Upload
doanmien
View
236
Download
0
Embed Size (px)
Citation preview
Implementation of
LADOTD Mass
Concrete & Maturity
Testing Specifications Presented by
Mark A. Cheek, PE, FACI
Vice-President
LTC 2018
Definition of mass concrete
“any volume of concrete with dimensions large enough to
require that measures be taken to cope with generation of
heat from hydration of the cement and attendant volume
change to minimize cracking”
– American Concrete Institute (ACI 207.1R-05)
What is mass concrete?
Not all mass concrete placements are enormous pours!
For most state DOT’s, it is defined as any concrete placement
where the smallest dimension exceeds 3-4 ft.
Even thin placements like slabs and columns can qualify
ACI 301-10 commentary provides the following recommended limits:
Thickness ≥ 4 ft
Cementitious content ≥ 660 pcy
Industry Trends
Larger concrete elements in structural applications
Flowable / SCC
High-strength concrete
Rapid construction
Service life requirements
All of these are leading to more concrete placements
being mass concrete. If not properly considered, can
contribute to an increased risk of thermally induced
damage!
Why do we care?
High internal concrete temperatures can
cause delayed ettringite formation (DEF)
High temperature differentials within a
concrete placement can cause thermal
cracking
Early Ages Late Ages
6
Hot CoolCool Cool
Typical Specification Limits
Maximum Temperature:
Typical maximum temperatures range from 154°F to
160°F.
If SCM’s are used, limits sometimes increase to
170°F or higher.
Maximum Temperature Differential:
Typical limits range from 35°F to 38°F.
More advanced modeling techniques allow for this to
exceed typical limits (Performance based)
7
Thermal Control Plans Placement plans developed to decrease the risk of
thermal issues. Typically include:
Thermal modeling
Mix design
Concrete & ambient temperature
Element dimensions
Thermal control measures
Detailed placement plan
Mix design
Thermal control measures
Embedded thermocouples to monitor
placement8
Concrete Mix Design
Limit cementitious materials content
Use supplementary cementitious materials
Use fly ash and slag to lower temperature rise
Fly ash up to 40-50% replacement typical
Slag up to 70% replacement typical
Silica fume can increase the temperature rise
9
Thermal Control Measures
Passive: Surface insulation
Blankets, form liners, foam insulation
Precool the concrete Ice, cold water, liquid nitrogen
Active: Cooling Tubes
Passive measures typically require
longer periods until the placement
can be accessed than active control
measures
10
LOUISIANA Standard Specifications
for
Roads and Bridger
2016
901.12 MASS CONCRETE
901.12.1 Description
Mass concrete is defined as a structural concrete
placement having a least dimension of 48 inches or
greater, or if designated on the plans or in the project
specifications as being mass concrete. Drilled shafts are
exempt from mass concrete requirements.
901.12.2 General
Submit proposals for the mass concrete mix design,
analysis, temperature monitoring, and control, including
insulation and methods, to the Department for review and
acceptance a minimum of 30 days prior to the placement of
any mass concrete.
901.12.3 Materials
The structural class designation for mass concrete is Class
MASS (A1, A2, or A3) as shown in Table 901-3.
901.12.3.1 Cement/Cementitious Combination
Use Type II portland cement. Replace portland
cement with fly ash at 20 percent to 50 percent by
weight or replace with slag cement at 50 percent to
70 percent by weight or a ternary mix meeting
specification requirements. Certify that the
cementitious combination generates a heat of
hydration of not more than 70 calories/gram (290
kJ/kg) at 7 days as determined by ASTM C186.
901.12.4 Construction
Produce a structure free from thermal cracks. Place mass
concrete continuously to eliminate cold joints.
Control differential temperatures by appropriate use of insulated
forms, curing blankets, or other acceptable methods.
If during the first 48 hours after placement, the temperature
differential nears 35 ºF (20 ºC), take corrective measures
immediately to remain within the limits. Furthermore, revise the
plan to maintain the limits on differential temperature on any
remaining placements of mass concrete. Obtain the engineer's
acceptance of the revised plan prior to implementation.
Strength gain and cooling of the mass concrete placements can
take a long time. Take all such time and strength considerations
into account when planning construction activities.
901.12.4.1 Analysis and Monitoring
Submit an analysis to the engineer of the projected thermal
developments within the mass concrete elements for the
anticipated concrete and ambient temperatures, along with
the proposed mix design and construction methods.
