PT.JURONG ENGINEERING LESTARI Last year 2015 we have gone through a successful re-structuring of PT.JEL. We are back on track and profitable again a er last year re-structuring. During the re-structuring we focus on grooming our exis ng poten al, capable, loyal and young staffs. As such, we have developed a training program for our staff in order to pursue their career path in PT.JEL. Both management and technical staffs are considered. PT.JEL will have more jobs coming as we are supported by our parent company, JEL (Singapore) therefore we need to groom and grow ourselves in PT.JEL in order to support the growth of JEL Group, be it in Indonesia or outside Indonesia. This year we have two on going projects. They are Ulubelu#3&4 Geothermal Power Plant equipment Installa on project and SMI Ethylene Booster Compressor Installa on project to be completed this year. One new Banggai Ammonia Plant Piping Work project to be started this year and to be completed by 4th quarter of year 2017. We are expec ng to secure more projects within this year in order to sustain our growth to beyond 2017. Therefore, we need to focus on performing our exis ng project with safety as first priority. We need to ensure our projects are performed with high produc vity and quality. Last year much improved performance is very much due to our more commi ed and cohesive Project Management team. It is also due to more energe c and responsive Site Management team. In order to repeat our last year performance we need to con nue to search, iden fy and groom our younger and poten al staffs. We need to recognize our staff performance by merit. Let's move forward together with pride and achieve another successful year! Yap Chee Lung President Director 10-Feb-2016 M F P D O PTJEL Oct—Dec 2015 Issues INSIDE THIS ISSUE: Message From P.D 1 Finance Department 2 Human Resource Department 3 Material Control & Procurement Depart- ment 5 EHS Department 7 Projects Update 9 I N

I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Embed Size (px)

Citation preview

Page 1: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

P T. J U R O N G E N G I N E E R I N G L E S TA R I

Last year 2015 we have gone through a successful re-structuring of PT.JEL. We are back ontrack and profitable again a er last year re-structuring.

During the re-structuring we focus on grooming our exis ng poten al, capable, loyal andyoung staffs. As such, we have developed a training program for our staff in order topursue their career path in PT.JEL. Both management and technical staffs are considered.

PT.JEL will have more jobs coming as we are supported by our parent company, JEL(Singapore) therefore we need to groom and grow ourselves in PT.JEL in order to supportthe growth of JEL Group, be it in Indonesia or outside Indonesia.

This year we have two on going projects. They are Ulubelu#3&4 Geothermal Power Plantequipment Installa on project and SMI Ethylene Booster Compressor Installa on projectto be completed this year. One new Banggai Ammonia Plant Piping Work project to bestarted this year and to be completed by 4th quarter of year 2017. We are expec ng tosecure more projects within this year in order to sustain our growth to beyond 2017.Therefore, we need to focus on performing our exis ng project with safety as first priority.We need to ensure our projects are performed with high produc vity and quality.

Last year much improved performance is very much due to our more commi ed andcohesive Project Management team. It is also due to more energe c and responsive SiteManagement team.

In order to repeat our last year performance we need to con nue to search, iden fy andgroom our younger and poten al staffs. We need to recognize our staff performance bymerit.

Let's move forward together with pride and achieve another successful year!

Yap Chee LungPresident Director10-Feb-2016

M F PD O PTJEL

O c t — D e c 2 0 1 5 I s s u e s

I N S I D E T H I S I S S U E :

Message From P.D 1

Finance Department 2

Human ResourceDepartment

3

Material Control &Procurement Depart-ment

5

EHS Department 7

Projects Update 9

I N

Page 2: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

We would like to warmly introduce our PTJELFinance teams which basically consist of 2departments. 1) Accounting Department tosupport for the monthly reporting to JEL HQand maintain proper filling on accountingdocuments. 2) Treasury and Tax Department tosupport for Company’s operation and taxrelated matter. PTJEL Finance team is led byMr. Jack Putra as Finance Head of Department.

Currently we are using SAP-ERP system for themonthly financial reporting. And for upcomingfinancial year in 2017, there will be change forthe financial year end from (January -December) to (April – March) as in compliancewith JEL HQ.

