17
SKAA 2513 HYDRAULICS STUDY ON FLOOD PROBLEM AT SG. PUSU STUDENT/ MATRIC NO. MOHD YUSRI BIN MOHAMED YUNUS SX130576KAWS04 MUHAMMAD ASYRAF BIN MASRI SX130588KAWS04 NUR NAZIRAH BINTI MOHD HADZIR SX130614KAWS04 PUTRI NORSAFIAH BINTI AHMAD HAIRUDIN SX130619KAWS04 RAHSIDI SABRI BIN MUDA SX130622KAWS04 SESI - SEM 2013/2014 2 SECTION 02 LECTURER DR. MOHAMAD HIDAYAT BIN JAMAL

Hydraulic Assignment

  • Upload
    pinh881

  • View
    30

  • Download
    10

Embed Size (px)

DESCRIPTION

Case study for hydraulic assignment

Citation preview

  • SKAA 2513

    HYDRAULICS

    STUDY ON FLOOD PROBLEM AT SG. PUSU

    STUDENT/

    MATRIC NO.

    MOHD YUSRI BIN MOHAMED YUNUS

    SX130576KAWS04

    MUHAMMAD ASYRAF BIN MASRI

    SX130588KAWS04

    NUR NAZIRAH BINTI MOHD HADZIR

    SX130614KAWS04

    PUTRI NORSAFIAH BINTI AHMAD HAIRUDIN

    SX130619KAWS04

    RAHSIDI SABRI BIN MUDA

    SX130622KAWS04

    SESI - SEM 2013/2014 2

    SECTION 02

    LECTURER DR. MOHAMAD HIDAYAT BIN JAMAL

  • ii

    TABLE OF CONTENTS

    CHAPTER TITLE PAGE

    1 INTRODUCTION 1

    1.1 Background 1

    1.2 Flooding and Drainage Issue 1

    1.3 Problem Statement 2

    1.4 Objectives of Study 3

    1.5 Scopes of Study 3

    2 ANALYSIS AND RESULT 4

    2.1 Existing Site Condition 4

    2.2 Analysis 4

    2.3 Result 5

    3 RECOMMENDATION 6

    4 REFERENCES 7

    APPENDICES

    Appendix 1 - Work Program

    Appendix 2 - Site Plan

    Appendix 3 - Calculation Sheet

  • CHAPTER 1

    1 INTRODUCTION

    1.1 Background

    The International Islamic University Malaysia (Universiti Islam

    Antarabangsa Malaysia), also known as IIUM or UIAM, is one of the Public

    Institutions of Higher Education (PIHE) in Malaysia. The main IIUM Campus is

    nestled in a valley in the rustic district of Gombak, a suburb of the capital city of

    Kuala Lumpur. This Garden of Knowledge and Virtue covers 700 acres, with elegant

    Islamic-style buildings surrounded by green-forested limestone hills, attracts avid

    photographers from among both locals and tourists.

    1.2 Flooding and Drainage Issue

    Flood is a nature and recurring event for a river and a stream. Flooding is a

    result of heavy or continuous rainfall exceeding the absorptive capasity of soil and

    the flow capacity of drainage, river or stream. This causes a water s to overflow onto

    adjacent lands or river bank. In general, those land most subject to recurring floods,

    situated adjacent to river and streams or drainage system is known as floodplains

    area. Table 1.0 shown flood type and their causes.

  • 2

    Table 1.1: Flood type and their causes

    Flood Type Causes of Flooding

    Extensive Basin Flood Riverbank Overflow

    Inundation Basin Flood Backwater effect from tidal influence affecting lower

    reaches

    Inland Flood Poor drainage from inland flood prone area

    Urban Flash Flood Inadequate drainage and storage system to catyer for rapid

    urbanization

    Flash floods are caused by the combination of various factors, among others

    including the failure of the system due to blocked and silted drainage, insufficient

    drainage systems, high rainfall intensities and improper garbage disposal.

    1.3 Problem Statement

    There are several flood occurrences in the Project area that have been

    recorded. However, severe flooding occurred in October 2010, April 2012 and the

    recent one in October 2013 (Rekod by Development Department IIUM). Most of the

    floods occurred during the inter monsoon period which brought high intensity

    rainfall to the relatively small catchment areas. In general, flood occurring at the low-

    lying areas could be aggravated by the insufficient capacity river, inadequate

    capacity of drains and coupled with sediment loading in the river and drainage

    system.

