Upload
others
View
3
Download
1
Embed Size (px)
Citation preview
HYDROGEOLOGICALINVESTIGATION TO MAINTAIN AN
ADEQUATE BODY OF WATER INLAKE JUALBUP
NOVEMBER 2012
REPORT FORCITY OF SUBIACO
(Report No. 317.0/12/01)
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage i
Rockwater Pty Ltd317.0/12/1
EXECUTIVE SUMMARY
The City of Subiaco is proposing to apply a polymer additive to the base of Lake Jualbup in
Shenton Park to reduce the lake-bed permeability and thereby maintain “adequate” water
levels in the lake throughout the summer months. The lake is primarily a compensating basin
utilised by the Water Corporation to accept and infiltrate local stormwater flow from the
Shenton Park catchment. Currently it acts as a groundwater recharge point in winter and
represents a groundwater expression in spring through summer, as long as groundwater levels
remain above the lake-bed surface. For the purposes of this investigation, an adequate body
of water has been assumed to be one in which the minimum lake-water depth is 0.5 m over
most of the lake area, or a minimum water level of 4.0 m AHD.
This investigation utilised numerical groundwater modelling techniques to assess the
hydrogeological impact on the lake and environmental surrounds for varying reductions in
lake-bed permeability. It further considered the effects of installing local infiltration
soakwells throughout the lake catchment to offset reduced infiltration from the lake to the
superficial aquifer, and considered the potential impact of raising the overflow-drain outlet
from the lake to reduce the likely increase in outflow from the system to ocean out-fall
resulting from reduced infiltration rates. In conducting the study, Rockwater examined
relevant information on Lake Jualbup and the City’s drainage network and compensating
basins, and water-table response as observed in the seven monitoring bores installed around
the lake in 2009.
Information provided by the distributors of the proposed polymer additive to the City of
Subiaco indicated that the polymer could only be applied in such a way as to completely seal
the lake bed in the area to which it is applied. The distributors suggested application in strips
to achieve the desired percentage reduction in lake bed permeability. During calibration of
the model, it was found that a reduction in permeability in one area simply led to an increase
in infiltration rates in any area where the permeability remained unchanged, and only very
small increases in lake-water levels were achieved under most circumstances. It was also
found that horizontal flow increased significantly when the lake bed permeabilities were
reduced, and it was concluded that the perimeter wall would need to be rebuilt and sealed if
the desired minimum water levels are to be obtained.
Given the constraints identified above, preliminary modelling investigated the reduction of
the lake-bed permeability by 25%, 50% and 75% assuming the application of the polymer
additive over 25%, 50% and 75% of the lake floor, sealing the lake bed progressively from
the south-west to north-east. The results indicated that the minimum water-level requirement
could only be met with a 75% reduction in lake bed permeability and so the scope of work
focused on this scenario.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage ii
Rockwater Pty Ltd317.0/12/1
With a 75 % reduction in lake-bed permeability and installation of low permeability walls
(modified lake conditions) the modelling indicates that minimum summer lake-water levels
would be about 4.2 m AHD under long-term average rainfall conditions (about 0.7 m higher
than for an unmodified lake system). Groundwater levels in the superficial aquifer would
only be affected immediately down-gradient of the lake where the polymer had been applied,
with maximum groundwater levels in this area being about 0.4 to 0.7 m lower, and minimum
groundwater levels being about 0.1 m lower. There would be no measureable effect on the
superficial aquifer regionally. Outflow from the lake to the main drain might increase by 2.7
to 4.4 times, which could be reduced by about 20% in the long term if the drain outlet was
raised by 0.3 m to 5.37 m AHD.
During an extended summer period with no rain, in a year where winter months have received
the long-term average rainfall, the modified lake would maintain water levels at greater than
0.5 m depth for about 9 weeks longer than under unmodified conditions. After this time,
water levels would fall below the desired minimum level and the eastern side of the lake
would dry up after another eight weeks with no rain. If the drain was raised, the period the
lake remained wet might be increased by an extra week or so. The modelling results suggest
that between 340 and 430 m3/d of groundwater would need to be pumped to the lake to
maintain water levels at 4.0 m AHD under these dry summer conditions.
It was found that at least 75% of the current lake inflow needed to be maintained to achieve
the desired minimum lake water levels. If the excess 25% of rainfall runoff from Shenton
Park was infiltrated via local infiltration soakwells, outflow from the lake could be reduced by
approximately 40%. This saving would increase to 60% if the drain outlet was raised by
0.3 m. Field monitoring of existing infiltration soakwells, however, raised questions as to the
practicality of infiltrating a significant proportion of runoff via soakwells, and further
hydrological investigation may be required.
Reducing the permeability of the lake-bed has implications for the risk of flooding that are
beyond the scope of this investigation. However, modelling suggests that maximum monthly
water levels may reach about 6.2 m AHD in a year of average rainfall and 6.9 m AHD during
a wet cycle; this does not allow for outflow to the main drain which may lower lake water
levels by up to 0.5 m/d. During a dry cycle, lake-water levels might still be maintained near
the desired minimum level in the modified lake.
This investigation has found that to maintain an adequate water-body in Lake Jualbup, it is
likely the polymer additive will need to be applied to at least 75% of the lake-bed surface,
working from the south-west back to the north-east. If practicable, application to 50% of the
lake might be trialled as a preliminary measure to test the modelling results. In addition, it is
recommended that the drain outlet elevation be raised 0.3 m to 5.37 m AHD to increase water
storage, increase infiltration outside the lake perimeter at times of high rainfall, and reduce
outflow to the main drain; thereby contributing to the maintenance of higher water levels in
the lake. Lake water levels, groundwater levels and lake water quality should continue to be
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage iii
Rockwater Pty Ltd317.0/12/1
monitored and assessed to validate the modelling results and provide ongoing review of the
modified conditions at the lake.
Disclaimer: Numerical groundwater modelling results and other calculations herein are
necessarily approximate because of the nature of natural systems. It is never possible to
obtain and extrapolate exact aquifer parameters. However, the modelling has used ‘state of
the art’ techniques, and has been calibrated to good data on lake and groundwater levels.
Rockwater Pty Ltd317.0/12/1
TABLE OF CONTENTSPAGE
EXECUTIVE SUMMARY I
1 INTRODUCTION 1
2 HYDROGEOLOGICAL SETTING 1
3 LAKE WATER QUALITY 3
3.1 Current Lake-Water Quality Conditions 3
3.2 Discussion on Current Lake-Water Quality Conditions 5
3.3 Potential Changes to Water Quality 6
3.4 Conclusions on Water Quality 7
4 STORMWATER RUNOFF AND INFILTRATION 7
4.1 Description of Stormwater Drainage System 7
4.2 Calculations of Volume of Surface-Water Runoff 8
4.3 Discussion of Rainfall and Runoff 9
4.4 Maximum Lake-Levels and Ocean Outflow 10
4.5 Soakwells 10
4.5.1 Infiltration Monitoring 11
4.5.2 Discussion 11
5 NUMERICAL MODELLING OF LAKE WATER LEVELS 12
5.1 Model Description 12
5.2 Model Calibration and Adopted Parameters 13
5.3 Model Operation 15
5.4 Preliminary Results of Modelling 17
5.4.1 Water Levels 17
5.4.2 Water-Flow Budget 17
5.4.3 Implications for Model Operation 19
5.5 Modelling Results 19
5.5.1 Impact on Groundwater Levels in the Superficial Aquifer 20
5.5.2 Lake Outflow 20
5.5.3 Raising the Drain Outlet 21
5.5.4 Maximum Lake Levels 22
5.5.5 Maintaining Lake Levels above the Desired Minimum during
Summer Periods of No Rainfall 22
5.5.6 Reducing Lake Inflow 23
5.5.7 Infiltration via Soakwells 24
5.5.8 Changes to Climatic Conditions 25
6 CONCLUSIONS AND RECOMMENDATIONS 25
REFERENCES 28
Rockwater Pty Ltd317.0/12/1
TABLE OF CONTENTS(Continued)
Tables
Table 1 : Stormwater drainage infrastructure – Shenton Park catchment area 8
Table 2 : Average annual runoff per 0.1 ha of shedding area for various rainfall intensities– based on calculations from Sim (1995) 9
Table 3 : Average rainfall and volume of runoff per month in the Shenton Park catchment 9
Table 4 : Adopted values of aquifer parameters 15
Table 5 : Modelled water flow budget 18
Table 6 : Lake outflow volume calculations 21
Table 7 : Estimated water requirements to maintain minimum desired water-levels 23
Table 8 : Calculated volumes of outflow for model simulations with and without soakwellinfiltration 24
Figures
1 Locality Map
2 Locality Map of Drainage Installations
3 Lake Jualbup Water Level Contour Map September 2011
4 Lake Jualbup Water Level Contour Map March 2012
5 Hydrograph Monitoring Bore GE4
6 Hydrograph of Monitoring Point LJ Lake (Rainfall Data from Bureau of Meteorology)
7 Hydrographs for Monitoring Bores LJ1 to LJ5
8 Stormwater Catchment Infrastructure Locations Shenton Park
9 Local Topography for Lake Jualbup and Surrounds
10 Water Levels in Stormwater Infiltration Wells with Daily Rainfalls from Shenton Park
Treatment Plant
11 Numerical Model Grid
12 Comparison Between Modelled and Measured Water Levels in Lake Jualbup
13 Comparison Between Modelled and Measured Groundwater Levels at Lake Jualbup
Monitoring Bores LJ1 and LJ5
14 Comparison Between Modelled and Measured Regional Groundwater Levels
Monitoring Bores HS1, CS1, MT1, GE4 and KS1
15 Comparison Between Modelled and Measured Lake Water Level Decline February
2008
16 Modelling Results for 25%, 50% and 75% Reduction in Lake Bed Permeability
17 Modelling Results for Simulated Changes to Lake Levels Resulting from 25%, 50%
and 75% Reduction in Lake Bed Permeability
18 Modelling Results for 50% and 75% Reduction in Lake Bed Permeability and New
Perimeter Wall
Rockwater Pty Ltd317.0/12/1
TABLE OF CONTENTS
(Continued)
Figures (cont.)
19 Simulated Groundwater Levels Calibrated Model and with 75% Reduction to Lake-
Bed Permeability Monitoring Bores LJ1 to LJ5
20 Simulated Groundwater Levels Calibrated Model and with 75% Reduction to Lake-
Bed Permeability Regional Monitoring Bores
21 Lake Water Drain Outflow Assessment
22 Summer Water Level Decline Calibrated Model, Lake-Bed Permeability Reduced
75% and with Reduced Permeability and Raised Drain Elevation
23 Simulated Lake Levels for a Period of No Summer Rainfall
24 Results for Modelling with Reduced Lake Inflow and Infiltration Via Soakwells
25 Drain Outlfow Comparison 75% Lake-Bed Permeability Reduction with Reduced
Lake Inflow
26 Lake Jualbup Modelled Maximum Groundwater Levels in a Wet Cycle : Perth 1961-
1966 Ave Annual Rainfall 927 mm
27 Modelling Results for 75% Reduction in Lake Bed Permeability – Wet Cycle
28 Modelling Results for 75% Reduction in Lake Bed Permeability and a Drying Climate
– Assumes 15% Reduction in Long Term Average Rainfall
Appendices
I Head-Discharge Relationship for Shenton Park Drain Outlet
II Peak Water Levels in Monitored Stormwater Infiltration Wells 16 July – 28 August
2012
III Monthly Recharge to Shenton Park Compensating Basins for Calibrated Model
IV Water Quality Assessment Figures for Lake Jualbup
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 1
Rockwater Pty Ltd317.0/12/1
1 INTRODUCTION
The City of Subiaco commissioned a study, commencing July 2012, investigating the
hydrogeological implications of maintaining adequate water levels in Lake Jualbup by
reducing the permeability of the Lake bed utilising a polymer additive. The lake is primarily
a compensating basin utilised by the Water Corporation to accept and infiltrate local
stormwater flow from a number of drains; it acts as a groundwater recharge point in winter
and represents a groundwater expression in spring through summer, as long as groundwater
levels remain above the lake-bed surface. This investigation considers the hydrogeological
impact on the lake and environmental surrounds for varying reductions in lake infiltration
rates. It further considers the effects of installing local infiltration soakwells (“soakwells”)
throughout the lake catchment to offset reduced infiltration from the lake to the superficial
aquifer, and assesses the potential impact of raising the overflow-drain outlet from the lake to
minimise the likely increase in outflow from the system to ocean out-fall resulting from
reduced infiltration rates.
An existing numerical groundwater model representing the shallow aquifer system at Subiaco
and adjoining areas (Rockwater 2009) has been reconstructed in Visual Modflow and
recalibrated to simulate the observed lake water levels and groundwater data collected from
monitoring bores in the area since 2009. The model is used to estimate the lake-level and
groundwater-level response to reduced infiltration through the base of the lake, the
widespread installation and operation of soakwells, and response to a raised drain outlet. It
will contribute to determining the optimal operating conditions for the lake and surrounds.
In conducting the study, Rockwater has examined relevant information on Lake Jualbup and
the City’s drainage network and compensating basins, and water table response as observed in
the seven monitoring bores installed around the lake in 2009 (Rockwater 2009) and several
regional monitoring bores. This report contains the results of these evaluations. We
acknowledge the assistance provided by the City of Subiaco and the useful data and
discussions provided by the Water Corporation and Subiaco resident Dr Geoffrey Dean. The
latter made available his many measurements of water levels in Lake Jualbup collected
between 2005 and 2010.
