I-435 South Loop Link Design-Build Project

I-435 South Loop Link Design-Build Project · 2019. 3. 1. · 3. 18” tie bars at 24” o/c 4. 8.5” PCCP Min. (Avg 10.5”) Innovative Coping . 3/19/2019 30 . Innovative Coping

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

  • I-435 South Loop Link Design-Build Project

  • About the Region

  • Project Location

  • Replace/Rehab Bridges Wornall Holmes 104th Street Corridor Resurfacing

    Corridor Mobility Study (155,000 VPD) Finding: Add Lanes Remove Loop Ramps at

    Holmes

    Purpose and Need

  • Project Area

  • Project Area PM Peak Hour Congestion

  • Project Goals

    1. Deliver the project utilizing a diverse workforce by May 1, 2020 within the program budget of $74.8 million.

    2. Minimize impacts to the traveling public during construction.

    3. Maximize safety and peak period travel speeds on the I-435 corridor.

    4. Minimize future maintenance needs.

  • • Deal Breakers:

    • Reconstruct Bridges over Wornall and Holmes.

    • Replace the deck and rehabilitate the bridge over 104th.

    • Provide a new riding surface on I-435 and ramps.

    • Improve mobility and safety along the I-435 corridor.

    • Construct new sidewalk along Stateline Road. 3/19/2019 8

    Configuration Requirements

  • Awarded as the Best Value Proposer

  • Challenges and Solutions

  • Project Goals

    Minimize Impacts to Traffic During Construction Minimize Future Maintenance Maximize Safety and Peak Period Travel Speeds

    3/19/2019 11

  • Concrete Overlay

  • 3/19/2019 13

    Wor

    nall

    Roa

    d

    I-435

  • 3/19/2019 14

  • Single Span Bridges

  • 3/19/2019 16

    Hol

    mes

    Roa

    d I-435

  • 3/19/2019 17

    https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=imgres&cd=&cad=rja&uact=8&ved=&url=https://www.usbank.com/index.html&psig=AOvVaw2bGPlQrztERDF16F_vfnx-&ust=1524688904963760https://grad.webster.edu/

  • 3/19/2019 18

    Phase 0 Install erosion control & clear slopes Prepare median shoulders Construct MSE walls at Holmes Provide turn lanes at Holmes and close loop ramps

  • Phase 1A 1. Move traffic towards median in 4 lanes 2. Widen slopes, construct retaining walls 3. Construct outside 5th lane, auxiliary lane & shoulder 4. Construct new bridges adjacent Wornall & Holmes bridges 5. Begin bridge deck widening at 104th and Blue River

  • 3/19/2019 20

    Phase 1B 1. Continue Phase 1 bridge construction 2. Move ramps to new ramp pavement 3. Construct remainder of ramp width

  • 3/19/2019 21

    Phase 1C & 1D 1. Pave remainder of Phase 1 2. Complete all ramp paving 3. Ramps complete and in final configuration

  • 3/19/2019 22

    Phase 2 1. Move 2 lanes of traffic to the new outside lanes 2. Leave 2 lanes of traffic adjacent to the median barrier 3. Construct the new lanes between the travel lanes

  • 3/19/2019 23

    Phase 2 (cont.) 1. Move 2 lanes of traffic to the new outside lanes 2. Leave 2 lanes of traffic adjacent to the median barrier 3. Construct second phase of new bridges.

  • 3/19/2019 24

    Phase 3 1. Move all 4 lanes to new pavement (outside) 2. Construct median pavement 3. Construct median side of bridges

  • 3/19/2019 25

    Phase 3B 1. Complete the deck replacement of the 104th St. Bridge

  • 3/19/2019 26

    Phase 3C 1. Complete all remaining aspects of the project.

    • Permanent striping, signing, drainage, grass growth, etc.

    Project Complete!

  • Innovation

  • Concrete Overlay

  • 3/19/2019 29

    RFP New Pavement Section 1. 6” Aggregate Base 2. 1.25” dowels at 15’ o/c 3. 30” tie bars at 30” o/c 4. 11” PCCP

    RBE Overlay Section 1. Existing UBAWS interlayer 2. 1.5” dowels at 12’ o/c 3. 18” tie bars at 24” o/c 4. 8.5” PCCP Min. (Avg 10.5”)

  • Innovative Coping

    3/19/2019 30

  • Innovative Coping

    3/19/2019 31

  • Unexpected Issues…

  • 3/19/2019 33

    Encountered composite soil pins during clearing Impacted NE, NW quadrants at Wornall, SE quadrant Holmes

  • 3/19/2019 34

    Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes

  • 3/19/2019 35

    Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes

  • 3/19/2019 36

    Previous Experimental Soil Stabilization Project Impacted NE, NW quadrants at Wornall, SE quadrant Holmes

  • 3/19/2019 37

    Encountered composite soil pins during clearing Impacted NE, NW quadrants at Wornall, SE quadrant Holmes

  • 3/19/2019 38

  • 3/19/2019 39

  • 3/19/2019 40

    Previous Experimental Soil Stabilization Project Solution was to replace unstable material

  • 3/19/2019 41

    Previous Experimental Soil Stabilization Project Substantial undergrading effort

  • 3/19/2019 42

    Problem Solved

  • Unexpected Issues…

  • 3/19/2019 44

    Blue River Bearings

  • Blue River Bearings

    13 of 19 bearings rocked beyond design

    2 adjacent bearings on WB bridge in failure

    WB bridge slab dropped 1.5” at lanes 2 & 3

  • 3/19/2019 46

    Blue River Bearings

  • 3/19/2019 47

    Blue River Bearings

  • 3/19/2019 48

    Blue River Bearings

  • Field Update

    Construction commenced with the issuing of NTP-2 3-23-18

    WB I-435 in phase 2B construction

    EB I-435 in phase 1B construction (90% paved)

    Blue River bridge widening nearly complete

    104th St UPRR bridge in slab construction phase

    KC ‘18/’19 Winter precipitation = 41 days and counting

  • 3/19/2019 50

    Potholes!

