IEM Daily Field Report
Prepared By: Joseph Spinelli IEM Representative
Page 1 of 4
Signed In Signed Out Southwest Brooklyn Marine Transfer Station
1824 Shore Parkway Brooklyn, New York 11214
Date: April 20, 2016 Inspector: Joseph Spinelli Location /
Description:
Project #: URLI1401 Site Time: 0700 to 1730 Assigned by: SPD
Day Weather General Site Conditions
Monday Thursday Clear Snow Warm Clear
Tuesday Friday Overcast Windy Hot Muddy
Wednesday Rain Cold Temperature Range: 55 ºF to 63 ºF
General Contractor: Prismatic Development Corporation (PDC) Construction Manager: URS / LiRo
G/C Name: Richard Tonnensen CM Name: Michael Balarezo / Michael Pokorny
S/C&S/C Supervisor: NA CM Phone #: 917-983-5608 / 917-983-5616
Equipment and Machinery in Use(1):
Crane(s)
Elevating Work Platforms
Forklift with extendable arm (Lull)
Concrete Pour Truck (1) List of equipment and machinery is based on field observations and is not inclusive of every equipment and machinery that may have been present at the site.
Personnel on Site(1):
Personnel Organization Personnel Organization
Personnel PDC Mike Balarezo URS / LiRo
Robert Amrhein Certified Safety Mike Pokorny URS / LiRo
Nelson Mendez EnTech Nabil Saadi URS / LiRo
Pavlos Kominakos Total Safety Consultant Roberto Vazquez URS / LiRo
Personnel AEL, Stonebridge, Giaquinto, Solar Inc. Victor Bogatyrev URS / LiRo
Andrew Port Louis Berger Tom Karas URS / LiRo
Erdal Gurten Greeley and Hanson (1) List of personnel on site is based on field observations and is not inclusive of every personnel that may have been present at the site.
Observations:
Time Stamp Details
Time On Site: 7:00 am
7:00 am Four air monitoring stations were set up at perimeter locations specified by the CM, forming a quadrangle around the anticipated work area. According to EnTech, air monitoring is occurring at the four air monitoring stations beginning at 6:40 am. The air monitoring station locations are depicted on the Sketch.
7:00 am to 3:15 pm GC installing rebar and wooden formwork for the construction of the elevated ramp in the eastern section of the site.
7:00 am to 12:00 pm GC installing scaffolding in the eastern section of the concrete slab.
7:00 am to 1:00 pm Solar Inc. installing conduit on the tipping ramp in the eastern section of the site.
Day / Date: Wednesday / April 20, 2016 Client: URS / LiRo H2M Project No.: URLI1401
Prepared By: Joseph Spinelli IEM Representative
Page 2 of 4
7:00 am to 3:00 pm Stonebridge utilizing two cranes and elevating work platforms at the site to install structural steel in the northwestern, eastern, and central sections of the concrete foundation slab. Stonebridge welding structural steel in the western section of the site.
7:00 am to 2:30 pm Giaquinto building interior cinder block walls for the main building in the northern section of the concrete foundation slab. Cement mixing and concrete block cutting in the northeastern section of the concrete foundation slab. Giaquinto utilizing a Lull forklift to move materials and garbage around the site.
7:35 am to 8:20 am Water tank truck filling up with water from a fire hydrant located on Bay 41st Street.
8:20 am, 11:35 am, 1:00 pm, 2:10 pm
The GC implemented dust suppression by wetting down the ground surface at the site with water from the water tank truck.
9:30 am to 10:00 am & 12:00 pm to 12:30 pm
Site work stops for a work break.
3:00 pm Site work stops for the day (with the exception of the concrete pump truck work).
3:00 pm to 3:45 pm GC utilizing a concrete pump truck to pour shear walls on the western section of the concrete foundation slab.
3:45 pm to 5:30 pm Concrete pump truck utilizing concrete wash out station. Concrete pump truck having technical difficulties. Concrete pump truck lowering the boom on the truck.
5:30 pm Concrete pump truck off-site. Site work stops for the day. EnTech removes air monitoring stations.
Time Off-Site: 5:30 pm
General Observations:
According to EnTech, particulate matter and total organic vapors were not detected at concentrations greater than the action levels.
Issues discussed this date with Construction Manager: None.
Persons Contacted: N/A
Status: N/A
Notes: N/A
IEM Daily Field Report
SKETCH
Prepared By: Joseph Spinelli IEM Representative
Page 3 of 4
`
Approximate Location of Air Monitoring Stations B3.
Approximate Location of Air Monitoring Stations B2.
Approximate Location of Air Monitoring Stations B1.
Approximate Location of Air Monitoring Stations B4.
Approximate location of interior cinder block wall installation
Approximate location of scaffolding construction
Approximate location of rebar and wooden formwork for ramp construction
Approximate location of structural steel installation
Approximate location of concrete pour for shear walls
Approximate location of concrete washout station
Approximate location of concrete pour for the ramp