    Floods occurred in many parts of the Project area and the frequent flooded

    locations are listed below:

    1. Low laying area within the vicinity of Kulliyah Architecture

    2. Main Road from gate 1.

    During the flood event in October 2013, the depth of flood water reached

    almost 0.6m at those area. The recorded flood depth are between 0.3m 0.65 m

    during heavy rainfall.

  • 3

    1.4 Objectives of Study

    The main objectives of this study are as follows:

    1. To conduct hydraulic analysis to existing Sg. Pusu channel.

    2. Providing a solution to the flooding problem.

    1.5 Scopes of Study

    The study was focused on Sg. Pusu near the gate 1 of IIUM, which was the

    location of the recent flood around the area. The scopes of study are:

    1. Survey the site to collect existing hydraulic geometric proporties of

    the channel.

    2. To analyse the colected data to determine the cause of the problem.

    3. To design the most optimum channel to solve the flooding problem.

    The location of the study site is shown below.

    Figure 1.1: Location of study site

  • CHAPTER 2

    2 ANALYSIS AND RESULT

    2.1 Existing Site Condition

    The channel is combination of 2 types of channel as listed below:

    1. Channel 1: Trapezoidal earth grass channel located upstream.

    2. Channel 2: Rectangular concrete channel located downstream.

    The site plan is attached in Appendix. The geometrical properties of the

    channel are tabulated below

    Table 2.1: Geometrical properties of existing channel.

    Channel ID Geometrical Properties

    L (m) y (m) B (m) z S (%)

    Channel 1 280 2.75 2.5 4 0.2

    Channel 2 200 3.2 6 0 0.32

    2.2 Analysis

    Analysis was made in accordance to MSMA 2nd Edition by JPS. The flow

    rate was calculated using rational method and hydraulic anaylisis was made using

    Manning equation. Calculation sheet is attached in Appendices.

  • 5

    2.3 Result

    Exsiting geometrical properties for both channel is sufficient to receive the

    calculated flow rate. However the transition between these two channels was proved

    to be the cause of the flood problem.

    The rectangular channel acted as a expansion for trapezoidal channel. Even

    though the bottom width of rectangular channel is wider than trapezoidal channel, the

    width is smaller compared to the critical width required by trapezoidal channel

    resulting the backwater. Height of backwater is greater than the depth of trapezoidal

    channel which caused the flood.

  • CHAPTER 3

    3 RECOMMENDATION

    The solution proposed to solved the problem is to embank the top bank of

    trapezoidal channel to increase the depth up to the height of backwater. 300mm

    freeboard has also been proposed as required by MSMA.

    This is the most suitable solution and selected based on following

    justifications:

    1. The least cost and time for contruction

    2. No interuption to existing channel

    3. No channel protection or diversion required

  • 4 REFERENCES

    Amat Sairin Demun (2010). Lecture Module for SKAA 2513 Hydraulics.

    Unpublished, UTM.

    Department of Irrigation and Drainage Malaysia, JPS (2012). Urban Stormwater

    Management Manual for Malaysia (MSMA 2nd Edition). Retrieved from

    http://www.water.gov.my on January 22, 2013.

  • APPENDIX 1

    Work Program

  • STUDY ON FLOOD PROBLEM AT SG. PUSU

    Work Program

    No. Works Description Action by

    March April May

    Week

    5

    Week

    6

    Week

    7

    Week

    8

    Week

    9

    Week

    10

    Week

    11

    Week

    12

    Week

    13

    1 Site Survey Yusri/Rashidi

    2 Survey Data Processing Yusri/Rashidi

    3 Plan Drawing Nazirah

    4 Calculation Asyraf

    5 Report Preparation Putri

    6 Submission

  • APPENDIX 2

    Site Plan

  • SPACEE S T D 1 9 9 3UTM TM

  • APPENDIX 3

    Calculation Sheet

  • Project:

    Group Assignment

    Calculate by:

    Asyraf

    Section:

    Sg. Pusu

    Date:

    9/5/2014

    Sheet. No:

    1/3

    Reference Calculation Output

    Equation 2.2

    Determine the flow rate:

    KTi

    d

    Where:

    i = average rainfall intensity (mm/hr)

    T = average recurrence interval, ARI (years)

    d = storm duration (hours)

    , , ,K = constants based on location

    Table 1.1

    Appendix 2.B

    Table 2.B1

    Select Major system for Institutional building/complex

    Assumed 2 hours storm duration

    Select Station ID 3217001, Km 16 Gombak

    66.328, 0.144, 0.230, 0.859K

    ARI = 100years

    d = 2

    0.144

    0.859

    66.328 10064.64

    2 0.23

    KTi

    d

    i = 64.64mm/hr

    Equation 2.3 360

    CiAQ

    Where:

    Q = flow rate (m3/s)

    C = runoff coefficient

    i = average rainfall intensity

    A = catchment area (ha.)

