ALMA Integrated Computing Team Coordination & Planning Meeting #1 Santiago, 17-19 April 2013. ICT infrastructure changes Erik Allaert. Overview. Mailing lists: centralize in one place Repository: CVS → SVN newer, still actively maintained technology - PowerPoint PPT Presentation
Citation preview
ALMA Integrated Computing Team
Coordination & Planning Meeting #1Santiago, 17-19 April 2013
ICT infrastructure changes
Erik Allaert
Mailing lists: centralize in one place
Repository: CVS → SVN newer, still actively maintained technology
TWiki: almaw.hq.eso.org → ictwiki.alma.cl new location new structure new version
JIRA: new server new version new project heavily customized workflow
Overview
April 2013 ICT planning meeting #1 / SCO 2
17 common ICT mailing lists, hosted centrally at SCO All lists configured same, same policy:
per default no monthly password reminder a limit of 3MB per message lists are archived list-membership is restricted, i.e. (un)subscription requires the
approval of a moderator lists are administered by SE-QM only …
For details: see
https://ictwiki.alma.cl/twiki/bin/view/SEQM/IctMailingLists
(requires account on ictwiki)
Mailing lists
April 2013 ICT planning meeting #1 / SCO 3
Note: only for project2 – other projects remain under CVS at cvssrv.hq.eso.org
Decided at September 2012 planning meeting – subject to conditions for using replication software (WANdisco)
Initially planned for January 2013, but postponed due to acceptance activities and other JAO priorities.
Scheduled for 18-22 March, ready on 20 March
CVS → SVN …
April 2013 ICT planning meeting #1 / SCO 4
Test-server (without replication) available well in advance to exercise normal operation by developers, NRI, build-farm, … allowed to identify more suitable directory structure tested fixes for code referring explicitly to CVS administrative files some Makefiles assumed particular file-permissions on binary
files, while SVN deals with that in a different way
After migration and enabling replication few WANdisco cases (talk-back script, logs, address already in
use) SVN client version
Pending: branching strategy / use of trunk
… CVS → SVN
April 2013 ICT planning meeting #1 / SCO 5
almasw.hq.eso.org: TWiki 4.3.1 (Apr 2009) Organized in webs corresponding to CIPT-subsystems In use in its current form since ~2004 Accumulated ~450 users (in spite of being open for almost all
webs)
ictwiki.alma.cl: Twiki 5.1.3 (Dec 2012) Organized in webs according to ICT-groups Subject to JAO access policy: user account needed (130 at start) Available for testing since ~Jan 2013, to users since Apr 2013 With read-only snapshot of almasw (as it was when frozen) Option to move old topics to new webs for limited time
TWiki
April 2013 ICT planning meeting #1 / SCO 6
Decided during Sept 2012 CIPT leads-meeting to go for new ICT “project” within JIRA
Opted for separate, independent server as JIRA host All ICT standard activities should have an ICT ticket (to
which other projects/tickets can link) Access to ICT-project: all ICT-members, TBD list of
scientists, operators, engineers (to be agreed with DSO/SIST/ASG)
Clear initial involvement of group-lead to decide on the priority of the issue
JIRA …
April 2013 ICT planning meeting #1 / SCO 7
jira.alma.cl: JIRA 4.4 > 130 projects, 40 issue-types, >1350 users, … several system-wide settings not optimal for ICT (e.g. resolution,
priority, time tracking, issue statuses, …)
New server: JIRA 5.2.9 9 issue types, with clear definition specific workflow for typical ICT software development process
… JIRA
April 2013 ICT planning meeting #1 / SCO 8