    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Mobilzation of site by EPC

    Contractor

    Jan-11 Jan-11

    2 Handing over of site to EPCContractor for Soil

    Investigation

    Jan-11 Jan-11 Sep-11

    3 Temporary fencing for land

    already acquired

    Mar-11 Mar-11

    4 Issue of Notice to Proceed to

    EPC Contractor

    Mar-11 Feb-11

    5 Consent to Establish for power

    plant

    Mar-11 Jun-11

    6 Kick of Meeting with EPC

    contractor

    Mar-11 Apr-11

    PROJECT TEAM: Dr. Ashok Harane, Sanjay Joshi

    Q4 (2011-12)

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)

    DATE :03-08-2011

    TC : Target Completion

    AC/EC : Actual/Expected Co

    COD (as per Investors PIM) : Unit 1 - September 2013; Unit 2 - March 2Expected COD (as per EPC Contract) : Unit 1 - November 2013 ; Unit 2 - May 201

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    2/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)

    7 Appointment of third party

    inspection agency

    Mar-11 Apr-11

    8 Acquisition of land for Phase I Sep-11

    9 Consent to Establish for port Apr-11 Jun-11

    10 Finalisation of Insurance

    package

    Mar-11 Aug-11

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    3/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)

    11 Provision for construction

    Power at one single location

    May-11 Aug-11

    12 Completion of land acquisition

    of 1181 acres

    Jun-11 Sep-11

    13 Completion of site grading Jun-11 Sep-11

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    4/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)

    14 Completion of approach road

    to site

    Jun-11 Dec-11

    15 MPH layout drawing finalized May-11 May-11

    16 Submit detailed geo-technical

    investigation report of MPH

    area

    Jun-11 Jun-11

    17 Test piling completion Sep-11

    18 Construction of site office

    completion

    Dec-11

    19 #1 A row of man-power housefoundation pilling completion Dec-11

    20 #1 BC row of main-power

    house foundation pilling

    com letion

    Feb-12

    21 Submission of Piling drawing

    of chimney

    Oct-11

    22 #2 A row of man-power house

    foundation pilling completion

    Mar-12

    23 #2 BC row of man-powerhouse foundation pilling

    completion

    Mar-12

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    5/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)

    24 Completion of boundary wall Dec-11

    25 #1 A row of main-power house

    excavation completion

    Feb-12

    26 #2 Man-power house

    foundation piling all

    Mar-12

    27

    #2 A row of main-power house

    excavation completion

    Mar-12

    Brief Status :

    Critical Issues :

    1 Availability of 30 acres of land for completion of soil investigation for phase I facilities

    2 Approval from RBI for opening of project office and bank account to Onshore works and services contractor (Tiejun)Support Required :

    1

    2

    Note : Report to be sent second & fourth Friday of every month

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    6/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    REMARK

    Some of the critical area of

    GIS, Fuel oil handling and sea

    water pump house is yet to be

    handed over to the contractor

    Work completed March 31,

    2011

    NTP issued on Feb 15, 2011.

    Mobilization advances paid

    for offshore equipment and

    material supply contracts and

    offshore services contract

    Consent to Establish received

    on June 14 2011 for both Port

    and Power project

    Kick off meeting held from

    April 25 to 29 2011 at JinanChina

    pletion

    014

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    7/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    REMARK

    Appointed Lloyds Register

    Asia as Independent

    inspection agency

    Total land acquired so far 729

    acres. About 30 acres of land

    is yet to be acquired for phase

    I (excluding ash pond)

    It is expected that the balance

    land for GIS and Fuel oilhandling system may be

    available by end Sept 2011

    Consent to Establish received

    on June 14 2011 for both Port

    and Power project

    The proposal is finalised in

    consultation with EPCcontractor and bids sent to 10

    insurance companies (4 PSUs

    and 6 private companies). Pre-

    bid meeting with insurance

    companies is held on June 8,

    2011. Replies to the queries

    of insurance companies are

    being compiled through

    SEPCO III. Insurance

    package is likely to be

    finalized by Aug 2011

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    8/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    REMARK

    Location for construction

    power finalised in

    consultation with Contractor

    and TNEB officials.

    Drawings have been furnished

    to Chief electrical

    inspectorrate and awaiting the

    approval. As per the rules of

    TNEB the Contractor needs

    to bring the equipments to the

    site before actual

    commencement of power

    supply. Contractor has

    already placed orders on

    Transformer and other

    equipments.

    Power supply may be

    available by mid August 2011

    It is expected that the entire

    land acquisition process may

    be completed by end

    September 2011

    Orders placed for boundary

    wall and site grading. Work

    commenced

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    9/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    REMARK

    Permission received from

    State PWD for construction of

    bridge over Buckingham

    canal

    Overall plot plan finalized.

    Floor plan finalization in

    progress

    Contractor furnished the soil

    investigation report for the

    bore holes completed

    Test piling commenced on

    July 31, 2011 and expected to

    be completed by September

    30, 2011

    Drawing finalized for site

    office

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    10/85

    ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project

    REMARK

    Works have alreadycommenced for boundary wall

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    11/85

    ACTIVITY PLAN: Phase II - 2400 MW Cuddalore Thermal Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Finalization of Technical

    Specifications

    Sep-11

    2 Financial Closure Dec-113 Acquisition of balance land for

    phase II

    Mar-12

    4 Issue of Notice to Proceed to

    EPC Contractor

    Mar-12

    5 Consent to Establish for Phase

    II

    Mar-12

    Brief Status :

    Critical Issues :

    1 Finalization of coal specifications and Unit configuration

    2 Acquisition of balance land for Cooling Towers, GIS

    Support Required :

    1

    2

    Note : Report to be sent second & fourth Friday of every month

    Expected COD : Unit 1 - March 2015; Unit 2 - July 2015; Unit 3 - Novemb

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    PROJECT TEAM: Dr. Ashok Harane, Sanjay Joshi

    DATE :03-08-2011

    TC : Target Completion

    AC/EC : Actual/Expected Co

    COD (as per Investors PIM) : Unit 1 - September 2014; Unit 2 - April 2015; Unit 3 - Sep

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    12/85

    ACTIVITY PLAN: Phase II - 2400 MW Cuddalore Thermal Power Project

    REMARK

    Land for BTG area is already

    available

    Consent to Establish would be

    available after entire land is

    available

    r 2015

    mpletion

    tember 2015

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    13/85

    ACTIVITY PLAN : 726 MW ONGC Tripura Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    May'11

    Unit 1 + Common TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 % Progress

    Overall Project Progress 72.32% 47.12% 81.27% 52.68% 91.16% 56.75% 93.00% 62.00% 97.00% 100.00%Engineering Progress 99.96% 91.62% 99.96% 95.59% 100.00% 97.34% 100.00% 98.00% 100.00% 100.00%

    Procurement, Manufacturing

    & Su ly Pro ress

    97.02% 79.34% 99.61% 85.25% 99.91% 91.78% 100.00% 93.00% 100.00% 100.00%

    Civil Construction Progress 98.76% 46.88% 99.65% 56.31% 100.00% 62.41% 100.00% 64.00% 100.00% 100.00%

    Erection Progress 23.15% 0.27% 46.06% 3.77% 75.00% 5.00% 96.00% 15.00% 99.00% 100.00%

    2 ODC Equipments Supply

    Schedule (at Site)

    GT Apr-11 Jun-11

    GTG Apr-11 Aug-11ST-HP Apr-11 Apr-11

    STG Apr-11 Aug-11

    HRSG Modules May-11 Aug-11

    HRSG Drums Apr-11 Jun-11

    HRSG Headers Apr-11 Jun-11

    Transformers & Reactors May-11 Aug-11

    3 Civil Works

    Piling

    GTG Foundation

    STG FoundationHRSG & Stack Foundation

    Power House Foundation

    Power House Superstructure Mar-11 Jul-11

    PROJECT Manager: Mohd. Zaheen Khan

    TIME FRAME

    AC/EC : Actual/Expected C

    TC : Target Completion

    DATE : 03-08-2011

    COD as per IM : Unit #1 D

    Expected Target COD: Unit # 1:

    Q4 (2011-12)

    January '11 March'11

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    14/85

    ACTIVITY PLAN : 726 MW ONGC Tripura Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    May'11

    Unit 1 + Common TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2011-12)

