HFC227ea Engineering Manual

  • Upload
    edik-ed

  • View
    227

  • Download
    0

Embed Size (px)

Citation preview

  • 7/27/2019 HFC227ea Engineering Manual

    1/38

    1

    Introduction___________________________________________________________

    With the Montreal Protocol conference from 1993, manufacturing of

    substances with Ozone Depleting Potential (ODP), including Halon 1301

    (CBrF3), Halon 1211 (CCIF2Br) and Halon 2201 (CHF2Br), which were used as fire

    extinguishing agents, was banned.

    HFC227ea as one of the Halon alternatives is a clean and safe fire suppression

    agent for use in total flooding automatic systems. Storage and distribution

    requirement are similar to Halon or other HFCs fire suppression systems andthe majority of system components are identical. Due to the difference in

    agent quantity and discharge characteristics, HFC227ea is not a direc t

    replacement (drop-in) for existing Halon 1301 installation. It is rated as Zero

    Ozone Depletion (ODP), is electrically non conductive, clean and leaves no

    residue.

    HFC227ea may consist of a single cylinder or several cylinders combination,

    manifold together and connected via a pipe network to a number of

    discharge nozzles. System discharge can be activated mechanically or

    electrically. Mechanical manual actuation is via a manual pull handle

    mounted on cylinder valve. Electrical ac tuation is via a solenoid actuator

    which mounted on the side of manual pull actuator and is energized

    automatically from detection and alarm control panel.

    Health and Safety

    Exposure to HFC227ea at the design concentration of 7% and up to 9.0% is

    not hazardous to health within a limited egress time. Exposure to higherconcentrations is permissible for a limited period. In accordance with NFPA

    2001, Halocarbon clean agent system for spaces that are normally occupied

    and designed to concentrations up to the NOAEL shall be permitted. Its Non

    Observed Adverse Effec t Level (NOAEL) for cardiac sensitization is 9%. With 9%

    concentration level, the maximum human exposure time shall not exceed 5

    minutes.

    The National Fire Protection Assoc iation (NFPA 2001 Standard on CleanAgent Fire Extinguishing Systems) recommends that unnecessary exposure to

    any agent be avoided and that personnel evacuate protected areas as

    quickly as possible to avoid the decomposition products of the clean agent.

    HFC227ea can decompose at high temperature or under fire to a form of

    halogen ac ids which is readily detec ted as a sharp, pungent odor even afterfire extinguished or long before hazardous maximum exposure levels are

    reached. Ventilation and openings are required to clear the protec ted areas

    after HFC227ea system discharged, no one is allowed to enter the areas

    during system discharge or before the area is totally ventilated and safe for

    occupancy again. Direct contact with the vaporizing liquid discharge from a

    HFC227ea nozzle has a cool chilling effect on objects and in extreme casescan cause frostbite to the skin. Ones should avoid direc t contac t with the

    agent.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    2/38

    2

    WARNING!

    The discharge of clean agent systems to extinguish a fire can result in a

    potential hazard to personnel from the natural form of the clean agent orfrom the products of combustion that result from exposure of the agent to the

    fire or hot surfaces. Unnecessary exposure of personnel either to the natural

    agent or to the products of decomposition shall be avoided.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    3/38

  • 7/27/2019 HFC227ea Engineering Manual

    4/38

    4

    HFC227ea contains no chlorine and bromine atoms, presenting no ozone

    depletion effect. According to medical findings, as an aerosol propellant,

    HFC227ea is used in pharmaceutical metered dose inhalers such as those

    used for dispensing asthma medication.

    NOTE:

    HFC227ea shall not be used on fires involving the following materials unless

    they have been tested to the satisfaction of the authority having jurisdiction.

    1. Certain chemicals or mixtures of chemicals, such as cellulose nitrate and

    gunpowder, those are capable of rapid oxidation in the absence of air.

