hydrogeological investigations

Embed Size (px)

Citation preview

  • 7/30/2019 hydrogeological investigations

    1/24

    1.0 INTRODUCTION

    AngloGold Ashanti (Iduapriem) Limited engaged Geo-Systems Consulting Limited, aHydrogeological and Geo-environmental Engineers to provide hydrogeological services

    leading to the construction of monitoring wells at the Greenfields Tailing Storage Facility.

    The scope of work involves the finding of potential site (geological anomaly) for the

    construction of the monitoring wells and also to identify places of higher resistivity where

    groundwater flow is unlikely. The Geophysical investigations have since been carried out andthis report is on the results obtained.

    Geo-Systems carried out the Hydrogeological studies (Siting) to ensure a smooth and

    successful implementation of the project and also to achieve a high success rate for the

    drilling works by applying the most scientific and appropriate approach to the site selection

    activity. The ensuing pages elaborate on the studies carried out.

    2.0 GEOPHYSICAL SETTING

    A brief description of the physical setting of the project areas are presented in terms of

    geological and hydrogeological conditions, topography, climate, vegetation, and drainage.

  • 7/30/2019 hydrogeological investigations

    2/24

    Attitude measurement on indistinct relict bedding observed in the weathering representative

    of the Banket Series Quartzite at the north western sector of the proposed site show dips of35

    0to the north east.

    Figure 2 1: Geological Map of Proposed TSF Site (Modified after SRK 1997)

  • 7/30/2019 hydrogeological investigations

    3/24

    3.1 Initial studies

    At the inception of the hydrogeological studies, a quick assessment of the terrain was carriedout. Information on the previous drilling activities in the areas was looked at, and other

    relevant hydrogeological information was accessed.

    3.2 Reconnaissance & Field Work

    3.2.1 Field Reconnaissance and Terrain Evaluation

    A Field reconnaissance survey was carried out in the project area to verify, confirm and

    update results of the preliminary information at hand. The essential information gathered

    in the area included; location of existing water supplies sources (boreholes, hand dug

    wells, streams) if any, location of dry holes from previous drilling activities.

    3.2.2 Geophysical profile measurements

    Geophysical profile measurements were carried out at a station interval of 10 meters

    along each traverse. The strategy for geophysical profiling was targeted at medium to

    deeper zones. The main geophysical profiling method applied was the electrical resistivity

    profiling using the Schlumberger array. On-site processing and interpretation of

  • 7/30/2019 hydrogeological investigations

    4/24

    to delineate fractures and aquifer zones, and depth of drilling. Two sites were selected for

    each borehole and prioritized as prime and alternate sites (ie.1st Choice and 2nd Choice).Accessibility of site for drilling machinery was also considered in the selection and

    prioritization of sites.

  • 7/30/2019 hydrogeological investigations

    5/24

    4.0 REPORTING

    In the following section details of work carried out by Geo-Systems in the GreenfieldsTailing Storage Facility, covering background information collection, field reconnaissance

    surveys, geophysical investigations, geophysical investigation results, geophysical data

    analyses and interpretation with tables, graphs, etc. have been presented. Recommendations

    on drilling sites and depths of drilling have also been outlined.

    4.0 LINE 3A1-3A2

    4.1 BackgroundThe line 3A1-3A2 is 300m in length and is located at southernmost part of the Greenfields

    Tailing Storage Facility. The area is covered and underlain by Kawere Conglomerate.

    4.2 Geophysical Investigation

    4.2.1 Horizontal Profiling

    The horizontal profiling was run along the line 3A1-3A2 with a total length of 300m as

  • 7/30/2019 hydrogeological investigations

    6/24

    Table 4.2: VES results and their interpretation

    Site No.

    App. Resistivity

    Range (Ohm-m)

    Expected Aquifer

    zone (m)

    Average

    weathering

    depth (m)

    Remarks

    VES1 4021338 1050 20 Water may occur in

    the weathered

    zone.

