Implementing Commissioning and the CxP for DOE Super ESPC Projects
Draft Guideline Review
Chuck Dorgan, P.E., Ph.D., CxAP
Roger Johnson
2
Tasks Yet to be Completed
Interviews and meetings with ESCOs Develop the working draft guideline on how
CxP can effectively be integrated with Super ESPC program
Develop sample tools/templates with the Cx Working Group members for use in Super ESPC projects– This should be an ongoing ‘sharing of formats’
that are proven from all projects
3
What is Our Goal?
Take the best of commissioning process practice and incorporate into the DOE Super ESPC process and Projects
Some tasks:– Develop a Draft Guide (our emphasis today)– Develop implementation tools– Develop the final draft guideline– Complete a pilot project– Develop case study and supporting documents
4
Our Goal in the Next 30 Minutes
Discuss the Basic Draft Guideline Review Products Developed for the
Guideline Review the California “School” Guideline
– What is in this guideline that needs to be modified for the DOE Super ESPC Guideline
Timetable for completion Who is available for a one on one review?
5
From Working Session in New Orleans
Key Words: documentation, timely, consistency, standardized, expectations, performance criteria, agreement, longevity, assurance, understanding complexity, training, realization of benefits, turnover, knowledge, satisfaction
This was in reaction to: What is not achieved on previous DOE Super ESPC projects? (Including – What do you want from Commissioning (CxP) to solve some of these needs?)
6
Second topic at New Orleans
Key Words:
guidelines, flow chart, metrics, education, training, definitions, commitment, checklists, deliverables, cost/benefits, roles and responsibilities, format
This was in reaction to: What Cx Tools do we need for the DOE Super ESPC projects?
7
What we provided as current working material and references
Volume 1: Current draft Overview of DOE Super ESPC Commissioning Process Guideline
Form 1: A working draft of a form to be completed to insure everyone understands the role of CxP and can relate to the Agency and Project Facilitator their understanding and experience with the CxP. To be completed at Phase 1, 2, or 3.
8
Volume 1
Overview Document: The document that is required to make sure everyone has the required background information, not only the day we initiate the CxP into Super ESPC projects, but for the long term, to insure we continue to always stay focused on the Why, What, Expectations, and Benefits of CxP
This is the document that is missing in many Cx programs
9
Working Draft DOE Super ESPC CxProcess – Volume 1
Phase 2: At the Initial Proposal Kickoff meeting facilitated by DOE
Discuss the role of CxP
10
Working Draft Super ESPC CxProcess – Volume 1
After the Initial Proposal Kickoff meeting:Phase 3 (or at some point possibly as early as Phase 2)
Designate the CxProcess leader or CxA (ESCO except for pilot) Form CxP Team (Agency/ESCO/PF) Convene a APR Workshop
(APR = Agency’s Project Requirements) Draft APR Document Use APR Document to guide development of the final proposal
and to increase certainty of acceptance
11
Working Draft Super ESPC CxProcess – Volume 1 (Phase 3)
Develop the initial Cx Plan Develop the issues/benefit log and report Develop checklist for Planning Phase and
Initial Project Development Phase, and as many as possible for all other phases (will be easier as we develop a library and experience with CxP in projects)
12
Working Draft Super ESPC CxProcess – Volume 1 (Phase 3)
Implement checklists for completion by ESCO and sampling verification by the CxA against APR document and CxPlan
(recommended?) ESCO and DOE facilitators both provide interim summary report on benefits, recommendations, and checklists at the end of each Phase, or shortly into the next Phase
13
Working Draft Super ESPC CxProcess – Volume 1
Cx Team meetings are scheduled and
held per CxPlanCx Team includes those listed in the
draft guide
Note: Sometimes the CxTeam may only be 2-3 people, such as ESCO designated Commissioning Process leader (CxA) and Agency Project Manager, CxTeam meetings should only involve those with a need related to CxP activities and issues
14
Working Draft Super ESPC CxProcess – Volume 1
Continuously refine the CxPlan and APR Document
based upon, and to match the actual proposal scope Basis of Design for Agency to review-Does it meet
the APR Implement the Cx Plan activities, revise Cx Plan as
required to match the actual project
15
Working Draft Super ESPC CxProcess – Volume 1
Implement checklists for completion by ESCO and
sampling verification by the CxA against APR document and CxPlan
Through the Benefits/Issue log support document, define energy and maintenance benefits, and expected indirect benefits (productivity, satisfaction, and others that will be standard for benchmarking, these will have been developed in the CxPlan or APR Document and will continuously be developed as we go)
16
Working Draft Super ESPC CxProcess – Volume 1
Phase 4 - After Award Implement design and construction checklists
for completion by ESCO, with sampling verification by the CxA against APR document and CxPlan
17
Working Draft Super ESPC CxProcess – Volume 1
Phase 4: Implementing the DO – Performing Modifications or Installations
Maintain the issues/benefits log and report Review training and verify training
– Provide Checklists
Assist in developing the Systems Manual– Provide Checklists
18
Working Draft Super ESPC CxProcess – Volume 1
Phase 4: Implementing the DO – Performing Modifications or Installations
Agency and CxA Participate in and formally verify performance and
other required tests or evaluations, this will include M&V
Agency/PF Reviews ESCO’s Cx Report and other material as
deemed appropriate Reviews the Continuous Commissioning Plan (Big
key to the Agency’s O&M)
19
Working Draft Super ESPC CxProcess – Volume 1
Phase 4: Operations and Occupancy
ESCO’s CxA assists Agency O&M staff in addressing any
operational, training, or performance issues Verifies effectiveness for any first year
additional training that is required Witnesses and verifies the report on any
Seasonal Testing (includes Agency’s participation)
20
Working Draft Super ESPC CxProcess – Volume 1
• Perform the first year scheduled continuous
commissioning requirements and/or assist the Agency in performing the requirements in the first year
21
Working Draft Super ESPC CxProcess – Volume 1
Phase 4: Operations and Occupancy UseCxA• Participate in a mid-year agency project and
warranty review • Develop the final CxP Report on the project• Execute a Lessons Learned workshop at the 8-10
month period to develop information for the Continuous Improvement Report
• Recommended Cx improvements
22
Deliverables by ESCO at End of One Year
Checklists for the DOE Super ESPC CxP Library
Summary of Lessons Learned Documented and Ad Hoc Benefits of the
CxProcess for the specific project
23
Volume 2-A:
Sample Guideline that can serve as an initial format example (to be modified to match the DOE Super ESPC CxP
program requirements)
24
Volume 2-A Example Guide
Example for a rehab of a University building– What is useful?– What needs to be added for a typical ESPC
project example?
25
Volume 2-B:
Format for developing CxP checklists for all phases. This includes examples for planning phase and construction phase
26
Volume 2-B Checklist Format
Planning Checklists Design Checklists Installation Checklists (includes pre-tests,
testing, controls, TAB, functional tests (in addition to test procedures)
Occupancy and Operations Checklists
27
Volume 3:
Sample Guideline that was developed for the California School construction and retro-commissioning(This has been provided for discussion of what may
be included in the ESPC Commissioning Guideline)
28
Volume 3 – California Schools
This will not be the Volume 3 for the ESPC CxP guide
From this example: – Is this sufficient coverage? Too much?– Do we want to cover electronic tools that are used
by CxAuthorities?
Will the guide be delivered in electronic format only, or print with CD?