Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Design & Engineering Services
IBM Mobile Measurement Technology
ET08SCE1030 Report
Prepared by:
Design & Engineering Services
Customer Service Business Unit
Southern California Edison
December 2010
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison
Design & Engineering Services December 2010
Acknowledgements
Southern California Edison’s Design & Engineering Services (DES) group is responsible for
this project. It was developed as part of Southern California Edison’s Emerging Technologies
Program under internal project number ET08SCE1030. DES project manager Devin Rauss
conducted this technology evaluation with overall guidance and management from Henry
Lau and Paul Delaney. For more information on this project, contact [email protected].
Disclaimer
This report was prepared by Southern California Edison (SCE) and funded by California
utility customers under the auspices of the California Public Utilities Commission.
Reproduction or distribution of the whole or any part of the contents of this document
without the express written permission of SCE is prohibited. This work was performed with
reasonable care and in accordance with professional standards. However, neither SCE nor
any entity performing the work pursuant to SCE’s authority make any warranty or
representation, expressed or implied, with regard to this report, the merchantability or
fitness for a particular purpose of the results of the work, or any analyses, or conclusions
contained in this report. The results reflected in the work are generally representative of
operating conditions; however, the results in any other situation may vary depending upon
particular operating conditions.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page i Design & Engineering Services December 2010
ABBREVIATIONS AND ACRONYMS
ASHRAE American Society of Heating, Refrigeration, and Air Conditioning Engineers
EEM Energy Efficiency Measure
FIRM Facility Integrated Resource Management
IT Information Technology
LBNL Lawrence Berkeley National Laboratory
MMT Mobile Measurement Technology
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page ii Design & Engineering Services December 2010
FIGURES Figure 1. Typical Breakdown of Energy Consumption within a
Data Center ................................................................. 7
Figure 2. IBM Mobile Measurement Technology (MMT) .................... 8
Figure 3. Sample Temperature Map of Data Center ........................ 9
Figure 4. Data Center Layout .................................................... 11
Figure 5. Temperature Map at 3.5 Feet ....................................... 12
Figure 6. Temperature Map at 4.5 Feet ....................................... 12
Figure 7. Temperature Map at 5.5 Feet ....................................... 13
Figure 8. Humidity Map at 4.5 Feet ............................................ 13
Figure 9. K20 Logger Points ...................................................... 15
Figure 10. Toyota HQ Central Plant Control System ....................... 16
Figure 11. Mechanical System Points ........................................... 16
Figure 12. Data Room Space Temperature and Humidity Points ....... 17
Figure 13. Project Monitoring Boundaries ...................................... 18
Figure 14. Daily kWh Consumption of IT Equipment ....................... 19
Figure 15. Daily kWh Consumption of CRAC Units .......................... 20
Figure 16. Ambient Dry Bulb Temperature of Surrounding Areas ..... 21
Figure 17. Modeled IT Equipment Inlet Temperature ...................... 22
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page iii Design & Engineering Services December 2010
TABLES Table 1. Data Table DC1 THM Point List ..................................... 24
Table 2. Data Table DC1 THM2 Point List ................................... 24
Table 3. Data Table K20 - T402 Point List ................................... 25
Table 4. Data Table K20 - T403 Point List .................................. 25
Table 5. Data Table K20 - T404 Point List .................................. 26
Table 6. Data Table K20 - T406 Point List .................................. 26
Table 7. Data Table K20 - T407 Point List .................................. 27
Table 8. Data Table K20 - T409 Point List .................................. 27
Table 9. Data Table E1st Point List ............................................ 27
Table 10. Data Table PLANT Point List ......................................... 27
Table 11. Data Table TOWER33 Point List .................................... 28
Table 12. Data Table CWP Point List ........................................... 28
Table 13. Data Table Rsview Point List ........................................ 28
Table 14. CRAC Specifications ...................................................... 28
Table 15. One-Time Water Flow Measurements .............................. 29
Table 16. One-Time Air Flow Measurements .................................. 29
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page iv
Design & Engineering Services December 2010
CONTENTS
EXECUTIVE SUMMARY _______________________________________________ 1
INTRODUCTION ____________________________________________________ 7
ASSESSMENT OBJECTIVES ___________________________________________ 10
TECHNICAL APPROACH/TEST METHODOLOGY ___________________________ 11
MMT Implementation ............................................................ 11
Monitoring Plan ..................................................................... 14
RESULTS_________________________________________________________ 19
RECOMMENDATIONS ______________________________________________ 23
RECOMMENDATIONS ______________________________________________ 23
APPENDICES _____________________________________________________ 24
REFERENCES, OPTIONAL ____________________________________________ 30
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 1
Design & Engineering Services December 2010
EXECUTIVE SUMMARY This project assesses IBM’s Mobile Measurement Technology (MMT) at a customer’s data
center. The MMT tool performs an audit of a data center, producing temperature and
humidity maps. From this increased knowledge of operating characteristics, modifications
can be made that improve the airflow within a data center, and ultimately energy efficiency
measures can be implemented. Through the implementation of these measures, energy
savings can be found, while maintaining safe operation of the data center.
