Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
I-435 South Loop Link Design-Build Project
About the Region
Project Location
Replace/Rehab Bridges Wornall Holmes 104th Street Corridor Resurfacing
Corridor Mobility Study (155,000 VPD) Finding: Add Lanes Remove Loop Ramps at
Holmes
Purpose and Need
Project Area
Project Area PM Peak Hour Congestion
Project Goals
1. Deliver the project utilizing a diverse workforce by May 1, 2020 within the program budget of $74.8 million.
2. Minimize impacts to the traveling public during construction.
3. Maximize safety and peak period travel speeds on the I-435 corridor.
4. Minimize future maintenance needs.
• Deal Breakers:
• Reconstruct Bridges over Wornall and Holmes.
• Replace the deck and rehabilitate the bridge over 104th.
• Provide a new riding surface on I-435 and ramps.
• Improve mobility and safety along the I-435 corridor.
• Construct new sidewalk along Stateline Road. 3/19/2019 8
Configuration Requirements
Awarded as the Best Value Proposer
Challenges and Solutions
Project Goals
Minimize Impacts to Traffic During Construction Minimize Future Maintenance Maximize Safety and Peak Period Travel Speeds
3/19/2019 11
Concrete Overlay
3/19/2019 13
Wor
nall
Roa
d
I-435
3/19/2019 14
Single Span Bridges
3/19/2019 16
Hol
mes
Roa
d I-435
3/19/2019 17
https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=imgres&cd=&cad=rja&uact=8&ved=&url=https://www.usbank.com/index.html&psig=AOvVaw2bGPlQrztERDF16F_vfnx-&ust=1524688904963760https://grad.webster.edu/
3/19/2019 18
Phase 0 Install erosion control & clear slopes Prepare median shoulders Construct MSE walls at Holmes Provide turn lanes at Holmes and close loop ramps
Phase 1A 1. Move traffic towards median in 4 lanes 2. Widen slopes, construct retaining walls 3. Construct outside 5th lane, auxiliary lane & shoulder 4. Construct new bridges adjacent Wornall & Holmes bridges 5. Begin bridge deck widening at 104th and Blue River
3/19/2019 20
Phase 1B 1. Continue Phase 1 bridge construction 2. Move ramps to new ramp pavement 3. Construct remainder of ramp width
3/19/2019 21
Phase 1C & 1D 1. Pave remainder of Phase 1 2. Complete all ramp paving 3. Ramps complete and in final configuration
3/19/2019 22
Phase 2 1. Move 2 lanes of traffic to the new outside lanes 2. Leave 2 lanes of traffic adjacent to the median barrier 3. Construct the new lanes between the travel lanes
3/19/2019 23
Phase 2 (cont.) 1. Move 2 lanes of traffic to the new outside lanes 2. Leave 2 lanes of traffic adjacent to the median barrier 3. Construct second phase of new bridges.
3/19/2019 24
Phase 3 1. Move all 4 lanes to new pavement (outside) 2. Construct median pavement 3. Construct median side of bridges
3/19/2019 25
Phase 3B 1. Complete the deck replacement of the 104th St. Bridge
3/19/2019 26
Phase 3C 1. Complete all remaining aspects of the project.
• Permanent striping, signing, drainage, grass growth, etc.
Project Complete!
Innovation
Concrete Overlay
3/19/2019 29
RFP New Pavement Section 1. 6” Aggregate Base 2. 1.25” dowels at 15’ o/c 3. 30” tie bars at 30” o/c 4. 11” PCCP
RBE Overlay Section 1. Existing UBAWS interlayer 2. 1.5” dowels at 12’ o/c 3. 18” tie bars at 24” o/c 4. 8.5” PCCP Min. (Avg 10.5”)
Innovative Coping
3/19/2019 30
Innovative Coping
3/19/2019 31
Unexpected Issues…
3/19/2019 33
Encountered composite soil pins during clearing Impacted NE, NW quadrants at Wornall, SE quadrant Holmes
3/19/2019 34
Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes
3/19/2019 35
Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes
3/19/2019 36
Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes
3/19/2019 37
Encountered composite soil pins during clearing Impacted NE, NW quadrants at Wornall, SE quadrant Holmes
3/19/2019 38
3/19/2019 39
3/19/2019 40
Previous Experimental Soil Stabilization Project Solution was to replace unstable material
3/19/2019 41
Previous Experimental Soil Stabilization Project Substantial undergrading effort
3/19/2019 42
Problem Solved
Unexpected Issues…
3/19/2019 44
Blue River Bearings
Blue River Bearings
13 of 19 bearings rocked beyond design
2 adjacent bearings on WB bridge in failure
WB bridge slab dropped 1.5” at lanes 2 & 3
3/19/2019 46
Blue River Bearings
3/19/2019 47
Blue River Bearings
3/19/2019 48
Blue River Bearings
Field Update
Construction commenced with the issuing of NTP-2 3-23-18
WB I-435 in phase 2B construction
EB I-435 in phase 1B construction (90% paved)
Blue River bridge widening nearly complete
104th St UPRR bridge in slab construction phase
KC ‘18/’19 Winter precipitation = 41 days and counting
3/19/2019 50
Potholes!