    January '11 March'11

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

    Raw Water Reservoir Jul-11 Aug-11 Dec-11

    Transformer Yard &

    Transformer Foundations

    May-11 Oct-11

    Switchyard May-11 Oct-11

    4 Erection Completion

    GT Oct-11 Nov-11

    GTG Oct-11 Nov-11

    ST-HP Oct-11 Nov-11

    STG Oct-11 Nov-11

    HRSG Modules Sep-11 Nov-11

    HRSG Drums Sep-11 Nov-11

    HRSG Headers Sep-11 Nov-11

    Transformers & Reactors Sep-11 Nov-11

    5 Commissioning Date

    Unit-I Feb-12

    Unit-II Jun-12

    Brief Status :

    Project Cost - Rs. 34,293 Mn ;Expenditure Incurred Rs. 16,814 Mn

    ODC Movement - All 90 ODCs dispatched from BHEL Manufacturing Units to Kolkata, All equipments (ODCs) are at Ashuganj/in transit to Pallatana/ at Site

    Critical Issues :

    1 Repair of Bypasses in the Bangladesh & Indian Section

    2 Progress of civil works and inadequate supervision by BHEL

    3 Movement of all equipment ODCs

    Support Required :

    1 BHEL to closely monitor progress of civil works and structure fabrication

    2 BHEL to deploy additonal and more experienced manpower at site

    Note : Report to be sent second & fourth Friday of every month

    - GT#1 successfully reached site

    - GT#2 enroute to site, currently in Bangladesh

    - 26 ODC consignment, comprising 15 modules & 11 equipments have reached project site through Bangladesh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    15/85

    ACTIVITY PLAN : 726 MW ONGC Tripura Power Project

    REMARKS

    Bypasses in

    Bangladesh & India section

    under repair

    April 2011 to oct'11

    Complete

    Complete

    Complete

    Complete

    Complete

    ompletion

    c'11, Unit#2 Mar'12Feb'12, Unit # 2: June'1

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    16/85

    ACTIVITY PLAN : 726 MW ONGC Tripura Power Project

    REMARKS

    1st compartment-Aug 11

    2nd compartment-Dec 11

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    17/85

    ACTIVITY PLAN : 363 MW ONGC Tripura Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Land

    2 Finalization of Gas Sales &

    Purchase Agreement

    Dec-11

    3 Financial Closure Jan-12

    4 Issue of Notice to Proceed to

    EPC Contractor

    Mar-12

    5 Additional Clearances Dec-11

    Brief Status :

    Critical Issues :

    1 Execution of Gas Supply & Purchase Agreement (GSPA)

    2 Financial Closure & issue of NTP to EPC Contractor by March'12

    Support Required :

    1

    2

    Note : Report to be sent second & fourth Friday of every month

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    PROJECT Manager: Mohd. Zaheen Khan

    DATE :03-08-2011

    TC : Target Completion

    AC/EC : Actual/Expected Co

    COD (as

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    18/85

    ACTIVITY PLAN : 363 MW ONGC Tripura Power Project

    REMARK

    Land for Phase II

    under possession

    Expected COD - Dec'13

    mpletion

    er Investors PIM) : June'13

    ACTIVITY PLAN 400 KV D/C P l t B i T i i Li A i t d ith 726 6 (2X363 3) MW P ll t CCGT P P j t f

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    19/85

    ACTIVITY PLAN : 400 KV D/C Palatana- Bongaigaon Transmission Line Associated with 726.6 (2X363.3) MW Pallatana CCGT Power Project of

    OTPC

    TC : Target Completion

    AC/EC : Actual/Expected Completion

    Sr No MAJOR ACTIVITY/MILESTONE REMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    A

    TC

    AC/EC

    1 Survey -Total Qty 246 Km 246* 246*

    2 Foundation -Total Qty 675 Nos 475* 411* 264** 151 113** 22 91** 91

    3 Erection -Total Qty 675 Nos 417* 230* 431** 126 319** 31 288** 288

    4 Stringing -Total Qty 246Kms 117* 25* 207** 22 196** 11 188** 188

    B

    TC

    AC/EC1 Survey -Total Qty 415 Km 415* 415*

    2

    Foundation -Total Qty 1125Nos 876* 497* 623** 171 457** 14 443** 150 293** 150

    Remaining 143 may spill

    over upto May-June

    2012

    3

    Erection -Total Qty 1125Nos 760* 232* 869** 121 772** 17 755** 200 555** 200

    Remaining 355 may spill

    over upto May-June

    2012

    4

    Stringing -Total Qty 415Kms 213* 14* 372** 13 384** 2 386** 100 286** 100

    Remaining 186 may spill

    over upto May-June

    2012

    C

    1 Survey -Total Qty 661 Km 661* 661*

    2 Foundation -Total Qty 1800 Nos 1351* 908* 887** 322 570** 36 534** 241 293** 150

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-2012) Q3 (2011-12) Q4 (2011-12)

    Nov. 2011

    Nov. 2011

    Critical Section for evaccuation -Palatana(Tripura) to Silcher(Assam) -246 Kms Long

    Nov. 2011

    Silcher -Bongaigaon Section-415 Kms long

    June. 2012

    Total - Palatana-Bongaigaon Section-661Kms long

    PROJECT MANAGER: V.L.Dua

    DATE : 03.08.2011

    COD as per IM : Nov 2011

    TIME FRAME

    Expected Target COD: Nov-2011/Jun-12

    ACTIVITY PLAN : 400 KV D/C Palatana Bongaigaon Transmission Line Associated with 726 6 (2X363 3) MW Pallatana CCGT Power Project of

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    20/85

    ACTIVITY PLAN : 400 KV D/C Palatana- Bongaigaon Transmission Line Associated with 726.6 (2X363.3) MW Pallatana CCGT Power Project of

    OTPC

    3 Erection -Total Qty 1800 Nos 1177* 462* 1300** 247 1091** 48 1043** 488 555** 200

    4 Stringing -Total Qty 661 Kms 330* 39* 579** 35 580** 13 574** 288 286** 100

    Project Cost - Rs.1770 Cr.

    **Including Backlog

    Brief Status

    1

    2

    3

    Critical Issues :

    1

    2

    3

    4

    Support Required : Nil

    Contract for Towers, Conductors, Insulators and pile & well foundation work awarded and work at site in progress

    Barak river

    On detailed survey Open cast foundation changed to Pile foundation. As an alternate, River Crossing (RC) towers at

    bank locations on opencast foundations with Truncated RC Tower shall be used.

    *Cumulative till Ist March, 2011

    Pile foundation at Champawati river completed except for pile capping.

    Well foundation work at Brahmaputra river commenced in November 2010.

    Brahmputra river

    a) Pile Foundation - Construction of coffer dam to facilitate pile casting in the submerged area is in progress. 33 out

    of 36 nos. of piles cast and balance activities are in progress.

    b) Well Foundation - Well sinking started and reached up to 31 m depth. Further, concreting of the well and sinking

    is in progress. For Second well, fabrication of caisson upto 6.4m out of approximately 18m has been completed and

    balance caisson is in progress and sinking is schedule to start by October 2011.

    Champabati river

    The piles already cast abandoned due to failure in integrity test. For fresh casting of piles, boring commenced. 8 out

    of 16 piles have been cast.

    Forest Clearance

    i) Tripura - Second stage forest clearance for starting the work, obtained on 17.08.2010.

    ii) Assam and Meghalaya - For second stage forest clearance, MoEF has sought further clarifications vide their letter

    dtd 13.04.2011. NETC on 28.04.2011 requested MoP for intervention for early second stage MoEF clearance.

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    21/85

    ACTIVITY PLAN 63 MW SV Power Project Chattisgarh

    Sr No MAJORACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Engineering

    2 Ordering

    3 Manufacturing

    4 Supply

    5 Erection

    a Boiler Drum

    b Economiser

    c Refractory furnanceInsulations

    d Deaerator

    e ID Fan

    f SA fan

    g PA fan

    h Steam Turbine Generator

    Alignment

    i Condensor

    j Condensate piping

    k ESP Structure

    l ESP Emitting and collectingframe

    m ESP hopper

    n ESP inlet hood

    o Fuel Bunker Chute to

    Furnance

    q Coal Handling plant Erection

    r Ash Handling plant Erection

    Ash Silo

    Pipe Rack

    Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    PROJECT MANAGER : Pradeep Aggarwal

    DATE : 03.08.2011

    TC : Target Completion

    AC/EC : Actual/Expected Comp

    COD as per IM : March-11

    Expected Target COD: Sept-11

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012)

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    22/85

    j g

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012)

    Equipment

    s Fuel Oil System

    t Fire Operating system

    u Chimneyv Cooling Tower

    w Weigh Bridge

    x CW and ACW system

    Chlorination system

    y WTP and ETP

    z LP Piping

    aa Compressed Air System

    ab AC and Vent

    ac 132 kv transmission line &

    LILO

    ad Pooling substationae Geneartor, Stationa and Unit

    Auxilliary Transformers

    af 6.6 kv HT s/g and LT s/g

    ag Plant earthing system

    ah Plant ligting system

    ak Cable trays

    al Power cables

    6 Testin and commissionin

    a Coal Washery unit

    b Refractory dry out

    c Boiler Light up

    d Alkali Boil out

    e Steam Blowing 7-May 25-Aug

    f Synchronisation 15-May 30-Aug

    g Load Trials 18-May 7-Sep

    h Performance acceptance test 25-May 10-Sep

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    23/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012)

    i Performance Guarantee Test 31-May 17-Sep

    M-BoP and E-BoP

    a Coal Handling plant

    b Ash Handling plantc Raw water pump house and

    Chlorination sys.

    d 132 kv line charging

    e Pooling substation

    f GT Testing and other

    electrical testings

    CoD 20-Sep

    Unit commissioning 31-May

    Brief Status :

    1

    23

    4

    5

    6

    7

    8

    Critical Issues :

    1

    Support Required : Nil

    Long term coal linkage for washery, GUVNL bid opened - under discussion

    O&M team of 30 people from Tata Power is working at site.