In this particular data center, the MMT tool and IBM team were able to make a number of
recommendations that yielded significant savings. The first recommendation was a series of
steps to improve the air distribution, namely; installing blanking panels, strip curtains to
partition the room, adjusting and installing new perforated floor panels, reducing leakage
around cables, and adjusting fan settings. Once these measures were implemented, the
improvement in airflow allowed for three Computer Room Air Conditioners to be shut off and
capped, as well as for all thermostatic setpoints to be raised 5°F.
The monitoring of this site showed that through the implementation of these measures,
daily cooling energy consumption was reduced 15.9%. The demand associated with these
energy savings is likely to be of similar magnitude, given the 24/7 operation of the cooling
equipment. However, in analyzing this data there appeared to be no savings attributable to
the raising of the setpoints, which goes against standard HVAC rules of thumb. Further
analysis indicated that this may be a result of the ambient temperatures, but no real
solution could be found.
This project was split into two phases; the first being the analysis of the field monitored
data, with a second, forthcoming, phase to develop a simulation model and utilize the field
monitored data to develop annual, normalized savings. It is recommended that this second
phase be completed in order to understand the setpoint energy consumption anomaly, the
annual energy savings, potential savings in different climate zones, and how various IT
loads would impact the savings.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 7
Design & Engineering Services December 2010
INTRODUCTION Energy consumption in data centers is a growing problem, as both the number of data
centers and the power draw of the equipment within continues to expand. A study
performed by the Lawrence Berkeley National Lab (LBNL) concluded that data centers
accounted for 1.2% of the total U.S. electrical consumption in 2005, and forecasted that this
number would double by 20101.
The Information Technology (IT) equipment, both in the energy required to run
computations and to keep this equipment cool, drives energy consumed within a data
center. Another study performed by LBNL found that in a typical data center, the IT
equipment accounted for 51% of the energy consumed, with the cooling equipment
accounting for another 33%2, as shown in Figure 1. The necessity to keep these
computations going, with no delay, often leads to over designed data centers, with little
regard for energy consumption.
FIGURE 1. TYPICAL BREAKDOWN OF ENERGY CONSUMPTION WITHIN A DATA CENTER
As energy costs have continued to grow, data center energy consumption has become a
greater focus. The IT and HVAC industries have seen the much work performed, particularly
by the American Society of Heating, Refrigeration, and Air Conditioning Engineers
(ASHRAE), to identify best practices for data center operation. Much of this work has dealt
with the cooling side of operations, as many times there is no room for improvement with
the computations. A major emphasis of ASHRAE’s work has been the optimization of airflow
within data centers, and resultantly optimizing temperatures.
This project assesses a technology developed by IBM, the Mobile Measurement Technology
(MMT), which produces energy savings on the cooling side. This project was performed at a
roughly 30,000 square foot data center in Torrance, California, with under floor air
distribution. The IBM MMT provided an assessment of the data center’s operations.
Recommendations for improvements were made and ultimately implemented. Field
monitoring was done to quantify the impacts of these recommendations, as well as provide
enough data to perform building energy simulations as part of Phase 2 of this project. This
report provides details on the technology, as well as the findings from Phase 1.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 8
Design & Engineering Services December 2010
BACKGROUND Seeing a need within the data center industry for a tool to increase data center
optimization, IBM developed the MMT. This technology, or more appropriately tool, is shown
in Figure 2.