Every year our staffs attend Seminar and Training to improve our knowledge and capability to keepup on any update of regulation related to finance, accounting and tax .

We are pleased to announce our Site FinanceOfficer for our ongoing Ulubelu 3 & 4 –2x55MW Geothermal PP Project is Mr. Sigit asshown in photo on the left.

Page 2

Site Finance Officer Announcement For New Project Secured

H.O Finance Team General Introduction

“Finance Department”

PTJEL Finance team members (from left to right):Delis, Yenny, Andrias, Jack, Mutiara and Farha

Volume 1 , Issue 1

Mr Wawan Setiawan

Mr Sigit Suparjiyanto

We are also pleased to announce our SiteFinance Officer for our newly secured Bang-gai Ammonia Plant Utility Piping Work pro-ject is Mr. Wawan Setiawan as shown inphoto on the right.

Page 3: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter Page 3

Site HR Officer Announcement for New Project Secured

Mr. Sukowiyono joined PTJEL since 26th January 2012 as Site Document ControlOfficer for NSI Project. On the 5th February 2013 he was assigned as Site Docu-ment Control Officer and assisting to prepare technical progress report at Bon-tang Kaltim 5 Project. On the 4th May 2015 he was assigned as Site DocumentControl Officer at CAPECCx Project at PT. Chandra Asri Petrochemical Plant inCilegon. On 13th November 2015 he was assigned as Welding Checker for QCDepartment at ECR – TAM Project in PT. Chandra Asri Petrochemical Plant in Ci-legon. On the 5th January 2016 he was assigned as Cost Controller Assistant at

Ethylene Booster Compressor Installation Project at PT.Styrindo Mono Indonesia – Cilegon. He has performedwell consistently for 6 projects consecutively.

Our management recognized his good work perfor-mance. Therefore he is selected to be trained as a certi-fied Welding Inspector at University of Indonesia’s Re-source Center of Material Science (RCMS).

Congratulation to Mr. Sukowiyono!

“Human ResourceDepartment”

Mr. Sukowiyono

Mr. Beny Sulaiman

SELECTED STAFF FOR TECHN ICAL TRA IN ING

PTJEL secured a new Project from PT. Rekind for theUtility Piping Work at Banggai Ammonia Plant Project(BAP) in Central Sulawesi.

Therefore we are pleased to announce Mr. Benny Su-laeman as Site HR Officer to lead Site Human Re-source Department.

We are also pleased to announce Mr. Syahril Hamidias GA & Community Development Officer to assist Mr.Benny Sulaeman.

Mr. Syahril Hamidi

Page 4: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

We are pleased to announce that PT.JEL is par cipa ng JEL’s Group Development Program.JEL Development Program’s purpose is to train our poten al Engineers as our next genera-

on of Site Managers and Leaders.PT.JEL’s Management has selected 3 most suitable and qualified PT.JEL’s staffs to a end thisDevelopment Program which will be couched by training providers like Cegos, SIM Universi-ty, MDIS and Kaplan. This Development Program will take 3 years to complete.In the near future, PT.JEL will start to have our own Development Program for our nextbadge of next genera on of Site Managers and Leaders.Congratula on to the below selected 3 staffs!!!

Page 4

Selected Staff for Management Training in JEL Group.

Mr. Gatot Widiyanto is our Site Manager at PT. Styrindo MonoIndonesia’s Ethylene Booster Compressor Installation Project atCilegon.

“Human ResourceDepartment”

Trisna Gunawan

Antos Sriandi

Mr. Antos Sriandi was our Site Manager at CAPECCxProject in PT. Chandra Asri Petrochemical Plant.

He has also just completed the PT.CAP HGPI project& Major Inspection GT#11 at PLTGU Sengkang.

Trisna Gunawan is our Site Manager for Banggai AmmoniaPlant Utility Piping Installation Project at Central Sulawesi.