    Erection work completed and no load trail runs completed

    As on date approx. 350 Cr exp.done out of total now envisaged cost of Rs 375 Cr (against earlier estimate of 360 crore

    increased mainly due to IDC and some misc works.

    Road work, Drains, coal storage area and ash dyke works are almost complete.

    9000 MT coal and 25 KL of LDO reached at site, around 20000 MT of coal being procured through e -auction and rea

    Coal washery of 2.5 MTPA has been commissioned and around 9000 MT coal washed.

    132 kv switchyard and Pooling station and further connection to CSEB is completeReservoir filled , all supplies completed for M-BoP

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    24/85

    REMARKS

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    letion

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    25/85

    REMARKS

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    CompletedCompleted

    Completed

    Completed

    Completed

    Completed

    Completed

    Commissioned and9000 MT Coal washed

    Completed

    Completed with oil.

    Completed

    Transmission line has

    already been charged

    ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    26/85

    REMARKS

    Completed

    CompletedCompleted

    Commissioned

    Commissioned

    Tested, incl control

    room

    ). The cost has been

    ching at site shortly.

    ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    27/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 NTP Sep/09

    2 Release of Civil drawings Mar/10

    3 Start of civil works Jul/10

    4 ESP foundation Jan/11

    5 Start of Boiler structural

    erection

    Feb/11 Jun/11

    a Start of TG deck foundations

    concreting

    Jan/11 Apr/11

    b Start of structural erection of PHB Mar/11 Jul/11

    c ESP Erection commencement Jul/11 Sep/11

    d Boiler drum lifting Nov/11 Jan/12

    e TG hall readiness for EoT erection Jul/11 Jan/12

    f TG deck readiness Aug/11 Nov/11

    g TG erection start Sep/11 Feb/12

    h Condenser erection start Sep/11 Feb/12

    i Boiler Hydro test Mar/12

    j Condenser Hydro test

    k Readiness of FD/ID fans &

    Ducting

    l Fuel oil requirement

    m Air leak test of furnance & Aux.

    n Turbine box up

    TIME FRAME (Phase I)

    PROJECT MANAGER : Pradeep Aggarwal

    DATE : 03.08.2011

    TC : Target Completio

    AC/EC : Actual/Expec

    COD as per IM: Phase1 Sept-12 , PExpected Target COD: Phase I: Mar-13,

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    28/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME (Phase I)

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    o Oil flusing

    q Alakali Boil out

    r Readiness of ESP incl. insulation

    Turbine on Barring gear

    Boiler light up

    Readiness of Mils and Aux. & coal

    piping

    s Steam blowing

    t Safety valve Floating

    u Synchronisation

    v Coal Firing

    w Performance acceptance Test

    CoD

    Unit -I

    Brief Status :

    Phase-I

    1

    2

    3

    4

    5

    Phase-II

    1

    2

    Critical Issues :

    1

    2

    3

    Support Required : Nil

    Soil investigations in progress and excavation work at boiler area started.

    FSA need to be done at the earliest for coal and agreement for Water linkage is also required to be in place.

    Power evacuation with OTPCL for around 400 MW need to be firm up. BPTA for 560 MW with PGCIL is in

    The acquisition of balance land

    Land- 700+ Acre land out of 804 acre has been acquired. Balance is in advance stage of acquisition.

    Major Engineering completed/EPC awarded/Manufacturing of BTG in progress

    Clearances- Mostly in place i.e. MoEF/AAI/SPCB/Arche.SoI/Mega power status/Min of Rail

    Coal Linkage- LoA issued for 1000 MW by Min. of coal. BG submitted for execution of FSA.Water linkage o

    Foundation works of Boiler and ESP completed for Phase-I, excavation for coal bunker,TG Building and chim

    EPC contract awarded , Common structures work of phase-I and Phase-II planned and started

    ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    29/85

    REMARKS

    Completed

    Completed

    Started

    Completed

    Boiler Erection work

    startedRaft completed, TG

    deck level yet to reach

    Started

    Foundation work almost

    completed

    Manufacturing

    completed. Yet to be

    inspected and reach at

    site.

    1-Jun-12

    27-May-12

    17-May-12

    1-Nov-12

    1-Sep-12

    n

    ted Completion

    hase II June-13

    Phase II: Dec-13

    ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    30/85

    REMARKS

    7-Jan-13

    7-Feb-13

    7-Dec-12

    6-Jan-12

    1-Feb-13

    18-Sep-12

    30-Jan-13

    30-Jan-13

    28-Feb-13

    15-Mar-13

    20-Mar-13

    31-Mar-13

    place

    btained for the project

    ney completed

    ACTION PLAN:100 MW Sorang Hydro Power Project

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    31/85

    AC/EC : Actual/Expected Completion

    Sr No MAJOR ACTIVITY/ MILESTONE TIME FRAME REMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Civil works NCC

    a Infrastructure works - - - - - - - - - - Completed

    b Trenchweir, Desilting Tank &

    Intakei Excavation - - - - - - - - - - Completed

    ii Concreting - - Jun/11 Jun/11 - - - - - - Completed

    c Head Race Tunnel

    i Excavation - - - - - - - - - - Completed

    ii Concreting/lining length - - - - - - Nov/11 - - Jan/12 700 m invert co

    completed

    60 m lining com

    d Surge shaft

    i Pilot Height - - - - - - - - - - Completed

    ii Widening height Mar/11 Mar/11 - - - - - - - - Completed

    e Vertical shaft

    i Pilot Height - - - - - - - - - - Completed

    ii Widening height/ concreting - - - - Aug/11 - - - - - Balance 20%

    f Penstock & Hydraluic Gates

    i Fabrication work - - - - - - Dec/11 - - Balance 10%

    ii Erection works Dec/11 Feb-12 Balance 90%

    g Power House and MAT

    i Excavation - - - - - - - - - - Completed

    ii Concreting - - - - - - Nov/11 - - - Balance 10%

    h Tail race tunnel

    i Excavation length - - - - - - - - - - Completed

    ii Lining in RM - - May/11 Apr/11 - - - - - - Completed

    i Suppy of E & M and Transmission

    Items

    Voith Siemens

    i EOT Crane - - - - - - - - - - Completed

    ii Turbine units - - - - - - - - - - Completed

    Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012)

    PROJECT MANAGER : N.D. Arora, Pradeep Aggarwal

    TC : Target Completion

    DATE : 03.08.2011

    COD as per IM: Unit # 1: Dec-11, Unit # 2: Dec-11Expected Target COD: Unit # 1: Feb'12, Unit # 2: Mar'12

    ACTION PLAN:100 MW Sorang Hydro Power Project

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    32/85

    Sr No MAJOR ACTIVITY/ MILESTONE TIME FRAME REMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/ECQ2 (2011-12) Q3 (2011-12) Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012)

    vi Mechanical and Electrical BoP - - - - - - Nov/11 - - - Balance 20%

    vii Transmission tower and conductors - - June-11 - - - - Nov-11 - - Supply commen

    foundation start

    Conductors reac

    j Erection

    i EOT Crane - - - - - - - - - - Completed

    ii Turbine and its Auxilliaries - - - - - - Dec/11 - - - Balance 40%iii Generator and its auxillaries - - - - - - Dec/11 - - - Balance 75% w

    iv Transformers - - June-11 - - - - Oct-11 - - Balance 40% w

    v Switchyard GIS - - - - Sep/11 - - Dec-11 - - Balance 100% w

    vi XLPE cables & other items - - - - - - Dec/11 - - - Balance 100% w

    vii Transmission tower and conductors - - - - - - Dec/11 - - Jan-12 Erection to start

    k Testing & Commissioning

    i Unit -I - - - - - - - - Feb/12 -

    ii Unit-II - - - - - - - - Mar/12 -

    Brief Status :

    1

    2

    3

    4

    5

    Critical Issues :

    1

    2

    Support Required :

    Civil : Excavation of all underground structures completed including HRT. The concreting works are in progress

    E&M : EoT crane erected and third stage embedments of Unit-I and Unit-II completed.

