ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Mobilzation of site by EPC
Contractor
Jan-11 Jan-11
2 Handing over of site to EPCContractor for Soil
Investigation
Jan-11 Jan-11 Sep-11
3 Temporary fencing for land
already acquired
Mar-11 Mar-11
4 Issue of Notice to Proceed to
EPC Contractor
Mar-11 Feb-11
5 Consent to Establish for power
plant
Mar-11 Jun-11
6 Kick of Meeting with EPC
contractor
Mar-11 Apr-11
PROJECT TEAM: Dr. Ashok Harane, Sanjay Joshi
Q4 (2011-12)
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)
DATE :03-08-2011
TC : Target Completion
AC/EC : Actual/Expected Co
COD (as per Investors PIM) : Unit 1 - September 2013; Unit 2 - March 2Expected COD (as per EPC Contract) : Unit 1 - November 2013 ; Unit 2 - May 201
8/3/2019 IEDCL_Implementation Master File 24-08-2011
2/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)
7 Appointment of third party
inspection agency
Mar-11 Apr-11
8 Acquisition of land for Phase I Sep-11
9 Consent to Establish for port Apr-11 Jun-11
10 Finalisation of Insurance
package
Mar-11 Aug-11
8/3/2019 IEDCL_Implementation Master File 24-08-2011
3/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)
11 Provision for construction
Power at one single location
May-11 Aug-11
12 Completion of land acquisition
of 1181 acres
Jun-11 Sep-11
13 Completion of site grading Jun-11 Sep-11
8/3/2019 IEDCL_Implementation Master File 24-08-2011
4/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)
14 Completion of approach road
to site
Jun-11 Dec-11
15 MPH layout drawing finalized May-11 May-11
16 Submit detailed geo-technical
investigation report of MPH
area
Jun-11 Jun-11
17 Test piling completion Sep-11
18 Construction of site office
completion
Dec-11
19 #1 A row of man-power housefoundation pilling completion Dec-11
20 #1 BC row of main-power
house foundation pilling
com letion
Feb-12
21 Submission of Piling drawing
of chimney
Oct-11
22 #2 A row of man-power house
foundation pilling completion
Mar-12
23 #2 BC row of man-powerhouse foundation pilling
completion
Mar-12
8/3/2019 IEDCL_Implementation Master File 24-08-2011
5/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12)
24 Completion of boundary wall Dec-11
25 #1 A row of main-power house
excavation completion
Feb-12
26 #2 Man-power house
foundation piling all
Mar-12
27
#2 A row of main-power house
excavation completion
Mar-12
Brief Status :
Critical Issues :
1 Availability of 30 acres of land for completion of soil investigation for phase I facilities
2 Approval from RBI for opening of project office and bank account to Onshore works and services contractor (Tiejun)Support Required :
1
2
Note : Report to be sent second & fourth Friday of every month
8/3/2019 IEDCL_Implementation Master File 24-08-2011
6/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
REMARK
Some of the critical area of
GIS, Fuel oil handling and sea
water pump house is yet to be
handed over to the contractor
Work completed March 31,
2011
NTP issued on Feb 15, 2011.
Mobilization advances paid
for offshore equipment and
material supply contracts and
offshore services contract
Consent to Establish received
on June 14 2011 for both Port
and Power project
Kick off meeting held from
April 25 to 29 2011 at JinanChina
pletion
014
8/3/2019 IEDCL_Implementation Master File 24-08-2011
7/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
REMARK
Appointed Lloyds Register
Asia as Independent
inspection agency
Total land acquired so far 729
acres. About 30 acres of land
is yet to be acquired for phase
I (excluding ash pond)
It is expected that the balance
land for GIS and Fuel oilhandling system may be
available by end Sept 2011
Consent to Establish received
on June 14 2011 for both Port
and Power project
The proposal is finalised in
consultation with EPCcontractor and bids sent to 10
insurance companies (4 PSUs
and 6 private companies). Pre-
bid meeting with insurance
companies is held on June 8,
2011. Replies to the queries
of insurance companies are
being compiled through
SEPCO III. Insurance
package is likely to be
finalized by Aug 2011
8/3/2019 IEDCL_Implementation Master File 24-08-2011
8/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
REMARK
Location for construction
power finalised in
consultation with Contractor
and TNEB officials.
Drawings have been furnished
to Chief electrical
inspectorrate and awaiting the
approval. As per the rules of
TNEB the Contractor needs
to bring the equipments to the
site before actual
commencement of power
supply. Contractor has
already placed orders on
Transformer and other
equipments.
Power supply may be
available by mid August 2011
It is expected that the entire
land acquisition process may
be completed by end
September 2011
Orders placed for boundary
wall and site grading. Work
commenced
8/3/2019 IEDCL_Implementation Master File 24-08-2011
9/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
REMARK
Permission received from
State PWD for construction of
bridge over Buckingham
canal
Overall plot plan finalized.
Floor plan finalization in
progress
Contractor furnished the soil
investigation report for the
bore holes completed
Test piling commenced on
July 31, 2011 and expected to
be completed by September
30, 2011
Drawing finalized for site
office
8/3/2019 IEDCL_Implementation Master File 24-08-2011
10/85
ACTIVITY PLAN: Phase I - 1200 MW Cuddalore Thermal Power Project
REMARK
Works have alreadycommenced for boundary wall
8/3/2019 IEDCL_Implementation Master File 24-08-2011
11/85
ACTIVITY PLAN: Phase II - 2400 MW Cuddalore Thermal Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Finalization of Technical
Specifications
Sep-11
2 Financial Closure Dec-113 Acquisition of balance land for
phase II
Mar-12
4 Issue of Notice to Proceed to
EPC Contractor
Mar-12
5 Consent to Establish for Phase
II
Mar-12
Brief Status :
Critical Issues :
1 Finalization of coal specifications and Unit configuration
2 Acquisition of balance land for Cooling Towers, GIS
Support Required :
1
2
Note : Report to be sent second & fourth Friday of every month
Expected COD : Unit 1 - March 2015; Unit 2 - July 2015; Unit 3 - Novemb
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
PROJECT TEAM: Dr. Ashok Harane, Sanjay Joshi
DATE :03-08-2011
TC : Target Completion
AC/EC : Actual/Expected Co
COD (as per Investors PIM) : Unit 1 - September 2014; Unit 2 - April 2015; Unit 3 - Sep
8/3/2019 IEDCL_Implementation Master File 24-08-2011
12/85
ACTIVITY PLAN: Phase II - 2400 MW Cuddalore Thermal Power Project
REMARK
Land for BTG area is already
available
Consent to Establish would be
available after entire land is
available
r 2015
mpletion
tember 2015
8/3/2019 IEDCL_Implementation Master File 24-08-2011
13/85
ACTIVITY PLAN : 726 MW ONGC Tripura Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
May'11
Unit 1 + Common TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 % Progress
Overall Project Progress 72.32% 47.12% 81.27% 52.68% 91.16% 56.75% 93.00% 62.00% 97.00% 100.00%Engineering Progress 99.96% 91.62% 99.96% 95.59% 100.00% 97.34% 100.00% 98.00% 100.00% 100.00%
Procurement, Manufacturing
& Su ly Pro ress
97.02% 79.34% 99.61% 85.25% 99.91% 91.78% 100.00% 93.00% 100.00% 100.00%
Civil Construction Progress 98.76% 46.88% 99.65% 56.31% 100.00% 62.41% 100.00% 64.00% 100.00% 100.00%
Erection Progress 23.15% 0.27% 46.06% 3.77% 75.00% 5.00% 96.00% 15.00% 99.00% 100.00%
2 ODC Equipments Supply
Schedule (at Site)
GT Apr-11 Jun-11
GTG Apr-11 Aug-11ST-HP Apr-11 Apr-11
STG Apr-11 Aug-11
HRSG Modules May-11 Aug-11
HRSG Drums Apr-11 Jun-11
HRSG Headers Apr-11 Jun-11
Transformers & Reactors May-11 Aug-11
3 Civil Works
Piling
GTG Foundation
STG FoundationHRSG & Stack Foundation
Power House Foundation
Power House Superstructure Mar-11 Jul-11
PROJECT Manager: Mohd. Zaheen Khan
TIME FRAME
AC/EC : Actual/Expected C
TC : Target Completion
DATE : 03-08-2011
COD as per IM : Unit #1 D
Expected Target COD: Unit # 1:
Q4 (2011-12)
January '11 March'11
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
14/85
ACTIVITY PLAN : 726 MW ONGC Tripura Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
May'11
Unit 1 + Common TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2011-12)
January '11 March'11
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
Raw Water Reservoir Jul-11 Aug-11 Dec-11
Transformer Yard &
Transformer Foundations
May-11 Oct-11
Switchyard May-11 Oct-11
4 Erection Completion
GT Oct-11 Nov-11