Locality maps showing the surface-water catchment and relevant infrastructure are presented
in Figures 1 and 2.
2 HYDROGEOLOGICAL SETTING
Subiaco is located within the Perth Basin, with the uppermost strata in the area being sand and
limestone of the Tamala Limestone formation. About 6 m or more of sand overlies
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 2
Rockwater Pty Ltd317.0/12/1
interlayered limestone and sand extending to 24 – 35 m below sea level. Collectively, these
and other shallow strata are referred to as the superficial formations.
The hydrogeology of the Perth Basin is described by Davidson (1995). Investigations of the
Subiaco/Lake Jualbup hydrogeology have been reported by McFarlane (1983), Sim (1995),
and Rockwater (2005a, 2005b and 2009). Groundwater in the superficial formations is
recharged by rainwater infiltration, and locally it flows westwards to the ocean and
southwards to the Swan River. Lake Jualbup, and other lakes and wetlands in the
metropolitan area, are topographic lows that receive water by groundwater flow and surface-
water runoff.
Aquifer permeability (= hydraulic conductivity in this report) of the limestone material in the
superficial deposits is very high (100 – 1000 m/d), resulting in high rates of groundwater flow
and low hydraulic gradients. Sands have intermediate permeabilities of generally 10 to
50 m/d while local swamp deposits have low (horizontal) permeabilities of commonly 0.1 to
2 m/d depending on the amount of clay, silt, peat, and cementation. In the vertical direction,
aquifer permeability of sedimentary strata is very much lower than the permeability in the
horizontal direction. The thickness and lithology of the swamp deposits at Lake Jualbup have
not been determined because of lack of access. Natural deposits have been partly altered by
one or more episodes of excavation and waste-dumping. Of the monitoring bores installed
during the previous investigation, only one (LJ3), near the north-eastern edge of the lake
(Fig. 2), intersected clayey material: 0.25 m of black organic sandy clay at 1.5 m depth
(Rockwater, 2009).
Maximum (post-winter, September 2011) and minimum (post-summer, March 2012) water-
table contours in the vicinity of the lake are presented in Figures 3 and 4. The water levels
were measured in monitoring bores installed for the City of Subiaco in 2009 or obtained from
data supplied by the Department of Water (DoW). Regular historical water levels are
available from one monitoring bore in the City of Subiaco - bore GE4 (in Rosalie Park about
600 m south-east of the lake) - and are plotted in Figure 5; measurements are taken
biannually, close to summer minima and winter maxima.
In September 2011 (Fig. 3) the water table was mounded beneath Lake Jualbup, sloping
downwards most strongly to the south (with a hydraulic gradient of 0.006) but also to the
north, east and west; its elevation was close to 4.5 m AHD near the Lake. With water levels
in the lake at about 4.7 m AHD, the lake is evidently acting as a recharge point to the
superficial aquifer following the winter rains. In March 2012 (Fig. 4) the water table near
Lake Jualbup sloped downwards to the south-south-west with a hydraulic gradient of 0.002;
its elevation was close to 3.2 m AHD near the Lake. The small pool of water at the western
end of the lake during summer is apparently connected to the shallow aquifer, with
groundwater flowing into the lake from the north (where the water table is higher), and out to
the south (where the water table is lower).
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 3
Rockwater Pty Ltd317.0/12/1
Groundwater levels in the Subiaco area generally fluctuate by 0.5 to 1 m annually in response
to recharge from winter rainfall and depletion in dry months, as illustrated by the hydrograph
for monitoring bore GE4 (Fig. 5). The data show a generally declining trend in regional water
levels averaging 0.03 m/yr between 1994 and 2008, although water levels have stabilised
somewhat since 2006. This reflects the rainfall trends over this time.
Groundwater discharges from the aquifer by subsurface flow to the coast and the Swan River,
by evaporation and transpiration at lakes and areas of shallow water table, and by pumping
from bores for the watering of parks and domestic gardens. Historically, groundwater levels
rose as a result of urbanisation, which led to a greater percentage of rainfall infiltration, but
they have subsequently declined since the 1970’s because of lower rainfall and to a lesser
extent an increase in groundwater pumping from bores.
The hydrographs for Lake Jualbup and surrounding bores are shown in Figures 6 and 7,
respectively. The lake-stage hydrograph is based mainly on measurements provided by
Shenton park resident Dr Geoffrey Dean. The lake water level responded to individual
rainfall events and rose by a maximum of 2.1 m, being limited by flow to the outlet to the
Shenton Park branch drain (at 5.07 m AHD). The water ultimately discharges as ocean
outfall. Because the lake receives run-off water from surrounding stormwater drains and
water pumped from the Aberdare compensating basin (CB) at QEII hospital, its water level
rises by more than double the seasonal fluctuation of the regional water table. Similarly,
groundwater levels immediately surrounding the lake fluctuate by up to 1.8 m in response to
the local recharge from the lake, and in 2010 and 2011 peaked higher and over a longer period
in response to additional water being pumped into the lake from dewatering operations at
QEII. The lake generally contributes water to the aquifer for around 6 months of the year.
3 LAKE WATER QUALITY
As part of the scope of work associated with the current hydrogeological investigation,
Rockwater has been requested to provide an indication of the minimum lake-water level
required to provide an “adequate” body of water in the lake, such that visual appeal and
suitable water quality is maintained. A minimum depth of 0.5 m over most of the eastern side
of the lake was proposed, and this has been assessed based on historical data. Advice is also
provided regarding potential changes to water quality in the lake resulting from the reduction
in lake bed permeability and the establishment of a permanent body of water at the Lake
Jualbup site.
3.1 CURRENT LAKE-WATER QUALITY CONDITIONS
In its current state, Lake Jualbup undergoes a wetting-drying cycle with maximum capacity in
winter, between July and September, and the lake commonly drying out in summer, between
January and March.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 4
Rockwater Pty Ltd317.0/12/1
The bed of the lake is estimated to lie at between 3.0 m AHD (western side) and 3.5 m AHD
(eastern side) over most of its area. Its banks slope to a little over 5 m AHD at the eastern end
and at a vegetated island. The lake has a wall and path around three quarters of its perimeter,
constructed to about 5 m AHD. Its length (east to west) is about 180 m and width is about
130 m, giving a surface area of about 2.3 ha. The island sits off-centre to the west, and
supports a mixture of Australian native and introduced species trees. Some grasses occur
around the fringe of the island. The lake is situated in grassed park-land and native vegetation
has recently been established on its eastern bank.
In winter, the lake generally fills for short periods to the elevation of a water outlet at
5.07 m AHD, giving a water depth of about 1.6 to 2.1 m. In low-rainfall winters, the lake
does not fill. In summer, the lake becomes almost or completely dry, with only a few stagnant
pools of water remaining.
Full mixing of the water column can be expected to occur during winter months by the effects
of wind, rainfall, and inflow of stormwater runoff. In summer, mixing is effected by wind,
council-operated fountains (when water-depth is sufficient), and to a small extent by
groundwater through-flow. Because of its shallow depth, stratification is probably minimal.
Key water quality parameters, as provided by the City of Subiaco, are presented in Figures
App IV – A to D in Appendix IV.
The figures show the lake water is very fresh, with an average salinity of about 250 mg/L
TDS and maximum salinity of about 575 mg/L TDS in late summer months. The water
temperature ranges from between about 15 oC in winter to about 25 oC in summer,
occasionally reaching above 30 oC. The median pH of the lake water is neutral at 6.8;
however, values can vary widely, from one very low value of 4 to as high as 9.5. It is
possible that some of the very high values are in error, although flow through concrete pipes
and/or water pumped from the dewatering operations at QEII may be contributing to the high
alkalinity. The one-off value of 4 in May 2007 is from a small area of water and is associated
with some high metal readings (particularly zinc) and may be real, possibly resulting from
rewetting of previously dry lake-bed deposits.
Dissolved oxygen (DO) levels in the lake frequently fall below 5 mg/L (the level where fish
will become stressed, ANZECC 2000), particularly to the east of the lake, and are generally
below the optimum 90% saturation level, averaging 4 mg/L in the east and 6 mg/L in the
west. Nutrient concentrations vary widely, with total nitrogen (TN) ranging from 0.07 mg/L
to 4.2 mg/L and total phosphorous (TP) ranging from 0.02 mg/L to 0.69 mg/L. Average TN
values (1.26 and 1.17 mg/L for east and west respectively) fall below the ANZECC 2000
guideline value for wetlands (1.5 mg/L). Average TP (0.22 and 0.17 mg/L for east and west
respectively) is above the guideline value for wetlands (0.06 mg/L).
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 5
Rockwater Pty Ltd317.0/12/1
Average values for the heavy metals copper, lead and zinc (Data supplied by CoS) are above
the ANZECC 2000, 80% protection trigger values.
The water quality plots show no evident correlation between water quality conditions and the
depth of water in the lake, with elevated nutrients and depleted oxygen levels occurring under
both high and low water level conditions, and vice versa.
Field notes recorded during sampling between 2008 and 2012 indicate stagnant water is
common during summer months, usually in small pools. There are also occasions, when water
levels are higher, up to 4.0 m AHD, when some stagnant water has been noted (November,
2008, May 2010, November 2010 and February 2011), although this appears to be in isolated
pools and is worse when water levels are lower (3.5 to 3.8 m AHD). There are occasional
references to midge and mosquito breeding associated with these pools. Algal blooms do not
appear common, although algae were noted in February 2011 and there was a likely bloom in
February 2012. The only notable difference in water quality at the time algae was present is
the unusually high water temperatures (> 30 oC), which may have triggered algal growth.
3.2 DISCUSSION ON CURRENT LAKE-WATER QUALITY CONDITIONS
A brief review of available reports for the site (see bibliography in References) suggests the
following processes may be contributing to current water quality conditions:
Stormwater inflow – the lake is primarily a compensating basin, receiving surface
water runoff from a highly urbanised environment. Nutrients (especially TP) and
heavy metals are likely to be introduced into the lake via the stormwater inflow,
particularly during “first flush” events (i.e. initial runoff following an extended dry
period);
Phosphorous and heavy metals input to the lake via the stormwater are likely to be
assimilated into the lake-bed sediments;
Degradation of vegetable matter – during the dry periods significant amounts of
vegetation, including “copious amounts” of grass and weeds cover the lake bed. As
the lake re-fills the vegetation dies and dissolved oxygen is likely consumed as the
organic matter is degraded. This is potentially a major contributor to depleted oxygen
levels in the lake;
Low DO levels may remobilise phosphorous into the water column.
Rewetting of dry, oxidised lake-bed sediments may release previously assimilated
heavy metals into the water column;
Small pools that remain in the drying lake-bed have been noted to be stagnant. It has
been reported that groundwater at the site is anaerobic, and therefore any through-flow
will not improve DO concentrations;
Old landfill – the lake is situated on an old landfill site, and it is possible that
groundwater containing elevated TN and ammonia is contributing to higher summer
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 6
Rockwater Pty Ltd317.0/12/1
nutrient concentrations. Similarly, the landfill may be the source of some heavy
metals.
3.3 POTENTIAL CHANGES TO WATER QUALITY
The proposed reduction in lake-bed permeability for Lake Jualbup is aimed at establishing a
permanent water body at the site. This represents a significant change in hydraulic conditions
and will necessarily have some impact on the water quality of the lake. The change from an
ephemeral water body to a permanent water body may justify a reclassification of the
ecosystem from a wetland to a constructed lake, which could potentially require more
stringent water quality control under the ANZECC 2000 guidelines.
A recent study on constructed lakes in the Perth metropolitan area (ENV Australia, 2008)
found that the most common problem associated with constructed lakes is eutrophication
(excess nutrients) and associated problems such as algal blooms, odour and midge
infestations. Other problems include invasion of feral fish and exotic flora and infrastructure
and maintenance issues. One key finding of the investigation was the absence of any
correlation between design features of the lake and problems such as eutrophication, with no
particular type of lake showing any greater susceptibility, or lack thereof, to eutrophication
than others. Instead, it was concluded that the best predictor for the effective performance of
a constructed lake is the water-nutrient balance. The lakes most susceptible to eutrophication
are those where residence time for the water is long (>30 days) and nutrient loads (TN and
TP) are high. Older lakes, where nutrients have had time to accumulate, appear to be more
susceptible to eutrophication.
The establishment of a permanent water body in Lake Jualbup could potentially have both
positive and negative impacts on the water quality:
It is unclear as to the nature of the polymer additive proposed for application to the
lake-bed, however it is possible that it may decrease the adsorptive capacity of the
lake-bed sediments, thereby increasing soluble concentrations of heavy metals and TP
in the water column;
With the lake-bed permanently inundated, there will no longer be the opportunity for
very large quantities of terrestrial vegetation to grow up during the dry season; this
should reduce the amount of organic matter degradation that occurs as the lake fills,
potentially reducing DO consumption and improving oxygen levels in the lake;
Improved oxygen levels may prevent remobilisation of TP from the sediments,
potentially reducing TP concentrations;
Without the drying cycle, lake-bed sediments will not become oxidised, minimising
the potential for acidification and re-mobilisation of metals;
The lake will no longer be in hydraulic connection with the groundwater during
summer, potentially decreasing TN, ammonia and/or heavy metal concentrations, if
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 7
Rockwater Pty Ltd317.0/12/1
these do in fact exist at higher levels in the groundwater at this site.