    2. Reactive metals such as lithium, sodium, potassium, magnesium, titanium,zirconium, uranium, and plutonium.

    3. Metal hydrides.

    4. Chemicals capable of under going auto thermal dec omposition, such as

    certain organic peroxides and hydrazine.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    5/38

    5

    SYSTEM COMPONENTS

    This sec tion shows the individual components:

    1. HCV Valves 9. Pilot Cylinder c/w Solenoid2. HCV Manual Pull Ac tuator 10. Heat & Smoke Detec tor

    3. Discharge Hose 11. Extinguishing Panel

    4. Solenoid Ac tuator 12. Sounder

    5. Cylinder 13. Alarm Bell

    6. Discharge Flashing Light 14. Abort Switch

    7. Nozzles 15. Door Warning Sign

    8. Manual Pull Box 16. Door Fan Test Equipment

    HCV valves

    Part no. Part name. Outlet size

    SPS1C001HVC20 HVC 20

    (for 25L cyl)

    1 BSP

    SPS1C001HVC40 HVC 40

    (for 45 -

    130L cyl)

    2 BSP

    SPS1C001HVC60 HVC 60(for 160 -

    230L cyl)

    2 1/2 BSP

    HCV manual pull Actuator

    Part no. Part name.

    SPS1C-003-MPAV Manual pull ac tuator

    Discharge hoses

    Part no. Part name.

    1. SPS1C-005-38mm

    SPS1C-005-50mm

    SPS1C-005-65mm

    2. SPS1C-006-8mm

    Discharge Hose

    Loop Hose

    1

    2

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    6/38

    6

    Solenoid Actuator

    Part no. Part name.

    CO2070-BR-XXX-XX Solenoid Actuator

    Cylinders

    Part no. Part name.

    SPS1C-004-25L

    SPS1C-004-45L

    SPS1C-004-75LSPS1C-004-100L

    SPS1C-004-130L

    SPS1C-004-160L

    SPS1C-004-190L

    SPS1C-004-230L

    25L cylinder

    45L cylinder

    75L cylinder100L cylinder

    130L cylinder

    160L cylinder

    190L cylinder

    230L cylinder

    Discharge Flashing Light

    Part no. Part name.

    FAS251-24VDC-STD Discharge Flashing

    Light

    Nozzle

    Part no. Part name.

    SPS-1C007-15mm

    SPS-1C007-20mm

    SPS-1C007-25MM

    Nozzle

    Nozzle

    1 Nozzle

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    7/38

    7

    Manual Pull Box

    Part no. Part name.

    CO2072-MS-STD-RD Manual Pull Box

    Pilot Cylinder c/w Solenoid

    Part no. Part name.

    CO205A-CS-001-SP Pilot Cylinder c/w

    Solenoid

    Optical Smoke Detector

    Part no. Part name.

    FAS1B-55000-317 Optical Smoke Detec tor

    Heat Detector

    Part no. Part name.

    FAS1B-55000-100 Heat Detec tor

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    8/38

    8

    Extinguishing Panel

    Part no. Part name.

    FAS0021P-002-RD Extinguishing Panel

    Sounder

    Part no. Part name.

    FAS4A-Y04-24VDC Sounder

    Alarm Bell

    Part no. Part name.

    FAS194-LA-150-RD Alarm Bell

    Abort Switch

    Part no. Part name.

    FAS258-AB-28V Abort Switch

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    9/38

    9

    Door Warning Sign

    Part no. Part name.

    MISC-SPD-DIV Door Warning Sign

    Door Fan Test Equipment

    Part no. Part name.

    SPS xxxxxxxxxx Door Fan Test Equipment

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    10/38

    10

    SYSTEM DESIGN

    Two main elements are critical to HFC227ea system design. The first is the risk

    assessment to determine the type of protec tion required, such as what kind of

    hazards to protect from, whether an occupied area or a restricted area,ventilation or openings, what kind of building, types of equipments, locations

    etc. The second is calculating the quantity of HFC227ea required, determine

    cylinder quantity, nozzle quantity, nozzle orifice size, pipe sizes, piping layoutand nozzle location base upon criteria of room sizes, floor height, raised floor

    and/or ceiling voids.

    Hazard Analysis

    An analysis of the hazards is useful and highly rec ommended to carry out bythe contractor/designer/supplier if such location is far too complex and

    difficult to visualize and/ or understand under a plan drawing. This enablecontractor to measure and provide an accurate details for designer/supplier

    to calculate a precise pre-engineered HFC227ea system for eac h application

    in accordance with NFPA 2001 standard.

    HFC227ea systems are suitable for use in normal commercial and industrial

    environments. The design concentration for Class A & C is 7.17% but differs for

    Class B fires. However, the minimum design concentration for flammable

    liquids is 9.0% based on commercial grade heptanes. All design

    concentration calculations are based on extinguishing concentrations plus an

    additional 20% safety factor for Class A & C and a 30% safety factor for Class

    B and all manually actuated only systems.

