analysing statistically the participants’
responses. Investigating a consensus among five
stakeholder groups in determining critical factors. Revising the conceptual framework of the
decision-making process.
Interview Allowing an investigation directly on critical factors. Allowing a discussion on
action plans in improving DW management in urban redevelopment projects. Allowing a validation of the
proposed decision-making framework.
Gaining in-depth practice opinions corresponding to each critical factor. Validating the proposed framework of
decision-making process. Developing action plans in improving DW
management in urban redevelopment projects.
Case study Allowing a development of supporting database. Allowing an application of
GIS-based in assisting the decision-making process
Developing a supporting database in making decision of DW management in urban redevelopment projects. Applying the GIS-based model as a
decision support tool to practically develop the database.
Literature needs to be reviewed in order to identify the global trend of urban
redevelopment; the need of DW management in urban redevelopment projects;
research problem; and the context of urban redevelopment DW management in
Vietnam. Based on the literature review, the conceptual decision-making framework
for improving DW management in urban redevelopment projects is proposed, which
includes 53 identified factors that influence the decision-making process. The analyses
Chapter 3: Research Design 71
of quantitative data and qualitative data can aid the interpretation for revising and
validating the conceptual decision-making framework.
A quantitative survey is an appropriate approach for understanding the stakeholders’
perspective and their consensus about critical decision-making factors, while a
qualitative approach for the interview is appropriate to elaborate and validate the
proposed decision-making framework from the survey result. In addition, the action
plans for improving DW management in urban redevelopment projects are finalised
by qualitative analysis. A case study is used for developing a supporting database by
the GIS-based tool. These selected methods are systemised into three research stages
in the research process, which will be presented in the next section.
3.5 RESEARCH PROCESS
The research process is designed to consist of three stages. It includes establishing the
conceptual framework, developing framework, and developing supporting database.
Research methodologies were consequently designed to adopt data collection and data
analysis as shown in Figure 3-3.
3.5.1 Establishing conceptual framework
The research begins with the initial stage of ‘establishing conceptual framework’, in
order to explore the conceptual framework for the study. The research problem was
first explored before research questions and objectives were identified. The relevant
theories, the context of study in Vietnam, and existing research of DW management
in urban redevelopment projects were then reviewed. The review of literature helped
identify the research gaps and factors influencing the DW management decision-
making in urban redevelopment projects. Based on the analysis of factors influencing
the decision-making process, the conceptual framework was proposed, then revised
and validated in the survey and interview studies in the next stage.
3.5.2 Development of the framework
In stage 2, the conceptual framework was developed through the questionnaire survey
and interview processes. The questionnaires were first clarified and amended in the
pilot study before the survey was conducted. Data collected from the survey were
analysed with SPSS in order to explore the perspectives and consensus of key
stakeholders who are involved in DW management in urban redevelopment projects.
72 Chapter 3: Research Design
Based on the results of the quantitative analysis, the critical factors were identified in
helping revise the conceptual framework. The semi-structured interviews were then
conducted with a strong focus on an in-depth investigation into the important impact
of critical factors. The qualitative data were analysed in order to validate the proposed
framework and synthesise the action plans that improve DW management in urban
redevelopment projects. In this stage, it also identified the critical factors through
Interview
Figure 3-3: Research process
Pilot study Questionnaire clarity and comprehensive
Investigate in depth critical factors
Stage 2: Development of framework
Questionnaire survey
Survey Structured questionnaire
Quantitative data analysis by SPSS
Revised decision-making framework
Qualitative content analysis
Decision-making framework validation
Action plans
Stage 3: Development of supporting database Urban redevelopment projects information C
ase stud
y Decision-making framework finalisation
Preparation of DW database
Developing GIS-Based model for supporting
d b
Stage 1: Establishing conceptual framework
Literature review Urban redevelopment DW management Study context in Vietnam Decision-making
Identify research problem and research gap
Establish research questions and objectives
Identify factors influencing decision-making process
Conceptual decision-making framework
Chapter 3: Research Design 73
interview study, which were analysed to develop critical supporting database in GIS-
based model in the next stage.
3.5.3 Development of supporting database
In the last stage, the critical supporting database was developed to facilitate the
decision-making process of DW management in urban redevelopment projects. A case
study comprises four real urban redevelopment projects in Ba Dinh district, Hanoi,
Vietnam, which were chosen to practically develop database of DW management in
the form of GIS-based model. The spatial and attribute data were collected regarding
the amount and components of DW, the locations of buildings and projects, and the
information of landfills. This database was integrated with critical decision-making
factors to establish decision-making framework for improving DW management in
Vietnamese urban redevelopment projects at district level.
3.6 RESEARCH METHODS
This research was developed as described above and conceptualised in Figure 3-4.
Four main research methods were adopted to conduct research into background
investigation, data collection, and data analysis. These include literature review, the
questionnaire survey, the interviews, and the case study. The research findings were
investigated based on the analysis of quantitative and qualitative data. The research
methodologies will be discussed in the following sections.
3.6.1 Literature review
Literature review plays a vital role in a study, helping the researcher highlight the
research problems and identify research gaps. According to Cavana, Delahaye, and
Sekaran (2001), ignoring both important and unimportant variables in the research
backgrounds may have negative influence on the validity and reliability of the findings
and research significance. In part, the literature review aimed to establish the research
background (McMurray, 2004).
As a consequence, the background knowledge could provide the rationale to set the
research questions and research objectives. The relevant knowledge is conceptualised
for further investigation in addressing the research questions. All the relevant
knowledge helps to develop the conceptual framework and justify the questionnaire
survey.
74 Chapter 3: Research Design
This research began with an extensive review of books, professional journals,
conference papers, government documents, internet resources, and so forth in the
global context as well as in the Vietnamese context. The knowledge relating to urban
redevelopment, DW management, sustainability, green construction, integrated waste
management, and decision-making theory was captured. Based on the review, the
concept of sustainability was explored to integrate in DW management, in order to
achieve sustainable urban redevelopment. Therefore, different aspects of sustainability
were analysed and integrated in exploring decision-making factors of DW
management in urban redevelopment projects, such as economic, environmental,
social, technical, and institutional.
In addition, a critical review was undertaken, focusing on the existing research
regarding DW management in urban redevelopment projects in order to identify the
research trends and research gaps. The research by Poon (1997) is reckoned as the
early research related to DW management in urban redevelopment in Hong Kong.
Based on that, the literature from 1997 to 2016 was therefore reviewed with reference
to research concerning the DW management of urban redevelopment projects.
All the 204 articles were analysed according to the year of publication, publication
outputs of country/region, distribution of outputs in journals and subject categories.
The publications from a range of leading journals were identified and used to explore
research trends. The results indicate that knowledge and experience of DW
management in urban redevelopment projects are limited. Hong Kong, the United
States, and United Kingdom are key contributors, while countries such as China, India
and Brazil are relatively less represented. Waste Management; Resources,
Conservation & Recycling; Building Research & Information; and Waste Management
& Research are identified as active journals in publishing DW management research.
The scope of this review identifies key knowledge gaps in current research and offers
recommendations for future research. The background literature and the context of
DW management in Vietnam were reviewed to synthesise the factors affecting DW
management in urban redevelopment projects, which established a conceptual
framework. The conceptual framework included 19 main themes covering five
categories: technical, environmental, economic, social, and institutional. These main
themes formed the main basis of the questionnaire design, which resulted in 53 factors
in the survey study.
Chapter 3: Research Design 75
3.6.2 Questionnaire survey
The questionnaire survey aimed at identifying which decision-making factors are
significantly concerned by stakeholders when they make decisions about DW
management in the context of urban redevelopment projects. The results of the
questionnaire survey helped to achieve the second research objective and generate data
which enable further analysis in the interview study. The questionnaire survey was
suitable for this study because it collects data from a large range of industry
perspectives. In addition, the respondents provided a ranking of the extent to which
the decision-making factors influence DW management in urban redevelopment
projects.
The questionnaires used in the survey contained, multiple choice questions, single-
choice questions, scale questions using a Likert scale, and open questions. After the
questionnaires were developed, a pilot test was conducted to evaluate the survey
procedures and to modify its contents, after which the questionnaires were altered for
the better. The main questionnaire included 53 influencing factors that were considered
to be in five categories, which were applicable to DW management in urban
redevelopment projects.
In the questionnaire survey, the survey samples were comprised of selected industry
practitioners and advisors in the field of DW management in Vietnamese urban
redevelopment projects, which were categorised in five groups. Firstly, academics
include experts who are working in the universities and research institutes advising the
development of C&D waste policy. Secondly, planners include people working in
government agencies and local authorities involving in the DW management planning
in urban redevelopment projects. Thirdly, consultants are defined as industry
practitioners, including private companies, advising on environmental considerations
of urban redevelopment DW management.
Engineers were selected from both civil construction and environmental disciplines in
construction and waste management contractor organisations. These organisations are
responsible for demolishing process, on-site waste classification, waste collection,
waste transport, and waste disposal. Finally, policy makers are defined as public sector
76 Chapter 3: Research Design
experts who directly involved in the development and implementation of the decision-
making process, policy and guidance of urban redevelopment DW management.
The questionnaires were sent to 500 respondents selected from five key stakeholder
groups who play a critical role in DW management in Vietnamese urban
redevelopment projects. However, only the respondents who were interested in this
survey and fulfilled the sample questionnaire were eligible for the research. The
respondents were provided with self-administered questionnaires and were asked to
rate, on a five-point Likert scale ranging from 1 = Not at all important to 5 = Extremely
important, to what extent the decision-making factors affected DW management in
urban redevelopment projects.
The data collected from the questionnaire survey was coded before the quantitative
analysis in Statistical Package for Social Science (SPSS) for Windows version 23. In
order to determine how many factors significantly influence urban redevelopment DW
management, six main tests were conducted to identify the critical factors. These
critical factors were then prepared for in-depth interviews. The purposes and results of
statistical analyses using SPSS (Statistical Analysis Package) are presented in Table
3-3.
The normality test was first conducted to find out the differences of the five groups’
stakeholder perspectives for all 53 factors. According to Field (2014), the difference
is calculated by deducting the scores of variables. The outcomes from the normality
test presented that the distributions of all the differences of 53 factors were
significantly non-normal with p<0.01 (Appendix B1). The non-parametric tests,
therefore, are required to compare the five groups of stakeholders’ perspectives in
ranking 53 research factors. The non-parametric Kruskal-Wallis test is used to
compare three or more independent samples and Post-hoch analyses of statistically
significant comparisons were used with multiple Mann-Whitney U tests to compare
two independent samples (Field, 2014).
Table 3-3: Methods of statistical analysis
No. Purpose Test Outcomes
Chapter 3: Research Design 77
1 ‐ Test the internal consistency of the scale
Cronbach’s alpha
‐ Data reliability
2
‐ Identify the most influenced decision-making factors of demolition waste management
Descriptive statics (mean and standard deviation)
‐ Respondents’ profile ‐ Different stakeholders’ perspectives on the critical decision-making factors ‐ Critical factors of decision-making for demolition waste management
3
‐ Determine the differences among the critical decision-making factors
Kendall’s coefficient of concordance (W)
‐ The differences in perceptions on the relative influence of decision-making factors’ rank among respondents
4
‐ Determine the statistically the significant divergences in the mean ranks of critical factors
Non-parametric Kruskal Wallis
‐ Chi-square (2)– rating distribution of the questionnaire ‐ P-value – significant difference in the mean ranks of critical factors
5
‐ Determine the statistically significant differences between the means of five stakeholder groups ‐ Ensure the robustness of the results from nonparametric Kruskal Wallis test
Parametric One-Way ANOVA
‐ P-value – significant difference in the means of critical factors
6
‐ Compare the differences in relative significance of factors between two independent groups
Non-parametric Mann Whitney test
‐ Probability value on critical decision-making factors ‐ P-value – significant difference in the mean ranks of critical factors between five groups of stakeholders.
7
‐ Compare the significant differences of factors between mean scores of two independent groups ‐ Ensure the robustness of the results from nonparametric Mann Whitney test
Parametric 2-sample t test
‐ P-value – significant difference in the mean ranks of critical factors
8
‐ Correct for type I errors in multiple comparison
Benjamini-Hochberg procedure
‐ P-corrected ‐ Correcting the significant P value that corresponding critical factors figured out from Kruskal Wallis and Mann Whitney tests
In addition, the robustness of survey quantitative analysis was confirmed by
conducting correlational tests in both nonparametric and parametric statistical
78 Chapter 3: Research Design
analysis. In this research, there were two equivalent pairs of hypothesis tests, which
were nonparametric Kruskal Wallis and parametric One-Way ANOVA, and
nonparametric Mann Whitney and parametric 2-sample t test. Further, the parametric
approach was used to examine whether there were any differences in stakeholder
groups’ perspectives. Moreover, the validity of the nonparametric statistical analysis
was increased by this approach.
As the distributions of survey data were identified non-normal by normality test, the
parametric approach required a data transformation. The data transformation was done
by logarithmic transformation in SPSS to make data conform to normality, which was
more appropriate for parametric testing (Changyong et al., 2014).
When testing for a statistically significant difference between two or five groups of
stakeholders, each critical factor is tested separately by Kruskal Wallis and Mann
Whitney tests and a p-value is computed for each critical factor. If the test results
provide the probability rate lower than 5% (p-value <0.05), the different perspectives
among two or five groups is statistically significant. These significant differences were
detected further by One-Way ANOVA and 2-sample test testing by p-values <0.05.
Furthermore, it is also important to correct the p-value of each critical factor to control
the type errors I in multiple tests. In this research, the False Discovery Rate (FDR) was
controlled with the Benjamini-Hochberg procedure (Benjamini & Hochberg, 1995).
Multiple testing corrections adjust the individual p-value generating a Benjamini-
Hochberg FDR – p-corrected value, which is used instead of convention rate of 5%.
The p-corrected is calculated by the following equation:
p-corrected =
where i is the rank of ascending input p-values; m is the total number of tests; and Q
is critical value for a false discovery rate. The largest p-value <p-corrected is
significant and all of the p-values smaller than it are also deemed significant. In this
research, the Benjamini-Hochberg critical value for a false discovery rate Q is chosen
to be 0.25, which is similar to the research of García‐Arenzana et al. (2014).
Regarding the results of the Kruskal Wallis test, if the difference was significant, the
Benjamini-Hochberg procedure was then applied to correct type I errors in multiple
comparisons. The Benjamini-Hochberg procedure was also used to correct p values
generated in the Mann Whitney test.
Chapter 3: Research Design 79
Based on the statistical nonparametric analysis, the results were then validated by
parametric testing and Benjamini-Hochberg procedure to identify 24 critical decision-
making factors. The finalised list of critical factors was verified by 22 practitioners in
Vietnam through interview study to ensure the influences and discussion of the
potential improvements of DW management.
3.6.3 Interview
According to Rogers and Bouey (1996), interviewing as a data collection technique in
post-positive research is a fairly common practice and involves the preparation of a
guide that lists a predetermined set of questions for the purpose of eliciting information
from participants. The semi-structured format provides a great amount of flexibility
and allows new questions and insights to be included during the course of the
interviews. The interviewees were identified and selected through purposive sampling
based on their familiarity with the subject matter. The interview questions were both
specific and open-ended and focused on major issues pertaining to the phenomenon
under investigation (Creswell & Plano Clark, 2011). Specific interview guides were
developed in order to ensure the common understanding among different stakeholders
working in different organisations, including government agencies, academic
institutes, and contractors.
The main purpose of the interview was to gather more in-depth information of each
critical factor explored from the survey for analysing data and validating the
framework. The interviewees were selected from those who engaged in the survey,
who expressed interest in participating in the interview (question 18 in the
questionnaire sample, Appendix A). A total of 29 survey respondents who stated their
willingness to involve in the interview were approached.
The sample criteria of selecting interviewees comprised the personal background,
experience, current positions, availability for the interview, and representation of
targeted organisations and cities in Vietnam. The background of the interviewees was
relevant to one of the disciplines in project management such as waste management,
urban planning, civil engineering, and sustainable development. In addition, 10-years
experience was required to ensure the interviewees’ in-depth understanding about the
research topic. The current positions of the interviewees were also considered in order
to identify the important roles in DW management decision-making in urban
redevelopment projects. Each participant was approached to check if they met the
80 Chapter 3: Research Design
criteria and be available in the interview period (from April to June 2017). Finally, the
22 selected interviewees represented for organizations and cities sampled in the survey
as well as five groups of key stakeholders, including academics, planners, consultants,
engineers, and policy makers.
Therefore, of the 29 participants, 22 interviewees were selected to participate in the
interview. The final 22 interviewees comprised four academics, three planners, three
consultants, six engineers, and six policy makers. The samples represented of all five
stakeholder groups are defined in section 3.6.2. All of the 22 interviewees had more
than 10 years of experience and held key positions in the projects.
Fourteen interviews were conducted face-to-face at the offices of interviewees, or at
coffee shops. Eight interviews were conducted by telephone. The interviews were
carried out in Vietnamese and each lasted an average of 45 minutes. An audio recorder
was used to record most of the interviews, and notes were also taken as a back-up.
Some interviewees objected to being recorded, out of fear of reprisals by superiors.
This request was adhered to by the researcher and detailed handwritten notes were
taken instead. Under the conditions of confidentiality, the names, positions and duty
stations of interviewees are not disclosed in this research.
Interviewees were asked to share their opinion regarding the importance of critical
factors in decision-making process of urban redevelopment DW management.
Interviewees were also requested to discuss the action plans for improving urban
redevelopment DW management in Vietnam. The semi-structured format provided a
great amount of flexibility and allowed new questions and insights to be included
during the course of the interviews.
The qualitative thematic analysis was then adopted to analyse the data collected from
the interviews to identify the influences of 24 critical factors on DW management in
the context of Vietnam. The results of the interview stage also provided the action
plans in accordance with critical factors suggested by the interviewees to improve DW
management in urban redevelopment projects in Vietnam. Due to the small sample
size of the interview, there was no benefit to be obtained from applying electronic
cognitive or pattern mapping software. Therefore, a manual method to transcription
analysis was adopted to pinpoint the key themes in terms of influencing and improving
DW management in Vietnamese urban redevelopment projects.
Chapter 3: Research Design 81
In the interview study, six critical decision-making factors were identified as crucial
information to develop a critical supporting database of DW management in GIS-
based model in the case study.
3.6.4 Case study
According to Adams, Khan, Raeside, and White (2007), the case study is the most
suitable method through which to identify best practice. There are three criteria to
achieve an effective case study, including using multiple sources of evidence;
establishing a database; and maintaining a chain of evidence (Yin, 2013). Accordingly,
the main purpose of the case study was to practically develop the supporting database
in the GIS-based model. The crucial data and practical concerns were identified from
the results of the survey and interview analysis involving the case study.
In this research, the case study was used as a practical example of how the supporting
database was developed in GIS-based model. This supporting database was considered
crucial information for improving decision-making process of urban redevelopment
DW management in Vietnam. Four mega urban redevelopment projects in Ba Dinh
district in Hanoi, Vietnam, were selected to develop the DW database. Both spatial
and attribute data were collected and analysed in GIS-based model at the district level.
Based on the case study method, this research introduced an approach of GIS
technology as a decision support tool that assists the decision makers in assessing and
qualifying the information about DW management.
In academia and practice, GIS-based model has been adopted in the fields of municipal
solid waste management and C&D waste management. According to Chalkias and
Lasaridi (2011), GIS is one of the most sophisticated modern technologies providing
tools to capture, store, manipulate, analyse and present spatial data. The data is
presented in thematic layers in the form of digital maps. These data are integrated with
the advanced related technologies to assist in the recording of spatial data and the direct
use of data for analysis and cartographic display. There were several approaches of
GIS-based model in municipal solid waste management such as siting waste
management, disposal facilities, optimising waste collection and transport (Chalkias
& Lasaridi, 2011). Karadimas and Loumos (2008) added that GIS has been
successfully adopted for sitting of recycling storage centres, estimating waste
generation, and predicting waste generation.
82 Chapter 3: Research Design
In the field of C&D waste management, GIS technologies were adopted in C&D waste
management such as reducing construction waste, quantifying DW flow, analysing
spatial construction materials (Li, Chen, Yong, & Kong, 2005; Tanikawa &
Hashimoto, 2009; Wu et al., 2016). The study by Li, et al. (2005) was to integrate GIS
with a Global Position System to minimise the amount of on-site waste by combining
construction materials and an equipment system based on the Wide Area Network.
While Tanikawa and Hashimoto (2009) and Wu, et al. (2016) use a GIS-based model
to estimate overall DW generation volume for aging stock at the regional level such as
Shenzhen city, China, Manchester, UK, and Wakayama city, Japan. In addition,
Tanikawa and Hashimoto (2009) present spatial distribution of construction materials
over time and clarified material accumulation with vertical location. Furthermore, Al-
Saggaf and Jrade (2015) integrate GIS with Buiding Information Modeling (BIM) in
DW estimation, classification, and transport at the project level. Similarly, Kleemann,
Lederer, Rechberger, and Fellner (2017) adopted GIS technology in analysing the
spatial distribution of construction materials used for the Vienna’s building stocks
regarding material components of various construction types, construction periods,
and the statistics of building structures.
By applying GIS technology, it is feasible to develop a database so that the spatial and
attribute analysis can support decision-making process. In the context of a case study
in Hanoi, Vietnam, this research used GIS-based model as the decision support system
for developing the critical DW database. The process of developing the GIS-based
model is presented in Figure 3-4.
The model of GIS allows the expression of the database in different forms, such as
maps, tables, and figures. The results of the case study were the DW volume estimation
for single building and single project; the volume of DW compositions such as bricks,
mortar and concrete, and metal; the number of trucks for inert DW (bricks, mortar, and
concrete) delivery; and options of choosing landfill sites.
The DW management database in GIS-based model in the case study was integrated
with 24 critical decision-making factors analysed and verified in the survey and
interview study in order to finalise the decision-making framework. This framework
provides critical factors and useful supporting database that decision makers can
consider in improving DW management in urban redevelopment projects at district
level.
Chapter 3: Research Design 83
3.7 ETHICAL CONSIDERATIONS
This study has been approved by the Human Research Ethics Committee (HREC) at
Queensland University of Technology. The QUT’s HREC confirms that the research
satisfies all necessary conditions set by the National Statement on Ethical Conduct in
Human Research regarding the participants’ rights and welfare in the survey study and
the interview study. The reference approval number of this research is 1600000588.
The respondents were voluntarily involved in the research and their decisions to
participate or not does not influence on their relationship with Queensland University
of Technology.
The research findings which were clarified to the participants do not directly impact
on their benefits. Instead, the research enriches their existing knowledge related to the
improvement of DW management in urban redevelopment projects, in which the
exploration and evaluation of the influences critical factors in the decision-making
Figure 3-4: Process of GIS-based model for the development of supporting database
Data collection
Spatial data
. Map/Satellite image of land-use . Map of transport . Locations of building and projects . Locations of C&D waste landfill site
Attribute data
. Structure information of buildings . Building components . C&D waste landfill locations and capacity
Estimation of DW volume (ton)
. Volume of DW composition
. DW volume of single building
. DW volume of single project
Choosing of landfill sites
. Distances to landfill sites
. Landfill capacity
Estimation of pick-up trucks
. The number of trucks for non- inert DW Integration of
spatial and attribute data
84 Chapter 3: Research Design
process are the main focus. The research findings will raise awareness about the
significance of sustainable urban redevelopment and the DW management.
In order for the participants to understand the research topic, the researcher introduced
the research purpose in the participant information sheet and provided consent forms
before asking them to fill out the questionnaires. Accordingly, the respondents can be
clear and confident in their participation. Since the consent form explains the
significance of the respondents’ participants, their decision to participate was agreed
by signing the consent form and sending it back to the researcher.
3.8 SUMMARY
This chapter elaborates the methodological steps that were undertaken to develop the
decision-making framework for improving DW management in urban redevelopment
projects. The quantitative and qualitative analyses were adopted in different research
stages to deal with the research questions, address the research objectives, and achieve
the research aim.
The research development process includes three main stages: establishing the
conceptual framework, developing the framework, and developing the supporting
database. Four main research methods were employed through the research process to
conduct research background investigation, data collection, and data analysis. These
were literature review, questionnaire survey, interviews, and case study, wherein two
data collection and analysis tools were used, namely SPSS and GIS. The data
collection and research findings are described in the next three chapters.
85
Chapter 4: Survey Study
4.1 INTRODUCTION
This chapter presents the data collected from the respondents who participated in
completing the questionnaire (see Appendix A). The findings from the analysis reveal
the critical decision-making factors for urban redevelopment DW management and the
conceptual framework of this research.
According to the research process, the survey study is an important stage in the data
collection phase. The survey was carried out after the conceptual decision-making
framework was established in the literature review. The questionnaire design, survey
instruments, the survey response rate, and validity are first described. The following
sections present the quantitative results to explore the stakeholders’ perspectives on
decision-making factors of urban redevelopment DW management and the critical
decision-making factors. Finally, the findings from the questionnaire survey are discussed
before the development of the conceptual decision-making framework of urban
redevelopment DW management.
4.2 QUESTIONNAIRE DESIGN
The questionnaire survey was employed to investigate the stakeholders’ perspectives
regarding decision-making on urban redevelopment DW management. The survey was
designed based on the theoretical decision-making factors identified in the background
literature with a synthesis and compilation process, resulting in the consolidation of 53
decision-making factors to be investigated. The questionnaire in this research is
developed on the Key Survey software. A pilot study was carried out to examine the
feasibility of the approach prior to performance of a full-scale research project that was
able to gather the expected data. Fellows and Liu (2015) indicate that the pilot survey is
also conducted to ensure the clarity, comprehensiveness and acceptability of the
questionnaire. A group of five respondents, including two university professionals, one
construction engineer, and one consultant, was asked to validate the questionnaire.
Respondents were asked for the extent of the clarity, language, design, and the
effectiveness, to minimise the problems of misinterpretation or misreading of the
86 Chapter 4: Survey Study
questions. No major changes were required, and the questionnaire contains five parts,
utilising a combination of multiple-choice questions, rating scale, and open-ended
questions. The samples of the questionnaire survey, including in English and Vietnamese,
are attached in Appendix A1 and A2.
The structure of the survey itself will be described as follows. The questionnaire consists
of five steps: (1) Respondent information, (2) General information, (3) Factor affecting
the decision-making process of DW management in urban redevelopment projects, (4)
Further information and (5) Optional question, as shown in table 4.1. In the first part of
the questionnaire, the respondents’ profiles are considered important to gather. This is
because the data reliability is based on the data source and the background of the person
who participates in the questionnaire survey (Ahuja, Yang, & Shankar, 2010). The
second part captured the general information regarding the DW management in urban
redevelopment projects. Part 3 is the main section of the survey, which required the
respondents to rate the importance of the potential decision-making factors using a 5-
point Linkert-scale from 1 representing ‘Not at all important’ to 5 representing
‘Extremely important’. Part 4 employed multiple choice questions and open text sections
for respondents to offer further information and additional recommendations. Finally, in
part 5, the respondents were asked to participate in the interview stage of this research.
Five groups of respondents' roles were investigated in the survey samples, namely,
academics, planners, consultants, engineers and policy makers who were directly
involved in the urban redevelopment DW management in Vietnam. The respondents were
asked to assess the significance of the decision-making factors based on their work
experience.
The respondents in the survey were selected from 54 organisations in three main cities in
Vietnam (Hanoi, Hai Phong, and Ho Chi Minh City) and were from different
organisations, such as the Ministry of Construction; Ministry of Natural Resources and
Environment; Ministry of Science and Technology; academic institutes (University of
Construction, Hanoi University of Science, Hanoi University of Natural Resources and
Environment); Construction companies, and Environmental Service companies in both
government and private sectors. These organisations are the professional institutions
involved in urban redevelopment DW management in Vietnam.
87
Table 4-1: Structure of the questionnaire
No. Category Purpose
1 Respondents’ information
To collect the respondents’ basic information for the purpose of categorisation, such as current position, type of organisation, professional experience, the role in the project.
2
General information relevant to urban redevelopment DW management.
To collect the information regarding the current implementation of DW management in urban redevelopment projects, such as the project location, the scale of the project, the network of stakeholders, the criteria of implementation of urban redevelopment projects.
3
Factors affecting the decision-making process of DW management in urban redevelopment projects
To collect the professional opinions of the determinant decision-making factors in urban redevelopment DW management. There were 5 categories of decision-making factors:
‐ Technical factors (16 factors): e.g., equipment of demolition projects, onsite sorting of demolition waste, planning the area for landfill, life cycle assessment.
‐ Environmental factors (11 factors): e.g., the willingness of DW management by stakeholders, understanding the uniqueness of demolition waste, 3R promotion, identifying the rate of recovery.
‐ Economic factors (8 factors): e.g., estimating the cost of demolition, cost-effective demolition plans, developing of recycling market.
‐ Social factors (9 factors): e.g., the role of community in decision-making process, effective feedbacks from community, job creation due to DW management.
‐ Institutional factors (9 factors): e.g., the role of key stakeholders in monitoring and feedbacks, providing guidelines of DW management plan, regular information update.
4 Further information relevant to urban redevelopment DW management
Further comments and opinions regarding the research topic are collected.
5 Optional question The respondents were invited to provide their contact details if they were able to participate in the interview round of this research.
4.3 SURVEY INSTRUMENT
The survey was carried out using two approaches of survey distribution to collect answers
from the survey participants, namely the online questionnaire and the face-to-face
88 Chapter 4: Survey Study
questionnaire survey. For the online questionnaire, the survey was carried out through an
online survey platform, called ‘Key Survey’, which can be accessed at
https://survey.qut.edu.au/site/.
There has been a growing trend of using the Internet and email for conducting the
questionnaire survey in the last two decades (Neuman, 2000). The advantages of an online
survey are reducing cost and time, gathering information from a large audience and
allowing respondents to maintain their anonymity (Van Selm & Jankowski, 2006). In
addition, the instant reports from the online survey can support the researcher to monitor
the data information, such as the number of participants and the amount of time spent
answering the questionnaire. This online tool can be flexibly designed and is at the
researcher’s disposal in achieving the research objectives.
Another method of survey distribution in this research was the face-to-face questionnaire
survey. This method was expected to gain higher response rates in comparison with other
methods. Face-to-face questionnaire survey was employed due to lack of response to the
questionnaire by potential respondents in the sample via the online survey method. The
participants were approached via phone or email before the researcher met them and
asked them to fill in the questionnaire.
4.4 SURVEY RESPONSE RATE AND VALIDITY
The survey was conducted from September 2016 to January 2017. In total, 500 survey
invitations were sent to the participants with the cover letter (Appendix A3), the consent
form and the questionnaire link or hard copy. The purpose of the research and assurances
of confidentiality are carefully stated in the cover letter. A total of 216 valid responses
were received in the questionnaire survey. The valid responses to the survey questionnaire
were ensured as to whether the questions were fully responded, whether there were any
irrational answers such as rating the same score for all questions, and whether the
respondent’s profile showed the limitations of experience in the field of urban
redevelopment DW management.
As mentioned above, this research employed two methods of survey distribution for the
questionnaire survey, namely the online questionnaire and the face-to-face questionnaire
survey. The combination of different data collection approaches can help the researcher
gain higher response rate of the survey. The responses received by each of the methods
are presented in the following.
89
Online questionnaires: The participants in the online survey were contacted via email to
be informed about the survey. The participants completed and returned the questionnaire
in about four weeks and the polite reminder postcard was sent to remind the participants
who did not complete the questionnaire in the survey period. After the allocated period
for responding to the online survey, out of 183 respondents, 166 responses were fully
completed and were considered valid for data analysis. The overall response rate for the
online questionnaire method was 33.2%. This low response rate may have been due to
the limited time available for working on the computer, especially for the participants
working on construction sites.
Face-to-face questionnaire survey: Due to the low response rate received from the online
survey, the researcher decided to use the method of face-to-face questionnaire survey to
conduct the questionnaire survey, helping to collect information from another 50
respondents. The response rate was 100% because the appointments with the participants
were made in person. The survey strictly followed the online questionnaire and the
researcher had explained any ambiguous survey questions or information during the
meeting. Therefore, all the responses were considered valid for data analysis.
Consequently, the response rate of both survey methods was 43.2%, corresponding with
the total number of 216 out of the total of the targeted number of 500 respondents. This
figure is well above the acceptable response rate, exceeding the normal rate of
approximately 30% in the construction industry (Akintoye, 2000; Love & Smith, 2003).
4.5 QUESTIONNAIRE RESULTS AND ANALYSES
4.5.1 Respondents’ profiles
As discussed above, the respondents’ profiles regarding their background, qualifications,
and experience are asked in Part A of the questionnaire. The 216 valid respondents across
the classification of their professional positions were categorised in five groups Table
4.2). The highest number of respondents was from the engineer group, including
construction engineers and environmental engineers, accounting for 26% of the total
number of respondents. This was followed by the academic group (24%), policy maker
group (20%) and planner group (17%). The consultant group was less interested in the
survey, representing only 13% of the responses.
90 Chapter 4: Survey Study
Table 4-2: Respondents’ information
The distribution of the respondents by organisation type is illustrated in Table 4.2. Out of
the 216 respondents, 33% were from research institutions, 22% were from the
government agency and 21% were from the local authority. The respondents from
contractors of construction and waste management were 16% and 8%, respectively. The
low rate of respondents from waste management contractors is attributed to the poor
environmental services for C&D waste in Vietnam.
Regarding respondents’ experience, all of the respondents surveyed have experience in
DW management in urban redevelopment projects. The respondents’ length of working
experience was reliable data across five groups (Table 4.2). Around 55% of the
respondents have had at least 10 years of experience in the field that the research topic
No Distribution of respondents Frequency Valid percent
1 Respondents’ profession
Engineer 57 26
Academic 51 24
Policymaker 42 20
Planner 37 17
Consultant 29 13
2 Type of organisations
Research institution 72 33
Government agency 47 22
Local authority 45 21
Construction contractor 34 16
Waste management contractor 18 8
3 Respondents’ experience
Under 5 years 15 7
5-10 years 82 38
10-15 years 65 30
15-20 years 41 19
Over 20 years 13 6
4 Frequency of involvement in demolition waste management
Rarely 21 10
Sometimes 82 38
Often 71 33
Always 42 19
91
deals with, whereas 6% of the respondents were stated to have had experience for over
20 years. This high level of respondent seniority enables the high credibility and high
quality of data collection. However, there were about 45% of respondents with under 10
years’ experience in urban redevelopment DW management.
There were 52% of the respondents who were often and always involved in urban
redevelopment DW management (Table 4.2). Around 38% of the respondents sometimes
participated in the field of the research topic and 10% were rarely engaged in DW
management in urban redevelopment projects. This may due to the fact the urban
redevelopment activities are quite new issues in Vietnam over the last decade.
The majority of the respondents undertaking urban redevelopment projects were from
Hanoi, accounting for 134 out of 216 respondents (Figure 4-1). The number of
respondents from Hai Phong and Ho Chi Minh cities was lower than in Hanoi, with 42
and 40 respondents, respectively. This figure represented the current status of urban
redevelopment in those cities in Vietnam, whereas Hanoi is the leading city in urban
redevelopment issues.
Figure 4-1: Distribution of the respondents by the places in which they implemented the urban redevelopment projects
0
20
40
60
80
100
120
140
160
Hai Phong Hanoi Ho Chi Minh city
Number ofparticipants
92 Chapter 4: Survey Study
4.5.2 Reliability of the questionnaire
The SPSS Statistics 23.0 program was used in evaluation in order to understand whether
measurement instruments were reliable and valid. Table 3-3 in Chapter 3 shows the
results and meanings of the reliability tests for different measurement scales.
Before the study proceeded with the analysis, the internal consistency of the measurement
scales for 53 decision-making factors was evaluated upon the calculation of Cronbach’s
Alpha, which normally ranges between 0 and 1. Pallant (2010) suggests that when the
value of Cronbach’s Alpha is above 0.7, the data is deemed to be reliable while the alpha
value of greater than 0.8 is often preferred. In addition, Darren and Mallery (1999) set
thresholds for evaluating reliability upon the value of Cronbach's alpha that the reliability
of measurement scales is deemed to be excellent, good, acceptable, questionable, poor or
unacceptable if the Cronbach’s Alpha is greater than 0.9, between 0.8 and 0.8; between
0.7 and 0.8; between 0.6 and 0.7; between 0.5 and 0.6 and less than 0.5 accordingly. Since
the Cronbach's alpha value for identified decision-making factors in urban redevelopment
DW management was 0.847, the reliability of the measurement scales and data was
evaluated as good.
4.5.3 Respondents’ perspectives
This section focuses on the rating of decision-making factors influencing the DW
management in urban redevelopment projects. The average mean score and standard
deviation were calculated for each potential decision-making factor to figure out its level
of importance and spread dispersion. These figures were different among the five
stakeholder groups. The mean values of the 53 potential decision-making factors range
from 2.45 to 4.44, which illustrates a discrepancy in significance among various decision-
making factors. The modest values of standard deviation (0.475 to 0.732) indicate an
insignificant diversity in the respondents’ ratings.
The mean and standard deviation of each decision-making factor are calculated from the
total sample to identify the level of importance. The standard deviation illustrates the
extent of variation from which the mean value is calculated. In this research, all of the
standard deviation values are smaller than 1.0 that affirms the data accuracy. If two or
more factors have the same mean value, the one with the lower standard deviation is
ranked as more important. The respondents’ perspectives are discussed in detail below.
93
4.5.3.1 Perspective of Academics
The findings as set out in Appendix B2 indicate that the impact level of decision-making
factors for urban redevelopment DW management according to 52 academics differs to
that of factors identified by other stakeholders. Among five categories of decision-making
factors, academics ranked institutional factors as the most important in decision-making
urban redevelopment DW management (mean value = 4.07) (Table 4-3). This is followed
by technical factors and environmental factors, with mean value of 3.951 and 3.970,
respectively. Social factors, conversely, were the least important (mean value = 3.368).
Table 4-3: Academics’ ratings of decision-making factors of demolition waste management
No. Decision-making
factors Number
of factors
Rank Mean
Std. Deviation
Minimum Maximum Minimum Maximum
1 Technical factors 16 3 5 3.951 .497 .706
2 Environmental factors
11 2 5 3.970 .525 .700
3 Economic factors 8 2 5 3.914 .563 .705
4 Social factors 9 1 5 3.368 .518 .759
5 Institutional factors 9 3 5 4.076 .473 .687
In general, out of 53 factors, 23 factors have been ranked by academics as very important,
with the mean value of more than 4.00. Three highest ranked decision-making factors are
‘guidelines of DW management’ (mean = 4.412), ‘on-site sorting’ (mean = 4.392),
‘determining the procedure’ (mean = 4.373). With regards to technical value, the results
express that the academics were more concerned about ‘on-site sorting of DW’ (mean
value = 4.392), ranking it as the most important factor in this category. This is the priority
factor in DW management (Poon, et al., 2001). Meanwhile in the category of
environmental factors, ‘promotion of 3R’ was ranked as the most important factor of
decision-making in urban redevelopment DW management (mean = 4.314). ‘Cost-
effectiveness of demolition plan’ was considered as the most important factor in the
economic category (mean = 4.333). ‘Preservation’ was identified as the most important
social-cultural factor, indicating the goal of sustainability in urban redevelopment
projects (mean = 4.255). In term of institutional factors, ‘guidelines of DW management’
94 Chapter 4: Survey Study
was in the first of the list for it topped the list in terms of the importance in improving
decision-making of urban redevelopment DW management (mean = 4.412).
4.5.3.2 Perspective of Planners
The findings as set out in Appendix B3 indicate that the impact level of decision-making
factors for urban redevelopment DW management, according to 37 planners, differs from
that of factors identified by other stakeholders. Among five categories of decision-making
factors, planners ranked institutional factors as the most important in decision-making
urban redevelopment DW management (mean value = 4.180) (Table 4-4). This is
followed by technical factors and environmental factors, with mean value of 3.867 and
3.26 respectively. In the meantime, social factors were the least important (mean value =
3.330).