GTG Oct-11 Nov-11
ST-HP Oct-11 Nov-11
STG Oct-11 Nov-11
HRSG Modules Sep-11 Nov-11
HRSG Drums Sep-11 Nov-11
HRSG Headers Sep-11 Nov-11
Transformers & Reactors Sep-11 Nov-11
5 Commissioning Date
Unit-I Feb-12
Unit-II Jun-12
Brief Status :
Project Cost - Rs. 34,293 Mn ;Expenditure Incurred Rs. 16,814 Mn
ODC Movement - All 90 ODCs dispatched from BHEL Manufacturing Units to Kolkata, All equipments (ODCs) are at Ashuganj/in transit to Pallatana/ at Site
Critical Issues :
1 Repair of Bypasses in the Bangladesh & Indian Section
2 Progress of civil works and inadequate supervision by BHEL
3 Movement of all equipment ODCs
Support Required :
1 BHEL to closely monitor progress of civil works and structure fabrication
2 BHEL to deploy additonal and more experienced manpower at site
Note : Report to be sent second & fourth Friday of every month
- GT#1 successfully reached site
- GT#2 enroute to site, currently in Bangladesh
- 26 ODC consignment, comprising 15 modules & 11 equipments have reached project site through Bangladesh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
15/85
ACTIVITY PLAN : 726 MW ONGC Tripura Power Project
REMARKS
Bypasses in
Bangladesh & India section
under repair
April 2011 to oct'11
Complete
Complete
Complete
Complete
Complete
ompletion
c'11, Unit#2 Mar'12Feb'12, Unit # 2: June'1
8/3/2019 IEDCL_Implementation Master File 24-08-2011
16/85
ACTIVITY PLAN : 726 MW ONGC Tripura Power Project
REMARKS
1st compartment-Aug 11
2nd compartment-Dec 11
8/3/2019 IEDCL_Implementation Master File 24-08-2011
17/85
ACTIVITY PLAN : 363 MW ONGC Tripura Power Project
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Land
2 Finalization of Gas Sales &
Purchase Agreement
Dec-11
3 Financial Closure Jan-12
4 Issue of Notice to Proceed to
EPC Contractor
Mar-12
5 Additional Clearances Dec-11
Brief Status :
Critical Issues :
1 Execution of Gas Supply & Purchase Agreement (GSPA)
2 Financial Closure & issue of NTP to EPC Contractor by March'12
Support Required :
1
2
Note : Report to be sent second & fourth Friday of every month
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
PROJECT Manager: Mohd. Zaheen Khan
DATE :03-08-2011
TC : Target Completion
AC/EC : Actual/Expected Co
COD (as
8/3/2019 IEDCL_Implementation Master File 24-08-2011
18/85
ACTIVITY PLAN : 363 MW ONGC Tripura Power Project
REMARK
Land for Phase II
under possession
Expected COD - Dec'13
mpletion
er Investors PIM) : June'13
ACTIVITY PLAN 400 KV D/C P l t B i T i i Li A i t d ith 726 6 (2X363 3) MW P ll t CCGT P P j t f
8/3/2019 IEDCL_Implementation Master File 24-08-2011
19/85
ACTIVITY PLAN : 400 KV D/C Palatana- Bongaigaon Transmission Line Associated with 726.6 (2X363.3) MW Pallatana CCGT Power Project of
OTPC
TC : Target Completion
AC/EC : Actual/Expected Completion
Sr No MAJOR ACTIVITY/MILESTONE REMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
A
TC
AC/EC
1 Survey -Total Qty 246 Km 246* 246*
2 Foundation -Total Qty 675 Nos 475* 411* 264** 151 113** 22 91** 91
3 Erection -Total Qty 675 Nos 417* 230* 431** 126 319** 31 288** 288
4 Stringing -Total Qty 246Kms 117* 25* 207** 22 196** 11 188** 188
B
TC
AC/EC1 Survey -Total Qty 415 Km 415* 415*
2
Foundation -Total Qty 1125Nos 876* 497* 623** 171 457** 14 443** 150 293** 150
Remaining 143 may spill
over upto May-June
2012
3
Erection -Total Qty 1125Nos 760* 232* 869** 121 772** 17 755** 200 555** 200
Remaining 355 may spill
over upto May-June
2012
4
Stringing -Total Qty 415Kms 213* 14* 372** 13 384** 2 386** 100 286** 100
Remaining 186 may spill
over upto May-June
2012
C
1 Survey -Total Qty 661 Km 661* 661*
2 Foundation -Total Qty 1800 Nos 1351* 908* 887** 322 570** 36 534** 241 293** 150
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-2012) Q3 (2011-12) Q4 (2011-12)
Nov. 2011
Nov. 2011
Critical Section for evaccuation -Palatana(Tripura) to Silcher(Assam) -246 Kms Long
Nov. 2011
Silcher -Bongaigaon Section-415 Kms long
June. 2012
Total - Palatana-Bongaigaon Section-661Kms long
PROJECT MANAGER: V.L.Dua
DATE : 03.08.2011
COD as per IM : Nov 2011
TIME FRAME
Expected Target COD: Nov-2011/Jun-12
ACTIVITY PLAN : 400 KV D/C Palatana Bongaigaon Transmission Line Associated with 726 6 (2X363 3) MW Pallatana CCGT Power Project of
8/3/2019 IEDCL_Implementation Master File 24-08-2011
20/85
ACTIVITY PLAN : 400 KV D/C Palatana- Bongaigaon Transmission Line Associated with 726.6 (2X363.3) MW Pallatana CCGT Power Project of
OTPC
3 Erection -Total Qty 1800 Nos 1177* 462* 1300** 247 1091** 48 1043** 488 555** 200
4 Stringing -Total Qty 661 Kms 330* 39* 579** 35 580** 13 574** 288 286** 100
Project Cost - Rs.1770 Cr.
**Including Backlog
Brief Status
1
2
3
Critical Issues :
1
2
3
4
Support Required : Nil
Contract for Towers, Conductors, Insulators and pile & well foundation work awarded and work at site in progress
Barak river
On detailed survey Open cast foundation changed to Pile foundation. As an alternate, River Crossing (RC) towers at
bank locations on opencast foundations with Truncated RC Tower shall be used.
*Cumulative till Ist March, 2011
Pile foundation at Champawati river completed except for pile capping.
Well foundation work at Brahmaputra river commenced in November 2010.
Brahmputra river
a) Pile Foundation - Construction of coffer dam to facilitate pile casting in the submerged area is in progress. 33 out
of 36 nos. of piles cast and balance activities are in progress.
b) Well Foundation - Well sinking started and reached up to 31 m depth. Further, concreting of the well and sinking
is in progress. For Second well, fabrication of caisson upto 6.4m out of approximately 18m has been completed and
balance caisson is in progress and sinking is schedule to start by October 2011.
Champabati river
The piles already cast abandoned due to failure in integrity test. For fresh casting of piles, boring commenced. 8 out
of 16 piles have been cast.
Forest Clearance
i) Tripura - Second stage forest clearance for starting the work, obtained on 17.08.2010.
ii) Assam and Meghalaya - For second stage forest clearance, MoEF has sought further clarifications vide their letter
dtd 13.04.2011. NETC on 28.04.2011 requested MoP for intervention for early second stage MoEF clearance.
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
21/85
ACTIVITY PLAN 63 MW SV Power Project Chattisgarh
Sr No MAJORACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Engineering
2 Ordering
3 Manufacturing
4 Supply
5 Erection
a Boiler Drum
b Economiser
c Refractory furnanceInsulations
d Deaerator
e ID Fan
f SA fan
g PA fan
h Steam Turbine Generator
Alignment
i Condensor
j Condensate piping
k ESP Structure
l ESP Emitting and collectingframe
m ESP hopper
n ESP inlet hood
o Fuel Bunker Chute to
Furnance
q Coal Handling plant Erection
r Ash Handling plant Erection
Ash Silo
Pipe Rack
Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
PROJECT MANAGER : Pradeep Aggarwal
DATE : 03.08.2011
TC : Target Completion
AC/EC : Actual/Expected Comp
COD as per IM : March-11
Expected Target COD: Sept-11
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012)
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
22/85
j g
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012)
Equipment
s Fuel Oil System
t Fire Operating system
u Chimneyv Cooling Tower
w Weigh Bridge
x CW and ACW system
Chlorination system
y WTP and ETP
z LP Piping
aa Compressed Air System
ab AC and Vent
ac 132 kv transmission line &
LILO
ad Pooling substationae Geneartor, Stationa and Unit
Auxilliary Transformers
af 6.6 kv HT s/g and LT s/g
ag Plant earthing system
ah Plant ligting system
ak Cable trays
al Power cables
6 Testin and commissionin
a Coal Washery unit
b Refractory dry out
c Boiler Light up
d Alkali Boil out
e Steam Blowing 7-May 25-Aug
f Synchronisation 15-May 30-Aug
g Load Trials 18-May 7-Sep
h Performance acceptance test 25-May 10-Sep
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
23/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012)
i Performance Guarantee Test 31-May 17-Sep
M-BoP and E-BoP
a Coal Handling plant
b Ash Handling plantc Raw water pump house and
Chlorination sys.
d 132 kv line charging
e Pooling substation
f GT Testing and other
electrical testings
CoD 20-Sep
Unit commissioning 31-May
Brief Status :
1
23
4
5
6
7
8
Critical Issues :
1
Support Required : Nil
Long term coal linkage for washery, GUVNL bid opened - under discussion
O&M team of 30 people from Tata Power is working at site.
