PLANNING

AND

APPLICATION OF EQUIPMENTSIN

HYDROPOWER PROJECTS 

MINI PROJECT THESIS

Submitted By,

RAJESH CHAUHAN (231026)

  NIKHIL DWIVEDI (231051)

SHILPAN PATEL (231134)

 NATIONAL INSTITUTE OF CONSTRUCTION

MANAGEMENT AND RESEARCH PUNE

Page 2: Hydro Power Projects

8/9/2019 Hydro Power Projects

http://slidepdf.com/reader/full/hydro-power-projects 2/6

INTRODUCTION

A key initiative of the Government of India is the development of hydropower to help meet the

country¶s energy needs and provide all its citizens with access to electricity by 2012. Today, world

generates about 848 GW of power of annual production. It contributes about 50% of total power 

  production in 50 countries as per WORLD ATLAS AND INDUSTRIAL GUIDE 2008.

Hydropower being an indigenously-available, clean and renewable source of energy, the

Government of India is keen to use the largely untapped potential in this area ± currently only 23 percent

of India¶s hydro potential is being utilized -- to provide the additional generating capacity it needs.

Moreover, additional hydropower capacity is desirable in India¶s generation mix, as it provides

the system operator with technically vital flexibility to meet the changes in demand which typically affect

a power network like that of India. The high density of household demand in India means that the system

can experience a peaking load of anything between 20,000 to 30,000 Megawatts. This sudden spurt in

demand can be best met by hydropower plants which have the ability to start up and shut down quickly.

Other sources of power cannot do this as economically.

Hydropower is the energy that comes from the force of moving water. The movement of water 

 between the earth and the atmosphere is the part of the continuous cycle. The sun draws moisture up from

the oceans and rives, and the moisture condenses into clouds. The moisture is released from the clouds as

a rain or snow. The oceans and the rivers are replenished with moisture and the cycle starts again. Gravity

causes the water on the earth to move from places to places from high ground to low ground. The force of 

moving water gets powerful on this occasion and it releases its potential energy with increased quantum

of force.

Hydropower electricity is the only low-carbon, controllable alternative to nuclear plants. It makes

complete sense to start building hydropower projects. This form of generating electricity is unique and it

 produces constant power twenty four hours a day. It is necessary to store water to ensure a reliable supply

of electricity can be generated from water energy whenever it is needed. Hydro-electricity is the most

widely used form of renewable energy. It is an important component of the energy grid for India. Solar 

energy is still meeting only a tiny fraction of the world's energy needs yet it is the energy source that has

enjoyed the greatest growth and continues to promise tremendous potential. Wave energy is still in its

infancy with most hydropower projects still in the experimental or demonstration phases with

numerous hydropower projects still trying to prove that the world's oceans can provide us with another 

sustainable source of power.

Page 3: Hydro Power Projects

8/9/2019 Hydro Power Projects

http://slidepdf.com/reader/full/hydro-power-projects 3/6

OBJECTIVES

y  To learn the application of modern equipments in hydropower projects.

y  To be getting familiar with modern equipments in construction industry.

y  It will help in introducing the modern techniques in hydropower projects.y  To know better utilization of resources and equipments with better planning techniques.

BACKGROUND 

Few years before India had not started use of equipments and planning tools growth in

construction of hydropower was insufficient. There are few reasons for that they are as follows:

y  Lack of automated control system

y  Less feasibility and planning

y  Poor technology in mining & tunneling

y  Poor application of methods and specifications of codes.

y   Non-availability of skilled labors

SCOPE OF PROJECT

Planning plays a key role in construction. It is the preconstruction activity by that saving in

time & cost and milestones of the project is formed as it provides a way to execute a project. Hydropower 

  projects are very complex in nature. The most used planning techniques in construction of hydropower 

are LOB. Hydropower projects are generally repetitive in nature. They need some limited equipments for 

massive work. Consequent use of equipment is must at different places of execution.

y  Proper planning will help in optimum utilization of the equipments.

y  Planning is the key tool that is drawing outline of the work.

y  Hydropower projects are the complex projects that cannot be implemented without investigation

otherwise it will be loss of money.

y  Proper planning leads to the maximum utilization of material.

y  It reduces the labor cost and variable cost.

y  It helps in monitoring and controlling the progress of the project.

y  It will be better in inventory management and control.

Page 4: Hydro Power Projects

8/9/2019 Hydro Power Projects

http://slidepdf.com/reader/full/hydro-power-projects 4/6

There is vast area of application of different types of modern equipment. There is use of 

equipment in the various activities such as:

y  Transportation of material

y  Concreting,

y  Mining

y  Excavation and hauling

y  Loading and unloading

y  Clearing of site

y  Crushing

y  Rolling and compacting

y  Paving and curbing

y  Sprinkling

y  Batching and mixing of concrete

y  Drilling

y  Gravel spreader 

y  Sweeper 

y  Grader 

y  Geo-composites 

y  Automated control and safety system(SCADA) 

y Power house

 

y  Canal paver 

Page 5: Hydro Power Projects

8/9/2019 Hydro Power Projects

http://slidepdf.com/reader/full/hydro-power-projects 5/6

METHODOLOGY

The thesis discovers the topics as introduction, history, planning & scheduling technique, its

application & way of implementation, all equipments with their application at site and their scope of use

in India, case study, etc.

The thesis will be prepared by using the print media, electronic media and personal observation.

There is lot of books, journals, magazines to be referred. We can access to the e-books, journals, reports,

surveys, corresponds to company employees through the electronic media. Other way of personal

observation is access to site where road construction is going on. We can also consulting our faculty

members.

CONCLUSION:

y  Hydropower sector is most aggressively growing but extremely unevenly.

y  Use of planning tools like MSP, Primavera will help in smooth implementation and timely

achieving project completion

y   Need for advanced automated control and safety systems for handling and water distribution

y  Modern construction industry is keen to adopt all new equipments in India

y   Need the support of Govt. for importing the new technologies and machines duty free.

y  More research should be carried out in planning and machine development.

y  While award of contract contractor should have sufficient equipments of specified qualification.