Table 4-4: Planners’ ratings of decision-making factors of demolition waste management
No. Decision-making
factors Number of
factors
Rank Mean
Std. Deviation
Minimum Maximum Minimum Maximum
1 Technical factors 16 2 5 3.867 .442 .763
2 Environmental factors
11 2 5 3.826 .479 .731
3 Economic factors 8 2 5 3.787 .548 .692
4 Social factors 9 1 5 3.330 .442 .758
5 Institutional factors 9 3 5 4.180 .468 .705
In general, out of 53 factors, 24 factors have been ranked by planners as very important
with the mean value of more than 4.00. The three highest ranked decision-making factors
are ‘guidelines of DW management’ (mean = 4.568), ‘information update’ (mean =
4.459), ‘on-site sorting’ (mean = 4.405). Similarly, to the results of academics’
perspective analysis, planners were more attentive to on-site sorting of DW (mean value
= 4.405), ranking it as the most important factor in this category. In the category of
environmental factors, ‘promotion of 3R’ was ranked as the most important factor of
decision-making in urban redevelopment DW management (mean = 4.270). ‘Cost-
effectiveness of demolition plan’ was considered as the most important factor in the
economic category (mean = 4.351). ‘Preservation’ was identified as the most social
95
factor, indicating the goal of sustainability in urban redevelopment projects (mean =
4.162). In terms of institutional factors, ‘guidelines of DW management’ was the first of
the list in terms of its importance in improving decision-making of urban redevelopment
DW management (mean = 4.568).
4.5.3.3 Perspective of Consultants
As depicted in Appendix B4, 29 consultants participating in the survey rated the impact
level of decision-making factors for urban redevelopment DW management differently
from that of factors pinpointed by other stakeholders. Among the five categories of
decision-making factors, institutional factors were given the greatest significance in
decision-making urban redevelopment DW management, which reflected a similar
pattern to the perspectives of academics and planners (mean value = 4.050) (Table 4-5).
What followed were technical factors and environmental factors, with mean value of
3.9659 and 3.881, respectively. In contrast, social-cultural factors were quoted as the least
important of all (mean value = 3.341).
Table 4-5: Consultants’ ratings of decision-making factors of demolition waste management
No. Decision-making
factors Number of
factors
Rank Mean
Std. Deviation
Minimum Maximum Minimum Maximum
1 Technical factors 16 2 5 3.959 .506 .712
2 Environmental factors
11 2 5 3.881 .516 .677
3 Economic factors 8 2 5 3.737 .455 .693
4 Social factors 9 2 5 3.341 .484 .689
5 Institutional factors 9 3 5 4.050 .409 .711
In general, out of 53 factors, 18 factors were ranked by consultant group as very important
with a mean value is greater than 4.00. The following five decision-making factors were
ranked as the most important by consultants: ‘determining the procedure’ (mean =
4.5217), ‘on-site sorting’ (mean = 4.448), ‘willingness of stakeholders’ (mean = 4.379),
‘guidelines of DW management’ (mean = 4.379), ‘information update’ (mean = 4.379).
With respect to technical value, the results reveal that the consultants assigned the most
96 Chapter 4: Survey Study
important factor to ‘determining the procedure’ in this category (mean = 4.517), while in
the category of environmental factors, ‘the willingness of stakeholders’ was rated as the
most significant factor of decision-making in improving of urban redevelopment DW
management (mean = 4.379). ‘Cost-effectiveness of demolition plan’ was regarded as the
most important factor in the economic category (mean = 4.138). ‘Preservation’ was
identified as the most important social factor (mean = 4.345). With respect to institutional
performance, ‘guidelines of DW management’ was at the top of the list for its importance
in improving decision-making of urban redevelopment DW management (mean = 4.379).
On the other hand, ‘accomplishing government’s policy and strategy on DW
management’ was rated as the least important factor (mean = 3.759).
4.5.3.4 Perspective of Engineers
As indicated in the results summarised in Appendix B5, 57 engineers were asked to rate
the impact level of decision-making factors for urban redevelopment DW management.
Among the five categories of decision-making factors, engineers ranked institutional
factors as the most important in decision-making urban redevelopment DW management,
which is pretty similar to other groups’ perspective on this category (mean value = 4.175)
(Table 4-6). The technical factors’ value was ranked second with mean value of 4.010.
This is closely followed by economic performance with mean value of 3.974.
In general, 23 out of 53 factors have been ranked by engineers as very important
determinants with the mean value of more than 4.00. The three following decision-
making factors were ranked by engineers as the most important: ‘on-site sorting’ (mean
= 4.491), ‘information update’ (mean = 4.474), ‘determining the procedure’ (mean =
4.421).
With regards to technical factors, the results investigate that the engineers ranked ‘on-site
sorting’ as the most important factor in this category (mean = 4.491). This is followed by
two factors of ‘determining the procedure’ and ‘GIS-based model for DW management’,
while in the category of environmental factors, ‘promotion of 3R’ was rated as the most
important factor of decision-making in improving of urban redevelopment DW
management. ‘Cost estimation of waste transport’ was considered as the most important
factors in the economic category (mean = 4.386). ‘Preservation’ was also identified as the
most social important factor (mean = 4.351).
97
Table 4-6: Engineers’ rating of decision-making factors of demolition waste management
No. Decision-making
factors Number
of factors
Rank Mean
Std. Deviation
Minimum Maximum Minimum Maximum
1 Technical factors 16 2 5 4.010 .489 .714
2 Environmental factors
11 2 5 3.821 .495 .682
3 Economic factors 8 2 5 3.974 .549 .706
4 Social factors 9 1 5 3.480 .481 .774
5 Institutional factors 9 3 5 4.175 .483 .704
The factors of ‘effective feedback by community’ and ‘community monitoring’ were
ranked as not overly important decision-making factors in urban redevelopment DW
management, with the value of 2.667 each. Concerning institutional performance,
‘regular information update’ was rated as the most important factor in improving
decision-making of urban redevelopment DW management.
4.5.3.5 Perspective of Policy makers
As indicated in the results summarised in Appendix B6, 43 policy makers were invited to
take part in the survey to rate the impact level of decision-making factors for urban
redevelopment DW management. Among the five categories of decision-making factors,
institutional factors occupied the most important part in decision-making urban
redevelopment DW management, which is similar to other groups (mean value = 4.116)
(Table 4-7). The environmental factor value ranked second, with a mean value of 3.91,
while the policy maker group rated the technical performance less important than
economic performance, with mean values of 3.839 and 3.866, respectively.
In general, out of 53 factors, 23 factors have been ranked by policy makers as very
important, with mean value of more than 4.00. The three following decision-making
factors were ranked by engineers as the most important: ‘guidelines of DW management’
(mean = 4.524), ‘preservation’ (mean = 4.429), ‘promotion of 3R’ (mean = 4.381).
98 Chapter 4: Survey Study
Table 4-7: Policy Makers’ rating of decision-making factors of demolition waste management
No. Decision-making
factors Number
of factors
Rank Mean
Std. Deviation
Minimum Maximum Minimum Maximum
1 Technical factors 16 2 5 3.839 .391 .672
2 Environmental factors
11 1 5 3.909 .412 .777
3 Economic factors 8 2 5 3.866 .434 .698
4 Social factors 9 1 5 3.381 .495 .763
5 Institutional factors 9 3 5 4.116 .366 .657
Regarding technical value, the results show that the policy makers rated ‘determining the
procedure’ as the most important factor in this category (mean = 4.333). This is followed
by two factors of ‘on-site sorting’ and ‘landfill planning’, with the mean values of 4.310
and 4.143, respectively. Similarly, to the engineers’ perspectives, in the category of
environmental factors, ‘promotion of 3R’ was rated as the most important factor of
decision-making in improving urban redevelopment DW management. The two factors
of ‘disposal control fee’ and ‘balancing of greenhouse gas’ were rated as the not too
important factors influencing decision-making of urban redevelopment DW management,
with the mean values of 3.619 and 3.048, respectively. ‘Cost-effectiveness of demolition
plan’ was considered as the most important factor in the economic category (mean =
4.310) and ‘cost for waste disposal’ was the least important (mean = 3.190).
‘Preservation’ was also identified as the most social important factor (mean = 4.429). The
factor of ‘effective feedback by community’ was ranked as a not too important decision-
making factor in urban redevelopment DW management, with the value of 2.595. As for
institutional performance, ‘guidelines of DW management’ was ranked as the most
important factor in improving decision-making of urban redevelopment DW
management, whereas ‘stakeholder feedback role’ was considered as the least important
factor (mean = 3.738).
4.5.4 Comparison of rankings among five groups of respondents
The key stakeholders’ perspectives on decision-making factors influencing urban
redevelopment DW management varied, according to the function of their organisation,
99
their experience and their roles in DW management projects. A comparison of rankings
of decision-making factors among key stakeholders is illustrated in Table 4-8.
In regard to technical value, engineers (G4) were more concerning than four other groups:
academics (G1, planners (G2), consultants (G3), and policy makers (G5), with mean
value was greater than 4.0. Two factors of ‘on-site sorting’ and ‘determining the
procedures’ were ranked in the top ten of all decision-making factors by all groups, with
the mean values of 4.412 and 4.384, respectively. There were differences in rating the
most important technical factor: ‘on-site sorting’ that ranked in eighth place by policy
makers (G5) and ranked in top three important factor by four other groups: academics
(G1, planners (G2), consultants (G3), and engineers (G4). Meanwhile, all five groups
rated ‘estimation of DW’, ‘landfill planning’, ‘choosing demolition method’ and ‘training
of demolition techniques’ as the top 26 decision-making factors for urban redevelopment
DW management, with the mean values ranging from 4.032 to 4.213. In addition, all five
respondent groups had little awareness of ‘life cycle assessment’ in improving urban
redevelopment DW management, with mean value of 3.347.
The environmental performance category received more concerning by academics (G1)
and policy makers (G5) than three other groups: planners (G2), consultants (G3), and
engineers (G4), with mean value was greater than 3.9. It is understood that environmental
issues are placed as important criteria in developing C&D waste policy in Vietnam. The
factor of ‘promotion of 3R’ was ranked in the top ten of the given decision-making factors
by the groups: academics (G1), planners (G2), consultants (G3) and policy makers (G5),
while the engineers (G4) agreed that this factor occupied the fifteenth place (mean =
4.282). On the other hand, ‘balancing of greenhouse gas’ was ranked in the five least
important decision-making factors by all groups (mean = 2.986).
According to the mean score, ‘cost-effectiveness of demolition plan’ was rated to be the
most important economic factor for improving urban redevelopment DW management in
Vietnam, with mean value of 4.306. Followed by ‘cost estimation of waste transport’,
with the mean value of 4.176 and engineers (G4) showed higher concern on this factor
than four other stakeholder groups. Also, ‘estimation of demolition cost’ was rated as a
100 Chapter 4: Survey Study
very important decision-making factor, which was in the top 25 of the list, except for the
rating of the consultant group (mean = 4.042). The factor of ‘developing of disposal cost’
was deemed to be the least important economic factor by all five stakeholder groups,
which ranked forty-eighth out of 53 factors (mean =3.273).
In the social category, ‘preservation’ and ‘disturbance’ were rated by all groups as very
important social factors, with mean values of 4.310 and 4.111, respectively. However,
policy makers (G5) were more concerning on these two important factors than four other
groups: academics (G1), planners (G2), consultants (G3), and engineers (G4). On the
other hand, ‘community’s support’, ‘community’s role’, ‘community’s monitoring’ and
‘community’s feedback’ were ranked in the five least important social factors by all five
groups, with the mean ranging from 2.583 to 2.931. It is surprising to see that although
many social factors have been considered as significant factors in Vietnamese urban
redevelopment projects, the social factors were ranked relatively low in the survey.
With respect to institutional performance, the highest ranking was ‘guidelines of DW
management’ among three groups: academics (G1), planners (G2) and policy maker (G5)
(mean = 4.444). This ranking was slightly different with two other groups: consultants
(G3) and engineers (G4), which ranked fourth and sixth respectively. ‘Information
update’ was rated in the top five of the list, but received a relatively lower rating by the
academic group (mean = 4.398). The three factors of ‘stakeholders’ responsibility’,
‘stakeholder feedback role’ and ‘understanding DW management procedure’ were ranked
by all groups as very important decision-making factors, ranking in the top 17 of the list
(mean > 4.200). The rest of the four decision-making factors – ‘stakeholders’ involvement
in early stage’, ‘control meeting’, ‘accomplishing policy’ and ‘stakeholders’ feedback’ -
were ranked by all groups in the top 35 of the 53 decision-making factors.
Table 4-8: A comparison of ratings of decision-making factors for urban redevelopment DW management among key stakeholders
No. Decision-making factors Rank Mean Ranking according to professional groups
G1 G2 G3 G4 G5
I. Technical factors
101
No. Decision-making factors Rank Mean Ranking according to professional groups
G1 G2 G3 G4 G5
1 On-site sorting/separating of demolition waste
2 4.412 2 3 2 1 8
2 Determining the procedures of demolition waste management
4 4.384 3 9 1 3 6
3 Estimation of demolition waste 10 4.213 19 8 7 13 17
4 Planning the area for landfills 13 4.181 9 6 10 21 15
5 Choosing demolition method (reduction of demolition time, cost and waste)
15 4.130 21 17 19 11 18
6 Planning the area for sorting platform 21 4.051 13 22 15 23 26
7 Training the human resources in demolition techniques
23 4.032 25 23 23 14 24
8 Planning storage space for recyclable materials
24 4.028 24 15 11 35 22
9 The use of GIS-based modeling demolition waste management
27 3.889 20 45 32 10 42
10 Sufficient equipment for demolition project
33 3.815 36 28 26 30 36
11 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
35 3.806 28 43 25 27 37
12 Identifying risks associate with building’s demolition
37 3.787 38 26 40 38 27
13 Managing time of the duration of demolition
39 3.741 41 31 41 37 32
14 The use of BIM-based in demolition waste management
41 3.713 40 39 21 34 45
15 Skilled personnel are available for conducting demolition project
46 3.380 43 48 44 46 47
16 Life cycle assessment 47 3.347 48 46 47 47 46
II. Environmental factors
1 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
8 4.282 5 10 9 15 3
2 The willingness of demolition waste management by stakeholders
12 4.190 6 12 3 22 21
3 Understanding the uniqueness of demolition waste before demolition stage
16 4.125 16 11 8 31 19
4 Training the human resources in the integrated waste management
17 4.120 11 25 36 16 7
102 Chapter 4: Survey Study
No. Decision-making factors Rank Mean Ranking according to professional groups
G1 G2 G3 G4 G5
5 Identifying rate of waste recovery 19 4.069 14 21 18 29 16
6 Environmental Impact Assessment 20 4.056 17 24 13 28 20
7 Understanding environmental issues of demolition waste generation
34 3.806 26 32 24 39 39
8 The use of recycled materials 38 3.778 32 36 38 40 28
9 Understanding of hazardous demolition waste
40 3.722 33 38 43 41 40
10 Disposal control (fee, landfill sites) 45 3.579 46 44 42 44 41
11 Balancing of greenhouse gases 49 2.986 49 51 49 51 49
III. Economic factors
1 Cost- effective demolition plans 7 4.306 4 5 16 8 9
2 Cost estimation of waste transport 14 4.176 18 18 27 5 12
3 Estimation of demolition cost 22 4.042 22 27 22 20 13
4 Cost estimation of waste treatment 26 3.912 37 34 35 18 23
5 Reducing cost of demolition waste transportation
30 3.856 29 33 29 26 33
6 Developing of recycling market 32 3.819 27 30 37 36 34
7 Saving the amount of energy use (fuels, electricity and others)
42 3.616 39 42 45 42 44
8 Developing an appropriate cost for waste disposal
48 3.273 47 47 48 48 48
IV. Social factors
1 Preservation of natural resources, cultural and heritage
6 4.310 8 14 6 7 2
2 Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
18 4.111 23 16 20 17 11
3 Reduction of risks, accidences for workers on demolition site
36 3.792 44 37 33 19 31
4 Job creation due to demolition waste management
43 3.616 42 40 46 43 38
5
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
44 3.593 45 41 39 45 43
6 Community’s supportive actions before demolition stage
50 2.963 50 49 50 49 51
103
No. Decision-making factors Rank Mean Ranking according to professional groups
G1 G2 G3 G4 G5
7 The role of community in decision-making process
51 2.931 51 50 51 50 50
8 Community’s monitoring of environmental conditions during demolition stage
52 2.611 52 52 53 53 52
9 Effective feedback by community 53 2.583 53 53 52 52 53
V. Institutional factors
1 Providing guidelines of demolition waste management plan
1 4.444 1 1 4 6 1
2 Regular information update 3 4.398 7 2 5 2 5
3 Understanding of responsibilities by all stakeholders
5 4.329 10 4 14 4 4
4 The roles of key stakeholders in monitoring and feedback
9 4.259 12 7 12 9 10
5 Understanding of demolition waste management procedures
11 4.199 15 13 17 12 14
6 Involvement of key stakeholders in early stage
25 3.921 34 20 28 24 25
7 Demolition project control meeting 28 3.889 35 19 30 25 30
8 Accomplishing government’s policy and strategy on demolition waste management
29 3.856 31 29 34 32 29
9 Effective feedback by stakeholders 31 3.824 30 35 31 33 35
Note: G1- Academic; G2 – Planner; G3- Consultant; G4- Engineer; G5 – Policy maker
4.5.5 Critical decision-making factors for demolition waste management in Vietnamese urban redevelopment projects
In order to analyse the factors with relatively high mean values, which reflect a higher
level of impact on decision-making, a criterion is set in this research for the exploration
of those critical factors. In selecting critical decision-making factors, the factor with mean
values that is greater than 4.0 is classified as the critical decision-making factor in
influencing DW management. Based on 53 decision-making factors identified in the
literature review, 24 factors were ranked by respondents as ‘important’ and ‘very
important’, receiving a mean value of more than 4.0. Table 4-9 shows the level of
importance of the 24 critical decision-making factors for urban redevelopment DW
management, based on the questionnaire results.
104 Chapter 4: Survey Study
The research findings reveal that the factor ‘Guidelines of DW management’ was ranked
at the first place among all important factors (mean value: 4.444). This finding echoes the
notion that ‘guidelines of DW management’ is the most important factor in DW
management (del Río Merino, et al., 2009). Furthermore, as expected, ‘on-site sorting of
DW’ was ranked as the second critical factor influencing DW management in urban
redevelopment projects (mean value: 4.412). Poon, et al. (2001) state that separation of
C&D waste onsite offers several benefits of waste treatment, such as less effort required
and better classification of inert and non-inert wastes in comparison with waste sorting
centrally conducted at a designated area on-site or off-site.
In the institutional factor group, the ‘Information update’ was ranked at the third place
(mean value: 4.398). This result is consistent with the finding by Kleemann, et al. (2014),
who recommended that providing the information of building materials prior to
demolition work is a prerequisite for the efficient recycling of DW. If urban
redevelopment projects’ participants access accurate and updated DW information when
making decisions, the DW management will be more efficient, particularly in reducing
and recycling waste.
It is also worth noting, that out of 16 technical factors in this research, 7 factors received
a high rating from the respondents, such as ‘determining the procedure of DW
management’, ‘landfill planning’, ‘Estimation of DW’, ‘choosing demolition methods’,
‘training of demolition techniques’, ‘sorting platform planning’ and ‘recycled materials
storage planning’. This finding echoes the results of several studies on C&D waste
management (Lu & Yuan, 2010; Lu, et al., 2011; Yuan, et al., 2011).
It should be noted that among 11 environmental decision-making factors, 6 factors were
ranked as important in DW management in urban redevelopment projects, which are
‘promotion of 3R in DW management’, ‘the willingness of stakeholders’, ‘the uniqueness
of DW’, ‘rate of recovery’, ‘environmental impact assessment’ and ‘training of DW
management’. This result reflects that respondents have perceived the environmental
impacts caused by DW.
Table 4-9: Factors rated by the respondents as important and very important (mean >4)
No. Decision-making Factors Mean Std.
Deviation Rank
1 Providing guidelines of demolition waste management plan
4.444 .498 1
105
No. Decision-making Factors Mean Std.
Deviation Rank
2 On-site sorting/separating of demolition waste 4.412 .521 2
3 Regular information update 4.398 .553 3
4 Determining the procedures of demolition waste management
4.384 .524 4
5 Understanding of responsibilities by all stakeholders 4.329 .660 5
6 Preservation of natural resources, cultural and heritage
4.310 .511 6
7 Cost- effective demolition plans 4.306 .646 7
8 Promotion of 3R in demolition waste management 4.282 .617 8
9 The roles of key stakeholders in monitoring and feedback
4.259 .680 9
10 Estimation of demolition waste 4.213 .648 10
11 Understanding of demolition waste management procedures
4.199 .475 11
12 The willingness of demolition waste management by stakeholders
4.190 .665 12
13 Planning the area for landfills 4.181 .610 13
14 Cost estimation of waste transport 4.176 .645 14
15 Choosing demolition methods 4.150 .588 15
16 Understanding the uniqueness of demolition waste before demolition stage
4.125 .585 16
17 Training the human resources in the integrated waste management
4.120 .582 17
18 Reduction of community disturbance during demolition stage
4.111 .732 18
19 Identifying rate of waste recovery 4.069 .594 19
20 Environmental Impact Assessment 4.056 .607 20
21 Planning the area for sorting platform 4.051 .634 21
22 Estimation of demolition cost 4.042 .612 22
23 Training the human resources in demolition techniques
4.032 .685 23
24 Planning storage space for recyclable materials 4.028 .510 24
The respondents’ perspective regarding the importance of stakeholders’ awareness and
training in improving DW management resonates with the study of Yuan, et al. (2011)
and Rao and Zhang (2015). In addition, it is found that identifying the environmental
106 Chapter 4: Survey Study
issues and the DW characteristics, as well as DW volume prior to demolition work can
help decision makers plan effective DW management in urban redevelopment projects.
(Marzouk & Azab, 2014; Tam, 2008).
It is surprising to realise that although many social factors have been reflected as
important in urban redevelopment projects (Roussat, et al., 2009b; Yau & Ling Chan,
2008; Zheng, et al., 2014), the social decision-making factors were ranked fairly low in
the research survey in terms of their influences on DW management in urban
redevelopment projects. Only two of eight social factors were ranked as important, which
are ‘reduction of community disturbance during demolition stage’ and ‘preservation of
natural resources, cultural and heritage’ with mean values of 4.111 and 4.310
respectively. This result may be due to a lower importance placed on the role of
community in DW management in Vietnam in comparison to the delivery of urban
redevelopment projects.
According to Spangenberg (2004), the institutional performance is one of the four major
aspects in achieving sustainability. In line with the ‘providing guidelines’ factor, four
other factors of this category were ranked at top-ten critical factors, such as ‘regular
information update’, ‘stakeholders’ responsibility’, ‘stakeholders’ roles in monitoring
and feedback’ and ‘understanding DW management procedures’. These results support
the stakeholders’ perspective that institutional factors play a vital role in influencing DW
management in urban redevelopment projects.
This research uses Kendall’s coefficient of concordance to evaluate the extent to which
the participants scored the 24 decision-making factors upon a similar order. When the
concordance coefficient value closes to 1, the factors’ rankings are relatively identical.
By contrast, when the concordance coefficient value closes to 0, the factors’ ratings are
different (Yeung, Chan, Chan, & Li, 2007). In this research, the coefficient value was
0.063, greater than the recommended threshold of 0.05 as shown in Table 4-10, therefore,
it is concluded that the participants had statistically indifferent preferences when they
scored decision-making factors. The significant differences of respondents’ perspectives
in rating critical factors are further detected in the next sections.
Table 4-10: Kendall’s coefficient of concordance
N 216
107
Kendall's Wa .063
Chi-Square 313.333
df 23
Asymp. Sig. 0.001
4.5.6 Agreement on critical decision-making factors
The decision-making framework of urban redevelopment DW management is developed
based on the agreement of ranking decision-making factors by five groups of respondents.
In order to finalise the critical decision-making factors, the agreement should be analysed
in detail to gain a clear picture of the inter-relationship among five respondent groups.
Kruskal-Wallis was tested to identify whether there are significant differences in the
respondents’ rating of the level of importance.
This test showed that there was no significant difference in ranking of decision-making
factors between five groups, as shown in Table 4-11. It is indicated that five groups of
respondents had a consensus regarding the perceptions and expectation of urban
redevelopment DW management. In contrast, three critical factors, namely, ‘cost
estimation of waste transport’, ‘training of DW management’, and ‘the uniqueness of
DW’ have slight differences across five groups with p-value less than 0.05.
The significant differences between five respondent groups in Kruskal-Wallis test were
further validated by a correlational parametric test, which was one-way ANOVA test. The
results are shown in Table 4.12. These results were consistent with the results from
Kruskal-Wallis test. There were significant differences between five groups in the ranking
of three critical factors, namely, ‘cost estimation of waste transport’, ‘training of DW
management’, and ‘the uniqueness of DW’.
109
Table 4-11: Comparison of rating of critical decision-making factors for improving urban redevelopment DW management among key stakeholders
No. Decision-making Factors Mean Std.
Deviation Rank G1 G2 G3 G4 G5
Kruskal-Wallis statistics (X2)
P-Value
1 Providing guidelines of demolition waste management plan
4.444 .498 1 37.98 41.18 37.60 36.07 40.38 5.371 .251
2 On-site sorting/separating of demolition waste
4.412 .521 2 37.62 38.57 39.57 38.63 36.67 3.503 .477
3 Regular information update 4.398 .553 3 35.63 39.36 38.10 38.16 37.91 2.764 .598
4 Determining the procedures of demolition waste management
4.384 .524 4 37.22 36.54 40.67 37.39 37.16 4.306 .366
5 Understanding of responsibilities by all stakeholders
4.329 .660 5 34.01 37.85 33.64 36.57 37.63 5.124 .275
6 Preservation of natural resources, cultural and heritage
4.310 .511 6 35.05 33.68 37.07 35.45 38.63 5.535 .237
7 Cost- effective demolition plan 4.306 .646 7 36.13 37.08 33.03 35.35 36.47 2.680 .613
8 Promotion of 3R in demolition waste management
4.282 .617 8 35.71 35.81 35.57 32.80 37.59 2.800 .592
9 The roles of key stakeholders in monitoring and feedback
4.259 .680 9 33.24 36.31 33.88 35.04 35.27 1.869 .760
10 Estimation of demolition waste 4.213 .648 10 31.53 36.30 36.22 33.87 32.45 4.040 .401
11 Understanding of demolition waste management procedures
4.199 .475 11 32.93 34.69 32.84 33.92 34.16 2.469 .650
12 The willingness of demolition waste management by stakeholders
4.190 .665 12 35.26 34.26 37.48 29.39 31.74 8.087 .088
110 Chapter 4: Survey Study
No. Decision-making Factors Mean Std.
Deviation Rank G1 G2 G3 G4 G5
Kruskal-Wallis statistics (X2)
P-Value
13 Planning the area for landfills 4.181 .610 13 34.05 36.28 34.43 28.90 33.08 6.659 .155
14 Cost estimation of waste transport 4.176 .645 14 31.99 31.85 27.43 36.24 34.97 13.649 .009*
15 Choosing demolition method 4.150 .588 15 31.64 32.58 29.40 33.96 32.57 5.430 .246
16 Understanding the uniqueness of demolition waste before demolition stage
4.125 .585 16 32.61 35.61 36.66 26.70 32.27 12.149 .016*
17 Training the human resources in the integrated waste management
4.120 .582 17 33.64 29.64 25.53 32.65 36.23 19.292 .001*
18 Reduction of community disturbance during demolition stage
4.111 .732 18 29.82 32.32 29.52 31.46 34.48 3.329 .504
19 Identifying rate of waste recovery 4.069 .594 19 33.11 31.05 31.67 27.39 33.23 5.146 .273
20 Environmental Impact Assessment 4.056 .607 20 32.29 30.82 33.74 27.15 31.78 5.202 .267
21 Planning the area for sorting platform 4.051 .634 21 33.04 30.86 32.53 28.75 28.02 5.228 .265
22 Estimation of demolition cost 4.042 .612 22 30.84 27.43 28.45 30.28 34.08 8.479 .076
23 Training the human resources in demolition techniques
4.032 .685 23 28.39 31.03 28.79 33.04 28.95 6.827 .145
24 Planning storage space for recyclable materials
4.028 .510 24 28.67 32.74 34.21 26.12 31.91 9.152 .057
Note: difference for Kruskal-Walllis test = 4
G1- Academic; G2 – Planner; G3- Consultant; G4- Engineer; G5 – Policy maker
P< 0.05: The mean difference among groups is statistically significant at the .05 level
111
Table 4-12: One-Way ANOVA statistic for log-transformed data of critical decision-making factors for improving urban redevelopment DW management
No. Factors Mean Std
Deviation Mean Square
Sig. (p-value)
1 Providing guidelines of demolition waste management plan
.645 .0483 .003 .252
2 On-site sorting/separating of demolition waste
.642 .0516 .002 .568
3 Regular information update .640 .0561 .003 .437
4 Determining the procedures of demolition waste management
.639 .0523 .002 .543
5 Understanding of responsibilities by all stakeholders
.631 .0703 .004 .479
6 Preservation of natural resources, cultural and heritage
.631 .0514 .005 .125
7 Cost- effective demolition plan .629 .0687 .003 .712
8 Promotion of 3R in demolition waste management
.627 .0652 .002 .799
9 The roles of key stakeholders in monitoring and feedback
.623 .0732 .002 .836
10 Estimation of demolition waste .620 .0697 .004 .532
11 Understanding of demolition waste management procedures
.619 .0485 .001 .688
12 The willingness of demolition waste management by stakeholders
.616 .0732 .008 .186
13 Planning the area for landfills .616 .0655 .007 .144
14 Cost estimation of waste transport .615 .0697 .018 0.00*
15 Choosing demolition method .611 .0636 .005 .258
16 Understanding the uniqueness of demolition waste before demolition stage
.611 .0633 .014 0.00*
17 Training the human resources in the integrated waste management
.610 .0630 .020 0.00*
18 Reduction of community disturbance during demolition stage
.607 .0806 .005 .597
19 Identifying rate of waste recovery .605 .0664 .007 .176
20 Environmental Impact Assessment .603 .0681 .005 .416
21 Planning the area for sorting platform .602 .0700 .005 .397
22 Estimation of demolition cost .601 .0688 .009 .101
23 Training the human resources in demolition techniques
.599 .0780 .010 .145
24 Planning storage space for recyclable materials
.597 .0563 .007 .061
Note: difference for One-Way ANOVA test = 4 G1- Academic; G2 – Planner; G3- Consultant; G4- Engineer; G5 – Policy maker P< 0.05: The mean difference among groups is statistically significant at the .05 level
112 Chapter 4: Survey Study
Based on the results from both nonparametric and parametric analysis, the significant
differences of three critical factors were further detected by the Benjamini-Hochberg
procedure (presented in Chapter 3). This procedure was used to compute p-values
corrected for multiple comparisons in nonparametric Kruskal Wallis test, which was p-
corrected. The total of 24 sets of p-values was adjusted for multiple comparisons, which
corresponded to 24 critical factors as presented in Table 4-13.
Table 4-13: Adjusted differences based on p-value generated in Kruskal-Wallis test
No. Critical factors Mean Std.
Deviation Rank
p-value
p-rank
p-corrected
1 Training in the integrated waste management
4.120 .582 17 .001 1 0.010*
2 Cost estimation of waste transport 4.176 .645 14 .009 2 0.021*
3 Understanding the uniqueness of demolition waste
4.125 .585 16 .016 3 0.031*
4 Planning storage space for recyclable materials
4.028 .510 24 .057 4 0.042
5 Estimation of demolition cost 4.042 .612 22 .076 5 0.052
6 The willingness of demolition waste management by stakeholders
4.190 .665 12 .088 6 0.063
7 Training in demolition techniques 4.032 .685 23 .145 7 0.073
8 Planning the area for landfills 4.181 .610 13 .155 8 0.083
9 Preservation of natural resources, cultural and heritage
4.310 .511 6 .237 9 0.094
10 Choosing demolition method 4.150 .588 15 .246 10 0.104
11 Providing guidelines of demolition waste management plan
4.444 .498 1 .251 11 0.115
12 Planning the area for sorting platform 4.051 .634 21 .265 12 0.125
13 Environmental Impact Assessment 4.056 .607 20 .267 13 0.135
14 Identifying rate of waste recovery 4.069 .594 19 .273 14 0.146
15 Understanding of responsibilities by all stakeholders
4.329 .660 5 .275 15 0.156
16 Determining the procedures of demolition waste management
4.384 .524 4 .366 16 0.167
17 Estimation of demolition waste 4.213 .648 10 .401 17 0.177
18 On-site sorting/separating of demolition waste
4.412 .521 2 .477 18 0.188
19 Reduction of community disturbance during demolition
4.111 .732 18 .504 19 0.198
20 Promotion of 3R in demolition waste management
4.282 .617 8 .592 20 0.208
21 Regular information update 4.398 .553 3 .598 21 0.219 22 Cost- effective demolition plan 4.306 .646 7 .613 22 0.229
23 Understanding of demolition waste management procedures
4.199 .475 11 .650 23 0.240
24 The roles of key stakeholders in monitoring and feedback
4.259 .680 9 .760 24 0.250
113
In this test, p-corrected = where i is the rank of ascending input p-values (p-rank); m
is the total number of tests (m=24); and Q is critical value for a false discovery rate
(q=0.25). The significant difference that was detected when the largest of p-value is less
than the p-corrected was ‘the uniqueness of DW’ factor, where the p-value (0.016) was
less than p-corrected (0.031). Thus, the first three tests were significant because the p-
value was less than that of ‘the uniqueness of DW’ factor and also less than p-corrected.
Accordingly, the three critical factors that were deemed truly significant, namely,
‘training of DW management’, ‘cost estimation of waste transport’, and ‘the uniqueness
of DW’ with p-corrected, were 0.010, 0.021, and 0.031 respectively.
These critical factors further detected the differences between two independent groups by
using the nonparametric test, which was Mann-Whitney test (Table 4-14). The test
revealed that there were significant differences between consultants (G3) and two other
groups: engineers (G4) and policy makers (G5) as regards the factor of ‘training of DW
management’. On the other hand, consultants are deemed to have more attention to this
critical factor (training of DW management) than academics. In addition, the planner
group was also identified to have a different perspective compared to the policy maker
group in training of DW management. This may be due to the fact that engineers and
policy makers considered the need of training in DW management, while the other three
groups (academics, planners, and consultants) thought that the local authority and the
government should provide contractors with the courses of DW management knowledge
often.
The Mann-Whitney test also divulged that planners (G2) in the research's respondents
had different perspectives on the significance level of the ‘cost estimation of waste
transport’ compared to the engineers (G4). This is possible because planners are not much
concerned about the cost of waste transport. In addition, significant differences in the
rating factor of ‘cost estimation of waste transport’ also existed between consultants (G3)
and two other stakeholder groups: engineers (G4) and policy makers (G5). It seems that
consultants worry less about ‘cost estimation of waste transport’ as they mainly get
involved in the environmental issues.
114 Chapter 4: Survey Study
The rating of ‘the uniqueness of DW’ also revealed the significant differences between
engineers (G4) and three other stakeholder groups: academics (G1), planners (G2) and
consultants (G3). It is believed that engineers tend to focus more on technical factors
rather than understanding the characteristics of DW. This might be related to the
insufficient knowledge of DW management, in which all stakeholders involved in DW
management process need to be equipped.
Table 4-14: Probability values in Mann-Whitney test on three critical factors
Comparison between groups of stakeholders
Mann-Whitney test results (p-value)
Training the human resources in the integrated waste management
Cost estimation of waste transport
Understanding the uniqueness of demolition waste before demolition stage
G1/G2 0.062 0.642 0.356
G1/G3 .001* 0.092 0.23
G1/G4 0.994 0.062 .032*
G1/G5 0.289 0.524 0.84
G2/G3 0.126 0.168 0.672
G2/G4 0.063 .017* .004*
G2/G5 .012* 0.242 0.341
G3/G4 .001* .001* .004*
G3/G5 .001* .019* 0.245
Note: * The probability value is significant at 0.05 level (2-tailed) G1- Academics; G2 - Planners; G3- Consultants; G4- Engineers; G5 - Policy makers
The Mann-Whitney test results above suggested that the three critical factors can be
statistically regarded as important to urban redevelopment DW management. The
respondents with different backgrounds and responsibilities may have different
perceptions about the factors affecting decision-making of urban redevelopment DW
management. Hence, the factors identified and rated as critical will act as a sound
foundation upon which the decision-making framework for urban redevelopment DW
management can be based.
The findings from Mann-Whitney test were further validated by a correlational
parametric test, which was 2-sample t test. The results are shown in Table 4.15. These
results were consistent with the results from Mann-Whitney test.
115
Table 4-15: Probability values in 2-sample t test on three critical factors
Comparison between groups of
stakeholders
2-sample t test results (p-value)
Training the human resources in the integrated waste management
Cost estimation of waste transport
Understanding the uniqueness of demolition waste before demolition stage
G1/G2 .055 .782 .246
G1/G3 .001* .093 .226
G1/G4 .955 .059 .025*
G1/G5 .390 .381 .652
G2/G3 .125 .145 .811
G2/G4 .060 .018* .002*
G2/G5 .015* .233 .165
G3/G4 .001* .000* .004*
G3/G5 .000* .011* .170
G4/G5 .360 .232 .134
Note: * The probability value is significant at 0.05 level (2-tailed) G1- Academics; G2 - Planners; G3- Consultants; G4- Engineers; G5 - Policy makers
However, the significant differences of the above three critical factors were further
detected by the Benjamini-Hochberg procedure. This made it possible to adjust the
different perspectives about the three critical factors mentioned above, across five groups
of stakeholders. Three sets of p-values of the three stated critical factors in Mann Whitney
test were adjusted for multiple comparisons and each set comprised of 10 tests
corresponding to each pair in five stakeholder groups. Table 4-16 presents the results of
adjusting p-values generated in the Mann-Whitney test by the Benjamini-Hochberg
procedure.
In this test, p-corrected = where i is the rank of ascending input p-values (p-rank); m
is the total number of tests (m=10); and Q is critical value for a false discovery rate
(q=0.25). Regarding the factor of ‘training of DW management’, after adjusting p-values,
using the Benjamini-Hochberg correction, the different perspectives between planners
(G2) and policy makers (G5), as well as the differences between consultants (G3) and
two other groups: engineers (G4) and policy makers (G5) were verified as discussed in
the previous section.
116 Chapter 4: Survey Study
Table 4-16: Adjusted differences based on p-value generated in Mann-Whitney test
No Comparison
between groups of stakeholders
1. Training the human resources in the integrated waste
management
2. Cost estimation of waste transport
3. Understanding the uniqueness of demolition waste before
demolition stage
p-value p-rank p-corrected p-value p-rank p-corrected p-value p-rank p-corrected
1 G1/G2 .062 5 .125** .642 10 .250 .356 8 .200
2 G1/G3 .001* 2 .050** .092 5 .125** .230 5 .125
3 G1/G4 .994 10 .250 .062 4 .100** .032* 3 .075**
4 G1/G5 .289 9 .225 .524 9 .225 .840 10 .250
5 G2/G3 .126 7 .175** .168 6 .150 .672 9 .225
6 G2/G4 .063 6 .150** .017* 2 .050** .004* 1 .025**
7 G2/G5 .012* 4 .100** .242 8 .200 .341 7 .175
8 G3/G4 .001* 3 .075** .001* 1 .025** .004* 2 .050**
9 G3/G5 .000* 1 .025** .019* 3 .075** .245 6 .150
10 G4/G5 .283 8 .200 .200 7 .175 .111 4 .100
Note: * The probability value is significant at 0.05 level (2-tailed)
** The adjusted probability is significant at p-value <p-corrected
G1- Academics; G2 - Planners; G3- Consultants; G4- Engineers; G5 - Policy makers
117
In addition, the significant differences that were revealed between academics (G1) and
two other groups, planners (G2) and consultants (G3) with p-corrected were 0.125 and
0.050 respectively, and between planners (G2) and two other groups, consultants (G3)
and engineers (G4) with p-corrected were 0.175 and 0.150 respectively. There is a
possibility that academics and planners are involved in the early stage of DW
management process, which is contrary to the other groups playing their roles in the
demolition stage.
Similarly, the significant differences between academics (G1) and two other groups,
consultants (G3) and engineers (G4) as regards to the factor of ‘cost estimation of
waste transport’ that were further detected significant with p-corrected were 0.125 and
0.100 respectively. It is believed that academics have a low level of concern about
cost-effectiveness compared to consultants and engineers, who directly work with the
DW management plan. On the other hand, the p-corrected values from sets of ‘the
uniqueness of DW’ were verified with the results of the Mann-Whitney test, which
was discussed in the previous section.
The above three critical factors (training of waste management, cost estimation of
waste transport, and the uniqueness of DW) existed the significant differences might
all contribute to the latent conflicts hindering the stakeholders’ interactions in urban
redevelopment DW management. These are verified in the interview study and should
be further addressed in future research.
