Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
logo
area
HL-LHC
Internal metrology and fiducialisationInternal Review 17 June 2019
Patrick Bestmann
logo
area
Internal Metrology
Patrick Bestmann 2
Internal metrology
Tooling Fabrication Tools & Molds
Parts Lamination, Colars, Coils, Keys
Magnets Main & Correctors
Coldmass
Cryo-
magnet
Assembly
MS
C &
Industr
y
Surv
ey
Fiducialisation
Assembly-
metrology
Assembly-
Metrology
Parts & Tools
metrology
logo
area
Internal Metrology & Fiducialisation
Internal metrology
All measurements needed for the assembly of magnets, coldmasses and Cryo-
assemblies....
Fiducialisation Transfer of the geometric / magnetic axis to the external fiducials on the vacuum vessel
Usually done with self centering beam tube probes and streched wire
Often combined with geometrical conformity control of extremities
Patrick Bestmann 3
R
T
S
logo
area
Triplet Magnets
Patrick Bestmann 4
Q1 & Q3 Build in US
Delivered cryostated & fiducialised to CERN
Full fiducialisation after transport at CERN
Q2 Coldmass build at CERN
Assembly metrology by MSC with help from SU
Full fiducialisation at CERN
Extended control needs
FSI integration =>talk Monitoring interne
logo
area
Triplet Magnets
Patrick Bestmann 5
Discussions with FNL colleagues ongoing
First measurements in US will be made with CERN assistance
CERN will provide: The methdodology (defined and agreed on)
The procedures (under approval)
The beam tube probe (drawings under approval)
Metric reflector supports (to be purchased) https://edms.cern.ch/document/2168890/1
https://edms.cern.ch/document/2168888/1
https://edms.cern.ch/document/2168886/1
136.7mm beam tube probehttps://edms.cern.ch/document/2141786/1
logo
area
Triplet Magnets
Patrick Bestmann 6
Fabrication control of all Vacuum Vessels @CERN First unit ready for measurements, procedures defined
Installation of auxillary fiducials & temporarily coordinate system for assembly
Metrology Procedures
First procedures for Vacuum vessel metrology
Coldmass metrology
Fiducialisation under approval
Assembly metrology already onging for first MQXB Deformation analysis after loading
logo
area
11T Dipoles
Patrick Bestmann 7
11T Dipole Coldmass constructed & measured by MSC
Cryostating with systematic controls of assembly before and after insertion into vacuum
vessel
Fiducialisation after cold test
215667526752
15660
logo
area
11T Dipoles
Patrick Bestmann 8
11T Dipole First series magnet arrived for cryostating
Assembly metrology before and after
Cryostating
Fiducialisation after cold test
logo
area
LEP Cryostats
Patrick Bestmann 9
LEP connection cryostat QEP coldmass build in SMI2, new structure
Continious assembly metrology & alignment by SU
Fiducialisation
QEN Bypass Alignment of cold-warm transitions (4 already done)
Fiducialisation
LEP(R/L)
A
LEP(R/L)
B
logo
area
LEP connection cryostats
Completly new construction strategy
Construction metrology & Coldbore alignment
2nd Coldtest in SM18 ongoing
Fiducialisation after cold test
Patrick Bestmann 10
logo
area
Cryo-bypass & Collimator
Patrick Bestmann 11
QEN Bypass Alignment of cold-warm transitions (4 already done)
Fiducialisation
TCLD Collimators Fiducialisation (Prototype + 1 Series done)
Alignment test in mock-up 926
Very critical assembly in terms of alignment
Alignment procedure already done
logo
area
D1 Magnets
Patrick Bestmann 12
First contact & discussions with KEK colleagues
Very well defined production procedure
Fully compatible with planned metrology measurements
Access to lamination until last moment for field direction
Laser Tracker
Targets on CM
Access to lamination
Endcover with References
R
S
T
logo
area
D2 Magnets
Patrick Bestmann 13
Build by MSC
Assembly measurements are made by MSC
Special build with two coldmasses
Probe production & consulting
Fiducialisation after cold test
94mm beam tube probehttps://edms.cern.ch/document/2141794/1
logo
area
Magnet Fiducialisation
Patrick Bestmann 14
We are quite well prepared now
All procedures in preparation or control state
Measurement hardware is ready
But waiting for more inputs concerning acceptance criteria and tolerances
logo
area
Magnet Fiducialisation
Patrick Bestmann 15
All magnets will be fiducialised after cold test at CERN By definition for magnets produced at CERN (LEP, 11T, D2 and Q2)
Produced by the collaboration as check for movements and integrity
Procedures are derived from existing LHC Cryomagnet procedure LHC-G-IP-0015 v.1.2
In order to be as universal as possible the naming conventions are extremly important
Introduction of a universal report template
Need to clarify magnetic measurement needs During constructions
During cold test
During final Fiducialisation
logo
area
Further Metrology
Patrick Bestmann 17
The assembly procedures are compiled at the moment
Assemblies like IR magnets and D2 have special needs during the further
assembly process Beam Screen alignment & control
Beam Position Monitor alignment & control
Cold WarmTransition alignment & control
logo
area
Open points
Patrick Bestmann 18
Naming conventions not fully defined Different from existing LHC conventions
Special assemblies and types which can, or not be rotated by 180°
Equipment and assembly names under creation For now only temp names, not good for documentation
First 11T assembly measured, still waiting for 11T Cryo-Assembly name
Tolerances Need to have approved tolerance tables for each assembly
Where to put our results? Not possible anymore in MMSMA
We could use a new approach and store this data in MTF
As usual all measurements are documented with reports in MTF, but without direct DB access
No problem for alignment, but as-build aperture model will be affected
logo
areaJean-Frederic FUCHS 19