HIDALGO COUNTY REGIONAL MOBILITY AUTHORITYPROJECT PROGRESS
1 http://www.hcrma.net
http://www.hcrma.net2
OVERVIEW
Mission StatementBoard LeadershipOur VisionProgressPartnership with
TxDOTQuestions
http://www.hcrma.net3
To provide our customers with a rapid and reliable alternative for the safe and efficient movement of people, goods and services.
MISSION STATEMENT
“”
http://www.hcrma.net4
BOARD LEADERSHIP Dennis Burleson, Chairman
Michael G. Cano, Vice Chairman
Ricardo Perez, Secretary/Treasurer
Joe Olivarez, Director
David Guerra, Director
Forrest Runnels, Director
Alonzo Cantu, Director
http://www.hcrma.net5
Enhance the quality of life and economic vitality of the region.
OUR VISION
“ ”
5 http://www.hcrma.net
http://www.hcrma.net6
OUR VISIONDEVELOP THE
INFRASTRUCTURE TO SERVE A POPULATIONOF APPROXIMATELY 800,000 RESIDENTS
http://www.hcrma.net7
Key Milestones for SH 365 Ph I Date
Advanced Funding Agreement Execution with TxDOT 11/2012
Update Strategic Plan (Using Updated T&R Updated Studies) 12/15/12
Environmental Classification Decision Issued by FHWA 11/12/12
Environmental Finalize EA with FONSI Issued by FHWA 4/24/14
Utilities (Compensable) including Design 9/1/15
Prop. Acquisition Svcs (including Title Reports + Appraisals) 1/2/15
Design Engineering / Geotechnical / Toll Facilities 2/3/14
Construction Letting (Bid Phase) 9/1/15
Construction Begins 12/1/15
Construction Ends (including closeout) / Toll Facilities Open 7/01/18
PROGRESS
Key Milestones for IBTC Date
Update Strategic Plan (Using Updated T&R Updated Studies) 12/15/12
Environmental Classification Decision Issued by FHWA 10/1/14
Environmental Finalize EA with FONSI Issued by FHWA 6/24/16
Utilities (Compensable) including Design 4/3/17
Prop. Acquisition Svcs (including Title Reports + Appraisals) 2/2/15
Design Engineering / Geotechnical / Toll Facilities 6/2/14
Construction Letting (Bid Phase) 12/15/16
Construction Begins 4/3/17
Construction Ends (including closeout) / Toll Facilities Open 10/1/19
Key Milestones for Section D Date
Update Strategic Plan (Using Updated T&R Updated Studies) 12/15/12
Environmental Classification Decision Issued by FHWA 1/2/17
Environmental Finalize EA with FONSI Issued by FHWA 12/3/18
Utilities (Compensable) including Design 10/1/21
Prop. Acquisition Svcs (including Title Reports + Appraisals) 10/1/19
Design Engineering / Geotechnical / Toll Facilities 3/2/20
Construction Letting (Bid Phase) 10/1/21
Construction Begins 4/1/22
Construction Ends (including closeout) / Toll Facilities Open 10/1/24
1
2
3
http://www.hcrma.net8
PARTNERSHIP WITH TxDOT Cat. 10 Demonstration and High Priority funds –
$1,493,439 to reimburse eligible preliminary engineering and environmental expenses.
Cat. 10 Coordinated Border Infrastructure funds – $5,600,000 to reimburse eligible construction expenses.
Cat. 12 Commission Discretionary funds – $112,055,735 to reimburse remaining eligible construction expenses up to $11,205,573.50 per year between 2018 and 2028.
http://www.hcrma.net9
QUESTIONS?
Please visit www.hcrma.net for more information