FIGURE 2. IBM MOBILE MEASUREMENT TECHNOLOGY (MMT)
As shown, the MMT is a motorized cart outfitted with a variety of sensors (e.g.,
temperature, pressure, etc.) and a computer for data storage. This cart drives through the
data center, during normal conditions, to capture operating characteristics. These
characteristics are converted into 3D temperature maps, at various heights, which provide
the basis for energy efficiency measure (EEM) recommendations. Figure 3 shows a
temperature map recorded at the test site.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 9
Design & Engineering Services December 2010
FIGURE 3. SAMPLE TEMPERATURE MAP OF DATA CENTER
The primary focus of these temperature maps is the identification of hot or cold spots in the
data center. ASHRAE publishes recommended temperature ranges for IT equipment that
most data center designers and operators follow. However, these recommendations are not
for the average space condition, rather they are for specific IT equipment inlet
temperatures. That is to say, the recommendation is that no piece of IT equipment falls
outside of the recommended range. In many cases, there is a single area or piece of
equipment that drives the cooling needs for the entire data center. These areas are
identified as hot or cold spots through the temperature mapping.
Once these spots have been identified, recommendations can be made to mitigate them.
The first recommendation, which is a pre-requisite to any further recommendations, is to
improve the distribution of the cold air. In many data centers, this amounts to installing
blanking plates, re-positioning perforated tiles, better sealing around wires, adjusting fan
settings, and various other measures to improve air distribution. Once these adjustments
have been made, the EEMs can be implemented. The improved air distribution often yields
recommendations to raise thermostatic setpoints, turn off air conditioning units, or both.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 10
Design & Engineering Services December 2010
ASSESSMENT OBJECTIVES The objectives of this project are twofold. The first objective of this project was to quantify
the impacts of the recommendations made because of the implementation of the MMT tool.
The second objective was to collect enough data to perform energy-building simulations that
would provide normalized, annual savings and could help to calibrate the data center
portion of eQuest underdevelopment.
The first objective was to be completed by working in conjunction with IBM and the site
energy management team, Roy Jorgensen and Associates Facility Integration Resource
Management (FIRM) team, to implement the MMT process and the recommended EEMs.
FIRM was also selected as the team to install the data collection hardware, as well as collect
and analyze the data. This field-collected data provided the basis for the quantification of
the MMT’s impacts. This objective was completed as part of Phase 1.
The second objective was also supported through the gathering of field data. Additionally,
construction documents were gathered to develop the model of the data center (e.g., how is
it constructed, what are the dimensions, etc.). Finally, details on the equipment within the
data center and its schedule were also collected. This information will be used to develop a
simulation model as part of Phase 2 of this project.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 11
Design & Engineering Services December 2010
TECHNICAL APPROACH/TEST METHODOLOGY The technical approach has been divided into two categories; MMT Implementation and
Monitoring Plan. These two categories are described in detail below.
MMT IMPLEMENTATION The data center used for this project is shown in Figure 4. It is roughly 30,000
square feet, with a main computer floor room, a printer room, a control room (shown
as KVM), and a test lab.
FIGURE 4. DATA CENTER LAYOUT
In August 2008, the MMT tool was used to diagnose the performance of this data
center. Figures 5 through 8 show temperatures maps produced at various heights, as
well as one humidity map. From these maps, airflow modifications were
recommended.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 12
Design & Engineering Services December 2010
FIGURE 5. TEMPERATURE MAP AT 3.5 FEET
FIGURE 6. TEMPERATURE MAP AT 4.5 FEET
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 13
Design & Engineering Services December 2010
FIGURE 7. TEMPERATURE MAP AT 5.5 FEET
FIGURE 8. HUMIDITY MAP AT 4.5 FEET
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 14
Design & Engineering Services December 2010
The recommended airflow modifications were made in December 2008 (after
baseline data was collected). The modifications made included:
Installing blanking panels to reduce leaks through servers
Installing material to reduce leaks around wires
Installing curtains to create hot and cold aisles
Installing higher performance perforated floor panels
Repositioning perforated floor panels
Adjusting air handler fan settings
After these modifications were made, additional data was collected to assess the
impacts. Additionally, monitoring sensors were installed by IBM, which allowed for
continued monitoring of room temperatures. Through the initial assessment and the
continued monitoring, the following EEMs were recommended and implemented:
Turn off three Computer Room Air Conditioners (CRACs)
Raise thermostatic setpoint 5°F
Each EEM was implemented incrementally, i.e., shut off one CRAC at a time, and
raise the setpoint 1°F at a time, with a stabilization period in between to ensure no
adverse effects. Data was collected through each period. Because of the incremental