    VES2 2691625 1040 15 Water may occur in

    the weathered

    zone.

    4.2.3 Recommendations

    The investigated sites have been ranked as shown in Table 4.3. The recommended

    maximum drilling depths for the various sites may not be exceeded. The decision to stop

    drilling or to continue will be taken by the supervisor on site.

  • 7/30/2019 hydrogeological investigations

    7/24

    SCHLUMBERGER HORIZONTAL PROFILING RESULTS

    LOCATION : GTSF DATE : 16-03-2011

    LINE :3A1-3A2

    20 30 40 50 60 70 80 90 100 110 120 130 140

    20 1291 2788 2031 2160 1899 1652 1909 1905 2174 1254 1464 922 1057

    40 1862 1797 1630 2561 2343 1942 1937 1631 1983 2368 1950 1637 1520

    150 160 170 180 190 200 210 220 230 240 250 260

    20 1265 1613 906 610 473 435 649 701 468 614 476 493

    40 1592 1809 1316 1112 940 1057 1368 1052 900 957 1061 1125

    Figure 4.1: Horizontal profiling results and curves for Line3A1-3A2

    50 100 150 200 250

    100

    1000

    10000

    100000

    VES2

    App.R

    es(ohms-m

    )

    AB/2 (m)

    20m

    40m

    LINE:3A1-3A2

    VES1

  • 7/30/2019 hydrogeological investigations

    8/24

  • 7/30/2019 hydrogeological investigations

    9/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES2 Date :16-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm)

    Mult

    factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 25.03 18.24 1.372 196.11 269.120

    7 0.5 33.41 15.09 2.214 153.21 339.224

    10 0.5 25.42 19.11 1.330 313.50 417.016

    15 0.5 7.71 9.62 0.801 706.36 566.114

    20 0.5 8.02 14.36 0.558 1256.36 701.670

    25 5.0 27.10 6.24 4.343 188.57 818.956

    30 5.0 30.69 10.21 3.006 275.00 826.616

    35 5.0 42.97 18.36 2.340 377.14 882.670

    40 5.0 21.90 11.11 1.971 495.00 975.743

    50 5.0 11.81 7.56 1.562 777.86 1215.145

    58 5.0 15.56 12.45 1.250 1049.40 1311.539

    70 5.0 16.80 16.47 1.020 1532.14 1562.842

    80 10.0 9.94 6.06 1.640 990.00 1623.861

    90 10.0 1257.14

    100 10.0 1555.71

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 4.2b: Vertical electric sounding curves for line3A1-3A2

    P(V)= Potential R(ohm)= Resistance C(I)= Current

    1 10 100

    10

    100

    1000

    10000

    App.R

    es.(

    ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line 3A1 to 3A2 -VES2

  • 7/30/2019 hydrogeological investigations

    10/24

    5.0 LINE 3B1-3B2

    5.1 Background

    The line 3B1-3B2 is 400m in length and is located at the southern part of the Greenfields

    Tailing Storage Facility. The area is covered and underlain by Kawere Conglomerate.

    5.2 Geophysical Investigation

    5.2.1 Horizontal Profiling

    The horizontal profiling was run along the line 3B1-3B2 with a total length of 400m as

    detailed in Table 5.1. Plots of apparent resistivity versus chainage (m) along the traverse

    lines are presented in Figure 5.1. The anomalous points were picked based on both direct

    observation and results of the resistivity readings.

    Table 5.1: Results and interpretation of Horizontal Profiling

    Line Bearing

    (o

    )

    Length

    ( )

    Anomalies Remarks

  • 7/30/2019 hydrogeological investigations

    11/24

    Table 5.2: VES results and their interpretation

    Site No.