4.6 MAIN FINDINGS OF THE QUESTIONNAIRE SURVEY
4.6.1 Main findings
The questionnaire survey results of this research highlight the following points with
regard to improving decision-making of urban redevelopment DW management:
The respondents selected 24 out of 53 decision-making factors as the critical decision-
making factors, which are presented in Table 4.9.
The critical factors represent a set of decision-making factors that are important in
improving urban redevelopment DW management. These factors have been voted
based on five categories, namely, technical performance, environmental performance,
118 Chapter 4: Survey Study
economic performance, social performance, and institutional performance, which are
all sustainable aspects.
The decision-making framework formulated on the basis of the critical factors will
assist decision makers in making the right decisions to improve urban redevelopment
DW management practices.
There were no additional factors identified by the respondents, which proved that the
questionnaire comprehensively encompassed relevant factors identified from reviews
of the previous literature.
According to the respondents’ background and roles, there are similarities among the
five groups of respondents in the ratings of the level of importance of potential
decision-making factors. The top five ranked decision-making factors received a
perception consensus of all groups in ‘guidelines of DW management’, ‘on-site
sorting’, ‘information update’, ‘determining the procedure’, and ‘stakeholders’
responsibility’. On the other hand, there were some differences in the ranking of the
level of importance for decision-making factors. This could be seen in the rating of
factors in the two categories of economic performance (‘cost estimation of waste
transport’), and environmental performance (‘the uniqueness of DW’ and ‘training of
waste management’). These factors were verified in the next chapter, interview study.
The performances of technique, environmental and institutional, significantly
influence the decision-making of urban redevelopment DW management, with 19 out
of 24 critical factors identified.
4.6.2 Revised conceptual framework
Based on the questionnaire survey results and the findings, the conceptual decision-
making framework is developed, as shown in figure 4-2. The critical decision-making
factors are grouped into five categories: technical, environmental, economic, social
and institutional. This conceptual framework was further investigated through the
interviews. In addition, a GIS-based model is developed based on case study, to
establish the decision support system for the decision-making framework.
119
4.7 SUMMARY
This chapter detailed the results and findings of the survey study. The findings in this
chapter answered the first research question: What are the key decision-making factors
influencing demolition waste management in Vietnamese urban redevelopment
projects?
The survey identified 24 decision-making factors based on their importance assesses
by five groups of stakeholders. The findings show that the technical, environmental
and institutional performances significantly influence the decision-making process of
urban redevelopment DW management. Based on the current DW management
performance in Vietnamese urban redevelopment projects, the 24 critical decision-
making factors were encapsulated into a revised conceptual framework. These critical
decision-making factors were further discussed by the interviewees in the interview
Choosing demolition method
DW management procedures
Waste classification and estimation
Planning for landfill, sorting area, and storage
Training
Stakeholder awareness
The uniqueness of DW
3R strategies and recovery
Environmental Impact Assessment
Cost-effectiveness plan
Cost estimation for demolition and DW transport
Preservation
Reduction of disturbance
Best practice guidelines
Stakeholder engagement
Information and communication
Technical
Environmental
Influencing
factors of
demolition waste
management
decision-making
in Vietnamese
urban
redevelopment
projects
Economic
Social
Institutional
Figure 4-2: Revised conceptual framework for improving decision-making in DW management for urban redevelopment projects
120 Chapter 4: Survey Study
study as presented in Chapter 5. Subsequently, the conceptual framework was also
refined in the interview stage.
121
Chapter 5: Interview
5.1 INTRODUCTION
The questionnaire survey results have refined the conceptual decision-making
framework for improving urban redevelopment DW management in Vietnam, which
has been clearly explained in the previous chapter. The conceptual decision-making
framework was then introduced and validated by key stakeholders in the stage of semi-
structured interviews and also involved the identification of action plans in response
to the revised decision-making framework. The other purpose of the interviews was to
identify the current practice, problems, and action plans regarding the critical decision-
making factors in improving urban redevelopment DW management in Vietnam. This
chapter first outlines the participant selection process and the participants’
background. It subsequently explains the use of interview instruments in the research.
Then, an explanation of how the data collected was interpreted and analysed is
described before the interview discussions are presented. This is followed by the main
findings of the interview study and finally, the interview results and findings are
summarised in the last section of the chapter.
5.2 INTERVIEWEES’ SELECTION AND THEIR BACKGROUND
5.2.1 Selection of interviewees
The selection of participants in the interview was conducted in order to obtain a good
representation of the organisations with regard to urban redevelopment DW
management in the three main cities in Vietnam, namely Hanoi, Hai Phong, and Ho
Chi Minh cities. In addition, the interviewees were selected based on their,
background, experience, current positions and availability for the interview, which
described in Chapter 3, Section 3.6.3. This is to ensure that the objectives of the
interviews can be achieved. Based on the questionnaire survey, 29 survey respondents
who expressed interest in participating in the interview were approached. Of these 29
participants, 22 interviewees were selected to participate in the interview, comprising
four academics, three planners, three consultants, six engineers, and six policy makers.
A total of 22 interviews were conducted from April to June 2017.
122 Chapter 5: Interview
Similar to the questionnaire participants, the interviewees represented five key
stakeholder groups. Among the 22 interviewees, four were researchers, three were
planners, three were consultants, six were engineers and six were policy makers. Out
of 22 respondents, 12 held relatively high positions in their organisations. Most of the
respondents were from Hanoi. This is because Hanoi is leading in urban
redevelopment activities in Vietnam and the organisations related to urban
redevelopment DW management are mainly located in Hanoi. The statistical
breakdown of interviewees can be seen in Table 5-1.
Table 5-1: Statistical Breakdown of Interviewees
Interviewee type Number of interviewees
By profession Academic 4
Planner 3
Consultant 3
Engineer 6
Policy maker 6
By executive level Manager/Director 12
Other 10
By geographical spread Hanoi 15
Hai Phong 3
Ho Chi Minh City 4
5.2.2 Interviewee background
In order to achieve the interview’s objective, the selected interviewees need to have
the capability to provide robust knowledge and extensive experience regarding urban
redevelopment DW management in Vietnam. In addition, their organisations play an
important role in the decision-making process in related fields. A summary of the
interviewees’ profile is presented in Table 5-2. All of the interviewees had more than
10 years of experience. Most of them held key positions in the projects such as
directors, decision makers, on-site managers, and environment managers. Thus, the
information, insights, and suggestions provided by the interviewees would be reliable
to help better interpret the critical decision-making factors from the questionnaire
survey.
123
Table 5-2: Interviewee Profiles
Respondent Organisation characteristic
Role in Project Experience (years)
Interview mode
R1 Government Director Decision maker 22 Face to face
R2 Government Decision maker 15 Face to face
R3 Government Associate Director/planner
18 Face to face
R4 Waste management contractor
Engineering Manager 10 Telephone
R5 Government Decision Maker 13 Face to face
R6 Government Associate Director/Planner
15 Face to face
R7 Local Authority Project Engineering manager
20 Face to face
R8 Academic Project Consultant 20 Face to face
R9 Academic Environmental Expert/Consultant
10 Face to face
R10 Construction contractor
On-site manager 17 Telephone
R11 Academic Technical Expert/Consultant
12 Face to face
R12 Local Authority Planner 15 Face to face
R13 Government Academic 15 Face to face
R14 Government Academic 14 Face to face
R15 Government Environment Manager/Academic
17 Telephone
R16 Construction contractor
On-site Manager 17 Telephone
R17 Local Authority Policy Maker 15 Telephone
R18 Academic Waste management Expert
20 Face to face
R19 Government Engineering Manager/Policy maker
21 Telephone
R20 Local Authority Senior Manager/Policy maker
20 Telephone
R21 Construction contractor
On-site Manager 17 Face to face
R22 Waste management contractor
Engineering Manager 18 Telephone
124 Chapter 5: Interview
5.3 INTERVIEW INSTRUMENTS
As discussed, the survey results that were drawn from in-depth interviews helped
interpret and elaborate on the critical decision-making factors. Before executing the
interview section, several processes are involved. Each interviewee was contacted
through email or by phone for an appointment. Interviewees were electronically
provided with the following information for better preparation.
A cover letter (Appendix C)
Information consent form for QUT research project
Interview question sheet (Table 5-3)
Conceptual framework (Figure 4-2)
Due to restrictions of locality and budget, two options for conducting the interviews
were chosen: either face to face or over the telephone. Out of 15 interviewees, 14 from
Hanoi participated in the face-to-face interviews. Eight interviews were conducted by
phone, with one interviewee from Hanoi, four interviewees from Ho Chi Minh and
three interviewees from Hai Phong.
The interview duration generally lasted from 35 to 65 minutes. Out of consideration
for privacy and ethical protection, all interviewees were promised complete
confidentiality regarding the data provided by them when transcribed. With the
interviewees’ consent, most of the interviews were recorded, and only two of the
interviewees did not allow their conversation to be recorded. Thus, the note-taking
method was applied to obtain the information from these two interviews.
5.4 INTERVIEW FORMAT AND STRUCTURE
The interview questions were designed based on the result of the questionnaire survey.
Five major questions were formulated with sub-questions provided in Table 5-3. The
questions were qualitative in nature, which allowed the interviewees to comment and
state their insights and experience on issues related to critical factors.
There were 15 main theme questions, which were grouped based on 24 critical
decision-making factors. In order to obtain the interview objective, four major
questions and four sub-questions were designed to discuss across 15 themes. As the
interview format is semi-structured, the interview questions could be open-ended and
altered.
125
Table 5-3: Interview questions
No. Theme Major questions Sub-Questions
1 Choosing demolition methods 1. Comment on the significant influence of critical decision-making factors of urban redevelopment DW management in Vietnam (Strengths and Weaknesses)
2. Comment on related policies and strategies of urban redevelopment DW management in Vietnam.
3. Comment on the challenges and opportunities that might be faced as a result of critical factors in the context of Vietnam.
4. Other points regarding urban redevelopment DW management that are missing from the interview
‐ What are the elements supporting factors?
‐ What could be improved?
‐ What adaptive actions can you offer to tackle the challenges?
‐ What other factors do you believe affect the decision-making of urban redevelopment DW management?
2 Determining demolition waste management procedures
3 Waste classification and estimation
4 Planning for landfill, sorting area, and storage
5
Training
• Demolition technique training • Waste management training
6 Stakeholders’ awareness
7 Uniqueness (types, characteristics of DW)
8
3R strategies and recovery
• Promotion of 3R • Rate of recovery
9 Environmental Impact Assessment
10
Cost estimation and cost-effectiveness
• Cost estimation of waste transport
• Cost estimation of demolition work
• Cost-effective demolition plans
11 Preservation (Prevention of natural resource, cultural and heritage)
12 Reduction of community disturbance
13 Best practice guidelines
14
Stakeholder engagement
• Stakeholder responsibility • Stakeholders’ role in monitoring
and feedback
15 Information and communication (Regular information update)
126 Chapter 5: Interview
According to Adams, et al. (2007) and Berg (2004), in order to obtain the valuable
information in the interview, a pilot interview needs to be conducted with the experts.
The interview questions were pre-tested with two academics and one practitioner to
ensure the suitability and comprehensibility of questions, especially in the context of
Vietnam. Minor alterations were made as a result of this pre-test. In order to ensure
the interviewees had a common understanding of each critical factor and theme, the
explanation was given before the interview took place.
5.5 INTERVIEW RESULTS AND DISCUSSION
The interview results are described based on the main themes listed above. In order to
analyse the interview data, content analysis was applied as an inductive approach.
Content analysis is a popular technique of both quantitative and qualitative data
analysis, which helps researchers to achieve research objectives (Adams, et al., 2007).
The purpose of the content analysis is to illustrate the content of the interviewees’
recommendations and to categorise the various expressed opinions. The interview
contents were categorised in 15 main themes and are analysed in the following section.
5.5.1 Choosing demolition methods
Choosing appropriate demolition methods is in relation to making decisions of DW
management. In this theme, seven interviewees (one academic, one planner, one
engineer, and four policy makers) held the belief that choosing demolition technology
is very important to DW management (R3, R4, R5, R14, R17, R19 and R22). One
engineering manager emphasised that technology leads to reduction of DW and
improvement of the waste classification (R22). However, two policy makers claimed
that the construction contractors may be reluctant to employ the best technology as it
is costly, and further training for workers is needed (R5, R19). A suggestion by one
policy maker is that the government should formulate the policy in encouraging and
enforcing the use of environmentally friendly technology (R5). This is in line with the
argument of Yeheyis, Hewage, Alam, Eskicioglu, and Sadiq (2013) that the rate of
reuse and recycling of C&D waste is mainly dependent on the demolition method
employed to remove materials from a structure, and the studies by Lu and Yuan (2010)
and (Wang & Yuan, 2008), which revealed that construction technology contributes
significantly to the reduction, reuse and recycling of C&D waste.
127
It is noteworthy that the construction industry is considered as a major polluter, that
should devise effective construction waste management plans with the efficiencies in
the environment and economic performances (Mcdonald & Smithers, 1998). This was
expressed by one local authority policy maker interviewee as follows:
‘There are different methods of dismantling the old buildings; however, it is
important to consider demolition methods for cost-effectiveness’ (R17).
5.5.2 Demolition waste management procedures
The survey results reflect that the procedures of the demolition process are considered
as an important factor influencing DW management decision-making. Seven
interviewees (one academic, three planners and three engineers) agreed that the
procedures and practices for each stage need to be clearly defined (R3, R6, R7, R10,
R12, R13, and R16). One governmental planner emphasised that ‘determining the
procedures is very important in helping stakeholders to manage time effectively,
minimise problems during demolition work and increase the rate of waste recovery’
(R6). This resonates with Poon, et al. (2001) in that an effective on-site C&D waste
management often involves the plan of different stages of waste management, from
clearance, collection, transport, and disposal. Thus, the need for a detailed and
comprehensive plan of C&D waste management in conducting the construction project
is to achieve waste minimisation and a high level of recycling waste (Yeheyis, et al.,
2013; Yuan, 2013). In Hong Kong, a waste management plan is required for all
construction projects from 2003 (Tam, 2008). On the other hand, in Vietnam, the
consensus among the interviewees is that urban redevelopment projects usually lack
the site procedure scheduling for DW management and delivery planning of DW. One
engineer, as an on-site manager, claimed that ‘the lack of DW management plan leads
to the ineffective DW management and low recovery rate in Vietnamese urban
redevelopment projects’ (R10). In addition, one academic suggested that
‘The procedures of demolition and demolition waste management are to be
clearly identified to make the right decisions. These should be early developed
before demolition work is undertaken by project managers’ (R13).
In order to determine the DW management procedures, interviewees proposed
solutions, including developing the DW management plan in the early stage before
128 Chapter 5: Interview
demolition work, formulating the policy on environmentally friendly technology, and
considering the cost-effectiveness of demolition methods.
5.5.3 Waste classification and estimation
This theme includes the decision-making factors of on-site sorting and waste
estimation. On-site sorting/separating of DW is essential to the effectiveness of DW
management. This, together with the factor of waste estimation, receives scrupulous
attention from respondents in the questionnaire survey.
According to Wu and Ann (2014), on-site sorting that is effectively implemented
would assist contractors in arranging and using materials properly. In addition, through
this strategy, contractors can increase the value of recyclable waste and avoid the
pollution of mixed materials. In fact, four interviewees (one consultant, two engineers
and one policy maker) complained that the main issues of C&D management in
Vietnam are the lack of on-site sorting practice and the fact that most of the C&D
waste generated in construction projects is mixed and even is disposed together with
municipal solid waste (R2, R11, R16, R17). In addition, one engineer reflected that
‘there is a poor classification of DW, especially DW generated in urban redevelopment
projects in Vietnam’ (R21). As a result, one academic from the government agency
reported that ‘resource recovery was less effective, which leads to the low rate of waste
recovery in Vietnam compared to developed countries’ (R13).
The study by Poon, et al. (2001) reported that there is a need for decomposing the
C&D waste into its components before delivery, for example into inert and non-inert
materials. This offers the separation sources advantages in terms of less effort required
and better segregation waste types, compared to off-site classification. However, Poon,
et al. (2001) also indicate that the construction industry in Hong Kong is reluctant to
conduct on-site waste classification and still has little incentive to implement on-site
classification. Three interviewees (two academics and one policy maker) were in
agreement that it is necessary to make the stakeholders aware of DW management by
participating in on-site sorting (R13, R14, R20). One engineer as a waste management
contractor put forward a suggestion for improving DW management:
‘Classification of demolition waste would require a priority for improvement
of demolition waste management by stakeholders involved in urban
redevelopment projects in Vietnam’ (R4).
129
According to Formoso, et al. (2002), waste estimations are more supportive to the
management process for the cause of enabling operational cost and information of
waste generation, which is useful for managers in controlling projects. Most of the
interviewees were in agreement with the significance of waste estimation in decision-
making of urban redevelopment DW management. One policy maker as the director
of a government agency emphasised that ‘the regulation on C&D waste management
(the circular 08/2017/TT-BXD) will be effectively implemented when the volume and
type of C&D waste of the waste stream are clearly understood’ (R1). This requires the
estimation of waste in construction projects and an interviewee as one planner from
the local authority suggested that ‘demolition waste estimation should be scheduled in
early stages as this information can help decision makers have right decisions of cost
and time effectiveness’. He provided an example that ‘based on waste estimation, the
contractors can estimate the number of trucks for waste transport and identify the
appropriate waste destinations’ (R12).
This theme helped obtain valuable suggestions from interviewees, including raising
awareness of on-site waste sorting, prioritising the waste classification to improve DW
management and increase the recovery rate, and estimating DW in the planning stage.
5.5.4 Planning for landfill, sorting area, and storage
Planning for waste management refers to planning of sorting platform, landfills for
waste disposal, and transfer station for recyclable DW. It is understandable that in view
of WM, the planning of WM from generation, collection and disposal enhances
effective DW management in a number of ways, such as increasing the recovery rate,
reducing cost and time of waste transport and remedying the impacts of DW on the
environment.
Three interviewees (two planners and one policy maker) reported that there is limited
landfill for C&D waste in Vietnam (R3, R6, R19). For example, ‘three out of five
landfill planning for the C&D waste disposal were full in 2012, namely Van Noi, Vinh
Quynh, and Dan Phuong’, one government planner reflected. With the speed of the
development in Vietnam, the C&D waste is predicted to increase sharply. In
consideration of limited landfills and the increase in C&D waste, four interviewees
(one planer, one consultant, one engineer, and one policy maker) agreed that planning
of the landfills should be given priority (R6, R9, R10, and R19). The same scenario is
130 Chapter 5: Interview
found in Shenzhen, China, where there have been limited C&D waste landfills from
2010 (Lu, et al., 2011). Lu, et al. (2011) also claimed that the planning of new landfills
by the government was far behind, as only one landfill was fully built in the strategy
between 2006 and 2010. In addition, Wong and Yip (2004) state that the Hong Kong
government searched for landfill spaces for C&D waste from 2016 to 2045, due to
running out of landfill spaces in 2015 and the lack of reclamation sites.
The study by Yuan (2013) reveals that consideration of systematically planning waste
recycling facilities based on transportation distances throughout the region can save
the waste transportation cost and heighten the contractors’ awareness of sending waste
to recycling facilities because of the convenience in transportation. However, in
Vietnam, little attention has been paid to planning recycling material storages or
transfer stations. Three interviewees (one planner, one consultant, and one policy
maker) stated that this may be due to the neglect of recyclable construction materials
(R5, R6, R9). In order to reduce the cost and time of waste transport and increase the
recovery rate, one government planner claimed that
‘the issues of C&D transport and disposal need to be addressed by promoting
the planning of waste storages, waste transfer stations and specific waste
landfills for construction and demolition waste’ (R6).
This is in line with the statement by Rao, Jha, and Misra (2007) that the long distance
involved in waste transport to the recycling facilities is uneconomical C&D waste
management. This can be set up close to a demolition site. In addition, planning the
optimal transfer stations and landfills should be based on the status of land-use and the
transportation network. Three interviewees (one planner and two engineers) were in
agreement that proper planning will result in effective management of DW by saving
time and cost for waste storages, waste transportation and waste disposal (R12, R16,
and R22). One planner from the local authority claimed that ‘it is pivotal to consider
which place is more suitable for transfer station or waste disposal in DW management
plan’ (R12).
Three interviewees (one academic and two planners) also pointed out that the
increasing trend of urban redevelopment in some cities in Vietnam will generate a huge
amount of DW, which calls for a need to plan a suitable site for recycled waste and
disposal waste at a large level (R3, R12, R18). One engineer as a construction
contractor reflected that ‘in Vietnam, DW is mainly used for land reclamation and site
131
formation’ and he suggested that ‘there is the need of further research into the use of
DW in road sub-based’ (R10). In supporting the site identification for DW
management, one engineer as on-site manager emphasised that ‘economic
development plan and land-use should be considered in landfill selection. In addition,
the cost-effective comparison should be taken into account for choosing the suitable
sites’ (R21).
The highlights of this theme were discussed by interviewees including prioritising
C&D waste planning, promoting the use of DW in road sub-base, and identifying the
suitable sites for transfer stations and landfill.
5.5.5 Training
Training the human resource and skilled personnel involves the decision-making
process that affects effective DW management. In support of this theme, many studies
revealed that the C&D waste generation is substantially affected by skilled
construction workers (Lu & Yuan, 2010; Tam & Tam, 2008; Wang & Yuan, 2008).
Wang and Yuan (2006) also state that one of the problems associated with construction
waste management is the lack of sufficient waste management skills. Three
interviewees (one academic, one consultant, and one policy maker) asserted that
sufficient training for the workforce involved in DW management is the most
important, raising the workforce’s awareness about DW management and the use of
advanced technology in waste classification (R2, R6, R15). One academic consultant
voiced that
‘The limited knowledge of demolition work and waste management may lead
to problems related to the low rate of waste recovery and increased cost of
waste management’ (R11).
In addition, one policy maker from a government agency proclaimed that ‘in order to
ensure safety in the demolition process and minimise the impacts of this process on
the environment and community, the personal skills of on-site workers need to be
trained’(R5). For example, through vocational training, workers can promote waste
minimisation, the policy maker added (R5). This resonates with a study by Wu and
Ann (2014), in that education and training are important to waste minimisation. In
reality, the amount of waste is increased due to the unawareness of its impact of the
environment and the construction workers can efficiently work with less waste if they
132 Chapter 5: Interview
are trained to deploy material tools in advance. Another two academics also agreed
that the technical factors influencing DW management are likely related to a lack of
technical personnel skills among stakeholders (R11 and R18). In Vietnam, most of the
construction workers may not be sufficiently trained about environmental protection,
waste management, or low waste technologies. Therefore, one of seven policy makers
suggested that ‘the capacity of key stakeholders in waste management and dismantling
process needs to be built and project managers should arrange time for training before
the implementation of projects’ (R2).
It was suggested by the interviewees that training is important to DW management, as
it can minimise waste generation and help in waste classification. Training in the early
stage, especially on-site skill training, can remedy the impacts on the environment and
the community.
5.5.6 Stakeholder awareness
Awareness refers to the willingness of DW management by stakeholders. Several
studies revealed that the practitioners’ perspective on resource saving, environmental
protection, is a vital factor of C&D waste minimisation, by changing their attitude
toward waste generation, classification, recycling and disposal (Manowong, 2012;
Osmani, Glass, & Price, 2008).
Two out of six engineers (R10, R16) discerned that the efficiency of DW management
depends on the awareness of stakeholders on classification of DW, waste recycling
and waste disposal. However, they reflected that the construction contractors have had
little awareness of DW management, as they perceived that it increases a project’s cost
and time and their company may lose benefits in equipment, training and waste
transport. This is in line with the research by Wong and Yip (2004), which revealed
that in Hong Kong, almost all of the contractors were indeed aware of the significance
of sustainable C&D waste management but they did not properly implement
environmental measures, and have been working for profits and survival. In addition,
the research by Poon, et al. (2001) and Yuan (2013), state that the environmental issues
including C&D waste management are not given priority in construction projects.
Three interviewees (one engineer and two policy makers) suggested that it is a
requirement to leverage the understanding about DW management by training,
promulgating C&D waste policies, and participating in on-site sorting (R2, R17, R21).
133
Interestingly, one consultant recognised the role of governments in raising
stakeholders’ awareness about sound DW management in urban redevelopment
projects:
‘This should be changed initially by key stakeholders and leaders in the
influential government agencies. The government should organise and sponsor
training programs with regard to DW management’ (R8).
This is consistent with findings by Wu and Ann (2014), that the contractors have
neutral environmental awareness as implementing C&D waste management would be
costly. Wu and Ann (2014) conclude that the government must place sustainability in
regional development because it has a high level of willingness in implementing C&D
waste management.
It is discussed that the DW management is affected by stakeholders’ awareness. There
is a need for raising their willingness by training, promulgating C&D waste policies,
and participating in on-site sorting, in which the government should play a key
leadership role.
5.5.7 The uniqueness of demolition waste
Understanding the nature of DW is essential for implementing effective DW
management. This is clearly expressed by stakeholders in the decision-making process.
Three interviewees (two academics and one policy maker) were in agreement that in
the next two decades, there will be large-scale urban redevelopment activities in
Vietnam, and it is predicted that there will be an overwhelming amount of DW
generation, such as in Hanoi and Ho Chi Minh City (R5, R8, R9). One engineer
interviewee, as the construction contractor, reflected that ‘the main proportions of DW
are bricks and mortar with low rate of cement because almost all of the buildings are
aged about 30 to 50 years’ (R10). This resonates with the study by Poon (1997), that
masonry, wood, concrete and brick typically produced more than half of DW
management.
One academic interviewee from the government agency affirmed that ‘the quality of
demolition waste is not suitable for the recycling purpose of construction materials,
such as concrete because the characteristics of demolition waste present a low
potential of recycling compared to waste from new construction’, and he suggested
134 Chapter 5: Interview
that ‘there is the need of investigation the DW characteristics in the early stage to
assist decision makers in effective DW management’ (R15). This is in line with the
research of Kofoworola and Gheewala (2009), in that the inventory of C&D waste
generation should be implemented, which provides useful information for recycling
waste strategy.
5.5.8 “3R” strategies and recovery
The survey results show ‘3R’ principles and waste recovery are the key decision-
making factors of DW management. Three interviewees (two policy makers and one
planner) were in agreement that the promotion of 3R strategies in urban redevelopment
DW management can increase the waste recovery rate and minimise waste volumes to
the landfills (R1, R4, R7). This resonates with the study by Yeheyis, et al. (2013), in
that reuse and recycle of C&D waste are the challenges to management of a large
amount of waste in achieving sustainable construction for a better environment. This
offers benefits in terms of reducing the use of raw materials and converting more
recyclables from the landfills (Abbas et al., 2006). However, one government
academic and one local authority planner alleged that in Vietnam, 3R strategy is often
neglected by contractors for many reasons, such as the lack of stakeholders’ awareness,
poor waste management plans and the lack of application of low waste technologies
(R12, R13). In addition, one policy maker as senior manager perceived that ‘there is
lack of incentive policy to encourage the focus on waste conversion in Vietnam’ (R20).
This is in line with the issue in Shenzhen, China, where there is unclear regulation to
support the strategies of reduction and recycling, or such regulations are hard, to a
certain extent, to follow (Yuan, 2013).
One policy maker from the local authority reported that ‘the government have just
enacted the circular 08/2017/TT-BXD about C&D waste management in May 2017,
which will be a concrete foundation for regulation related to the development of 3R
strategies’ (R17). In order to promote 3R in DW management, one academic
consultant interviewee suggested that
‘3R strategies should be regulated in C&D waste management in Vietnam and
encouraged at the source by economic intensive programs and recycling
market development’ (R18).
135
Regarding the recovery rate of DW, one academic and one policy maker asserted that
effective urban redevelopment DW management in Vietnam is of great importance for
the purpose of increasing recovery rate (R8, R19). In addition, the policy maker
maintained that ‘this is because the amount of DW in the urban redevelopment projects
are foreseen to constitute a high quantity of C&D waste in some major cities in
Vietnam and the running out of C&D waste landfills is likely in the future’ (R19). This
is supported by Hendriks and Jansen (2001), who stated that C&D waste is considered
as secondary raw material that should be strongly encouraged by the authorities and
by the construction industry because of facing due to the possibility of rising waste
disposal fees and the limitations on the exploration of primary raw material. One policy
maker interviewee, as a local authority, emphasised the use of DW as secondary
materials: ‘the government should plan effectively the use of recycled material, such
as providing more details of demolition waste composition’ (R20).
In addition, one government planner stressed that ‘in order to ensure the increased
recovery rate, the stakeholders should consider not only the 3R strategies but also the
demolition technologies and waste onsite-classification’ (R6).
Interviewees provided valuable suggestions for the purpose of better 3R adaptation
and increased recovery rate, including promoting 3R in C&D waste management by
economic intensive programs and recycling market development, and increasing the
waste recovery rate based on 3R strategies, demolition technologies, and on-site
sorting.
5.5.9 Environmental impact assessment
Environmental impact assessment is vital to conform to urban redevelopment DW
management projects to environmental safety and thereby ensure sustainable
economic development. The consensus among the interviewees is that this principle is
regulated in Vietnam’s law on environmental protection and it is obligated in
development projects. However, one policy maker as senior manager claimed that ‘the
regulation of environmental impact assessment is ineffectively implemented’ (R20).
This resonates with the study by Yeung (2008), which expounded that a
comprehensive environmental performance assessment scheme for building is an
effort to achieve ‘green building’ in Hong Kong. This scheme encourages contractors
136 Chapter 5: Interview
to implement effective waste management strategies, such as waste reduction, waste
reuse, and waste recycling.
The interviewees also underscored that the ISO 14001 certification has been
considered in some organisations dealing with waste management to achieve
environmental excellence; however, the environmental management system in
Vietnam is not sufficiently regulated for effective C&D waste management (R11,
R18). According to Rodríguez, Alegre, and Martínez (2007), some construction
companies in Madrid, Spain, have obtained an environmental management system
based on ISO standard 14000 to control the main environmental issues associated with
their activities, such as waste generation. By doing this, the construction companies
reap the benefits of fostering public awareness of environmental protection and
fulfilling applicable related legislation.
Therefore, it is important to strictly regulate environmental management in the
construction industry to effectively address the C&D waste issues, as one policy maker
suggested that in order to have the acceptability of urban redevelopment projects,
environmental impact assessment by the government is necessary to figure out the
environmental issues and the solutions to those issues, especially the issues of DW
(R5).
The highlight of this theme discussed by interviewees is that the environmental impact
assessment should be obligatory in construction projects through more stringent
regulations in the construction industry.
5.5.10 Cost estimation and cost-effectiveness
This theme consists of cost estimation of demolition work and waste transport and
cost-effective demolition plans. An engineer interviewee and a consultant interviewee
were in agreement that cost estimation is necessary for decision-making in DW
management, because it allows project managers to single out the best way of
conducting the projects, such as cost of demolition, cost of DW delivery and cost of
DW disposal (R4, R15). In addition, one government policy maker argued that ‘cost
analysis is also significant to achieve economic feasibility in demolition waste
management’ (R1). This resonates with a study by Yeheyis, et al. (2013), which states
that stakeholders must be well informed about the feasible cost saving of waste
reduction and the environmental impacts of C&D waste in order to avoid the
137
unnecessary extra re-work in construction work. One engineering manager claimed
that ‘there are some hindrances that trigger the delayed demolition work and increase
demolition waste management cost, such as finance and the technique’ (R22). He also
suggested that ‘it is necessary to consider reducing time and cost of demolition work’
(R22).
According to Wang, et al. (2004), a successful and sustainable C&D waste
management depends on a justifiable financial framework for various stakeholders. In
addition, the study by Begum, Siwar, Pereira, and Jaafar (2006) indicated that a
benefit-cost analysis - a procedure for estimating all costs incurred and profits gained
from a business opportunity or proposal - for minimising construction waste can raise
revenue for environmental policies and prevention efforts, discourage waste disposal,
and avoid the environmental impacts of waste treatment and disposal. Therefore, it is
vital to evaluate the cost-benefit of various C&D waste management scenarios. This is
consistent with the findings by Yuan, et al. (2011).
Three interviewees (one policy maker and two consultants) claimed that the cost of
waste management is a burden for contractors, such as cost for waste classification,
waste transportation and waste disposal (R5, R13, R14). Their consensus is that cost
efficiency should be considered before projects are implemented. This is in line with
a study by Kwong (2003) showing that contractors need to build cost-effective
demolition plans. In addition, one engineer interviewee complained that ‘the evidence
of the cost saving of DW management in urban redevelopment projects can assist the
contractors in implementing DW management effectively and raise their awareness of
environmental protection’ (R7).
5.5.11 Preservation
Preservation refers to minimising the impacts of DW management on natural resources
and preserving cultural heritage. According to Yeoh and Huang (1996), there is an
increase in conservation-redevelopment conflict in urban development. This is
because rapid urban redevelopment results in the loss of cultural heritage. In line with
this perspective, the study by Chan and Lee (2008b) revealed that preservation of
historical structure and features is one of six considered urban design factors in
achieving sustainable urban renewal. This was expressed by three academic
interviewees, who articulated that urban redevelopment projects have been
138 Chapter 5: Interview
implemented mainly for an economic purpose and have neglected environmental and
social needs (R8, R9, and R18). In order to approach sustainability, serious
consideration should be given to natural resource preservation and reduction of the
environmental impact on the neighbourhood. One consultant suggested that ‘the
government should have a policy on integrated sustainable demolition waste
management that covers aspects such as the preservation of surrounding areas and
the mitigation of the disturbance to community’ (R11).
It is understandable that C&D waste recovery, including reuse of C&D waste, can
reinforce the preservation of natural spaces and reduce the exploration of mineral
resources (del Río Merino, et al., 2009). However, five interviewees (two academics,
one consultant, one engineer and one policy maker) reported that in the construction
industry in Vietnam, most of the regulations rarely govern the natural resource
preservation or purely mention this issue from broad perspectives (R8, R9, R13, R15,
R20). As a consequence, there is still the problem of waste illegal dumping, which has
caused severe damage to the natural resources. One academic and one policy maker
were in agreement that there is a need for specific principles around the issues
associated with DW management, such as land-use, pollution and heritage
preservation (R9, 20).
5.5.12 Reduction of disturbance on the community
Reducing the impacts of environmental pollution and noise pollution on the
community is important in making decisions of DW management. Interviewees were
in agreement that consideration of project social performance is strictly required to
ensure a better quality of life for the community. This resonates with the study by
Farfel, et al. (2005) in that stakeholders should be more aware of demolition-related
public health problems because the process of urban redevelopment is a major source
of lead being released into the environment. Two interviewees (one academic and one
consultant) emphasised that the demolition work has acted as a source of
environmental pollution, but the contractors have not paid much attention to the
environmental safety for the community (R11, R15). This may be due to the lack of
environmental regulations in the construction industry. One policy maker
recommended that ‘it is important for the Vietnamese government to give priority to
the reduction of the impacts on the community in addition to the conventional project
objectives such as economic and environmental’ (R20).
139
5.5.13 Regulations/guidelines
This theme includes the understanding the DW management procedures and providing
guidelines of DW management, which refers to promoting the best practice guidelines.
It is not easy for stakeholders to achieve efficiencies in DW management while at the
same time needing to take into account the environmental and social aspects of the
urban redevelopment projects. Therefore, it is not surprising that providing guidelines
of DW management is ranked as the most important factor for improving DW
management in urban redevelopment projects in Vietnam. The consensus among the
interviewees is that there is a lack of specific regulations or legislation for requiring
the management of C&D waste. This is in line with the situation in China, where the
lack of accurate regulations of C&D waste is one of the reasons for the poor C&D
waste management (Yuan, 2013). This means that there is no instruction to guide the
contractors in implementing C&D waste management in China. Two policy maker
interviewees conceded that there are a number of related decrees of C&D waste, but
the related regulations are too general, which is probably due to the combination
management of solid waste and C&D waste (R2, 17).
One policy maker from the government agency perceived that ‘DW management is not
normally expected to bring great profits for contractors due to its costs on the
equipment and management approaches; thus, stakeholders may be reluctant to
manage DW’ (R1). One engineer as on-site manager expressed the view that ‘in order
to fulfil the stakeholders’ responsibility in DW management, the government should
issue the guidelines for assisting all stakeholders in understanding the procedures of
DW management”’(R16). In addition, one policy maker suggested that ‘the
government should promote sustainability in urban redevelopment activities, which
will encourage stakeholders to integrate DW management in the demolition work’
(R2).
5.5.14 Stakeholder engagement
This theme explores the factors concerning the responsibility of stakeholders involved
in the DW management process and their roles in monitoring and providing feedback
about DW management. In fact, one engineer from a construction contractor reported
that ‘the stakeholders’ responsibilities of C&D waste management are regulated in
the new circular that was enacted in May 2017’ (R16). However, he also claimed that
140 Chapter 5: Interview
‘these responsibilities are too general in the construction industry and there is the
need of delegation of specific responsibilities in urban redevelopment DW
management’. Two interviewees (one academic and one engineer) reckoned that urban
redevelopment DW management in Vietnam is complicated because it involves
different stakeholders, with different fields of interest (R10, R15,). One engineering
manager expressed that ‘demonstrating the key stakeholders’ role in the different
stages of the demolition process can help achieve the effective DW management’
(R22). He gave the example that ‘the collection and disposal of DW by waste
contractors is more professional and effective than construction contractors’. This is
in line with findings by Manowong (2012) in that it is significant to identify who needs
to be involved in the construction waste management process.
According to a study by Yuan (2013), the responsibilities between the government
agencies and the local authority in C&D waste management are fuzzy, which hinders
the better C&D waste management practice. One planner interviewee from the local
authority emphasised that ‘in order to fulfil the stakeholders’ responsibility in DW
management, the government should issue the guidelines for supporting all
stakeholders involved in site management and site planning for waste management’
(R12). In addition, other engineer interviewee as project manager emphasised that
‘government should take the leading role in improving urban redevelopment DW
management, which encourages and enforces the stakeholders to effectively
participate in DW management’ (R7). This resonates with the finding by Lu and Yuan
(2010), in that without a strong direction and supervision from the government in
construction projects, other stakeholders, such as clients and contractors, may be
reluctant to conduct C&D waste management.
5.5.15 Information and communication
The component involved in this theme is regular information update. The information
update is an essential means of communication among stakeholders in effective urban
redevelopment DW management. However, such data are usually recorded with
construction waste in solid waste management reports in general by the Ministry of
Natural Resource and Environment (MONRE). The consensus among interviewees is
that Vietnam currently has no inventory or exact data on DW management, such as the
141
amount of waste, waste types or recycling material rate. One academic interviewee
manifested that ‘the DW information is difficult to update and control because of the
illegal disposal of C&D waste and a poor DW management plan’ (R18). He also
suggested that ‘it is imperative to formulate the policies to prompt the contractors to
share and report the waste management information’. In addition, two-out-of-six
policy makers claimed that there is the need of establishing a database platform for
C&D waste management (R4, R19). By doing this, the key stakeholders can be active
in making DW management plans and 3R strategies. This accords with the finding by
Shen, et al. (2007), which stated that providing a tool to facilitate stakeholders in
accessing the project information and sharing the knowledge and information in
working together towards better project performance is of utter importance.
In addition, one government planner interviewee claimed that ‘sharing the information
related to DW management should be required in the early stage of demolition work
to avoid the increase in the cost of waste management due to miscommunication’ (R6).
5.6 IMPROVING DEMOLITION WASTE MANAGEMENT IN VIETNAMESE URBAN REDEVELOPMENT PROJECTS
The purpose of the interviews was to validate the conceptual framework involved in
24 critical factors of DW management in urban redevelopment projects and proposed
action plans to improve DW management in Vietnamese urban redevelopment
projects. The main findings were extracted from the interview as shown in Table 5-4.
Table 5-4: Major findings of the interview study
No. Theme Action plan
1 Demolition methods Choosing the demolition methods with the
government’s support and consultation
2 Demolition waste management procedures
Demolition procedures need to be defined clearly Effective scheduling demolition work in early stage
3 Waste classification and estimation
Promoting on-site waste classification Improving skills of waste sorting Promoting the use of recycling materials
4 Planning for landfill, sorting area, and storage
Priority of landfills and transfer stations planning Identifying suitable sites for transfer stations and
landfills
142 Chapter 5: Interview
No. Theme Action plan
5 Training
Providing training courses of DW management and demolition technology
Building capacity in using low waste technology
6 Stakeholder awareness
Raising awareness of key stakeholders Promoting incentive policies
7 The uniqueness of demolition waste
Assessment of DW characteristics in the early stage of demolition work
Understanding the DW characteristics
8 “3R” strategies and recovery
Promoting specific 3R strategies Increasing reuse and recycling by intensive
economic programs
9 Environmental Impact Assessment
Regulating strict environmental policies
10 Cost estimation and cost- effectiveness
Development of cost-effective scenarios Cost estimation for specific stage of DW
management
11 Preservation Integrated preservation in DW management
12 Reduction of community disturbance
Priority given to the community’s safety in project objectives.