Through-flow and outflow to the groundwater system will be restricted, increasing
residence time for the water in the lake, potentially increasing the risk of
eutrophication of the lake;
If groundwater is high in TN, using it to maintain water levels in the lake could
contribute to water quality problems.
3.4 CONCLUSIONS ON WATER QUALITY
There is no significant correlation between the key water quality parameters and water level
depth in Lake Jualbup, although notes taken during sampling tend to indicate more visually
pleasing conditions and less obvious water stagnation when lake levels are greater than
4 m AHD.
A number of water quality changes can be expected as the lake moves from an ephemeral
wetland to a permanent lake, and these have been summarised. As the processes are complex
and highly interconnected, water quality monitoring should continue at the lake to assess the
net effect of these changes.
The planting of native grasses and vegetation at the lakes edge may lower nutrient and heavy
metal concentrations, reducing the risk of eutrophication.
4 STORMWATER RUNOFF AND INFILTRATION
Lake Jualbup acts as a compensating basin within the Shenton Park catchment, with
stormwater directed to the lake via local stormwater drains that collect rainfall runoff from the
streets and pavements throughout the catchment. Most stormwater drains in the catchment
direct their inflow to the lake via piped drainage. However, upgrading of stormwater drains
from around 2006 to 2009 has led to a number of drainage pits being replaced with infiltration
soakwells, which enable the collected rainfall runoff to infiltrate directly to the water table at
that location; some overflow from these drains may still be directed to the lake following high
intensity rainfall events. The details of the catchment system in relation to the lake and direct
aquifer recharge are provided below.
4.1 DESCRIPTION OF STORMWATER DRAINAGE SYSTEM
Runoff from paved areas is collected predominantly in the City’s piped drainage system
which includes about 2000 export drainage pits, with water-entry at road pavement level at
local low elevations. The installations are termed “gullies” (with horizontal grill) and “side-
entry pits”. Locations and associated drainage infrastructure are shown in Figure 8. The
drainage pits in the Shenton Park catchment allow runoff water to enter the local drains which
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 8
Rockwater Pty Ltd317.0/12/1
are directed to the Lake Jualbup or Aberdare Rd compensating basins (CBs). Water from
Aberdare Rd is pumped into Lake Jualbup via a branch drain, and any overflow from Lake
Jualbup is directed to the Subiaco Main drain via a branch drain. Since August 2010,
additional water has been pumped from Aberdare Rd CB to Lake Jualbup as a result of
dewatering operations associated with building-excavations at QEII hospital. The drains are
all enclosed pipes. The main drains and associated compensating basins are operated by the
Water Corporation. The Subiaco main drain water eventually reaches the ocean north of
Swanbourne Beach.
All the drainage is by gravity, with the exception of water pumped from the Aberdare Rd CB
to Lake Jualbup when water levels reach a trigger value. The Shenton Park catchment covers
293 hectares and includes an area of about 80 ha in the City of Nedlands, south of Aberdare
Road. For its assessment purposes, the Water Corporation has assigned 81 sub-catchments
based on the pipe-network configuration and the types of land development affecting water
runoff.
A summary of drainage infrastructure for the Shenton Park catchment is provided in Table 1,
based on information provided by the Water Corporation (Rockwater, 2009) and City of
Subiaco. The table shows total catchment area and the assigned value for the impervious areas
connected to surface-drainage. The drainage system – comprising 764 drainage pits, 60 local
infiltration soakwells, two compensating basins and two branch drains – is designed to
prevent deleterious flooding arising from moderately severe rainfall events; i.e. 5 year ARI
storm and 10 year ARI storm runoff, for residential and commercial developments,
respectively. The drain capacity, therefore is designed for high flow conditions, and provides
no indication of total flow volumes under usual conditions. Rates and volumes of flow are not
measured in any of the drain pipes.
Table 1 : Stormwater drainage infrastructure – Shenton Park catchment area
Total area (ha) 293
Impervious Shedding Area (ha) 63
Drainage Pits 764
Infiltration Soakwells 60
Compensating Basins 2
Branch Drains 2
Drain Outlets into Lake Jualbup 11
Lake Outlet Drain to Branch Drain 1
4.2 CALCULATIONS OF VOLUME OF SURFACE-WATER RUNOFF
Using a quadratic function derived empirically for the Shenton Park catchment (Discharge
(m3) = 43.3 x daily rainfall (mm) + 1.61 daily rainfall2 (mm) – 33.1 for 7 ha shedding area)
(Sim, 1995)), and a range of daily rainfall values, Rockwater has previously estimated annual
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 9
Rockwater Pty Ltd317.0/12/1
runoff per 0.1 ha for the Shenton Park catchment since 1999. These calculations were
updated for the current investigation and are presented in Table 2.
Table 2 : Average annual runoff per 0.1 ha of shedding area for various rainfall
intensities – based on calculations from Sim (1995)
Rainfall/DayAdopted Value
Rainfall/Day
Calculated Runoff
per 0.1 ha
Average No. of
Runoff Days/Year
Average Annual
Runoff
per 0.1 ha
mm mm m3 d m3
3-5 4 2.4 13.6 33
5-10 7.5 5.5 19.1 105
10-15 12.5 10.9 11.3 123
15-20 17.5 17.4 5.2 92
20-30 25 29.4 5.2 152
30-40 35 49.4 1.5 72
40-50 45 73.9 1.2 85
*50+ 55 103.1 0.5 52
Total 714
*Average 2008 to 2011.
Calculations made for the 2009 report used a combined average for rainfall data from Perth
and Subiaco treatment plant stations. The updated calculations for 2009 to 2012 are based
on Subiaco rainfall data alone. The average values reported here are an average of the results
obtained for the 2009 report and the updated calculations. Rainfalls of less than 3 mm/d have
been assumed to produce negligible runoff, because very small and low-intensity rainfalls are
essentially all consumed by depression storage and evaporation. Average volumes of runoff
per month, calculated using runoff per 0.1 ha and are listed in Table 3. Ninety per cent of the
runoff takes place (on average) in the seven months April to October.
Table 3 : Average rainfall and volume of runoff per month in the Shenton Park
catchment
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year
Average Monthly
Rainfall - Subiaco11.7 13.9 18.2 37.1 83.7 142.7 148.0 105.2 72.9 40.8 23.4 9.5 707.1
Average No.
of Runoff Days in
Each Month
1.0 5.5 0.9 3.2 6.0 9.5 12.1 9.2 8.0 3.1 2.5 0.9 62
Runoff (calc.)
per 0.1 ha (m3)19 9 22 41 79 125 138 111 63 31 15 11 663
Shenton Park
Runoff (m3 x 103)11.7 5.4 14.0 26.0 49.7 78.6 87.0 69.7 39.9 19.6 9.7 6.6 418
4.3 DISCUSSION OF RAINFALL AND RUNOFF
Not all of the calculated volume of runoff for the Shenton Park catchment reaches Lake
Jualbup. A significant but unknown amount of the water collected at the Aberdare Road CB
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 10
Rockwater Pty Ltd317.0/12/1
infiltrates to the aquifer beneath the storage pond at that site, rather than being pumped to the
Lake.
In most years of average to high rainfall, the water level in Lake Jualbup rises to the level of
the outflow drain (at 5.07 m AHD) and overflow water passes to the Subiaco main drain via a
branch drain. This was observed in 2008 and 2009, when the annual Perth rainfall was 808
and 607 mm, respectively. It probably also occurred in 2011, when the annual Perth rainfall
was 861 mm; however, it was not measured due to less frequent lake-level monitoring. The
volume of water that leaves the Lake is not measured, and it would vary depending on the
timing and duration of high-rainfall events. In low rainfall years, such as 2010, it has been
observed that the water level in Lake Jualbup remains below the outflow drain, and all the
runoff is retained.
4.4 MAXIMUM LAKE-LEVELS AND OCEAN OUTFLOW
Once lake levels reach 5.07 m AHD, water flows into the branch-drain outflow at the north-
west side of the lake, and is directed to the Subiaco Main Drain and ultimately the ocean
(Fig. 2). The lake-level monitoring results show that water rose above the outlet level on at
least four occasions between January 2008 and May 2012 (Fig. 6). The daily lake-monitoring
data (Dean, 2011) show that water levels remained above the outlet for six days in
July/August 2008, for three days in July 2009 and for four days in August 2009. Lake water
levels did not rise above the outlet height in 2010, and only monthly measurements were
made in 2011 and 2012, so the duration of any outflow is not known.
The head discharge relationship for the outlet drain has been provided by the Water
Corporation (Appendix I). The values are calculated, not measured. For lake levels of about
5.2 m AHD, up to 13,740 m3/d might flow from the lake to the drain, equivalent to about
0.5 m of lake storage per day.
At the lake’s peak measured water level (5.22 m AHD on 31 July 2008) the water would have
remained contained well within the park boundary, which has a topographic low of about
6.5 m AHD on the western side, along Herbert Rd (Fig. 9).
4.5 SOAKWELLS
The soakwells are concrete cylinders of 1.2 m diameter and 2.0 to 2.4 m depth with an open
base and lateral slots. Runoff water enters via gullies or side-entry openings. Overflow water
from the soakwells discharges into drain pipes and thence to the local drains, or back to the
road pavement and thence to a downstream drainage pit. About 60 of the drainage pits in the
Shenton Park catchment, and over 200 in the City of Subiaco as a whole, were converted to
soakwells between 2006 and 2009, and there is potential for the remainder to be converted.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 11
Rockwater Pty Ltd317.0/12/1
4.5.1 Infiltration Monitoring
Water levels were recorded in three soakwells (119 and 142 Keightly Rd and 5 Waverley St)
at one-minute intervals through the end of July and August 2012, with a total rainfall of
35 mm and 110 mm, for each month respectively. The overall results are provided in
Figure 10, with detailed plots shown in Appendix II. The findings are summarised below.
Daily rainfalls ranged from 0.4 to 20 mm.
Peak water levels in the soakwell in Waverley St reached a maximum depth of about
1.5 m, while those in Keightly Rd reached a maximum of about 1.0 m. These levels are
below the drain inlets and the soakwells do not appear to have overflowed.
Peak water levels in Waverly St declined to near the base of the soakwell in about two
hours from the cessation of rainfall, while peak water levels in the soakwells on
Keightly Rd declined to near the base within 30 minutes.
Infiltration rates (calculated from the average rates of water-level decline after the
water-level peaks) in Waverley St ranged from 11 to 43 m3/d, with volumes of up to 3.4
m3 infiltrated over approximately 5 hours for rainfall events in the order of 10 – 20
mm/d. In the Keightly Rd soakwells, infiltration rates ranged from 20 to 66 m3/d, with
total volumes of up to about 1.7 m3 infiltrated over approximately 90 minutes for a 12
mm/d rainfall event.
In August 2012, a total of 15 m3, 4.2 m3 and 1.8 m3 of stormwater was infiltrated
directly to the superficial aquifer via the three soakwells in Waverley St and 142 and
119 Keightly Rd, respectively, for total measured monthly rainfall of 110 mm over 11
rainfall runoff days (rainfall >3.0 mm).
It appears that the Keightly Rd soakwells receive less rainfall runoff than the
Waverley St soakwells, which may be related to their location and spacing. They have
small catchment areas. It is also possible, that the volume of water appears to be less
due to the higher infiltration rates in these soakwells.
The variability in the volume of water flowing into the soakwells over a relatively small
area indicates that careful siting of the soakwells is required to ensure optimum
interception of rainfall runoff.
The operational infiltration rates measured in these soakwells are similar to the values
obtained from average rates of water-level decline in the controlled infiltration test rates
measured in 2009 (18 to 57 m3/d).
4.5.2 Discussion
For rainfalls of 3 to 20 mm per day the soakwells appear to be efficient at infiltrating runoff
water: probably 100 per cent of water intercepted. For larger and very intense rainfalls, some
excess water will overflow the soakwells and pass into the piped drainage system. Rainfalls
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 12
Rockwater Pty Ltd317.0/12/1
of 20 to 40 + mm per day contribute about half the estimated annual runoff from the Subiaco
catchments (Table 2).
The condition (cleanliness) of the soakwells will have a strong bearing on their efficiency in
transmitting water to the underlying aquifer. Likely impediments include:
Debris inhibiting water entry to the Gully/SEP
Leaf and other debris on the floor of the soakwell
Siltation of the floor and underlying sand (aquifer)
The number of soakwells installed in each drainage basin will determine the average
pavement area draining to the soakwells. Small local catchments are less likely – than large
catchments – to give rise to excess water, and ‘overtopping’ of soakwells.
Given the undetermined elements affecting the amount of water that may bypass the
soakwells, calculations in this report allow for infiltration of up to 75 per cent of the estimated
runoff from rainfalls exceeding 3 mm per day. This is down slightly on the 80 per cent used
in previous investigations (Rockwater 2009). During periods of exceptionally intense rainfall,
and/or if there are significant siltation and debris effects, the soakwell efficiency could reduce
to lower percentages.
The low total volumes of water measured in the monitored soakwells (average 7 m3 total
volume per soakwell for a 110 mm rainfall month) raises some questions as to the practicality
of infiltrating a significant proportion of runoff via local soakwells. With 742 soakwells, this
would allow 5,200 m3 to infiltrate in a 110 mm rainfall month. Actual runoff is calculated to
be 73,000 m3 (August, Table 3). However, the 7 m3 per soakwell might not be typical, as the
catchments for the tested soakwells were quite small; also, the analyses of the data did not
allow for the amount of run-off water that might have entered the soakwells during the water-
level decline from the peaks. A catchment-wide hydrological investigation (including the use
of recording-pluviometers) would be beneficial prior to implementing management practices
based on assumptions of large volumes of local infiltration.