    Class A Fires involving solid materials usually of an organic nature, in

    which combustion normally takes place with the formation of

    glowing embers.

    Class B Fires involving flammable liquids or liquefiable solids and

    flammable gases.

    Class C Fires involving energized electrical equipment where the

    elec trical non conductivity of the extinguishing media is of

    importance.

    Design concentrations are determined by NFPA 2001.

    HFC227ea cup-burner value is 6.7% for commercial heptane fuel. Nozzle

    distribution test concentration is 6.9%.

    Nozzle efficiency factor = nozzle distribution test concentration / cupburnervalue.

    = 6.9/6.7 = 1.03

    Safety factor: Class A = 1.2

    Class B = 1.3Class C = 1.2

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    11/38

    11

    Minimum design concentrationClass A fire (determine by fire test) 5.8% x 1.03 x 1.2 = 7.17%

    Class B fire (commercial grade heptane) 6.7% x 1.03 x 1.3 = 9.0%

    Class B fire (other C lass B fuels) cupburner value x 1.03 x 1.3 = no less than

    9.0%Class C fire same concentration as Class A fire

    Although HFC227ea is tested capable to extinguish fire under Class A, B & C, it

    is not effective on the following:

    Class A Deep seated fires.

    Class D combustible metals.

    Chemicals capable of auto-thermal decomposition.

    Chemicals capable of rapid oxidation.

    Enclosures with hot surfaces >400 C (>752 F).

    Volume of Hazard

    In order for the design concentration can be achieved and maintained, the

    total flooding applications hazard area must be an enclosed space with nosignificant openings. In general, the design is based on an empty area. All

    subsequent furniture, fittings or even the large equipment and cabinets

    should not be considered in the design calculation as it has a little effect on

    the actual concentration and as it is assumed that the internal area is

    required to be flood with the agent.

    Temperature of Hazard

    The extinguishing agent required must be based on the anticipated minimum

    ambient temperature in the hazard area. Precaution must be taken that the

    calculated concentration for normally manned areas at the anticipatedmaximum ambient temperature in the area does not exceed the

    NOAEL/LOAEL values as per the NFPA2001, sec tion 1.5 - Safety

    Filled and pressurized cylinders should not be exposed to temperatures other

    than the storage / operating temperature range of 0 to 50C (32F to 120F).

    This also includes while being transport or storage.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    12/38

    12

    System Design Procedure

    Kindly follow these procedures when designing HFC-227ea systems:-

    Hazard analyses and survey of protected area.

    Determine the required design concentration for the hazard.

    Determine the hazard altitude level and correction factor. (Refer to

    Table B)

    Calculate the agent quantity to provide required design

    concentration at minimum expected ambient temperature in

    protected area.

    Determine the cylinder size.

    Determine the integrity of the protec ted area.

    Loc ate nozzles.

    Locate and design pipe work.

    Check the percentage agent split at tees.

    Identity all pipe lengths, rises, drops, and nozzle.

    Note:For flow splits less than 30%, the split shall be done through a side teewith the smaller flow going through the side tee member. The minimum

    flow through the side tee member is 10%. The maximum flow through the

    tee is 90%. For the flow splits equal to or greater than 30%, the split shall be

    done through a bull head tee. The maximum flow through a bull tee is

    70%.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    13/38

    13

    Example: Tee Split Design Diagrams

    a) Side Tee Split limits. B) Bull Tee Split limits.

    90 70% 70 30%

    30 70%

    10 30%

    c) Side Tee Orientation correct d) Side Tee Orientation incorrect

    Correct Incorrect

    Tee splits tee splits

    e) Bull Tee Orientation correct f) Bull Tee Orientation incorrec t

    Correct tee splitsIncorrect

    Tee splits

    NOTE: Incorrec t orientation of side and bull tee could result in separation of HFC-227ea from the Nitrogen(due to HFC-227ea greater density). The design would a lso be outside the parameters permitted by theca lculation software. Refer to diagram d) and f).

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    14/38

    14

    Design Calculations

    The required agent quantity is based on the volume of protec ted area at the

    lowest expec ted ambient temperature and concentration required. To

    obtain the minimum agent quantity required, use the following equation:

    W = (V/S) x ( C/100 C)

    W = weight of Agent required

    V = volume of protec ted area

    S = spec ific vapour volume

    S = 0.1269 + 0.000513 T

    C = Required HFC-227ea Design Concentration (% by volume) at Design

    Temperature (t).