13 Regulations/guidelines Providing appropriate guidelines Regulations of integrated waste management Promoting sustainability
14 Stakeholder engagement
Defining clearly stakeholders’ responsibilities Enhancing efficient communication Appropriate institutional arrangement The leading role of government
15 Information and communication
Regular reporting Building database of demolition waste Sharing information in the early stage of demolition
work
The interviewees were asked to provide their comments on how influential each
critical decision-making factor is. Most of the interviewees expressed that the proposed
framework fully covered the major and relevant factors. These factors were confirmed
by the interviewees as accurate and reasonable and deserved to be considered in
improving DW management in Vietnamese urban redevelopment projects.
Regarding the three critical factors that were found, the significant differences of
respondent’s’ perspectives in rating the importance, and the consensus among the
interviewees, was made. Training is considered as important to DW management,
which can minimise waste generation and help in waste classification. In addition,
143
training in the early stage, especially on-site skill training, can remedy the impacts on
the environment and the community. In support of this factor, many studies revealed
that the C&D waste generation is substantially affected by skilled construction workers
(Lu & Yuan, 2010; Tam & Tam, 2008; Wang & Yuan, 2008). It is noteworthy that
training of DW management and demolition techniques is grouped in the theme of
‘training’.
The interviewees were in agreement that cost estimation is necessary for decision-
making in DW management, because it allows project managers to single out the best
way of conducting the projects, such as cost of demolition, cost of DW delivery and
cost of DW disposal. This is in line with a study by Kwong (2003), showing that
contractors need to build cost-effective demolition plans. As per interviewees’
suggestion, there is the need of investigation into the DW characteristics in the early
stage to assist decision makers in effective DW management. This is supported by the
research of Kofoworola and Gheewala (2009), in that the inventory of C&D waste
generation should be implemented, which provides useful information for recycling
waste strategy.
Summarily, the interview study elicited interviewees’ opinions and insights, which
assist to formulate the efficient decision-making framework or urban redevelopment
DW management. This framework will assist the decision makers in making the right
decisions in achieving effective urban redevelopment DW management in Vietnam.
In addition, the findings from the interview study are analysed and remarked as
variable actions of improving the urban redevelopment DW management in Vietnam
with 15 main themes of critical factors. Interestingly, the discussion and actions
suggested by the interviewees relating to six factors (waste classification and
estimation; planning for landfill, sorting area, and storage; the uniqueness of
demolition waste; “3R” strategies and recovery; and cost estimation and cost-
effectiveness) supported the development of the database of DW in the case study.
This information enables decision makers to assess and qualify the DW database in
making the decision for improving DW management with the better understanding and
the cost-effectiveness.
144 Chapter 5: Interview
5.7 SUMMARY
This chapter illustrates the results of data analysis, which were obtained through the
semi-structured interviews with 22 interviewees from the five stakeholder groups:
academics, planners, consultants, engineers, and policy makers. It describes the in-
depth understanding of experienced respondents about the significant influence of 24
critical decision-making factors on DW management in urban redevelopment projects,
which resulted from the survey study, in Chapter 4. The findings in this chapter are the
actions suggested by the interviewees, towards improving DW management in
Vietnamese urban redevelopment projects based on critical decision-making factors.
The critical factors and conceptual decision-making framework were validated and
verified by interviewees who hold the key positions in DW management in Vietnamese
urban redevelopment projects. There is prevailing awareness towards integrated DW
management among stakeholders in achieving sustainability. This is to ensure that the
critical decision-making factors are significantly considered in improving DW
management in Vietnamese urban redevelopment projects. The findings in this chapter
answered the second research question: How do the key decision-making factors
influence demolition waste management in Vietnamese urban redevelopment projects?
This analysis was to investigate the contextual relationships among critical factors,
which will act as the foundation for developing a database supporting the decision-
making process of DW management in an urban redevelopment project. Based on the
interviewees’ feedback, six critical factors including (1) on-site sorting, (2) rate of
waste recovery, (3) cost-effectiveness demolition plan, (4) estimation of DW, (5) cost
estimation of waste transport, and (6) landfill planning, were further analysed to
develop the DW database. This database of DW is considered crucial information that
supports stakeholders in making decision. The process of database development in a
GIS-based model is described in Chapter 6.
145
Chapter 6: Case study
6.1 INTRODUCTION
The conceptual decision-making framework for improving urban redevelopment DW
management in Vietnam is formulated in previous chapters. In order to develop this
conceptual framework, the critical decision-making factors were identified through the
questionnaire survey on five groups of key stakeholders in the survey study. The
conceptual framework was then discussed and validated by experienced respondents
in the semi-structured interview round in the interview study. Based on the findings
from both quantitative and qualitative analysis, as discussed in the Chapter 4 and 5,
six critical factors including on-site sorting, rate of waste recovery, cost-effectiveness
demolition plan, estimation of DW, cost estimation of waste transport, and landfill
planning were analysed to develop the database of DW in the GIS-based model. This
model is a decision support tool, which incorporates with the proposed decision-
making framework in order to facilitate decision making in DW management at district
level. The GIS-based model is designed for the case study in Hanoi, including four
mega urban redevelopment projects.
The outline of this chapter is as follows. It first describes the purpose of the case study.
This is followed by the selection of the case study conducted in this research and data
collection and analyses. The development of the decision support system based on GIS
is then presented before the case study results are discussed. The chapter ends with a
summary about the important results of the case study.
6.2 CASE STUDY PURPOSE
The case study was used as an example of the application to practically demonstrate
how the supporting database developed can assist decision makers in improving DW
management in urban redevelopment projects. In this research, ArcGIS software was
adopted as a decision support tool for developing the spatial database and Excel
software was used for data calculation. Both spatial and attribute data were collected
regarding the critical factors considered in the proposed decision-making framework.
The collected data was then computed and combined for the preparation of input data.
146 Chapter 6: Case study
Finally, the necessary information for DW management was captured for the GIS-
based model database.
This database was integrated with the proposed framework to assist decision makers
in the decision-making process. This supporting database includes the information of
DW volume, DW compositions, DW transport, and the selection of landfill sites all of
which were computerised based on six critical decision-making factors. The GIS-
based model is designed for the case study in Vietnam aiming at improving DW
management in urban redevelopment projects. The case study provided a clear
example of developing the database of DW management at district level.
6.3 CASE STUDY SITE CONTEXT
The case study was adopted as a research method and was briefly described in Chapter
3. The case study was conducted after the data of the questionnaire survey and
interviews were analysed. According to Berg (2004), the case selection should ensure
that the case provides relevant data that reflects the research hypotheses or the research
problem. There are two options of conducting case studies that the researcher can
select to collect and analyse the research data, namely single case, and multiple cases.
A single case study normally emphasises the critical, unique or unprecedented nature
of the selected case to confirm or challenge a theory; in order to avoid
misrepresentation, the researcher needs to justify carefully the selection of the case
(Blaxter, 2010; Mark, et al., 2009). On the other hand, (Blaxter (2010)) and Mark, et
al. (2009) argue that a multiple case study reflects the logical and replicable
generalisation of the research findings through different cases. These researchers also
stated that a single case study is often preferred, because the research results are
supposedly strengthened by replicating the pattern and improving the confidence in
the robustness of the theory.
In this research, a single case was employed in order to answer the research question
about the requirement of the supporting database of DW management in urban
redevelopment projects in Vietnam. The selection of case study established the
following criteria:
- The case study should be located and represented for the trend of urban
redevelopment in Vietnam.
147
- The main purpose of the case study is redeveloping the aging buildings.
- The case study should be multiple urban redevelopment projects within a
district.
- The case study will be conducted in the next 10 years and has the potential of
environmental impacts caused by DW.
Based on the above criteria, Ba Dinh, one of four old central districts in Hanoi, was
selected to develop decision support tool, GIS-based model, as illustrated in Figure 6-
1. Ba Dinh district is the political centre of Vietnam, where most of the government
offices and embassies are located. This district covers an area of about 9.25 m2,
spanning over 21°2'9.118" N and 105°49'34.928" E, with a population of 228,352 and
population density of about 24,703 people per square kilometre. It is witnessed that Ba
Dinh occupies many two-storey to five-storey building blocks built in the 1970s, most
of which have almost reached the end of their life span. In addition, many of old
buildings in Ba Dinh are severely blighted and pose serious environmental risks to the
residents’ safety (Huy, 2015). According to Vietnamnet (2016), 25 out of 42 high-risk
old buildings in Hanoi are located in Ba Dinh district, where three old buildings are at
risk level D, which is the highest risk level and can be a danger to the residents, and
22 old buildings are at risk level C. These require urban redevelopment of residential
areas, which will have the capacity to modernise neighbourhoods and improve housing
conditions on a large scale in Ba Dinh district (Hoang, 2017).
Consequently, a large volume of DW will be generated, which requires an effective
DW management. Therefore, the case study area is appropriate due to the level of
urban redevelopment and the need of DW management, which can reflect the merit of
a supporting database integrated with the decision-making framework.
At present, 7 out of 107 proposed redevelopment projects in Hanoi are completed and
8 projects, including resident and non-resident buildings, which have been approved,
have been undertaken in Ba Dinh, Thanh Xuan, Dong Da and Cau Giay districts (Bao
Anh, 2011). Ba Dinh district has four redevelopment projects that are waiting for the
commitment, which are Giang Vo; Ngoc Khanh I; Ngoc Khanh II; and Thanh Cong
(Mai Hoa, 2015).
148 Chapter 6: Case study
Figure 6-1: Location of Ba Dinh district
These projects indicate that the local government is acting for the cause of urban
redevelopment, which can lead to massive DW. On the other hand, there is a lack of
plans in effective DW management in Vietnam, particularly in Hanoi. The information
of four projects in this case study is shown in Table 6-1.
149
Table 6-1: The project information of the case study
No Name of urban
redevelopment project Number of buildings
Type of building structure
Year of construction
1 Giang Vo 5 Brick-concrete
structure 1974
2 Ngoc Khanh I 3 Brick-concrete
structure 1976
3 Ngoc Khanh II 4 Brick-concrete
structure 1976
4 Thanh Cong 25 Brick-concrete
structure 1971
To specify, the Thanh Cong project is the largest project, with 25 five-floor buildings,
Ngoc Khanh I project comprises three five-floor buildings, Ngoc Khanh II project
comprises only four three-floor buildings, and Giang Vo project comprises five five-
storey buildings. All of the old buildings in those four urban redevelopment projects
are three to five-storey blocks and are dated back over 40 years. These buildings were
of brick-concrete structure, which was deemed as the major structure type in the 1970s.
This study focused on sorting and estimating the materials of brick, concrete, mortar,
and metal, wherein mortar was combined with concrete in waste estimation because
these two materials are usually attached together in the demolition process and it is
hard to classify them on-site.
6.4 CASE STUDY DATA COLLECTION METHOD
Based on the results from the survey and interviews, there are six critical factors that
can provide valuable references for decision makers in the decision-making process of
DW management in urban redevelopment projects. The critical factors are considered
to be analysed to answer the question regarding which information is crucial to develop
a supporting database of DW management, including six factors: (1) on-site sorting,
(2) rate of waste recovery, (3) cost-effectiveness demolition plan, (4) waste estimation,
(5) cost estimation of waste transport, and (6) landfill planning. The results of the case
study help to fulfil the factor of ‘regular information update’, which was ranked as the
third most important factor in the rankings.
150 Chapter 6: Case study
In order to support DW management decision-making process in urban redevelopment
projects, essential information was collected to develop a supporting database. There
are two sources from which the data is collected, which are stated as follows.
6.4.1 The spatial data
The spatial information was gathered to provide background information about the
research area, locations of urban redevelopment projects, and landfill sites. Spatial data
at the district level were collected from available open-street map framework of the
research area, Hanoi land-use maps, Google satellite images, transport networks,
locations of urban redevelopment projects, and locations of C&D waste landfill sites.
Data at the project level included the locations of four urban redevelopment projects
and the buildings in each project that were digitised on Google satellite image with
fieldwork ground control checking. In addition, the locations of C&D waste landfills
were also drawn in a similar way. Figure 6-2 presents the locations of four urban
redevelopment projects in Ba Dinh district.
151
152 Chapter 6: Case study
Figure 6-2: Locations of four urban redevelopment projects in Ba Dinh district
153
6.4.2 The attribute information
Attribute information, known as non-spatial data, was gathered through documents
and the site investigation, in order to provide the data integrated with the spatial
elements. The attribute data collected in accordance with the six critical factors as
mentioned above include the number of buildings in each urban redevelopment
project, the buildings’ structural types, buildings’ components, buildings’ structure
information, the capacity of landfills for C&D waste. To collect the related data, the
site visit was conducted in May 2017. The site visit evaluation was to obtain in-depth
information concerning the number of floors of the building in each project, the
number of units, the size of the units, the number and size of stairs, and the size of
corridors and the detailed information of demolition buildings in the four urban
redevelopment projects, as provided in Appendix D1. It must be accentuated that the
number of units and the number of floors could vary from building to building. In
addition, some general information may not be sufficient during the site visit process.
For example, many of the traditional iron doors and windows were also candidates for
alteration; many of them have been replaced with wooden ones by the residents.
Therefore, the component of wood was hard to estimate. In the next step, this
information was then analysed to develop the database, which is integrated with the
spatial information to constitute a supporting database for DW management.
6.5 DEVELOPMENT OF DEMOLITION WASTE DATABASE
The process of developing the supporting database for DW management includes three
steps as follows. First, the collected attribute data were calculated through Excel
software. Second, the spatial data were processed through ArcGIS software to
integrate with and link to the attribute data. Finally, the adapted data were presented
in the database in the form of map layers. The database was stored in the form of a
Geodatabase file in both vector and raster format. The GIS-based tool was used as the
platform for managing and displaying the supporting database in accordance with
selected factors.
154 Chapter 6: Case study
In order to provide crucial information for decision-making, the volume of the total
DW and three main material types namely: brick, concrete and mortar, and metal of
DW were estimated. This phase demonstrates the important step for preparing the
attribution database. Through this phase, the waste conditions such as reuse, recycle,
or disposal are determined.
In the subsequent step, the spatial data were processed in ArcGIS to present specific
values related to each critical factor. In this step, the ArcGIS tool was adopted to
integrate the input data for the model. The total volume of DW, the volume of three
main DW materials, the number of pick-up trucks, and the selection of landfill sites
were assigned to the themes in ArcGIS tools. Then, it can easily access the information
pertaining to the DW of each project. For example, the information of recycling waste
per building or per project such as metal can be extracted from the database by
selecting the location of the building or project in ArcMap.
6.6 CASE STUDY RESULTS AND DISCUSSION
6.6.1 Demolition waste estimation
According to Lu (2014), estimation of the amount of C&D waste has been long
underscored for policy makers, academics, practitioners, and the like. The information
of C&D waste generation could help in designing strategies of reduction, reuse, and
recovery in order to conserve natural resources and energy by using materials more
efficiently (USEPA, 2009). This study adopted the methodology of waste estimation
as waste weight per area, which was first reported in the study by Yost and Halstead
(1996). The waste generation rate of brick, mortar, concrete, and metal in estimating
the waste volume was based on material index introduced by the Vietnam Ministry of
Construction, which is weight (kg) of material per m2.
The project DW generation was estimated in two steps. First, the measurements of
three main materials in the building of each project were conducted, and can be seen
in Appendix D1.
The volume of brick generated in each project was calculated by using Equation 1.
155
DWbp = BRf * WIb * Fn * Bn (1)
where DWbp is the volume of brick generated in each project (tons); BRf is the number
of bricks generated in each floor based on the total areas in the units and shared public
areas; WIb is waste index for brick; Fn is the number of floors in each building; and Bn
is the number of buildings in each project.
The volume of mortar and concrete generated in each project was calculated by using
Equation 2.
DWmcp = CMa * WImc * Fn * Bn (2)
where DWmcp is the volume of concrete and mortar generated in each project (tons);
CMa is the total surface areas of the units and shared public area in each floor; WImc is
waste index for mortar and concrete; Fn is the number of floors in each building; and
Bn is the number of buildings in each project.
The volume of metal generated in each project was calculated by using Equation 3.
DWmp = Mu * WIm * Fn * Bn (3)
where DWmp is the volume of metal generated in each project (tons); Mu is the volume
of metal generated in each floor of the building based on the metal estimation in each
unit; WIm is waste index for metal; Fn is the number of floors in each old building; and
Bn is the number of buildings in each project.
Accordingly, in the next step, the total volume of DW generation in a project was
calculated by using Equation 4. The results show that 162,860 tons of DW is a
significant waste stream, which must be analysed in making plans of waste
management by reusing on-site and off-site, recycling, or disposal. The waste
estimation of the total DW per building and per project was created in Excel software
as attribute information. Then, all the attribute data were integrated in layout ArcGIS
tools. The total volume of DW corresponding with the four urban redevelopment
projects can be seen in Figure 6-3.
156 Chapter 6: Case study
DWp = DWbp + DWmcp + DWmp (4)
where DWp is the total volume of DW generated in each project (tons); DWbp is the
volume of brick generated in each project; DWmcp is the volume of concrete and mortar
generated in each project; DWmp is the volume of metal generated in each project.
The estimation result of DW generated in the four projects is summarised in Figure 6-
3 and presented in the GIS model in Figure 6-4. As is illustrated, Thanh Cong is the
largest project with a total DW volume of about 124,788 tons and Ngoc Khanh II is
the smallest project, predicted to generate 5,405 tons of DW.
Figure 6-3: The total volume of DW generation in four urban redevelopment projects
0
20,000
40,000
60,000
80,000
100,000
120,000
140,000
Giang Vo Ngoc Khanh I Ngoc Khanh II Thanh Cong
DW volume
157
Figure 6-4: The DW volume generation in four projects presented in GIS model
158 Chapter 6: Case study
6.6.2 Demolition waste classification
The statistics of DW components is useful information for decision makers in
formulating DW recycling and reuse strategies and analysing cost-effectiveness. The
data listed in Appendix D1 demonstrates that the statistics of three main materials for
the four urban redevelopment projects were determined by the equations mentioned
above. By integrating the estimation results in ArcGIS tools, the performance of
different materials per building and per project is presented. Figure 6-5 shows the main
material components of DW in four projects.
Figure 6-5: Demolition waste generation divided by materials in four urban redevelopment projects
The proportion of bricks in four projects was comparatively higher, ranging from
45.3% to 47.5%, whereas the second major material of DW in urban redevelopment
projects is a combination of mortar and concrete, ranging from 43.8% to 44.7%. These
components should be considered for on-site reuse or transported to the transfer station
for reuse in other constructions such as road base and public fill areas. Metal is
considered as recyclable material accounting a negligible proportion, ranging from
0.3% to 0.7%. These data were integrated in the GIS model as shown in Figure 6-6.
0.0
20,000.0
40,000.0
60,000.0
80,000.0
100,000.0
120,000.0
140,000.0
Giang Vo NgocKhanh I
NgocKhanh II
ThanhCong
Other
Metal
Mortar and concrete
Brick
159
Figure 6-6: Demolition waste generation divided by materials in four urban redevelopment projects presented in GIS model
160 Chapter 6: Case study
It is noteworthy that each sorting material could be extracted in a new layer that can
help decision makers in further analysis and statistics. This can help contractors in
urban redevelopment projects to identify the DW information in a particular building
or project, regarding the waste component volume, reuse, and recyclable materials.
In addition, separate analysis of different materials in different layers can help decision
makers in drawing up plans of demolition and estimating cost-effectiveness for DW
management. For example, the information of mortar and concrete can help
contractors decide on which scale reuse should be done and estimate the cost of waste
transport. Furthermore, by this approach, contractors can save time in making
decisions about reuse and recycling. The estimation of the number of trucks that are
used to deliver each type of DW is described in the next section.
6.6.3 Demolition waste transport
According to Cheng and Ma (2013), estimation of the number of trucks for waste pick-
up is needed for two reasons. First, if the number of trucks is underestimated, the waste
pick-up truck could be overloading because the contractors attempt to load all the
waste, which can lead to a fine imposed by the local authority. On the other hand,
overestimating the number of trucks will cost contractors money as well as result in a
waste of space for waste loading. Therefore, it is vital to provide the estimation of the
number of trucks for picking-up different types of DW. Accordingly, decision makers
and contractors could plan an effective DW management. The number of trucks per
project is estimated for picking-up bricks, mortar and concrete, which are considered
as non-inert materials by Equation 4.
TRn= DWinp/DWtr (4)
where TRn is the number of pick-up trucks in each project; DWinp is the total volume
of inert materials in each project (tons) which are based on the total volume of bricks,
mortar and concrete; DWtr is the truck capacity (tons).
In this study, the number of trucks for waste transport per project was estimated with
a truck’s capacity of 24 tons as shown in Figure 6-7. Accordingly, the Thanh Cong
project requires the largest number of pick-up trucks, amounting to about 4,755 trucks.
161
Figure 6-7: Estimation of the number of pick-up trucks per project for non-inert waste
162 Chapter 6: Case study
The number of pick-up trucks for Ngoc Khanh II project is much lower, at about 203
trucks. Estimation of the number of pick-up trucks for DW in each project is vital for
contractors to formulate strategies in order to save time and the cost of DW
management.
Supposing the project has a plan of reusing non-inert waste on-site, the number of
pick-up trucks is estimated based on the volume of DW that need to be transported
after the total DW generated and the volume of DW to be reused in the project are
estimated. The reuse of DW on-site is effective DW management in reducing waste
transport cost and the amount of waste to the landfill. In addition, decision makers can
select appropriate transfer stations and C&D waste landfills based on transportation
routes in order to save time and energy for waste transport.
6.6.4 Selection of landfill sites
According to Kontos, Komilis, and Halvadakis (2005), properly selected landfill sites
for multiple solid waste could reduce the cost of waste disposal and minimise the
environmental impacts. Recently, GIS has been considered a powerful tool in waste
management, particularly in selecting the landfill sites (Kontos, et al., 2005; Şener,
Şener, Nas, & Karagüzel, 2010). In fact, in Vietnam, the cost of DW transport is one
of the major obstacles that make contractors reluctant to implement DW management.
Therefore, it is of great importance to minimise the distance from DW location to the
landfills or transfer stations.
This research created a database for selecting landfill sites, regarding the provided
number of C&D waste landfill sites in Hanoi, the landfill site capacity (ton per day),
and the distances to the landfill sites, as shown in Figure 6-8. According to the Hanoi
Department of Construction, 13 landfill sites were designed for C&D waste disposal
with different capacities, ranging from 150 to 4,000 ton per day (Nguyen, 2011) (refer
to Appendix D2). Three out of twelve landfills have no data of the site’s capacity. The
distances from waste locations to the landfills were calculated by Google Earth to
identify the optimal routes. The shortest distance from the waste location is 8.4km,
which is the location of the Lam Du landfill site, with no data of the site capacity.
163
Figure 6-8: The information of C&D waste landfill sites in Hanoi
164 Chapter 6: Case study
Similarly, the distance from the waste location to Ngoc Thuy landfill site is only
8.6km, but the site capacity has not been taken into consideration. These could hinder
the contractors to make decisions of waste disposal to these two landfills. On the
contrary, Xuan Son landfill site has the longest distance to the waste location (50.3km),
with the largest site capacity (4,000 ton/per day).
At the district level, the total volume of DW was about 124,778 ton as can be seen in
Figure 6-3. Thus, the scenarios of DW disposal are vitally considered because the large
volume of DW stream. It is noteworthy that the information of the landfill site only
provides supporting data for the decision makers in choosing the landfill site or transfer
station so that the cost of DW transport can be lowered.
6.7 SUMMARY
The supporting database developed in the GIS-based tool is useful information for
decision makers to make DW management decisions in urban redevelopment projects.
The layer maps present the quantitative and objective references for the decision-
making process as a decision support system. The selected factors conceptualised to
develop the database include six factors: (1) on-site sorting, (2) rate of waste recovery,
(3) cost-effectiveness demolition plan, (4) waste estimation, (5) cost estimation of
waste transport, and (6) landfill planning. Thanks to the supporting database integrated
in GIS-based model and convenient access to this database, stakeholders can
effectively and efficiently communicate with others involved in the decision-making
process of DW management and create a platform of DW information before and
during demolition work. The findings in this chapter answered the third research
question: What is the necessary information to support key stakeholders in demolition
waste management in Vietnamese urban redevelopment projects at the district level?
This chapter presents the development of a supporting database in the GIS-based tool
under the context of four urban redevelopment projects in Ba Dinh district, Hanoi,
Vietnam. The development of the supporting database involved waste estimation,
waste classification, waste transport and selection of landfill sites. This GIS-based
model (including the DW database) was integrated with the proposed decision-making
framework. The research findings are summarised and discussed in the next chapter.
165
Chapter 7: Discussion and Findings
7.1 INTRODUCTION
This chapter explains and discusses the results of the research. The findings from
Chapters 4, 5 and 6, as well as relevant literature of DW management in urban
redevelopment projects are incorporated in order to achieve the third research objective
which is ‘developing a decision-making framework and critical supporting information
to assist decision makers in improving demolition waste management in Vietnamese
urban redevelopment projects at the district level’. Accordingly, the conceptual
framework as presented in Chapter 2 is explained. The findings from Chapter 4 and 5 that
validate the conceptual framework are discussed in detail. Next, the discussion about the
development of the supporting database by the GIS model as presented in Chapter 6 is
discussed before the research findings are provided and linked to the extant literature.
7.2 CONCEPTUAL FRAMEWORK
The research commenced with a literature review focusing on urban redevelopment, the
link between sustainability and urban redevelopment, DW management, the context of
DW management in Vietnamese urban redevelopment, and organisational decision-
making. This literature review was conducted to address the first research objective,
which is ‘explore the current DW management in urban redevelopment projects and in
the context of Vietnam’.
This provided the useful knowledge to investigate domains of information that are needed
to formulate the research gaps and the factors affecting DW management decision-
making in urban redevelopment projects, which served as the foundation to formulate the
conceptual framework. To be specific, research gaps indicated that there are many
challenges in managing urban redevelopment DW due to the complexities involved, such
as poor waste management planning, the overlapping of responsibility and ineffective
time and cost management (Lu, Lau, & Poon, 2009; Wu, Yu, Shen, & Liu, 2014).
Therefore, effective waste management requires a clear decision-making process that
includes key stakeholders and involves project performances towards sustainability.
166 Chapter 7: Discussion and Findings
The knowledge of sustainable urban redevelopment, integrated waste management, and
organisational decision-making are embedded in the conceptual framework, in which 19
themes for analysis are identified and categorised into five categories including technical,
environmental, economic, social, and institutional. Analysing the multi-criterion themes
can help decision makers understand the influencing factors of DW management in urban
redevelopment projects. For example, considering the preservation of natural resources
and heritage ensures the social sustainability of DW management. In addition, urban
regeneration projects can be a source of conflict if they are poorly planned (Yau & Ling
Chan, 2008). In light of this, the engagement of key stakeholders in implementing DW
management also needs to be carefully planned in order to avoid the overlap of
responsibilities. This is supportive in saving time and cost in urban redevelopment
projects. Furthermore, demolition techniques should also be considered before the
demolition work to facilitate the urban redevelopment DW management process. Thus,
choosing an appropriate demolition method can ease on-site waste sorting and increase
the waste recovery rate (Poon, et al., 2004). Furthermore, considering the environmental
factors, such as understanding associated environmental issues, applying 3R strategies,
and raising environmental awareness, can assist in addressing the environmental impacts
of urban redevelopment projects.
Based on the background literature, a number of issues covering five main categories
including technical, environmental, economic, social, and institutional, have been
analysed and grouped into 19 main themes. As a result, a list of 53 factors that potentially
influence DW management decision-making was synthesised. For example, six decision-
making factors including DW management procedure, waste sorting, waste estimation,
planning for landfills, planning for sorting area, and planning for area of recycling waste,
were investigated regarding the theme of ‘DW management process’. The theme of
‘policy and guideline’ was composed by two factors which are ‘providing guidelines of
DW management plan’ and ‘accomplishing government’s policy and strategy on DW
management’.
The conceptual framework in improving DW management in urban redevelopment
projects was developed covering 5 categories with 19 main themes, whereas 53 decision-
making factors were used as a baseline to design questionnaires in the survey study. These
findings revealed the concern about urban redevelopment DW management in both
academic and practice as well as the factors influencing the decision-making process.
167
Related literature highlights that developed countries, such as in the United Kingdom,
other Europeans countries, and the United States, have better understanding of urban
redevelopment DW management. For example, the rate of recovery C&D waste in
Denmark, Belgium, and Netherlands, are relatively high (Brodersen, et al., 2002). In
addition, upon the trend of urban redevelopment which is occurring in China and Hong
Kong, many researchers are placing greater emphasis on various aspects in urban
redevelopment DW management, such as environmental performance, stakeholder
engagement, and decision support. These contributions are proposed to help other
developing nations, such as India and Brazil, where they seem to be comparatively less
active in researching the demolition waste management. Therefore, in order to improve
decision-making process of DW management in the context of Vietnamese urban
redevelopment projects, the original conceptual framework (as shown in Figure 2-11) was
further refined and revised based on the survey and interview findings.
7.3 REVISED CONCEPTUAL FRAMEWORK
Apart from revising the conceptual framework by analysing stakeholders’ perspectives in
the survey study, the interview study verified the proposed framework by asking for
expert opinions. In this research, the survey was conducted to answer the first research
question: What are the key decision-making factors influencing demolition waste
management in Vietnamese urban redevelopment projects? The interview study was
implemented to answer the second research question: How do the key decision-making
factors influence demolition waste management in Vietnamese urban redevelopment
projects?
In this regard, the second research objective was addressed, which is ‘identifying critical
decision-making factors of DW management in urban redevelopment projects’. Central
to this objective were three other related sub-objectives: investigating the different
concerns and expectations of key stakeholders in making decisions about urban
redevelopment DW management; identifying the critical decision-making factors in
achieving effective DW management; and developing the action plans for each critical
factor to enhance DW management.
In the survey study, the quantitative analysis generated 24 out of 53 decision-making
factors which were found to have influence on DW management in Vietnamese urban
redevelopment project. The framework was revised based on 24 critical factors as
168 Chapter 7: Discussion and Findings
presented in Figure 4-2. Most of these critical factors gained consensus across the five
stakeholder groups, while there were some differences in the rating regarding levels of
importance. The deep understanding of those critical factors was explored in the interview
study, which also revealed the actions in improving urban redevelopment DW
management in Vietnam. These factors have been assessed against five categories,
namely, technical performance, environmental performance, economic performance,
social performance, and institutional performance representing aspects of sustainability,
as discussed below.
7.3.1 Technical factors
Eight critical factors were found relating to the technical aspect of sustainability practice.
These factors comprised ‘determining the procedure’, ‘on-site sorting’, ‘the amount of
DW management’, ‘landfill planning’, ‘choosing of demolition methods’, ‘training of
DW management and demolition technique’, ‘sorting platform planning’, and ‘planning
storage for recycled materials’, which were categorised under five themes.
Choosing demolition methods
Choosing demolition technology is very important to DW management because the right
technology leads to reduction of DW generation and improvement of the waste
classification. This is consistent with the finding by Yeheyis, et al. (2013) in that the rate
of reuse and recycling of C&D waste mainly depends on the demolition method employed
to remove materials from a structure. In this light, interview results expressed that it is
important to determine the demolition methods in achieving the cost-effectiveness in DW
management.
Demolition waste management procedures
Determining the procedures of DW management processes was identified as an important
factor influencing the DW management decision-making. This is in line with the finding
by Poon, et al. (2001), which adds that effective waste management on the construction
site usually involves scheduling from waste clearance, waste collection and waste
disposal, which should be developed before construction activities. The interview results
also reflected that scheduling would help contractors manage time effectively, minimise
problems during demolition work and increase the rate of waste recovery. Thus, a detailed
and comprehensive plan of C&D waste management in conducting the construction
169
project is needed to achieve the waste minimisation and high level of recycling waste
(Yeheyis, et al., 2013; Yuan, 2013).
Waste classification and estimation
This theme includes the decision-making factors of on-site sorting and waste estimation,
which has garnered scrupulous attention from the respondents in the questionnaire survey.
Wu and Ann (2014) highlight that on-site sorting that is effectively implemented would
assist the contractors in arranging materials and using them properly. In addition, via this
strategy, the contractors can increase the value of recyclable waste and avoid the pollution
of mixed materials. Interestingly, ‘on-site sorting’ was ranked the third in terms of its
importance by key stakeholders. The result of the interview study also revealed that the
main issues of C&D management in Vietnam include the lack of on-site sorting practice
and the fact that most of C&D waste generated in construction projects was mixed and
even disposed together with municipal solid waste. Thus, it is important to integrate on-
site sorting in DW management plans.
Waste estimations are more supportive of the management process for they enable
operational cost and information of waste generation, which is useful for managers in
controlling projects (Formoso, et al., 2002). It was also discussed in interview results that
DW estimation should be scheduled in the early stage as this information can help
decision makers improve cost and time effectiveness. It is noteworthy that estimation of
DW generation and its components in many urban redevelopment projects is to assess the
feasibility of recycled materials on a large scale.
In line with the importance of waste sorting and waste estimation in implementing DW
management, the DW database, such as waste amounts and compositions, was considered
in developing the supporting decision-making process. For example, the estimation of
metal materials was found to help decision makers in planning for recycling waste,
including recycling storage and waste transport. Four recent urban redevelopment
projects in Ba Dinh district, Hanoi, Vietnam were investigated via a case study in order
to develop the database to be used in urban redevelopment DW management. The amount
of DW and its compositions were calculated for a single aged building and a single
project. The development of database and associated discussion was presented in Chapter
6.
170 Chapter 7: Discussion and Findings
Planning for landfill, sorting area, and storage
It is understandable that the planning of DW from generation, collection, and disposal
offers more benefits to effective DW management, such as increasing the recovery rate,
reducing cost and time of waste transport and remedying the impacts of DW on the
environment. The interview results revealed that the issues of collection, transport, and
disposal of DW need to be addressed by promoting the planning of waste storages, waste
transfer stations and specific waste landfills. In this view, Yuan (2013) highlights that
planning waste recycling facilities based on the transportation distances throughout the
region can save the waste transportation cost and increase the contractors’ awareness of
sending waste to recycling facilities because of the convenience in transportation.
Thus, the saving of time and cost in the DW management process focused not only on
onsite works but also in the transportation of waste to the landfills or storage. The
information of landfills, including the landfill capacity and landfill location, was found to
be important in choosing the most cost-effective options for waste transportation. This
information was used as input data in the case study to compute the scenarios of DW
disposal in the landfills so that the cost-effectiveness considered.
Training
According to del Río Merino, et al. (2009), all construction projects impact the
environment due to the use of raw materials, environmental pollution, energy
consumption, and waste generation. In addition, choosing the appropriate demolition
method can ease on-site waste sorting and increase the waste recovery rate (Poon, et al.,
2004). Therefore, training human resources and skilled personnel involves the decision-
making process, which is a prerequisite for improving DW management in urban
redevelopment projects. However, there was a significant difference between the five key
stakeholders’ perspectives in the survey study. The 2-sample t-test revealed that engineers
and policy makers paid more concern to the need of training in DW management. The
influence of training in DW management was discussed in the interview study, which
helps stakeholders in minimising and classifying of DW. The interview results reflected
that sufficient training for the workforce involved in DW management is the most
important, raising the workforce’s awareness about DW management and the use of
advanced technology in waste classification. The interview results also unveiled that the
limited knowledge of demolition work and waste management may lead to the problems
171
of DW management in urban redevelopment projects, such as the low rate of waste
recovery and increased cost of waste management.
7.3.2 Environmental factors
Five critical factors were identified related to the environmental aspect of sustainability
practice. These factors comprise ‘promotion of 3R’, ‘the willingness of stakeholders’,
‘the uniqueness of DW’, ‘rate of recovery’, and ‘environmental impact assessment’,
which were categorised into four themes.
Stakeholder awareness
Stakeholder awareness refers to the willingness of stakeholders to undertake DW
management. Lack of interest and understanding among stakeholders could hinder the
improvement of DW management in urban redevelopment projects. Interview results
reflected that the efficiency of DW management depends on the awareness of
stakeholders on the classification of DW, waste recycling and waste disposal. Equally
importantly, practitioners’ perspectives on resource saving, environmental protection is a
vital factor of C&D waste minimisation, through changing attitudes towards waste
generation, classification, recycling, and disposal (Manowong, 2012; Osmani, et al.,
2008).
The uniqueness of demolition waste
One of the concerns voiced by stakeholders in the decision-making process is to
understand the nature of DW in order to implement effective DW management. However,
interview results reflected that the characteristics of DW presented a low potential of
recycling compared to waste from new construction. Poon (1997) also highlights that
masonry, wood, concrete and brick typically produced more than half of DW
management. The different economic contexts would lead to the difference in the
selection of construction materials. In addition, the survey results showed that engineers
paid less attention on this factor than other groups including academics, planners, and
consultants. This suggests that insufficient knowledge of DW may lead to a poor DW
management plan for waste recycling, waste reuse, and waste disposal. Thus, there is a
need for investigating the DW characteristics in the early stage to assist the decision
makers for effective DW management.
172 Chapter 7: Discussion and Findings
‘3R’ strategies and recovery
The survey results show that ‘3R’ principles and waste recovery are the key decision-
making factors of DW management in urban redevelopment projects. These strategies
should be given high priority when selecting waste disposal measures (Peng, et al., 1997)
since that could increase waste recovery rate and remedy environmental impacts, as well
as pressure on landfills. This finding resonates with the study by Yeheyis, et al. (2013) in
which reusing and recycling of C&D waste are considered the challenges to the
management of large amounts of waste, in achieving sustainable construction. However,
in Vietnam, 3R strategy is often neglected by contractors for many reasons, such as the
lack of stakeholders’ awareness, poor waste management plans and the lack of low waste
technology applications. Therefore, promoting 3R in C&D waste management yields to
a higher waste recovery rate.
In order to effectively implement 3R strategies, the DW compositions need to be clearly
assessed. The estimations of different kinds of DW, such as bricks, metal, and mortar, are
supportive of reuse and recycling plans so as to increase the rate of waste recovery. For
example, based on the amount of mortar, contractors can compute for the rate of on-site
reuse or reuse for other construction elements. Therefore, the decision-making factor of
‘rate of recovery’ was selected to be computerised in the GIS-based model as presented
in Chapter 6.
Environmental impact assessment
Environmental impact assessment is a particularly important process of evaluating the
likely environmental impacts of a project that needs to be considered in urban
redevelopment DW management with regard to sustainability. The study by del Río
Merino, et al. (2009) highlights that all construction projects impact the environment
through the use of raw materials, environmental pollution, energy consumption, and
waste generation. Therefore, environmental impacts assessment is required to examine
the anticipated environmental effects of urban redevelopment DW management projects.
Although this approach is regulated in Vietnam’s law on environment protection, it is still
not effectively implemented.
173
7.3.3 Economic factors
Cost estimation and cost-effectiveness
Three critical factors were investigated related to the economic aspect of sustainability
practice. These factors included ‘cost-effectiveness’, ‘cost of demolition’, and ‘cost of
waste transport’, which were categorised into the theme of ‘cost estimation and cost-
effectiveness’. Cost-effective plans would assist stakeholders in saving energy and the
DW management cost, as well as the cost of demolition work. The study by Yeheyis, et
al. (2013) highlights that contractors must thoroughly analyse about the feasible cost of
waste reduction and the environmental impacts of C&D waste in order to avoid the
unnecessary extra cost and re-work during the construction.
In the survey study, the factor of ‘cost of waste transport’ was perceived differently by
stakeholders. Engineers and policy makers consider waste transport with high importance
level, while planners and consultants did not have significant concern for this factor.
However, the results from the interview study reflected that the evidence of the cost
saving of DW management can assist the contractors in implementing DW management
effectively, which include the cost of demolition and cost of DW management delivery.
Therefore, cost efficiency should be considered before projects are implemented.
Since stakeholders in Vietnamese urban redevelopment projects were found to be
reluctant to implement DW management, it is imperative to assess the cost-effectiveness
of DW management, including waste transportation, in order to reduce the cost of
management. Therefore, the two economic factors which are cost-effectiveness and cost
of waste transport were elaborated in the GIS-based model via a case study. This involved
the analysis of the number of trucks for loading of different types of DW and the optimal
routes of waste transport to the landfills.