5 NUMERICAL MODELLING OF LAKE WATER LEVELS
5.1 MODEL DESCRIPTION
An existing numerical model (Rockwater 2009) was reconstructed to simulate the water levels
in Lake Jualbup and the surrounding shallow aquifer in relation to rainfall events and
estimated catchment runoff (lake inflow). The new model utilises Visual Modflow 2011.1
which has been developed from the industry standard, MODFLOW software (McDonald and
Harbaugh, 1988). The latest model replaces a previous PMWIN version to make use of
Visual Modflow’s “re-wetting” capacity, which allows cells that have become dry to be
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 13
Rockwater Pty Ltd317.0/12/1
resaturated thereby enabling more-accurate modelling of the lake water-levels and local
surrounds.
The model covers an area measuring 6 km north-south from Lake Monger to the Swan River,
and 9 km east-west from Kings Park to the coast (Fig. 11). It comprises a rectangular grid of
66 rows and 64 columns with cells sizes ranging from 14 mx14 m around the lake to 460 m x
350 m in outlying areas.
The model has two layers, both representing the unconfined superficial aquifer and has
identical input parameters over most of the model area. Layer 1, is used to model the lake,
with the top of the layer set at topographic elevation and the lake cells given unlimited
horizontal hydraulic conductivity and a storage value of one. Cells immediately adjacent to
the lake have been given a reduced horizontal hydraulic conductivity to simulate boundary
conditions between the lake and the surrounding aquifer cells. The permeability of the lake
bed is simulated by varying the vertical hydraulic conductivity of the lake cells.
Constant-head cells were set on the western edge of the model to represent the ocean, and in
the south-eastern area to represent the Swan River. Here, the assigned water-level elevations
are 0 m AHD. Groundwater flows into the modelled area from the north-east and out of the
modelled area to the south-south-west; this flow was simulated using constant-head cells with
water levels set at elevations conforming to measured regional values.
Initial water levels were set at average groundwater levels extrapolated from monitoring-bore
measurements, and aquifer parameters were assigned based on previous modelling
(Rockwater, 2009) and adjusted during calibration, as described below.
5.2 MODEL CALIBRATION AND ADOPTED PARAMETERS
The model was calibrated by adjusting recharge and evapotranspiration parameters to
simulate the observed fluctuations in lake-water and in groundwater levels recorded over the
period 2008 to 2011 at the site monitoring bores (LJ1 to LJ5) and representative regional
monitoring bores (MT1, HS1, CS1, GE4 and KS1) (Fig. 2). Monthly values of rainfall
recharge and estimated runoff to Lake Jualbup, Aberdare Rd CB and Mabel Talbot CB were
used. Additional recharge was also input to Lake Jualbup from August 2010 to December
2011 to represent pumping of dewatering water to the lake from QEII.
Regional rainfall recharge to the aquifer was simulated using 28 per cent of measured
monthly rainfall (Subiaco WTP). The installation of soakwells was simulated by infiltrating
75 per cent of measured monthly rainfall in locations where installation has occurred, from
the year of installation. Monthly runoff into Lake Jualbup was simulated by inputting
additional recharge to the cells representing Lake Jualbup (24,750 m2 area) based on the
calculated volume of runoff over the Shenton Park catchment area. The pumping inflow from
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 14
Rockwater Pty Ltd317.0/12/1
QEII dewatering was similarly input based on estimated additional pumping volumes from
Aberdare Rd. Inflows to the Mabel Talbot and Aberdare Rd compensating basins were also
simulated using the recharge package. Modelled runoff recharge volumes are provided in
Appendix III.
Evaporation from the lake and CBs was simulated using the mean of the monthly rate of pan-
evaporation from Armadale and Upper Swan (Bureau of Meteorology) multiplied by a pan
factor of 0.8. The adopted rates ranged from 606 mm/year (1.7 mm/d) in June to
3156 mm/year (8.6 mm/d) in January.
Comparisons between modelled lake and groundwater levels and measured values are
provided in Figures 12 to 14. The figures show a good to reasonable match between the
simulated and measured results.
Once the simulated lake-water and groundwater levels were reasonably matched to the
measured data, the model was run over a short time interval (54 days) to simulate summer
infiltration at Lake Jualbup. The modelled lake water-level response was compared to
measured water-level decline over the period 8 February 2008 to end of March 2008. The
hydraulic conductivity in the lake cells and the starting groundwater levels were adjusted until
simulated lake water-levels declined at a rate comparable to the measured lake-level decline
over a summer period without rain.
The calibration process showed that the infiltration rate and minimum lake water-level at the
end of summer are most sensitive to the prevailing groundwater conditions (i.e. surrounding
groundwater levels). The modelling was much less sensitive to changes in permeability,
which could be varied by an order of magnitude with little difference in results. The initial
groundwater levels were set to values near the summer minimum (taken from model
simulation results near the end of January), with starting lake levels input at the measured
3.98 m AHD. The full February 2008 recharge was input to the lake cells on the first day of
modelling (to simulate the large rainfall event that filled the lake on that occasion) with no
recharge thereafter. The results are presented in Figure 15 and show a good match between
the modelled and measured infiltration. The results from sensitivity model runs are also
shown in Figure 15 to illustrate how infiltration is affected by changes in lake-bed
permeability and prevailing groundwater levels.
Modelled infiltration rates for the lake over the period of calibration (2008 to mid-2012)
ranged between a minimum of 30 m3/d in summer to a maximum of 2,900 m3/d in winter,
with average values of 650 m3/d and 1,480 m3/d for summer and winter respectively, or an
overall average of 980 m/d. These values are consistent with those reported previously, based
on measured infiltration rates (Rockwater 2005).
The final adopted values for the model aquifer parameters are listed in Table 4. Horizontal
hydraulic conductivity (Kh) values range from 15 to 120 m/d, with the highest values
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 15
Rockwater Pty Ltd317.0/12/1
reflecting the increased proportion of limestone towards the coast. The lake cells were
allocated unrestricted horizontal flow (Kh = 1,000 m/d), with cells immediately surrounding
the lake assigned Kh values lower than the surrounding aquifer (1 to 5 m/d) to represent
reduced hydraulic conductivity due to lake deposits, the wall and surrounding vegetation.
The assigned vertical hydraulic conductivity (Kv) values are 0.1 x Kh m/d, except at Lake
Jualbup where Layer 1 is assigned values of 0.2 to 0.5 m/d. The values for Kv are higher than
used in previous models, but were necessary to simulate predominantly downward flow to the
underlying groundwater system, and were similar to values reported in previous sensitivity
analysis where recharge rates more closely matched the calculated runoff values (Rockwater
2009).
Table 4 : Adopted values of aquifer parameters
Parameter Layer 1 Layer 2
General Values Lake Jualbup General Values
Horizontal Hydraulic
Conductivity (m/d)15 – 120
1,000 and
1 to 5 at boundary15 – 120
Vertical Hydraulic
Conductivity (m/d)0.1 x Kh 0.2 – 0.5 0.1 x Kh
Specific Yield 0.2 1.0 0.2
Storage Coefficient N/A N/A 0.001
N/A = not applicable
5.3 MODEL OPERATION
The primary purpose of the modelling is to assess the efficacy of reducing the permeability of
the lake bed to reduce leakage and maintain an adequate water body in the lake throughout the
year, and to determine the subsequent effects on the surrounding environment, in particular
the potential increase in outflow to the ocean and the reduced infiltration to the superficial
aquifer.
The modelling investigated the effect on water levels in the lake under three different
scenarios:
1. Reduction of lake bed permeability by 25 per cent;
2. Reduction of lake bed permeability by 50 per cent, and;
3. Reduction of lake bed permeability by 75 per cent.
It was originally planned to run each scenario over a period of ten years and consider the
results in the context of each of two options:
1. Maximum lake water levels based on the current height of the drain outlet, and;
2. Maximum lake water levels based on raising the drain outlet by 0.3 m.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 16
Rockwater Pty Ltd317.0/12/1
And address the following:
1. How long is the body of water maintained above the desired minimum water level
(4 m AHD) during periods of no rainfall;
2. By how much will runoff to the lake (i.e. lake inflow) need to be reduced to minimise
loss of water to the outlet drain (as a percentage of current inflow estimates);
3. What volume of water is estimated to flow to the ocean with and without soakwells,
and the potential volume of water saved from overflow through the installation of
local infiltration facilities;
4. What volume of water could potentially be infiltrated to the shallow aquifer via local
soakwells, and an estimate of the number and location necessary to achieve the
required reduction to runoff;
5. How much bore water may be required to supplement the lake and maintain water
levels in an average rainfall year during summer months, and;
6. How would groundwater levels respond in a cycle of higher rainfall. (Added to scope
subsequent to meeting with the Water Corporation).
The polymer application proposed for reducing the permeability of the lake-bed forms an
impermeable seal over the area to which it is applied. It has been advised by the suppliers of
the polymer that the degree of permeability of the seal cannot practically be adjusted by
varying the amount of polymer applied per unit area. Therefore, the percentage of reduction in
the total lake-bed permeability is to be varied by changing the area covered with polymer.
Consequently, the reduction of lake-bed permeability was modelled by making 25, 50 and 75
per cent of the lake cells impermeable (Kv = 0.0001 m/d) for each modelling scenario,
respectively. The modelled scenario is that the polymer was first applied to the south-western
25% of the lake, and then applied in 25% segments progressively north-eastwards. Reduced
permeability at the lake boundary was simulated by decreasing the permeability of the cells
by 50 to 90% (Kh to 0.5 m/d and Kv to 0.125 m/d).
For the predictive modelling runs, average monthly rainfall values for the Subiaco treatment
plant were used (to calculate groundwater recharge of 28% regionally and 75% in areas with
direct stormwater infiltration) along with the calculated values for average rainfall runoff
(Table 3), 90% of which was input to Lake Jualbup as recharge and 10% to Aberdare Rd CB.
The model predicts the water-level fluctuations for the next ten years with the assumption of
average rainfall each year.
For the purposes of modelling, an adequate water body is taken to be one where minimum
lake water-levels are maintained just below the current base of wall at 4.0 m AHD, providing
a minimum water depth of 0.5 m over most of the lake.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 17
Rockwater Pty Ltd317.0/12/1
5.4 PRELIMINARY RESULTS OF MODELLING
5.4.1 Water Levels
Figure 16 shows the results of preliminary modelling, plotting simulated lake water-levels for
each of the three scenarios (25, 50 and 75% reduction in lake bed permeability) compared to
modelled lake levels obtained with no reduction in permeability, i.e. the calibrated model.
The figure shows that minimum lake water-levels could be expected rise 0.4 m from the 2009
and 2010 minimum levels, to 3.4 m AHD, solely as a result of an increase in annual rainfall to
the long-term average. It also shows that of the three scenarios, only a reduction in lake bed
permeability of 75% would achieve the desired minimum water level of 4.0 m AHD assuming
an extended period of average annual rainfall.
A comparison is shown in Figure 17 between the calibrated lake-level simulation and the
results for each of the three scenarios between 2008 and 2012. It can be seen that for a
reduction in lake-bed permeability of 25%, minimum water levels would have been between
0.1 and 0.4 m higher; for a reduction in lake-bed permeability of 50%, minimum water levels
would have been between 0.2 and 0.6 m higher; and for a reduction in lake-bed permeability
of 75%, minimum water levels would have been between 0.3 and 0.8 m higher. In each case,
the eastern side of Lake Jualbup would have dried up during the summers of 2009 and 2010,
and, with the possible exception of the 75% reduced lake-bed permeability scenario, in 2011
and 2012 summer water levels would have fallen well below the desired 4.0 m AHD.
5.4.2 Water-Flow Budget
The water-flow budget was assessed for the calibrated model and the 75% reduction scenario
using the zone budget function in Visual Modflow to compare flow rates over the simulated
time period corresponding to 2009 (i.e. stress periods 13 to 24). The results are presented in
Table 5.
It can be seen that in the calibrated model, approximately 20% of simulated infiltration was
horizontal flow to the lake surrounds, with 80% of the infiltration downwards to the
underlying aquifer in the south-west portion of the lake to be sealed (Zone: SW area sealed).
Following the application of a polymer seal over the base of the lake, the horizontal flow
component increased to 45% of the total infiltration (assuming the sides of the lake are not
completely sealed). Overall, the model predicts a 20% decrease in horizontal flow and 60%
decrease in downward flow over the area sealed for 75% permeability reduction.
The water budget also shows that following the application of the polymer, water will be
mainly lost from the unsealed portion of the lake (Zone: NE area unsealed) with infiltration
rates in this area increasing to three times those simulated for the calibrated model (from a
monthly average of about 155 m3/d to about 490 m3/d).