3/19/2019 51
Recreational Pothole
3/19/2019 52
Decorative Pothole
3/19/2019 53
Spa Relaxation Pothole
3/19/2019 54
Happy Valentine Pothole
3/19/2019 55
Potholes!
3/19/2019 56
Pothole Warning Program
3/19/2019 57
EB I-435 March-April 1. Complete Blue River &
104th St Bridges Phase 1 2. Pave to bridge ends and
complete 104th St ramp
WB I-435 March-April 1. Complete Holmes &
Wornall Phase 2 bridges 2. Pave additional interior
lane project length
3/19/2019 58
EB I-435 May-June 1. Complete Holmes &
Wornall Phase 2 bridges & 104th St Phase 2 re-deck
2. Pave additional interior lane project length
WB I-435 May 1. Complete Holmes &
Wornall Phase 2 bridges 2. Pave additional interior
lane project length
3/19/2019 59
EB I-435 July 1. Pave additional interior
lane project length
WB I-435 June 1. Pave additional interior
lane project length
3/19/2019 60
EB I-435 August-October 1. Pave additional interior
lane project length 2. Make Storm Improvements 3. Holmes/Wornall Phase 3
Bridge Work 4. 104th St Phase 3A Re-deck
WB I-435 August-October 1. Pave additional interior lane
project length 2. Make Storm Improvements 3. Holmes/Wornall Phase 3
Bridge Work 4. 104th St Phase 3A Re-deck
3/19/2019 61
EB I-435 November 1. No work
WB I-435 November 1. Final Re-deck phase
104th St bridge
3/19/2019 62
I-435 Dec. 2019-May 2020 1. Establish seed growth 2. Complete signing 3. Complete permanent
pavement marking
https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=imgres&cd=&cad=rja&uact=8&ved=&url=https://brandongaille.com/16-most-famous-engineering-company-logos/&psig=AOvVaw1W060rts-MCpNNwpT8KZhR&ust=1520530311508037http://www.se3.us/index.phphttp://parsonkc.com/
https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjsq47Nsv7aAhXixYMKHYpbCwgQjRx6BAgBEAU&url=https://www.saintlukesgiving.org/pages/2013/events/paint/ptt-2016/events---paint-2017---sponsors---17&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjsq47Nsv7aAhXixYMKHYpbCwgQjRx6BAgBEAU&url=https://www.saintlukesgiving.org/pages/2013/events/paint/ptt-2016/events---paint-2017---sponsors---17&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwir64rYsv7aAhWB24MKHTDOBNIQjRx6BAgBEAU&url=http://www.acig.com/membership/current-members&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjW9-bksv7aAhUs4oMKHUg1DhEQjRx6BAgBEAU&url=http://peterlclevinger.org/golf-tournament-2015/tournament-sponsors/&psig=AOvVaw0cl8q6WG15YMgvnBt9NVZT&ust=1526153450376606https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiV9Pv4sv7aAhWl64MKHY27Bm0QjRx6BAgBEAU&url=http://www.blackandmcdonald.com/&psig=AOvVaw0IL2GXpJ9Od3KSKADsbkk7&ust=1526153491216927
3/19/2019 65
I-435 South Loop Link�Design-Build Project�About the RegionSlide Number 3Slide Number 4Project AreaProject AreaProject GoalsSlide Number 8Awarded as the Best Value ProposerChallenges and Solutions�Project GoalsConcrete OverlaySlide Number 13Slide Number 14Single Span BridgesSlide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26InnovationConcrete OverlaySlide Number 29Innovative CopingInnovative CopingUnexpected Issues…Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Slide Number 38Slide Number 39Slide Number 40Slide Number 41Slide Number 42Unexpected Issues…Blue River BearingsBlue River BearingsBlue River BearingsBlue River BearingsBlue River BearingsField UpdatePotholes!Recreational PotholeDecorative PotholeSpa Relaxation PotholeHappy Valentine PotholePotholes!Pothole Warning ProgramSlide Number 57Slide Number 58Slide Number 59Slide Number 60Slide Number 61Slide Number 62Slide Number 63Slide Number 64Slide Number 65