steps, these EEMs took some time to implement. The CRACs were shut off from
January to February 2009, while the setpoint was raised over the course of March
2009. Detailed monitoring information is as follows.
MONITORING PLAN Jorgensen’s FIRM team installed temporary data loggers to record the agreed-upon
data center floor-mounted computer room air conditioning units’ (CRACs’) points, as
well as a couple of loads served by the static switches but outside the boundaries of
the data room under study. K20 loggers by ENERNET Corp. were selected because of
the total number of points each was capable of monitoring. These loggers collected
data on a 5-minute interval. Figure 9 provides a graphic perspective of the installed
system.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 15
Design & Engineering Services December 2010
FIGURE 9. K20 LOGGER POINTS
One-time water flow for each CRAC was measured using a leased Shenitech STUF-
200H portable flow meter. FIRM retained American Air Balance Co. to conduct airflow
measurements for two representative CRAC units (one 20-ton and one 30-ton). A
portable data logger (Dent ELITEpro) was used to record the energy for the closed
system cooling water pumps. The logger remained in place for approximately three
weeks.
FIRM was able to use the existing control system located in the remote central plant
to collect temperature and flow data on the remote pumps and cooling towers, as
well as the outside air temperature and humidity. A screen capture of the control
system is included as Figure 10. Further, Figure 11 provides a graphic view of the
specific points that are included in the monitoring project.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 16
Design & Engineering Services December 2010
FIGURE 10. TOYOTA HQ CENTRAL PLANT CONTROL SYSTEM
FIGURE 11. MECHANICAL SYSTEM POINTS
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 17
Design & Engineering Services December 2010
An existing Stonewater Controls energy monitoring system provides energy use data
on the central plant pumps and cooling towers as well as the two static switches
serving the data equipment load on the raised floor. The system structure is depicted
as a part of Figure 2. Space temperatures and humidity are collected utilizing the
existing Leibert SiteScan system, which FIRM connected to Toyota’s Delta
Automation data server. The location of the sensors on the floor is shown in
Figure 12.
FIGURE 12. DATA ROOM SPACE TEMPERATURE AND HUMIDITY POINTS
FIRM installed six K20 data loggers to accommodate the number of points required
to determine the total energy use within the project boundaries. Figure 13 shows the
boundaries of the project, less the two areas marked in bright green.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 18
Design & Engineering Services December 2010
FIGURE 13. PROJECT MONITORING BOUNDARIES
The data loggers were installed in one of the two electrical rooms located outside the
project boundaries (not shown in the image above). The points monitored by these
loggers are noted in the tables in the Appendix.
There are three electric panels that serve load outside the project boundaries that
are served by the static switches. These panels, designated KVM, TestLab#1 and
TestLab#2, were monitored by points on the K20 loggers and their load subtracted
from the total data center load.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 19
Design & Engineering Services December 2010
RESULTS As noted previously in this report, the focus of data center operation is to provide adequate
cooling so that the IT equipment does not fail. The amount of heat that must be removed is
in direct relation to the amount of power consumed by the IT equipment. For any fair
comparison is to be drawn, the IT equipment load must be kept consistent. This load was
monitored throughout the project and is shown in Figure 14. From this chart, it can be
concluded that the IT equipment load was kept within a reasonable tolerance (the green
trend line shows almost no change). Therefore, the cooling equipment has to remove the
same load throughout the project duration.
8,400
8,450
8,500
8,550
8,600
8,650
8,700
8,750
8,800
11/2
2/20
08
11/2
9/20
08
12/6
/200
8
12/1
3/20
08
12/2
0/20
08
12/2
7/20
08
1/3/
2009
1/10
/200
9
1/17
/200
9
1/24
/200
9
1/31
/200
9
2/7/
2009
2/14
/200
9
2/21
/200
9
2/28
/200
9
3/7/
2009
3/14
/200
9
3/21
/200
9
3/28
/200
9
4/4/
2009
4/11
/200
9
4/18
/200
9
Date
Dail
y E
nerg
y C
on
su
mp
tio
n (
kW
h/d
ay)
FIGURE 14. DAILY KWH CONSUMPTION OF IT EQUIPMENT
The CRAC units’ energy consumption was monitored throughout the project and is graphed
in Figure 15. The average daily consumption of the baseline period was 6411 kWh/day.