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 18
Rockwater Pty Ltd317.0/12/1
Table 5 : Modelled water flow budget
Model ZoneRecharge to
Layer 1
Recharge to
Layer 2
Total
Recharge
Horizontal flow
to surrounds
Downward
Infiltration
Total
Infiltration
(m3/d) (m3/d) (m3/d) (m3/d) (m3/d) (m3/d)
NE to SW
(m3/d)
SW to NE
(m3/d)
Calibrated SW area to be sealed
SP 13 117 117 54 211 265 34
SP 14 0 0 22 50 72 7
SP 15 122 37 159 24 79 103
SP 16 60 21 81 20 42 62
SP 17 17 19 36 17 29 46
SP 18 315 355 670 49 193 242
SP 19 1223 120 1343 103 768 871 13 44
SP 20 2516 2516 332 1514 1846 231 178
SP 21 1483 1483 275 1194 1469 62 83
SP 22 816 816 178 785 963 54 38
SP 23 37 37 70 286 356 43
SP 24 196 196 57 219 276 36
Average 100 448 548 40 29
75% reduction SW area sealed
SP 13 117 117 57 125 182 180
SP 14 0 0 34 74 108 68
SP 15 158 158 31 69 100 63
SP 16 83 83 26 58 84 26
SP 17 33 2 35 19 48 67 4
SP 18 623 42 665 39 131 170 139
SP 19 1319 25 1344 81 241 322 765
SP 20 2516 2516 175 370 545 832
SP 21 1483 1483 179 360 539 780
SP 22 816 816 155 312 467 647
SP 23 37 37 101 212 313 382
SP 24 196 196 65 143 208 217
Average 80 179 259 Neg. 342
Calibrated NE area to be unsealed
SP 13 35 35 34 34 35
SP 14 0 0 14 14 7
SP 15 47 47 30 30
SP 16 24 24 10 10
SP 17 0 10 10 5 5
SP 18 1 195 196
SP 19 398 398 41 261 302 13
SP 20 744 744 117 506 623 232
SP 21 439 439 83 377 460 62
SP 22 241 241 42 227 269 54
SP 23 11 11 54 54 43
SP 24 58 58 37 37 35
Average 24 130 153 40 Neg.
75% reduction NE area unsealed
SP 13 35 35 35 269 304 180
SP 14 0 0 10 126 136 68
SP 15 47 47 8 109 117 63
SP 16 24 24 49 49 26
SP 17 9 2 11 14 14
SP 18 166 30 196 223 223 139
SP 19 398 398 88 622 710 765
SP 20 743 743 206 997 1203 833
SP 21 438 438 202 948 1150 781
SP 22 241 241 165 804 969 647
SP 23 11 11 88 511 599 383
SP 24 58 58 44 318 362 217
Average 71 416 486 Neg. 342
Flow between SW
Sealed and NE
Unsealed Area of
Lake
Note: Neg. refers to negligible
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 19
Rockwater Pty Ltd317.0/12/1
5.4.3 Implications for Model Operation
The results from the preliminary modelling indicated that application of the polymer to only
part of the base of the lake, without sealing the sides, is unlikely be sufficiently effective in
reducing infiltration rates to maintain lake water-levels at the desired minimum level. Of the
three scenarios modelled, only a reduction in permeability of 75% was able to raise minimum
lake water-levels to a level considered sufficient for the maintenance of an “adequate water
body” in the lake, assuming annual rainfall levels increase to their long-term average in the
immediate and ongoing future.
Given the uncertainty of any of the proposed management options being able to deliver the
desired objective, a meeting was sought with the City of Subiaco to discuss how to proceed
with the model operation. The meeting outcomes are summarised below:
Application of the polymer to 100% of the lake to form a complete seal is not an
option, based on community consultation and subsequent undertakings of the Council,
therefore it will not be modelled;
There are plans to restore the lake wall along the southern and western boundaries.
This should significantly reduce horizontal flow from the lake in these areas; therefore
the model will be re-run for the 50% and 75% lake-bed cover with hydraulic and
vertical hydraulic conductivities of the boundary cells in these areas further reduced to
0.001 m/d and 0.0001 m/d, respectively.
Detailed assessment of the further options with regard to raising the drain outlet and
increasing local stormwater infiltration through installation of soakwells etc. will only
be conducted for the 75% reduction scenario and the 50% reduction scenario if
modelling results from dot point 2 above indicate it is warranted.
Modelling runs will include an additional scenario to allow for “drying climate”
conditions.
5.5 MODELLING RESULTS
The 50% and 75% reduction scenarios were re-run assuming significantly reduced horizontal
and vertical flow along the southern and western lake boundary, as detailed in Section 4.4.3
above. The results are shown in Figure 18.
It can be seen that further reducing the permeability of the lake wall did not increase lake
water-levels sufficiently in the 50% reduction scenario to achieve the desired minimum lake
water-levels, which remain around 3.8 m AHD (approximately 0.3 m above base of eastern
lobe of the lake) under long-term average rainfall conditions. Reducing the permeability in
the lake wall increased simulated long-term lake water-levels in the 75% reduction scenario
by a further 0.2 m, giving an annual minimum water level of around 4.2 m AHD under long-
term average rainfall conditions (this is 0.7 m above minimum long-term water levels for the
calibrated model).
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 20
Rockwater Pty Ltd317.0/12/1
The modelling runs for the various management options detailed in Section 2.3 were
conducted for the 75% reduced lake-bed permeability scenario, and the results are presented
below.
5.5.1 Impact on Groundwater Levels in the Superficial Aquifer
Figure 19 shows a comparison between simulated groundwater levels for the calibrated model
and the 75% reduction model at Lake Jualbup. It can be seen that the impact on groundwater
levels at the site will be confined to those monitoring bores immediately down-gradient of the
sealed area of the lake, LJ1 and LJ2, where maximum (winter) groundwater levels will be
about 0.7 and 0.4 m lower, respectively, and will occur about one to two months later.
Minimum (summer) groundwater levels in both bores will be within 0.1 m of the pre-sealed
levels. In the monitoring bores up-gradient of the lake and adjacent to the unsealed area,
minimum and maximum levels will remain essentially the same with some small lag in when
maximum water levels are reached.
There will be no measurable impact on groundwater levels regionally (Fig. 20).
5.5.2 Lake Outflow
It is not possible to simulate the flow of water away from the lake via an enclosed drain using
a numerical groundwater modelling package, such as Visual Modflow. However, estimates
of the volume of water above the drain outlet can be made by multiplying the maximum head
above the outlet elevation (5.07 m AHD) by the lake area. (In reality the water levels would
not reach the modelled elevations as the water would spread over a larger area as the lake
walls are breached.) Comparisons between measured and simulated lake water-levels for
calibrated and reduced-permeability model runs are provided in Figure 21 and the results of
volume calculations for the model results, including values for a raised drain outlet (at 5.37 m
AHD) are shown in Table 6.
It can be seen in Figure 21 that modelled lake-levels generally peak higher and over a longer
duration than those measured. This is to be expected as the model does not simulate flow
away from the lake via the overflow drain, nor does it allow the water to spread over a larger
area beyond the lake walls. The impact of reducing the lake bed permeability on maximum
water levels and volumes of outflow can be broadly assessed by comparing the difference
between the calibrated model results and the 75% reduction model run for the years 2008 and
2009 (where the results are not further complicated by dewatering input to the lake) and into
the future assuming a long-term average rainfall.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 21
Rockwater Pty Ltd317.0/12/1
Table 6 : Lake outflow volume calculations
Maximum Lake-
Level (m AHD)
Maximum Level
Above Drain
Outlet (m)
Calculated
Volume Outflow
(m3)
Maximum Level
Above Drain
Outlet (m)
Calculated
Volume Outflow
(m3)
% Water
Saved with
Higher Outlet
Calibrated Model
2008 5.86 0.79 19,553 0.51 12,623 35%
2009 5.41 0.34 8,415 0.05 1,238 85%
75% Reduction
2008 7.2 2.12 52,470 1.82 45,045 14%
2009 6.69 1.51 37,373 1.21 29,948 20%
Factor Increase in Modelled Outflow with Reduced Lakebed Permeabilty
2008 2.7
2009 4.4
Long Term - Ave. Rainfall
Calibrated Model 5.52 0.45 11,138 0.15 3,712 67%
75% Reduction 6.8 1.73 42,818 1.43 35,393 17%
Factor Increase in Modelled Outflow with Reduced Lakebed Permeabilty
3.8
Current Drain Outlet Elevation Raised Drain Outlet Elevation
In general, the modelling suggests that a reduction in lake bed permeability of 75% will
increase outflow to ocean outfall by a factor of between 2.7 and 4.4 (i.e. outflow will be about
3 to 4 times greater than with no reduction in lake-bed permeability). Raising the drain outlet
by 0.3 m could decrease ocean outflow by about 20 to 85% with the higher percentages
relating to situations where the lake-levels rise only small heights above the proposed raised
drain-outlet elevation.
5.5.3 Raising the Drain Outlet
To assess the effect of raising the drain elevation on summer water levels, the model was run
to simulate lake-water level decline over a summer interval with no rain and compared results
for different starting water levels. The model used to calibrate summer infiltration was first
run with lake-bed permeability reduced by 75% and then run again with starting lake-water
levels set 0.3 m higher; the results are presented in Figure 22. The modelling indicates that
lake water-levels would be about 0.7 m higher at the end of the summer period with the lake-
bed permeability reduced by 75%, and that this would increase a further 0.1 m (total 0.8 m
higher) if the starting water levels were 0.3 m higher.
An additional benefit of raising the drain elevation would be to provide more time and a
larger area over which water would be able to infiltrate, thereby increasing recharge to the
aquifer at the site.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 22
Rockwater Pty Ltd317.0/12/1
5.5.4 Maximum Lake Levels
The maximum lake levels generated in the model runs are not representative of the true lake
levels that would occur at the site. This is because: (1) water in the model is confined to the
area of the lake cells, rather than spreading over a larger area as the lake walls are breached,
and (2) flow from the drain outlet is not accounted for.
Using the volumes calculated in Section 4.5.2, maximum water levels at the park can be
estimated using the Shenton Park compensating basin volumes provided by the Water
Corporation (Appendix I). For a maximum modelled lake-level of 6.8 m (based on long-term
average rainfall and a 75% reduction in lake-bed permeability), the volume of water above the
drain outlet is calculated by the model to be 42,820 m3. This corresponds to a maximum water
level at the park of about 6.2 m AHD, covering an area of about 42,500 m2 (1.7 times the area
of the lake). These estimates do not take into consideration the drain outflow, which could
lower water levels by around 0.4 m/d (based on the data available, this value is valid for both
the current and proposed drain outlet elevations).
5.5.5 Maintaining Lake Levels above the Desired Minimum during Summer Periods of
No Rainfall
The length of time an “adequate water body” would be maintained in the lake during a period
of no rainfall was assessed by running the 75% reduction model with no rainfall recharge
from December to March, and comparing the results with the calibrated model and the 75%
reduction scenario. The results for drought summer conditions are shown in Figure 23. The
modelling indicates lake levels would fall below the desired minimum (4.0 m AHD) after
approximately 9 weeks and would decline to a minimum of about 3.5 m AHD. Water levels
would remain below the minimum desired level for about 10.5 weeks, assuming average
rainfall in April. Water levels in the lake would remain above the minimum desired level for
about eight weeks longer than they would under the current conditions, and the lake would
retain water in the eastern side for an additional five weeks.
Given that raising the drain outlet by 0.3 m may result in lake levels being about 0.1 m higher
at the end of an extended period with no rainfall (Section 4.5.1), it can be estimated that the
lake levels may remain above the minimum desired level for about a further one week if the
drain outlet was raised.
An estimate of the volume of water required to be pumped to the lake to maintain an adequate
body of water over the period in which levels fall below the desired minimum was obtained
by running the model from January to April 2016, with starting groundwater levels set at
those modelled for the end of January and lake levels held at 4.0 m AHD using a constant
head boundary. The zone budget package was used to calculate the water inflow to the lake
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 23
Rockwater Pty Ltd317.0/12/1
from the constant head boundary, which equates to the total net seepage and evaporation from
the lake. The results are presented in Table 7.
Table 7 : Estimated water requirements to maintain minimum desired water-levels
Month
Estimated
Water
Requirement Total Volume
(m3/d) (m3)
January 341 10,571
February 392 10,976
March 427 13,237
April 367 11,377
Total 46,161
The modelling results indicate that with the lake-bed permeability reduced by 75% during an
extended summer period of no rainfall in an otherwise average rainfall year, pumping rates of
between about 370 and 430 m3/d may be required to maintain lake levels at 4.0 m AHD.
While these values are considered to be realistic, they should be taken as approximations due
to the uncertainties inherent in groundwater modelling.
5.5.6 Reducing Lake Inflow
To assess by how much the runoff to the lake would have to be reduced to minimise water
outflow to the ocean, the model was run to simulate 25 %, 50 % and 75 % less runoff
recharge to the lake. The corresponding amount of runoff water not recharged to the lake was
assumed to be infiltrated via soakwells within the Shenton Park catchment. The resulting lake
water levels are shown in Figure 24.