    T = Design temperature in protected area (C)

    Design Example

    Server Room: 6.3m x 6m x 2.5m(H) = 94.5m

    T = 20C for calculation example

    (7% required design c oncentration example only)

    W = (94.5 0.1373) x (7 (100 -7) ) = 51.81kg

    or

    94.5m x 0.5483 (flooding factor) = 51.8kg

    Note: Refer to table A for flooding factor.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    15/38

    15

    Table A HFC-227ea Total FloodingQuantity

    Temp Specific Weight Requirements of protected space, W/V (kg/m3)

    Vapour

    Volume Design concentration (by volume)

    T S

    oC kg/m3 7% 8% 9% 10% 11% 12%

    -10 0.1215 0.6169 0.7158 0.8142 0.9147 1.0174 1.1225

    -5 0.1241 0.6064 0.7005 0.7987 0.8951 0.9957 1.0985

    0 0.1268 0.5936 0.6858 0.78 0.8763 0.9748 1.0755

    5 0.1294 0.5816 0.6719 0.7642 0.8586 0.955 1.0537

    10 0.132 0.5700 0.6585 0.749 0.8414 0.936 1.0327

    15 0.1347 0.5589 0.6457 0.7344 0.8251 0.9178 1.0126

    20 0.1373 0.5483 0.6335 0.7205 0.8094 0.9004 0.9934

    25 0.1399 0.5382 0.6217 0.7071 0.7944 0.8837 0.975

    30 0.1425 0.5284 0.6104 0.6943 0.7800 0.8676 0.9573

    35 0.145 0.5190 0.5996 0.6819 0.7661 0.8522 0.9402

    40 0.1476 0.5099 0.5891 0.6701 0.7528 0.8374 0.9230

    45 0.1502 0.5012 0.5790 0.6586 0.7399 0. 823 0.908

    50 0.1527 0.4929 0.5694 0.6476 0.7276 0.8093 0.8929

    55 0.1553 0.4847 0.5600 0.6369 0.7156 0.796 0.8782

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    16/38

  • 7/27/2019 HFC227ea Engineering Manual

    17/38

    17

    Table D Equi valent L ength

    Diameter

    (mm)

    90 Elbow

    (m)

    45 Elbow

    (m)

    Thru Tee

    (m)

    Side Tee

    (m)

    Union

    (m)

    10 0.4 0.18 0.24 0.82 0.09

    15 0.52 0.24 0.3 1.04 0.12

    20 0.67 0.3 0.42 1.37 0.15

    25 0.85 0.4 0.55 1..74 0.18

    32 1.13 0.52 0.7 2.29 0.24

    40 1.31 0.61 0.82 2.65 0.27

    50 1.68 0.79 1.06 3.41 0.37

    65 2.01 0.94 1.25 4.08 0.43

    80 2.5 1.16 1.55 5.06 0.55

    100 3.26 1.52 2.01 6.64 0.73

    125 4.08 1.92 2.56 8.35 0.91

    150 4.94 2.32 3.08 10 1.07

    Equivalent length table for pipe fittings.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    18/38

    18

    INSTALLATION INSTRUCTIONS

    GENERAL

    Prior to installing the HFC-227ea fire suppression system, the installer must be

    familiar with the system and have previous experience in installation ofgaseous suppression systems. The installer must refer to the piping and

    instrumentation diagram and general arrangement drawings for the system

    and c heck that all components are complete and in order. If the installation is

    carried out by untrained or inexperience personnel, they may jeopardize the

    integrity of the system, their own safety and of others as well as the warranty

    of the system.

    The instructions in this sec tion as well as information contained in thecomponent data sheets should be read by the installer.

    The location of the cylinder bank shall have sufficient floor loading capability,a flat dry floor and walls or solid structures for securing the system. The owner /

    client should satisfy themselves in this regard.

    All necessary work permits & procedures shall be obtained / established firstto the satisfaction of the client, owner or the local authorities having

    jurisdiction.

    SAFETY

    The HFC-227ea system is filled to a pressure of 25 bars at a reference

    temperature of 20oC. The cylinders have the different sizes which could fill withdifferent quantity of agent. Safety precautions must be adhered to in the

    handling of the HFC-227ea cylinders.

    Some safety precautions to follow are: -

    1) The transport cap shall always be screwed onto the cylinder whenever

    the cylinder is moved, being loaded or unloaded.

    2) Always use suitable lifting gear, (forklift, truck or hoist) when loading or

    unloading cylinders. Do not offload the cylinders by dropping them to

    the ground.