Erection work completed and no load trail runs completed
As on date approx. 350 Cr exp.done out of total now envisaged cost of Rs 375 Cr (against earlier estimate of 360 crore
increased mainly due to IDC and some misc works.
Road work, Drains, coal storage area and ash dyke works are almost complete.
9000 MT coal and 25 KL of LDO reached at site, around 20000 MT of coal being procured through e -auction and rea
Coal washery of 2.5 MTPA has been commissioned and around 9000 MT coal washed.
132 kv switchyard and Pooling station and further connection to CSEB is completeReservoir filled , all supplies completed for M-BoP
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
24/85
REMARKS
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
letion
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
25/85
REMARKS
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
CompletedCompleted
Completed
Completed
Completed
Completed
Completed
Commissioned and9000 MT Coal washed
Completed
Completed with oil.
Completed
Transmission line has
already been charged
ACTIVITY PLAN - 63 MW SV Power Project - Chattisgarh
8/3/2019 IEDCL_Implementation Master File 24-08-2011
26/85
REMARKS
Completed
CompletedCompleted
Commissioned
Commissioned
Tested, incl control
room
). The cost has been
ching at site shortly.
ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa
8/3/2019 IEDCL_Implementation Master File 24-08-2011
27/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 NTP Sep/09
2 Release of Civil drawings Mar/10
3 Start of civil works Jul/10
4 ESP foundation Jan/11
5 Start of Boiler structural
erection
Feb/11 Jun/11
a Start of TG deck foundations
concreting
Jan/11 Apr/11
b Start of structural erection of PHB Mar/11 Jul/11
c ESP Erection commencement Jul/11 Sep/11
d Boiler drum lifting Nov/11 Jan/12
e TG hall readiness for EoT erection Jul/11 Jan/12
f TG deck readiness Aug/11 Nov/11
g TG erection start Sep/11 Feb/12
h Condenser erection start Sep/11 Feb/12
i Boiler Hydro test Mar/12
j Condenser Hydro test
k Readiness of FD/ID fans &
Ducting
l Fuel oil requirement
m Air leak test of furnance & Aux.
n Turbine box up
TIME FRAME (Phase I)
PROJECT MANAGER : Pradeep Aggarwal
DATE : 03.08.2011
TC : Target Completio
AC/EC : Actual/Expec
COD as per IM: Phase1 Sept-12 , PExpected Target COD: Phase I: Mar-13,
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa
8/3/2019 IEDCL_Implementation Master File 24-08-2011
28/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME (Phase I)
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
o Oil flusing
q Alakali Boil out
r Readiness of ESP incl. insulation
Turbine on Barring gear
Boiler light up
Readiness of Mils and Aux. & coal
piping
s Steam blowing
t Safety valve Floating
u Synchronisation
v Coal Firing
w Performance acceptance Test
CoD
Unit -I
Brief Status :
Phase-I
1
2
3
4
5
Phase-II
1
2
Critical Issues :
1
2
3
Support Required : Nil
Soil investigations in progress and excavation work at boiler area started.
FSA need to be done at the earliest for coal and agreement for Water linkage is also required to be in place.
Power evacuation with OTPCL for around 400 MW need to be firm up. BPTA for 560 MW with PGCIL is in
The acquisition of balance land
Land- 700+ Acre land out of 804 acre has been acquired. Balance is in advance stage of acquisition.
Major Engineering completed/EPC awarded/Manufacturing of BTG in progress
Clearances- Mostly in place i.e. MoEF/AAI/SPCB/Arche.SoI/Mega power status/Min of Rail
Coal Linkage- LoA issued for 1000 MW by Min. of coal. BG submitted for execution of FSA.Water linkage o
Foundation works of Boiler and ESP completed for Phase-I, excavation for coal bunker,TG Building and chim
EPC contract awarded , Common structures work of phase-I and Phase-II planned and started
ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa
8/3/2019 IEDCL_Implementation Master File 24-08-2011
29/85
REMARKS
Completed
Completed
Started
Completed
Boiler Erection work
startedRaft completed, TG
deck level yet to reach
Started
Foundation work almost
completed
Manufacturing
completed. Yet to be
inspected and reach at
site.
1-Jun-12
27-May-12
17-May-12
1-Nov-12
1-Sep-12
n
ted Completion
hase II June-13
Phase II: Dec-13
ACTIVITY PLAN - 1050 MW Nilanchal Thermal Power Project - Orissa
8/3/2019 IEDCL_Implementation Master File 24-08-2011
30/85
REMARKS
7-Jan-13
7-Feb-13
7-Dec-12
6-Jan-12
1-Feb-13
18-Sep-12
30-Jan-13
30-Jan-13
28-Feb-13
15-Mar-13
20-Mar-13
31-Mar-13
place
btained for the project
ney completed
ACTION PLAN:100 MW Sorang Hydro Power Project
8/3/2019 IEDCL_Implementation Master File 24-08-2011
31/85
AC/EC : Actual/Expected Completion
Sr No MAJOR ACTIVITY/ MILESTONE TIME FRAME REMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Civil works NCC
a Infrastructure works - - - - - - - - - - Completed
b Trenchweir, Desilting Tank &
Intakei Excavation - - - - - - - - - - Completed
ii Concreting - - Jun/11 Jun/11 - - - - - - Completed
c Head Race Tunnel
i Excavation - - - - - - - - - - Completed
ii Concreting/lining length - - - - - - Nov/11 - - Jan/12 700 m invert co
completed
60 m lining com
d Surge shaft
i Pilot Height - - - - - - - - - - Completed
ii Widening height Mar/11 Mar/11 - - - - - - - - Completed
e Vertical shaft
i Pilot Height - - - - - - - - - - Completed
ii Widening height/ concreting - - - - Aug/11 - - - - - Balance 20%
f Penstock & Hydraluic Gates
i Fabrication work - - - - - - Dec/11 - - Balance 10%
ii Erection works Dec/11 Feb-12 Balance 90%
g Power House and MAT
i Excavation - - - - - - - - - - Completed
ii Concreting - - - - - - Nov/11 - - - Balance 10%
h Tail race tunnel
i Excavation length - - - - - - - - - - Completed
ii Lining in RM - - May/11 Apr/11 - - - - - - Completed
i Suppy of E & M and Transmission
Items
Voith Siemens
i EOT Crane - - - - - - - - - - Completed
ii Turbine units - - - - - - - - - - Completed
Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012)
PROJECT MANAGER : N.D. Arora, Pradeep Aggarwal
TC : Target Completion
DATE : 03.08.2011
COD as per IM: Unit # 1: Dec-11, Unit # 2: Dec-11Expected Target COD: Unit # 1: Feb'12, Unit # 2: Mar'12
ACTION PLAN:100 MW Sorang Hydro Power Project
8/3/2019 IEDCL_Implementation Master File 24-08-2011
32/85
Sr No MAJOR ACTIVITY/ MILESTONE TIME FRAME REMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/ECQ2 (2011-12) Q3 (2011-12) Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012)
vi Mechanical and Electrical BoP - - - - - - Nov/11 - - - Balance 20%
vii Transmission tower and conductors - - June-11 - - - - Nov-11 - - Supply commen
foundation start
Conductors reac
j Erection
i EOT Crane - - - - - - - - - - Completed
ii Turbine and its Auxilliaries - - - - - - Dec/11 - - - Balance 40%iii Generator and its auxillaries - - - - - - Dec/11 - - - Balance 75% w
iv Transformers - - June-11 - - - - Oct-11 - - Balance 40% w
v Switchyard GIS - - - - Sep/11 - - Dec-11 - - Balance 100% w
vi XLPE cables & other items - - - - - - Dec/11 - - - Balance 100% w
vii Transmission tower and conductors - - - - - - Dec/11 - - Jan-12 Erection to start
k Testing & Commissioning
i Unit -I - - - - - - - - Feb/12 -
ii Unit-II - - - - - - - - Mar/12 -
Brief Status :
1
2
3
4
5
Critical Issues :
1
2
Support Required :
Civil : Excavation of all underground structures completed including HRT. The concreting works are in progress
E&M : EoT crane erected and third stage embedments of Unit-I and Unit-II completed.