Figure 24 shows that at least 75% of the current average inflow to the lake needs to be
maintained if the minimum desired lake-water levels are to be achieved. A comparison
between maximum modelled lake levels for 75% reduction scenario with and without 25%
soakwell infiltration is shown in Figure 25; it shows that maximum lake levels would be
about 0.7 m lower, corresponding to about 40% less outflow from the lake (Table 8). This
saving would increase to about 60% if the drain outlet was raised by 0.3 m.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 24
Rockwater Pty Ltd317.0/12/1
Table 8 : Calculated volumes of outflow for model simulations with and without
soakwell infiltration
75% Reduction in Lake-bed
Permeability
Maximum Lake-
Level
Maximum Level
Above Existing
Drain Outlet
Calculated
Volume
Maximum Level
Above Proposed
Drain Outlet
Calculated
Volume
(m AHD) (m) (m3) (m) (m3)
Without Infiltration 6.8 1.73 42,818
With 25% Infiltration 6.1 1.03 25,493 0.73 18,068
Decrease in Modelled Outflow 17,325 24,750
Percentage Less Outflow 40% 58%
5.5.7 Infiltration via Soakwells
Comparison between modelled inflow via soakwells in the calibrated model and the values
measured in the field suggests the model significantly over-estimates soakwell infiltration
rates (e.g. for the Shenton Park catchment, soakwells in the calibrated model contributed the
equivalent to 156 m3 per drain for a month with total rainfall of 110 mm, whereas the
measured volumes of infiltration were between 1.8 and 15 m3 (average 7 m3) for August
2012, with total rainfall of 110 mm). The discrepancy potentially occurs because of the size
of the model cells to which the higher recharge rates are applied (minimum 15 m x 50 m), and
the more restricted flow conditions imposed on the concrete lined soakwells. In addition, it is
unclear from the field results as to how much of the measured rainfall actually fell in the areas
studied and how much runoff occurs in the catchment zone serviced by each of the soakwells,
and so the percentage of rainfall intercepted and infiltrated at the monitored sites is unknown.
The modelled recharge via soakwells has been allowed to stand in the calibrated model, and
simply represents slightly higher rates of overall regional rainfall recharge.
Given the noted limitations in the current model set-up and the uncertainty in the field results
(Section 3.5) no attempt has been made to quantify the number or specify locations for
soakwells at this time. There were reported to be a total of 742 ‘export drainage pits’ in the
Shenton Park catchment, and this would be the total number of soakwell sites currently
available; 60 of these have to date been converted to soakwells. A detailed field investigation
covering the whole catchment area would be needed to clarify the efficacy of soakwell
infiltration and optimum siting for the soakwells.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 25
Rockwater Pty Ltd317.0/12/1
5.5.8 Changes to Climatic Conditions
Wet Cycle
The Water Corporation has requested that the model be run to simulate a “wet cycle” in order
to obtain background hydrogeological conditions for input into their surface-water modelling,
which investigates potential flooding conditions under a worst case scenario. The present
groundwater model was run using rainfall data from the Perth Airport (BOM station 9021)
over the period 1961 to 1966, when the average annual rainfall was 927.4 mm – 30% higher
than the Shenton Park long-term annual average of 707.4 mm. The runoff recharge to the lake
was also increased by 30%. The results are presented in Figure 26.
Figure 26 shows that maximum groundwater levels in the immediate vicinity of the lake may
reach 6 m AHD, which would bring the water table very close to ground level. Groundwater
mounding would centre on the north-east sector of the lake where the impermeable seal is
absent. Maximum modelled lake levels are 8 m AHD (Fig. 27). This corresponds to a
modelled volume of 72,520 m3 above the current drain outlet, which can be used to obtain an
estimated peak value of about 6.9 m AHD (using the plot in Appendix I). This does not
allow for the water-level decline of approximately 0.4 m/d that will occur as a result of water
discharging to the outflow drain and so actual peak levels would be significantly lower.
Drying Climate
It is generally considered that the climate in South Western Australia is likely to become drier
over time (Department of Water, 2009) and so the implications for management of Lake
Jualbup have been considered.
The model was run to simulate a drying climate, assuming a 15% decrease in rainfall and
associated runoff. The results are shown in Figure 28, and indicate that long-term average
minimum lake levels might be about 0.3 m lower, but would be maintained at about
3.9 m AHD, close to the desired minimum lake levels. Long term average maximum lake
levels would be about 0.5 m lower. Actual lake levels would probably be lower than
presented however, as the corresponding increases in evapotranspiration and local pumping
have not been considered.
6 CONCLUSIONS AND RECOMMENDATIONS
Numerical groundwater modelling has been undertaken to assess the hydrogeological
requirements for maintenance of “an adequate body of water” in Lake Jualbup throughout the
year. For the purposes of this investigation, an adequate body of water has been assumed to
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 26
Rockwater Pty Ltd317.0/12/1
be one in which lake levels are maintained at a minimum of 4.0 m AHD, providing a
minimum water depth in the lake of 0.5 m.
Preliminary modelling investigated the reduction of the lake-bed permeability by 25%, 50%
and 75% by the application of a polymer over 25%, 50% and 75% of the lake floor. The
results indicated that the minimum water-level requirement could only be met with a 75%
reduction in lake bed permeability (i.e. with 75% of the lake-bed, made impermeable) and so
the scope of work was modified, in consultation with the City of Subiaco, to focus on this
scenario. The reviewed model operation also assumes that a new wall will be built along the
southern and western boundary of the lake, to reduce horizontal flow of water out of the lake.
For a 75 % reduction in lake-bed permeability, the reviewed model indicates that minimum
summer water levels in the lake would increase by about 0.7m to 4.2 m AHD, assuming long-
term average monthly rainfall. Minimum summer lake levels of 3.8 m AHD (an increase of
0.3 m) could be maintained, assuming long term average rainfall, if 50% of the lake bed was
made impermeable.
If the lake-bed permeability was reduced by 75%, groundwater levels in the superficial
aquifer would only be affected immediately down-gradient of the lake where the polymer had
been applied, with maximum groundwater levels in this area falling by about 0.4 to 0.7 m and
minimum groundwater levels about 0.1 m lower. There would be no measureable effect on
the superficial aquifer regionally.
Outflow from the lake to the main drain might increase by 2.7 to 4.4 times for a 75%
reduction in lake-bed permeability. Outflow for this scenario could be reduced by about 20%
in the long term if the drain outlet was raised by 0.3 m to 5.37 m AHD. In addition, raising
the drain outlet could potentially increase the end of summer minimum water levels by a
further 0.1 m and provide increased opportunity for local infiltration of water to the aquifer
via the grassed area surrounding the lake.
During an extended (four month) summer period with no rain, the lake may still dry out over
the eastern side, with water levels falling to almost 3.5 m AHD. Modelled lake water levels
fell below the desired minimum after about nine weeks with no rainfall, and reached a
minimum of 3.5 m AHD after seventeen weeks with a 75% reduction in lake-bed
permeability. The lake levels remained above the desired minimum for about eight weeks
longer than they would under current conditions, and the lake remained wet for an additional
five weeks. If the drain was raised, the lake might retain water for an additional week or so.
The modelling results suggest between 340 and 430 m3/d would need to be pumped to the
lake to maintain water levels at 4.0 m AHD under these conditions.
Modelling of reduced lake inflow (for the 75% reduced permeability scenario), showed that in
order to achieve the desired minimum lake water levels at least 75% of the current inflow
needed to be maintained. If 25% of the rainfall runoff from Shenton Park was infiltrated via
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 27
Rockwater Pty Ltd317.0/12/1
local infiltration soakwells, outflow from the lake could be reduced by approximately 40%.
This saving would increase to 60% if the drain outlet was raised by 0.3 m. While the model
results are promising, field monitoring of existing infiltration soakwells raised questions as to
the practicality of infiltrating a significant proportion of runoff via soakwells and a
catchment-wide hydrological investigation would be appropriate prior to implementing
management practices based on the assumption of large volumes of local infiltration.
Reducing the permeability of the lake-bed has implications for the risk of flooding that are
beyond the scope of this investigation. What the modelling does suggest, however, is that
maximum monthly water levels may reach about 6.2 m AHD in a year of average rainfall and
6.9 m AHD in a wet cycle (extended period with 30% higher than average rainfalls). These
levels do not allow for outflow to the main drain, which could lower water levels by about
0.4 m/d. Groundwater level contours have been provided showing maximum groundwater
levels in a wet cycle for use by the Water Corporation in their surface water modelling.
Given the potential for average annual rainfall to continue to decline, the model was run to
simulate a dry cycle (15% less rainfall). The results indicate that for a 75% reduction in lake
bed permeability, lake water levels could still be maintained near the desired minimum level,
at 3.9 m AHD; however this is conservative and higher evapotranspiration rates and increased
local pumping might lower the level further.
It is unlikely that reducing the lake-bed permeability by anything less than 75% will achieve
the desired outcome of maintaining an adequate water body in Lake Jualbup, and so
application of the polymer seal to 75% of the lake-bed surface, working from the south-west
back to the north-east is recommended. If practicable, application to 50% of the lake might
be trialled as a preliminary measure to test the modelling results.
In addition, it is recommended that the drain outlet elevation be raised 0.3 m to 5.37 m AHD
to maximise infiltration outside the lake perimeter, reduce outflow to the main drain and
contribute to the maintenance of higher water levels in the lake.
Lake water levels, groundwater levels and lake water quality should continue to be monitored
and assessed to validate the modelling results and provide ongoing review of the modified
conditions at the lake.
Dated: 26 November 2012 Rockwater Pty Ltd
K. J. Johnston
Principal Hydrogeologist
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 28
Rockwater Pty Ltd317.0/12/1
REFERENCES
Davidson, W. A., 1995, Hydrogeology and groundwater resources of the Perth Region,
Western Australia: Western Australian Geological Survey, Bulletin 142
Department of Water, 2009. Perth-Peel regional water plan 2010 – 2030. Responding to our
drying climate. Draft for public comment, December 2009.
McDonald, M.G., and W.A. Harbaugh, 1988, MODFLOW, A Modular Three-Dimensional
Finite-Difference Ground-Water Flow Model. U.S. Geological Survey, Washington,
DC. (A:3980), open file report 83–875, Chapter A1.
McFarlane, D.J. 1983: Effects of urbanization on groundwater quality and quantity in Perth,
Western Australia. University of Western Australia, Department of Geology, PhD
thesis.
Rockwater Pty Ltd, 2005a Hydrogeology of Lake Jualbup, Shenton Park, and options for
maintaining water levels. Unpublished Report (317.0/05/01) for City of Subiaco.
Rockwater Pty Ltd, 2005b Water Requirements for maintaining lake level, Lake Jualbup,
Shenton Park. Unpublished Report (317.0/05/02) for City of Subiaco.
Rockwater Pty Ltd, 2009 Hydrogeological evaluation to guide stormwater management
principles in the City of Subiaco. Unpublished Report (317.0/09/01) for City of
Subiaco.
Sim, D.A., 1995 The impact of stormwater runoff on the hydrogeology and chemistry of an
urban lake. Dissertation for Degree of Bachelor of Science, Natural Resource
Management. Department of Soil Science, University of Western Australia.
Water Quality Bibliography
ENV Australia Pty Ltd, 2008. Constructed lakes in the Perth metropolitan area and South
West region. Literature review and interview project. Prepared for Department of
Water, Western Australian Local Government Association and Urban Development
Institute of Australia. November 2008.
Horticulture and Turf Diagnostic Services, 2008. Monitoring program of lake water and
sediment quality in the City of Subiaco. Prepared for City of Subiaco. February 2008.
City of Subiaco
Hydrogeological Investigation to Maintain an Adequate Body of Water in Lake JualbupPage 29
Rockwater Pty Ltd317.0/12/1
JDA Consultant Hydrogeologists, 2007. WESROC total water cycle monitoring program
2004-2006. Prepared on behalf of Western Suburbs Regional Organisation of
Councils. January 2007.
Sims, D.A., 1995, The Impact of Stormwater Runoff on the Hydrology and Chemistry of an
Urban Lake. Dissertation submitted to Department of Soil Science, UWA, Western
Australia.