    App. Resistivity

    Range (Ohm-m)

    Expected Aquifer

    zone (m)

    Average

    weathering

    depth (m)

    Remarks

    VES3 377792 1060 25 Water may occur in

    the weathered

    zone.VES4 391689 10 - 70 25 Water may occur in

    the weathered zone

    VES5 656 - 1146 10 - 50 20 Water may occur in

    the weathered zone

    VES6 667

    1286 10 - 40 20 Water may occur inthe weathered zone

    VES7 608 - 1613 10 - 30 15 Water may occur in

    the weathered zone

  • 7/30/2019 hydrogeological investigations

    12/24

    SCHLUMBERGER HORIZONTAL PROFILING

    RESULTS

    LOCATION :GTSF DATE : 17-03-2011

    LINE :3B1-3B2

    20 30 40 50 60 70 80 90 100 110 120 130 140 150 160

    20 676 377 457 598 982 626 1653 1984 1258 417 946 1135 489 405 549

    40 647 532 717 1294 1980 1050 1352 1206 1103 1156 734 987 568 369 555

    220 230 240 250 260 270 280 290 300 310 320 330 340 350 360

    20 710 702 759 1081 1198 1911 1361 1674 2021 706 1365 1617 1670 865 2521

    40 737 1201 959 1012 1171 1569 1578 1639 1655 1432 2263 2113 1866 1526 2572

    Figure 5.1: Horizontal profiling results and curves for Line3B1-3B2

    20 40 60 80 100 120 140 160 180

    100

    1000

    10000

    VES4

    App.Res(ohms-m)

    Chainage (m)

    20m40m

    LINE:3B1-3B2

    VES3

    220 240 260 280 300 320 340 360

    100

    1000

    10000

    100000

    VES7VES6

    App.Res(ohms-m)

    Chainage (m)

    20m40m

    LINE:3B1-3B2

    VES5

  • 7/30/2019 hydrogeological investigations

    13/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES3 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm) Mult factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 19.73 6.56 3.007 196.11 589.756

    7 0.5 28.52 8.54 3.340 153.21 511.756

    10 0.5 6.59 4.32 1.526 313.50 478.546

    15 0.5 2.01 3.54 0.567 706.36 400.645

    20 0.5 1.24 4.13 0.301 1256.36 377.546

    25 5.0 15.89 6.56 2.422 188.57 456.756

    30 5.0 9.69 5.45 1.779 275.00 489.089

    35 5.0 9.02 6.65 1.357 377.14 511.634

    40 5.0 5.60 5.21 1.075 495.00 532.132

    50 5.0 3.64 4.87 0.747 777.86 581.312

    58 5.0 3.59 6.12 0.587 1049.40 616.423

    70 5.0 3.33 7.43 0.448 1532.14 686.756

    80 10.0 2.70 3.76 0.717 990.00 709.809

    90 10.0 4.36 7.650 0.570 1257.14 716.534100 10.0 2.42 4.76 0.509 1555.71 792.423

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 5.2a: Vertical electric sounding curves for line3B1-3B2

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100

    10

    100

    1000

    10000

    App.Res.(ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line 3B1 to 3B2 -VES3

  • 7/30/2019 hydrogeological investigations

    14/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES4 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm)

    Mult

    factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 26.24 7.32 3.585 196.11 702.980

    7 0.5 21.08 4.77 4.422 153.21 677.508

    10 0.5 12.42 6.13 2.025 313.50 634.870

    15 0.5 1.56 2.07 0.754 706.36 532.756

    20 0.5 2.56 6.89 0.372 1256.36 467.453

    25 5.0 23.68 9.13 2.594 188.57 489.131

    30 5.0 6.88 3.66 1.882 275.00 517.423

    35 5.0 6.00 4.76 1.261 377.14 475.645

    40 5.0 8.01 9.65 0.830 495.00 410.798

    50 5.0 3.44 6.85 0.503 777.86 391.423

    58 5.0 2.02 5.07 0.398 1049.40 417.645

    70 5.0 1.30 4.13 0.314 1532.14 481.534

    80 10.0 1.19 2.22 0.537 990.00 531.76890 10.0 3.59 7.31 0.491 1257.14 616.813

    100 10.0 2.35 5.31 0.443 1555.71 689.067

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 5.2b: Vertical electric sounding curves for line3B1-3B2