    3) Use a suitable cylinder trolley to move the cylinders. Do not roll them on

    the ground.

    4) At site, if the cylinders are not to be installed immediately, store either

    on their sides with wedges to prevent them from rolling or secure themusing ropes or belts in an upright position. The storage area must be dry

    and in a place where they will not be damaged.

    5) Do not remove the screwed cylinder transport cap from the cylinder

    unless the cylinders are securely held in position by its clamps orbrackets.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    19/38

    19

    6) Never attempt to remove a cylinder valve from a pressurized cylinder.

    7) Do not use extreme force (hammers, long levers, pipe wrench, etc.) on

    any part of the valve or actuating components.

    8) Cylinders, valves, and actuating components SHALL NOT BE drilled,

    braised, welded, machined or stamped. The only permitted processes

    are cleaning and painting of the cylinders.

    9) In the event of any abnormalities such as jammed or deformed valves,

    cracks or other apparent weaknesses, keep away and inform the

    appropriate engineer.

    10)Heavy protective gloves (preferably textile or leather) should be worn

    at all times for the manual handling of cylinders to minimize the risk ofhand injury. During discharge, all connected parts of the cylinder and

    valve are likely to bec ome very cold and there is a risk of "frostbite" if

    any of the parts are handled at that time with unprotected hands,

    particularly if hands are wet.

    11)Safety footwear shall always be worn at all times.

    HFC-227ea System Installation Procedures

    1) The following drawings and instructions should be as a minimum bein the possession of the installer :-

    a) P & I Diagram

    b) Piping Isometric

    c) Piping Plan

    d) Cylinder Bank Assemblye) Electrical Wiring Diagram

    f) Installation Procedures, this sec tion.

    g) Material List

    Material Preparation.

    a) Prior to carrying out the assembly and installation, check that all

    the required materials have arrived at site and they are in good

    condition.

    b) Ensure that the protected areas and cylinder storage areas

    matches the drawings in layout and size. Inform the projec t

    manager of any discrepancies.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    20/38

    20

    Transport and Storage of Materials

    The cylinders must be fitted with transport caps whenever they are moved or

    when they are not connected to the manifold.

    When the cylinders and associated equipment arrive on site, they shall bestored in a dry room within a temperature range of 0oC and 50oC until they

    are needed for installation.

    When storing the cylinders, secure them so that they cannot fall or roll.

    Avoid exposing the cylinders from sunlight and heat.

    NOTE:

    The cylinders must not be dropped or rolled when transporting or moving

    them. A suitable trolley should be used to move the cylinders.

    Installation of the low pressure pipe distribution network

    The low pressure pipe network begins after the manifold. The pipes used shall

    be Sch. 40 ASTM A-106A or other equivalent standards which can

    accommodate the maximum pressure calculated in the network. Refer to

    table E.

    1) Piping should be installed in accordance with good commercialpractice. Screwed pipe should be cleaned of oil and swarf.

    Screwed joints should be sealed using PTFE on the male threads.

    Care should be taken to avoid possible restrictions due to foreign

    matter, faulty fabrication or improper installation. The piping system

    should be securely supported with due allowance for agent thrustforces and thermal expansion/contraction, and should not be

    subjected to mechanical, chemical, vibration, corrosion or other

    damages. Where explosions are likely, the piping system should be

    attached to supports that are least likely to be displaced. A

    galvanized steel pipe is recommended as they are less likely to

    corrode within a short period of time. If rust flakes or particles arepresent within the pipe, they may come loose during a discharge

    and may be able to block off the orifices in the nozzles thus

    jeopardizing the release. Also the rust c loud / spray may ruin the

    ceiling tiles, or may damage sensitive equipment within the

    enclosure. Special coatings or corrosion resistant materials must be

    used in corrosive environments.

    2) After installation of the pipe work it is recommended to flush the

    pipe work in order to remove dirt / particles, sealing material,

    cutting burrs, etc. as well as to verify that flow is continuous and

    that the piping is unobstructed. Flushing should be performed priorto the pressure testing of the pipe work and after any rectification

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    21/38

    21

    work on the pipe network. If water is used for flushing, ensure that

    the pipe work is blown dry to minimize internal corrosion of the

    piping. If gaseous media is used, (compressed air, nitrogen, etc.)

    ensure that the pipe work has not been sealed off in any way.