Transmission: The work order for 10 towers provided to M/s RRV, Hyderabad. The erection expected by Jan-12
Project Cost: Rs 7560 Mn, Incurred Rs 5420 million (Till June 2011) . The physical progress is around 76%
Project likely to be commissioned by March-12
Erection of Penstock
Proper Site Management
Nil
ACTIVITY PLAN - 45 MW Tirap hydro power project
8/3/2019 IEDCL_Implementation Master File 24-08-2011
33/85
Sr No MAJOR
ACTIVITY/MILESTONE
REMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Detailed survey and
investigations
- - - - - - - - - - Completed
2 Detailed Project Report
i Finalization - - - - - - - - - - Completed
ii Approval Jun-11 Jul-11 Techno-economic clearance
obtained from State Govt.
3 EIA/EMP studies
i EIA/EMP studies report as per
approved ToR of MoEF
- - Jun-11 - Jul-11 - - - - Three seasons studies
completed, report to be
submitted to SPCB onclearence from Forest Dept.
ii Environment Clearance Sep-11 Dec-11
4 Preparation of EPC bid
documents-Civil, Hydro
Mechnical and E&M works
Mar-11 - - - - - - - - - EPC bidding documents are
ready. Bid process would start
after status on land acuisition
is cleared.
5 Selection of EPC Contractor
and award of EPC works for
different Packages
- - - - - - Dec-11 Mar-12 - -
Expected as per IM : Unit # 1: Feb'15, Unit # 2:
PROJECT Team : Mr. N.D.Arora, Neeraj Jain
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
COD as per IM: Unit # 1: March-15, Unit # 2: March-
DATE: 03.08.2011
TC : Target Completion
AC/EC : Actual/Expected Completion
ACTIVITY PLAN - 45 MW Tirap hydro power project
8/3/2019 IEDCL_Implementation Master File 24-08-2011
34/85
Sr No MAJOR
ACTIVITY/MILESTONE
REMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
6 Financial closure - - - - - - - - Mar-12 - Through IFIN
7 Agreements & Contracts
i Land Acquisition/ Lease
Agreement
- - - - - - Dec-11 - - - Joint Land Survey Completed,
acquisition process to be
commenced by DC
Changlang.Land owners
consent is to be taken.
ii Execution of Power Purchase - - - - - - - - - - Merchant power envisaged
iii Execution of BPTA - - - - Sep-11 - - - - -
iv Execution of EPC Agreement - - - - - - Dec-11 - - -
v Execution of Loan Agreements - - - - - - - - Mar-12 -
Brief Status :
1
2
3
4
Critical Issues :
1
Support Required :
EPC Bid documents for Civil & HM and E&M works have been finalised.
Three seasons studies completed. EIA report is under compilation incorporating land details.To be submitted to CPCB for public
hearing after clearance from State Forest Department.
TEC approved by State Govt.
The joint land survey completed with GoAP officials, meeting held with DC Changlang, public hearing to be called by D.C for
consent of land owner
Land Acquisition
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
35/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
A LAND
1 Visit for site selection Oct-10
2 Finalization of Site Oct-10
3 Demand Note by Land
Allotment A ency
4 Deposit of Money for Land
Acquisition
5 Signing of Lease Deed Mar-12
B DPR for Generation Project
1 Selection TechnicalConsultant (TC) & Issue of
LOI - TC
Oct-10
2 Site Visit, Kick off meeting
with TC
Oct-10
3 Submission of Pre-feasiblity
report
Dec-10
4 Submission of Data to TC Nov-10
IMD Data
Water Analysis
PROJECT TEAM : Feby Koshy, Akhil, Zaheen
DATE : 03.08.20
TC : Target Co
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
AC/EC : Actual/
COD as per IM:
Expected Target
May-11 Dec-11
Unit # 2: Mar-16, Unit # 3: Sep - 16, Unit # 4 Mar-17, Unit # 5 Se
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
36/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
Soil Data Apr-11 May-11
Contour Data
Topo Sheets
Other Maps
Any other Data / AMSL
5 Preliminary Plant layout and
preliminary design
Dec-10
6 Submission of Draft DPR Mar-11 May-11
7 Presentation on Draft DPR Mar-11 May-11
8 Finalization of Layout Mar-11 Nov-11
9 Finalization of DPR Apr-11 Nov-11
C Environmental and R&R
1 Selection of Environmental
Consultant & Issue of LOI
Oct-10
2 Submission of Form I ,
MoE&F
Dec-10
3 Start of EIA Mar-11 Mar-11
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
37/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
4 TOR Approval Jun-11 Oct-11
5 Additional studies as per
approved ToR
6 Presentation on draft EIA
report
7 Submission of draft EIA
report
8 Final EIA Report
9 Submission of EIA report to
State A ency
10 Public Hearing
11 Filing of application forEnvironment Clearance
12 Clearance from MOE&F
D Site Related Investigations
1 Selection of Topo Survey
Consultant & issue LOI
2 Selection of Geotechnical
Consultant & issue LOI
Feb-11
3 Submission of Topo Survey
Report
4 Submission of Geotechnical
Investigation Report
Apr-11 May-11
5 Any other project specific
studies
E Statutory Clearances /
A rovals
1 Filing for NoC from AAI for
stack height
May-11 Aug-11
2 Receipt of NoC from AAI Nov-11
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
38/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
3 Filing of Application for
Mega Power Status4 Recept of Mega Status
5 Filing for CTE
6 Reciept of CTE
F Infrastructure
1 Finalization of Transport
Consultant for equipments
2 Finalization of Transport
Route
3 Application for Water
Linkage / allocation
Oct-11
4 Execution of Water Supply
Agreement
5 Application for Construction
Water/allocation
6 Application for Construction
Power
G Fuel
1 Finalization of Fuel
re uirement
Oct-11
2 Fuel Specs from potential
Fuel suppliers
3 Finalization of Fuel supplier
4 Submission of
MoU/Agreement to Fuel
Su lier
5 Execution of MoU/Agreement
with Fuel Supplier
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
39/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
H Open Access
1 Filing of application withCTU
2 Standing Committee meeting
3 Grant of Long Term Open
Access
4 Execution of BPTA
I Selection of EPC
Contractor/Packages
1 Selection of Consultant for
preparing EPC specs & Issueof LOI
Oct-11
2 Finalization of bid
specifications for EPC
Contractor
Nov-11
3 Finalization of bid document Dec-11
4 Issue of bids Jan-12
5 Pre-bid conference
6 Last date for bids submission
7 Bid evaluation & selection8 Issue of Notice to Proceed
9 Execution of EPC Agreement
10 Selection of Consultant for
PMC & Issue of LOI
J Financial closure
1 Appointment of Debt
syndication agency
Dec-11
2 Preparation of PIM &
Financial Model
Feb-12
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
MAJOR
8/3/2019 IEDCL_Implementation Master File 24-08-2011
40/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
3 Circulation of PIM to Banks
etc
Feb-12
4 Obtaining Sanctions from
Banks etc
6 Execution of Loan Agreement Mar-12
K Agreements & Contracts
1 Land Acquisition/ Lease
Agreement
Apr-11 Mar-12
2 Execution of Fuel Supply
Agreemnt
3 Execution of Water SupplyAgreement
4 Execution of Power Purchase
Agreement
5 Execution of BPTA
6 Execution of EPC Agreement
7 Execution of Loan
Agreements
Status:
Critical Issues:
Action Plan:
1) Power Plant TOR application taken up by MoE&F in April 2011 to be re-considered by MoEF after SEZ TOR is approved ; SEZ To
3) Draft DPR finalized, Geo-Tech investigations completed, EIA - part base line monitoring completed
1) Being an integrated project, the delay in SEZ ToR approval is delaying Power Plant ToR clearance
1) IMICL & IL&FS Ecosmart to expedite SEZ ToR approval
2) MoU for lease of 1500 acres of land signed, part advance released
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
41/85
REMARKS
11
pletion
Expected Completion