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100

    10

    100

    1000

    10000

    App.Res.(ohms-m)

    AB/2(m )

    Schlumberger VES at Line 3B1 to 3B2 -VES4

  • 7/30/2019 hydrogeological investigations

    15/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES5 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm) Mult factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 18.91 5.65 3.347 196.11 656.481

    7 0.5 31.38 6.45 4.865 153.21 745.323

    10 0.5 19.37 7.68 2.523 313.50 791.112

    15 0.5 4.43 4.08 1.086 706.36 767.418

    20 0.5 1.94 3.43 0.566 1256.36 710.659

    25 5.0 22.85 6.09 3.753 188.57 707.619

    30 5.0 24.75 9.67 2.559 275.00 703.756

    35 5.0 3.93 2.12 1.853 377.14 698.760

    40 5.0 2.49 1.67 1.489 495.00 737.089

    50 5.0 3.88 3.78 1.027 777.86 798.512

    58 5.0 5.76 7.42 0.775 1049.40 813.660

    70 5.0 2.50 4.21 0.593 1532.14 908.734

    80 10.0 2.98 3.07 0.973 990.00 963.53190 10.0 6.08 7.560 0.805 1257.14 1011.834

    100 10.0 2.85 3.86 0.737 1555.71 1146.712

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 5.2c: Vertical electric sounding curves for line3B1-3B2

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100

    10

    100

    1000

    10000

    App.Res.(o

    hms-m

    )

    AB/2(m)

    Schlumberger VES at Line 3B1 to 3B2 -VES5

  • 7/30/2019 hydrogeological investigations

    16/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES6 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm) Mult factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 10.45 3.07 3.403 196.11 667.320

    7 0.5 22.05 4.53 4.867 153.21 745.630

    10 0.5 12.48 4.87 2.563 313.50 803.408

    15 0.5 3.58 3.23 1.107 706.36 781.787

    20 0.5 3.28 5.43 0.604 1256.36 759.313

    25 5.0 37.74 9.05 4.171 188.57 786.445

    30 5.0 13.57 4.56 2.976 275.00 818.534

    35 5.0 6.41 2.76 2.324 377.14 876.545

    40 5.0 4.28 2.21 1.939 495.00 959.634

    50 5.0 8.71 6.87 1.269 777.86 986.734

    58 5.0 8.12 8.43 0.964 1049.40 1011.131

    70 5.0 8.10 11.42 0.709 1532.14 1086.423

    80 10.0 8.91 7.68 1.160 990.00 1148.645

    90 10.0 10.33 10.67 0.968 1257.14 1216.534100 10.0 7.55 9.13 0.827 1555.71 1286.834

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 5.2d: Vertical electric sounding curves for line3B1-3B2

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100

    10

    100

    1000

    10000

    App.Res.(ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line 3B1 to 3B2 -VES6

  • 7/30/2019 hydrogeological investigations

    17/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES7 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm)

    Mult

    factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 9.57 2.65 3.612 196.11 708.340

    7 0.5 20.05 4.76 4.212 153.21 645.320

    10 0.5 13.54 6.98 1.940 313.50 608.121

    15 0.5 4.30 4.56 0.942 706.36 665.32520 0.5 1.99 3.53 0.562 1256.36 706.534

    25 5.0 35.28 7.89 4.471 188.57 843.132

    30 5.0 31.43 9.43 3.333 275.00 916.560

    35 5.0 42.92 14.00 3.066 377.14 1156.312

    40 5.0 33.08 11.43 2.894 495.00 1432.657

    50 5.0 16.89 8.68 1.946 777.86 1513.534

    58 5.0 20.19 13.56 1.489 1049.40 1562.423

    70 5.0 8.90 9.65 0.922 1532.14 1412.834

    80 10.0 10.76 7.54 1.427 990.00 1412.52390 10.0 10.57 8.68 1.218 1257.14 1531.113