    Make sure that no one is in any of the rooms in which the pipe workis to be flushed. Where necessary, filter bags should be used to

    collect any dirt or particles being blown out of the pipe work

    espec ially if there is equipment in the room.

    3) The pipe work should be leak tested prior to installing the discharge

    nozzles. Leak testing of the distribution pipe work should be carried

    out as follows :-

    a) Verify that all manifold check valves are fitted onto themanifold. Plug off the nozzle points using suitable plugs.

    b) Connec t the nitrogen test supply cylinder assembly to the

    manifold.c) Make sure that no one is in any of the rooms in which the

    pipe work is to be tested.

    d) Slowly pressurize the distribution pipe network to 3 bar.

    e) Check the pipe network for leaks. If there are no leaks,proceed to pressure test the pipe work to 3 bar for about 10

    minutes. Any pressure drop should not exceed 20% of the

    test pressure.

    f) Release the pressure slowly after testing.

    g) If rectification work was carried out, flush the pipe works first

    prior to pressure test the pipe work again.

    The following tables show the maximum allowable pressure (psi) for steel pipe

    with threaded end connection as well as rolled grooved or welded end

    connections.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    22/38

    22

    Table E

    Maximum Allowable Pressure (psi) for steel pipe with threaded end

    connections

    Schedule Nom. Wall Grade A-106C A-53BA-53B A-53A

    Pipe A-106B A-106A

    Size Thickness Type Seamless Seamless ERW Seamless

    40 1/2" 0.109 2593 2222 1896 1778

    3/4" 0.113 2234 1915 1634 1532

    1" 0.133 2026 1736 1482 1390

    11/4" 0.140 1782 1528 1304 1222

    11/2" 0.145 1667 1429 1220 1144

    2" 0.154 1494 1280 1093 1025

    21/2" 0.203 1505 1193 1100 1032

    3" 0.216 1392 1096 1018 954

    4" 0.237 1278 1022 935 876

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    23/38

    23

    Table F

    Acceptable Fittings Maximum Pipe Size

    Class 300 malleable/ductile iron up to 3" NPS1,000-lb rated ductile iron / forged steel > 3"

    Class 300 flanged joints All

    Source: NFPA2001 - 2004 Edition

    Note: Other fittings manufactured to equivalent standards / codes can be

    used so long as they can withstand the working pressure.

    Installation of the Discharge nozzle

    1) Install the appropriate nozzles with the correc t orifice sizes in their

    designated locations as per the piping isometric drawing & plan.

    2) Screw the discharge nozzles into their fittings, using PTFE tape to

    make a tight seal. Use a spanner to make the nozzles hand tight.

    A. Miscellaneous1) Install the entrance warning signs on all entry doors into the

    protected area.

    2) Install the manual release warning signs adjacent to the cylinder

    equipped with the manual release.

    3) Check the integrity of the protected area for excessive openings

    which could result in unacceptable leakage of the c lean agent.

    NOTE 1: A fan integrity test may be used to ascertain the integrity ofthe enclosure.

    NOTE 2: A discharge test is usually notencouraged for HFC gases todetermine the performance of the system.

    4) Check the interconnections between the actuation device and

    the control panel, as well as the pressure switches and the audio &

    visual alarms plus equipment and ventilation systems shutdown.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    24/38

    24

    Pipe Hangers/Support

    The maximum distance between hangers/support should not exceed the

    distances as stated in table G. Piping shall be sec urely supported using solid

    supports, giving due allowance for thrust forces and thermal expansion and

    contrac tion and should not be subjected to mechanical, chemical, vibrationor other influence unless special prec autions are made.

    Adequate hanger/support shall be provided for nozzles and their reactive

    forces such that in no case shall the distance from last hanger/support be

    more than 300mm.

    Table G Hanger Spacing

    Pipe Size

    (mm)

    Maximum Spacing

    (m)

    10 1

    15 1.5

    20 1.8

    25 2.1

    32 2.4

    40 2.7

    50 3.4

    65 3.5

    80 3.7100 4.3

    150 5.2

    Electrical Clearance

    When exposed electrical conductors are present in the protected enclosure,

    safety clearance no smaller than those listed in Table H shall be provided,

    where practicable between electrical conductors and all parts of the systemthat may be approached during maintenance. Where these clearances

    cannot be achieved, warning notices shall be provided and a safe system of

    maintenance work shall be adopted.

    Minimum clearance from any on or about the permanent equipment where

    a person may be required to stand (measure from the position of the

    feet).Section clearance to the nearest unscreened live conductor in air.