Land to be leased out to
NPCL by ALPL/SPPL
COD: Unit # 1: Sep- 15,
MoU with ALPL/SPPL done
for 1500 acres land, Part
advance Rs. 10 Cr paid
pt -17, Unit # 6 : Mar-18
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
8/3/2019 IEDCL_Implementation Master File 24-08-2011
42/85
REMARKS
Geo-Tech Investigations
Completedcompleted
completed
Obtained from Survey of
India
Baseline monitoring for EIA
completed in June 2011 for
Ambient Air Quality
Monitoring, Water Quality
Monitoring (Surface and
Groundwater), Noise
Environment Monitoring,
Soil Quality, Marine Water
and Sediment Quality
Monitoring is under progress
To be finalized based on ToR
approval & close to financialclosure
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
43/85
REMARKS
Will reapply once ToR for
SEZ is a roved
Available
completed
Available
completed
Enquiries initiated for Area
Drainage & hydrological
study
Certified data received from
SoI
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
44/85
REMARKS
Apply after SEZ ToR is
approved
Apply for domestic linkage
after ToR a roval
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
45/85
REMARKS
Apply after 50% Power Tie-
u
ACTIVITY PLAN - 4000 (6*660) MW Coal Based TPP - Nana Layja, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
46/85
REMARKS
MoU already executed
filed on June 8, 2011 by
ACTIVITY PLAN: 274.4 MW Wind Power Project
PROJECT TEAM: Anand Nair, Akshay Sharma
Date : 03 08 2011
8/3/2019 IEDCL_Implementation Master File 24-08-2011
47/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC TC AC TC AC TC AC TC AC TOTAL
1 Sub Lease in favour of ILFS 74.4 MW 74.4 MW
2 SLEC/ Registeration of Land in
favour of EIL Companies Done
74.4 MW 74.4 MW 200.8 MW 275.2 MW
3 Construction of Roads &
Platforms
74.4 MW 56 MW 3.2 MW 60.0MW 140.8 MW 275.2 MW
4 Foundation Casting Activities 50.4 MW 40.8 MW 24 MW 16.8 MW 60.0MW 140.8 MW 275.2 MW
5 Arrival of WECs 60 MW 60 MW 14.4 MW 14.4 MW 200.8 MW 275.2 MW
6 Erection Of Towers 10.4MW 10.4 MW 16 MW 11.2 MW 48 MW 105.6 MW 143.2 MW 275.2 MW
7 Erection Of WECs 10.4MW 10.4 MW 16 MW 10.4 MW 48 MW 57.6 MW 143.2 MW 275.2 MW
8 Construction of Internal OH
33KV line
74.4 MW 50.4 MW 157.6 MW 42.4 MW 275.2 MW
9 Construction of Evacuation Sub-
Station
50.4 MW 50.4 MW 200.8 MW 251.2 MW
TC : Target Completi
AC/EC : Actual/Expe
TIME FRAME
Date : 03.08.2011
All Numbers Repesent MW out of a total target of 1004 MW by 2015
Expected Target CO
COD as per I
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
ACTIVITY PLAN: 274.4 MW Wind Power Project
Sr NoMAJOR
ACTIVITY/MILESTONETIME FRAME
8/3/2019 IEDCL_Implementation Master File 24-08-2011
48/85
Sr NoACTIVITY/MILESTONE
TC AC TC AC TC AC TC AC TC AC TOTAL
Q4 (2010-11) Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
10 Construction of External EHV 2 50.4 MW 50.4 MW 200.8 MW 251.2 MW
11 Execution of PPA 26.4 MW 10.4 MW 48 MW 24 MW 176.8 MW 275.2 MW
12 Commissioning of the WECs 14.4 MW 74MW 0.8 MW 200.8 MW 275.2 MW
Status:
Critical Issue:
Action Plan:
2) Deferred Equity Structure currently being sought with various banks such as First Gulf Bank, Barclays, HSBC etc.
1) 74.4 MW is under construction in three states
2) Order has been placed on July 7th for the 200 MW:
- IFIN has been mandated to source debt funds at an effective interest cost of 11.5%
1) Total Equity Requirement of Rs. 285.9 crores (Debt : Equity = 75 : 25)
1) Equity infusion will be funded through a mix of deferred equity structure and funds received from IEDCL divestment
ACTIVITY PLAN: 274.4 MW Wind Power Project
8/3/2019 IEDCL_Implementation Master File 24-08-2011
49/85
REMARKS
M.P. does not
require an
evacuation sub
station to be
constructed
on
ted Completion
Unit # 2: Mar'12
: Unit # 1: Aug'11
Unit # 2: Mar'12
: Unit # 1: Sept'11
ACTIVITY PLAN: 274.4 MW Wind Power Project
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
50/85
M.P. does not
require an external
EHV 2 line
ACTIVITY PLAN: Wind Power Project
Fincial Year State (Project Location) MW COD
8/3/2019 IEDCL_Implementation Master File 24-08-2011
51/85
FY 2011-12 Rajasthan (Sipla) 26.4 Jun11
M.P. (Ratedi) 24 July11
T.N. (V'kullum) 24 Aug11
Karnataka 100 Mar12
A.P 50.4 Mar12
Gujarat (Lalpur) 50.4 Mar12
Total 275.2
FY 2012-13 Vkulum/ TN 50.4 Sep/12
Banswara3/Rajasthan 50.4 Sep/12
Lalpur/ Gujarat 50.4 Sep/12
Tungabhadra/Andhra Pradesh 50.4 Mar/13
Banswara4/Rajasthan 50.4 Mar/13
Tungabhadra/Andhra Pradesh 49.6 Mar/13
Tadas/ Karnataka 50.4 Mar/13
Total 352.0
FY 2012-13 Lalpur/ Gujarat 50.4 Sep/13
Chandwad/ Maharashtra 50.4 Sep/13
Chandwad/ Maharashtra 24.8 Sep/13
Rajgarh/ Rajasthan 50.4 Mar/14
Rajgarh/ Rajasthan 49.6 Mar/14
Tadas/Karnataka 50.4 Mar/14
Gadag N/ Karnataka 50.4 Mar/14
Total 326.4
ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited
PROJECT MANAGER: Mr. Punyatma Dwivedi, Pavas Agarwal
DATE 03 08 201
8/3/2019 IEDCL_Implementation Master File 24-08-2011
52/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 EPC COGEN
1.1 Boiler
1.1.1 Steam Drum Lifting Completed1.1.2 Hydro Test Completed
1.1.3 Refractory Dry Out Completed
1.1.4 Alkali Boil Out Completed
1.1.5 Steam Blowing Completed
1.1.6 Safety valve floating Completed
1.2 Turbo Generator
1.2.1 Lube Oil Flushing Completed
1.2.2 TG Alignment & Grouting Completed
1.2.3 Turbine on barring gear Completed
1.2.4 Turbine Rolling on steam Completed
1.2.5 Start of synchronization Trials Completed1.3 Water Treatment Planty
1.3.1 Clarifier Completed
1.3.2 DM Plant Completed
1.3.3 Balance Civil Works Completed
1.4 Cooling Tower
1.4.1 Civil Works Completed
1.4.2 Erection & Commissioning Completed
1.5 RCC Chimney
1.5.1 Raft Foundation Completed
1.5.2 100m Cell Casting Completed
1.5.3 Refractory Lining Works Completed1.5.4 Commissioning Completed
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
DATE : 03.08.201
TC : Target Com
AC/EC : Actual/E
Expected Target
Q4 (2011-12)
COD as per IM: J
ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited
Sr NoMAJOR
ACTIVITY/MILESTONETIME FRAME
8/3/2019 IEDCL_Implementation Master File 24-08-2011
53/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
1.6 Fuel Handling System
1.6.1 Bagasse Handling System Completed
1.6.2 Coal Handling System Completed
1.7 Under Ground Service Reservoir
1.7.1 UGSR 1st compartment Completed
1.7.2 UGSR 2nd compartment Completed
1.7.3 Raw Water Pump House Completed
2 Power Evacuation System
2.1 Stub setting and Foundation Completed
2.2 Tower Erection Completed
2.3 Stringing Completed
2.4 Plant Sub station Completed
2.5 Jaysingpur Substation Completed
3 Raw Water Pumping System
3.1 Pipeline Completed
3.2 Jackwell 1-Jan-11 30-Sep-11
3.3 11 kv Line 1-Jan-11 30-Sep-11
4 HSF Modification Works
4.1 Modifications in Boiling House Completed
4.2 Modifications in Milling Section Completed
Brief Status :
Critical Issues :
Support Required :
Transmission of Power using 132 KV line is expected by 1st Week of August 2011
ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited
1
8/3/2019 IEDCL_Implementation Master File 24-08-2011
54/85
REMARKS
Misc Works such as
Internal Road, Drains,
Compund Wall and other
Finishing Works are in
Progress
1
letion
xpected Completion
OD : August'11
an'11
ACTIVITY PLAN : 36 MW Bagasse Based Cogeneration Project of Urjankur Shree Datta Power Company Limited
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
55/85
Only 2 Nos of Mill Drive
replacement is balance,
which is bin taken u
Water Supply to Cogen
Plant has been arranged
through HSF's existing
Pipeline
Approval for charging the
line is in progress.