  • 3/19/2019 51

    Recreational Pothole

  • 3/19/2019 52

    Decorative Pothole

  • 3/19/2019 53

    Spa Relaxation Pothole

  • 3/19/2019 54

    Happy Valentine Pothole

  • 3/19/2019 55

    Potholes!

  • 3/19/2019 56

    Pothole Warning Program

  • 3/19/2019 57

    EB I-435 March-April 1. Complete Blue River &

    104th St Bridges Phase 1 2. Pave to bridge ends and

    complete 104th St ramp

    WB I-435 March-April 1. Complete Holmes &

    Wornall Phase 2 bridges 2. Pave additional interior

    lane project length

  • 3/19/2019 58

    EB I-435 May-June 1. Complete Holmes &

    Wornall Phase 2 bridges & 104th St Phase 2 re-deck

    2. Pave additional interior lane project length

    WB I-435 May 1. Complete Holmes &

    Wornall Phase 2 bridges 2. Pave additional interior

    lane project length

  • 3/19/2019 59

    EB I-435 July 1. Pave additional interior

    lane project length

    WB I-435 June 1. Pave additional interior

    lane project length

  • 3/19/2019 60

    EB I-435 August-October 1. Pave additional interior

    lane project length 2. Make Storm Improvements 3. Holmes/Wornall Phase 3

    Bridge Work 4. 104th St Phase 3A Re-deck

    WB I-435 August-October 1. Pave additional interior lane

    project length 2. Make Storm Improvements 3. Holmes/Wornall Phase 3

    Bridge Work 4. 104th St Phase 3A Re-deck

  • 3/19/2019 61

    EB I-435 November 1. No work

    WB I-435 November 1. Final Re-deck phase

    104th St bridge

  • 3/19/2019 62

    I-435 Dec. 2019-May 2020 1. Establish seed growth 2. Complete signing 3. Complete permanent

    pavement marking

  • https://www.google.com/url?sa=i&rct=j&q=&esrc=s&source=imgres&cd=&cad=rja&uact=8&ved=&url=https://brandongaille.com/16-most-famous-engineering-company-logos/&psig=AOvVaw1W060rts-MCpNNwpT8KZhR&ust=1520530311508037http://www.se3.us/index.phphttp://parsonkc.com/

  • https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjsq47Nsv7aAhXixYMKHYpbCwgQjRx6BAgBEAU&url=https://www.saintlukesgiving.org/pages/2013/events/paint/ptt-2016/events---paint-2017---sponsors---17&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjsq47Nsv7aAhXixYMKHYpbCwgQjRx6BAgBEAU&url=https://www.saintlukesgiving.org/pages/2013/events/paint/ptt-2016/events---paint-2017---sponsors---17&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwir64rYsv7aAhWB24MKHTDOBNIQjRx6BAgBEAU&url=http://www.acig.com/membership/current-members&psig=AOvVaw3_0wjrnJL_lLxW9vP6x7ak&ust=1526153401087763https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwjW9-bksv7aAhUs4oMKHUg1DhEQjRx6BAgBEAU&url=http://peterlclevinger.org/golf-tournament-2015/tournament-sponsors/&psig=AOvVaw0cl8q6WG15YMgvnBt9NVZT&ust=1526153450376606https://www.google.com/url?sa=i&source=images&cd=&cad=rja&uact=8&ved=2ahUKEwiV9Pv4sv7aAhWl64MKHY27Bm0QjRx6BAgBEAU&url=http://www.blackandmcdonald.com/&psig=AOvVaw0IL2GXpJ9Od3KSKADsbkk7&ust=1526153491216927

  • 3/19/2019 65

    I-435 South Loop Link�Design-Build Project�About the RegionSlide Number 3Slide Number 4Project AreaProject AreaProject GoalsSlide Number 8Awarded as the Best Value ProposerChallenges and Solutions�Project GoalsConcrete OverlaySlide Number 13Slide Number 14Single Span BridgesSlide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26InnovationConcrete OverlaySlide Number 29Innovative CopingInnovative CopingUnexpected Issues…Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Slide Number 38Slide Number 39Slide Number 40Slide Number 41Slide Number 42Unexpected Issues…Blue River BearingsBlue River BearingsBlue River BearingsBlue River BearingsBlue River BearingsField UpdatePotholes!Recreational PotholeDecorative PotholeSpa Relaxation PotholeHappy Valentine PotholePotholes!Pothole Warning ProgramSlide Number 57Slide Number 58Slide Number 59Slide Number 60Slide Number 61Slide Number 62Slide Number 63Slide Number 64Slide Number 65