Once the airflow modifications were made, the average daily consumption was slightly
increased to 6436 kWh/day. The modifications to the air distribution system were expected
to be negligible; this 0.3% increase is considered within the error of the testing. With the
shut off of the first CRAC unit, also the first EEM recommended, came the first noticeable
change in consumption. The daily energy consumption dropped to 6170 kWh/day, a
reduction of 3.7% compared to the baseline. As the next CRAC was shut off, greater savings
were seen. The daily consumption was reduced further to 5891 kWh/day, a 8.1% reduction
from the baseline. With the third and final CRAC shut off came even more savings. The daily
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 20
Design & Engineering Services December 2010
energy consumption went down to 5388 kWh/day, a 15.9% reduction in consumption. The
final EEM was to raise the setpoints on the CRAC units by 5°F. From Figure 15 it is evident
that this measure did not provide any additional savings (average daily energy consumption
remained at 5388 kWh/day). This result was not anticipated. Further data analysis was
completed in order to hypothesize the reason for this result.
4,000
4,500
5,000
5,500
6,000
6,500
7,000
11/2
2/20
08
11/2
9/20
08
12/6
/200
8
12/1
3/20
08
12/2
0/20
08
12/2
7/20
08
1/3/
2009
1/10
/200
9
1/17
/200
9
1/24
/200
9
1/31
/200
9
2/7/
2009
2/14
/200
9
2/21
/200
9
2/28
/200
9
3/7/
2009
3/14
/200
9
3/21
/200
9
3/28
/200
9
4/4/
2009
4/11
/200
9
4/18
/200
9
Date
Dail
y E
nerg
y C
on
su
mp
tio
n (
kW
h/d
ay)
Baseline Airflow Mitigation CRAC 1 Shut Off CRAC 2 Shut Off CRAC 3 Shut Off Raise Setpoint
FIGURE 15. DAILY KWH CONSUMPTION OF CRAC UNITS
Although data centers are internally load driven and generally not affected by ambient
conditions, this particular data center used air-cooled CRAC units. The heat absorbed within
the data center by the CRAC units is rejected to externally located condensing units, which
are subject to the ambient conditions. On-site weather data was not collected, so alternative
resources were sought. Figure 16 shows the weather data from the two SCE weather
stations that were closest to the test site; Long Beach and El Segundo, California. A linear
fit to the El Segundo dry bulb temperature shows little to no change over the course of the
testing. However, a similar fit to the Long Beach data shows a steady increase in
temperature. It is believed that this increase is what caused the unexpected results
accompanying the raised setpoint EEM.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 21
Design & Engineering Services December 2010
30
40
50
60
70
80
90
100
11/22/2008 12/12/2008 1/1/2009 1/21/2009 2/10/2009 3/2/2009 3/22/2009 4/11/2009 5/1/2009
Date
Dry
Bu
lb T
em
pera
ture
(°F
)
Long Beach El Segundo Linear (Long Beach) Linear (El Segundo)
FIGURE 16. AMBIENT DRY BULB TEMPERATURE OF SURROUNDING AREAS
As noted previously, the operating temperature of the data center is not optimized for some
point within the room, but rather for the IT equipment inlet. The IBM team modeled the
inlet temperatures for the IT equipment throughout the project, the results of which appear
in Figure 17. Clearly, the airflow distribution or hotspot mitigation work, yielded lower inlet
temperatures to the IT equipment. As a result, the various EEMs could be deployed without
raising the inlet temperature above the baseline conditions. This allowed for the IT
equipment, running the same number of computations, to be cooled to the same
temperature, utilizing less energy.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 22
Design & Engineering Services December 2010
FIGURE 17. MODELED IT EQUIPMENT INLET TEMPERATURE
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 23
Design & Engineering Services December 2010
RECOMMENDATIONS From this phase of the project, it is clear that implementing airflow distribution measures,
combined with shutting off CRAC units and raising thermostatic setpoints, can yield
significant savings. However, given the short timeframe of this project, and the lack of
weather-normalized data, there is some need to continue this work. It is recommended that
Phase 2 of this project, and the objectives identified earlier, be completed in order to truly
understand the potential for this tool. It is also important to understand that much of the
savings seen within this project are a result of holding the operation of the data center
consistent. In actuality, data centers are very dynamic building types, with wide ranges of
loads and operating characteristics. The use of the building energy simulation, to be
developed in Phase 2, would also help to better understand how these EEMs would perform
under not only differing weather conditions, but also IT equipment loads.