    Transmission: The work order for 10 towers provided to M/s RRV, Hyderabad. The erection expected by Jan-12

    Project Cost: Rs 7560 Mn, Incurred Rs 5420 million (Till June 2011) . The physical progress is around 76%

    Project likely to be commissioned by March-12

    Erection of Penstock

    Proper Site Management

    Nil

    ACTIVITY PLAN - 45 MW Tirap hydro power project

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    33/85

    Sr No MAJOR

    ACTIVITY/MILESTONE

    REMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Detailed survey and

    investigations

    - - - - - - - - - - Completed

    2 Detailed Project Report

    i Finalization - - - - - - - - - - Completed

    ii Approval Jun-11 Jul-11 Techno-economic clearance

    obtained from State Govt.

    3 EIA/EMP studies

    i EIA/EMP studies report as per

    approved ToR of MoEF

    - - Jun-11 - Jul-11 - - - - Three seasons studies

    completed, report to be

    submitted to SPCB onclearence from Forest Dept.

    ii Environment Clearance Sep-11 Dec-11

    4 Preparation of EPC bid

    documents-Civil, Hydro

    Mechnical and E&M works

    Mar-11 - - - - - - - - - EPC bidding documents are

    ready. Bid process would start

    after status on land acuisition

    is cleared.

    5 Selection of EPC Contractor

    and award of EPC works for

    different Packages

    - - - - - - Dec-11 Mar-12 - -

    Expected as per IM : Unit # 1: Feb'15, Unit # 2:

    PROJECT Team : Mr. N.D.Arora, Neeraj Jain

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    COD as per IM: Unit # 1: March-15, Unit # 2: March-

    DATE: 03.08.2011

    TC : Target Completion

    AC/EC : Actual/Expected Completion

    ACTIVITY PLAN - 45 MW Tirap hydro power project

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    34/85

    Sr No MAJOR

    ACTIVITY/MILESTONE

    REMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    6 Financial closure - - - - - - - - Mar-12 - Through IFIN

    7 Agreements & Contracts

    i Land Acquisition/ Lease

    Agreement

    - - - - - - Dec-11 - - - Joint Land Survey Completed,

    acquisition process to be

    commenced by DC

    Changlang.Land owners

    consent is to be taken.

    ii Execution of Power Purchase - - - - - - - - - - Merchant power envisaged

    iii Execution of BPTA - - - - Sep-11 - - - - -

    iv Execution of EPC Agreement - - - - - - Dec-11 - - -

    v Execution of Loan Agreements - - - - - - - - Mar-12 -

    Brief Status :

    1

    2

    3

    4

    Critical Issues :

    1

    Support Required :

    EPC Bid documents for Civil & HM and E&M works have been finalised.

    Three seasons studies completed. EIA report is under compilation incorporating land details.To be submitted to CPCB for public

    hearing after clearance from State Forest Department.

    TEC approved by State Govt.

    The joint land survey completed with GoAP officials, meeting held with DC Changlang, public hearing to be called by D.C for

    consent of land owner

    Land Acquisition

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    35/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    A LAND

    1 Visit for site selection Oct-10

    2 Finalization of Site Oct-10

    3 Demand Note by Land

    Allotment A ency

    4 Deposit of Money for Land

    Acquisition

    5 Signing of Lease Deed Mar-12

    B DPR for Generation Project

    1 Selection TechnicalConsultant (TC) & Issue of

    LOI - TC

    Oct-10

    2 Site Visit, Kick off meeting

    with TC

    Oct-10

    3 Submission of Pre-feasiblity

    report

    Dec-10

    4 Submission of Data to TC Nov-10

    IMD Data

    Water Analysis

    PROJECT TEAM : Feby Koshy, Akhil, Zaheen

    DATE : 03.08.20

    TC : Target Co

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    AC/EC : Actual/

    COD as per IM:

    Expected Target

    May-11 Dec-11

    Unit # 2: Mar-16, Unit # 3: Sep - 16, Unit # 4 Mar-17, Unit # 5 Se

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    36/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    Soil Data Apr-11 May-11

    Contour Data

    Topo Sheets

    Other Maps

    Any other Data / AMSL

    5 Preliminary Plant layout and

    preliminary design

    Dec-10

    6 Submission of Draft DPR Mar-11 May-11

    7 Presentation on Draft DPR Mar-11 May-11

    8 Finalization of Layout Mar-11 Nov-11

    9 Finalization of DPR Apr-11 Nov-11

    C Environmental and R&R

    1 Selection of Environmental

    Consultant & Issue of LOI

    Oct-10

    2 Submission of Form I ,

    MoE&F

    Dec-10

    3 Start of EIA Mar-11 Mar-11

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    37/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    4 TOR Approval Jun-11 Oct-11

    5 Additional studies as per

    approved ToR

    6 Presentation on draft EIA

    report

    7 Submission of draft EIA

    report

    8 Final EIA Report

    9 Submission of EIA report to

    State A ency

    10 Public Hearing

    11 Filing of application forEnvironment Clearance

    12 Clearance from MOE&F

    D Site Related Investigations

    1 Selection of Topo Survey

    Consultant & issue LOI

    2 Selection of Geotechnical

    Consultant & issue LOI

    Feb-11

    3 Submission of Topo Survey

    Report

    4 Submission of Geotechnical

    Investigation Report

    Apr-11 May-11

    5 Any other project specific

    studies

    E Statutory Clearances /

    A rovals

    1 Filing for NoC from AAI for

    stack height

    May-11 Aug-11

    2 Receipt of NoC from AAI Nov-11

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    38/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    3 Filing of Application for

    Mega Power Status4 Recept of Mega Status

    5 Filing for CTE

    6 Reciept of CTE

    F Infrastructure

    1 Finalization of Transport

    Consultant for equipments

    2 Finalization of Transport

    Route

    3 Application for Water

    Linkage / allocation

    Oct-11

    4 Execution of Water Supply

    Agreement

    5 Application for Construction

    Water/allocation

    6 Application for Construction

    Power

    G Fuel

    1 Finalization of Fuel

    re uirement

    Oct-11

    2 Fuel Specs from potential

    Fuel suppliers

    3 Finalization of Fuel supplier

    4 Submission of

    MoU/Agreement to Fuel

    Su lier

    5 Execution of MoU/Agreement

    with Fuel Supplier

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    39/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    H Open Access

    1 Filing of application withCTU

    2 Standing Committee meeting

    3 Grant of Long Term Open

    Access

    4 Execution of BPTA

    I Selection of EPC

    Contractor/Packages

    1 Selection of Consultant for

    preparing EPC specs & Issueof LOI

    Oct-11

    2 Finalization of bid

    specifications for EPC

    Contractor

    Nov-11

    3 Finalization of bid document Dec-11

    4 Issue of bids Jan-12

    5 Pre-bid conference

    6 Last date for bids submission

    7 Bid evaluation & selection8 Issue of Notice to Proceed

    9 Execution of EPC Agreement

    10 Selection of Consultant for

    PMC & Issue of LOI

    J Financial closure

    1 Appointment of Debt

    syndication agency

    Dec-11

    2 Preparation of PIM &

    Financial Model

    Feb-12

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

    MAJOR

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    40/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    3 Circulation of PIM to Banks

    etc

    Feb-12

    4 Obtaining Sanctions from

    Banks etc

    6 Execution of Loan Agreement Mar-12

    K Agreements & Contracts

    1 Land Acquisition/ Lease

    Agreement

    Apr-11 Mar-12

    2 Execution of Fuel Supply

    Agreemnt

    3 Execution of Water SupplyAgreement

    4 Execution of Power Purchase

    Agreement

    5 Execution of BPTA

    6 Execution of EPC Agreement

    7 Execution of Loan

    Agreements

    Status:

    Critical Issues:

    Action Plan:

    1) Power Plant TOR application taken up by MoE&F in April 2011 to be re-considered by MoEF after SEZ TOR is approved ; SEZ To

    3) Draft DPR finalized, Geo-Tech investigations completed, EIA - part base line monitoring completed

    1) Being an integrated project, the delay in SEZ ToR approval is delaying Power Plant ToR clearance