Include a copy of model results, with site and element
specific data, and any electronic files. Describe the
measures and procedures intended to maintain, monitor,
and control the temperature differential between the interior
and exterior of the mass concrete elements. A maximum
temperature during curing of 160 º F (70 º C) and a
maximum differential temperature of 35 °F (20 °C) is
allowed. An abbreviated submittal may be allowed for
previously approved mass concrete mix designs.
901.12.4.2 Monitoring Devices
Provide temperature-monitoring devices to record
temperature development between the interior and the
exterior of the element at points acceptable to the engineer.
Monitor a minimum of two independent sets of interior and
exterior points for each element to provide redundancy.
Locate the monitoring points at the geometric center of the
element for the interior point and two inches from the
surface along the shortest line from the geometric center to
the nearest surface of the element for the exterior point.
Monitoring devices shall be automatic sensing and recording
instruments that record information at a maximum interval of
one hour. Calibrate monitoring devices to the manufacture’s
recommendations. These devices shall operate within the
temperature range of 0 to 180 ºF (-18 to 82 ºC) with an
accuracy of ± 2 ºF (±1 C). Take readings and record the
temperature data at intervals no greater than 6 hours to
ensure that the automatic devices are working properly and
that the temperatures are within allowable limits. The intervals
of one and six hours shall begin immediately after casting is
complete and shall continue until the maximum temperature
differential is reached and begins to drop. Transmit these
readings to the engineer daily.
Prior to the placement of mass concrete, perform a test of the
automatic and manual thermal sensing and recording
equipment to ensure they are operational.
Macarthur Interchange
Completion - Phase 1B
(H.009933)
Mass Elements
- 31 Footing (range in height from 5’
to 8’)
- 37 Pier Placements (range in width
from 5’ to 25’)
- 10 out of 39 Caps (range in depth
from 4’ to 7.5’)
Mix Design Cement Type I/II 162 lbs/yd3
Slag Cement Grade 100 379 lbs/yd3
Water 238 lbs/yd3
Coarse Aggregate 1879 lbs/yd3
Fine Aggregate 1164 lbs/yd3
Air Content 5%
Chemical Admixtures
ASTM C 494 Type A, HRWR
W/CM 0.44
Thermal Model
for
5’ Thick Footing
Installation
Geometric center of the element for the
interior point
Two inches from the surface along the
shortest line from the geometric center to
the nearest surface of the element for the
exterior point.
At each location use a minimum two
logger.
Logger Types
Cable Lengths 4ft to 200ft
MAT-02-1H180D
MAT-02-1M2D
TPL-02-1H28D
TPL-02-15M28D
Insulation
Insulation Recommendations
Install blankets preferable before placement
Blankets must completely cover all portions of
the formwork and any portion that extends
above or beyond the limits of the placement
Blankets should be held tightly against the
formwork to prevent air movement between the
blankets and forms
Protruding steel should be insulated
Insulation for the placement should extend a
minimum of 3 ft. onto any adjoining existing
concrete
Monitoring
Field Monitoring
Remote Monitoring
Watch real time in your office
Email and Text notifications
Maturity Meters for Any-Time
Strength Measurements
Brief History of the Maturity Method
The “maturity concept” was proposed in the late 1940s and early 1950s
as a technique to account for the combined effects of time and
temperature on the strength development of a concrete mixture (Nurse
1949; McIntosh 1949; Saul 1951).