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 24
Design & Engineering Services December 2010
APPENDICES The following tables detail the data collection points, as captured in the tables in the data
database.
TABLE 1. DATA TABLE DC1 THM POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
TEMP 1 Space Temperature – refer to Figure 3
TEMP 2 Space Temperature - refer to Figure 3
TEMP 3 Space Temperature - refer to Figure 3
TEMP 4 Space Temperature - refer to Figure 3
TEMP 5 Space Temperature - refer to Figure 3
TEMP 6 Space Temperature - refer to Figure 3
TEMP 7 Space Temperature - refer to Figure 3
HUMID 1 Space Humidity - refer to Figure 3
HUMID 2 Space Humidity - refer to Figure 3
HUMID 3 Space Humidity - refer to Figure 3
HUMID 4 Space Humidity - refer to Figure 3
HUMID 5 Space Humidity - refer to Figure 3
HUMID 6 Space Humidity - refer to Figure 3
HUMID 7 Space Humidity - refer to Figure 3
TABLE 2. DATA TABLE DC1 THM2 POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
TEMP 1 Space Temperature - refer to Figure 3
TEMP 2 Space Temperature - refer to Figure 3
TEMP 3 Space Temperature - refer to Figure 3
HUMID 1 Space Humidity - refer to Figure 3
HUMID 2 Space Humidity - refer to Figure 3
HUMID 3 Space Humidity - refer to Figure 3
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 25
Design & Engineering Services December 2010
TABLE 3. DATA TABLE K20 - T402 POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
1AC_kwa AC-1 Phase A kW
1AC_kwb AC-1 Phase B kW
1AC_kwc AC-1 Phase C kW
1Comp_kwa AC-1 Compressor Phase A kW
1Comp_kwb AC-1 Compressor Phase B kW
1Comp_kwc AC-1 Compressor Phase C kW
1SF_kwa AC-1 Supply Fan Phase A kW
1SF_kwc AC-1 Supply Fan Phase C kW
1Hum_kwa AC-1 Humidifier Phase A kW
1Hum_kwb AC-1 Humidifier Phase B kW
1Hum_kwc AC-1 Humidifier Phase C kW
1Reh_kwa AC-1 Reheat Phase A kW
1Reh_kwb AC-1 Reheat Phase B kW
1Reh_kwc AC-1 Reheat Phase C kW
1AC_SAT AC-1 Supply Air Temp (F)
1AC_SAH AC-1 Supply Air Humidity (%)
1AC_RAT AC-1 Return Air Temp (F)
1AC_RAH AC-1 Return Air Humidity (%)
1AC_SWT AC-1 Supply Water Temp (F)
1AC_RWT AC-1 Return Water Temp (F)
TABLE 4. DATA TABLE K20 - T403 POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
6AC_kwa AC-6 Phase A kW
6AC_kwb AC-6 Phase B kW
6AC_kwc AC-6 Phase C kW
6SF_kwa AC-6 Supply Fan Phase A kW
6SF_kwc AC-6 Supply Fan Phase C kW
6Comp_kwa AC-6 Compressor Phase A kW
6Comp_kwb AC-6 Compressor Phase B kW
6Comp_kwc AC-6 Compressor Phase C kW
6Hum_kwa AC-6 Humidifier Phase A kW
6Hum_kwb AC-6 Humidifier Phase B kW
6Hum_kwc AC-6 Humidifier Phase C kW
6Reh_kwa AC-6 Reheat Phase A kW
6Reh_kwb AC-6 Reheat Phase B kW
6Reh_kwc AC-6 Reheat Phase C kW
9SF_kwa AC-9 Supply Fan Phase A kW
9SF_kwc AC-9 Supply Fan Phase C kW
6AC_SAT AC-6 Supply Air Temp (F)
6AC_SAH AC-6 Supply Air Humidity (%)
6AC_RAT AC-6 Return Air Temp (F)