    Table 2.5 Select highest coefficient for major system

    Measured catchment area

    C = 0.95

    A = 450ha.

    0.95 64.64 450

    77360 360

    CiAQ

    377Q m s

  • Project:

    Group Assignment

    Calculate by:

    Asyraf

    Section:

    Sg. Pusu

    Date:

    9/5/2014

    Sheet. No:

    2/3

    Reference Calculation Output

    Table 2.3

    Check Existing Channel

    Channel 1 (trapezoidal grass channel):

    2.75

    2.5

    4

    0.035

    280

    69.7 68.80.0032

    280

    d m

    B m

    z

    n

    L m

    S

    552 2 3

    3 3

    2 23 32

    52 3

    232

    2 1

    2.5 4 77 0.0352.74

    0.00322.5 2 1 4

    By zyAR S A Qn QnQ

    n S SP B y z

    y yy m

    y

    subcriticalo cy y

    2.74oy m

    subcritical

    oy d OK

    Table 2.3

    Channel 2 (rectangular concrete channel):

    3.2

    6

    0.015

    200

    68.8 68.40.002

    200

    d m

    B m

    n

    L m

    S

    5533

    2 23 3

    53

    23

    2

    6 77 0.0153.21

    0.0026 2

    ByA Qn Qn

    S SB yP

    yy m

    y

    subcriticalo cy y

    3.21oy m

    subcritical

    oy d OK

    Check transition from channel 1 to channel 2:

    22 2.5 2.74 2 2.742.74 3.49

    2 2 2 2 2.74 4 4 2.74o o o

    A By zyE y y m

    T B zy

    min 0 3.49o o oE E h E E m

    min2 3 3.49 2 3 2.33cy E m

    3 3 39.81 2.33 11.12c cq gy m ms

    77 11.12 6.93c cB Q q m

    2 6 cB m B

    3.49oE m

    6cB m

    2 controlB

  • Project:

    Group Assignment

    Calculate by:

    Asyraf

    Section:

    Sg. Pusu

    Date:

    9/5/2014

    Sheet. No:

    3/3

    Reference Calculation Output

    3

    2 277 6 12.83q Q B m ms

    2 23 3 12.83 9.81 2.56cy q g m 2 2.56cy m

    min 1.5 1.5 2.56 3.84cE y m min 2 3.84E m

    2 2 2.56cy y m 2 2.56y m

    1,3 min min min0 3.84E E h E E m 1,3 3.84E m

    2 2

    3 3 32 2

    3 3

    12.833.84 2.56

    2 19.62

    qy y m y m

    gy y 3 2.56y m

    2 2

    1 1 1 11 1 1 1

    1 1

    2.5 43.84 3.02

    2 2 2 2 2.5 8

    A By zy y yy y y m y m

    T B zy y

    1 13.02y m d

    overflow

    Determine length of backwater:

    Calculated at 5 depth intervals

    2

    3

    2

    1

    1

    Q T

    y gAx

    S K

    K

    3.02 2.7417.5

    5 0.0032

    y

    S

    Let 2

    31

    Q T

    gA and

    2

    1K

    K

    17.5x

    y y T A R K x m

    3.020

    2.964 2.992 26.436 43.288 1.593 1687.047 0.803 0.352 39.935

    2.908 2.936 25.988 41.820 1.566 1611.090 0.785 0.289 47.493

    2.852 2.880 25.540 40.378 1.538 1537.293 0.766 0.219 61.037

    2.796 2.824 25.092 38.960 1.511 1465.631 0.744 0.141 92.098

    2.740 2.768 24.644 37.567 1.483 1396.078 0.719 0.054 234.799

    Total Length 475.36

    475.36 280

    Backwater length channel length overflow the whole channel

    16.3.3

    Proposed Channel

    Proposed to increase top bank along channel 1.

    Depth to be provided = 3.1m

    Freeboard = 0.3m

    Proposed new depth = 3.4m

    Additional bank height = 3.4 2.75 = 0.65m

    Proposed

    geometric:

    2.5

    3.4

    4

    B m

    y m

    z