Upload
dangkhanh
View
222
Download
6
Embed Size (px)
Citation preview
How To: Cx Fire Life Safety Systems
David J. LeBlanc, PE, FSFPE
AIA Quality Assurance
The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-AIA members are available upon request.
This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.
Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.
2
Learning Objectives
1. Understand the unique challenges with Cx Fire Protection and Life
Safety Systems on Gigantic International Projects.
2. NFPA 3 Cx process for Fire Protection and Life Safety Systems.
3. Understand the role of the Fire Commissioning Agent (FCxA) and
how they integrate with the full building commissioning team and
Commissioning Authority (CxA).
4. Understand the difference between Commissioning (NFPA3) and
Integrated Testing (NFPA 4) for Fire Protection and Life Safety
Systems.
3
• Commissioning - NFPA 3
• Terminology
• Why different?
• Importance of Cx F&LS
• Maintenance
• Large International Project
• Case Studies Lessons learned
• Updates
• Wrap-Up/Questions
Overview
4
Commissioning – “A systematic process that provides
documented confirmation that building systems function
according to the intended design criteria set forth in the
project documents and satisfy the owner’s operational
needs, including compliance with applicable laws,
regulations, codes, and standards.”
NFPA 3 – Commissioning of Fire Protection
Systems
5
• Fire Protection Industry-term Commissioning utilized incorrectly.
• Acceptance Testing with Engineer or local Building/Fire Department is often incorrectly termed “Commissioning”.
• Commissioning is a systematic process not just a test.
• NFPA3 should help with Terminology.
ACCEPTANCE TESTING ≠ COMMISSIONING
• Integrated Testing Agent (ITA) – NFPA 4 new term
Terminology
6
• Owner
• Architect / Engineer
• Commissioning Agent (CxA) – if overall
building commissioning
• Fire Commissioning Agent (FCxA) –
reports to CxA
• Integrated Testing Agent (ITa)
• Contractor
• Subcontractors
• Registered Design Professionals
(RDP)
• Authorities Having Jurisdiction (AHJ)
Key Stakeholders
7
• Owner’s Project Requirements (OPR)
• Basis of Design (BOD)
• Commissioning Plan
• Integrated Testing Plan
• Commissioning Record Document
Key Documents
8
• Qualified FCxA and ITa required
• Advanced knowledge & experience in installation and operation of systems
• Advanced knowledge & experience in installation, operation, and interfaces between the various systems
NFPA 3 & 4 Qualifications
9
NFPA 3 New and Existing Buildings
• Commissioning (Cx) is done on new buildings or
new systems.
• Re-commissioning (Re-Cx) is commissioning of
existing systems that were previously
commissioned.
• Retro-commissioning (RCx) is commissioning of
existing systems that were not previously
commissioned
10
• Occupants don’t know they’re there
• They need to spring into action during emergency
• Need them to work properly to occupy building
• Each system type has separate NFPA standard to meet
• Integrate these systems to work together for common goal
What is Different about Cx Fire Life Safety Systems
11
Fire and Life Safety
Standards
Products –Materials &
Systems
Compartments & Separations
Active Systems
Egress Systems
Structural Fire Protection
Emergency Operations
Prevention and
Maintenance
Fire Protection is a Holistic Approach
12
• Fire Life Safety Systems do
not provide comfort, improve
occupant productivity, nor
enhance occupants overall
experience with the building
environment.
• Performance is only
measured through proper
commissioning or during a
fire / life safety emergency.
• Do really want to wait until an
actual real world event to see
how the performance of the
Fire Life Safety System is?
Main Difference about Cx Fire Life Safety Systems
13
• Documentation critical
• Access for future ITM
• Configuration and equipment location for availability
• What needs to be tested and how often
• Maintenance Code required – not optional
Cx Helps Future Maintenance of Fire Life Safety Systems
14
• Many fire protection systems sit dormant until
emergency conditions
• Life safety systems are essential in protecting
occupants, contents of, and the building itself
and notifying occupants during emergency
conditions
• Owners are legally obligated to have properly
functioning fire protection systems and to
maintain and test these systems.
• The complex integration of fire protection
systems is at an all time high
• Non-commissioned or improperly
commissioned fire protection systems are a
liability for owners and commissioning firms.
Importance of Commissioning Fire Protection and
Life Safety Systems
15
Performance Tests
16
What Is Reliability & Survivability?
• Continuous and
uninterrupted performance
during a fire emergency
• Reliable components and
power supply
• Electrical safety and
equipment protection is a
secondary concern
The pump is sacrificial
17
• Requirements focus on the continuous uninterrupted operation of the fire pump.
• Electrical safety is considered a secondaryobjective.
• Fire pump equipment is considered sacrificial.
• As such, Equipment and Conductors may constitute a fire hazard.
• Protection of the premise and occupants of paramount importance.
Survivable
18
Large F& LS Commissioning Projects
19
• ESL
• US Based vs local practices
• Quality of subcontractors
• Shear size of the overall project
• Volume of Documentation
• Organization of Info
• Lacking local experienced personnel
• Manpower consistency
• Inspector writes up nonconformance not person clearing item
• Break down of collected info to designate to various companies for different purposes
Challenges with Cx Gigantic International Projects
20
• Involvement during the Design and Construction
• Local experienced personnel PM, Team leaders, and QC with
domestic travelers providing bulk of manpower.