6AC_RAH AC-6 Return Air Humidity (%)
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 26
Design & Engineering Services December 2010
TABLE 5. DATA TABLE K20 - T404 POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
9AC_kwa AC-9 Phase A kW
9AC_kwb AC-9 Phase B kW
9AC_kwc AC-9 Phase C kW
9Comp_kwa AC-9 Compressor Phase A kW
9Comp_kwb AC-9 Compressor Phase B kW
9Comp_kwc AC-9 Compressor Phase C kW
9Hum_kwa AC-9 Humidifier Phase A kW
9Hum_kwb AC-9 Humidifier Phase B kW
9Hum_kwc AC-9 Humidifier Phase C kW
9Reh_kwa AC-9 Reheat Phase A kW
9Reh_kwb AC-9 Reheat Phase B kW
9Reh_kwc AC-9 Reheat Phase C kW
13AC_kwa AC-13 Phase A kW
13AC_kwb AC-13 Phase B kW
13AC_kwc AC-13 Phase C kW
9AC_SAT AC-9 Supply Air Temp (F)
9AC_SAH AC-9 Supply Air Humidity (%)
9AC_RAT AC-9 Return Air Temp (F)
9AC_RAH AC-9 Return Air Humidity (%)
9AC_SWT AC-9 Supply Water Temp (F)
9AC_RWT AC-9 Return Water Temp (F)
TABLE 6. DATA TABLE K20 - T406 POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
4AC_kwa AC 4 Phase A kW
4AC_kwb AC 4 Phase B kW
4AC_kwc AC 4 Phase C kW
5AC_kwa AC 5 Phase A kW
5AC_kwb AC 5 Phase B kW
5AC_kwc AC 5 Phase C kW
7AC_kwa AC 7 Phase A kW
7AC_kwb AC 7 Phase B kW
7AC_kwc AC 7 Phase C kW
8AC_kwa AC 8 Phase A kW
8AC_kwb AC 8 Phase B kW
8AC_kwc AC 8 Phase C kW
10AC_kwa AC 10 Phase A kW
10AC_kwb AC 10 Phase B kW
10AC_kwc AC 10 Phase C kW
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 27
Design & Engineering Services December 2010
TABLE 7. DATA TABLE K20 - T407 POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
6Cond_kwa AC-6 Condenser Phase A kW
6Cond_kwb AC-6 Condenser Phase B kW
6Cond_kwc AC-6 Condenser Phase C kW
PRCond1_kwa Print Room Condenser Phase A kW
PRCond1_kwb Print Room Condenser Phase B kW
PRCond1_kwc Print Room Condenser Phase C kW
PRAHU_kwa Print Room Leibert Phase A kW
PRAHU_kwb Print Room Leibert Phase B kW
PRAHU_kwc Print Room Leibert Phase C kW
TLAB1_kwa Tech Lab Panel 1 Phase A kW
TLAB1_kwb Tech Lab Panel 1 Phase B kW
TLAB1_kwc Tech Lab Panel 1 Phase C kW
TLAB2_kwa Tech Lab Panel 2 Phase A kW
TLAB2_kwb Tech Lab Panel 2 Phase B kW
TLAB2_kwc Tech Lab Panel 2 Phase C kW
TABLE 8. DATA TABLE K20 - T409 POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
2AC_kwa AC-2 Phase A kW
2AC_kwb AC-2 Phase B kW
2AC_kwc AC-2 Phase C kW
3AC_kwa AC-3 Phase A kW
3AC_kwb AC-3 Phase B kW
3AC_kwc AC-3 Phase C kW
7Cond_kwa AC-7 Condenser Phase A kW
7Cond_kwb AC-7 Condenser Phase B kW
7Cond_kwc AC-7 Condenser Phase C kW
PRCond2_kwa Print Room Condenser 2 Phase A kW
PRCond2_kwb Print Room Condenser 2 Phase B kW
PRCond2_kwc Print Room Condenser 2 Phase C kW
KVM_kwa KVM Room Panel Phase A kW
KVM_kwb KVM Room Panel Phase B kW
KVM_kwc KVM Room Panel Phase C kW
TABLE 9. DATA TABLE E1ST POINT LIST
POINT ID POINT DESCRIPTION
dt Date and time
StaticSw2 Static Switch #1 Total kW
StaticSw1 Static Switch #2 Total kW
