13
SHRP2 Implementation | July 22, 2014 Implementation Update AASHTO RAC Meeting, July 22, 2014 Debra Elston, Director, Office of Corporate Research, Technology, and Innovation Management, FHWA Jim McDonnell, Program Director, Engineering, AASHTO

Implementation Update AASHTO RAC Meeting, July 22, 2014

  • Upload
    uttara

  • View
    47

  • Download
    5

Embed Size (px)

DESCRIPTION

Implementation Update AASHTO RAC Meeting, July 22, 2014 Debra Elston, Director, Office of Corporate Research, Technology, and Innovation Management, FHWA Jim McDonnell , Program Director, Engineering, AASHTO. What we’ll cover. Implementation milestones SHRP2 budget - PowerPoint PPT Presentation

Citation preview

Page 1: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation UpdateAASHTO RAC Meeting, July 22, 2014

Debra Elston, Director, Office of Corporate Research, Technology, and Innovation Management, FHWAJim McDonnell, Program Director, Engineering, AASHTO

Page 2: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

What we’ll cover

• Implementation milestones• SHRP2 budget• Project management system• Program evaluation• Implementation assistance update• Continual improvement• Next steps

Page 3: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation Milestones

Page 4: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation Status to Date

Of the more than 100 research projects, we are moving forward with 64 products in 42 distinct implementation efforts

SHRP2 Deployment Snapshot100+ Research projects Original projects undertaken by TRB

64 Implementable products As prioritized by FHWA and AASHTO

42 Total anticipated implementation efforts

64 products implemented as 42 products/product bundles

27 Efforts on the street 24 in IAP rounds 1 – 4 + 3 additional deployments = 64% deployment

15 Efforts remaining 36 percent remaining

12 Planned efforts 9 new products in rounds 5 & 6 + 3 non IAP

3 Product disposition TBD R01, R06F, C40

Page 5: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation Budget

$126.0

$5.0

$5.3$7.4

$12.5$11.8

SHRP2 Implementation Budget (in $M)

Product Development & Implementation * (75%)

Pre implementation (3%)

Communications & Out-reach (3%)

Program Administration (4%)

Contingency (8%)

FHWA/AASHTO Implemen-tation Staff (7%)

Focus Area BreakdownRenewal - $40.5Capacity - $24.6Reliability - $27.7Safety - $33.4

Page 6: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Project Management and Tracking

• 2-pronged, quarterly tracking system in place– MS Project– Narrative, qualitative report

• Quarterly reporting structure– Universal template, Highlights, Challenges– Summary report per focus area per quarter

• Key highlights from first quarterly report – Example– Approaching milestone of 50000 trained in L12/32 TIM– Champions and opinion leaders identified for C06– Showcases, demos and workshops held for R04, R05, R09, R10

& R26

Page 7: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

SHRP2 Program Evaluation

Products

OutputsCompleted R&T

Implementation Activities (Workshops, Training,

Grants,Lead Adopters, etc.)

Knowledge DisseminationSpecification AdoptedChange in Behavior

Innovation Tested/Deployed

Saved Time, Money or Lives

Outcomes

Impacts/BenefitsSelect Product

Evaluations

Implementation Assistance

Results

Tracking System

SHRP2 Implementation | June 2014 7

Page 8: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation Assistance ProgramSo Far…• SHRP2 IAP projects underway in 48 states; more coming in round 4• Applications Received (Rounds 1-4): 414

– from 49 State DOTs + DC DOT– from 38 MPOs– from 10 tribes, 6 “others,” FHWA/FLH

• Awards (Rounds 1-3): 65 recipients received 146 awards (representing work on 180 projects*)

– 44 State DOTs + DC DOT– 16 MPOs– 1 tribe, 3 “others,” FHWA/FLH

• Beyond the IAP – successful implementation efforts ongoing in Traffic Incident Management (L12) – 41 states involved

• Thus, all 50 states + DC are engaged in SHRP2 implementation

Page 9: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation Assistance

SHRP2 Implementation | June 2014 9

Page 10: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Implementation AssistanceRound 4

Economic Analysis Tools bundle – C03/11Advanced Travel Analysis Tools bundle – C10/04/05/16

Pavements: New Composite Pavement Systems – R21 Rapid Technologies to Enhance QC on Asphalt Pavements – R06C Tools to Improve PCC Pavement Smoothness During Construction – R06EStructures: Nondestructive Testing for Concrete Bridge Decks – R06A Nondestructive Testing for Tunnel Linings – R06G Service Life Design for Bridges – R19AProject Delivery: Managing Risk in Rapid Renewal Projects – R09 Innovative Strategies for Managing Complex Projects – R10

Reliability Data and Analysis Tools bundle – L02/05/07/08 (C11)

Concept to Countermeasure – Research to Deployment Using the SHRP2 Safety Databases

Page 11: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

Planning for more products

Product IPW IAP roundPlanWorks (C01) Fall 2014 Round 5Capacity Process Bundle (C02/08/09/12/15) Spring 2014 Round 5Service Limit State Design for Bridges (R19B) Fall 2014 Round 53D Utility Location Data Repository (R01A) Winter 2014 Rounds 5 & 6Utility Locating Technologies/Innovation in Locating Deep Utilities (R01B/C)

Winter 2014 Round 6

Techniques to Fingerprint Construction Materials (R06B)

Fall 2014 Round 6

Advanced Methods to Identifying Pavement Delamination (R06D)

Fall 2014 Round 6

WISE: Workzone Impact Estimation Software (R11)

Summer 2014 Round 6

Nondestructive Testing for Concrete Bridge Decks (R06A)

Winter 2013 Round 6

Round 5 – January 2015Round 6 – June 2015

Page 12: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

We are listening…

Challenge Solution Result

Engage transportation agencies in every state

State visits; increased targeted outreach and communication; better time intervals throughout IAP; examination of widest potential audience

As of Round 4, all but 2 AASHTO member departments have applied through the IAP. MPOs, local DOTs, and others are also applying.

Connect customers and facilitate peer-to-peer knowledge transfer

Updated GoSHRP2 site features In the Field section; commitment to contributing to peer exchange; updated contact info on site

More availability of user data and stronger linkage of peer connections

Streamline the post-selection IAP activities

Use lessons learned to standardize process

Expectations are managed, funds are allocated more timely, and projects are initiated quicker

Page 13: Implementation Update AASHTO RAC Meeting, July  22, 2014

SHRP2 Implementation | July 22, 2014

The future

• Continual process improvement• Coordination between AASHTO and FHWA• Keeping pace with product developments • Key successes• Safety implementation• Reauthorization• Questions, feedback from the Implementation

Advisory Committee• www.fhwa.dot.gov/goshrp2