Mr Trisna Gunawan

Mr Antos Sriandi

Mr Gatot Widiyanto

Page 5: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter

SAP is a software used in our company to support business processintegration. In this MM Module’s data entry is to create purchaserequisition and good receipt release on system. The data entry isused to be performed by Mr. Khuluq but is now performed by Ms SriLukmiati Sari. This task was handed over by Mr.Khusnul Khuluq toMs.Sri Lukmiati Sari. Mr. Khuluq’s present task is to provide supportto Ms. Sari if there is any problems. Mr. Khuluq’s primary new task isto complete the inventory of PT.JEL’s tools and assets in Tools Cen-ter in Cilegon.

Page 5

Mr.Ngadirin Has Obtained SIOP For Operating Crawler Crane

N E W S A P D A T A E N T R Y F O R M A T E R I A L C O N T R O LM O D U L E , M S S R I L U K M I A T I S A R I

We are pleased to announce our Tools Center supervisor Mr. Ngadirin has obtained (SIO)license to operate crawler crane operator on 1st January, 2016. He is certified to operatecrawler crane up to 50T capacity

“Material Control &Procurement Dept.”

Mr Ngadirin’s SIO

Site Material Control Officer Announcement For New ProjectWe are pleased to announce our site material controlofficer for our newly secured Banggai Ammonia PlantUtility Piping Work project is Mr.Merlang Indra.

He is trained and briefed about PT.JEL’s Material Con-trol Procedure and Policy prior to mobilizing to Banggaisite

Mr Khuluq Training Mr Merlang IndraMaterial Control Procedure forBanggai Ammonia Project

Page 6: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter Page 6

P T . J E L ’ S S T A N D A R D I Z E O F F I C E R C O N T A I N E RA P P E A R A N C E

“Material Control &Procurement Dept.”

We are pleased to announce our PT.JEL’s Standardize Office ContainerAppearance as per below sketch.

Page 7: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

In order to improve and ensure all site complies to PT.JEL’s EHS Plan, we have anintroduction meeting to introduce our new EHS’s Coordinator and Auditor, Ms. Novaon the 3rd February 2016 at PT. Jurong Engineering Lestari’s Head Office in Jakarta.The meeting was conducted by PT.JEL’s President Director, Mr. Yap. This meetingwas attended by Safety Representative from all PT.JEL’s Project. They are Mr. ErryGunawan Safety Coordinator from Ulubelu Project, Mr. Arif Hakim Safety Coordinatorfrom SMI Project and Mr. Novitra Safety Coordinator from Banggai Project.The first agenda for this EHS meeting is to introduce PT. JEL’s New EHS Coordinator& Auditor, Ms. Novalia Zahroini (Nova). She will replace Mr. Job Purba. For functionaljob, all site safety must reported direct to EHS Coordinator & Auditor. .After lunch we are continue meeting about PT. JEL’s EHS Policy & Procedure briefingconducted by EHS Department Coordinator & Auditor. JEL EHS Policy & Proceduremust be share to all Site Safety. The Last Agenda is about EHS Best Project selectionCriteria Formulation, quarterly we will choose one EHS Best Project. The Criteria hasbeen agreed for selection and is in compliance to PT. JEL KPI (Key Performance Indi-cator), Near Missed Incident must be reported, project program compliance.

Page 7

I N T R O D U C T I O N O F P T . J E L ’ S N E W H S E ’ SC O O R D I N A T O R & A U D I T O R , M S . N O V A L I AZ A H R O I N I ( N O V A )

“EHS Department”

Ms. Novalia, Mr. Novitra, Mr. Erry , Mr. Arif Hakim (from right to left)

Page 8: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Contractor Safety Management System (CSMS) is a standard provides requirements which manage-ment level, contractor and subcontractor must meet and follow when engaged by company for anywork. Company’s objective is for contractor to be working to a satisfactory standard meeting all com-pany and legislative regulation.

CSMS is evidence that PT. Jurong Engineering Lestari (JEL ) committed to the management of safety,health and environment. This standard provides guidelines that all parties must follow to ensureOEHS (Occupational Environmental Health and Safety) is managed during the course of business.