DC1CTwrs Data Center Cooling Towers and Pump Total kW
TABLE 10. DATA TABLE PLANT POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
OAT Outside Air Temp (F)
OAH Outside Air Humidity (%)
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 28
Design & Engineering Services December 2010
TABLE 11. DATA TABLE TOWER33 POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
CWST Closed Loop Condenser Water Supply Temp (F)
CWRT Closed Loop Condenser Water Return Temp (F)
TABLE 12. DATA TABLE CWP POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
KW1 Phase A kW
KW2 Phase B kW
KW3 Phase C kW
AvgVolt Average voltage
AvgAmp Average Amps
KW Hour Total Pump kWh
TABLE 13. DATA TABLE RSVIEW POINT LIST
POINT ID POINT DESCRIPTION dt Date and time
HXSTemp Heat Exchanger Supply Water Temp
HXRTemp Heat Exchanger Return Water Temp
Twr3Flow Cooling Tower 3 Flow (gpm)
Twr3TempIN Cooling Tower 3 Inlet Temp (F)
Twr3TempOut Cooling Tower 3 Outlet Temp (F)
Twr4Flow Cooling Tower 4 Flow (gpm)
Twr4TempIN Cooling Tower 4 Inlet Temp (F)
Twr4TempOut Cooling Tower 4 Outlet Temp (F)
TABLE 14. CRAC SPECIFICATIONS
UNIT # MODEL # SERIAL # TONS COND. DESIGN
CFM
HUMIDIFIER
DESIGN KW
FAN
DESIGN
HP
CRAC-1 FE267W-AGES 365350-003 20 Water 10,200 9.6 7.5
CRAC-2 FE267W-AGES 365350-005 20 Water 10,200 9.6 7.5
CRAC-3 FE267W-AGES 365350-001 20 Water 10,200 9.6 7.5
CRAC-4 FE267W-AGES 365350-004 20 Water 10,200 9.6 7.5
CRAC-5 FE267W-AGES 365350-002 20 Water 10,200 9.6 7.5
CRAC-6 DH380AAGE1 393233-003 30 Air 15,200 9.6 10
CRAC-7 DH380AAGE1 393233-001 30 Air 15,200 9.6 10
CRAC-8 DH412WUAGES 524730-003 30 Water 15,200 9.6 10
CRAC-9 DH412WUAGES 524730-001 30 Water 15,200 9.6 10
CRAC-10 DH412WUAGES 524730-002 30 Water 15,200 9.6 10
Cond-6 CDF510CA 0037C37657
Cond-7 CDF510CA 0037C37659
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 29
Design & Engineering Services December 2010
TABLE 15. ONE-TIME WATER FLOW MEASUREMENTS
POINT DATE/TIME MEASURED MEASURED FLOW (GPM) CRAC-1 2/7/09 – 16:30 20.5
CRAC-2 2/7/09 – 12:15 53.7
CRAC-3 2/7/09 – 14:30 34.8
CRAC-4 2/7/09 – 14:50 0
CRAC-5 2/7/09 – 12:40 0
CRAC-6 NA NA
CRAC-7 NA NA
CRAC-8 2/7/09 – 15:30 0
CRAC-9 2/7/09 – 15:55 56.5
CRAC-10 2/7/09 – 16:45 94.3
Closed Cooling Loop 2/7/09 – 11:15 428.3
Tower-3 Open Loop 2/7/09 – 09:00 662.8
Tower-4 Open Loop 2/7/09 – 10:15 641.9
TABLE 16. ONE-TIME AIR FLOW MEASUREMENTS
POINT DATE MEASURED MEASURED FLOW (CFM) CRAC-9 2/7/09 20.5
CRAC-6 2/7/09 18,391
IBM Mobile Measurement Technology ET08SCE1030
Southern California Edison Page 30
Design & Engineering Services December 2010
REFERENCES 1 Koomey, Jonathan G. (February 15, 2007), "Estimating Total Power Consumption by
Servers in the U.S. and the World". Final Report, Lawrence Berkeley National Laboratory.
2 Tschudi, William (March 30, 2004), "Energy Efficient Data Centers". Final Report,
Lawrence Berkeley National Laboratory.