Carino and Tank
Specifications
ACI
301 Standard Specifications for Structural
Concrete (paragraph 2.3.4)
318 Building Code Requirements for
Structural Concrete (paragraph 6.2)
Specifications
ACI
228.1R In-place Methods of Estimating Concrete Strength (paragraph 2.7)
306 Cold Weather Concreting (paragraph 6.4)
Specifications
FHWA
SA-97-105 Guide to Non-destructive Testing
of Concrete
ASTM
C 1074 Practice for Estimating Concrete
Strength by the Maturity Method
Used by DOT’sState
Allows Mat
Alabama X
Alaska X
Arizona X
Arkansas X
California X
Colorado X
Conneticut X
Delaware X
Florida X
Georgia X
Hawaii X
Idaho X
Illinois X
Indiana X
Iowa X
Kansas X
Kentucky X
Louisiana
Maine X
Maryland X
Massachusetts X
Michigan X
Minnesota X
Mississippi X
Missouri X
Montana X
Nebraska X
Nevada X
New Hampshire X
New Jersey X
New Mexico X
New York X
North Carolina X
North Dakota X
Ohio X
Oklahoma X
Oregon X
Pennsylvania X
Rhode Island X
South Carolina X
South Dakota X
Tennessee X
Texas X
Utah X
Vermont
Virginia X
Washington X
West Virginia X
Wisconsin X
Wyoming X
District of Columbia X
Benefits of Using the Maturity
Method (to the project)
Accelerate construction schedules
Reduce man-hours
Reduce test specimen cost
=
Remove shoring and re-shoring sooner
Allows earlier form removal and with confidence
that the operation is safe; rented forms can be returned sooner
Post-tensioning tendons can be stressed earlier
Open roadways to traffic in less time
Engineering Benefits of Using the
Maturity Method
Provides a better representation of in-place
concrete strength gain (compressive or flexural)
than laboratory or field cured specimens
Enables any-time in-place strength
measurements
Enables in-place strength measurements at
“lowest strength (youngest concrete)” locations
Enables in-place strength measurements at
“critical stress” locations
Maturity Rule
“Concrete of the same mix at the same
maturity (reckoned in temperature-time)
has approximately the same strength
whatever combination of temperature and
time go to make up that maturity.”
A.G.A. Saul, 1951
Maturity Functions
Temperature-time Factor (Nurse-Saul)
M = Σ (Ta – To ) Δt
Equivalent age (Arrhenius)
te = Σe –Q[ 1/Ta – 1/Ts ] Δt
Nurse – Saul Function
(Temperature – time factor)
M = Σ (Ta – To ) Δt
M = the temperature – time factor (TTF) at age t, degree – hours
Ta = average concrete temperature during time interval, Δt
Δt = a time interval, hours
To = 0˚ C or 32˚F
Datum Temperature
To = 0˚C
Traditionally, the datum temperature has
been the temperature below which strength
gain ceases, which has been assumed to be
about 0°C (32°F)
In-Place Concrete Temperature (Ta)
Ambient conditions
Types & amounts of cementitious
materials
Admixtures
Size and shape of the structure
Formwork & Insulation
Implementing the Concrete
Maturity Method
Strength-Maturity Relationship
y = 734.43Ln(x) - 3685.9
R2 = 0.9931
1000
1500
2000
2500
3000
3500
4000
500 5500 10500 15500 20500 25500
Maturity Index (TTF) (C-hrs)
Co
mp
ressiv
e S
tren
gth
(p
si)
1. Develop a mixture specific calibration curve
2. Embed maturity loggers into plastic concrete
3. Take maturity (TTF) measurements
4. Use the calibration curve to estimate strength from maturity (TTF) measurements
Laboratory Test Data
Developing a mixture specific curve
Developing a mixture specific curve
Strength - Maturity Relationship
1000
1500
2000
2500
3000
3500
4000
500 5500 10500 15500 20500 25500Maturity Index (TTF) (C - hrs.)
Co
mp
ressiv
e S
tren
gth
(p
si)
1 Day
3 Day
28 Day
7 Day
14 Day
Strength-Maturity Relationship
1000
1500
2000
2500
3000
3500
4000
500 5500 10500 15500 20500 25500
Maturity Index (TTF) (C-hrs)
Co
mp
res
siv
e S
tre
ng
th (
ps
i)
Y = 734.43Ln(x) – 3685.9
R2 = 0.9931
Maturity equation – defines the strength-maturity
relationship (logarithmic best fit curve)
Y = 734.43Ln(x) – 3685.9
The R2 value indicates the reliability of the
strength-maturity relationship
R2 = 0.9931
Using the Strength-Maturity
Relationship CurveStrength-Maturity Relationship
3000
3500
4000
4500
5000
5500
6000
500 5500 10500 15500 20500 25500
Maturity Index (TTF) (C-hrs)
Co
mp
res
siv
e S
tre
ng
th (
ps
i)
4029 °C-H
4450 psi
Utilizing Maturity for form
Removal
On average forms were removed 4 days
earlier!
Warm weather – removed in 5 days
Cold weather – removed in 7 days
Questions