8/3/2019 IEDCL_Implementation Master File 24-08-2011
56/85
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
Sr NoMAJOR
ACTIVITY/MILESTONETIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
57/85
1.3.1 Clarifier 1-Jan-11 30-Sep-11
1.3.2 DM Plant 10-Jan-11 30-Sep-11
1.3.3 Balance Civil Works 5-Jan-11 15-Sep-11
1.4 Cooling Tower1.4.1 Civil Works 1-Jan-11 15-Aug-11
1.4.2 Erection & Commissioning 15-Jan-11 15-Oct-11
1.5 RCC Chimney
1.5.1 Raft Foundation Completed
1.5.2 100m Cell Casting Completed
1.5.3 Refractory Lining Works 1-Jan-11 15-Sep-11
1.5.4 Commissioning 1-Jan-11 30-Sep-11
1.6 Fuel Handling System
1.6.1 Bagasse Handling System 1-Jan-11 31-Oct-11
1.6.2 Coal Handling System 15-Jan-11 31-Oct-11
1.7 Under Ground Service
Reservoir
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
Sr NoMAJOR
ACTIVITY/MILESTONETIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
58/85
1.7.1 UGSR 1st compartment 1-Jan-11 22-May-11
1.7.2 UGSR 2nd compartment 5-Jan-11 31-Oct-11
1.7.3 Raw Water Pump House 5-Jan-11 30-Sep-11
2 Power Evacuation System
2.1 Stub setting and Foundation 1-Jan-11 30-Sep-11
2.2 Tower Erection 15-Jan-11 15-Nov-112.3 Stringing 15-Feb-11 15-Dec-11
2.4 Plant Sub station 15-Feb-11 15-Oct-11
2.5 Wathar Substation 15-Feb-11 15-Nov-11
3 Raw Water Pumping System
3.1 Pipeline 1-Jan-11 15-Aug-11
3.2 Jackwell 15-Jan-11 15-Sep-11
3.3 11 kv Line 15-Jan-11 15-Oct-11
4 HSF Modification Works
4.1Modifications in
Boiling House30-Oct-11
30-Oct-11
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
Sr NoMAJOR
ACTIVITY/MILESTONETIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12)
4 2 Modifications in Milling
8/3/2019 IEDCL_Implementation Master File 24-08-2011
59/85
4.2 Modifications in Milling
Section 10/30/2011 30-Oct-11
Brief Status :
Critical Issues :
Support Required :
EPC Contractor WIL is facing severe financial Crunch and payments to Sub-contractors is getting delayed frequently whic
cascading effect on sub-vendors resulting in to delayed work at Site and supply of material.
ACTION PLAN: Matter has been taken up with WIL's top management. There has beenlittle improvement in progress at
Power Evacuation System: RoW Acquition issue due to stiff opposition of the Landowners
Civil & Mechanical Works are in Progress for all the Packages
Action Plan: Alternative plans are being worked out to expedite the progress
Full time Manpower Requirement for Supervision of Transmission Line Works and Civil Works
WTP-WTP work suffered heavily due to commercial issues of Doshion with WIL.
Action Plan- Matters are sorted out by WIL. Things have started improving since this week.
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
8/3/2019 IEDCL_Implementation Master File 24-08-2011
60/85
REMARKS
IBR Hydrotest
completedsuccessfully on
04.06.2011.
letion
oiler) : Oct-11h boiler) : Dec-11
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
REMARKS
Civil work
8/3/2019 IEDCL_Implementation Master File 24-08-2011
61/85
C v wo
completed.
Completed
One Cell will be
completed by 15-
09-2011.
Refractory Lining
in progress.80 %
completed.
Civil Foundation
work in
progress.Structura
l Material rec'd
at site. And
erection started.
Targetted to
complete up to
MBC by 30 Sep.
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
62/85
Leakage test done
on 27.05.2011 to
10.06.2011.Minor
Leakage
observed.Will beattended
completion of II
nd compt..
Work in progress.
Bay location yet
to be handed over
by MSETCL.
Completed
The HSF is
thinking of
alternative plan of
modification and
hence award of
contract under
hold due to
request of HSF.
ACTIVITY PLAN : 44 MW Bagasse Based Cogeneration Project of Urjankur Shree Tatyasaheb Kore Warana Power Company Limited
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
63/85
h is having
Site.
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
PROJECT MANAGER : Pramod Tikkas, Sanjay Joshi
DATE : 03 08 2011
8/3/2019 IEDCL_Implementation Master File 24-08-2011
64/85
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
A LAND
1 Visit for site selection
2 Finalization of Site
3 Submission of Proposal for Land
Acquisition4 Measurement of Land by
District Inspectorate of land
Record (DILR)
5 Submission of Report by DILR
to Dist. Collector Kutch (
Revenue dept)
6 Dist collector recommendationto state level approval committee
for approval of allottment of land
May-11 Aug-11
7 Demand Note by Land Allotment
Agency/ Revenue dept
May-11 Oct-11
Q4 (2011-12)
COD as per IM: Sep
DATE : 03.08.2011
TC : Target Comple
AC/EC : Actual/Exp
Expected Target COD: March
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
65/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q ( 0 )Q ( 0 0 0 ) Q ( 0 0 ) Q ( 0 ) Q3 ( 0 )
8 Deposit of Money for Land
Acquisition
May-11 Oct-11
9 Registration in the name of SPVNBEL
Jun-11 Oct-11
B Preparation of DPR
1 Selection and appointment of
Technical Consultant (TC) for
DPR and EPC Specs
2 Site Visit, Kick off meeting with
3 Submission of Data to TC
IMD Data
Water Analysis
Contour Data
Topo Sheets
Other Maps
Any other Data / AMSL
4 Submission of Draft DPR
5 Finalization of Layout
6 Finalization of DPR
C Appointment of consultant for
Site Related Investigations
1 Selection and appointment of
Biomass assessment consultant(Zenith Energy services,
Hyderabad)
2 Selection and Appointment of
Topo Survey Consultant . R. N.
Consultancy services,
Ahmedabad
3 Selection and Appointment of
Geotechnical Consultant M. K.