Rockwater Pty Ltd317.0/12/1
FIGURES
CLIENT: City of Subiaco
PROJECT: Hydrogeological Investigation - Lake Jualbup
DATE: July 2012
Dwg. No: 317.0/12/1-1
LOCALITY MAP
Rockwater Pty Ltd
Figure 1
317.0/Surfer/Fig 1 Subi Topo & Cadastral.srf
387000 387500 388000 388500 389000 389500 390000 390500 391000 391500
Eastings (m MGA)
6461500
6462000
6462500
6463000
6463500
6464000
6464500
6465000
6465500
6466000
6466500
6467000
6467500
Nort
hin
gs
(mM
GA
)LEGEND
City of Subiaco
Catchment, Wembley-JolimontMain Drain (Mabel Talbot)
Catchment, Subiaco MainDrain (Cliff Sadlier)
Catchment, Shenton Park(Jualbup)
Main Drain
Branch Drain
Compensation Basin
Aberdere Rd CB
Lake Jualbup
Cliff Sadlier
Mabel Talbot
386500 387000 387500 388000 388500 389000 389500 390000 390500
Eastings (m MGA)
6462000
6462500
6463000
6463500
6464000
6464500
6465000
6465500
Nort
hin
gs
(mM
GA
)
MT1
HS1
CS1
LJ1
LJ2LJ3
LJ4 LJ5
KS1
GE4
GD6
SW1
SW2SW3
Rockwater Pty Ltd
317.0/Surfer/Fig 2 Subi Locality Plan.srf
CLIENT: City of Subiaco
PROJECT: Hydrogeological Evaluation - Lake Jualbup
DATE: July 2012
Dwg. No: 317.0/12/1-2
Figure 2
SWAN RIVER
KINGS PARK
Catchment, Wembley-JolimontMain Drain (Mabel Talbot)
Catchment, Subiaco MainDrain (Cliff Sadlier)
Catchment, Shenton Park(Lake Jualbup)
Compensating Basin
Main Drain
Branch Drain
Piezometer
Soakwell, Tested July/August 2012
Soakwell installed prior toApril 2009
LEGEND
317.0/Surfer/Fig 3 Lake Jualbup WLs Sep 11.srf
Figure 3
387550 387600 387650 387700 387750 387800 387850 387900 387950
Eastings (m MGA)
6463400
6463450
6463500
6463550
6463600
6463650
6463700
6463750
Nort
hin
gs
(mM
GA
)
(LJ1)
(LJ2)
(LJ3)
(LJ4) (LJ5)
4.15
4.49
4.47
4.29 4.31
4.1
4.2
4.2
4.3
4.3
4.3
4.4
4.4
4.4
4.4
4.5
4.5
4.5
317.0/Surfer/Fig 4 Lake Jualbup WLs Mar 12.srf
Figure 4
387550 387600 387650 387700 387750 387800 387850 387900 387950
Eastings (m MGA)
6463400
6463450
6463500
6463550
6463600
6463650
6463700
6463750
Nort
hin
gs
(mM
GA
)
(LJ1)
(LJ2)
(LJ3)
(LJ4) (LJ5)
3.01
3.27
3.46
3.61 3.79
3
3.2
3.2
3.4
3.4
3.6
3.6
3.8
Fig
ure
5
Rockw
ate
rP
tyLtd
31
7.0
/Gra
ph
er/
Fig
5G
E4
Hyd
rog
raph
.grf
1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 20120
1
2
3
4
5
Wate
rLevel(m
AH
D)
1978 1980 1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 20120
100
200
300
400
500
600
700
800
900
1000
Rain
fall(m
m)
Fig
ure
6
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Fig
6L
ake
Le
vels
20
08
-20
12
.grf
Feb-08 Aug-08 Feb-09 Aug-09 Feb-10 Aug-10 Feb-11 Aug-11 Feb-12 Aug-12 Feb-13
Date
0
10
20
30
40
50
60
70
Rain
fall(m
m)
0
2
4
6
Pum
phours
Perth Metro Subiaco Treatment Plant
Feb-08 Aug-08 Feb-09 Aug-09 Feb-10 Aug-10 Feb-11 Aug-11 Feb-12 Aug-12
Date
0
1
2
3
4
5
6
Wate
rLeve
l(mA
HD
)
Monthly lake levels - RW
Daily lake levels - GD
Fig
ure
7
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Fig
7L
J1to
LJ5
Hyd
rog
rap
hs.g
rf
Ap
r-09
Ma
y-09
Jun
-09
Jul-0
9
Au
g-0
9
Se
p-0
9
Oct-0
9
No
v-09
De
c-09
Jan
-10
Fe
b-1
0
Ma
r-10
Ap
r-10
Ma
y-10
Jun
-10
Jul-1
0
Au
g-1
0
Se
p-1
0
Oct-1
0
No
v-10
De
c-10
Jan
-11
Fe
b-1
1
Ma
r-11
Ap
r-11
Ma
y-11
Jun
-11
Jul-1
1
Au
g-1
1
Se
p-1
1
Oct-1
1
No
v-11
De
c-11
Jan
-12
Fe
b-1
2
Ma
r-12
Ap
r-12
Ma
y-12
Jun
-12
Jul-1
2
Date
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
0
20
40
60
Rain
fall
(mm
)
Pumping into the lakefrom QEII dewatering
Ap
r-09
Ma
y-09
Jun
-09
Jul-0
9
Au
g-0
9
Se
p-0
9
Oct-0
9
No
v-09
De
c-09
Jan
-10
Fe
b-1
0
Ma
r-10
Ap
r-10
Ma
y-10
Jun
-10
Jul-1
0
Au
g-1
0
Se
p-1
0
Oct-1
0
No
v-10
De
c-10
Jan
-11
Fe
b-1
1
Ma
r-11
Ap
r-11
Ma
y-11
Jun
-11
Jul-1
1
Au
g-1
1
Se
p-1
1
Oct-1
1
No
v-11
De
c-11
Jan
-12
Fe
b-1
2
Ma
r-12
Ap
r-12
Ma
y-12
Jun
-12
Jul-1
2
Date
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
Bores about 100 m north of Lake Jualbup
Rockwater Pty Ltd
317.0/Surfer/Fig 8 Drainage Gullys.srf
CLIENT: City of Subiaco
PROJECT: Hydrogeological Evaluation - Lake Jualbup
DATE: July 2012
Dwg. No: 317.0/12/1-8
Figure 8
SWAN RIVER
KINGS PARK
Catchment, Wembley-JolimontMain Drain (Mabel Talbot)
Catchment, Subiaco MainDrain (Cliff Sadlier)
Catchment, Shenton Park(Lake Jualbup)
Compensating Basin
Drainage Cell
Main Drain
Branch Drain
Gully Drainage Pit
Side-entry Drainage Pit
Soakwell, monitored July/August 2012
Soakwell installed prior toApril 2009
Drain Outlet
LEGEND
386500 387000 387500 388000 388500 389000 389500 390000 390500
Eastings (m MGA)
64620
00
6462500
6463000
6463500
6464000
6464500
6465000
6465500
Nort
hin
gs
(mM
GA
)
SW1
SW2SW3
6
6
7
7
7
8
8
8
10
10
10
10
10
10
12
12
12
12
12
12
14
14
14
1414
14
14
16
16
16
16
16
18
18 20
387300 387400 387500 387600 387700 387800 387900 388000 388100
Eastings (m MGA)
646310
06463200
6463300
6463400
6463500
6463600
6463700
6463800
6463900
Nort
hin
gs
(mM
GA
)
LJ1
LJ2
LJ3
LJ4 LJ5
Rockwater Pty Ltd
317.0/Surfer/Fig 9 Local topograph.srf
CLIENT: City of Subiaco
PROJECT: Hydrogeological Evaluation - Lake Jualbup
DATE: September 2012
Dwg. No: 317.0/12/1-9
Figure 9
Compensating Basin
Topographic contour (m AHD)
Branch Drain
Piezometer
LEGEND
Herb
ert
Rd
Keightly Rd
Excels
ior
St
Evans St
Nicholson Rd
Lake Ave
Fig
ure
10
31
7.0
/Gra
ph
er/F
ig1
0S
oa
kwe
llsJu
lya
nd
Au
gu
st.grf
21-Jul-12 28-Jul-12 4-Aug-12 11-Aug-12 18-Aug-12 25-Aug-12 1-Sep-12
0.80
1.20
1.60
2.00
2.40Pre
ssu
reH
ead
notco
mpensa
ted
(m)
0
10
20
30
Daily
Rain
fall(m
m)
Rainfall (mm) Pressure head (m)
21-Jul-12 4-Aug-12 18-Aug-12 1-Sep-12
0.80
1.20
1.60
2.00Pre
ssure
Head
notco
mpensa
ted
(m)
0
10
20
30
Daily
Rain
fall(m
m)
Rainfall (mm) Pressure head (m)
21-Jul-12 28-Jul-12 4-Aug-12 11-Aug-12 18-Aug-12 25-Aug-12 1-Sep-12
0.80
1.20
1.60
2.00Pre
ssure
Head
notco
mpensa
ted
(m)
0
10
20
30
Daily
Rain
fall(m
m)
Rainfall (mm) Pressure head (m) 142 Keightly Rd
119 Keightly Rd
5 Waverly St
Rockwater Pty Ltd
317.0/Surfer/Fig 11 Model extent.srf
CLIENT: City of Subiaco
PROJECT: Hydrogeological Evaluation - Lake Jualbup
DATE: September 2012
Dwg. No: 317.0/12/1-11
Figure 11
Fig
ure
12
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
2M
od
elle
dL
ake
Le
vels
20
08
-20
12
.grf
Feb-08 Aug-08 Feb-09 Aug-09 Feb-10 Aug-10 Feb-11 Aug-11 Feb-12 Aug-12
Date
0
10
20
30
40
50
60
70
Rain
fall(m
m)
0
2x104
4x104
6x104
Modelle
dR
echarg
e(m
m/yr)
Perth Metro Subiaco Treatment Plant
Feb-08 Aug-08 Feb-09 Aug-09 Feb-10 Aug-10 Feb-11 Aug-11 Feb-12 Aug-12
Date
0
1
2
3
4
5
6
Wate
rLeve
l(mA
HD
)
Monthly lake levels - RW Daily lake levels - GD Modelled lake levels Modelled recharge
0
2x104
4x104
6x104
Modelle
dR
echarg
e(m
m/yr)
Fig
ure
13
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
3L
J1to
LJ5
.grf
Jan
-08
Fe
b-0
8
Ma
r-08
Ap
r-08
Ma
y-08
Jun
-08
Jul-0
8
Au
g-0
8
Se
p-0
8
Oct-0
8
No
v-08
De
c-08
Jan
-09
Fe
b-0
9
Ma
r-09
Ap
r-09
Ma
y-09
Jun
-09
Jul-0
9
Au
g-0
9
Se
p-0
9
Oct-0
9
No
v-09
De
c-09
Jan
-10
Fe
b-1
0
Ma
r-10
Ap
r-10
Ma
y-10
Jun
-10
Jul-1
0
Au
g-1
0
Se
p-1
0
Oct-1
0
No
v-10
De
c-10
Jan
-11
Fe
b-1
1
Ma
r-11
Ap
r-11
Ma
y-11
Jun
-11
Jul-1
1
Au
g-1
1
Se
p-1
1
Oct-1
1
No
v-11
De
c-11
Jan
-12
Fe
b-1
2
Ma
r-12
Ap
r-12
Ma
y-12
Jun
-12
Jul-1
2
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
Fig
ure
14
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
4M
od
elle
dW
Ls
Re
gio
na
lBo
res.g
rf
Jan
-08
Fe
b-0
8
Ma
r-08
Ap
r-08
Ma
y-08
Jun
-08
Jul-0
8
Au
g-0
8
Se
p-0
8
Oct-0
8
No
v-08
De
c-08
Jan
-09
Fe
b-0
9
Ma
r-09
Ap
r-09
Ma
y-09
Jun
-09
Jul-0
9
Au
g-0
9
Se
p-0
9
Oct-0
9
No
v-09
De
c-09
Jan
-10
Fe
b-1
0
Ma
r-10
Ap
r-10
Ma
y-10
Jun
-10
Jul-1
0
Au
g-1
0
Se
p-1
0
Oct-1
0
No
v-10
De
c-10
Jan
-11
Fe
b-1
1
Ma
r-11
Ap
r-11
Ma
y-11
Jun
-11
Jul-1
1
Au
g-1
1
Se
p-1
1
Oct-1
1
No
v-11
De
c-11
Jan
-12
Fe
b-1
2
Ma
r-12
Ap
r-12
Ma
y-12
Jun
-12
Jul-1
2
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
Wate
rLeve
l(mA
HD
)
3.0
3.5
4.0
4.5
5.0
5.5
6.0
6.5
Wate
rLeve
l(mA
HD
)
Fig
ure
15
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
5In
filtratio
nC
urve
.grf
7-F
eb-08
21-F
eb-08
6-M
ar-08
20-Mar-08
2.5 3
3.5 4
4.52
.6
2.7
2.8
2.9
3.1
3.2
3.3
3.4
3.6
3.7
3.8
3.9
4.1
4.2
4.3
4.4
LakeWaterLevels(mAHD)
Me
asu
red
Wa
ter
Le
ve
ls
Mo
de
lled
Wa
ter
Le
vels
Gro
un
dw
ate
rL
eve
ls1
mh
igh
er
La
keP
erm
ea
bility
(Kh
&K
v)
Re
du
ce
d1
0x
Fig
ure
16
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
6R
ed
uce
dp
erm
ea
bility
La
keL
eve
ls
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22
3
4
5
6
7
8
Wate
rLevel(m
AH
D)
Lake Levels - no reduction in permeability Lake Levels - reduced permeability
75% Reduced Lake Bed Permeability
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
50% Reduced Lake Bed Permeability
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
25% Reduced Lake Bed Permeability
Minimum desired lake-water level
Calibrated intervalPredictive modelling
Calibrated interval Predictive modelling
Calibrated intervalPredictive modelling
Fig
ure
17
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
7R
ed
uce
dp
erm
ea
bility
La
keL
eve
ls
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12
3
4
5
6
7
8
Wate
rLevel(m
AH
D)
Lake Levels - no reduction in permeability Lake Levels - reduced permeability
75% Reduced Lake Bed Permeability
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
50% Reduced Lake Bed Permeability
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
25% Reduced Lake Bed Permeability
Minimum desired lake-water level
Fig
ure
18
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
8R
ed
uce
dp
erm
ea
bility
La
keL
eve
lsN
ew
Wa
ll.grf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
75% Reduced Lake Bed Permeability
3
4
5
6
7
Wate
rLeve
l(mA
HD
)
50% Reduced Lake Bed Permeability
Minimum desired lake-water level
Fig
ure
19
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
9L
J1to
LJ5
75
pcre
d.g
rf
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Wate
rLeve
l(mA
HD
)
Fig
ure
20
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
0m
od
elle
dW
Ls
Re
gio
na
l75
pcre
d.g
rf
2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
Wate
rLeve
l(mA
HD
)
3.0
3.5
4.0
4.5
5.0
5.5
6.0
Wate
rLevel(m
AH
D)
Fig
ure
21
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
1W
ate
ro
utflo
wa
ssessm
en
t.grf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22 Jan-23
3
4
5
6
7
8
9
Wate
rLeve
l(mA
HD
)
Current Drain Outlet ElevationProposed Drain Outlet Elevation
Calibrated interval Predictive modelling
Fig
ure
22
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
2In
filtratio
nC
urve
.grf
7-F
eb-08
21-F
eb-08
6-M
ar-08
20-Mar-08
2.5 3
3.5 4
4.52
.6
2.7
2.8
2.9
3.1
3.2
3.3
3.4
3.6
3.7
3.8
3.9
4.1
4.2
4.3
4.4
LakeWaterLevels(mAHD)
Ca
libra
ted
Mo
de
lWa
ter
Le
ve
ls
La
ke
-be
dP
erm
ea
bility
Re
du
ce
d7
5%
La
ke
-be
dP
erm
ea
bility
Re
du
ce
d7
5%
Ou
tlet
Dra
inR
ais
ed
0.3
m
Fig
ure
23
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
3N
osu
mm
er
rain
.grf
1-Dec-15 29-Dec-15 26-Jan-16 23-Feb-16 22-Mar-16 19-Apr-16
2.5
3.0
3.5
4.0
4.5
5.0
5.5
6.0
Wate
rLeve
l(mA
HD
)
Current Drain Outlet Elevation
Proposed Drain Outlet Elevation
Minimum desired lake-water level
Fig
ure
24
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
4S
Win
filtratio
nm
od
ellin
g.g
rf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22
3
4
5
6
7
8
9
Wate
rLeve
l(mA
HD
)
Current Drain Outlet Elevation
Proposed Drain Outlet Elevation
Minimum desired lake-water level
Fig
ure
25
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
5S
Win
filtratio
nd
rain
ou
tflow
com
p.g
rf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22
3
4
5
6
7
8
9
Wate
rLeve
l(mA
HD
)
Current Drain Outlet Elevation
Proposed Drain Outlet Elevation
Minimum desired lake-water level
317.0/Surfer/Fig 26 Wet cycle.srf
Figure 26
387550 387600 387650 387700 387750 387800 387850 387900 387950
Eastings (m MGA)
6463400
6463450
6463500
6463550
6463600
6463650
6463700
6463750
Nort
hin
gs
(mM
GA
)
(LJ1)
(LJ2)
(LJ3)
(LJ4) (LJ5)
4.5
55
5
5.5
5.5
5.5
6
Fig
ure
27
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
7R
ed
uce
dp
erm
ea
bility
La
keL
eve
lsW
etC
ycle.g
rf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22
3
4
5
6
7
8
Wate
rLeve
l(mA
HD
)
Overflow Drain Elevation
Calibrated interval Predictive modelling
Fig
ure
28
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig2
87
5p
cre
dd
rycycle
lake
leve
ls.grf
Jan-08 Jan-09 Jan-10 Jan-11 Jan-12 Jan-13 Jan-14 Jan-15 Jan-16 Jan-17 Jan-18 Jan-19 Jan-20 Jan-21 Jan-22 Jan-23
3
4
5
6
7
8
9
Wate
rLeve
l(mA
HD
)
Current Drain Outlet Elevation Minimum Desired Lake Level
Calibrated interval Predictive modelling
Rockwater Pty Ltd317.0/12/1
APPENDIX I
HEAD DISCHARGE RELATIONSHIP FOR
SHENTON PARK DRAIN OUTLET
Ap
pI-
A
31
7.0
/Gra
ph
er/H
ydro
ge
olo
gica
lInve
stiga
tion
/Mo
de
lling
Re
sults/F
ig1
9W
ate
ro
utflo
wa
ssessm
en
t.grf
Plots generated using data provided by the Water Corporation.