7.3.4 Social factors
Only two critical factors were investigated related to the social aspect of sustainability
practice. These factors comprised ‘preservation’ and ‘reduction of community
disturbance’.
Preservation
174 Chapter 7: Discussion and Findings
Preservation refers to minimising the impacts of DW management on natural resources
and preserving cultural heritage. Heritage should be preserved properly for the enjoyment
of society through different generations (Fung, 2004). Interview results revealed that the
government should adopt a policy on integrated sustainable DW management that covers
aspects such as preservation of surrounding areas. This is consistent with the findings by
Chan and Lee (2008b), in that the preservation of historical structures and features is one
of six considered urban design factors in achieving sustainable urban renewal. Therefore,
natural resource preservation and reduction of environmental impacts on the
neighbourhood should be seriously considered to achieve sustainability.
Reduction of disturbance on the community
Similarly, reducing the impacts of environmental pollution and noise pollution on the
community is important in making decisions about DW management. Interview results
indicated that the Vietnamese government needs to give priority to reducing the impacts
of environmental pollution and noise pollution on the community, in addition to the
conventional objectives such as economic and environmental ones. The study by Farfel,
et al. (2005) highlights that stakeholders should be more aware of demolition-related
public health problems because the process of urban redevelopment acts as a major source
of lead released into the environment. Thus, consideration of project social performance
is strictly required to ensure a better quality of life for the community.
7.3.5 Institutional factors
Five critical factors were found related to the institutional aspect of sustainability practice.
These factors comprised ‘providing guidelines’, ‘stakeholders’ responsibilities’, ‘roles of
stakeholders’, ‘regular information update’, and ‘understanding the procedure’, which
were categorised under three themes.
Regulations/guidelines
This theme includes understanding the DW management procedures and providing
guidelines of DW management, which refers to promoting the best practice guidelines.
Among all influenced factors, ‘Guidelines of DW management’ received the highest
rating from five of the key stakeholder groups. This finding echoes the notion that a good
policy system is considered the most important factor of successful waste management in
175
construction projects (Lu & Yuan, 2010). In fact, interviews conducted in Vietnam
demonstrated that DW management is not normally expected to offer profits to
contractors due to the costs of equipment and management approaches; thus, stakeholders
may be reluctant to manage DW. Consequently, in order to fulfil the stakeholders’
responsibilities in DW management, the government should issue the guidelines for
assisting all stakeholders in understanding the procedures of DW management.
Stakeholder engagement
This theme pertains to the factors of the responsibility of stakeholders involved in the
DW management process and their roles in monitoring and providing feedback on DW
management, as was revealed from the survey study. In Vietnam, stakeholders’
responsibilities are too general and obscure in the construction industry. The fuzzy
responsibility between the government agencies and the local authorities in C&D waste
management obstructs the better C&D waste management practice (Yuan, 2013). Specific
responsibilities need to be clearly allocated in urban redevelopment DW management. In
addition, in order to fulfil the stakeholders’ responsibilities in DW management, the
government should issue the guidelines for supporting all stakeholders involved in site
management and site planning for waste management.
Information and communication
The component involved in this theme is regular information update, which is essential
communication among stakeholders in effective urban redevelopment DW management.
In Vietnam, the DW information is difficult to update and control because of the illegal
disposal of C&D waste and a poor DW management plan. It is imperative to formulate
policies to encourage the contractors to share and report the waste management
information.
The finding by Shen, et al. (2007) also highlights that it is necessary to provide a tool to
expedite stakeholders’ access to the project information and share the knowledge and
information, while collaborating for better project performance. It is noteworthy that
sharing information about DW management should be required in the early stage of
demolition work to avoid the increase in the cost of waste management as a result of
miscommunication.
176 Chapter 7: Discussion and Findings
In conclusion, the responses of the interviewees indicated that the critical factors
identified in the survey study are important to improve DW management in urban
redevelopment projects in Vietnam. In addition, the action plans were proposed by
interviewees in order to solve the problems associated with each factor. The interview
findings also provided the suggested actions corresponding with critical decision-making
factors, which were towards improving DW management in Vietnamese urban
redevelopment projects (Table 5-4). Based on the action plans, the DW databases were
identified to support decision makers to make decisions about DW management in urban
redevelopment projects.
The crucial information of DW management includes the volume of DW and its
components, the rate of recycled materials, and the distances of waste transport. With
reference to the decision-making process, specific factors for DW management were
identified. The crucial information is in accordance with the critical factors: (1) on-site
sorting, (2) rate of waste recovery, (3) waste estimation, and (4) planning area for
landfills. This DW database also provided a cost-effective analysis, which answers the
questions related to two critical factors: (1) cost-effective demolition plans and (2) cost
estimation of waste transport. All of DW database was integrated in the GIS-based model,
which supports the requirement of regular information updates.
7.4 GIS-BASED DECISION SUPPORT SYSTEM
Based on the critical factors extracted from survey and interview study, the supporting
database of DW management decision-making was introduced in a GIS-based tool. The
critical factors are considered to be analysed to answer the question regarding the type of
information, which is crucial in developing a supporting database of DW management,
including six factors: (1) on-site sorting, (2) rate of waste recovery, (3) cost-effective
demolition plan, (4) waste estimation, (5) cost estimation of waste transport, and (6)
landfill planning. Based on these critical factors, the supporting database includes the
information of DW volume, DW types, and DW transport, and the selection of landfill
sites.
Accordingly, crucial information about DW should be given to DW management
characteristics in an urban redevelopment context. This aimed to address the third
177
research question: What is the necessary information to support key stakeholders in
demolition waste management in Vietnamese urban redevelopment projects at the district
level?
A case study of four urban redevelopment projects in Ba Dinh district was adopted to
develop the database of DW. Estimating the generation of DW helped in classifying DW
components of bricks, mortar, concrete, and metal. Through the GIS-model, a
comprehensive supporting database for decision-making was provided. In the database,
the portion of potential recycled materials such as metal is relatively low, accounting for
0.3% to 0.7%. This is due to the nature of DW in urban redevelopment projects in
Vietnam.
However, reuse and recycling of the components such as bricks, mortar, and concrete
should be considered for such purposes as reuse on-site, public fills, or road base. The
information of the amount of DW components in Ba Dinh urban redevelopment projects
can help contractors devise plans of effective reuse or recycling of waste.
In addition, the number of pick-up trucks was estimated for inert materials such as brick,
mortar, and concrete. It is hard to accurately estimate the required number of trucks for
metal materials in demolition sites due to the large volume. Furthermore, the optimal
routes of DW transport to the C&D waste landfill sites and the landfill sites’ capacity per
day were provided in a GIS-based model. This supporting information can save
contractors time and cost of DW management. For example, the fuel consumption of DW
transport can be reduced by choosing the optimal routes.
The supporting database maps generated are beneficial towards DW management
decision-making in urban redevelopment projects. These maps present a quantitative and
objective reference for the decision-making process, which helps decision makers on the
subjective and qualitative judgement. As the demolished buildings in four urban
redevelopment projects in Ba Dinh district are aged over 40 years and their structured
information is not sufficient, GIS-based model is the most suitable in DW management
at the district level. It makes great use of the information stored in spatial maps by
incorporating the GIS map displayed in spatial information, of each building in each
project at the district level.
178 Chapter 7: Discussion and Findings
7.5 FINALISED DECISION-MAKING FRAMEWORK
Based on the findings of the survey and interview study, the proposed framework
presented in Chapter 4 (Figure 4-2) was finalised by integrating the findings from the case
study. The finalised decision-making framework is shown in Figure 7-1. This, together
with the development of a decision support system, helps achieve the third research
objective, which is ‘developing a decision-making framework and critical supporting
information to assist decision makers in improving demolition waste management in
urban redevelopment projects at the district level’.
The finalised decision-making framework consists of the decision-making factors and
supporting database, which facilitates stakeholders to effectively assess and qualify the
demolition waste database in different urban redevelopment projects. The 24 decision-
making factors were explored by investigating the multi-criteria of DW management
issues in the background literature and analysing both quantitative and qualitative data in
the survey and interview study. Thus, the conceptual framework was validated upon the
perspectives of key stakeholders in Vietnam, which are argued to contribute to addressing
the DW management issues in Vietnamese urban redevelopment projects. Meanwhile,
special consideration of supporting database was placed on six critical factors. These
critical factors were analysed and computerised to develop database of DW in GIS-based
model with spatial and attribute information.
The integrated framework creates a collaborative platform of DW management
information. The engagement of stakeholders in assessing and qualifying the DW
database before the demolition process becomes a key factor contributing to the
effectiveness of DW management in urban redevelopment projects. The finalised
decision-making framework is beneficial to decision makers in making decision in
Vietnamese urban redevelopment DW management. Firstly, perspectives of integrated
waste management and sustainable urban redevelopment are embedded in the framework,
which reinforce the importance in raising stakeholders’ awareness. In addition, a GIS-
based model, as the decision support tool, facilitates decision makers in analysing DW
database for the purposes of cost and plan effectiveness. Thirdly, stakeholders can easily
communicate with other stakeholders participated in the decision-making process. With
the decision-making framework and the support of the GIS model, the stakeholders can
179
effectively convey their ideas about the influencing factors and crucial information to
other stakeholders. As a result, considering sustainability aspects, costing and planning
effectiveness and stakeholders’ communication can help improve the decision-making
process of urban redevelopment DW management.
Thus, a plan aiming at saving cost and time, while minimising the environmental impacts
should be taken into account in achieving effective DW management. The integration of
a GIS-based model and the decision-making framework is a typical example of
collaborative decision-making in improving urban redevelopment DW management at
the district level in Vietnam.
It is noteworthy that the ages of old buildings in Vietnamese urban redevelopment
projects are commonly over 40 years old. Thus, the compositions of DW may be different
from that in other countries. In addition, due to the specific economic and policy context
in Vietnam, the decision-making factors may be rated differently by the five stakeholder
groups from that in other developed and developing countries. However, the proposed
decision-making framework may be considered in similar developing countries, such as
China, Brazil, and India which have similar considerations in urban redevelopment
projects, stakeholder engagement, and development context.
180 Chapter 7: Discussion and Findings
DW
man
agem
ent i
n ur
ban
rede
velo
pmen
t pro
ject
s
Technical
Choosing demolition method
DW management procedures
DW estimation The total volume of DW generation
DW classification The volume of devided materials
Planning for landfill, sorting area and storage Landfill location and capacity
Training
Environmental
Stakeholder awareness
The uniqueness of DW
3R strategies and recovery The information of reused materials
Environmental Impact Assessment
Economic
Cost-effectiveness
Distances to landfill, number of pick-up trucks, landfill information, and potential recycled DWCost estimation of demolition
Cost of DW transport Distances to landfill and number of pick-up trucks
SocialPreservation
Reduction of disturbance
Institutional
Best pratice guidelines
Stakeholder engagement
Information & communication
Decision-making factors Supporting database
Attribute data
Spatial data
. Land-use map/satellite image of sites to be redeveloped
. Locations of projects and C&D waste landfill sites
. Map of transport networks
Quantitative support
. Building information (name, address, structure type, surface areas)
GIS tools
Figure 7-1: Finalised decision-making framework for improving DW management in urban redevelopment projects at district level
181
7.6 FINDINGS RELATED TO THE EXTANT LITERATURE
Urban redevelopment is a hot topic emerging globally, particularly in developing
countries (Zheng, et al., 2014). As a result, a big issue concerning practitioners and
academics for years is DW management decision-making with regard to sustainability
in urban redevelopment projects, as reviewed in Chapter 2. The recent research has
contributed to DW management in urban redevelopment projects regarding decision
support, environmental challenges, stakeholder engagement, strategy and solution, and
evaluation.
The key knowledge gaps in current research and recommendations for future research
were identified under four main topics: decision support, decision-making, stakeholder
engagement, and evaluation. Thus, there is potential to explore and expand knowledge
in these disciplines, particularly in view of the complexities and challenges involved
in implementing DW management in urban redevelopment projects. The knowledge,
insights, and recommendations provided help establish a framework to critically
address the issues associated with urban redevelopment DW management in order to
further promote the sustainability of urban redevelopment. The integration of the
framework with the GIS-based database is an effective support for the decision-
making process.
The results from the survey and interviews revealed critical factors that guide the
improvement of DW management in urban redevelopment projects. These factors also
formed a basic knowledge for DW management in achieving sustainable urban
redevelopment. In addition, the findings of the research indicate that effective DW
management expanding to sustainable practices should be supported by the
willingness of the stakeholders to improve their knowledge and skills. The interviews
in this study also discussed the significant factors needed to improve DW management
in urban redevelopment projects, which provided profound insights from the experts
and verified the theoretical assumptions and survey results.
The essence of this research is to find more knowledge and add to the existing body of
knowledge that integrates the supporting database with the decision-making
framework to support decision makers in making decisions about DW management in
urban redevelopment projects. Accordingly, within the GIS-based system, a platform
182 Chapter 7: Discussion and Findings
of DW information is created and updated before and during the demolition process,
which is very helpful in urban redevelopment DW management. In addition, the
suggestions of action plans for improving DW management decision-making were
sourced from experienced and knowledgeable experts. Furthermore, the research
findings can be served as a reference for other developing countries that have similar
urban redevelopment contexts as Vietnam.
7.7 SUMMARY
This chapter discussed the findings from the four main research stages, namely the
literature review, survey study, interview study, and finally case study, which were
integrated into the finalised decision-making framework. The background literature
provided a strong basis for developing the conceptual framework, by accounting all
the five sustainability aspects including technical, environmental, economic, social,
and institutional. The insight and perspectives of the five respondent groups in the
survey study were analysed to identify 24 critical factors for efficient decision-making.
Semi-structured interviews were carried out to identify each critical factor thoroughly
while framing action plans in order to improve Vietnamese urban redevelopment DW
management decision-making. The multi-criteria analysis in the survey and interview
study validated the conceptual framework, which is argued can improve DW
management toward more sustainable urban redevelopment in Vietnam. In addition,
based on the critical factors identified by quantitative analysis and the action
plans explored by qualitative analysis, six critical factors were further analysed and
computerised to develop the supporting database for DW management decision-
making. The supporting database included spatial and attribute information of urban
redevelopment DW management at district level.
The research findings were finalised to form the decision-making framework by
integrating the validated framework and supporting database of DW management.
From a practical perspective, the finalised decision-making framework can provide
comprehensive and multi-criteria references with both spatial and attribute information
for decision makers in urban redevelopment DW management at district level.
183
Chapter 8: Conclusion
8.1 INTRODUCTION
Demolition waste is a critical environmental issue for the construction industry. Both
developed and developing countries are facing challenges in the form of urban
redevelopments that generate large amounts of DW. The demolition of existing
buildings is a predominant feature of urban redevelopment and therefore its waste
management is particularly important. However, there is still a lack of accurate
construction waste data, especially in developing countries (Wu, et al., 2014). This
may be due to the focus of previous research on both construction waste and
demolition waste, leading to a gap in the understanding of DW, particularly that of
urban redevelopment projects. Furthermore, there are many challenges in managing
urban redevelopment DW due to the complexities involved, such as poor waste
management planning, the overlapping of responsibilities and ineffective time and cost
management (Lu, Lau, & Poon, 2009; Wu, Yu, Shen, & Liu, 2014). The above issues
warrant the research presented in this dissertation to promote sustainability and
improve urban redevelopment DW management by establishing a decision-making
framework tailored to the Vietnamese urban redevelopment context.
This chapter outlines the achievement of the stated research objectives, presents an
overview of the research conclusion, highlights the research contributions and
limitations, and finally recommends the implications for future research.
8.2 REVIEW OF RESEARCH OBJECTIVES AND DEVELOPMENT PROCESSES
The aim of this research was to develop a comprehensive decision-making framework
for improving DW management in Vietnamese urban redevelopment projects at the
district level. Three main objectives were established in order to achieve the research
aim, as follows:
(1) To explore the current DW management in urban redevelopment projects and
in the context of Vietnam.
184 Chapter 8: Conclusion
(2) To identify critical decision-making factors of DW management in urban
redevelopment projects.
(3) To develop a decision-making framework and critical supporting information
to assist decision makers in improving demolition waste management in
Vietnamese urban redevelopment projects at the district level.
These research objectives serve as a guide throughout the entire research process
(Figure 3-3) in order to achieve the research aim. A mixed method was employed in
this research, applying three different methods to answer the research questions and
achieve the research objectives. The research methods adopted correlating research
objectives are presented in Table 8-1.
The achievement of the first research objective is the domain of information related to
urban redevelopment DW management on a global scale and in the context of Vietnam
(presented in Chapter 2). Based on this useful information, the research gaps were
identified and the list of 53 research decision-making factors was formulated.
Accordingly, the conceptual framework was investigated in the literature review
process (Figure 2-11, Chapter 2).
Table 8-1: The research design related to research objectives
Research objectives Methods Tools
Exploring the current DW management in urban redevelopment projects and in the context of Vietnam
- Literature review
- Document
review
Identifying critical decision-making factors of DW management in urban redevelopment projects at the district level
- Questionnaire
survey - Interview
- Quantitative
analysis - Qualitative
analysis Developing a decision-making framework
and critical supporting information to assist decision makers in improving demolition waste management in Vietnamese urban redevelopment projects at the district level
- Case study
- Quantitative
analysis - GIS-Based
The second objective was designed to answer research questions one and two, which
are, ‘what are the key decision-making factors influencing demolition waste
management in Vietnamese urban redevelopment projects? And how do the key
decision-making factors influence demolition waste management in Vietnamese urban
185
redevelopment projects?’ The survey and the interview study were conducted to
achieve the second research objective (presented in Chapters 4 and 5). Subsequently,
a list of 24 critical factors was identified and the conceptual framework was then
revised (Figure 4-2). In addition, the action plans were synthesised from the
interviewees’ suggestions for improving DW management in Vietnamese urban
redevelopment projects.
Based on the results achieved from the previous study, a case study was conducted in
order to identify the crucial information that is needed for DW management decision-
making in urban redevelopment projects (presented in Chapter 6). The supporting
database was integrated in a GIS-based model to address the third research question:
What is the necessary information to support key stakeholders in demolition waste
management in Vietnamese urban redevelopment projects at the district level? The
integration of the proposed decision-making framework and the supporting database
was finally developed to achieve the third research objective (Figure 7-1 in Chapter
7).
8.3 DECISION-MAKING FRAMEWORK FOR IMPROVING DEMOLITION WASTE MANAGEMENT IN VIETNAMESE URBAN REDEVELOPMENT PROJECTS
The aim of this research has been fulfilled and a decision-making framework has been
developed that is argued to improve DW management in Vietnamese urban
redevelopment projects. The research conclusions synthesised from the key findings
reported in the previous chapters are presented in the following sections.
8.3.1 The factors influencing demolition waste management in Vietnamese urban redevelopment projects
In the context of Vietnam, there is a lack of regulation supporting DW management in
the Vietnamese construction industry, especially in urban redevelopment projects. In
addition, obtaining reliable data on C&D waste is not easy, as data in this discipline is
often managed together with municipal waste data, which makes it difficult to
precisely estimate the amount of DW in urban redevelopment projects.
Based on the literature review, 53 research factors that have the potential to improve
DW management in urban redevelopment projects in Vietnam were investigated. The
wording of these factors was essentially based on the comprehensive review of related
186 Chapter 8: Conclusion
knowledge acquired from the literature review. The relevant literature for each factor
was presented in Table 2-2 in Chapter 2, which represents a wide range of experiences
from researchers and practitioners in different countries and regions. It is important to
identify the most influencing factors for the context of Vietnamese urban
redevelopment. It is noteworthy that the concept of sustainable urban redevelopment
is embedded in the research factors, which were categorised into five categories:
technical, environmental, economic, social, and institutional.
The findings from the literature review were used as a baseline for developing the
questionnaires in the survey study. A questionnaire survey was adopted to investigate
the critical factors, which are of significant concern among key stakeholders in making
decisions about DW management in the context of Vietnamese urban redevelopment
projects. The survey was designed on the basis of 53 decision-making factors
identified in the literature review. Five groups of respondents that have been working
in the field of DW management in Vietnamese urban redevelopment projects were the
targeted key stakeholders from different organisations in three main cities in Vietnam
(Hanoi, Hai Phong, and Ho Chi Minh City), including academics, planners,
consultants, engineers, and policy makers. The respondents were asked to rank the
level of importance of each factor based on their knowledge and experience.
The quantitative analysis revealed 24 critical factors that have a significant influence
on improving DW management in Vietnamese urban redevelopment projects
(presented in Table 4-9, Chapter 4). Interestingly, three critical factors (training of DW
management, cost estimation of waste transport, and the uniqueness of DW),
represented significant differences between respondents’ perspectives. Thus, the
conceptual framework was revised based on identified 24 critical factors which were
categorised into five categories related to sustainability (presented in Figure 4-2 in
Chapter 4).
The top-five critical factors in the rankings were in the categories of institutional and
technical, wherein three factors were in the institutional category: providing guidelines
of DW management plan, regular information update, and understanding of
stakeholders’ responsibilities, which were ranked first, third, and fifth respectively.
This echoes the notion that the right decision can be made if the institutional factors
that contribute to effective DW management are considered. In this light, Yuan (2013)
also indicates that the lack of accurate regulations of C&D waste is one of the reasons
187
for the poor C&D waste management. Therefore, accomplishing policies and strategies
will help decode the problems, which are too general or not detailed enough for
implementing DW management in urban redevelopment projects.
In addition, updated and accurate information of DW is required for essential
communication among stakeholders in effective urban redevelopment DW
management. In support of this finding, Shen, et al. (2007) provide a tool to enable
stakeholders to access the project information and share the knowledge and
information while working together towards better project performance.
Consequently, this research developed a GIS-based model for storing and displaying
the supporting database to aid decision-making in this area. Furthermore, the
misalignment of stakeholder responsibilities in C&D waste management is another
contributing factor hindering better C&D waste management practice (Yuan, 2013).
Thus, it is significant finding to identify who needs to participate in the construction
waste management process (Manowong, 2012).
Two other critical factors of the top five in the rankings were in the technical category,
including on-site sorting and determining the DW management procedures, which
were ranked second and fourth respectively. It is of note that on-site sorting, when
effectively implemented, can assist the contractors in arranging and using materials
properly (Wu & Ann, 2014). Thus, this factor, together with the factor of waste
estimation, needs to be seriously considered in DW management, as it can be used to
develop the DW database. In addition, defining C&D waste management procedure
should also be seriously considered in effective waste management planning,
particularly scheduling before construction activities (Poon, et al., 2001). Thus, this
finding suggests there is a need for a detailed and comprehensive plan of C&D waste
management to achieve waste minimisation and a high level of recycling waste
(Yeheyis, et al., 2013; Yuan, 2013).
Regarding environmental performance, six critical factors were determined as an
important influence on urban redevelopment DW management. To be specific, the
factor of ‘promotion of 3R in DW management’ was explored as the most important
factor in the environmental category and was ranked eighth of all given factors. The
reason for promoting 3R strategies is offering the benefits in reducing the use of raw
materials and converting more recyclable from the landfills (Abbas, et al., 2006).
188 Chapter 8: Conclusion
These strategies were considered by Peng, et al. (1997), as an important factor in
choosing waste management measures. Moreover, the second environmental factor,
‘stakeholder awareness’ was ranked twelfth in the rankings. This resonates with the
confirmation that this factor proves valuable in waste minimisation through changing
practitioners’ attitudes towards waste generation, classification, recycling and disposal
(Manowong, 2012; Osmani, et al., 2008).
Regarding economic performance, three critical factors were considered to have an
important influence on urban redevelopment DW management. The first economic
factor was ‘cost-effective demolition plan’, which was ranked seventh in the rankings.
This factor is broadly considered as an important factor of a successful and sustainable
C&D waste management (Wang, et al., 2004). Regarding social performance,
“preservation of natural resources, cultural, and heritage” was one of the only two
social critical factors, which was ranked sixth. Broadly, this factor is defined by Chan
and Lee (2008b) as one of the most considered urban design factors in attaining
sustainability in urban renewal.
In conclusion, the rankings of the critical factors of the research suggested a strong
relationship to all five aspects of sustainability in urban redevelopment DW
management. Through the survey data analysis, the first research question was
addressed by identifying 24 critical factors that significantly influence DW
management in urban redevelopment in Vietnam.
8.3.2 Action plans for improving demolition waste management in Vietnamese urban redevelopment projects
The interviewees in the interview study were asked to provide their comments on how
influential each critical decision-making factor is, in improving DW management in
Vietnamese urban redevelopment projects, and what action is required to improve DW
management in relation to each factor. The qualitative approach was selected as a tool
to analyse interview results to sort out the action plans suggested by interviewees.
Results from this method affirmed that the second research question was addressed,
which was “how do the key decision-making factors influence demolition waste
management in Vietnamese urban redevelopment projects?”
Similarly, to the questionnaire participants, the interviewees represented five key
stakeholder groups. Among the 22 interviewees, four were researchers, three were
planners, three were consultants, five were engineers and seven were policy makers.
189
All the interviewees generally agreed that the proposed framework covered the major
factors. These 24 critical factors were confirmed by the interviewees as important
factors in improving DW management in Vietnamese urban redevelopment projects;
therefore, should be considered to improve DW management in Vietnamese urban
redevelopment projects. The findings from the interview study were analysed as
possible actions of improving urban redevelopment DW management in Vietnam,
which were grouped into 15 main themes of critical factors (presented in Table 5-4,
Chapter 5).
With regard to the five themes of technical performance, eleven action planning areas
were suggested by interviewees to improve DW management in Vietnamese urban
redevelopment projects. One engineering manager emphasised that technology leads
to the reduction of DW and the improvement of the waste classification. However,
there is a need for government support and consultation in ‘choosing demolition
methods’, particularly, the application of environmentally-friendly technology.
Defining clearly DW management procedures in the early stage of demolition work
was the action plans suggested for the theme of ‘DW management procedures’.
Interview findings also related to the theme of ‘waste classification and estimation’.
First, interviewees suggested the classification of DW should be implemented on-site
of the demolition. In order to encourage on-site waste classification, waste sorting
should be improved and the use of recycled materials should be promoted. In addition,
DW estimation can be a prerequisite of DW management that should be considered
before the demolition stage. Subsequently, the DW information could assist decision
makers and contractors in planning waste classification and waste recycling.
The theme of ‘planning for landfill, sorting area, and storage’ received attention from
the interviewees and suggested DW management including giving priority to landfills
and transfer station planning; identifying suitable sites for transfer stations and
landfills was considered important. From these, identifying suitable landfill sites and
transfer stations appears to be needed in order to develop DW delivery plans and
reduce costs for DW transport, particularly for the large-scale DW volume from
different urban redevelopment projects at the district level. ‘Training’ was considered
as an important factor in improving urban redevelopment DW management. Providing
appropriate training courses in DW management and demolition technology was
190 Chapter 8: Conclusion
proposed in order to advance stakeholders’ skill levels in demolition and waste
classification, particularly skill in capturing the benefits of low waste technology. Such
training raises the stakeholder awareness of DW management and waste classification.
Seven action plans relating to the four themes of environmental performance were
conveyed by interviewees to improve DW management in Vietnamese urban
redevelopment projects. In order to raise stakeholder awareness, interviewees
suggested the government should promulgate C&D waste policies to encourage
stakeholder engagement in urban redevelopment DW management. In addition,
identifying the DW characteristics in the early stage is crucial to understand what type
of DW is contained in the building to be demolished. This, together with the
‘promotion of 3R strategies’ and policies in increasing reuse and recycled waste, could
increase waste recovery rate and minimise DW disposal in the landfill. Regulating
strict environmental policies was also suggested to ensure there was an obligation in
the implementation of ‘environmental impact assessment’ for each urban
redevelopment project in order to address the environmental impacts associated with
DW management.
Two action plans were recommended by interviewees for the theme of economic
performance, which are the development of cost-effective scenarios and cost
estimation for specific stages of DW management. The information of cost analysis of
DW management could help decision makers select the most effective DW
management scenarios, and save costs of DW collection, DW transport, DW recycling,
and DW disposal. Regarding two themes of social performance, two action plans were
nominated, which are the integration of ‘preservation’ into DW management and
prioritising the ‘community’s safety’ in the project’s objectives. These require the
stakeholders to pay attention to environmental protection and the quality of a
neighbourhoods’ life in DW management.
Nine action plans relating to the three themes of institutional performance were
suggested by interviewees to improve DW management in Vietnamese urban
redevelopment projects. Interviewees suggested providing the best practice guidelines
to assist all stakeholders and encourage the development of a deep understanding of
the procedures of DW management, their responsibilities, and the institutional
arrangement in DW management. In addition, in order to improve the stakeholder
engagement, it was suggested the government should take the leading role in DW
191
management, and also highlighted was the importance to incorporate the sustainability
element in DW management regulations to encourage stakeholders to get more
involved in DW management in urban redevelopment projects. Developing the DW
database and regular reporting were suggested with a view to improving the
‘communication’ among stakeholders. These would also help stakeholders efficiently
communicate and share information in the pre-demolition stage, during the demolition
stage, and in the post-demolition stage.
In conclusion, interviewees supported the claim that all 24 critical factors play an
important role in improving DW management in Vietnamese urban redevelopment
projects. In addition, the action plans suggested by the interviewees supported six
identified critical factors that could be used to develop the DW database and improve
the DW management decision-making process.
8.3.3 Supporting database for urban redevelopment demolition waste management decision-making process
The interview results identified six critical factors that can provide valuable support
for decision makers in the DW management decision-making process in urban
redevelopment projects, including (1) on-site sorting, (2) rate of waste recovery, (3)
cost-effectiveness demolition plan, (4) estimation of DW, (5) cost estimation of waste
transport, and (6) landfill planning. A case study was conducted to define the six above
critical factors to fulfil the factor of ‘information update’, which was ranked as the
third critical factor in the rankings (presented in Figure 7.1, Chapter 7).
In order to support the DW management decision-making process in urban
redevelopment projects, essential information was collected to develop a supporting
database. The information from the four projects in this case study is shown in Table
6-1, Chapter 6. There are two sources from where the data is collected.
The process of the supporting database development included three steps as follows.
First, the collected attribute data were calculated through Excel software. Second, the
spatial data were processed through ArcGIS software, to be integrated and linked with
the attribute data. Finally, the crucial data information was stored in the form of map
layers.
192 Chapter 8: Conclusion
Subsequently, the volume of DW and its components were estimated (presented in
Appendix D). The DW estimation was calculated for each type of DW (brick, mortar,
concrete, and metal) and the total of DW in four projects. The GIS maps were used to
integrate the data of DW with each building and each project (presented in Figure 6-4
and 6-6, Chapter 6). It is argued in this thesis, that this information can assist decision
makers in planning demolitions, estimating DW management cost-effectiveness and
can potentially save time in decision-making relating to the reuse and recycling of
construction waste.
In addition, based on the total volume of inert DW, including brick, mortar, and
concrete, the number of pick-up trucks was calculated (presented in Figure 6-7).
Accordingly, decision makers and contractors could plan an effective DW transport
plan that could help reduce the time and the cost of transport. Furthermore, based on
the number of C&D waste landfill sites in Hanoi, the landfill site capacity per day, and
landfill site locations, the scenarios of choosing suitable landfill were presented in
Figure 6-8. It is argued that this approach can assist decision makers analyse the cost-
effectiveness of DW transport.
The case study provided useful information for decision makers in DW management
in urban redevelopment projects in the areas of waste estimation, waste classification,
waste transport, and selection of landfill sites. In addition, the case study demonstrated
the possibility for project managers to update DW management information to allow
all stakeholders to access and communicate throughout the DW management process.
Subsequently, the decision-making framework for improving DW management in
Vietnamese urban redevelopment projects was developed based on the integration of
24 critical factors and the supporting database (presented in Figure 7-1, Chapter 7).
8.4 RESEARCH CONTRIBUTIONS
The ultimate contribution of the research is suggesting a decision-making framework
consisting of key decision-making factors, and a database to assist the decision-making
process of DW management in Vietnamese urban redevelopment projects. The holistic
consideration of sustainable aspects and extensive participation of key stakeholders
makes it possible to contribute to both academia and industry practice.
193
8.4.1 Contribution to academic knowledge
(1) Improving the current literature of demolition waste management in urban
redevelopment projects in developing countries
DW management has received much attention over the last two decades as one of the
main indicators of sustainable construction. However, the literature review revealed
that there is a general lack of research effort relating to DW management in urban
redevelopment projects. Although the current literature provides a broader coverage
of C&D waste management in the construction industry, it does not focus specifically
on DW management, particularly in the field of urban redevelopment in developing
countries. This research identified four main knowledge gaps and recommendations
for future research were offered in the developing countries context, namely:
stakeholder engagement, decision support, environmental challenges, strategy and
solutions, and performance evaluation.
(2) Providing new knowledge in the decision-making process of DW management
in urban redevelopment projects with a focus on sustainability.
As an early contribution, this research addressed the identified research gaps and
provides a holistic interpretation of important decision-making factors to be considered
in DW management in the urban redevelopment projects, particularly in developing
countries. There was no previous research pertaining to a holistic view of the decision-
making process for improving DW management in urban redevelopment projects. All
of the research factors were sparsely studied in different research projects within the
field of urban redevelopment DW management. However, these factors were complex
and strongly linked to sustainability. In this research, the sustainability thinking is
embedded in the affecting factors represented as multi-criteria for improving DW
management, where technical, environmental, economic, social, and institutional
aspects overlap.
In this research, the critical factors were identified based on the consensus of key
stakeholders in DW management in Vietnamese urban redevelopment projects,
namely academics, planners, consultants, engineers, and policy makers. Therefore,
the research contributes to new knowledge of multiple stakeholders’ perspectives on
the critical decision-making factors for improving DW management in urban
redevelopment projects. The comparative analysis provides the platform to balance
194 Chapter 8: Conclusion
five aspects of sustainable urban redevelopment and identifies consensual critical
decision-making factors for improving DW management. The research findings
provide a strong foundation for other researchers investigating DW management in
developing countries, particularly related to the identified factors influencing DW
management in urban redevelopment projects at different levels.
The case study incorporating the GIS-based model also provides a new knowledge in
developing a support system and the associated information for making DW
management decision in urban redevelopment projects. This finding helps decision
makers take into account multiple criteria in the decision-making process, which
involves both spatial and attribute database.
8.4.2 Contribution to the industry practice
(1) Implications for the demolition waste management participants
The involvement of five key stakeholder groups in the questionnaire survey and the
interview study provides a unique contribution in understanding different practitioner
perspectives on factors affecting DW management in urban redevelopment projects.
The critical factors encompassed all five aspects of sustainable project performance,
including technical, environmental, economic, social, and institutional. These results
can potentially assist specific stakeholders to increase their awareness of sustainability
and to solve problems associated with DW management.
Research results relating to the influencing factors suggest that a sustainable approach
is essential in improving the overall performance of DW management in complex
urban redevelopment projects, particularly in developing countries. The proposed
approach could benefit stakeholders in terms of improving communication, sharing
information, and understanding roles in DW management in urban redevelopment
projects.
The decision-making framework also included a supporting database that is argued to
provide stakeholders with necessary DW information to support in the decision-
making process in urban redevelopment projects. This new approach contributes to
improving the planning for reuse and recycling of DW, particularly considering the
size and scale of urban redevelopment projects at a district level. In addition, the GIS-
based model was integrated in decision-making framework to provide a visual
representation and quantification of the DW flow from demolition work.
195
(2) Implications for the construction industry
In previous research, DW is often managed in a piecemeal way without appropriate
consideration of the broader sustainability implications. The decision-making
framework was proposed based on the five aspects of sustainability from the
perceptions of the five key stakeholders (academics, planners, consultants, engineers,
and policy makers) through survey and interview study in Vietnam. This framework
offers significant benefits in addressing sustainability issues associated with urban
redevelopment DW in developing countries. The list of 24 critical factors related to
the decision-making process may be used as key criteria in evaluating DW
management performance towards sustainable urban redevelopment in Vietnam.
The critical decision-making factors enable stakeholders to better understand the isues
influencing DW management. Also, the integration of decision-making factors and
supporting database in the proposed framework can be used to facilitate the
stakeholder buy-in and involvement in implementing urban redevelopment DW
management strategy. This can help stakeholders in considering priority issues in
implementing DW management. In addition, the supporting database provides
stakeholders with the crucial information of DW management in assessing the cost and
plan effectiveness.
Further, a key implication of the research is related to the need of stakeholders in taking
a holistic approach to managing DW in a large scale urban redevelopment projects.
Particularly, the GIS-based tool might be applied as a decision support tool to create a
platform for more detailed DW database. This is expected to improve the quality of
information available to stakeholders and encourage more information shared in urban
redevelopment projects on a large scale.
It is recommended that critical decision-making factors should be considered by
Vietnam government in their strategies of developing industry-wide construction and
formulating DW management policies towards sustainable urban redevelopment.
8.5 RESEARCH LIMITATIONS
This research developed a decision-making framework including a supporting
database to improve DW management in Vietnamese urban redevelopment projects.
This research took a multi-criteria approach to sustainability within this research
196 Chapter 8: Conclusion
context. Despite the significant contribution of the research, there are research
limitations that need to be acknowledged to provide opportunities for future research.
The key limitations of the study were:
Although research samples involved industry practitioners and experts in the
field of urban redevelopment DW management, they varied in experiences and
perspectives. Further, research samples may not represent the entire industry
practitioners and academics in Vietnam. Therefore, larger sample sizes within
the five groups would provide improved external validity to the research
results.
The buildings to be demolished in all four case study projects dated back over
40 years. The structure design was hand-drawn and was hard to source. In
addition, the structure of units has been illegally altered and expanded by
residents. Efforts were made to check the accuracy of the sites and building
layouts to mitigate risk of errors relating to building information.
The DW estimation was only calculated for four main DW components.
Further estimation of some other materials, such as plastic and wood, should
be calculated, which would provide useful information for DW management
and recycling strategies.
The cost of DW transport was analysed based only on the distances to the
landfills due to time and resource constraints. Further research should take into
account other factors, such as disposal fees, or time consumed for waste
transport.
Given that this research only focused on DW management in Vietnamese urban
redevelopment projects, this may limit the ability to generalise other research
context. However, the research results are likely to apply in similar projects in
other similar developing countries in consideration of increasing urban
redevelopment trends and the economic and policy contexts.
8.6 RECOMMENDATIONS FOR FUTURE RESEARCH
In light of the research findings and research limitations, future research projects are
proposed as follows. Firstly, key related literature revealed that other developing
countries may encounter similar issues relating to DW management in urban
redevelopment projects. Although this research focuses on Vietnamese urban
197
redevelopment projects, this research also references the experience from both
developed and developing countries to contribute to the development of the proposed
decision-making framework. Therefore, it is recommended that this framework should
be further tested in similar developing countries, such as China, India, or Brazil. This
may improve the validity of the framework outside the chosen research context and
increase its generalisability. This future research may entail adapting the decision-
making framework to those countries by taking their specific regulations, cultural and
political environments into consideration.
Although many social factors are considered as important factors in urban
redevelopment projects, the social factors for improving urban redevelopment DW
management were ranked relatively low by five stakeholder groups in the study. These
included relatively low rankings for ‘the role of community in decision-making
process’, ‘increasing of public awareness’, and ‘job creation’. It is recommended
future studies focus on the social decision-making factors that influence DW
management in urban redevelopment projects. In addition, further investigation will
enhance the reasons to why social factors may be considered less important in DW
management decision-making in developing countries, like Vietnam.
The DW management process comprises different stages, such as DW collection, DW
classification, DW transport, and DW disposal. Cost analysis for the entire DW
management process might provide useful information to assess the cost-effectiveness
of the DW management plan. In the case study, this research focused on only the
number of pick-up trucks and distances to the landfills in the DW transport cost
analysis. Therefore, a general recommendation is that more research is required to
consider further information for cost analysis of collecting, sorting, and disposal of
DW in urban redevelopment projects. As a result, the cost-benefit analysis would be
more useful for decision makers in considering the economic performance of DW
management in urban redevelopment projects.
In this research, the volume of DW generation was estimated by waste weight per area
method, which was first reported in the study by Yost and Halstead (1996). In addition,
insufficient information of demolished buildings may affect the accuracy of DW
estimation. It is recommended that future research should concentrate on improving
the quality of data input for the DW estimation, particularly for all types of DW.
198 Chapter 8: Conclusion
Accordingly, further research could consider a comprehensive collection of building
information for DW estimation. It is expected the increased accuracy of the DW
information can assist decision makers to increase the rate of DW recovery and
minimise the environmental impacts.