Soil Testing Laboratory,Ahmedabad
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
66/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q ( )Q ( ) Q ( ) Q ( ) Q ( )
4 Selection and appointment of
consultant for Ground water
assessment/ LULC studies -Environmental Management
Centre , Mumbai
Feb-11 Feb-11
5 Submission of Biomass
Assessment Report
6 Submission of Topo Survey
Report
7 Submission of Geotechnical
Investigation Report
Jun-11 Jul-11 Jul-11
8 Obtaining data on Ground water
availabil ity from Gujarat waterSupply and Sewarage Board
( GWS&SB)
9 Submission of Sustainability
Assessment study Report on
Ground water assessment and
recharging Possibilities,
Geohydrological Report and
Rainwater harvesting proposal
Apr-11 Apr-11
10 Submission of Report on
Transportation network analysis/
LULC studies, Report on
developing community linkage
programme
Jun-11 Aug-11
D Statutory Clearances /
Approvals
1 Application to GEDA for In-
Principal Approval
2 Receipt of In-principal approval
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
67/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
3 Receipt of Final approval from
GEDA
Jun-11 Oct-11
4 Receipt of distance certificate
from Survey of India
Mar-11 Mar-11
5 Filing for NoC from AAI for
stack height
Apr-11 Apr-11
6 Receipt of NoC from AAI Jun-11 Oct-11
7 Receipt of NOC from Industries
Dept
Mar-11 Mar-11
8 Receipt of NOC from Forest
Dept
Apr-11 Apr-11
9 Applied for Geology and Mining
NOC
10 Receipt of NOC from Geology
and Mining dept
11 Filing for CTE Jan-11 Jan-11
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
68/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
12 Reciept of CTE Jun-11 Oct-11
E Infrastructure
1 Application to CGWB for
drawal of Ground Water
Apr-11 Apr-11
2 Permission for Ground Water
drawal from (CGWB)
Jun-11 Oct-11
3 Application to Gujarat Water
Infrastructure Limited (GWIL)
Mar-11 Mar-11
4 Sanction of Demand by GWIL May-11 Sep-11
5 Application for Construction
Power
Apr-11 Apr-11 Jul-11
F Evacuation arrangement
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
69/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
1 Application for Grid connectivity
2 Obtention of Grid connectvity
from GETCO
May-11 May-11
G Fuel
1 Submission of proposal to
Gujarat Forest Dept (GFD) for
fuel tie up
2 Submission of Draft Concession
agreement to GFD
Apr-11 April -11/
June -11/
August-11
3 Execution of Agreement with
GFD
May-11 Sep-11
H Selection of EPC Contractor
1 Selection of Consultant for
preparing EPC specs & Issue of
LOI
2 Finalization of bid specifications
for EPC Contractor
3 Finalization of bid document
4 Issue of BID Mar-11 Mar-11
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
70/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
5 BID received Apr-11 Jun-11
6 Bid evaluation & selection May-11 Aug-11
7 Selection of Consultant for PMC
& Issue of LOI
May-11 Aug-11
8 Issue of Notice to Proceed Jun-11 Oct-11
I Financial closure
1 Preparation of PIM & FinancialModel
May-11 Aug-11
2 Circulation of PIM to Banks etc May-11 Aug-11
3 Obtaining Sanctions from Banks
etc
Jun-11 Sep-11
4 Execution of Loan Agreement Jun-11 Oct-11
J Agreements & Contracts
2 Execution of (Fuel Supply)Concession Agreement with
GFD
May-11 Sep-11
3 Execution of Power Purchase
Agreement
May-11 Aug-11
4 Execution of EPC Agreement May-11 Sep-11
5 Execution of Loan Agreements Jun-11 Oct-11
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
Sr NoMAJOR
ACTIVITY/MILESTONE
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Q4 (2011-12)Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
8/3/2019 IEDCL_Implementation Master File 24-08-2011
71/85
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
Brief Status
1) Created SPV in the name of Nakhatrana Biomass Energy Limited on July 21,2011
3)' IREL as one of the respondent filed reply against the petition with Sr. Civil Judge at Bhuj Court on July 2
4) Submitted proposal for issuance of advance possession of land till final land allotment to Dist Collector,
5) Geotechnical Investigation completed
6) GWIL Completed feasibility study for water supply on July 30,2011.
7) GETCO completated feasibility study for grid connectivity. Obtained connectivity at 66KV Kotda Substati
8) PPA draft approval is process with GUVNL
Critical Issues
1) Allotment of 30 Acres of land may get delayed due to the petition filed by the locals againsy Govt
2) Sanction of Narmada water demand by Gujarat Water Infrastructure Limited and permission for ground w
3) NOC from Pollution Control Board subject to water sanction by GWIL
4) Execution of Concession Agreement for fuel tie-up
5) Financial closure
Support Required
1) Support from Govt of Gujarat for allotment of land and sanction of water Demand from GWIL
2) Support from Forest Dept for execution of concession agreement
9)Gujarat Forest Dept(GFD) issued allocation of @ 35,500 Ha of land in Banni and Kachchh Forest. Draft C
10) Received revised EPC offers from IJT and Cethar vessels, EPC cost offered are in the range of 5.5. to 5.negotiations are in progress
2)Deposited 1% surcharge as processing fee with Revenue Dept. Proposal forwarded to Dist. Town Planning
on August 03,2011
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
ion
8/3/2019 IEDCL_Implementation Master File 24-08-2011
72/85
REMARKS
Completed.
Completed . On september 2009
Completed. On 8 July 2010
Completed.Carried out on Dec 2,2010
DILR submitted Land measurement
report to revenue Dept on December
15,2010, Composite map on April
18,2011 in compliance to the query
raised by Revenue dept.
1% surcharge deposited with Revenue
dept.on July 14,2011. Dist. Collector,
Kachchh moved the file to DTP for
valuation on August 03,3011
Proposal forwarded to DTP on August
03,2011. Upon valuation by DTP and
recommendation by Dist Collector,
proposal will be forwarded to
Additional Secretary(Revenue)by end
of August 2011. If the land valuation is
more than 1 Cr, the proposal will be
presented in the cabinet for approval.
t -12
ion
cted Completion
13
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
73/85
After state level approval the deposit
will be made.
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed
Completed . On Sept 3,2010
Completed. On June 17,2010
Completed. On Dec 31, 2010.
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
74/85
Completed. Environment Management
Consultant appointed on Feb 28,2011
Completed . Report Submitted on
November 2010
Completed . Report Submitted on Dec.
2010
Received report on July 12,2011
Obtained on 4.11.2010
Report Submitted by EMC The reports
is required for filing application to
CGWB for ground water drawal
permission (application filed with
CGWB)
Data collection completed, analysis and
report preparation in progress.
Completed. Applied on May 26,2010
Obtained In -Principal approval on
August 26, 2010
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
75/85
After submission of valid land transfer
document, permission for Water
drawal from CGWB / GWIL, GPCB
NoC, PPA and financial closure
Certificate obtained (SoI did not issue
authenticated map)
Application submitted on April 25,201.
after receipt of distance certificate
AAI is insisting for authentication on
map also. Being restricted zone, Govt.
agencies are reluctenct to authenticate
maps. However, we have obtained
authentication from Thalati and the
application is resubmitted on
08.07.2011
Obtained. On March 29,2011
Obtained. On April 18,2011
Completed. Applied on August
23,2010
Obtained. on December 23,2010
Completed. Application inwarded
online in GPCB Portal in Jan ,2010
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
76/85
GPCB may issue NOC subject to
Acquisition of land and NOC from
CGWB or GWIL. Quality of groundwater and its treatment is major issue
in accepting the application by GPCB.
Water treatment schemes is under
discussion with EPC vendors. Initiated
process for obtaining Adequacy
Certificate and TSDF Membership as
desired by GPCB
Application filed on April 28,2011
Getting permission is critical
considering ground water recharging at
very low annual rainfall in Kachchh .
Submitted on March 30, 2011
(requirement is 330 Cu.m per day) .
Feasibility study completed by GWIL.The proposal will be discussed in
Tapping committee meeting for
approval. Date of the meeting is not yet
declared.
Applied. on April 18,2011 to PGVCL.
Demand sanctioned for Construction
Power subject to submission of valid
land transfer documents. PGVCL
furnished the estimate of @9 lakhs, the
same is to be deposited within onemonth's period from the date of issue of
estimate
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
C l t d A li d O t b 2010
8/3/2019 IEDCL_Implementation Master File 24-08-2011
77/85
Completed. Applied on October 2010,
Joint survey with GETCO Completed
Feasibili ty for grid connectivity
Obtained on 24 May 2011.
Completed.Proposal submitted on Dec
31,2010
Submitted revised concession
agreement on 15 June ,2011 as per
model draft provided by GFD and
tentative reservation of forest land vide
letter dated June 6,2011. Revised drafthanded over on August 3,2011.
Finalisation is in process
Concession Agreement draft is under
finalisation with GFD. The draft will
then be sent for approval to finance
dept for finalisation of Commercial
terms i.e. Royalty rate / security deposit
. Upon finalisation of commercial terms
the agreement will be executed
Completed. PROCON Engineers
appointed on Jun 30,2010
Completed . October 2010
Completed . Dec.2010
Completed .Bid isued to Greenesol, IJT
, Cethar vessels, Thermax,
GBENMASS & Cheema Boilers
Limited on March 3, 2011
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
IJT CETHAR GB Engg Cheema
8/3/2019 IEDCL_Implementation Master File 24-08-2011
78/85
IJT, CETHAR , GB Engg., Cheema
Boilers have submitted offer. Thermax
and Areva are also being considered.
Revised commercial offer from IJT
and Cethar received. Negotiation with
IJT, Cethar and GB in progress
Provided land is allocated
PIM and Model is ready. Waiting forfinalisation of EPC Cost
After finalisation of EPC Cost
Sanction subject to allotment of land
After allotment of land
Gujarat Forest Dept asked to revisedthe Draft concession agreement on July
16,2011.Revised draft again handed
over on August 3,2011
Comments on Draft PPA submitted to
GUVNLon 27 May 2011 and
thereafter on June 23,2011 for their
consideration. Draft PPA under
process for approval with GUVNL
board.
After allotment of land
ACTIVITY PLAN: 12 MW Community Linked Biomass Based Power Project,Kachchh, Gujarat
REMARKS
8/3/2019 IEDCL_Implementation Master File 24-08-2011
79/85
,2011.