    100 10.0 5.77 5.56 1.037 1555.71 1613.45

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 5.2e: Vertical electric sounding curves for line3B1-3B2

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100

    10

    100

    1000

    10000

    App.Res

    .(ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line 3B1 to 3B2 -VES7

  • 7/30/2019 hydrogeological investigations

    18/24

    6.0 LINE 3A1-2A1

    6.1 Background

    The line 3A1-2A1 is 400m in length and is located at the southeastern part of the Greenfields

    Tailing Storage Facility. The area is covered and underlain by Kawere Conglomerate.

    6.2 Geophysical Investigation

    6.2.1 Horizontal Profiling

    The horizontal profiling was run along the line 3A1-2A1 with a total length of 400m. The

    line3A1-2A1 was subdivided in to line1 and line2, each of length 200m, as detailed in

    Table 6.1. The subdivision was due to the presence of a stream at the midsection of the

    line3A1-2A1 which hinders a continuous profiling. Plots of apparent resistivity versus

    chainage (m) along the traverse lines are presented in Figure 6.1. The anomalous points

    were picked based on both direct observation and results of the resistivity readings.

    T bl 6 1 R l d i i f H i l P fili

  • 7/30/2019 hydrogeological investigations

    19/24

    Table 6.2: VES results and their interpretation

    Site No.App. ResistivityRange (Ohm-m)

    Expected Aquiferzone (m)

    Averageweathering

    depth (m)

    Remarks

    VES8 498846 1060 20 Water may occur in

    the weathered

    zone.VES9 371606 10 - 70 25 Water may occur in

    the weathered zone

    VES10 386509 10 - 70 25 Water may occur in

    the weathered zone

    VES11 434

    713 10 - 60 20 Water may occur inthe weathered zone

    6.2.3 Recommendations

    Th i i d i h b k d h i T bl 6 3 Th d d

  • 7/30/2019 hydrogeological investigations

    20/24

    SCHLUMBERGER HORIZONTAL PROFILING

    RESULTS

    LOCATION :3A1-

    2A1

    DATE : 17-03-

    2011

    LINE :1

    20 30 40 50 60 70 80 90 100 110 120 130 140 150 160 170

    20 713 696 531 1001 868 701 616 519 631 541 546 686 713 589 413 518

    40 891 801 721 997 961 816 713 691 806 631 601 738 869 608 384 686

    LINE :2

    20 30 40 50 60 70 80 90 100 110 120 130 140 150 160

    20 486 416 410 536 616 510 498 486 716 813 1001 736 816 708 963

    40 616 573 396 716 736 606 536 513 896 1001 1131 868 981 1001 1142

    Figure6.1: Horizontal profiling results and curves for Line3A1-2A1

    20 40 60 80 100 120 140 160 180

    100

    1000

    10000

    VES9

    App.R

    es(ohms-m

    )

    AB/2 (m)

    20m

    40m

    LINE:1

    VES8

    20 40 60 80 100 120 140 160 180

    100

    1000

    10000

    VES11

    App.R

    es(ohms-m

    )

    AB/2 (m)

    20m

    40m

    LINE:2

    VES10

  • 7/30/2019 hydrogeological investigations

    21/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES8 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm) Mult factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 9.56 3.76 2.543 196.11 498.634

    7 0.5 7.40 2.08 3.561 153.21 545.613

    10 0.5 7.80 4.76 1.638 313.50 513.534

    15 0.5 4.34 5.76 0.754 706.36 532.756

    20 0.5 3.19 7.34 0.435 1256.36 546.132

    25 5.0 15.04 5.02 2.994 188.57 564.523

    30 5.0 9.56 4.52 2.116 275.00 581.878

    35 5.0 6.29 4.02 1.563 377.14 589.645

    40 5.0 10.27 8.45 1.215 495.00 601.534

    50 5.0 6.48 7.45 0.870 777.86 676.423

    58 5.0 4.51 6.75 0.669 1049.40 701.634

    70 5.0 2.61 5.45 0.480 1532.14 734.845

    80 10.0 7.42 9.34 0.794 990.00 786.212

    90 10.0 7.44 11.430 0.651 1257.14 818.476

    100 10.0 3.72 6.83 0.544 1555.71 846.332AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 6.2a: Vertical electric sounding curves for line3A1-2A1