    1) IMICL & IL&FS Ecosmart to expedite SEZ ToR approval

    2) MoU for lease of 1500 acres of land signed, part advance released

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    41/85

    REMARKS

    11

    pletion

    Expected Completion

    Land to be leased out to

    NPCL by ALPL/SPPL

    COD: Unit # 1: Sep- 15,

    MoU with ALPL/SPPL done

    for 1500 acres land, Part

    advance Rs. 10 Cr paid

    pt -17, Unit # 6 : Mar-18

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    42/85

    REMARKS

    Geo-Tech Investigations

    Completedcompleted

    completed

    Obtained from Survey of

    India

    Baseline monitoring for EIA

    completed in June 2011 for

    Ambient Air Quality

    Monitoring, Water Quality

    Monitoring (Surface and

    Groundwater), Noise

    Environment Monitoring,

    Soil Quality, Marine Water

    and Sediment Quality

    Monitoring is under progress

    To be finalized based on ToR

    approval & close to financialclosure

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    43/85

    REMARKS

    Will reapply once ToR for

    SEZ is a roved

    Available

    completed

    Available

    completed

    Enquiries initiated for Area

    Drainage & hydrological

    study

    Certified data received from

    SoI

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    44/85

    REMARKS

    Apply after SEZ ToR is

    approved

    Apply for domestic linkage

    after ToR a roval

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    45/85

    REMARKS

    Apply after 50% Power Tie-

    u

    ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    46/85

    REMARKS

    MoU already executed

    filed on June 8, 2011 by

    ACTIVITY PLAN: 274.4 MW Wind Power Project

    PROJECT TEAM: Anand Nair, Akshay Sharma

    Date : 03 08 2011

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    47/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC TC AC TC AC TC AC TC AC TOTAL

    1 Sub Lease in favour of ILFS 74.4 MW 74.4 MW

    2 SLEC/ Registeration of Land in

    favour of EIL Companies Done

    74.4 MW 74.4 MW 200.8 MW 275.2 MW

    3 Construction of Roads &

    Platforms

    74.4 MW 56 MW 3.2 MW 60.0MW 140.8 MW 275.2 MW

    4 Foundation Casting Activities 50.4 MW 40.8 MW 24 MW 16.8 MW 60.0MW 140.8 MW 275.2 MW

    5 Arrival of WECs 60 MW 60 MW 14.4 MW 14.4 MW 200.8 MW 275.2 MW

    6 Erection Of Towers 10.4MW 10.4 MW 16 MW 11.2 MW 48 MW 105.6 MW 143.2 MW 275.2 MW

    7 Erection Of WECs 10.4MW 10.4 MW 16 MW 10.4 MW 48 MW 57.6 MW 143.2 MW 275.2 MW

    8 Construction of Internal OH

    33KV line

    74.4 MW 50.4 MW 157.6 MW 42.4 MW 275.2 MW

    9 Construction of Evacuation Sub-

    Station

    50.4 MW 50.4 MW 200.8 MW 251.2 MW

    TC : Target Completi

    AC/EC : Actual/Expe

    TIME FRAME

    Date : 03.08.2011

    All Numbers Repesent MW out of a total target of 1004 MW by 2015

    Expected Target CO

    COD as per I

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    ACTIVITY PLAN: 274.4 MW Wind Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONETIME FRAME

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    48/85

    Sr NoACTIVITY/MILESTONE

    TC AC TC AC TC AC TC AC TC AC TOTAL

    Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    10 Construction of External EHV 2 50.4 MW 50.4 MW 200.8 MW 251.2 MW

    11 Execution of PPA 26.4 MW 10.4 MW 48 MW 24 MW 176.8 MW 275.2 MW

    12 Commissioning of the WECs 14.4 MW 74MW 0.8 MW 200.8 MW 275.2 MW

    Status:

    Critical Issue:

    Action Plan:

    2) Deferred Equity Structure currently being sought with various banks such as First Gulf Bank, Barclays, HSBC etc.

    1) 74.4 MW is under construction in three states

    2) Order has been placed on July 7th for the 200 MW:

    - IFIN has been mandated to source debt funds at an effective interest cost of 11.5%

    1) Total Equity Requirement of Rs. 285.9 crores (Debt : Equity = 75 : 25)

    1) Equity infusion will be funded through a mix of deferred equity structure and funds received from IEDCL divestment

    ACTIVITY PLAN: 274.4 MW Wind Power Project

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    49/85

    REMARKS

    M.P. does not

    require an

    evacuation sub

    station to be

    constructed

    on

    ted Completion

    Unit # 2: Mar'12

    : Unit # 1: Aug'11

    Unit # 2: Mar'12

    : Unit # 1: Sept'11

    ACTIVITY PLAN: 274.4 MW Wind Power Project

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    50/85

    M.P. does not

    require an external

    EHV 2 line

    ACTIVITY PLAN: Wind Power Project

    Fincial Year State (Project Location) MW COD

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    51/85

    FY 2011-12 Rajasthan (Sipla) 26.4 Jun11

    M.P. (Ratedi) 24 July11

    T.N. (V'kullum) 24 Aug11

    Karnataka 100 Mar12

    A.P 50.4 Mar12

    Gujarat (Lalpur) 50.4 Mar12

    Total 275.2

    FY 2012-13 Vkulum/ TN 50.4 Sep/12

    Banswara3/Rajasthan 50.4 Sep/12

    Lalpur/ Gujarat 50.4 Sep/12

    Tungabhadra/Andhra Pradesh 50.4 Mar/13

    Banswara4/Rajasthan 50.4 Mar/13

    Tungabhadra/Andhra Pradesh 49.6 Mar/13

    Tadas/ Karnataka 50.4 Mar/13

    Total 352.0

    FY 2012-13 Lalpur/ Gujarat 50.4 Sep/13

    Chandwad/ Maharashtra 50.4 Sep/13

    Chandwad/ Maharashtra 24.8 Sep/13

    Rajgarh/ Rajasthan 50.4 Mar/14

    Rajgarh/ Rajasthan 49.6 Mar/14

    Tadas/Karnataka 50.4 Mar/14

    Gadag N/ Karnataka 50.4 Mar/14

    Total 326.4

    ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited

    PROJECT MANAGER: Mr. Punyatma Dwivedi, Pavas Agarwal

    DATE 03 08 201

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    52/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 EPC COGEN

    1.1 Boiler

    1.1.1 Steam Drum Lifting Completed1.1.2 Hydro Test Completed

    1.1.3 Refractory Dry Out Completed

    1.1.4 Alkali Boil Out Completed

    1.1.5 Steam Blowing Completed

    1.1.6 Safety valve floating Completed

    1.2 Turbo Generator

    1.2.1 Lube Oil Flushing Completed

    1.2.2 TG Alignment & Grouting Completed

    1.2.3 Turbine on barring gear Completed

    1.2.4 Turbine Rolling on steam Completed

    1.2.5 Start of synchronization Trials Completed1.3 Water Treatment Planty

    1.3.1 Clarifier Completed

    1.3.2 DM Plant Completed

    1.3.3 Balance Civil Works Completed

    1.4 Cooling Tower

    1.4.1 Civil Works Completed

    1.4.2 Erection & Commissioning Completed

    1.5 RCC Chimney

    1.5.1 Raft Foundation Completed

    1.5.2 100m Cell Casting Completed

    1.5.3 Refractory Lining Works Completed1.5.4 Commissioning Completed

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

    DATE : 03.08.201

    TC : Target Com

    AC/EC : Actual/E

    Expected Target

    Q4 (2011-12)

    COD as per IM: J

    ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited

    Sr NoMAJOR

    ACTIVITY/MILESTONETIME FRAME

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    53/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    1.6 Fuel Handling System

    1.6.1 Bagasse Handling System Completed

    1.6.2 Coal Handling System Completed

    1.7 Under Ground Service Reservoir

    1.7.1 UGSR 1st compartment Completed

    1.7.2 UGSR 2nd compartment Completed

    1.7.3 Raw Water Pump House Completed

    2 Power Evacuation System

    2.1 Stub setting and Foundation Completed

    2.2 Tower Erection Completed

    2.3 Stringing Completed

    2.4 Plant Sub station Completed

    2.5 Jaysingpur Substation Completed

    3 Raw Water Pumping System

    3.1 Pipeline Completed

    3.2 Jackwell 1-Jan-11 30-Sep-11

    3.3 11 kv Line 1-Jan-11 30-Sep-11

    4 HSF Modification Works

    4.1 Modifications in Boiling House Completed

    4.2 Modifications in Milling Section Completed

    Brief Status :

    Critical Issues :

    Support Required :

    Transmission of Power using 132 KV line is expected by 1st Week of August 2011

    ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited

    1

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    54/85

    REMARKS

    Misc Works such as

    Internal Road, Drains,

    Compund Wall and other

    Finishing Works are in

    Progress

    1

    letion

    xpected Completion

    OD : August'11

    an'11

    ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    55/85

    Only 2 Nos of Mill Drive

    replacement is balance,

    which is bin taken u

    Water Supply to Cogen

    Plant has been arranged

    through HSF's existing

    Pipeline

    Approval for charging the

    line is in progress.