    Ground clearance to the nearest part not at earth potential of an insulator

    supporting a live conductor.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    25/38

    25

    Table H Safety Clearance

    Maximum Rated

    Voltage

    (KV)

    Minimum Section

    Clearance

    (m)

    Minimum Ground

    Clearance

    (m)15 2.6 2.5

    33 2.75

    44 2.9

    6 3.1

    88 3.2

    110 3.35

    132 3.5

    165 3.8

    220 4.3275 4.6

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    26/38

    26

    System Operation

    General

    The SRI HFC-227ea fire suppression system must be used in conjunction with a

    detection and control system in order for the extinguishing system to operateautomatically. Some issues must be addressed before deciding on the bestdetection system. They are:-

    a) the speed of detection required

    b) what phenomenon to detect, e.g. Smoke, heat, flame, gas, fuel mist,

    etc.

    c) Relative acceptability of unwanted alarms

    d) Cost effectiveness

    Generally, all gaseous extinguishing systems requires a detection and control

    system to operate automatically. Detectors are needed to sense the fire,while the control system would give the signal to all visual & audio alarms,

    shutdown auxiliary equipment, and activate the suppression system.

    Detection Speed

    A gas extinguishing system's speed of extinguishment is usually moredependant on the response time of the detection system, rather than the

    discharge time of the gas. There is a wide variety of detec tion and controltechnologies available in order to cover the different types of fire risks.

    However, the technologies differ greatly in cost, and as such it is important to

    select a system that offers the client the optimum and cost-effec tive fire

    protection system.

    Types of Detectors

    The types of detectors commonly used in gaseous fire extinguishing systems

    are smoke detectors and heat detectors. For certain special hazards, flame

    detectors and gas detectors are used.

    Smoke detectors are available in several types, optical, aspirated and air

    aspiration system. The first two types are widely available at reasonable prices

    and are c ommonly used. Aspirated type is slightly more expensive but their

    response time is faster. For an even faster response time an air aspiration

    system can be used. However, they are much more expensive and are moresuited for clean room environments. Generally, the more sensitive the

    detec tors, the more prone they are to false alarms.

    Heat detectors are normally available in 3 types, rate of rise (ROR), fixed

    temperature or a combination of both ROR and fixed temperature. Heat

    detec tors are less prone to false alarms and are cheaper compared to smokedetectors. However, in most cases, a fire may well be underway before the

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    27/38

    27

    heat detector operates. In high risks or sensitive areas using a gaseous

    extinguishing system, the delay of a heat detector would cause fire damages

    which might be unacceptable to the client.

    Flame detectors are employed where flammable liquids or powders are

    present since fires spread very rapidly. Flame detectors are available in 2types, ultra-violet (UV) and infrared (IR) flame detec tor. UV flame detector

    respond faster compared to the IR flame detector. UV detectors can be

    blinded by dirt or grease while IR detectors can be blinded by water.

    Consideration must be given to incorporate a monitoring system on these

    detec tors to give a fault alarm if they are blinded.

    Detector Spacing

    Currently, there is no one internationally recognized standard for detector

    spacing therefore the detec tor requirements shall be based on the respective

    countries' standard or as required by the loc al authority having jurisdiction.

    There is a general consensus that while the detec tors used for fire alarms can

    be installed at its maximum area coverage, those used for triggering gas

    suppression systems should be reduced or halved. This is bec ause detectorsinstalled at the maximum approved spacing for fire alarm use could result in

    excessive delay in agent release, especially when more than one detection

    device is required to be in alarm before automatic actuation results.

    Detector Location

    Detec tors should be placed in a protected enclosure with the following aims:

    1) to give the detectors the best chance to detect a fire quickly, and

    2) to reduce the risk that the detec tors give a false alarm.

    To make sure that the detec tors can sense a fire, do:-

    1) locate them at least 1 m from all obstructions.

    2) assure a free passage of smoke to the detectors. Install detectors in a

    cable floor as well as the main room if the cable floor should also beprotected.

    3) evaluate the impact of the ventilation systems on detectors; they

    sometimes either prevent the smoke reaching the detection chamber

    or else contaminate detectors in air currents with dust.