Finally, this study was undertaken with a focus on developing the GIS-based model
for supporting decision makers via quantitative analysis. It is recommended that the
GIS model and other tools such as BIM could be deployed in future research for
capturing and sharing the database for not only project or district level, but also
potentially at a city and national level. The revised model with more accurate input
data in supporting DW management and validating the proposed framework will be
developed upon this research and further enhance the information available to decision
makers in the sustainable delivery of urban redevelopment projects.
Bibliography 199
Bibliography
Abbas, A., Fathifazl, G., Isgor, O., Razaqpur, A., Fournier, B., & Foo, S. (2006). Environmental benefits of green concrete. In EIC Climate Change Technology, 2006 IEEE (pp. 1-8): IEEE.
Adams, D., & Hastings, E. (2001). Urban renewal in Hong Kong: transition from
development corporation to renewal authority. Land Use Policy, 18(3), 245-258.
Adams, J., Khan, H. T., Raeside, R., & White, D. I. (2007). Research methods for
graduate business and social science students: SAGE publications India.
Ahuja, V., Yang, J., & Shankar, R. (2010). IT-enhanced communication protocols for
building project management. Engineering, Construction and Architectural Management, 17(2), 159-179.
Akintoye, A. (2000). Analysis of factors influencing project cost estimating practice.
Construction Management & Economics, 18(1), 77-89.
Akintoye, A. S., & MacLeod, M. J. (1997). Risk analysis and management in
construction. International journal of project management, 15(1), 31-38.
Al-Saggaf, A., & Jrade, A. (2015). Benefits of integrating BIM and GIS in construction
management and control.
Andersen, H. S. (2003). Urban Sores. On the interaction between segregation, urban
decay and deprived neighbourhoods: Ashgate.
Arthurson, K. (1998). Redevelopment of public housing estates: the Australian
experience. Urban Policy and Research, 16(1), 35-46. doi:DOI:
10.1080/08111149808727746
Begum, R. A., Siwar, C., Pereira, J. J., & Jaafar, A. H. (2006). A benefit–cost analysis
on the economic feasibility of construction waste minimisation: the case of Malaysia. Resources, Conservation and Recycling, 48(1), 86-98.
Benjamini, Y., & Hochberg, Y. (1995). Controlling the false discovery rate: a practical
and powerful approach to multiple testing. Journal of the royal statistical society. Series B (Methodological), 289-300.
200 Bibliography
Berg, B. L. (2004). Methods for the social sciences: Pearson Education Inc, United
States of America.
Bernt, M. (2009). Partnerships for demolition: The governance of urban renewal in East
Germany's shrinking cities. International Journal of Urban and Regional Research, 33(3), 754-769.
Biddle, D. (2001). Deconstruction industry'demolishes' the alternative. In Business,
23(3), 27-27.
Bjerregaard, M. (2008). Demolition waste: are we doing our best? In Proceedings of the
Institution of Civil Engineers-Waste and Resource Management (Vol. 161, pp. 45-49): Thomas Telford Ltd.
Blaxter, L. (2010). How to research: McGraw-Hill Education (UK).
Blengini, G. A. (2009). Life cycle of buildings, demolition and recycling potential: a
case study in Turin, Italy. Building and environment, 44(2), 319-330.
Bowie, J., Farfel, M., & Moran, M. H. (2005). Community experiences and perceptions
related to demolition and gut rehabilitation of houses for urban redevelopment. Journal of Urban Health, 82(4), 532-542. doi:10.1093/jurban/jti075
Brodersen, J., Juul, J., Jacobsen, H., & Tsotsos, D. (2002). Review of selected waste
streams. Retrieved from http://www.eea.europa.eu/publications/technical_report_2001_69
Brooks, K. A., Adams, C., & Demsetz, L. A. (1994). Germany's construction and
demolition debris recycling infrastructure: what lessons does it have for the US. Sustainable construction, 16, 647-656.
Broudehoux, A.-M. (1994). Neighborhood regeneration in Beijing: An overview of
projects implemented in the inner city since 1990. Mcgill University.
Bryman, A., & Bell, E. (2015). Business research methods: Oxford University Press,
USA.
Bryson, J. M., & Bromiley, P. (1993). Critical factors affecting the planning and
implementation of major projects. Strategic Management Journal, 14(5), 319-337.
Bibliography 201
Cavana, R. Y., Delahaye, B. L., & Sekaran, U. (2001). Applied business research: Qualitative and quantitative methods: John Wiley & Sons Australia.
Chalkias, C., & Lasaridi, K. (2011). Benefits from GIS based modelling for municipal
solid waste management. In Integrated Waste Management-Volume I: InTech.
Chan, A. P., Scott, D., & Chan, A. P. (2004). Factors affecting the success of a
construction project. Journal of construction engineering and management, 130(1), 153-155.
Chan, E., & Lee, G. K. (2008a). Critical factors for improving social sustainability of
urban renewal projects. Social Indicators Research, 85(2), 243-256.
Chan, E. H., & Lee, G. K. (2008b). Contribution of urban design to economic
sustainability of urban renewal projects in Hong Kong. Sustainable Development, 16(6), 353-364.
Changyong, F., Hongyue, W., Naiji, L., Tian, C., Hua, H., & Ying, L. (2014). Log-
transformation and its implications for data analysis. Shanghai archives of psychiatry, 26(2), 105.
Chen, X., & Lu, W. (2017). Identifying factors influencing demolition waste generation
in Hong Kong. Journal of cleaner production, 141, 799-811.
Cheng, J. C., & Ma, L. Y. (2013). A BIM-based system for demolition and renovation
waste estimation and planning. Waste management, 33(6), 1539-1551.
Cooke, S., & Slack, N. (1991). Making management decisions. New York: Prentice
Hall.
Corbin, J., Strauss, A., & Strauss, A. L. (2014). Basics of qualitative research: Sage.
Couch, C. (1990). Urban renewal: theory and practice: Macmillan.
Couch, C., & Dennemann, A. (2000). Urban regeneration and sustainable development
in Britain: The example of the Liverpool Ropewalks Partnership. Cities, 17(2), 137-147.
Couch, C., Sykes, O., & Börstinghaus, W. (2011). Thirty years of urban regeneration in
Britain, Germany and France: The importance of context and path dependency. Progress in Planning, 75(1), 1-52.
202 Bibliography
Creswell, J. (2009). Research design: Qualitative, quantitative, and mixed methods
approaches: SAGE Publications, Incorporated.
Creswell, J. W. (2013). Research design: Qualitative, quantitative, and mixed methods
approaches: Sage publications.
Creswell, J. W., & Plano Clark, V. (2011). Choosing a mixed methods design.
Designing and conducting mixed methods research, 53-106.
Darren, G., & Mallery, P. (1999). SPSS for Windows Step by Step: A simple guide and
reference. Needham Heights, MA: Allyn & Bacon.
De Benedetto, L., & Klemeš, J. (2009). The Environmental Performance Strategy Map:
an integrated LCA approach to support the strategic decision-making process. Journal of Cleaner Production, 17(10), 900-906.
De Sousa, C. A. (2008). Brownfields redevelopment and the quest for sustainability
(Vol. 3): Emerald Group Publishing.
Deilmann, C., Effenberger, K.-H., & Banse, J. (2009). Housing stock shrinkage:
vacancy and demolition trends in Germany. Building Research & Information, 37(5-6), 660-668.
del Río Merino, M., Azevedo, I. S. W., & Gracia, P. I. (2009). Sustainable construction:
construction and demolition waste reconsidered. Waste management & research, 28, 118-129. doi:10.1177/0734242X09103841
Delmas, M., & Toffel, M. W. (2004). Stakeholders and environmental management
practices: an institutional framework. Business strategy and the Environment, 13(4), 209-222.
Demberel, E. (2010). Strategies for the sustainable redevelopment of residential
buildings in Ulaanbaatar, Mongolia Master. RMIT University, Melbourne, Australia.
Diaz, L., Savage, G., & Golueke, C. (1996). Sustainable community systems: the role of
integrated solid waste management. In International Madison Waste Conference Municipal and Industry Waste (pp. 280-291): Department of Engineering Professional Development
Bibliography 203
Dieu, T. (2017, June 21, 2017). The issues of urban redevelopment in Ho Chi Minh city. Retrieved from http://vietnamnet.vn/vn/bat-dong-san/du-an/cai-tao-chung-cu-cu-tp-hcm-ngay-cang-xa-roi-muc-tieu-363656.html
Ding, T., & Xiao, J. (2014). Estimation of building-related construction and demolition
waste in Shanghai. Waste Management, 34(11), 2327-2334.
Do, H. (2017). Hai Phong urban redevelopment plan. Retrieved from
https://baomoi.com/hai-phong-thao-do-hang-loat-nha-tap-the-cu-nat-xay-dung-chung-cu-cao-tang/c/24164923.epi
Dowall, D. E. (1994). Urban residential redevelopment in the People's Republic of
China. Urban Studies, 31(9), 1497-1516.
Dutton, J. E. (1993). Interpretations on automatic: A different view of strategic issue
diagnosis. Journal of Management Studies, 30(3), 339-357.
Elbanna, S. (2006). Strategic decision‐making: Process perspectives. International
Journal of Management Reviews, 8(1), 1-20.
Ercan, M. A. (2011). Challenges and conflicts in achieving sustainable communities in
historic neighbourhoods of Istanbul. Habitat International, 35(2), 295-306. doi:https://doi.org/10.1016/j.habitatint.2010.10.001
EUROSTAT. (2017). Waste statistics. Retrieved July 20, 2017
http://ec.europa.eu/eurostat/statistics-explained/index.php/Waste_statistics#Total_waste_generation
Fang, K., & Zhang, Y. (2003). Plan and market mismatch: Urban redevelopment in
Beijing during a period of transition. Asia Pacific Viewpoint, 44(2), 149-162. doi:10.1111/1467-8373.00190
Farfel, M. R., Orlova, A. O., Lees, P. S., Rohde, C., Ashley, P. J., & Chisolm, J. J.
(2005). A study of urban housing demolition as a source of lead in ambient dust on sidewalks, streets, and alleys. Environmental research, 99(2), 204-213. doi:10.1016/j.envres.2004.10.005
Fatta, D., Papadopoulos, A., Avramikos, E., Sgourou, E., Moustakas, K., Kourmoussis,
F., . . . Loizidou, M. (2003). Generation and management of construction and demolition waste in Greece—an existing challenge. Resources, Conservation and Recycling, 40(1), 81-91. doi:10.1016/S0921-3449(03)00035-1
204 Bibliography
Fellows, R. F., & Liu, A. M. (2015). Research methods for construction: John Wiley & Sons.
Field, A. (Singer-songwriter). (2014). Factor Analysis Using SPSS. Research Methods
II. On.
Fong, P. K. (1985). Issues in urban redevelopment: the Land Development Corporation.
Built Environment (1978-), 283-293.
Formoso, C. T., Soibelman, L., De Cesare, C., & Isatto, E. L. (2002). Material waste in
building industry: main causes and prevention. Journal of construction engineering and management, 128(4), 316-325.
Fredrickson, J. W. (1985). Effects of decision motive and organizational performance
level on strategic decision processes. Academy of Management journal, 28(4), 821-843.
Fung, A. (2004). Sustainable development and the conservation of natural and cultural
heritage. Sustainable development in Hong Kong, 387-420.
García‐Arenzana, N., Navarrete‐Muñoz, E. M., Lope, V., Moreo, P., Vidal, C., Laso‐
Pablos, S., . . . Santamariña, C. (2014). Calorie intake, olive oil consumption and mammographic density among Spanish women. International journal of cancer, 134(8), 1916-1925.
Gephart Jr, R. P. (1991). Multiple methods for tracking corporate social performance:
Insights from a study of major industrial accidents. Research in corporate social performance and policy, 12, 359-383.
Gotham, K. F. (2001). Urban redevelopment, past and present. critical perspectives on
urban redevelopment, 6, 1-31.
Grebler, L. (1964). Urban renewal in European countries: its emergence and potentials:
University of Pennsylvania Press.
Ha, S.-K. (2001). Developing a community-based approach to urban redevelopment.
GeoJournal, 53(1), 39-45.
Habitat, U. (2006). State of the World’s Cities 2006/7. New York: United Nations.
Hain, P. (1980). Neighbourhood participation. London: Temple Smith.
Bibliography 205
Harrison, K. W., Dumas, R. D., Solano, E., Barlaz, M. A., Brill Jr, E. D., & Ranjithan,
S. R. (2001). Decision support tool for life-cycle-based solid waste management. Journal of Computing in Civil Engineering, 15(1), 44-58.
He, S., & Wu, F. (2007). Socio-spatial impacts of property-led redevelopment on
China’s urban neighbourhoods. Cities, 24(3), 194-208.
Hendriks, C., & Pietersen, H. (2000). Sustainable Raw Materials–Construction and
Demolition Waste (165-SRM). State-of-the-Art Report of RILEM Technical Committee.
Hendriks, C. F., & Jansen, G. (2001). Reuse of construction and demolition waste in the
Netherlands for road constructions. HERON, vol. 46 (2), 2001.
Hendriks, C. F., & Janssen, G. (2001). Application of construction and demolition
waste. HERON, vol. 46 (2), 2001.
Hill, R. C., & Bowen, P. A. (1997). Sustainable construction: principles and a
framework for attainment. Construction Management & Economics, 15(3), 223-239.
Hitt, M. A., & Tyler, B. B. (1991). Strategic decision models: Integrating different
perspectives. Strategic management journal, 12(5), 327-351.
Ho, E. C.-m. (2012). Renewing the urban regeneration approach in Hong Kong: Run
Run Shaw Library, City University of Hong Kong.
Hoang, N. (2017). The three important urban redevelopment projects in the Hanoi.
Retrieved from http://cafef.vn/ha-noi-cai-tao-3-khu-chung-cu-cu-tren-dat-vang-the-nao-20170402084818305.chn
Holcomb, H. B. B., Robert A. (1981). Revitalizing Cities: Resource Publications in
Geography.
Huang, W.-L., Lin, D.-H., Chang, N.-B., & Lin, K.-S. (2002). Recycling of construction
and demolition waste via a mechanical sorting process. Resources, Conservation and Recycling, 37(1), 23-37.
Hui, E. C., Wong, J. T., & Wan, J. K. (2008). A review of the effectiveness of urban
renewal in Hong Kong. Property Management, 26(1), 25-42.
206 Bibliography
Hung, M.-L., Ma, H.-w., & Yang, W.-F. (2007). A novel sustainable decision making model for municipal solid waste management. Waste management, 27(2), 209-219.
Huuhka, S., & Lahdensivu, J. (2014). Statistical and geographical study on demolished
buildings. Building Research & Information, 41(1), 73-96. doi:10.1080/09613218.2014.980101
Huy, G. (2015). A holistic view of aging building redevelopment Retrieved from
Vietnam Government Web Portal website: http://thanglong.chinhphu.vn/Home/Cai-tao-chung-cu-cu-can-nhin-tong-the-trong-chinh-trang-do-thi/20159/14591.vgp
Hyder Consulting, E. C. S. R. S. (2011). Construction and Demolition Waste Status
Report. Retrieved from http://www.environment.gov.au/protection/national-waste-policy/publications/construction-and-demolition-waste-status-report
Imrie, R., Lees, L., & Raco, M. (2009). Regenerating London: governance,
sustainability and community in a global city: Routledge.
Itard, L., & Klunder, G. (2007). Comparing environmental impacts of renovated
housing stock with new construction. Building Research & Information, 35(3), 252-267. doi:10.1080/09613210601068161
Jim, C.-Y. (1994). Urban renewal and environmental planning in Hong Kong. The
Environmentalist, 14(3), 163-181.
Johnson, P., & Clark, M. (2006). Business and management research methodologies:
Sage.
Karadimas, N. V., & Loumos, V. G. (2008). GIS-based modelling for the estimation of
municipal solid waste generation and collection. Waste Management & Research, 26(4), 337-346.
Kazemian, A. R. (1991). Urban renewal planning versus local values PhD. Chalmers
University of Technology Göteborg, Sweden
Kibert, C. J. (1994). Establishing principles and a model for sustainable construction. In
Proceedings of the First International Conference on Sustainable Construction (pp. 6-9): Tampa Florida, November.
Bibliography 207
Kibert, C. J., & Chini, A. (2000). Deconstruction as an essential component of sustainable construction. In Proceedings of the second Southern African conference on sustainable development in the built environment, Pretoria (pp. 1-5).
Kleemann, F., Lederer, J., Aschenbrenner, P., Rechberger, H., & Fellner, J. (2014). A
method for determining buildings’ material composition prior to demolition. Building Research & Information, 44(1), 51-62. doi:10.1080/09613218.2014.979029
Kleemann, F., Lederer, J., Rechberger, H., & Fellner, J. (2017). GIS‐based analysis of
Vienna's material stock in buildings. Journal of Industrial Ecology, 21(2), 368-380.
Kofoworola, O. F., & Gheewala, S. H. (2009). Estimation of construction waste
generation and management in Thailand. Waste management, 29(2), 731-738.
Kontos, T. D., Komilis, D. P., & Halvadakis, C. P. (2005). Siting MSW landfills with a
spatial multiple criteria analysis methodology. Waste management, 25(8), 818-832.
Kourmpanis, B., Papadopoulos, A., Moustakas, K., Kourmoussis, F., Stylianou, M., &
Loizidou, M. (2008). An integrated approach for the management of demolition waste in Cyprus. Waste Management & Research, 26(6), 573-581.
Kourmpanis, B., Papadopoulos, A., Moustakas, K., Stylianou, M., Haralambous, K., &
Loizidou, M. (2008). Preliminary study for the management of construction and demolition waste. Waste Management & Research, 26(3), 267-275.
Kwong, M. H. (2003). Sustainable development in civil engineering—The Hong Kong
experience. In Proc., 2nd Int. Conf. on Construction in the 21st Century (CITC-II) Sustainability and Innovation in Management and Technology (pp. 15-19): Hong Kong Polytechnic Univ.
Lam, P. T., Chan, E. H., Poon, C., Chau, C., & Chun, K. (2010). Factors affecting the
implementation of green specifications in construction. Journal of environmental management, 91(3), 654-661.
Lee, G. K., & Chan, E. H. (2008a). The analytic hierarchy process (AHP) approach for
assessment of urban renewal proposals. Social Indicators Research, 89(1), 155-168.
208 Bibliography
Lee, G. K., & Chan, E. H. (2008b). Factors affecting urban renewal in high-density city: Case study of Hong Kong. Journal of Urban Planning and Development, 134(3), 140-148.
Lee, S. L. (1996). Urban conservation policy and the preservation of historical and
cultural heritage: The case of Singapore. Cities, 13(6), 399-409.
Leigh, N. G., & Patterson, L. M. (2006). Deconstructing to redevelop: A sustainable
alternative to mechanical demolition: The economics of density development finance and pro formas. Journal of the American Planning Association, 72(2), 217-225. doi:10.1080/01944360608976740
Li, H., Chen, Z., Yong, L., & Kong, S. C. (2005). Application of integrated GPS and
GIS technology for reducing construction waste and improving construction efficiency. Automation in Construction, 14(3), 323-331.
Li, J., Ding, Z., Mi, X., & Wang, J. (2013). A model for estimating construction waste
generation index for building project in China. Resources, Conservation and Recycling, 74, 20-26.
Li, S.-M., & Song, Y.-l. (2009). Redevelopment, displacement, housing conditions, and
residential satisfaction: a study of Shanghai. Environment and Planning A, 41(5), 1090-1108.
Liu, C., Pun, S.-K., & Langston, C. (2005a). A preliminary study on building
demolition engineering and management. World Transactions on Engineering and Technology Education, 4(2), 201.
Liu, C., Pun, S., & Langston, C. (2005b). A preliminary study on building demolition
engineering and management. World Transactions on engineering and technology education, 4(2), 201.
Lombardi, D. R., Porter, L., Barber, A., & Rogers, C. D. (2011). Conceptualising
sustainability in UK urban regeneration: A discursive formation. Urban Studies, 48(2), 273-296.
Love, P. E., & Smith, J. (2003). Benchmarking, benchaction, and benchlearning: rework
mitigation in projects. Journal of Management in Engineering, 19(4), 147-159.
Lu, M., Lau, S.-C., & Poon, C.-S. (2009). Simulation approach to evaluating cost
efficiency of selective demolition practices: Case of Hong Kong’s Kai Tak airport demolition. Journal of Construction Engineering and Management, 135(6), 448-457.
Bibliography 209
Lu, W. (2014). Estimating the Amount of Building-Related Construction and
Demolition Waste in China. In Proceedings of the 18th International Symposium on Advancement of Construction Management and Real Estate (pp. 539-548): Springer.
Lu, W., & Yuan, H. (2010). Exploring critical success factors for waste management in
construction projects of China. Resources, conservation and recycling, 55(2), 201-208.
Lu, W., & Yuan, H. (2011). A framework for understanding waste management studies
in construction. Waste Management, 31(2011), 1252-1260. doi:10.1016/j.wasman.2011.01.018
Lu, W., Yuan, H., Li, J., Hao, J. J., Mi, X., & Ding, Z. (2011). An empirical
investigation of construction and demolition waste generation rates in Shenzhen city, South China. Waste management, 31(4), 680-687.
Mália, M., de Brito, J., Pinheiro, M. D., & Bravo, M. (2013). Construction and
demolition waste indicators. Waste Management & Research, 31(3), 241-255. doi:10.1177/0734242X12471707
Manowong, E. (2012). Investigating factors influencing construction waste management
efforts in developing countries: an experience from Thailand. Waste Management & Research, 30(1), 56-71.
Mark, S., Philip, L., & Adrian, T. (Singer-songwriters). (2009). Research methods for
business students. On: Prentice Hall.
Marrero, M., Solis-Guzman, J., Molero-Alonso, B., Osuna-Rodriguez, M., & Ramirez-
de-Arellano, A. (2011). Demolition waste management in Spanish legislation. The Open Construction and Building Technology Journal, 5(Supl 2 M7), 162-173.
Marzouk, M., & Azab, S. (2014). Environmental and economic impact assessment of
construction and demolition waste disposal using system dynamics. Resources, Conservation and Recycling, 82, 41-49.
Mayer, I. S., van Bueren, E. M., Bots, P. W., van der Voort, H., & Seijdel, R. (2005).
Collaborative decisionmaking for sustainable urban renewal projects: a simulation–gaming approach. Environment and Planning B: planning and design, 32(3), 403-423.
210 Bibliography
Mcdonald, B., & Smithers, M. (1998). Implementing a waste management plan during the construction phase of a project: a case study. Construction Management & Economics, 16(1), 71-78. doi:10.1080/014461998372600
McMurray, A. (2004). A commonsense approach: Cengage Learning Australia.
Miller, J. M. (1959). New Life for Cities Around the World: International Handbook on
Urban Renewal: Books International.
Mintzberg, H., & Waters, J. A. (1985). Of strategies, deliberate and emergent. Strategic
management journal, 6(3), 257-272.
Morris, T. (2006). Social work research methods: four alternative paradigms: Sage.
Morrissey, A. J., & Browne, J. (2004). Waste management models and their application
to sustainable waste management. Waste management, 24(3), 297-308.
Mui, D. H.-F., & Sankaran, S. (2004). An effective project management-based
application model for sustainable urban renewal in Hong Kong. In: Project Management Institute.
Mulder, E., de Jong, T. P., & Feenstra, L. (2007). Closed Cycle Construction: An
integrated process for the separation and reuse of C&D waste. Waste Management, 27(10), 1408-1415.
Munoth, N., Jain, R., Raheja, G., & Brar, T. (2013). Issues of Sustainable
Redevelopment of City Core: A Study of Developed and Developing Countries. Journal of The Institution of Engineers (India): Series A, 94(2), 117-122.
Najm, M. A., & El-Fadel, M. (2004). Computer-based interface for an integrated solid
waste management optimization model. Environmental Modelling & Software, 19(2004), 1151-1164. doi:10.1016/j.envsoft.2003.12.005
Nelson, K. P. (1988). Gentrification and distressed cities: an assessment of trends in
intrametropolitan migration. Madison.
Neuman, L. W. (2000). Social research methods: Qualitative and quantitative
approaches (4th ed.). Boston: Allyn and Bacon.
Ng, I. (1998). Urban redevelopment in Hong Kong: The partnership experience.
International Journal of Public Sector Management, 11(5), 414-420.
Bibliography 211
Ng, M. K., Cook, A., & Chui, E. W. (2001). The road not travelled: A sustainable urban
regeneration strategy for Hong Kong. Planning Practice and Research, 16(2), 171-183.
Nguyen, M. (2011). Status of construction waste management in Vietnam. Retrieved
from http://www.xaydungbenvung.com/2014/06/thuc-trang-chat-thai-ran-xay-dung-o.html
Nguyen, M. (2015). Status of construction waste management in Vietnam. Retrieved
from http://www.xaydungbenvung.com/2014/06/thuc-trang-chat-thai-ran-xay-dung-o.html
Nisbet, M., Venta, G., & Foo, S. (2012). Demolition and deconstruction: review of the
current status of reuse and recycling of building materials. AWMA (Air Waste Manag. Assoc.
Omann, I., & Spangenberg, J. H. (2002). Assessing social sustainability. In Biennial
Conference of the International Society for Ecological Economics (Vol. 7).
Ortiz, O., Castells, F., & Sonnemann, G. (2009). Sustainability in the construction
industry: A review of recent developments based on LCA. Construction and Building Materials, 23(1), 28-39.
Osmani, M., Glass, J., & Price, A. D. (2008). Architects’ perspectives on construction
waste reduction by design. Waste Management, 28(7), 1147-1158.
Pallant, J. (Singer-songwriter). (2010). SPSS survival manual: A step by step guide to
data analysis using SPSS . Maidenhead. On: Open University Press/McGraw-Hill.
Papadakis, V. M., Lioukas, S., & Chambers, D. (1998). Strategic decision-making
processes: the role of management and context. Strategic management journal, 19(2), 115-147.
Patton, M. Q. (2002). Qualitative interviewing. Qualitative research and evaluation
methods, 3, 344-347.
Peng, C.-L., Scorpio, D. E., & Kibert, C. J. (1997). Strategies for successful
construction and demolition waste recycling operations. Construction Management & Economics, 15(1), 49-58. doi:10.1080/014461997373105
212 Bibliography
Petersen, M. (2004). Construction Demolition Waste. Vol. 2. J. J. R. Mukesh C. Limbachiya (Ed.) Strategic construction and demolition waste management tool for sustainable urban renewal (pp. 303).
Poon, C., Ann, T., & Ng, L. (2001). On-site sorting of construction and demolition
waste in Hong Kong. Resources, conservation and recycling, 32(2001), 157-172.
Poon, C. S. (1997). Management and recycling of demolition waste in Hong Kong.
Waste management & research, 15, 561-572. doi:10.1080/0144619042000213283
Poon, C. S., Yu, A. T. W., See, S. C., & Cheung, E. (2004). Minimizing demolition
wastes in Hong Kong public housing projects. Construction Management and Economics, 22(8), 799-805.
Power, A. (2008). Does demolition or refurbishment of old and inefficient homes help
to increase our environmental, social and economic viability? Energy Policy, 36(2008), 4487-4501. doi:10.1016/j.enpol.2008.09.022
Qualharini, E. L., & Flemming, L. (2009). Rehabilitation and sustainability of buildings
in Rio de Janeiro. Journal of Building Appraisal, 5(2), 123-131. doi:10.1057/jba.2009.25
Rao, A., Jha, K. N., & Misra, S. (2007). Use of aggregates from recycled construction
and demolition waste in concrete. Resources, conservation and Recycling, 50(1), 71-81.
Rao, C., & Zhang, Q. (2015). Construction Waste Management in Urban Renewal.
International Symposium on Social Science, 2015, 17-20.
Ravetz, J. (2000). Integrated assessment for sustainability appraisal in cities and
regions. Environmental impact assessment review, 20(1), 31-64.
Rodríguez, G., Alegre, F. J., & Martínez, G. (2007). The contribution of environmental
management systems to the management of construction and demolition waste: The case of the Autonomous Community of Madrid (Spain). Resources, conservation and recycling, 50(3), 334-349.
Rogers, G., & Bouey, E. (1996). Collecting your data. Qualitative research for social
workers: Phases, steps, and tasks, 4, 50-87.
Bibliography 213
Rotmans, J., van Asselt, M., & Vellinga, P. (2000). An integrated planning tool for sustainable cities. Environmental impact assessment review, 20(3), 265-276.
Roussat, N., Dujet, C., & Mehu, J. (2009a). Choosing a sustainable demolition waste
management strategy using multicriteria decision analysis. Waste management, 29(2009), 12-20. doi:10.1016/j.wasman.2008.04.010
Roussat, N., Dujet, C., & Mehu, J. (2009b). Choosing a sustainable demolition waste
management strategy using multicriteria decision analysis. Waste management, 29, 12-20. doi:10.1016/j.wasman.2008.04.010
Roussat, N., Méhu, J., Abdelghafour, M., & Brula, P. (2008). Leaching behaviour of
hazardous demolition waste. Waste Management, 28, 2032-2040. doi:10.1016/j.wasman.2007.10.019
Şener, Ş., Şener, E., Nas, B., & Karagüzel, R. (2010). Combining AHP with GIS for
landfill site selection: a case study in the Lake Beyşehir catchment area (Konya, Turkey). Waste management, 30(11), 2037-2046.
Seo, S., & Hwang, Y. (1999). An estimation of construction and demolition debris in
Seoul, Korea: waste amount, type, and estimating model. Journal of the Air & Waste Management Association, 49(8), 980-985. doi:10.1080/10473289.1999.10463863
Shen, L. Y., Li Hao, J., Tam, V. W. Y., & Yao, H. (2007). A checklist for assessing
sustainability performance of construction projects. Journal of civil engineering and management, 13(4), 273-281.
Sohn, S.-K. (2003). Changes in the Residential Features of Seoul in the 20th Century.
Seoul, 20th Century: Growth and Change of the Last, 100.
Somasundaram, S., Jeon, T.-W., Kang, Y.-Y., Kim, W.-I., Jeong, S.-K., Kim, Y.-J., . . .
Shin, S. K. (2015). Characterization of wastes from construction and demolition sector. Environmental monitoring and assessment, 187(1), 1-14. doi:10.1007/s10661-014-4200-0
Spangenberg, H. (2004). Sustainability beyond environmentalism: the missing
dimensions. GoSDWorking, Paper No. 2
Sproull, N. L. (2002). Handbook of research methods: A guide for practitioners and
students in the social sciences: Scarecrow press.
214 Bibliography
Steinberg, F. (1996). Conservation and rehabilitation of urban heritage in developing countries. Habitat International, 20(3), 463-475.
Sumathi, V., Natesan, U., & Sarkar, C. (2008). GIS-based approach for optimized siting
of municipal solid waste landfill. Waste management, 28(11), 2146-2160. doi:10.1016/j.wasman.2007.09.032
Tam, V. W. (2008). On the effectiveness in implementing a waste-management-plan
method in construction. Waste management, 28(6), 1072-1080.
Tam, V. W., & Tam, C. M. (2008). Waste reduction through incentives: a case study.
Building Research & Information, 36(1), 37-43.
Tanikawa, H., & Hashimoto, S. (2009). Urban stock over time: spatial material stock
analysis using 4d-GIS. Building Research & Information, 37(5-6), 483-502.
Thomas, J. M., & Hwang, H.-Y. (2003). Social Equity in Redevelopment and Housing
United States and Korea. Journal of Planning Education and Research, 23(1), 8-23.
Turok, I., & Mykhnenko, V. (2007). The trajectories of European cities, 1960–2005.
Cities, 24(3), 165-182.
USEPA. (2009). Estimating 2003 building-related construction and demolition materials
amounts. Retrieved December 13, 2017, from US. Environmental Protection Agency
Uzun, C. N. (2005). Residential transformation of squatter settlements: Urban
redevelopment projects in Ankara. Journal of Housing and the Built Environment (20(2), 183-199. doi:DOI: 10.1007/s10901-005-9002-9
van Bueren, E., & ten Heuvelhof, E. (2005). Improving governance arrangements in
support of sustainable cities. Environment and planning B: Planning and Design, 32(1), 47-66.
van Dijk, S., Tenpierik, M., & van den Dobbelsteen, A. (2014). Continuing the
building's cycles: A literature review and analysis of current systems theories in comparison with the theory of Cradle to Cradle. Resources, Conservation and Recycling, 82, 21-34.
Bibliography 215
Van Selm, M., & Jankowski, N. W. (2006). Conducting online surveys. Quality & Quantity, 40(3), 435-456.
Vego, G., Kučar-Dragičević, S., & Koprivanac, N. (2008). Application of multi-criteria
decision-making on strategic municipal solid waste management in Dalmatia, Croatia. Waste management, 28(11), 2192-2201.
Vietnamnet. (2016). The list of 42 high risk old buildings in Hanoi. Retrieved from
http://vietnamnet.vn/vn/bat-dong-san/cong-bo-danh-sach-42-chung-cu-cu-nguy-hiem-sap-do-o-ha-noi-290358.html
Walker, A. (2015). Project management in construction: John Wiley & Sons.
Wang, J.-Y., Kang, X.-P., & Wing-Yan Tam, V. (2008). An investigation of
construction wastes: an empirical study in Shenzhen. Journal of Engineering, Design and Technology, 6(3), 227-236.
Wang, J., & Yuan, H. (2006). Integrated analysis of the current situation of construction
industry in Chinese eight major provinces and cities. Construction economy, 9, 5-8.
Wang, J., & Yuan, H. (2008). On-site construction waste management model based on
system dynamics. Science & Technology Progress and Policy, 25(10), 74-78.
Wang, J., & Yuan, H. (2011). Factors affecting contractors’ risk attitudes in
construction projects: Case study from China. International Journal of Project Management, 29(2), 209-219.
Wang, J. Y., Touran, A., Christoforou, C., & Fadlalla, H. (2004). A systems analysis
tool for construction and demolition wastes management. Waste management, 24(10), 989-997. doi:10.1016/j.wasman.2004.07.010
WCED, W. C. o. E. a. D. (1987). Our Common Future. Retrieved from
Williams, K., & Dair, C. (2007). What is stopping sustainable building in England?
Barriers experienced by stakeholders in delivering sustainable developments. Sustainable development, 15(3), 135-147.
Wilson, D. C., Velis, C. A., & Rodic, L. (2013). Integrated sustainable waste
management in developing countries. In Proceedings of the Institution of Civil Engineers: Waste and Resource Management (Vol. 166, pp. 52-68): Thomas Telford.
216 Bibliography
Wong, E. O., & Yip, R. C. (2004). Promoting sustainable construction waste
management in Hong Kong. Construction Management and Economics, 22(6), 563-566. doi:10.1080/0144619042000226270
Wu, F., & He, S. (2005). Changes in traditional urban areas and impacts of urban
redevelopment: a case study of three neighbourhoods in Nanjing, China. Tijdschrift voor economische en sociale geografie, 96(1), 75-95.
Wu, H., Wang, J., Duan, H., Ouyang, L., Huang, W., & Zuo, J. (2016). An innovative
approach to managing demolition waste via GIS (geographic information system): a case study in Shenzhen city, China. Journal of Cleaner Production, 112, 494-503.
Wu, Z., & Ann, T. (2014). Evaluating the effectiveness of construction and demolition
waste management strategies. In Proceedings of the 18th International Symposium on Advancement of Construction Management and Real Estate (pp. 531-538): Springer.
Wu, Z., Ann, T., Shen, L., & Liu, G. (2014). Quantifying construction and demolition
waste: An analytical review. Waste Management, 34(9), 1683-1692.
Wyatt, D. P., & Gilleard, J. (1994). Deconstruction: an environmental response for
construction sustainability. In Sustainable Construction, Proceedings of the 1st International Conference of CIB TG16, Tampa, Fla (pp. 6-9).
Yan, H., Shen, Q., Fan, L. C., Wang, Y., & Zhang, L. (2010). Greenhouse gas emissions
in building construction: A case study of One Peking in Hong Kong. Building and Environment, 45(4), 949-955.
Yau, Y., & Ling Chan, H. (2008). To rehabilitate or redevelop? A study of the decision
criteria for urban regeneration projects. Journal of Place Management and Development, 1(3), 272-291. doi:10.1108/17538330810911262
Yeh, A. G.-O. (1990). Public and private partnership in urban redevelopment in Hong
Kong. Third World Planning Review, 12(4), 361-383.
Yeheyis, M., Hewage, K., Alam, M. S., Eskicioglu, C., & Sadiq, R. (2013). An
overview of construction and demolition waste management in Canada: a lifecycle analysis approach to sustainability. Clean Technologies and Environmental Policy, 15(1), 81-91.
Bibliography 217
Yeoh, B. S., & Huang, S. (1996). The conservation-redevelopment dilemma in Singapore: the case of the Kampong Glam historic district. Cities, 13(6), 411-422.
Yeung, A. (2008). Construction and demolition materials management in Hong Kong.
In Proceedings of the Institution of Civil Engineers: Municipal Engineer (Vol. 161, pp. 43-49): Thomas Telford (ICE Publishing). The Journal's web site is located at http://www. municipalengineer. com.
Yeung, J. F., Chan, A. P., Chan, D. W., & Li, L. K. (2007). Development of a
partnering performance index (PPI) for construction projects in Hong Kong: a Delphi study. Construction Management and Economics, 25(12), 1219-1237.
Yin, R. K. (2013). Case study research: Design and methods: Sage publications.
Yost, P. A., & Halstead, J. M. (1996). A methodology for quantifying the volume of
construction waste. Waste management & research, 14(5), 453-461.
Yuan, H. (2011). A dynamic model for assessing the effectiveness of construction and
demolition waste management. The Hong Kong Polytechnic University. Retrieved from http://hdl.handle.net/10397/4917
Yuan, H. (2013). A SWOT analysis of successful construction waste management.
Journal of Cleaner Production, 39, 1-8.
Yuan, H., & Shen, L. (2011). Trend of the research on construction and demolition
waste management. Waste management, 31(4), 670-679. doi:10.1016/j.wasman.2010.10.030
Yuan, H., Shen, L., & Wang, J. (2011). Major obstacles to improving the performance
of waste management in China's construction industry. Facilities, 29(5/6), 224-242. doi:10.1108/02632771111120538
Zhang, X., & Li, Y. (2012). Multi-Attribute Decision Making in Choosing Suitable
Construction Waste Management Methods. In Construction Research Congress 2012: Construction Challenges in a Flat World, Proceedings of the 2012 Construction Research Congress.
Zhao, W., Leeftink, R., & Rotter, V. (2010). Evaluation of the economic feasibility for
the recycling of construction and demolition waste in China—The case of Chongqing. Resources, Conservation and Recycling, 54(6), 377-389.
218 Bibliography
Zheng, H. W., Shen, G. Q., & Wang, H. (2014). A review of recent studies on sustainable urban renewal. Habitat International, 41, 272-279.
Zielenbach, S. (2000). Art of Revitalization: Taylor & Francis.
Zimmermann, M., Althaus, H.-J., & Haas, A. (2005). Benchmarks for sustainable
construction: A contribution to develop a standard. Energy and Buildings, 37(11), 1147-1157.
Zuckerman, M. (1991). Psychobiology of personality: Combrige University Press.
Appendices 219
Appendices
APPENDIX A. QUESTIONNAIRE SURVEY
Appendix A1: A sample of questionnaire (in English)
Survey on factors affecting demolition waste management in urban redevelopment
projects in Vietnam
This questionnaire is part of a PhD research that aims to improve the decision-making processes of demolition waste management from urban redevelopment in Vietnam. The objective of the questionnaire is to identify factors affecting the demolition waste management.
Your response is kept strictly confidential.
Note: Urban redevelopment in this research is defined as demolition of aging buildings and constructions of new buildings on the same site, including residential and commercial buildings.