Kachchh
n
ater abstraction from CGWB.
ncession Agreement under finalisation,
Crs/MW, Cost optimisation and
Dept for valuation
ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project
PROJECT TEAM: Anand Nair, Akshay Sharma
Date: 03.08.2011
TC : Target Completion
AC/EC : Actual/Expected Completion
8/3/2019 IEDCL_Implementation Master File 24-08-2011
80/85
Sr NoMAJOR
ACTIVITY/MILESTONEREMARK
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL
A LAND
1 Identif ication of
Disctrict/Location
436MW 436MW - 80 MW 516 MW
2 Visit for site selection 60MW 180 MW 138MW 378 MW3 Finalization of Site 60MW 180 MW 138MW 378 MW
4 Submission of Proposal for Land
Acquisition
12 MW 12MW 36MW 44MW 144MW 138MW 378 MW Negotiations are under way for
buying land for 48 MW
5 Deposit of Money for Land 12MW 12MW 36MW 44MW 144MW 240 MW
6 Signing of Lease Deed if required Land is being bought outright
B DPR for Generation Project
1 Selection Technical Consultant
(TC) & Issue of LOI - TC
516MW 516MW 516MW Dalkia Energy Services is
technical Consultant: ProjectDevelopment Agreement has
been signed between PTC
Bermaco and Dalkia India.
MoU signed between IREL,
2 Site Visit, Kick off meeting with
TC
84 MW 84 MW 156 MW 138MW 378 MW
3 Submission of Pre-feasiblity 60MW 60MW 180 MW 138MW 378 MW
4 Submission of Data to TC 60MW 60MW 180 MW 138MW 378 MW
5 Preliminary Plant layout and 60MW 60MW 180 MW 138MW 378 MW7 Presentation on Draft DPR 60MW 60MW 180 MW 132MW 360 MW
8 Finalization of Layout 60MW 60MW 180 MW 132MW 360 MW
9 Finalization of DPR 60MW 60MW 180 MW 132MW 360 MW
C Environmental and R & R
1 Selection of Environmental
Consultant & Issue of LOI
84 MW 156MW 240 MW
All Numbers Repesent MW out of a total target of 516 MW by 2014
TIME FRAME
Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)
COD as per IM: March-13
Expected Target COD: March-13
ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project
Sr NoMAJOR
ACTIVITY/MILESTONEREMARK
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL
TIME FRAME
Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)
2 Submission of Form I , MoE&F 84 MW 156MW 240 MW
8/3/2019 IEDCL_Implementation Master File 24-08-2011
81/85
3 Start of EIA 84 MW 156MW 240 MW
4 TOR Approval 84 MW 156MW 240 MW
5 Additional studies as per
approved ToR
84 MW 156MW 240 MW
6 Presentation on draft EIA report 84 MW 156MW 240 MW
7 Submission of draft EIA report 84 MW 156MW 240 MW
8 Final EIA Report 84 MW 156MW 240 MW
9 Submission of EIA report to State
Agency
84 MW 156MW 240 MW
10 Public Hearing 84 MW 156MW 240 MW
11 Filing of application for
Environment Clearance
84 MW 156MW 240 MW
12 Clearance from MOE&F 84 MW 156MW 240 MW
D Site Related Investigations 84 MW 156MW 240 MW
E Statutory Clearances /
Approvals
84 MW 156MW 240 MW
F Infrastructure
1 Finalization of TransportConsultant for equipments
84 MW 156MW 240 MW
2 Finalization of Transport Route 84 MW 156MW 240 MW
3 Application for Water Linkage /
allocation
84 MW 156MW 240 MW
4 Execution of Water Supply
Agreement
84 MW 156MW 240 MW
5 Application for Construction
Water/allocation
84 MW 156MW 240 MW
6 Application for Construction
Power
84 MW 156MW 240 MW
G Fuel
1 Finalization of Fuel requirement 240MW 240MW
2 Fuel Specs from potential Fuel
suppliers
240MW 240MW
3 Finalization of Fuel supplier 516 MW 516MW
Fuel Supply Company will be a
60:40 JV between Dalkia and
Bermaco Energy Systems Ltd.
ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project
Sr NoMAJOR
ACTIVITY/MILESTONEREMARK
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL
TIME FRAME
Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)
4 Submission of MoU/Agreement 516 MW 516MW
8/3/2019 IEDCL_Implementation Master File 24-08-2011
82/85
to Fuel Supplier
5 Execution of MoU/Agreement
with Fuel Supplier
240 MW 276MW 516MW
H Open Access
1 Filing of application with CTU 240MW 240 MW
2 Standing Committee meeting 240MW 240 MW
3 Grant of Long Term Open
Access
240MW 240 MW
4 Execution of BPTA 240MW 240 MW
I Selection of EPCContractor/Packages
240MW 276MW 516MW
1 Selection of Consultant for
preparing EPC specs & Issue of
LOI
240MW 276MW 516MW Dalkia India is the chosen EPC
consultant
J Financial closure
1 Selection of Debt syndication
agency
240 MW 240 MW
2 Financial Structure of the Project 84 MW 84 MW 156 MW 240 MW
3 Preparation of PIM & Financial
Model
84MW 156MW 240 MW
4 Circulation of PIM to Banks etc 84MW 156MW 240 MW
5 Obtaining Sanctions from Banks
etc
84MW 156MW 240 MW
6 Execution of Loan Agreement 84MW 156MW 240 MW
K Agreements & Contracts
1 Land Acquisition/ LeaseAgreement
12MW 12MW 84 MW 144MW 240 MW
2 Execution of Fuel Supply
Agreemnt
240MW 276MW 516 MW
3 Execution of Water Supply
Agreement
84MW 156MW 240MW
4 Execution of Power Purchase
Agreement
WILL BE EXECUTED POST Q4 2011-12
ACTIVITY PLAN: 766 MW PTC/ BERMACO Biomass Power Project
Sr NoMAJOR
ACTIVITY/MILESTONEREMARK
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC TOTAL
TIME FRAME
Q1 (2011-12) Q2 (2011-12) Q3 (2011-12) Q4 (2011-12) Q1 (2012-13)
5 Execution of BPTA
8/3/2019 IEDCL_Implementation Master File 24-08-2011
83/85
6 Execution of EPC Agreement 84MW 156MW 240 MW
7 Execution of Loan Agreements 84MW 156MW 240 MW
Remark
NOTE I:
Phase State No of
Projects MW
Cumulati
ve MW
1 Punjab 7 84
Bihar 13 156
PHASE I Total 240 240
2 Bihar 13 156
Tamil Nadu 10 120
PHASE II Total 276 516
NOTE II:
Tri-partite MoU signed between Dalkia/ IREL and Bermaco for the development of 1000MW Biomass Based Power Plants in India
Licenses/ Approvals / Project Development Work is underway to implement additional 484MW
ACTIVITY PLAN : Indo Nepal Cross Border 400KV D/C Muzaffarpur- Dhalkebar Transmission line
PROJECT MANAGER : V. L Dua
DATE : 03.08.2011
TC : Target Completion
AC/EC A t l/E t d C l ti
8/3/2019 IEDCL_Implementation Master File 24-08-2011
84/85
Sr NoMAJOR
ACTIVITY/MILESTONEREMARKS
TC AC/EC TC AC/EC TC AC/EC TC AC/EC TC AC/EC
A India Portion-100KMs long
Project Cost - Rs.1440 Million
1 Finalization of TSA between
NEA and CPTC
Jul-11 Sep-11
2 Financial closure Dec-11
3 Bidding & Award of works Mar-12
4 Commencenment of Construction Mar-12
B Nepal Portion -45KMs long
Project Cost - Rs.710 Million
1 Finalization of TSA between
NEA and PTCN
Jul-11 Sep-11
2 Financial closure Dec-113 Bidding & Award of works Mar-12
4 Commencenment of Construction Mar-12
COD as per IM: -
Expected Target COD: Indian Portion: Mar 14
Nepal Portion: Mar 14
TIME FRAME
Q4 (2010-2011) Q1 (2011-2012) Q2 (2011-12) Q3 (2011-12)
AC/EC : Actual/Expected Completion
Q4 (2011-12)
ACTIVITY PLAN : Indo Nepal Cross Border 400KV D/C Muzaffarpur- Dhalkebar Transmission line
Brief Status :
1
2
3
The work of DPR & Route survey completed.
Approval under Section 68 of EA 2003 received.
Transmission License CERC has issued Transmission License on 22.03.2011
8/3/2019 IEDCL_Implementation Master File 24-08-2011
85/85
4
5
6
Critical Issues :
1
Support Required : Nil
Final signing of ITSA.
Implementation & Transmission Service Agreement (ITSA) - Final draft of ITSA both for India and Nepal portion
finalized and initialled on 21.07.2011.For approval U/s 164 of EA 2003, scheme notified in the local dailies in May 2011 and subsequently notified in Govt.
Signing of PPA with PTC