• Rotating team of inspectors
• Standardized templates for inspectors
• Project Assistants manage info, documents, and distribution
• Items broken out by System Type, Floor, and Area
• NCR Master list capable of sorting and distribution to expedite
owner and GC distribution to clear items
• Documentation of items not being completed after contractor told
work items completed (Owner back charges)
Approaches and Solutions
21
Process Flow Chart
22
And Questionable Practices
23
And Questionable Practices
24
Final, Finished, Complete?
25
• Require synchronization to
avoid photosensitive epilepsy
• High flash rate (strobing effect)
can induce seizures in some
people
Fire Alarm Visual Notification
26
• Building occupied for years and was undergoing renovation.
• Lack of documentation and no evidence it was commissioned resulted in a thorough test of the system to verify installation, operation, and performance.
• One test scenario was to simulate a transfer to emergency power for entire building during heavy load, including smoke control systems, fire pumps, and fire alarm systems all running under normal power to verify it continued to perform and that the transfer to emergency generator worked.
Case StudyExisting High Rise Building with an Atrium Smoke Control System and Stair
Pressurization System.
27
21st NCBC Conference
Result
28
• Under normal power systems
activated properly, but on
emergency power transfer all of
the dampers closed, even
though some were suppose to
be open.
• Smoke control fans were on
emergency power, but all the
dampers were on normal power
and failed safe close upon loss
of power.
5. Existing fire protection and life safety
systems are many times not properly
configured, coordinated, integrated, or
commissioned.
21st NCBC Conference
Lessons Learned
1. Emergency/Standby power critical for fire protection and life safety
systems.
2. Showcased importance of proper Commissioning and Retro-
Commissioning
3. Highlighted importance of integrated test plans
4. Systems need to properly function in various conditions, not only
ideal normal conditions.
29
• Relatively new Low-rise large
building with Atrium smoke control
system.
• Actual fire outside of Atrium
activated non-atrium sprinkler water
flow in a remote area of building
• Atrium smoke control system
activated in real life (not suppose to
per basis of design and
project/owner objective).
Case Study
21st NCBC Conference30
• Smoke from remote area of building was
dragged through the building causing
extensive damage and clean-up.
• Improperly configured smoke control
sequence did much more harm
21st NCBC Conference
Result
31
1. Improperly configured systems not only not helpful, can
cause more problems.
2. Need comprehensive test scenarios and when systems
should activate, but also when they should not activate.
3. Proper Commissioning of fire protection and life safety
systems critical for proper orientation.
4. Non-Commissioned systems have significantly
increased rate of not properly functioning and possibly
doing more harm putting occupants, property, and the
building at risk from fire and life safety.
21st NCBC Conference
Lessons Learned
32
• Emergency generator was tested prior to all the systems
were completed and connected to the emergency generator
and signed off.
• Generator was properly sized to accommodate load
• As part of life safety systems test a full load on
emergency generator was done with the smoke control
system, fire pump, fire alarm system, emergency lighting,
and other systems running.
Case Study
New High-Rise Hotel with Pressurized Stairs, Fire Pump, Fire Alarm
System, Emergency Lighting, and other Systems on the Emergency
Generator
33
21st NCBC Conference
• During life safety test transfer to emergency
generator the generator tripped out.
• All systems in the building went down with no
power and dark – no lighting (night test)
• Generator had capacity but not properly
balanced and configured as other systems were
added to the emergency generator load.
21st NCBC Conference
Result
34
1. Need to commission systems when they
are first brought online, but also after
other systems are finished.
2. Importance of Commissioning to identify
and resolve problems.
Lessons Learned
35
21st NCBC Conference
• Fire Protection Life Safety
Commissioning Team brought in late to
the project after much of the system
were installed.
• Systems and smoke control shafts
were constructed, sealed, and painted.
• Required duct leakage test was
never conducted prior to sealing shafts.
Importance of Commissioning Team Brought
In EarlyNew Construction Mixed-Use High Rise Project with A Smoke Control
System
36
21st NCBC Conference
• Smoke control system could not meet performance of .10 inch water gauge pressure differential.
• Leaky duct was the culprit, which would have been identified if the duct test was conducted.
• Had to take down the drywall shaft for entire building to fix the duct work, conduct duct test, and replace shaft and paint.
• Additional cost and schedule impact.
Results
37
21st NCBC Conference
1. Best to bring in Commissioning Team during
the design phase.
2. Need to conduct commissioning testing and
component verification at the proper
installation point during construction.
3. Skipping Commissioning or improperly
delaying steps most likely will cost you
significantly more financially and impact
schedule.
Lessons Learned
38
21st NCBC Conference
NFPA 3 & 4 Updates
• Standard vs Recommended
Practice
• 2015 Edition of NFPA 3
Commissioning – Recommended
Practice
• New NFPA 4 (2015 Edition) is a
Standard and only deals with
Integrated Testing
• Integrated Testing Agent (ITa)
• Future - next edition NFPA 3
Standard
39
• ICC publishes the set of International Codes – IBC & IMC
• ICC Draft ANSI Commissioning Standard – ICC 1000
• Current form ICC 1000 is vague, but covers all systems
• Public Comment April 2015
• Currently Categorizing Public Comment
• Board suspending committee activity until committee status report is received and reviewed.
ICC Update
40
David LeBlanc, PE, FSFPE
Vice President
JENSEN HUGHES
www.jensenhughes.com
508-620-8900Thank You!