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    56/85

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    Sr NoMAJOR

    ACTIVITY/MILESTONETIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    57/85

    1.3.1 Clarifier 1-Jan-11 30-Sep-11

    1.3.2 DM Plant 10-Jan-11 30-Sep-11

    1.3.3 Balance Civil Works 5-Jan-11 15-Sep-11

    1.4 Cooling Tower1.4.1 Civil Works 1-Jan-11 15-Aug-11

    1.4.2 Erection & Commissioning 15-Jan-11 15-Oct-11

    1.5 RCC Chimney

    1.5.1 Raft Foundation Completed

    1.5.2 100m Cell Casting Completed

    1.5.3 Refractory Lining Works 1-Jan-11 15-Sep-11

    1.5.4 Commissioning 1-Jan-11 30-Sep-11

    1.6 Fuel Handling System

    1.6.1 Bagasse Handling System 1-Jan-11 31-Oct-11

    1.6.2 Coal Handling System 15-Jan-11 31-Oct-11

    1.7 Under Ground Service

    Reservoir

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    Sr NoMAJOR

    ACTIVITY/MILESTONETIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    58/85

    1.7.1 UGSR 1st compartment 1-Jan-11 22-May-11

    1.7.2 UGSR 2nd compartment 5-Jan-11 31-Oct-11

    1.7.3 Raw Water Pump House 5-Jan-11 30-Sep-11

    2 Power Evacuation System

    2.1 Stub setting and Foundation 1-Jan-11 30-Sep-11

    2.2 Tower Erection 15-Jan-11 15-Nov-112.3 Stringing 15-Feb-11 15-Dec-11

    2.4 Plant Sub station 15-Feb-11 15-Oct-11

    2.5 Wathar Substation 15-Feb-11 15-Nov-11

    3 Raw Water Pumping System

    3.1 Pipeline 1-Jan-11 15-Aug-11

    3.2 Jackwell 15-Jan-11 15-Sep-11

    3.3 11 kv Line 15-Jan-11 15-Oct-11

    4 HSF Modification Works

    4.1Modifications in

    Boiling House30-Oct-11

    30-Oct-11

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    Sr NoMAJOR

    ACTIVITY/MILESTONETIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)

    4 2 Modifications in Milling

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    59/85

    4.2 Modifications in Milling

    Section 10/30/2011 30-Oct-11

    Brief Status :

    Critical Issues :

    Support Required :

    EPC Contractor WIL is facing severe financial Crunch and payments to Sub-contractors is getting delayed frequently whic

    cascading effect on sub-vendors resulting in to delayed work at Site and supply of material.

    ACTION PLAN: Matter has been taken up with WIL's top management. There has beenlittle improvement in progress at

    Power Evacuation System: RoW Acquition issue due to stiff opposition of the Landowners

    Civil & Mechanical Works are in Progress for all the Packages

    Action Plan: Alternative plans are being worked out to expedite the progress

    Full time Manpower Requirement for Supervision of Transmission Line Works and Civil Works

    WTP-WTP work suffered heavily due to commercial issues of Doshion with WIL.

    Action Plan- Matters are sorted out by WIL. Things have started improving since this week.

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    60/85

    REMARKS

    IBR Hydrotest

    completedsuccessfully on

    04.06.2011.

    letion

    oiler) : Oct-11h boiler) : Dec-11

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    REMARKS

    Civil work

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    61/85

    C v wo

    completed.

    Completed

    One Cell will be

    completed by 15-

    09-2011.

    Refractory Lining

    in progress.80 %

    completed.

    Civil Foundation

    work in

    progress.Structura

    l Material rec'd

    at site. And

    erection started.

    Targetted to

    complete up to

    MBC by 30 Sep.

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    62/85

    Leakage test done

    on 27.05.2011 to

    10.06.2011.Minor

    Leakage

    observed.Will beattended

    completion of II

    nd compt..

    Work in progress.

    Bay location yet

    to be handed over

    by MSETCL.

    Completed

    The HSF is

    thinking of

    alternative plan of

    modification and

    hence award of

    contract under

    hold due to

    request of HSF.

    ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    63/85

    h is having

    Site.

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    PROJECT MANAGER : Pramod Tikkas, Sanjay Joshi

    DATE : 03 08 2011

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    64/85

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    A LAND

    1 Visit for site selection

    2 Finalization of Site

    3 Submission of Proposal for Land

    Acquisition4 Measurement of Land by

    District Inspectorate of land

    Record (DILR)

    5 Submission of Report by DILR

    to Dist. Collector Kutch (

    Revenue dept)

    6 Dist collector recommendationto state level approval committee

    for approval of allottment of land

    May-11 Aug-11

    7 Demand Note by Land Allotment

    Agency/ Revenue dept

    May-11 Oct-11

    Q4 (2011-12)

    COD as per IM: Sep

    DATE : 03.08.2011

    TC : Target Comple

    AC/EC : Actual/Exp

    Expected Target COD: March

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    65/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q ( 0 )Q ( 0 0 0 ) Q ( 0 0 ) Q ( 0 ) Q3 ( 0 )

    8 Deposit of Money for Land

    Acquisition

    May-11 Oct-11

    9 Registration in the name of SPVNBEL

    Jun-11 Oct-11

    B Preparation of DPR

    1 Selection and appointment of

    Technical Consultant (TC) for

    DPR and EPC Specs

    2 Site Visit, Kick off meeting with

    3 Submission of Data to TC

    IMD Data

    Water Analysis

    Contour Data

    Topo Sheets

    Other Maps

    Any other Data / AMSL

    4 Submission of Draft DPR

    5 Finalization of Layout

    6 Finalization of DPR

    C Appointment of consultant for

    Site Related Investigations

    1 Selection and appointment of

    Biomass assessment consultant(Zenith Energy services,

    Hyderabad)

    2 Selection and Appointment of

    Topo Survey Consultant . R. N.

    Consultancy services,

    Ahmedabad

    3 Selection and Appointment of

    Geotechnical Consultant M. K.

    Soil Testing Laboratory,Ahmedabad

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    66/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q ( )Q ( ) Q ( ) Q ( ) Q ( )

    4 Selection and appointment of

    consultant for Ground water

    assessment/ LULC studies -Environmental Management

    Centre , Mumbai

    Feb-11 Feb-11

    5 Submission of Biomass

    Assessment Report

    6 Submission of Topo Survey

    Report

    7 Submission of Geotechnical

    Investigation Report

    Jun-11 Jul-11 Jul-11

    8 Obtaining data on Ground water

    availabil ity from Gujarat waterSupply and Sewarage Board

    ( GWS&SB)

    9 Submission of Sustainability

    Assessment study Report on

    Ground water assessment and

    recharging Possibilities,

    Geohydrological Report and

    Rainwater harvesting proposal

    Apr-11 Apr-11

    10 Submission of Report on

    Transportation network analysis/

    LULC studies, Report on

    developing community linkage

    programme

    Jun-11 Aug-11

    D Statutory Clearances /

    Approvals

    1 Application to GEDA for In-

    Principal Approval

    2 Receipt of In-principal approval

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    67/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    3 Receipt of Final approval from

    GEDA

    Jun-11 Oct-11

    4 Receipt of distance certificate

    from Survey of India

    Mar-11 Mar-11

    5 Filing for NoC from AAI for

    stack height

    Apr-11 Apr-11

    6 Receipt of NoC from AAI Jun-11 Oct-11

    7 Receipt of NOC from Industries

    Dept

    Mar-11 Mar-11

    8 Receipt of NOC from Forest

    Dept

    Apr-11 Apr-11

    9 Applied for Geology and Mining

    NOC

    10 Receipt of NOC from Geology

    and Mining dept

    11 Filing for CTE Jan-11 Jan-11

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    68/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    12 Reciept of CTE Jun-11 Oct-11

    E Infrastructure

    1 Application to CGWB for

    drawal of Ground Water

    Apr-11 Apr-11

    2 Permission for Ground Water

    drawal from (CGWB)

    Jun-11 Oct-11

    3 Application to Gujarat Water

    Infrastructure Limited (GWIL)