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100 1000

    10

    100

    1000

    10000

    App.R

    es.(ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line1 -VES8

  • 7/30/2019 hydrogeological investigations

    22/24

    Project : GTSF

    Community :

    Tarkwa

    Client : AGA IDUPRIEM

    District

    :

    Survey No.:VES9 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm)

    Mult

    factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 12.69 4.56 2.782 196.11 545.623

    7 0.5 21.90 6.61 3.313 153.21 507.650

    10 0.5 4.58 2.95 1.552 313.50 486.53415 0.5 2.48 3.83 0.647 706.36 456.760

    20 0.5 1.01 3.07 0.329 1256.36 413.034

    25 5.0 14.46 6.70 2.158 188.57 407.008

    30 5.0 8.33 5.70 1.461 275.00 401.767

    35 5.0 4.06 3.86 1.051 377.14 396.383

    40 5.0 2.16 2.78 0.777 495.00 384.565

    50 5.0 2.33 4.87 0.478 777.86 371.723

    58 5.0 2.30 5.87 0.392 1049.40 411.808

    70 5.0 1.89 6.07 0.311 1532.14 476.423

    80 10.0 2.77 5.45 0.509 990.00 503.823

    90 10.0 3.98 8.670 0.459 1257.14 576.509

    100 10.0 2.90 7.43 0.390 1555.71 606.322

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 6.2b: Vertical electric sounding curves for line3A1-2A1

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100 1000

    10

    100

    1000

    10000

    App.R

    es.(o

    hms-m

    )

    AB/2(m)

    Schlumberger VES at Line1 -VES9

  • 7/30/2019 hydrogeological investigations

    23/24

    Project : GTSF Community : Tarkwa

    Client : AGA IDUPRIEM District :

    Survey No.:VES10 Date :17-03-2011

    AB/2(m) MN/2(m) P(V) C(I) R(ohm)

    Mult

    factor App Res

    (ohm)

    1 0.2 7.54

    1.5 0.2 17.36

    2 0.2 31.11

    3 0.2 70.40

    5 0.2 9.13 3.43 2.661 196.11 521.767

    7 0.5 14.74 4.53 3.255 153.21 498.657

    10 0.5 7.92 5.21 1.520 313.50 476.513

    15 0.5 2.36 3.67 0.642 706.36 453.323

    20 0.5 0.68 2.07 0.327 1256.36 410.50825 5.0 8.61 3.87 2.225 188.57 419.645

    30 5.0 9.46 6.45 1.466 275.00 403.138

    35 5.0 4.61 4.34 1.062 377.14 400.645

    40 5.0 1.85 2.31 0.802 495.00 396.745

    50 5.0 3.20 6.45 0.497 777.86 386.434

    58 5.0 1.93 5.03 0.384 1049.40 402.807

    70 5.0 2.33 8.65 0.270 1532.14 413.323

    80 10.0 1.86 4.53 0.411 990.00 406.867

    90 10.0 1.43 3.77 0.381 1257.14 478.554

    100 10.0 1.52 4.65 0.328 1555.71 509.665

    AB = distance between outer electrodes

    MN=distance between inner electrodes Figure 6.2c: Vertical electric sounding curves for line3A1-2A1

    P(V) = Potential R (ohm) = Resistance C(I) = Current

    1 10 100 1000

    10

    100

    1000

    10000

    App.R

    es.(

    ohms-m

    )

    AB/2(m)

    Schlumberger VES at Line2 -VES10

  • 7/30/2019 hydrogeological investigations

    24/24