SECTION 1. RESPONDENT INFORMATION
1. Please indicate your current position?
Academic
Planner
Consultant
Engineer
Policy maker
Other
2. What is the business nature of your organization?
Government agency
Local authority
Academic institution
Construction contractor
Waste management contractor
Other
3. How long have you been involved in practice/research in waste management?
0-5 years
5-10 years
10-15 years
15-20 years
Over 20 years
4. What is your organization’s level of involvement in demolition waste management?
Never
Rarely
Sometime
Often
220 Appendices
Always
5. What is your role in demolition waste management?
Director/Manager
Decision maker
Site engineer
Waste transporter
Other
SECTION 2. GENERAL INFORMATION
6. Please indicate the location of your last complete urban redevelopment project?
Hanoi
Hai Phong
Ho Chi Minh City
Other
7. Which of the following describes accurately your last complete urban redevelopment project scale?
Within a building
Multi-building
Multi-project
Other
8. In your professional capacity, which stakeholders do you need to work with?
Government agency
Local authority
Planner
Technical contractor
Construction contractor
Other
9. Making plans before demolition stage is important to urban redevelopment demolition waste management?
Strong disagree
Disagree
Neither agree nor disagree
Agree
Strongly agree
10. Which aspects do you think the most important in urban redevelopment demolition waste management?
Cost
Environment
Time
Safety
Policy
Other
Appendices 221
SECTION 3. FACTORS AFFECTING THE DECISION-MAKING PROCESS OF URBAN REDEVELOPMENT DEMOLITION WASTE MANAGEMENT
The following 5 categories contain the most significant identified factors to the decision-making process of demolition waste management in urban redevelopment projects. With your experience, please indicate the appropriate rating level in each that describes the significance of these factors.
11. Technical factors
Not at all important
(1)
Low important
(2)
Neither important
nor unimportant
(3)
Very important
(4)
Extremely important
(5)
Sufficient equipment for demolition project
Training the human resources in demolition techniques
Skilled personnel are available for conducting demolition project
Choosing demolition method (reduction of demolition time, cost and waste)
The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
Determining the procedures of demolition waste management
On-site sorting/separating of demolition waste
Estimating the amount of demolition waste
The use of BIM-based model in demolition waste management
The use of GIS-based model in demolition waste management
Planning the area for landfills
Planning the area for sorting platform
Planning storage space for recyclable materials
Managing time of the duration of demolition
Identifying ricks associate with building’s demolition
Life cycle assessment
222 Appendices
12. Environmental factors
Not at all important
(1)
Low important
(2)
Neither important nor unimportant
(3)
Very important
(4)
Extremely important
(5)
Understanding environmental issues of demolition waste generation
The willingness of demolition waste management by stakeholders
Training the human resources in the integrated waste management
Understanding the uniqueness of demolition waste before demolition stage
Environmental Impact Assessment
Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
The use of recycled materials
Understanding of hazardous demolition waste
Disposal control (fee, landfill sites)
Identifying rate of recovery
Balancing of greenhouse gases
13. Economic factors
Not at all important
(1)
Low important
(2)
Neither important nor unimportant
(3)
Very important
(4)
Extremely important
(5)
Estimating the cost of demolition
Estimating the cost of waste transport
Estimating the cost of waste treatment
Cost- effective demolition plans
Developing of recycling market
Reducing cost of demolition waste transportation
Saving the amount of energy use (fuels, electricity and others)
Developing an appropriate cost for waste disposal
Appendices 223
14. Social factors
Not at allimportant
(1)
Low important
(2)
Neither important nor unimportant
(3)
Very important
(4)
Extremely important
(5)
The role of community in demolition waste management
Community’s supportive actions before demolition stage
Community’s monitoring of environmental conditions during demolition stage
Effective feedback by community
Reduction of risks, accidences for workers on demolition site
Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
Preservation of natural resources, cultural and heritage
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
Job creation due to demolition waste management
15. Institutional factors
Not at allimportant
(1)
Low important
(2)
Neither important nor unimportant
(3)
Very important
(4)
Extremely important
(5)
The roles of key stakeholders in monitoring and feedback
Understanding of responsibilities by all stakeholders
Understanding of demolition waste management procedures
Effective feedback by stakeholders
Demolition project control meeting
Providing guidelines of demolition waste management plan
Regular information update
Involvement of key stakeholders in early stage
224 Appendices
Accomplishing government’s policy and strategy on demolition waste management
16. The following statements are related to an impact of the significant factors listed in the previous section to improve decision-making process for demolition waste management. With your experience, please indicate the level of agreement with the statements by circling the appropriate scale.
Strongly agree
Disagree Neither agree nor disagree
Agree Strongly agree
Environment degradation should be paid more attention
Maximise profit from demolition waste is my concern
Develop a planning tool (ICT-based solutions)
Develop a forum of communication among stakeholders
Manage demolition waste in multi- buildings/projects
17. Please state any other relevant points which have not been mentioned anywhere in this questionnaire.
SECTION 4. FURTHER INFORMATION
18. Please indicate whether the researchers can contact you for a follow-up interview?
Yes
No
Please enter your most convenient contact information such as name, company, email address and phone
number (personal information will remain confidential)
Thank you very much for contributing your valuable time in completing this questionnaire! Should you have any enquiries about this survey or the scope of my research, please do not hesitate to contact me as shown below:
Diep Thi Bui
Phone: +61 452256311
Email: [email protected]
-END-
Appendices 225
Appendix A2: A sample of questionnaire (in Vietnamese)
Nghiên cứu các yếu tố ảnh hưởng đến công tác quản lý chất thải phá dỡ của các dự án cải tạo chung cư cũ ở Việt nam
Bảng khảo sát này phục vụ luận án tiến sỹ của nghiên cứu sinh Bùi Thi Diệp.
Nghiên cứu này nhằm mục tiêu cải thiện quá trình ra quyết định trong việc quản lý chất thải phá dỡ có nguồn gốc từ các dự án cải tạo chung cư cũ ở Việt nam. Bảng các các câu hỏi được thực
hiện nhằm xác định rõ các yếu tố làm ảnh hưởng đến công tác quản lý chất thải phá dỡ.
Bảng câu hỏi không yêu cầu nêu tên và thông tin cá nhân của anh/chị.
Xin cảm ơn anh/chị đã tham gia đóng góp cho nghiên cứu. Mọi câu trả lời của quý vị được bảo đảm giữ bí mật một cách tuyệt đối.
Lưu ý: Dự án cải tạo chung cư cũ trong nghiên cứu này được hiểu là quá trình phá dỡ các các tòa nhà chung cư cũ và xây dựng mới trên cùng vị trí.
PHẦN 1. THÔNG TIN NGHỀ NGHIỆP
1. Xin vui lòng cho biết chức danh của anh/chị?
Nghiên cứu viên
Chuyên viên lập kế hoạch
Tư vấn môi trường
Kỹ sư xây dựng
Chuyên viên xây dựng chính sách
Khác
2. Cơ quan của anh/chị là:
Quản lý nhà nước
Chính quyền địa phương
Đơn vị nghiên cứu
Nhà thầu xây dựng
Nhà thầu quản lý chất thải
Khác
3. Kinh nghiệm của anh/chị đã tham gia thực hiện/nghiên cứu trong lĩnh vực quản lý chất thải phá dỡ?
0-5 năm
5-10 năm
10-15 năm
15-20 năm
Trên 20 năm
4. Cơ quan của anh/chị tham gia quản lý chất thải phá dỡ ở mức độ nào?
Chưa bao giờ
226 Appendices
Hiếm khi
Thỉnh thoảng
Thường thường
Luôn luôn
5. Vai trò của anh/chị trong dự án quản lý chất thải phá dỡ:
Quản lý dự án
Giám sát dự án, xây dựng quy định
Kỹ sư công trường
Vận chuyển chất thải phá dỡ
Khác
PHẦN 2. THÔNG TIN VỀ DỰ ÁN CẢI TẠO CHUNG CƯ CŨ
6. Xin vui lòng cho biết địa danh mà anh/chị đã tham gia thực hiện dự án quản lý chất thải phá dỡ?
Hà Nội
Hải Phòng
Thành phố Hồ Chính Minh
Khác
7. Quy mô dự án cải tạo chung cư cũ mà anh/chị đã tham gia thực hiện?
Một tòa nhà
Nhiều tòa nhà
Nhiều dự án
Khác
8. Khi thực hiện dự án, anh/chị cần làm việc với những đối tác nào?
Cơ quan quản lý nhà nước
Chính quyền địa phương
Cơ quan quy hoạch xây dựng
Cơ quan kỹ thuật
Nhà thầu xây dựng
Khác
9. Việc lập kế hoạch trước khi phá dỡ có quan trọng đối với quản ý chất thải phá dỡ?
Hoàn toàn không đồng ý
Không đồng ý
Bình thường
Đồng ý
Hoàn toàn đồng ý
10. Theo anh/chị yếu tố nào là có ảnh hưởng nhất đối với quản lý chất thảo phá dỡ ở chung cư cũ?
Chi phí thực hiện dự án
Bảo vệ môi trường
Thời gian thực hiện dự án
An toàn lao động
Appendices 227
Chính sách quản lý chất thải
Khác
PHẦN 3. NHỮNG YẾU TỐ ẢNH HƯỞNG ĐẾN CÔNG TÁC QUẢN LÝ CHẤT THẢI PHÁ DỠ
Nghiên cứu bước đầu xác định các yếu tố ảnh hưởng đến công tác quản lý chất thải phá dỡ và chia theo 5 nhóm chính, đó là nhóm các yếu tố kỹ thuật, môi trường, kinh tế, xã hội và thể chế. Theo kinh nghiệm của anh/chị, xin hãy đánh giá mức độ quan trọng của các yếu tố đối với công tác quản lý chất thải phá dỡ theo thang điểm từ 1 đến 5 (từ hoàn toàn không quan trọng đến cực kỳ quan trọng).
11. Các yếu tố kỹ thuật
Hoàn toàn không quan
trọng (1)
Không quan trọng (2)
Bình thường
(3)
Rất quan trọng (4)
Cực kỳ quan trọng (5)
Trang bị đầy đủ phương tiện phá dỡ
Đào tạo nguồn nhân lực về kỹ thuật phá quản lý chất thải
Kỹ năng của người thực hiện công tác phá dỡ
Lựa chọn phương pháp phá dỡ (giảm thiểu thời gian, giá thành, khối lượng chất thải)
Áp dụng phương pháp phá dỡ chọn lọc (phân loại chất thải tại công trình, phân loại chấtthải cho tái sử dụng và tái chế)
Xác định quy trình quản lý chất thải phá dỡ
Phân loại chất thải tại công trình
Ước lượng khối lượng chất thải phá dỡ
Áp dụng mô trình quản lý thông tin xây dựng (BIM) trong quản lý chất thải phá dỡ
Áp dụng Hệ thống thông tin địa lý (GIS) trong quản lý chất thải phá dỡ
Hoạch định bãi chứa chất thải phá dỡ
Hoạch định khu vực phân loại chất thải phá dỡ
Hoạch định khu vực chứa chất thải có thể tái chế
Giám sát thời gian thực hiện phá dỡ
228 Appendices
Xác định các rủi ro trong quá trình phá dỡ
Đánh giá vòng đời chất thải phá dỡ
12. Các yếu tố môi trường
Hoàn toàn
không quantrọng (1)
Không quan trọng (2)
Bình thường
(3)
Rất quan trọng (4)
Cực kỳ quan trọng (5)
Xác định các vấn đề môi trường do chất thải phá dỡ gây ra
Các bên liên quan sẵn sàng tham gia quản lý chất thải phá dỡ
Đào tạo nguồn nhân lực cho quản lý tổng hợp chất thải
Khảo sát thành phần chất thải phá dỡ trước khi thực hiện phá dỡ
Đánh giá tác động môi trường của công tác phá dỡ
Áp dụng chiến lược 3R trong quản lý chất thải phá dỡ (giảm thiểu, tái sử dụng và tái chế)
Chính sách khuyến khích tái chế chất thải phá dỡ
Xác định chất thải phá dỡ có tinh độc hại
Kiểm soát việc chôn lấp chất thải phá dỡ (lệphí, bãi chứa)
Xác định tỷ lệ tái sử dụng và tái chế chất thải phá dỡ
Biện pháp giảm phát thải khí nhà kính do chất thải phá dỡ
13. Các yếu tố kinh tế
Hoàn toàn
không quantrọng (1)
Không quan trọng (2)
Bình thường
(3)
Rất quan trọng (4)
Cực kỳ quan trọng (5)
Khái toán chi phí phá dỡ
Khái toán chi phí vận chuyển chất thải
Khái toán chi phí xử lý chất thải
Đánh giá hiệu quả kinh tế của các phương án phá dỡ
Phát triển thị trường vật liệu tái chế
Appendices 229
Giảm chi phí vận chuyển chất thải phá dỡ
Tiết kiệm sử dụng năng lượng (xăng dầu, điện)
Xây dựng biểu giá chôn lấp chất thải phù hợp
230 Appendices
14. Các yếu tố xã hội
Hoàn toàn không quan
trọng (1)
Không quan trọng (2)
Bình thường
(3)
Rất quan trọng (4)
Cực kỳ quan trọng (5)
Vai trò của cộng đồng trong việc quản lý chất thải phá dỡ
Các hoạt động hỗ trợ của cộng đồng trước khi thực hiện phá dỡ (đánh giá, phân loại chất thải, tuyên truyền về 3R)
Sự tham gia giám sát môi trường của cộng đồng trong quá trình phá dỡ
Lấy ý kiến phản hồi của cộng đồng về quá trình phá dỡ
Giảm thiểu rủi ro cho người lao động khi thực hiệnphá dỡ
Giảm thiểu tác động môi trường cho cộng đồngtrong quá trình phá dỡ (tiếng ồn, bụi, ô nhiễm khác)
Bảo vệ tài nguyên thiên nhiên và di sản văn hóa trong quá trình phá dỡ và xử lý chất thải
Nâng cao ý thức cộng đồng về quản lý tổng hợp chất thải và cải tạo chung cư cũ bền vững
Quản lý chất thải phá dỡ tạo cơ hội việc làm cho xã hội
15. Các yếu tố thể chế
Hoàn toàn không quan
trọng (1)
Không quan trọng (2)
Bình thường
(3)
Rất quan trọng (4)
Cực kỳ quan trọng (5)
Vai trò của các bên tham gia trong công tác giám sát và đánh giá quản lý chất thải phá dỡ
Phân công nhiệm vụ cụ thể cho các bên tham gia
Các bên tham gia được thông tin đầy đủ về quy trình quản lý chất thải phá dỡ
Vai trò quan trọng của công tác tổng kết, đánh giá của các bên tham gia
Họp các bên liên quan về đánh giá, theo dõi dự án phá dỡ và công tác quản lý chất thải
Ban hành văn bản hướng dẫn thực hiện quản lý chất thải phá dỡ
Thường xuyên cập nhật thông tin về chất thải trong quá trình phá dỡ
Sự tham gia của các bên liên quan từ giai đoạnchuẩn bị thực hiện dự án phá dỡ
Hoàn thiện chính sách và chiến lược đối với công tác quản lý chất thải phá dỡ
Appendices 231
16. Với kinh nghiệm của bản thân, xin anh/chị cho biết mức độ đồng ý của mình về các yếu tố cần được xem xét trong quá trình ra quyết định quản lý chất thải phá dỡ?
Hoàn toàn không đồng ý
Không đồng ý
Bình thường
Đồng ý Hoàn toàn đồng ý
Cần phải chú trọng hơn nữa đến các vấn đề môi trường (bảo vệ tài nguyên, cảnh quan, ô nhiễm môi trường, chôn lấp hợp vệ sinh)
Tăng giá trị kinh tế từ chất thảiphá dỡ đến mức tối đa (Tái chế, tái sử dụng)
Áp dụng công nghệ thông tin hỗtrợ quá trình ra quyết định quản lý chất thải phá dỡ (BIM, GIS hoặc phần mềm khác)
Thiết lập diễn đàn thông tincho các bên tham gia có thể dễ dàng chia sẻ và cập nhật thông tin về quản lý chất thải phá dỡ
Quản lý chất thải phá dỡ ở quy mô lớn gồm nhiều toà nhà hoặc dự án phá dỡ
17. Ngoài các yếu tố ảnh hưởng đã nêu, xin anh/chị vui lòng nêu và nhận xét về vấn đề nổi bật khác ảnh hưởng đến công tác quản lý chất thải phá dỡ của các dự án cải tạo chung cư cũ
PHẦN 4. THÔNG TIN KHÁC
18. Anh/chị có sẵn sàng tham gia cuộc phỏng vấn trong thời gian tới (sau khi nghiên cứu có kết quả của vòng trả lời câu khỏi khảo sát này)?
Có
Không
Nếu có, anh/chị hãy cho biết thông tin liên hệ thuận tiện nhất như họ tên, công ty, địa chỉ email, số điện thoại (thông tin cá nhân luôn được bảo mật)
Rất cám ơn anh/chị đã dành thời gian để trả lời bộ câu hỏi này. Nếu anh/chị muốn nhận được bản tóm tắt kết quả nghiên cứu của khảo sát này, xin liên lạc theo địa chỉ dưới đây. Kết quả sẽ được gửi sau khi nghiên cứu được hoàn thành và được phép công bố.
Thông tin liên lạc của nghiên cứu sinh: Bùi Thi Diệp ĐT: +61 452256311
Email: [email protected]
-HẾT-
232 Appendices
Appendix A3: Invitation Letter - Questionnaire Survey Invitation to a survey on:
Critical factors of improving demolition waste management for Vietnamese
urbane redevelopment projects
Dear Sir/madam
My name is Diep Thi Bui from School of Civil Engineering & Built Environment,
Queensland University of Technology (QUT). I am currently undertaking a PhD into the
improvement of decision-making process of demolition waste management for
Vietnamese urban redevelopment.
I’m looking for stakeholders, i.e. experts from construction firms, construction and
demolition waste firms, government agencies, and academic institutions to complete a
25-30 minute online questionnaire. You will be asked about your experience and opinions
regarding factors affecting DW management decision-making in Vietnamese urban
redevelopment projects. Your answers are of importance for the research team to
recognise the critical factors and issues associated with urban redevelopment DW
management.
Please view the attached Participant Information Sheet and Consent Form for further
details on the study.
Should you wish to participate or have any questions, please contact me via email.
Please note that this study has been approved by the QUT Human Research Ethics
Committee (approval number 1600000588).
Best regards
Diep Thi Bui
PhD Candidate Student
School of Civil Engineering and Built Environment
Science and Engineering Faculty
Queensland University of Technology (QUT)
Tel: +61 4 5225 6311/+84 9 0345 5101
Email: [email protected]
Appendices 233
APPENDIX B. SURVEY ANALYSIS RESULTS
Appendix B1: Results of normality test
Factors Kolmogorov-Smirnov Shapiro-Wilk
Statistic df Sig. Statistic df Sig.
Sufficient equipment for demolition project
.273 216 .000 .808 216 .000
Training the human resources in demolition techniques
.282 216 .000 .812 216 .000
Skilled personnel are available for conducting demolition project
.325 216 .000 .798 216 .000
Choosing demolition method (reduction of demolition time, cost andwaste)
.342 216 .000 .754 216 .000
The use of selective demolition method (on-site sorting, separate wastefor reuse and recycling)
.319 216 .000 .794 216 .000
Determining the procedures of demolition waste management
.365 216 .000 .684 216 .000
On-site sorting/separating of demolition waste
.360 216 .000 .677 216 .000
Estimating the amount of demolition waste .291 216 .000 .782 216 .000
The use of BIM-based modelr in demolition waste management
.347 216 .000 .750 216 .000
The use of GIS-based model in demolition waste management
.285 216 .000 .824 216 .000
Planning the area for landfills .325 216 .000 .766 216 .000
Planning the area for sorting platform .305 216 .000 .783 216 .000
Planning storage space for recyclable materials
.378 216 .000 .686 216 .000
Managing time of the duration of demolition
.375 216 .000 .726 216 .000
Identifying ricks associate with building’s demolition
.397 216 .000 .702 216 .000
Life cycle assessment .314 216 .000 .801 216 .000
Understanding environmental issues of demolition waste generation
.309 216 .000 .791 216 .000
The willingness of demolition waste management by stakeholders
.284 216 .000 .794 216 .000
Training the human resources in the integrated waste management
.346 216 .000 .750 216 .000
Understanding the uniqueness of demolition waste before demolition stage
.344 216 .000 .752 216 .000
Environmental Impact Assessment .328 216 .000 .770 216 .000
234 Appendices
Factors Kolmogorov-Smirnov Shapiro-Wilk
Statistic df Sig. Statistic df Sig.
Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
.306 216 .000 .762 216 .000
The use of recycled materials .339 216 .000 .767 216 .000
Understanding of hazardous demolition waste
.318 216 .000 .791 216 .000
Disposal control (fee, landfill sites) .300 216 .000 .774 216 .000
Identifying rate of waste recovery .338 216 .000 .760 216 .000
Balancing of greenhouse gases .324 216 .000 .763 216 .000
Estimation of demolition cost .323 216 .000 .774 216 .000
Cost estimation of waste transport .297 216 .000 .783 216 .000
Cost estimation of waste treatment .315 216 .000 .776 216 .000
Cost- effective demolition plans .274 216 .000 .770 216 .000
Developing of recycling market .337 216 .000 .756 216 .000
Reducing cost of demolition waste transportation
.288 216 .000 .806 216 .000
Saving the amount of energy use (fuels, electricity and others)
.308 216 .000 .797 216 .000
Developing an appropriate cost for waste disposal
.311 216 .000 .762 216 .000
The role of community in decision making process
.328 216 .000 .765 216 .000
Community’s supportive actions before demolition stage
.284 216 .000 .827 216 .000
Community’s monitoring of environmental conditions during demolition stage
.324 216 .000 .793 216 .000
Effective feedback by community .305 216 .000 .807 216 .000
Reduction of risks, accidences for workers on demolition site
.330 216 .000 .796 216 .000
Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
.232 216 .000 .805 216 .000
Preservation of natural resources, cultural and heritage
.395 216 .000 .673 216 .000
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
.299 216 .000 .817 216 .000
Job creation due to demolition waste management
.318 216 .000 .752 216 .000
The roles of key stakeholders in monitoring and feedback
.255 216 .000 .784 216 .000
Appendices 235
Factors Kolmogorov-Smirnov Shapiro-Wilk
Statistic df Sig. Statistic df Sig.
Understanding of responsibilities by all stakeholders
.281 216 .000 .768 216 .000
Understanding of demolition waste management procedures
.431 216 .000 .635 216 .000
Effective feedback by stakeholders .333 216 .000 .760 216 .000
Demolition project control meeting .316 216 .000 .776 216 .000
Providing guidelines of demolition waste management plan
.369 216 .000 .632 216 .000
Regular information update .334 216 .000 .712 216 .000
Involvement of key stakeholders in early stage
.402 216 .000 .664 216 .000
Accomplishing government’s policy and strategy on demolition waste management
.360 216 .000 .736 216 .000
236 Appendices
Appendix B2: Academics’ ratings of decision-making factors of demolition waste
management
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
I. Technical factors 3.951
1 On-site sorting/separating of demolition waste
52 3 5 4.392 .563 2
2 Determining the procedures of demolition waste management
52 3 5 4.373 .559 3
3 Planning the area for landfills 52 3 5 4.235 .580 9
4 Planning the area for sorting platform 52 3 5 4.176 .706 13
5 Estimating the amount of demolition waste
52 3 5 4.118 .548 19
6 The use of GIS-based model in demolition waste management
52 3 5 4.118 .646 20
7 Choosing demolition method (reduction of demolition time, cost and waste)
52 3 5 4.098 .634 21
8 Planning storage space for recyclable materials
52 3 5 3.980 .542 24
9 Training the human resources in demolition techniques
52 3 5 3.961 .685 25
10 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
52 3 5 3.902 .602 28
11 Sufficient equipment for demolition project
52 3 5 3.765 .613 37
12 Identifying ricks associate with building’s demolition
52 3 5 3.745 .555 38
13 The use of BIM-based model in demolition waste management
52 3 5 3.706 .497 40
14 Managing time of the duration of demolition
52 3 5 3.627 .559 41
15 Skilled personnel are available for conducting demolition project
52 3 5 3.588 .691 43
16 Life cycle assessment 52 2 4 3.431 .533 48
II. Environmental factors 3.970
1 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
52 3 5 4.314 .700 5
2 The willingness of demolition waste management by stakeholders
52 3 5 4.294 .666 6
3 Training the human resources in the integrated waste management
52 3 5 4.196 .525 11
4 Identifying rate of waste recovery 52 3 5 4.176 .584 14
5 Understanding the uniqueness of demolition waste before demolition stage
52 3 5 4.157 .538 16
Appendices 237
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
6 Environmental Impact Assessment 52 3 5 4.137 .657 17
7 Understanding environmental issues of demolition waste generation
52 3 5 3.922 .589 26
8 The use of recycled materials 52 3 5 3.863 .542 32
9 Understanding of hazardous demolition waste
52 3 5 3.863 .595 33
10 Disposal control (fee, landfill sites) 52 2 5 3.490 .606 46
11 Balancing of greenhouse gases 52 2 4 3.255 .555 49
III. Economic factors 3.914
1 Cost- effective demolition plans 52 3 5 4.333 .705 4
2 Cost estimation of waste transport 52 3 5 4.137 .687 18
3 Estimation of demolition cost 52 3 5 4.078 .621 22
4 Developing of recycling market 52 3 5 3.922 .621 27
5 Reducing cost of demolition waste transportation
52 3 5 3.902 .602 29
6 Cost estimation of waste treatment 52 3 5 3.765 .703 36
7 Saving the amount of energy use (fuels, electricity and others)
52 3 5 3.725 .563 39
8 Developing an appropriate cost for waste disposal
52 2 4 3.451 .636 47
IV. Social factors 3.368
1 Preservation of natural resources, cultural and heritage
52 3 5 4.255 .518 8
2
Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
52 3 5 4.039 .713 23
3 Job creation due to demolition waste management
52 3 5 3.608 .716 42
4
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
52 2 5 3.588 .746 44
5 Reduction of risks, accidences for workers on demolition site
52 2 4 3.588 .566 45
6 Community’s supportive actions before demolition stage
52 2 5 3.176 .759 50
7 The role of community in decision-making process
52 2 4 3.118 .582 51
8 Community’s monitoring of environmental conditions during demolition stage
52 1 4 2.490 .668 52
238 Appendices
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
9 Effective feedback by community 52 1 4 2.451 .636 53
V. Institutional factors 4.076
1 Providing guidelines of demolition waste management plan
52 4 5 4.412 .492 1
2 Regular information update 52 3 5 4.294 .604 7
3 Understanding of responsibilities by all stakeholders
52 3 5 4.235 .644 10
4 The roles of key stakeholders in monitoring and feedback
52 3 5 4.196 .687 12
5 Understanding of demolition waste management procedures
52 3 5 4.176 .473 15
6 Effective feedback by stakeholders 52 3 5 3.902 .533 30
7 Accomplishing government’s policy and strategy on demolition waste management
52 3 5 3.882 .582 31
8 Involvement of key stakeholders in early stage
52 3 5 3.804 .486 34
9 Demolition project control meeting 52 3 5 3.784 .571 35
Appendices 239
Appendix B3: Planners’ ratings of decision-making factors of demolition waste
management
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
I. Technical factors 3.867
1 On-site sorting/separating of demolition waste
37 4 5 4.405 .498 3
2 Planning the area for landfills 37 3 5 4.324 .626 6
3 Estimating the amount of demolition waste
37 3 5 4.297 .463 8
4 Determining the procedures of demolition waste management
37 4 5 4.297 .661 9
5 Planning storage space for recyclable materials
37 3 5 4.108 .516 15
6 Choosing demolition method (reduction of demolition time, cost and waste)
37 3 5 4.108 .567 17
7 Planning the area for sorting platform 37 3 5 4.027 .687 22
8 Training the human resources in demolition techniques
37 2 5 4.027 .833 23
9 Identifying ricks associate with building’s demolition
37 3 5 3.838 .442 26
10 Sufficient equipment for demolition project
37 2 5 3.811 .739 28
11 Managing time of the duration of demolition
37 3 5 3.784 .479 31
12 The use of BIM-based modelin demolition waste management
37 3 5 3.622 .545 39
13 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
37 2 5 3.486 .692 43
14 The use of GIS-based model in demolition waste management
37 2 5 3.432 .603 45
15 Life cycle assessment 37 2 5 3.324 .747 46
16 Skilled personnel are available for conducting demolition project
37 2 5 2.973 .763 48
II. Environmental factors 3.826
1 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
37 3 5 4.270 .450 10
2 Understanding the uniqueness of demolition waste before demolition stage
37 4 5 4.270 .608 11
3 The willingness of demolition waste management by stakeholders
37 3 5 4.216 .630 12
4 Identifying rate of waste recovery 37 3 5 4.027 .645 21
5 Environmental Impact Assessment 37 2 5 4.000 .624 24
6 Training the human resources in the integrated waste management
37 3 5 3.973 .552 25
7 Understanding environmental issues of demolition waste generation
37 2 5 3.757 .548 32
8 The use of recycled materials 37 3 5 3.676 .530 36
240 Appendices
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
9 Understanding of hazardous demolition waste
37 2 5 3.622 .639 38
10 Disposal control (fee, landfill sites) 37 2 5 3.486 .731 44
11 Balancing of greenhouse gases 37 2 4 2.784 .479 51
III. Economic factors 3.787
1 Cost- effective demolition plans 37 3 5 4.351 .676 5
2 Cost estimation of waste transport 37 3 5 4.081 .595 18
3 Estimation of demolition cost 37 3 5 3.838 .553 27
4 Developing of recycling market 37 3 5 3.784 .630 30
5 Reducing cost of demolition waste transportation
37 3 5 3.757 .683 33
6 Cost estimation of waste treatment 37 3 5 3.730 .652 34
7 Saving the amount of energy use (fuels, electricity and others)
37 2 5 3.514 .692 42
8 Developing an appropriate cost for waste disposal
37 2 4 3.243 .548 47
IV. Social factors 3.330
1 Preservation of natural resources, cultural and heritage
37 3 5 4.162 .553 14
2 Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
37 3 5 4.108 .737 16
3 Reduction of risks, accidences for workers on demolition site
37 2 4 3.649 .538 37
4 Job creation due to demolition waste management
37 3 5 3.541 .558 40
5
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
37 3 5 3.541 .650 41
6 Community’s supportive actions before demolition stage
37 2 5 2.973 .687 49
7 The role of community in decision-making process
37 2 4 2.838 .442 50
8 Community’s monitoring of environmental conditions during demolition stage
37 1 4 2.622 .758 52
9 Effective feedback by community 37 1 4 2.541 .767 53
V. Institutional factors 4.180
1 Providing guidelines of demolition waste management plan
37 4 5 4.568 .502 1
2 Regular information update 37 4 5 4.459 .505 2
3 Understanding of responsibilities by all stakeholders
37 3 5 4.405 .644 4
4 The roles of key stakeholders in monitoring and feedback
37 3 5 4.324 .709 7
5 Understanding of demolition waste management procedures
37 3 5 4.216 .534 13
6 Demolition project control meeting 37 3 5 4.054 .468 19
Appendices 241
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
7 Involvement of key stakeholders in early stage
37 3 5 4.054 .705 20
8 Accomplishing government’s policy and strategy on demolition waste management
37 3 5 3.811 .518 29
9 Effective feedback by stakeholders 37 3 5 3.730 .652 35
242 Appendices
Appendix B4: Consultants’ ratings of decision-making factors of demolition waste
management
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
I. Technical factors 3.959
1 Determining the procedures of demolition waste management
29 3 5 4.517 .574 1
2 On-site sorting/separating of demolition waste
29 4 5 4.448 .506 2
3 Estimating the amount of demolition waste
29 3 5 4.310 .712 7
4 Planning the area for landfills 29 3 5 4.207 .559 10
5 Planning storage space for recyclable materials
29 3 5 4.207 .563 11
6 Planning the area for sorting platform 29 3 5 4.138 .693 15
7 Choosing demolition method (reduction of demolition time, cost and waste)
29 3 5 3.966 .566 19
8 The use of BIM-based model in demolition waste management
29 3 5 3.931 .623 21
9 Training the human resources in demolition techniques
29 3 5 3.931 .651 23
10 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
29 3 5 3.897 .557 25
11 Sufficient equipment for demolition project
29 3 5 3.862 .693 26
12 The use of GIS-based model in demolition waste management
29 3 5 3.793 .559 32
13 Identifying ricks associate with building’s demolition
29 3 5 3.690 .712 40
14 Managing time of the duration of demolition
29 3 5 3.655 .553 41
15 Skilled personnel are available for conducting demolition project
29 2 5 3.552 .686 44
16 Life cycle assessment 29 2 5 3.241 .689 47
II. Environmental factors 3.881
1 2. The willingness of demolition waste management by stakeholders
29 3 5 4.379 .728 3
2 4. Understanding the uniqueness of demolition waste before demolition stage
29 3 5 4.310 .541 8
3 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
29 3 5 4.241 .577 9
Appendices 243
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
4 Environmental Impact Assessment 29 3 5 4.172 .642 13
5 Identifying rate of waste recovery 29 3 5 4.103 .673 18
6 Understanding environmental issues of demolition waste generation
29 3 5 3.931 .651 24
7 Training the human resources in the integrated waste management
29 3 5 3.759 .577 36
8 The use of recycled materials 29 3 5 3.690 .541 38
9 Disposal control (fee, landfill sites) 29 3 5 3.621 .561 42
10 Understanding of hazardous demolition waste
29 3 5 3.621 .677 43
11 Balancing of greenhouse gases 29 2 4 2.862 .516 49
III. Economic factors 3.737
1 Cost- effective demolition plans 29 3 5 4.138 .639 16
2 Estimation of demolition cost 29 3 5 3.931 .651 22
3 Cost estimation of waste transport 29 3 5 3.862 .685 27
4 Reducing cost of demolition waste transportation
29 3 5 3.860 .693 29
5 Cost estimation of waste treatment 29 3 5 3.759 .636 35
6 Developing of recycling market 29 3 4 3.724 .455 37
7 Saving the amount of energy use (fuels, electricity and others)
29 3 4 3.517 .509 45
8 Developing an appropriate cost for waste disposal
29 2 4 3.103 .618 48
IV. Social factors 3.341
1 Preservation of natural resources, cultural and heritage
29 4 5 4.345 .484 6
2 Reduction of community disturbance during demolition stage (e.g.demolition noise, dust and other pollutions)
29 3 5 3.966 .680 20
3 Reduction of risks, accidences for workers on demolition site
29 3 5 3.759 .689 33
4
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
29 3 5 3.690 .541 39
5 Job creation due to demolition waste management
29 3 5 3.483 .634 46
6 Community’s supportive actions before demolition stage
29 2 4 2.793 .559 50
7 Effective feedback by community 29 2 4 2.691 .541 51
244 Appendices
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
8 The role of community in decision-making process
29 2 4 2.690 .604 52
9 Community’s monitoring of environmental conditions during demolition stage
29 2 4 2.655 .553 53
V. Institutional factors 4.050
1 Providing guidelines of demolition waste management plan
29 4 5 4.379 .494 4
2 Regular information update 29 3 5 4.379 .561 5
3 Understanding of responsibilities by all stakeholders
29 3 5 4.172 .602 12
4 The roles of key stakeholders in monitoring and feedback
29 3 5 4.172 .658 14
5 Understanding of demolition waste management procedures
29 3 5 4.103 .409 17
6 Involvement of key stakeholders in early stage
29 3 5 3.862 .516 28
7 Demolition project control meeting 29 3 5 3.828 .711 30
8 Effective feedback by stakeholders 29 3 5 3.793 .675 31
9 Accomplishing government’s policy and strategy on demolition waste management
29 3 5 3.759 .636 34
Appendices 245
Appendix B5: Engineers’ rating of decision-making factors of demolition waste
management
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
I. Technical factors 4.010
1 On-site sorting/separating of demolition waste
57 3 5 4.491 .539 1
2 Determining the procedures of demolition waste management
57 3 5 4.421 .533 3
3 The use of GIS-based model in demolition waste management
57 2 5 4.298 .706 10
4 Choosing demolition method (reduction of demolition time, cost and waste)
57 3 5 4.263 .583 12
5 Estimating the amount of demolition waste
57 3 5 4.263 .642 13
6 Training the human resources in demolition techniques
57 3 5 4.228 .598 14
7 Planning the area for landfills 57 3 5 4.035 .654 21
8 Planning the area for sorting platform 57 3 5 4.018 .517 23
9 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
57 3 5 3.947 .692 27
10 Sufficient equipment for demolition project
57 3 5 3.912 .714 30
11 Planning storage space for recyclable materials
57 2 5 3.895 .489 34
12 The use of BIM-based model in demolition waste management
57 3 5 3.872 .588 35
13 Managing time of the duration of demolition
57 2 5 3.860 .611 37
14 Identifying ricks associate with building’s demolition
57 2 5 3.772 .535 38
15 Skilled personnel are available for conducting demolition project
57 3 4 3.491 .504 46
16 Life cycle assessment 57 2 5 3.368 .645 47
II. Environmental factors 3.821
1 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
57 3 5 4.211 .559 15
2 Training the human resources in the integrated waste management
57 3 5 4.193 .549 16
3 The willingness of demolition waste management by stakeholders
57 2 5 4.018 .582 22
4 Environmental Impact Assessment 57 3 5 3.930 .495 28
246 Appendices
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
5 Identifying rate of waste recovery 57 2 5 3.930 .623 29
6 Understanding the uniqueness of demolition waste before demolition stage
57 3 5 3.912 .606 31
7 Understanding environmental issues of demolition waste generation
57 3 5 3.772 .682 39
8 The use of recycled materials 57 3 5 3.760 .576 40
9 Understanding of hazardous demolition waste
57 2 5 3.754 .635 41
10 Disposal control (fee, landfill sites) 57 3 5 3.667 .636 44
11 Balancing of greenhouse gases 57 2 4 2.895 .673 51
III. Economic factors 3.974
1 Cost estimation of waste transport 57 3 5 4.386 .590 5
2 Cost- effective demolition plans 57 3 5 4.333 .636 8
3 Cost estimation of waste treatment 57 3 5 4.140 .549 18
4 Estimation of demolition cost 57 2 5 4.088 .635 20
5 Reducing cost of demolition waste transportation
57 2 5 3.965 .706 26
6 Developing of recycling market 57 3 5 3.860 .639 36
7 Saving the amount of energy use (fuels, electricity and others)
57 3 5 3.737 .669 42
8 Developing an appropriate cost for waste disposal
57 2 4 3.281 .620 48
IV. Social factors 3.480
1 Preservation of natural resources, cultural and heritage
57 4 5 4.351 .481 7
2 Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
57 3 5 4.158 .774 17
3 Reduction of risks, accidences for workers on demolition site
57 2 5 4.105 .724 19
4 Job creation due to demolition waste management
57 3 5 3.702 .706 43
5
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
57 2 5 3.632 .698 45
6 Community’s supportive actions before demolition stage
57 2 4 3.053 .666 49
7 The role of community in decision-making process
57 2 4 2.982 .582 50
Appendices 247
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
8 Community’s monitoring of environmental conditions during demolition stage
57 1 4 2.667 .607 52
9 Effective feedback by community 57 1 4 2.667 .715 53
V. Institutional factors 4.175
1 Regular information update 57 3 5 4.474 .538 2
2 Understanding of responsibilities by all stakeholders
57 3 5 4.404 .704 4
3 Providing guidelines of demolition waste management plan
57 4 5 4.368 .487 6
4 The roles of key stakeholders in monitoring and feedback
57 3 5 4.316 .686 9
5 Understanding of demolition waste management procedures
57 3 5 4.263 .483 11
6 Involvement of key stakeholders in early stage
57 3 5 3.982 .551 24
7 Demolition project control meeting 57 3 5 3.965 .533 25
8 Accomplishing government’s policy and strategy on demolition waste management
57 3 5 3.912 .544 32
9 Effective feedback by stakeholders 57 3 5 3.895 .588 33
248 Appendices
Appendix B6: Policy Makers’ rating of decision-making factors of demolition waste
management
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
I. Technical factors 3.839
1 Determining the procedures of demolition waste management
43 4 5 4.333 .471 6
2 On-site sorting/separating of demolition waste
43 4 5 4.310 .462 8
3 Planning the area for landfills 43 3 5 4.143 .559 15
4 Estimating the amount of demolition waste
43 3 5 4.126 .586 17
5 Choosing demolition method (reduction of demolition time, cost and waste)
43 3 5 4.119 .543 18
6 Planning storage space for recyclable materials
43 3 5 4.071 .402 22
7 Training the human resources in demolition techniques
43 2 5 3.929 .632 24
8 Planning the area for sorting platform 43 3 5 3.905 .569 26
9 Identifying ricks associate with building’s demolition
43 3 5 3.881 .391 27
10 Managing time of the duration of demolition
43 3 5 3.738 .491 32
11 The use of selective demolition method (on-site sorting, separate waste for reuse and recycling)
43 3 5 3.714 .502 36
12 Sufficient equipment for demolition project
43 3 5 3.714 .665 37
13 The use of GIS-based model in demolition waste management
43 2 5 3.524 .587 42
14 The use of BIM-based model in demolition waste management
43 3 4 3.405 .491 45
15 Life cycle assessment 43 2 5 3.310 .672 46
16 Skilled personnel are available for conducting demolition project
43 2 4 3.214 .465 47
II. Environmental factors 3.909
1 Promotion of 3R in demolition waste management (reduction, reuse and recycling of demolition waste)
43 3 5 4.381 .615 3
2 Training the human resources in the integrated waste management
43 3 5 4.310 .597 7
3 Identifying rate of waste recovery 43 3 5 4.143 .412 16
Appendices 249
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
4 Understanding the uniqueness of demolition waste before demolition stage
43 3 5 4.119 .662 19
5 Environmental Impact Assessment 43 3 5 4.095 .610 20
6 The willingness of demolition waste management by stakeholders
43 3 5 4.095 .750 21
7 The use of recycled materials 43 2 5 3.857 .710 28
8 Understanding environmental issues of demolition waste generation
43 3 5 3.667 .678 38
9 Understanding of hazardous demolition waste
43 1 5 3.647 .777 40
10 Disposal control (fee, landfill sites) 43 3 5 3.619 .532 41
11 Balancing of greenhouse gases 43 2 4 3.048 .575 49
III. Economic factors 3.866
1 Cost- effective demolition plans 43 3 5 4.310 .556 9
2 Cost estimation of waste transport 43 3 5 4.238 .569 12
3 Estimation of demolition cost 43 3 5 4.190 .545 13
4 Cost estimation of waste treatment 43 3 5 4.048 .434 23
5 Developing of recycling market 43 3 5 3.738 .537 33
6 Reducing cost of demolition waste transportation
43 3 5 3.738 .657 34
7 Saving the amount of energy use (fuels, electricity and others)
43 2 5 3.476 .698 44
8 Developing an appropriate cost for waste disposal
43 2 4 3.190 .587 48
IV. Social factors 3.381
1 Preservation of natural resources, cultural and heritage
43 4 5 4.429 .495 2
2 Reduction of community disturbance during demolition stage (e.g. demolition noise, dust and other pollutions)
43 3 5 4.238 .717 11
3 Reduction of risks, accidences for workers on demolition site
43 3 5 3.762 .526 31
4 Job creation due to demolition waste management
43 3 5 3.667 .713 39
250 Appendices
No. Decision-making Factors N Minimum Maximum Mean Std.