    Mar-11 Mar-11

    4 Sanction of Demand by GWIL May-11 Sep-11

    5 Application for Construction

    Power

    Apr-11 Apr-11 Jul-11

    F Evacuation arrangement

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    69/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    1 Application for Grid connectivity

    2 Obtention of Grid connectvity

    from GETCO

    May-11 May-11

    G Fuel

    1 Submission of proposal to

    Gujarat Forest Dept (GFD) for

    fuel tie up

    2 Submission of Draft Concession

    agreement to GFD

    Apr-11 April -11/

    June -11/

    August-11

    3 Execution of Agreement with

    GFD

    May-11 Sep-11

    H Selection of EPC Contractor

    1 Selection of Consultant for

    preparing EPC specs & Issue of

    LOI

    2 Finalization of bid specifications

    for EPC Contractor

    3 Finalization of bid document

    4 Issue of BID Mar-11 Mar-11

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    70/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    5 BID received Apr-11 Jun-11

    6 Bid evaluation & selection May-11 Aug-11

    7 Selection of Consultant for PMC

    & Issue of LOI

    May-11 Aug-11

    8 Issue of Notice to Proceed Jun-11 Oct-11

    I Financial closure

    1 Preparation of PIM & FinancialModel

    May-11 Aug-11

    2 Circulation of PIM to Banks etc May-11 Aug-11

    3 Obtaining Sanctions from Banks

    etc

    Jun-11 Sep-11

    4 Execution of Loan Agreement Jun-11 Oct-11

    J Agreements & Contracts

    2 Execution of (Fuel Supply)Concession Agreement with

    GFD

    May-11 Sep-11

    3 Execution of Power Purchase

    Agreement

    May-11 Aug-11

    4 Execution of EPC Agreement May-11 Sep-11

    5 Execution of Loan Agreements Jun-11 Oct-11

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    Sr NoMAJOR

    ACTIVITY/MILESTONE

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    71/85

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    Brief Status

    1) Created SPV in the name of Nakhatrana Biomass Energy Limited on July 21,2011

    3)' IREL as one of the respondent filed reply against the petition with Sr. Civil Judge at Bhuj Court on July 2

    4) Submitted proposal for issuance of advance possession of land till final land allotment to Dist Collector,

    5) Geotechnical Investigation completed

    6) GWIL Completed feasibility study for water supply on July 30,2011.

    7) GETCO completated feasibility study for grid connectivity. Obtained connectivity at 66KV Kotda Substati

    8) PPA draft approval is process with GUVNL

    Critical Issues

    1) Allotment of 30 Acres of land may get delayed due to the petition filed by the locals againsy Govt

    2) Sanction of Narmada water demand by Gujarat Water Infrastructure Limited and permission for ground w

    3) NOC from Pollution Control Board subject to water sanction by GWIL

    4) Execution of Concession Agreement for fuel tie-up

    5) Financial closure

    Support Required

    1) Support from Govt of Gujarat for allotment of land and sanction of water Demand from GWIL

    2) Support from Forest Dept for execution of concession agreement

    9)Gujarat Forest Dept(GFD) issued allocation of @ 35,500 Ha of land in Banni and Kachchh Forest. Draft C

    10) Received revised EPC offers from IJT and Cethar vessels, EPC cost offered are in the range of 5.5. to 5.negotiations are in progress

    2)Deposited 1% surcharge as processing fee with Revenue Dept. Proposal forwarded to Dist. Town Planning

    on August 03,2011

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    ion

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    72/85

    REMARKS

    Completed.

    Completed . On september 2009

    Completed. On 8 July 2010

    Completed.Carried out on Dec 2,2010

    DILR submitted Land measurement

    report to revenue Dept on December

    15,2010, Composite map on April

    18,2011 in compliance to the query

    raised by Revenue dept.

    1% surcharge deposited with Revenue

    dept.on July 14,2011. Dist. Collector,

    Kachchh moved the file to DTP for

    valuation on August 03,3011

    Proposal forwarded to DTP on August

    03,2011. Upon valuation by DTP and

    recommendation by Dist Collector,

    proposal will be forwarded to

    Additional Secretary(Revenue)by end

    of August 2011. If the land valuation is

    more than 1 Cr, the proposal will be

    presented in the cabinet for approval.

    t -12

    ion

    cted Completion

    13

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    73/85

    After state level approval the deposit

    will be made.

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed

    Completed . On Sept 3,2010

    Completed. On June 17,2010

    Completed. On Dec 31, 2010.

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    74/85

    Completed. Environment Management

    Consultant appointed on Feb 28,2011

    Completed . Report Submitted on

    November 2010

    Completed . Report Submitted on Dec.

    2010

    Received report on July 12,2011

    Obtained on 4.11.2010

    Report Submitted by EMC The reports

    is required for filing application to

    CGWB for ground water drawal

    permission (application filed with

    CGWB)

    Data collection completed, analysis and

    report preparation in progress.

    Completed. Applied on May 26,2010

    Obtained In -Principal approval on

    August 26, 2010

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    75/85

    After submission of valid land transfer

    document, permission for Water

    drawal from CGWB / GWIL, GPCB

    NoC, PPA and financial closure

    Certificate obtained (SoI did not issue

    authenticated map)

    Application submitted on April 25,201.

    after receipt of distance certificate

    AAI is insisting for authentication on

    map also. Being restricted zone, Govt.

    agencies are reluctenct to authenticate

    maps. However, we have obtained

    authentication from Thalati and the

    application is resubmitted on

    08.07.2011

    Obtained. On March 29,2011

    Obtained. On April 18,2011

    Completed. Applied on August

    23,2010

    Obtained. on December 23,2010

    Completed. Application inwarded

    online in GPCB Portal in Jan ,2010

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    76/85

    GPCB may issue NOC subject to

    Acquisition of land and NOC from

    CGWB or GWIL. Quality of groundwater and its treatment is major issue

    in accepting the application by GPCB.

    Water treatment schemes is under

    discussion with EPC vendors. Initiated

    process for obtaining Adequacy

    Certificate and TSDF Membership as

    desired by GPCB

    Application filed on April 28,2011

    Getting permission is critical

    considering ground water recharging at

    very low annual rainfall in Kachchh .

    Submitted on March 30, 2011

    (requirement is 330 Cu.m per day) .

    Feasibility study completed by GWIL.The proposal will be discussed in

    Tapping committee meeting for

    approval. Date of the meeting is not yet

    declared.

    Applied. on April 18,2011 to PGVCL.

    Demand sanctioned for Construction

    Power subject to submission of valid

    land transfer documents. PGVCL

    furnished the estimate of @9 lakhs, the

    same is to be deposited within onemonth's period from the date of issue of

    estimate

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

    C l t d A li d O t b 2010

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    77/85

    Completed. Applied on October 2010,

    Joint survey with GETCO Completed

    Feasibili ty for grid connectivity

    Obtained on 24 May 2011.

    Completed.Proposal submitted on Dec

    31,2010

    Submitted revised concession

    agreement on 15 June ,2011 as per

    model draft provided by GFD and

    tentative reservation of forest land vide

    letter dated June 6,2011. Revised drafthanded over on August 3,2011.

    Finalisation is in process

    Concession Agreement draft is under

    finalisation with GFD. The draft will

    then be sent for approval to finance

    dept for finalisation of Commercial

    terms i.e. Royalty rate / security deposit

    . Upon finalisation of commercial terms

    the agreement will be executed

    Completed. PROCON Engineers

    appointed on Jun 30,2010

    Completed . October 2010

    Completed . Dec.2010

    Completed .Bid isued to Greenesol, IJT

    , Cethar vessels, Thermax,

    GBENMASS & Cheema Boilers

    Limited on March 3, 2011

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

    IJT CETHAR GB Engg Cheema

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    78/85

    IJT, CETHAR , GB Engg., Cheema

    Boilers have submitted offer. Thermax

    and Areva are also being considered.

    Revised commercial offer from IJT

    and Cethar received. Negotiation with

    IJT, Cethar and GB in progress

    Provided land is allocated

    PIM and Model is ready. Waiting forfinalisation of EPC Cost

    After finalisation of EPC Cost

    Sanction subject to allotment of land

    After allotment of land

    Gujarat Forest Dept asked to revisedthe Draft concession agreement on July

    16,2011.Revised draft again handed

    over on August 3,2011

    Comments on Draft PPA submitted to

    GUVNLon 27 May 2011 and

    thereafter on June 23,2011 for their

    consideration. Draft PPA under

    process for approval with GUVNL

    board.

    After allotment of land

    ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat

    REMARKS

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    79/85

    ,2011.