We must proud to announce that our CSMS score for PT.REKIND has improved from 57% in year2014 to 76% in year 2015. With a 76% score, our company is qualified to participate in PT.REKIND’sOil & Gas Project too.

We must keep increase our qualification and implementation for environment, health and safety. Ifwe want our project to complete safely, create solid safety specifications. Every job should begin witha thorough risk assessment where the applicable hazards and risks are identified, analyzed andprioritized. Then we can implement specifications to make sure risks are reduced to acceptable lev-els.

CSMS is arguably the most important part of our management. This can be accomplished throughlooking for a combination of lagging indicators (e.g. AFR (Accident Frequency Rate), ASR (AccidentSeverity Rate, incidents rates etc.) and leading indicators (looking at the management systems thatare in place, internal training programs, tool box meeting, etc)

Page 8

Contractor Safety Management System( CSMS ) By PT.REKIND

“EHS Department”

Certificate Contractor Safety Management System ( CSMS ) By Rekind

Page 9: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter

Project Name : Banggai Ammonia Plant ProjectClient : PT Rekayasa IndustriOwner : PT Panca Amara Utama (PAU)Location : Banggai, Luwuk, Central Sula

wesiDuration : 18 Months ( 1 March 2016 –

31 August 2017)Site Manager : Trisna GunawanScope of Works : Utility Package #3, Piping Work

Fabrication and Installation.

Project Name : Ulubelu Unit 3 & 4 Geothermal Power Project, 2 x 55 MWClient : PT Rekayasa IndustriOwner : PT Pertamina Geothermal Energy (PGE)Location : Ulubelu, Tanggamus, Lampung, IndonesiaDuration : 16 Months ( 24 August 2015 – 24 December 2016)Site Manager : Deny Wahayu SusantoScope of Works : Mechanical erection for 2 x 55MW

Page 9

O N G O I N G P R O J E C T : G T 1 1 C - I N S P E C T I O N M A J O R

O V E R H A U L S E N G K A N G C O M B I N E D C Y C L E P O W E R

P L A N T

Newly Secured Project: Banggai Ammonia Plant,Banggai, Luwuk, Central Sulawesi

O N G O I N G P R O J E C T : U L U B E L U U N I T 3 & 4 G E O T H E R M A L P O W E RP R O J E C T , 2 X 5 5 M W O N U L U B E L U , T A N G G A M U S , L A M P U N G ,I N D O N E S I A

Project Name : GT 11 C-Inspection Major Overhaul

Client : PT Consolidated Electric Power AsiaLocation : Sengkang Combined Cycle Power Plant

Jln PLTGU Ds Patila,Kec Pammana, KabWajo,South Sulawesi

Duration : 1 Month ( January 2016 –February 2016 )

Team Leader : Antos Sriandi.

“ P R O J E C TU P D A T E ”

Our Ulubelu 2 x 55MW GeothermalPower Plant Project Team

Our Sengkang Project Team

Our BAP Project Team In PT.JEL H.O

Page 10: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter

Project Name : INSTALL NEW ETHYLENE BOOSTER COMPRESSOR

Client : PT. STYRINDO MONO INDONESIA (PT.SMI)Location : PULOAMPEL – SERANG – BANTENDuration : 7 Months ( October 2015 – April 2016)Site Manager : Gatot WidiyantoScope of Works : Install new ethylene booster compressor

Project Name : Provide Destination Line PV-8701B,PV-8702B, PV-8703B toLP Flare

Client : PT. Chandra Asri PetrochemicalLocation : Anyer, Banten - IndonesiaDuration : 1 Month and 3 Weeks (July 5th,

2015 ~ August 30th, 2015)Site Manager : Arche Husni

Page 10

C P : T E C R P I P I N GP A C K A G E 1 T A M - C A P A N Y E R - C I L E G O N

ON GOING PROJECT: INSTALL NEW ETHYLENE BOOSTERCOMPRESSORPULOAMPEL – SERANG – BANTEN

C O M P L E T E D T H E W O R K O N P R O V I D E D E S T I N A T I O N L I N E P V -8 7 0 1 B , P V - 8 7 0 2 B , P V - 8 7 0 3 B T O L P F L A R E A N Y E R , B A N T E N