5 6 7 8Elevation (m AHD)
0
20000
40000
60000
80000
100000
120000
140000
Volu
me
Above
5m
AH
D(m
3)
5 6 7 8Elevation (m AHD)
20000
30000
40000
50000
60000
Pla
nA
rea
Above
5m
AH
D(m
2)Modelled volume
Corresponding Water Level
Maximum lake levels:long term average rainfall.
Maximum lake levels:Wet cycle30% above long term average rainfall.
Rockwater Pty Ltd317.0/12/1
APPENDIX II
PEAK WATER LEVELS IN MONITORED STORMWATER
INFILTRATION WELLS 16 JULY – 28 AUGUST 2012
App
II-
A
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII-
5W
ave
rlyJu
lyd
ata
.grf
0 120 240 360 480 600
Time (min)
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 60 120 180 240 300 360 420
Time (min)0 60 120 180 240 300
Time (min)0 60 120 180 240 300
Time (min)0 60 120 180 240
Time (min)0 180 360 540
Time (min)
31 July 2012 1 August 2012 1 August 2012 2 August 2012
(3.0 mm) (4.8 mm) (12.4 mm)(6.6 mm) (12.8 mm)
16 July 2012 2 & 3 August 2012
(20.0 mm)
App
II-
B
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII
-5
Wa
verly
Au
gu
stDa
ta.g
rf
12 August 2012 14 August 2012 21 August 201227 August 2012 28 August 2012
(11.9 mm) (5.2 mm) (10.5 mm)(16.0 mm)
6 Aug 2012
(4.2 mm) (2.2 mm)
0 60 120 180
Time (min)
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 60 120 180 240
Time (min)0 10 20 30 40 50 60
Time (min)0 10 20 30 40 50 60
Time (min)0 120 240 360 480 600 720 840 960
Time (min)
App
II-
C
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII
-1
19
Ke
igh
tlyJu
lyd
ata
.grf
0 10 20 30 40 50 60
Time (min)
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 60 120 180 240 300
Time (min)0 60 120 180 240
Time (min)0 10 20 30 40 50 60
Time (min)0 180 360 540
Time (min)
31 July 2012 1 August 2012 1 August 2012 2 August 2012
(3.0 mm) (20.0 mm) (12.4 mm)(12.8 mm)
16 July 2012
(6.6 mm)
App
II-
D
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII
-1
19
Ke
igh
tlyA
ug
ust
Da
ta.g
rf
0 30 60 90 120
Time (min)
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 10 20 30 40 50 60
Time (min)0 60 120 180
Time (min)0 120 240 360
Time (min)0 120 240 360 480 600 720
Time (min)
12 August 2012 14 August 2012 21 August 201227 August 2012 28 August 2012
(11.9 mm) (5.2 mm) (10.5 mm)(16.0 mm)
6 Aug 2012
(4.2 mm) (2.2 mm)
App
II-
E
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII
-1
42
Ke
igh
tlyJu
lyd
ata
.grf
0 10 20 30 40 50 60
Time (min)
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 60 120 180 240 300
Time (min)0 60 120 180 240
Time (min)0 10 20 30 40 50 60
Time (min)0 180 360 540
Time (min)0 60 120 180 240
Time (min)
31 July 2012 1 August 2012 1 August 2012 2 August 2012
(3.0 mm) (20.0 mm) (12.4 mm)(12.8 mm)
16 July 2012
(6.6 mm)
3 August 2012
App
II-
F
31
7.0
/Gra
ph
er/H
ydro
inve
stiga
tion
/So
akw
ella
na
lysis/Ap
pII
-1
42
Ke
igh
tlyA
ug
ust
Da
ta.g
rf
0 30 60 90 120
Time (min)
0.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
1.00
1.10
1.20
1.30
1.40
1.50
1.60
1.70
1.80
1.90
2.00
2.10
2.20
Pre
ssure
Head
notco
mpensa
ted
(m)
0 10 20 30 40 50 60
Time (min)0 60 120 180
Time (min)0 120 240 360
Time (min)0 120 240 360 480 600 720
Time (min)
12 August 2012 14 August 2012 21 August 201227 August 2012 28 August 2012
(11.9 mm) (5.2 mm) (10.5 mm)(16.0 mm)
6 Aug 2012
(4.2 mm) (2.2 mm)
Rockwater Pty Ltd317.0/12/1
APPENDIX III
MONTHLY RECHARGE TO SHENTON PARK COMPENSATING
BASINS FOR CALIBRATED MODEL
Appendix III - Monthly Recharge to Shenton Park Compensating Basins for Calibrated Model
Date
Relative
time Measured WL
Total Runoff for
Shenton Park
Catchment
Dewatering
Recharge
Total Recharge to
Compensating Basins
(90% to Lake Jualbup,
10% Aberdare Rd)
(days) (m AHD) (m3/month) (m3/month) (mm/yr)
31-Jan-08 31 3 0 0 4
28-Feb-08 59 3.24 29460 0 14441
31-Mar-08 91 3.72 18501 0 9058
30-Apr-08 121 3.95 76800 0 37628
31-May-08 152 3.95 26526 0 13095
30-Jun-08 182 4.37 99469 0 48737
31-Jul-08 213 5.21 118929 0 58380
31-Aug-08 244 4.30 21237 0 10389
30-Sep-08 274 4.42 36696 0 18031
31-Oct-08 305 4.08 8330 0 4157
30-Nov-08 335 3.98 27912 0 13754
31-Dec-08 366 3.71 4933 0 2455
31-Jan-09 397 3.53 0 0 1
28-Feb-09 425 3.45 6837 0 3357
31-Mar-09 456 3.36 3440 0 1698
30-Apr-09 486 3.00 1493 0 742
31-May-09 517 3.68 28778 0 14088
30-Jun-09 547 4.47 57726 0 28422
31-Jul-09 578 4.70 109061 0 53367
31-Aug-09 609 4.63 63980 0 31416
30-Sep-09 639 4.65 34898 0 17245
31-Oct-09 670 4.37 1493 0 764
30-Nov-09 700 3.87 8330 0 4127
31-Dec-09 731 3.40 0 0 0
31-Jan-10 762 3.10 0 0 0
28-Feb-10 790 3.00 0 0 0
31-Mar-10 821 3.93 64968 0 31681
30-Apr-10 851 3.78 23434 0 11516
31-May-10 882 4.03 43178 0 21212
30-Jun-10 912 3.94 15210 0 7568
31-Jul-10 943 4.54 87510 0 42934
31-Aug-10 974 4.71 39056 7423 22766
30-Sep-10 1004 4.62 17157 36416 26120
31-Oct-10 1035 4.98 10320 35938 22487
30-Nov-10 1065 4.27 3440 23949 13312
31-Dec-10 1096 3.98 4933 23231 13720
31-Jan-11 1127 3.83 6880 28530 17222
28-Feb-11 1155 3.47 0 12145 5889
31-Mar-11 1186 3.3 0 9706 4706
30-Apr-11 1216 3.25 3440 7685 5466
31-May-11 1247 3.2 50761 2958 26340
30-Jun-11 1277 4.8 129632 6033 66392
31-Jul-11 1308 5.4 97463 11948 53641
31-Aug-11 1339 5.02 72068 11948 41092
30-Sep-11 1369 5.09 50002 11563 30160
31-Oct-11 1400 5.07 34393 11948 22676
30-Nov-11 1430 4.6 13305 8672 10753
31-Dec-11 1461 4.5 62184 5974 33278
31-Jan-12 1492 3.8 0 0 0
29-Feb-12 1521 3.5 14399 0 7070
31-Mar-12 1552 3.3 0 0 0
30-Apr-12 1582 5.04 76738 0 37516
31-May-12 1613 3.9 18607 0 9175
I:\317-0\Reports\Appendices\Appendix III - Modelled Runoff Recharge
Rockwater Pty Ltd317.0/12/1
APPENDIX IV
WATER QUALITY ASSESSMENT FIGURES FOR LAKE JUALBUP
App
IV-
A
31
7-0
/Gra
ph
er/L
ake
WQ
/Ap
pIV
aa
llda
ta.g
rf
0
100
200
300
400
500
600Tota
lDiss
olv
ed
Solid
s(m
g/L
)
4
5
6
7
8
9
10
pH
Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12
0
10
20
30
40
50
60
Da
ilyR
ain
fall(m
m)
0
2
4
6
La
keW
ate
rleve
l(m
AH
D)
0
10
20
30
40
50
60
Te
mpera
ture
(°C)
App
IV-
B
31
7-0
/Gra
ph
er/L
ake
WQ
/Ap
pIV
ba
llda
ta.g
rf
0.0
1.0
2.0
3.0
4.0
Tota
lNitro
gen
(mg/L
)
0.0
1.0
2.0
3.0
4.0
Tota
lPho
sphoru
s(m
g/L
)
Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12
0
10
20
30
40
50
60
Daily
Rain
fall
(mm
)
0
2
4
6
Lake
Wate
rlevel(m
AH
D)
0
2
4
6
8
10
12
14
Diss
olv
ed
Oxyg
en
(mg/L
)
App
IV-
C
31
7-0
/Gra
ph
er/L
ake
WQ
/Ap
pIV
ca
lldata
.grf
0
100
200
300
400
500
600Tota
lDiss
olv
ed
Solid
s(m
g/L
)
4
5
6
7
8
9
10
pH
Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12
0
10
20
30
40
50
60
Da
ilyR
ain
fall(m
m)
0
2
4
6
La
keW
ate
rleve
l(m
AH
D)
0
10
20
30
40
50
60
Te
mpera
ture
(°C)
App
IV-
D
31
7-0
/Gra
ph
er/L
ake
WQ
/Ap
pIV
da
llda
ta.g
rf
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
Tota
lNitro
gen
(mg/L
)
0.0
0.1
0.3
0.4
0.5
0.7
0.8
0.9
1.1
1.2
Tota
lPho
sphoru
s(m
g/L
)
Jan-03 Jan-04 Jan-05 Jan-06 Jan-07 Jan-08 Jan-09 Jan-10 Jan-11 Jan-12
0
10
20
30
40
50
60
Daily
Rain
fall
(mm
)
0
2
4
6
Lake
Wate
rlevel(m
AH
D)
0
2
4
6
8
10
12
Dis
solve
dO
xygen
(mg/L
)