Improving Program Performance at FAA (and DOT). EVM at FAA. FAA goal is to manage entire program using EVMS in accordance with ANSI/EIA 748 Manage/measure all resources Requires changes in behavior by all parties FAA EVM differs from legacy approach Program level, not just contractors - PowerPoint PPT Presentation
Citation preview
PowerPoint PresentationPresented to: NDIA PMSC By: Keith Kratzert Date: February 1, 2007 Improving Program Performance at FAA (and DOT) * February 1, 2007 EVM at FAA FAA goal is to manage entire program using EVMS in accordance with ANSI/EIA 748 Manage/measure all resources FAA EVM differs from legacy approach Program level, not just contractors Will not change existing contracts * February 1, 2007 February 1, 2007 (Government and Industry) Green EVM Flag for all major programs assessed in FY05 (which have significant DME remaining) Assess EVM for new major programs, establish targets and make progress For all major programs, demonstrate EVM policy compliance and 50% of Program Manager use of EVM Expand Executive use of EVM in their decision making process OMB-300 EVM Scores (and see some evidence) February 1, 2007 Formed as a continuation of the program management processes effort Co-Chaired by ATO-A and AIO Membership includes: AIO representatives CFO representatives February 1, 2007 FAA to assess its financial processes against the ANSI standard EVM toolkit study Executive awareness training February 1, 2007 Full EVM implementation by end of FY 07. EVM part of Program Managers toolkit. Full EVM reporting for all major investments. Use of EVM makes a major difference in ability of FAA programs to stay on track and within budget. * February 1, 2007 Baseline management guidance Proposed EVM surveillance, IBR, certification, and executive program performance reporting processes will be developed and implemented Based on NDIA guidelines major contractor “Best Practices” February 1, 2007 Formed a DOT EVM Working Group to develop departmental policy Performed preliminary research for EVM Guidance Completed draft of DOT EVM policy, guidance and implementation plan Developing and documenting EVM practices, procedures and processes for DOT Conducted IV&Vs of operating administrations EVM programs DOT EVM implementation plan in development * February 1, 2007 DOT Next Steps Brief DOT CIO Council on proposed EVM policy, practices and procedures Formalize DOT EVM Council Begin institutionalizing EVM within the department