Project Name : ECR PIPING PACKAGE 1 TAM-CAP

2015

Client : PT. CHANDRA ASRI PETROCHEMI

CAL

TYPE OF PROJECT : TURN AROUND MAINTENANCE

Location : Sengkang Combined Cycle Power

Duration : 5 Month ( August 2015 – December

2016 )

Team Leader : Gatot Widiyanto

“ P R O J E C TU P D A T E ”

Our PV Line Project Team

Our ECR Piping Project Team

SMI Project Team

Page 11: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Internal Newsletter

Project Name : GTG Hot Gas Path InspectionClient : Alstom Service – SurabayaLocation : Chandra Asri Petrochemical

Plant – Anyer – CilegonDuration : 1 Months ( October 2015 –

November 2015)Site Manager : Antos SriandiScope of Works : Hot Gas Inspection & Electri

cal/ Instrument Work .

Project Name : STG & Boiler Batu Bara Plant Project

Client : PT Rekayasa Industri

Owner : PT PUSRI Palembang

Loca on : Palembang, South Sumatera, Indonesia

Dura on : 8 Months ( 27 October 2014 – 8 July 2015)

Site Manager: Deny Wahayu Susanto

Scope of Works : Underground and RWI Piping Work

Page 11

C O M P L E T E D P R O J E C T : W O R K O N I M P R O V E M E N TO F H P E T H Y L E N E P I P E A T R A G A SB R I G D E , K A M P U N G R A G A S - B O J O N E G A R A , B A N T E N

Completed Project: GTG Hot Gas Path Inspection

Chandra Asri Petrochemical Plant – Anyer – Cilegon

C O M P L E T E D P R O J E C T : S T G & B O I L E R B A T U B A R A P L A N TP R O J E C T P A L E M B A N G , S O U T H S U M A T E R A , I N D O N E S I A

Project Name : IMPROVEMENT HP ETHYLENE PIPE

AT RAGAS BRIGDE

Client : PT. CHANDRA ASRI

PETROCHEMICA

Location : Kampung Ragas - Bojonegara,

Banten

Duration : 1 Month ( October 2015 –

November 2015 )

Team Leader : Maman Surahman

“ P R O J E C TU P D A T E ”

Our Team GHPI

Project Completion dinner

Lowering New Pipe Spool

Page 12: I N M F P D O PTJEL - PT. Jurong Engineering Lestariptjel.com/images/files/News/2015 - Dec.pdf · & Major Inspection GT#11 at PLTGU Sengkang. Trisna Gunawan is our Site Manager for

Head office:10th Floor Maspion PlazaJalan Gunung Sahari Raya Kavling 18Jakarta 14420, Indonesia

P T . J U R O N G E N G I N E E R I N GL E S T A R I

A Subsidiary ofJurong Engineering Limited

We’re on the Web!www.ptjel.com

C P R O J E C T : W A T E R T R E A T M E N T & W A S T E

W A T E R T R E A T M E N T P L A N T C H A N D R A A S R I

Project Name : Water Treatment & Waste Water Treatment Plant

Client : Toyo Engineering – IKPT

Location : Chandra Asri Petrochemical Plant – Anyer – Cilegon

Duration : 12 months (Dec’14 to Nov’15)

Scope : Installation of Mechanical Eqpt., Structure & Piping.

Site Manager : Antos Sriandi

Our WT & WTP Project Team

WT & WTP Project Tool BoxMeeting

Project Name : Patuha 1 x 55MW GPP 1st Year Maintenance Project

Client : Toshiba Corporation (under Marubeni Corporation)

Location : Patuha, Ciwidey, Bandung, Indonesia

Duration : 1 Month ( 1st – 30th September 2015)

Scope : Modification Mechanical Work and Assist Toshiba

Site Manager : Arief Khoirudin

C P R O J E C T : P 1 5 5 M W GP P 1 Y M P

Replacement Work In Progress