Deviation Rank
5
Increasing public awareness of integrated demolition waste management/sustainable urban redevelopment
43 2 5 3.524 .763 43
6 The role of community in decision-making process
43 2 4 2.881 .697 50
7 Community’s supportive actions before demolition stage
43 1 4 2.690 .672 51
8 Community’s monitoring of environmental conditions during demolition stage
43 1 4 2.643 .610 52
9 Effective feedback by community 43 1 4 2.595 .580 53
V. Institutional factors 4.116
1 Providing guidelines of demolition waste management plan
43 4 5 4.524 .499 1
2 Regular information update 43 3 5 4.381 .532 4
3 Understanding of responsibilities by all stakeholders
43 3 5 4.381 .653 5
4 The roles of key stakeholders in monitoring and feedback
43 3 5 4.262 .657 10
5 Understanding of demolition waste management procedures
43 3 5 4.190 .449 14
6 Involvement of key stakeholders in early stage
43 3 5 3.905 .366 25
7 Accomplishing government’s policy and strategy on demolition waste management
43 3 5 3.857 .559 29
8 Demolition project control meeting 43 3 5 3.810 .626 30
9 Effective feedback by stakeholders 43 3 5 3.738 .580 35
Appendices 251
APPENDIX C. INVITATION LETTER – INTERVIEW
Invitation to an interview on:
CRITICAL FACTORS OF IMPROVING DEMOLITION WASTE MANAGEMENT
FOR VIETNAMESE URBANE REDEVELOPMENT PROJECTS
Dear Sir/madam
Thanks again for agreeing to take part in the study. I am writing to confirm our meeting on date,
time.
To quickly recap, I am currently undertaking a PhD study in the School of Civil Engineering and
Built Environment, Science and Engineering Faculty at Queensland University of Technology
(QUT). I am doing a study into the improvement of decision-making process of demolition waste
management for Vietnam urban redevelopment at a large scale.
The interview questions will be sent for your reference before the interview takes place.
The main items to be discussed are:
1. The significant influence of critical factors of urban redevelopment DW management in
Vietnam.
2. Comment on related policy and strategy of urban redevelopment DW management in
Vietnam.
3. Comment on the challenges and opportunities that might be faced by critical factors in the
context of Vietnam.
4. Provide your opinion about the action plans for improving DW management in Vietnamese
urban redevelopment projects.
Please note that this study has been approved by the QUT Human Research Ethics Committee
(approval number 1600000588). Please kindly see the attached sheet (Participant information for
QUT research project) for more information about my research.
The confidentiality of every participant in this study is of the utmost importance. Your identity
will not be disclosed and data summited will not be identified by the responses.
Should you wish to find out more about the research or have any questions, please contact me via
email.
Best regards
Diep Thi Bui
PhD Candidate Student
252 Appendices
School of Civil Engineering and Built Environment
Science and Engineering Faculty
Queensland University of Technology (QUT)
Tel: +61 4 5225 6311/+84 9 0345 5101
Email: [email protected]
Appendices 253
APPENDIX D. DATA COLLECTION AND ANALYSIS FOR CASE STUDY
Appendix D1: Estimation of demolition waste for each urban redevelopment project in Ba Dinh district
No Project Building name Block
symbol
Block Length
(m)
Block width (m)
Storey numbers
Total block height (m)
1 Giang Vo Building D GV_D1 71.3 11.87 5 15.0
2 Giang Vo Building D GV_D3 71.3 11.87 5 15.0
2 Giang Vo Building D GV_D4 71.3 11.87 5 15.0
3 Giang Vo Building D GV_D5 71.3 11.87 5 15.0
4 Giang Vo Building D GV_D6 71.3 11.87 5 15.0
5 Ngoc Khanh I Building A NK_A1 79.2 10.87 5 15.0
6 Ngoc Khanh I Building A NK_A2 79.2 10.87 5 15.0
7 Ngoc Khanh I Building B NK_B 79.2 10.77 5 15.0
8 Ngoc Khanh II Building D NK_D1 31.8 12.87 3 8.4
9 Ngoc Khanh II Building D NK_D2 31.8 12.87 3 8.4
10 Ngoc Khanh II Building D NK_D3A 28.8 12.87 3 8.4
11 Ngoc Khanh II Building D NK_D3B 27.0 12.87 3 8.4
12 Thanh Cong Building A TC_A1 103.5 12.77 5 15.0
13 Thanh Cong Building A TC_A2 103.5 12.77 5 15.0
14 Thanh Cong Building A TC_A3 103.5 12.77 5 15.0
15 Thanh Cong Building A TC_A4 103.5 12.77 5 15.0
16 Thanh Cong Building A TC_A5 103.5 12.77 5 15.0
17 Thanh Cong Building A TC_A6 51.8 12.77 5 15.0
18 Thanh Cong Building A TC_A6A 51.8 12.77 5 15.0
19 Thanh Cong Building B TC_B1 169.7 11.77 5 15.0
20 Thanh Cong Building B TC_B2 35.6 12.77 5 15.0
21 Thanh Cong Building B TC_B2A 106.9 12.77 4 12.0
22 Thanh Cong Building B TC_B3 35.6 12.77 5 15.0
23 Thanh Cong Building B TC_B4 35.6 12.77 5 15.0
24 Thanh Cong Building B TC_B5 106.9 12.77 5 15.0
25 Thanh Cong Building B TC_B6 35.6 12.77 5 15.0
26 Thanh Cong Building B TC_B7 35.6 12.77 5 15.0
27 Thanh Cong Building D TC_D1 69.6 9.57 5 15.0
28 Thanh Cong Building D TC_D10 34.8 9.57 5 15.0
29 Thanh Cong Building D TC_D11 34.8 9.57 5 15.0
30 Thanh Cong Building D TC_D2 34.8 9.57 5 15.0
31 Thanh Cong Building D TC_D3 69.6 9.57 5 15.0
32 Thanh Cong Building D TC_D4_1 30.3 8.77 5 15.0
33 Thanh Cong Building D TC_D4_2 33.7 8.77 5 15.0
34 Thanh Cong Building D TC_D7 69.6 9.57 5 15.0
35 Thanh Cong Building D TC_D8 69.6 9.57 5 15.0
36 Thanh Cong Building D TC_D9 34.8 9.57 5 15.0
254 Appendices
No Storey height
(m)
unit numbers in each floor
Stair numbers of each floor
Width of each
stair (m)
unit height in actual use (m)
unit length
actual use (m)
unit width in actual
use (m)
Total unit area in
actual use (m2)
1 3.0 16 2 3.4 2.8 9.2 3.8 35.0
2 3.0 16 2 3.4 2.8 9.2 3.8 35.0
2 3.0 16 2 3.4 2.8 9.2 3.8 35.0
3 3.0 16 2 3.4 2.8 9.2 3.8 35.0
4 3.0 16 2 3.4 2.8 9.2 3.8 35.0
5 3.0 12 2 3.4 2.8 8 5.8 46.4
6 3.0 12 2 3.4 2.8 8 5.8 46.4
7 3.0 12 2 3.4 2.8 8 5.8 46.4 8 2.8 8 1 2.8 2.8 10 3.4 34.0
9 2.8 8 1 2.8 2.8 10 3.4 34.0 10 2.8 6 1 2.8 2.8 10 4.1 41.0
11 2.8 6 1 2.8 2.8 10 3.8 38.0
12 3.0 24 2 3.4 2.8 10 3.8 38.0
13 3.0 24 2 3.4 2.8 10 3.8 38.0
14 3.0 24 2 3.4 2.8 10 3.8 38.0
15 3.0 24 2 3.4 2.8 10 3.8 38.0
16 3.0 24 2 3.4 2.8 10 3.8 38.0
17 3.0 12 1 3.4 2.8 10 3.8 38.0
18 3.0 12 1 3.4 2.8 10 3.8 38.0
19 3.0 36 3 3.4 2.8 9 4.2 37.8
20 3.0 8 1 3.4 2.8 10 3.8 38.0
21 3.0 24 3 3.4 2.8 10 3.8 38.0
22 3.0 8 1 3.4 2.8 10 3.8 38.0
23 3.0 8 1 3.4 2.8 10 3.8 38.0
24 3.0 24 3 3.4 2.8 10 3.8 38.0
25 3.0 8 1 3.4 2.8 10 3.8 38.0
26 3.0 8 1 3.4 2.8 10 3.8 38.0
27 3.0 12 2 3.4 2.8 6.8 5 34.0
28 3.0 6 1 3.4 2.8 6.8 5 34.0
29 3.0 6 1 3.4 2.8 6.8 5 34.0
30 3.0 6 1 3.4 2.8 6.8 5 34.0
31 3.0 12 2 3.4 2.8 6.8 5 34.0
32 3.0 4 1 3.4 2.8 6 6.5 39.0
33 3.0 4 2 3.4 2.8 6 6.5 39.0
34 3.0 12 2 3.4 2.8 6.8 5 34.0
35 3.0 12 2 3.4 2.8 6.8 5 34.0
36 3.0 6 1 3.4 2.8 6.8 5 34.0
Appendices 255
No Room number in each
unit
Width of bed
room 1 (m)
Length of bed room 1
(m)
Total bed room 1
area (m2)
Total wall area of bed
room 1 (m2)
Width of bed room
2 (m)
Length of bed room
2 (m)
Total bed room 2
area (m2)
1 4 3.7 3.8 15.37 42.08 2 4 8.95
2 4 3.7 3.8 15.37 42.08 2 4 8.95
2 4 3.7 3.8 15.37 42.08 2 4 8.95
3 4 3.7 3.8 15.37 42.08 2 4 8.95
4 4 3.7 3.8 15.37 42.08 2 4 8.95
5 4 2.8 5.8 17.58 49.88 2.8 5.2 15.83
6 4 2.8 5.8 17.58 49.88 3.8 5.2 21.26
7 4 2.8 5.8 17.58 49.88 3.8 5.2 21.26
8 3 2.8 5 15.25 43.26 2.8 3.6 11.16
9 3 2.8 5 15.25 43.26 2.8 3.6 11.16
10 3 3.2 5.8 19.99 57.32 2.8 3.6 11.16
11 3 3 5.8 18.78 53.94 2.8 3.6 11.16
12 4 2 6 13.18 38.35 2 4 8.95
13 4 2 6 13.18 38.35 2 4 8.95
14 4 2 6 13.18 38.35 2 4 8.95
15 4 2 6 13.18 38.35 2 4 8.95
16 4 2 6 13.18 38.35 2 4 8.95
17 4 2 6 13.18 38.35 2 4 8.95
18 4 2 6 13.18 38.35 2 4 8.95
19 4 2.6 5 14.20 40.25 2.6 4 11.48
20 4 2.6 5 14.20 40.25 2.6 4 11.48
21 4 2.6 5 14.20 40.25 2.6 4 11.48
22 4 2.6 5 14.20 40.25 2.6 4 11.48
23 4 2.6 5 14.20 40.25 2.6 4 11.48
24 4 2.6 5 14.20 40.25 2.6 4 11.48
25 4 2.6 5 14.20 40.25 2.6 4 11.48
26 4 2.6 5 14.20 40.25 2.6 4 11.48
27 4 3.5 3.2 12.40 33.47 3.5 3.6 13.85
28 4 3.2 3.5 12.36 33.67 3.5 3.6 13.85
29 4 3.2 3.5 12.36 33.67 3.5 3.6 13.85
30 4 3.5 3.2 12.40 33.47 3.5 3.6 13.85
31 4 3.5 3.2 12.40 33.47 3.5 3.6 13.85
32 4 3.5 4 15.29 42.34 2.5 4.8 13.15
33 4 3.5 4 15.29 42.34 3.5 3.6 13.85
34 4 3.2 3.5 12.36 33.67 3.5 3.6 13.85
35 4 3.2 3.5 12.36 33.67 3.5 3.6 13.85
36 4 3.2 3.5 12.36 33.67 3.5 3.6 13.85
256 Appendices
No Total wall area of bed room 2 (m2)
Width of
dining room (m)
Length of dining room (m)
Total dining
room area (m2)
Total wall area of dining
room (m2)
Width of bath
room & WC (m)
Length of bath room & WC (m)
Total bath room & WC area
(m2)
1 25.96 1.8 5.5 10.97 34.58 1.5 2 3.60
2 25.96 1.8 5.5 10.97 34.58 1.5 2 3.60
2 25.96 1.8 5.5 10.97 34.58 1.5 2 3.60
3 25.96 1.8 5.5 10.97 34.58 1.5 2 3.60
4 25.96 1.8 5.5 10.97 34.58 1.5 2 3.60
5 46.09 3 3.7 12.24 36.39 1.5 2.2 3.92
6 61.29 3 3.7 12.24 36.39 1.5 2.2 3.92
7 61.29 3 3.7 12.24 36.39 1.5 2.2 3.92
8 32.00 1.8 2.2 4.65 13.86 1.5 1.5 2.79
9 32.00 1.8 2.2 4.65 13.86 1.5 1.5 2.79
10 32.00 1.8 2.2 4.65 13.86 1.5 2 3.60
11 32.00 1.8 2.2 4.65 13.86 1.5 2 3.60
12 26.26 1.8 7 13.85 44.07 1.8 3 6.19
13 26.26 1.8 7 13.85 44.07 1.8 3 6.19
14 26.26 1.8 7 13.85 44.07 1.8 3 6.19
15 26.26 1.8 7 13.85 44.07 1.8 3 6.19
16 26.26 1.8 7 13.85 44.07 1.8 3 6.19
17 26.26 1.8 7 13.85 44.07 1.8 3 6.19
18 26.26 1.8 7 13.85 44.07 1.8 3 6.19
19 33.36 1.6 6 10.68 34.25 1.6 3 5.54
20 33.36 1.6 6 10.68 34.25 1.6 3 5.54
21 33.36 1.6 6 10.68 34.25 1.6 3 5.54
22 33.36 1.6 6 10.68 34.25 1.6 3 5.54
23 33.36 1.6 6 10.68 34.25 1.6 3 5.54
24 33.36 1.6 6 10.68 34.25 1.6 3 5.54
25 33.36 1.6 6 10.68 34.25 1.6 3 5.54
26 33.36 1.6 6 10.68 34.25 1.6 3 5.54
27 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
28 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
29 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
30 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
31 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
32 38.81 2 4.5 10.00 30.90 1.5 2 3.60
33 39.59 2 4.5 10.00 30.90 1.5 2 3.60
34 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
35 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
36 39.59 1.5 3.8 6.51 20.44 1.5 3 5.22
Appendices 257
No Total wall area of bath & WC (m2)
Corridor width per unit (m)
Wall height of corridor
barrier per unit (m)
Total wall area of corridor
barrier per unit (m2)
Balcony numbers in unit
Balcony width in unit (m)
Balcony length in unit (m)
1 10.74 1.4 1.2 4.8 1 0.8 3.8
2 10.74 1.4 1.2 4.8 1 0.8 3.8
2 10.74 1.4 1.2 4.8 1 0.8 3.8
3 10.74 1.4 1.2 4.8 1 0.8 3.8
4 10.74 1.4 1.2 4.8 1 0.8 3.8
5 11.54 1.6 1.2 7.2 1 0.8 5.8
6 11.54 1.6 1.2 7.2 1 0.8 5.8
7 11.54 1.6 1.3 7.8 1 0.8 5.8
8 8.05 1.6 1.3 4.7 1 0.8 3.4
9 8.05 1.6 1.3 4.7 1 0.8 3.4
10 10.80 1.6 1.3 5.6 1 0.8 3.4
11 10.80 1.6 1.3 5.2 1 0.8 3.4
12 19.24 1.5 1.3 5.2 1 0.8 3.8
13 19.24 1.5 1.3 5.2 1 0.8 3.8
14 19.24 1.5 1.3 5.2 1 0.8 3.8
15 19.24 1.5 1.3 5.2 1 0.8 3.8
16 19.24 1.5 1.3 5.2 1 0.8 3.8
17 19.24 1.5 1.3 5.2 1 0.8 3.8
18 19.24 1.5 1.3 5.2 1 0.8 3.8
19 17.43 1.5 1.3 5.8 1 0.8 4.2
20 17.43 1.5 1.3 5.2 1 0.8 3.8
21 17.43 1.5 1.3 5.2 1 0.8 3.8
22 17.43 1.5 1.3 5.2 1 0.8 3.8
23 17.43 1.5 1.3 5.2 1 0.8 3.8
24 17.43 1.5 1.3 5.2 1 0.8 3.8
25 17.43 1.5 1.3 5.2 1 0.8 3.8
26 17.43 1.5 1.3 5.2 1 0.8 3.8
27 16.53 1.5 1.3 6.8 1 0.8 5
28 16.53 1.5 1.3 6.8 1 0.8 5
29 16.53 1.5 1.3 6.8 1 0.8 5
30 16.53 1.5 1.3 6.8 1 0.8 5
31 16.53 1.5 1.3 6.8 1 0.8 5
32 11.04 1.5 1.3 8.7 1 0.8 6.5
33 11.04 1.5 1.3 8.7 1 0.8 6.5
34 16.53 1.5 1.3 6.8 1 0.8 5
35 16.53 1.5 1.3 6.8 1 0.8 5
36 16.53 1.5 1.3 6.8 1 0.8 5
258 Appendices
No Wall height of
balcony of unit (m)
Total wall area of balcony in
each unit (m2)
Door numbers in each unit
Door height in each unit
(m)
Door width in each unit
(m)
Each door area of each
unit (m2)
Door material
1 1 4.0 5 2.1 0.8 1.68 Iron
2 1 4.0 5 2.1 0.8 1.68 Iron
2 1 4.0 5 2.1 0.8 1.68 Iron
3 1 4.0 5 2.1 0.8 1.68 Iron
4 1 4.0 5 2.1 0.8 1.68 Iron
5 1 6.0 5 2.1 0.8 1.68 Iron
6 1 6.0 5 2.1 0.8 1.68 Iron
7 1 6.0 5 2.1 0.8 1.68 Iron
8 1 3.6 5 1.9 0.8 1.52 Iron
9 1 3.6 5 1.9 0.8 1.52 Iron
10 1 4.3 5 1.9 0.8 1.52 Iron
11 1 4.0 5 1.9 0.8 1.52 Iron
12 1 4.0 5 2.1 0.8 1.68 Iron
13 1 4.0 5 2.1 0.8 1.68 Iron
14 1 4.0 5 2.1 0.8 1.68 Iron
15 1 4.0 5 2.1 0.8 1.68 Iron
16 1 4.0 5 2.1 0.8 1.68 Iron
17 1 4.0 5 2.1 0.8 1.68 Iron
18 1 4.0 5 2.1 0.8 1.68 Iron
19 1 4.4 5 2.1 0.8 1.68 Iron
20 1 4.0 5 2.1 0.8 1.68 Iron
21 1 4.0 5 2.1 0.8 1.68 Iron
22 1 4.0 5 2.1 0.8 1.68 Iron
23 1 4.0 5 2.1 0.8 1.68 Iron
24 1 4.0 5 2.1 0.8 1.68 Iron
25 1 4.0 5 2.1 0.8 1.68 Iron
26 1 4.0 5 2.1 0.8 1.68 Iron
27 1 5.2 5 2.1 0.8 1.68 Iron
28 1 5.2 5 2.1 0.8 1.68 Iron
29 1 5.2 5 2.1 0.8 1.68 Iron
30 1 5.2 5 2.1 0.8 1.68 Iron
31 1 5.2 5 2.1 0.8 1.68 Iron
32 1 6.7 5 2.1 0.8 1.68 Iron
33 1 6.7 5 2.1 0.8 1.68 Iron
34 1 5.2 5 2.1 0.8 1.68 Iron
35 1 5.2 5 2.1 0.8 1.68 Iron
36 1 5.2 5 2.1 0.8 1.68 Iron
Appendices 259
No Specific
weight of ion
(kg/m3)
Total weight of door (kg)
Window number in each unit
Window height in each unit
(m)
Window width in each unit
(m)
Each window area in
each unit (m2)
Window material
Total weight of window
(kg)
1 770 77.616 2 1.5 1 1.5 Wood 69.3 2 770 77.616 2 1.5 1 1.5 Wood 69.3
2 770 77.616 2 1.5 1 1.5 Wood 69.3
3 770 77.616 2 1.5 1 1.5 Wood 69.3
4 770 77.616 2 1.5 1 1.5 Wood 69.3
5 770 77.616 2 1.5 1.2 1.8 Iron 83.16
6 770 77.616 2 1.5 1.2 1.8 Iron 83.16
7 770 77.616 2 1.5 1.2 1.8 Iron 83.16
8 770 70.224 2 1.2 1.2 1.44 Iron 66.528
9 770 70.224 2 1.2 1.2 1.44 Iron 66.528
10 770 70.224 2 1.2 1.2 1.44 Iron 66.528
11 770 70.224 2 1.2 1.2 1.44 Iron 66.528
12 770 77.616 2 1.2 1 1.2 Wood 55.44
13 770 77.616 2 1.2 1 1.2 Wood 55.44
14 770 77.616 2 1.2 1 1.2 Wood 55.44
15 770 77.616 2 1.2 1 1.2 Wood 55.44
16 770 77.616 2 1.2 1 1.2 Wood 55.44
17 770 77.616 2 1.2 1 1.2 Wood 55.44
18 770 77.616 2 1.2 1 1.2 Wood 55.44
19 770 77.616 2 1.2 1 1.2 Wood 55.44
20 770 77.616 2 1.2 1 1.2 Wood 55.44
21 770 77.616 2 1.2 1 1.2 Wood 55.44
22 770 77.616 2 1.2 1 1.2 Wood 55.44
23 770 77.616 2 1.2 1 1.2 Wood 55.44
24 770 77.616 2 1.2 1 1.2 Wood 55.44
25 770 77.616 2 1.2 1 1.2 Wood 55.44
26 770 77.616 2 1.2 1 1.2 Wood 55.44
27 770 77.616 2 1.2 1 1.2 Wood 55.44
28 770 77.616 2 1.2 1 1.2 Wood 55.44
29 770 77.616 2 1.2 1 1.2 Wood 55.44
30 770 77.616 2 1.2 1 1.2 Wood 55.44
31 770 77.616 2 1.2 1 1.2 Wood 55.44
32 770 77.616 2 1.2 1 1.2 Wood 55.44
33 770 77.616 2 1.2 1 1.2 Wood 55.44
34 770 77.616 2 1.2 1 1.2 Wood 55.44
35 770 77.616 2 1.2 1 1.2 Wood 55.44
36 770 77.616 2 1.2 1 1.2 Wood 55.44
260 Appendices
No Total wall area for each
unit (m2)
Number of brick for wall in each unit
Specific weight of
brick (kg/brick)
Total weight of brick for wall in each
unit (kg)
Mortar weight for wall in each
unit (liter)
Mortar cover weight for wall in each unit (liter)
1 122.2 19,799.9 1.6 31,679.8 5,500.0 2,077.8
2 122.2 19,799.9 1.6 31,679.8 5,500.0 2,077.8
2 122.2 19,799.9 1.6 31,679.8 5,500.0 2,077.8
3 122.2 19,799.9 1.6 31,679.8 5,500.0 2,077.8
4 122.2 19,799.9 1.6 31,679.8 5,500.0 2,077.8
5 157.2 25,460.3 1.6 40,736.5 7,072.3 2,671.8
6 172.4 27,923.4 1.6 44,677.4 7,756.5 2,930.2
7 172.9 28,016.9 1.6 44,827.0 7,782.5 2,940.0
8 105.5 17,094.2 1.6 27,350.8 4,748.4 1,793.8
9 105.5 17,094.2 1.6 27,350.8 4,748.4 1,793.8
10 123.9 20,076.7 1.6 32,122.6 5,576.8 2,106.8
11 119.9 19,417.8 1.6 31,068.5 5,393.8 2,037.7
12 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
13 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
14 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
15 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
16 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
17 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
18 137.2 22,224.5 1.6 35,559.2 6,173.5 2,332.2
19 135.5 21,949.0 1.6 35,118.4 6,096.9 2,303.3
20 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
21 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
22 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
23 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
24 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
25 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
26 134.6 21,799.9 1.6 34,879.9 6,055.5 2,287.6
27 122.1 19,772.2 1.6 31,635.6 5,492.3 2,074.9
28 122.2 19,803.5 1.6 31,685.6 5,501.0 2,078.1
29 122.2 19,803.5 1.6 31,685.6 5,501.0 2,078.1
30 122.1 19,772.2 1.6 31,635.6 5,492.3 2,074.9
31 122.1 19,772.2 1.6 31,635.6 5,492.3 2,074.9
32 138.6 22,448.1 1.6 35,916.9 6,235.6 2,355.7
33 139.3 22,574.2 1.6 36,118.7 6,270.6 2,368.9
34 122.2 19,803.5 1.6 31,685.6 5,501.0 2,078.1
35 122.2 19,803.5 1.6 31,685.6 5,501.0 2,078.1
36 122.2 19,803.5 1.6 31,685.6 5,501.0 2,078.1
Appendices 261
No Specific weight of mortar (kg/liter)
Total weight of mortar cover
weight for wall in each unit
(kg)
Total weigth of wall for each
unit (kg)
Total ceiling area of each
unit (m2)
Ceiling volume of each unit
(m3)
Cement weight for ceiling in each unit (kg)
1 1.6 12,124.4 43,804.1 35.0 7.0 2,587.0
2 1.6 12,124.4 43,804.1 35.0 7.0 2,587.0
2 1.6 12,124.4 43,804.1 35.0 7.0 2,587.0
3 1.6 12,124.4 43,804.1 35.0 7.0 2,587.0
4 1.6 12,124.4 43,804.1 35.0 7.0 2,587.0
5 1.6 15,590.5 56,327.1 46.4 9.3 3,433.6
6 1.6 17,098.8 61,776.2 46.4 9.3 3,433.6
7 1.6 17,156.0 61,983.0 46.4 9.3 3,433.6
8 1.6 10,467.6 37,818.4 34.0 6.8 2,516.0
9 1.6 10,467.6 37,818.4 34.0 6.8 2,516.0
10 1.6 12,293.9 44,416.5 41.0 8.2 3,034.0
11 1.6 11,890.4 42,959.0 38.0 7.6 2,812.0
12 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
13 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
14 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
15 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
16 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
17 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
18 1.6 13,609.1 49,168.3 38.0 7.6 2,812.0
19 1.6 13,440.4 48,558.7 37.8 7.6 2,797.2
20 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
21 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
22 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
23 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
24 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
25 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
26 1.6 13,349.1 48,229.0 38.0 7.6 2,812.0
27 1.6 12,107.4 43,743.0 34.0 6.8 2,516.0
28 1.6 12,126.6 43,812.2 34.0 6.8 2,516.0
29 1.6 12,126.6 43,812.2 34.0 6.8 2,516.0
30 1.6 12,107.4 43,743.0 34.0 6.8 2,516.0
31 1.6 12,107.4 43,743.0 34.0 6.8 2,516.0
32 1.6 13,746.0 49,662.9 39.0 7.8 2,886.0
33 1.6 13,823.2 49,941.9 39.0 7.8 2,886.0
34 1.6 12,126.6 43,812.2 34.0 6.8 2,516.0
35 1.6 12,126.6 43,812.2 34.0 6.8 2,516.0
36 1.6 12,126.6 43,812.2 34.0 6.8 2,516.0
Appendices i
No Yellow sand weight for
ceiling in each unit (m3)
Specific weight of yellow sand
(kg/m3)
Total weight of yellow sand for ceiling in
each unit (kg)
Macadam weight for
ceiling in each unit (m3)
Specific weight of macadam
(kg/m3)
Total weight of macadam for ceiling in each
unit (kg)
1 3.6 1,450.0 5,272.0 5.0 1,500.0 7,425.5
2 3.6 1,450.0 5,272.0 5.0 1,500.0 7,425.5
2 3.6 1,450.0 5,272.0 5.0 1,500.0 7,425.5
3 3.6 1,450.0 5,272.0 5.0 1,500.0 7,425.5
4 3.6 1,450.0 5,272.0 5.0 1,500.0 7,425.5
5 4.8 1,450.0 6,997.1 6.6 1,500.0 9,855.4
6 4.8 1,450.0 6,997.1 6.6 1,500.0 9,855.4
7 4.8 1,450.0 6,997.1 6.6 1,500.0 9,855.4
8 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
9 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
10 4.3 1,450.0 6,182.8 5.8 1,500.0 8,708.4
11 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
12 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
13 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
14 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
15 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
16 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
17 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
18 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
19 3.9 1,450.0 5,700.2 5.4 1,500.0 8,028.7
20 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
21 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
22 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
23 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
24 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
25 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
26 4.0 1,450.0 5,730.4 5.4 1,500.0 8,071.2
27 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
28 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
29 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
30 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
31 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
32 4.1 1,450.0 5,881.2 5.5 1,500.0 8,283.6
33 4.1 1,450.0 5,881.2 5.5 1,500.0 8,283.6
34 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
35 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
36 3.5 1,450.0 5,127.2 4.8 1,500.0 7,221.6
ii Appendices
No Steel germ weight for ceiling in each unit
(kg)
Mortar cover
weight for ceiling in each unit
Toral weight of mortar
cover for ceiling in
Total weight of ceiling for each unit
(kg)
Enameled tile
number for floor in each
Specific weight of enameled
tile for floor in
Total weight of enameled
tile for floor in
Mortar cover
weight for floor in
each unit
Total weight of mortar
cover for floor in
1 2,223.5 559.4 895.0 18,402.9 1,538 0.25 385 541.9 867.0
2 2,223.5 559.4 895.0 18,402.9 1,538 0.25 385 541.9 867.0
2 2,223.5 559.4 895.0 18,402.9 1,538 0.25 385 541.9 867.0
3 2,223.5 559.4 895.0 18,402.9 1,538 0.25 385 541.9 867.0
4 2,223.5 559.4 895.0 18,402.9 1,538 0.25 385 541.9 867.0
5 2,951.0 556.8 890.9 24,128.0 2,042 0.25 510 719.2 1,150.7
6 2,951.0 556.8 890.9 24,128.0 2,042 0.25 510 719.2 1,150.7
7 2,951.0 556.8 890.9 24,128.0 2,042 0.25 510 719.2 1,150.7
8 2,162.4 272.0 435.2 17,462.4 1,496 0.25 374 527.0 843.2
9 2,162.4 272.0 435.2 17,462.4 1,496 0.25 374 527.0 843.2
10 2,607.6 246.0 393.6 20,926.4 1,804 0.25 451 635.5 942.4
11 2,416.8 228.0 364.8 19,395.2 1,672 0.25 418 589.0 942.4
12 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
13 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
14 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
15 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
16 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
17 2,416.8 456.0 729.6 19,760.0 1,672 0.25 418 589.0 942.4
18 2,416.8 456.0 729.6 19,760.0 1,672 0.25 418 589.0 942.4
19 2,404.1 304.0 2,177.3 21,107.5 1,663 0.25 416 585.9 937.4
20 2,416.8 304.0 486.4 19,516.8 1,672 0.25 418 589.0 942.4
21 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
22 2,416.8 304.0 486.4 19,516.8 1,672 0.25 418 589.0 942.4
23 2,416.8 304.0 486.4 19,516.8 1,672 0.25 418 589.0 942.4
24 2,416.8 912.0 1,459.2 20,489.6 1,672 0.25 418 589.0 942.4
25 2,416.8 304.0 486.4 19,516.8 1,672 0.25 418 589.0 942.4
26 2,416.8 304.0 486.4 19,516.8 1,672 0.25 418 589.0 942.4
27 2,162.4 408.0 652.8 17,680.0 1,496 0.25 374 527.0 843.2
28 2,162.4 204.0 326.4 17,353.6 1,496 0.25 374 527.0 843.2
29 2,162.4 204.0 326.4 17,353.6 1,496 0.25 374 527.0 843.2
30 2,162.4 204.0 326.4 17,353.6 1,496 0.25 374 527.0 843.2
31 2,162.4 408.0 652.8 17,680.0 1,496 0.25 374 527.0 843.2
32 2,480.4 156.0 249.6 19,780.8 1,716 0.25 429 604.5 967.2
33 2,480.4 156.0 249.6 19,780.8 1,716 0.25 429 604.5 967.2
34 2,162.4 408.0 652.8 17,680.0 1,496 0.25 374 527.0 843.2
35 2,162.4 408.0 652.8 17,680.0 1,496 0.25 374 527.0 843.2
36 2,162.4 204.0 326.4 17,353.6 1,496 0.25 374 527.0 843.2
Appendices iii
No White cement
weight for floor in
each unit
Total weight of floor for each unit
(kg)
Number of pillars
Area of each pillar
(m2)
Height of each pillar
(m)
Metal weight for each pillar
(kg)
Cement weight for each pillar
(kg)
Sand weight for each pillar
(m3)
1 8.390 1,259.96 6 0.09 2.8 80.14 .24 0.13
2 8.390 1,259.96 6 0.09 2.8 80.14 93.24 0.13
2 8.390 1,259.96 6 0.09 2.8 80.14 93.24 0.13
3 8.390 1,259.96 6 0.09 2.8 80.14 93.24 0.13
4 8.390 1,259.96 6 0.09 2.8 80.14 93.24 0.13
5 11.136 1,672.26 6 0.09 2.8 80.14 93.24 0.13
6 11.136 1,672.26 6 0.09 2.8 80.14 93. 9324 0.13
7 11.136 1,672.26 6 0.09 2.8 80.14 93.24 0.13
8 8.160 1,225.36 6 0.09 2.8 80.14 93.24 0.13
9 8.160 1,225.36 6 0.09 2.8 80.14 93.24 0.13
10 9.840 1,477.64 6 0.09 2.8 80.14 93.24 0.13
11 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
12 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
13 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
14 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
15 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
16 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
17 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
18 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
19 9.072 1,362.31 6 0.09 2.8 80.14 93.24 0.13
20 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
21 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
22 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
23 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
24 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
25 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
26 9.120 1,369.52 6 0.09 2.8 80.14 93.24 0.13
27 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
28 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
29 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
30 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
31 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
32 9.360 1,405.56 4.5 0.09 2.8 80.14 93.24 0.13
33 9.360 1,405.56 4.5 0.09 2.8 80.14 93.24 0.13
34 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
35 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
36 8.160 1,225.36 4.5 0.09 2.8 80.14 93.24 0.13
iv Appendices
No Total weight
of sand for each pillar
(kg)
Macadam weight for each pillar
(m3)
Total weight of macadam for
each pillar (kg)
Total weight for pillar of
each department
Total weigth for each unit (ton)
Total weight for each building (ton)
1 190.008 0.20 294.84 3949.34 67.56 5405.06
2 190.008 0.20 294.84 3949.34 67.56 5405.06
2 190.008 0.20 294.84 3949.34 67.56 5405.06
3 190.008 0.20 294.84 3949.34 67.56 5405.06
4 190.008 0.20 294.84 3949.34 67.56 5405.06
5 190.008 0.20 294.84 3949.34 86.24 5174.25
6 190.008 0.20 294.84 3949.34 91.69 5501.19
7 190.008 0.20 300.00 3971.28 91.92 5514.92
8 190.008 0.20 294.84 3949.34 60.59 1454.21
9 190.008 0.20 294.84 3949.34 60.59 1454.21
10 190.008 0.20 294.84 3949.34 70.91 1276.32
11 190.008 0.20 294.84 3949.34 67.81 1220.58
12 190.008 0.20 294.84 3949.34 75.11 9013.18
13 190.008 0.20 294.84 3949.34 75.11 9013.18
14 190.008 0.20 294.84 3949.34 75.11 9013.18
15 190.008 0.20 294.84 3949.34 75.11 9013.18
16 190.008 0.20 294.84 3949.34 75.11 9013.18
17 190.008 0.20 294.84 3949.34 74.38 4462.81
18 190.008 0.20 294.84 3949.34 74.38 4462.81
19 190.008 0.20 294.84 3949.34 75.11 4462.81
20 190.008 0.20 294.84 3949.34 73.20 2927.91
21 190.008 0.20 294.84 3949.34 74.17 7120.37
22 190.008 0.20 294.84 3949.34 73.20 2927.91
23 190.008 0.20 294.84 3949.34 73.20 2927.91
24 190.008 0.20 294.84 3949.34 74.17 8900.46
25 190.008 0.20 294.84 3949.34 73.20 2927.91
26 190.008 0.20 294.84 3949.34 73.20 2927.91
27 190.008 0.20 294.84 2962.01 65.74 3944.60
28 190.008 0.20 294.84 2962.01 65.49 1964.59
29 190.008 0.20 294.84 2962.01 65.49 1964.59
30 190.008 0.20 294.84 2962.01 65.42 1962.51
31 190.008 0.20 294.84 2962.01 65.74 3944.60
32 190.008 0.20 294.84 2962.01 73.94 1478.89
33 190.008 0.20 294.84 2962.01 74.22 1484.47
34 190.008 0.20 294.84 2962.01 65.81 3948.76
35 190.008 0.20 294.84 2962.01 65.81 3948.76
36 190.008 0.20 294.84 2962.01 65.49 1964.59
Appendices v
Appendix D2: The information of landfill sites for construction and demolition waste
in Hanoi
No Landfill site Area (ha)
Capacity (Ton per
day) Company name
Distance (km)
0 Nam Son, Phu Dien, Soc Son district
83.5 4,000 URENCO 45.57
1 Song Phuong commune, Hoai Duc district
1.5 150 Thanh Cong company
22.1
2 Phung Town, Dan Phuong district
4.6 300 Thanh Cong company
20.5
3 Minh Khai commune, Hoai Duc district
1.5 150 Thanh Cong company
16.53
4 Vinh Quynh, Thanh Tri district
4.9 600 Technology and Ecology Joint Stock Company
14.32
5 Ta Thanh Oai, Thank Tri district
1.5 800-1,000 MESC company 18.16
6 Lam Du, Long Bien district
4.5 URENCO 8.43
7 Kieu Ky commune, Gia lam distric
14 150 URENCO 26.29
8 Ngoc Thuy, Long Bien district
URENCO 8.6
9 Xuan Son, Son Tay 83.7 1,200-1,300
Son Tay environment and urban construction company limited
50.31
10 Lien Ha, Dong Anh district URENCO 24.2
11 Van Noi, Dong anh district 7.5 800-1,000 URENCO 15.04
12 Nguyen Khe, Dong Anh district
1,000 Thanh Long environmental service company
21.36