    Kachchh

    n

    ater abstraction from CGWB.

    ncession Agreement under finalisation,

    Crs/MW, Cost optimisation and

    Dept for valuation

    ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project

    PROJECT TEAM: Anand Nair, Akshay Sharma

    Date: 03.08.2011

    TC : Target Completion

    AC/EC : Actual/Expected Completion

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    80/85

    Sr NoMAJOR

    ACTIVITY/MILESTONEREMARK

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL

    A LAND

    1 Identif ication of

    Disctrict/Location

    436MW 436MW - 80 MW 516 MW

    2 Visit for site selection 60MW 180 MW 138MW 378 MW3 Finalization of Site 60MW 180 MW 138MW 378 MW

    4 Submission of Proposal for Land

    Acquisition

    12 MW 12MW 36MW 44MW 144MW 138MW 378 MW Negotiations are under way for

    buying land for 48 MW

    5 Deposit of Money for Land 12MW 12MW 36MW 44MW 144MW 240 MW

    6 Signing of Lease Deed if required Land is being bought outright

    B DPR for Generation Project

    1 Selection Technical Consultant

    (TC) & Issue of LOI - TC

    516MW 516MW 516MW Dalkia Energy Services is

    technical Consultant: ProjectDevelopment Agreement has

    been signed between PTC

    Bermaco and Dalkia India.

    MoU signed between IREL,

    2 Site Visit, Kick off meeting with

    TC

    84 MW 84 MW 156 MW 138MW 378 MW

    3 Submission of Pre-feasiblity 60MW 60MW 180 MW 138MW 378 MW

    4 Submission of Data to TC 60MW 60MW 180 MW 138MW 378 MW

    5 Preliminary Plant layout and 60MW 60MW 180 MW 138MW 378 MW7 Presentation on Draft DPR 60MW 60MW 180 MW 132MW 360 MW

    8 Finalization of Layout 60MW 60MW 180 MW 132MW 360 MW

    9 Finalization of DPR 60MW 60MW 180 MW 132MW 360 MW

    C Environmental and R & R

    1 Selection of Environmental

    Consultant & Issue of LOI

    84 MW 156MW 240 MW

    All Numbers Repesent MW out of a total target of 516 MW by 2014

    TIME FRAME

    Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)

    COD as per IM: March-13

    Expected Target COD: March-13

    ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONEREMARK

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL

    TIME FRAME

    Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)

    2 Submission of Form I , MoE&F 84 MW 156MW 240 MW

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    81/85

    3 Start of EIA 84 MW 156MW 240 MW

    4 TOR Approval 84 MW 156MW 240 MW

    5 Additional studies as per

    approved ToR

    84 MW 156MW 240 MW

    6 Presentation on draft EIA report 84 MW 156MW 240 MW

    7 Submission of draft EIA report 84 MW 156MW 240 MW

    8 Final EIA Report 84 MW 156MW 240 MW

    9 Submission of EIA report to State

    Agency

    84 MW 156MW 240 MW

    10 Public Hearing 84 MW 156MW 240 MW

    11 Filing of application for

    Environment Clearance

    84 MW 156MW 240 MW

    12 Clearance from MOE&F 84 MW 156MW 240 MW

    D Site Related Investigations 84 MW 156MW 240 MW

    E Statutory Clearances /

    Approvals

    84 MW 156MW 240 MW

    F Infrastructure

    1 Finalization of TransportConsultant for equipments

    84 MW 156MW 240 MW

    2 Finalization of Transport Route 84 MW 156MW 240 MW

    3 Application for Water Linkage /

    allocation

    84 MW 156MW 240 MW

    4 Execution of Water Supply

    Agreement

    84 MW 156MW 240 MW

    5 Application for Construction

    Water/allocation

    84 MW 156MW 240 MW

    6 Application for Construction

    Power

    84 MW 156MW 240 MW

    G Fuel

    1 Finalization of Fuel requirement 240MW 240MW

    2 Fuel Specs from potential Fuel

    suppliers

    240MW 240MW

    3 Finalization of Fuel supplier 516 MW 516MW

    Fuel Supply Company will be a

    60:40 JV between Dalkia and

    Bermaco Energy Systems Ltd.

    ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONEREMARK

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL

    TIME FRAME

    Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)

    4 Submission of MoU/Agreement 516 MW 516MW

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    82/85

    to Fuel Supplier

    5 Execution of MoU/Agreement

    with Fuel Supplier

    240 MW 276MW 516MW

    H Open Access

    1 Filing of application with CTU 240MW 240 MW

    2 Standing Committee meeting 240MW 240 MW

    3 Grant of Long Term Open

    Access

    240MW 240 MW

    4 Execution of BPTA 240MW 240 MW

    I Selection of EPCContractor/Packages

    240MW 276MW 516MW

    1 Selection of Consultant for

    preparing EPC specs & Issue of

    LOI

    240MW 276MW 516MW Dalkia India is the chosen EPC

    consultant

    J Financial closure

    1 Selection of Debt syndication

    agency

    240 MW 240 MW

    2 Financial Structure of the Project 84 MW 84 MW 156 MW 240 MW

    3 Preparation of PIM & Financial

    Model

    84MW 156MW 240 MW

    4 Circulation of PIM to Banks etc 84MW 156MW 240 MW

    5 Obtaining Sanctions from Banks

    etc

    84MW 156MW 240 MW

    6 Execution of Loan Agreement 84MW 156MW 240 MW

    K Agreements & Contracts

    1 Land Acquisition/ LeaseAgreement

    12MW 12MW 84 MW 144MW 240 MW

    2 Execution of Fuel Supply

    Agreemnt

    240MW 276MW 516 MW

    3 Execution of Water Supply

    Agreement

    84MW 156MW 240MW

    4 Execution of Power Purchase

    Agreement

    WILL BE EXECUTED POST Q4 2011-12

    ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project

    Sr NoMAJOR

    ACTIVITY/MILESTONEREMARK

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL

    TIME FRAME

    Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)

    5 Execution of BPTA

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    83/85

    6 Execution of EPC Agreement 84MW 156MW 240 MW

    7 Execution of Loan Agreements 84MW 156MW 240 MW

    Remark

    NOTE I:

    Phase State No of

    Projects MW

    Cumulati

    ve MW

    1 Punjab 7 84

    Bihar 13 156

    PHASE I Total 240 240

    2 Bihar 13 156

    Tamil Nadu 10 120

    PHASE II Total 276 516

    NOTE II:

    Tri-partite MoU signed between Dalkia/ IREL and Bermaco for the development of 1000MW Biomass Based Power Plants in India

    Licenses/ Approvals / Project Development Work is underway to implement additional 484MW

    ACTIVITY PLAN : Indo Nepal Cross Border 400KV D/C Muzaffarpur- Dhalkebar Transmission line

    PROJECT MANAGER : V. L Dua

    DATE : 03.08.2011

    TC : Target Completion

    AC/EC A t l/E t d C l ti

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    84/85

    Sr NoMAJOR

    ACTIVITY/MILESTONEREMARKS

    TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC

    A India Portion-100KMs long

    Project Cost - Rs.1440 Million

    1 Finalization of TSA between

    NEA and CPTC

    Jul-11 Sep-11

    2 Financial closure Dec-11

    3 Bidding & Award of works Mar-12

    4 Commencenment of Construction Mar-12

    B Nepal Portion -45KMs long

    Project Cost - Rs.710 Million

    1 Finalization of TSA between

    NEA and PTCN

    Jul-11 Sep-11

    2 Financial closure Dec-113 Bidding & Award of works Mar-12

    4 Commencenment of Construction Mar-12

    COD as per IM: -

    Expected Target COD: Indian Portion: Mar 14

    Nepal Portion: Mar 14

    TIME FRAME

    Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)

    AC/EC : Actual/Expected Completion

    Q4 (2011-12)

    ACTIVITY PLAN : Indo Nepal Cross Border 400KV D/C Muzaffarpur- Dhalkebar Transmission line

    Brief Status :

    1

    2

    3

    The work of DPR & Route survey completed.

    Approval under Section 68 of EA 2003 received.

    Transmission License CERC has issued Transmission License on 22.03.2011

  • 8/3/2019 IEDCL_Implementation Master File 24-08-2011

    85/85

    4

    5

    6

    Critical Issues :

    1

    Support Required : Nil

    Final signing of ITSA.

    Implementation & Transmission Service Agreement (ITSA) - Final draft of ITSA both for India and Nepal portion

    finalized and initialled on 21.07.2011.For approval U/s 164 of EA 2003, scheme notified in the local dailies in May 2011 and subsequently notified in Govt.

    Signing of PPA with PTC