    Conventional detectors should be installed in crossed zones, where each

    zone is made up of detectors installed diagonally to each other. In any case

    a minimum of two detec tors must operate before the gas is released

    automatically.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    28/38

    28

    Typical Sequence

    The following is a typical sequence of events (details may vary according to

    local prac tice or regulations):-

    a) A detector goes into alarm

    b) Visual and audible pre-alarm is given

    c)The ventilation system is automatically switched off

    d) A second detec tor goes into alarm, confirming the fire condition.

    e) Visual and audible fire alarm is given and the time delay is started.

    f) Any automatic closing of doors or openings is initiated.

    g) After the preset delay, a signal is sent to the elec tric actuator to

    release the gas.

    h) A visual alarm is given, indicating the release of the gas.

    Other possible events which could alter this sequence are:

    a)The release signal may be manual; it will have the same effect as the

    second (confirmation) detection signal.

    b)There might be an Abort or Hold switch to prevent a discharge, forexample when people are present in the enclosure.

    All control panels normally would have a fac ility for adjusting the time delay

    but the range may vary from 0 60 seconds depending on the local

    requirements.

    It is not the intention of this sec tion to recommend any particular makes of

    detec tors and control systems since each countries have their own standards

    and regulations. As such, the proposed detec tion and control system shall

    have the approval of the Local Authority having J urisdiction.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    29/38

    29

    Condition During a Fire

    The users fire and safety instruction to personnel should include advice on theconditions prevailing during the discharge on a HFC-227ea system. This

    advice is intended to prepare the personnel for the situations likely to arise

    and therefore minimize the risks of panic. Three major conditions prevailduring HFC-227ea systems discharge of which personnel should be made

    aware:

    HFC-227ea Concentration

    HFC-227ea total flooding systems greater than 9% design conc entration

    should only be used with manual actuation in normally occupied areas. A

    normally occ upied area is defined as an area intended for occupancy.

    Any area protected by HFC-227ea system should be evac uated prior to startof system discharge. Where egress of normally occupied areas cannot be

    accomplished within one minute, HFC-227ea total flooding systems shall be

    designed not to exceed 9% concentration.

    Refer to NFPA 2001, clause 1.5.1.2 for additional information.

    HFC-227ea Decomposition

    HFC-227ea decomposes when exposed to temperatures exceeding 482C.

    The rate of this decomposition is dependent upon the size of the area whereextreme temperatures are found, and also upon the length of HFC-227ea

    exposure time.

    To avoid decomposition, the HFC-227ea systems are designed to discharge

    and extinguish the fire quickly. (NFPA 2001, clause 5.7.1.2 Discharge time)

    Hydrogen Fluoride is the most toxic decomposition product. This materialgenerates a sharp acrid odour, which is easily detected and acts as a

    warning and a good safeguard to personnel.

    HFC-227ea Discharge Condition

    HFC-227ea has a low boiling point; consequently the discharge is very cold at

    the point where it leaves the nozzle. Care should be taken to avoid working

    within 1 meter of HFC-227ea discharge nozzles.

    The velocity of discharge of HFC-227ea from a discharge nozzle is very high,

    care should be taken to insure that objects which may become dangerousprojectiles are secured or removed from the protected area.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    30/38

    30

    Actions Following a Fire

    General

    These notes are only applicable to the protected area(s) protec ted by a

    HFC-227ea fire extinguishing system. Where such a system may form part of,or combine with other forms of fire protection systems then composite

    instruction for all systems are necessary to ensure the safety of personnel and

    property following a fire. The organization will have appointed, or nominated,a responsible person to act as a Fire Officer or Safety Officer to look after

    the safety issue. Actions following a fire should be coordinated and/or

    direc ted by the officer.

    Ac tions Immediately Following a Fire

    These ac tions should, at a minimum, include the following:

    Advise the Fire Brigade or police if appropriate.

    Organize a roll call of employees and any visitors.

    Prevent unauthorized personnel from entering the protected area.

    In the case of deep seated fires, the protected area should be kept

    tightly closed for at least 60 minutes after discharge of HFC-227ea

    extinguishing agent. It is important that the fire be completely

    extinguished before ventilating the area. Before permitting any one toenter the area, ventilate thoroughly or ensure self-contained breathingequipment is used.

    Do not enter the protected area in which fire has been extinguished

    with an open flame or lighted cigarette as the possible presence of

    flammable vapours may cause re-ignition or explosion.

    Should it be necessary to enter a area containing HFC-227ea or

    decomposition products the following precautions should be taken;

    Use a fresh air mask or self contained breathing equipment.

    Do not use a filter mask or canister type mask.

    Do not enter area unless you are under observation from outside the

    area, or tethered by a lifeline.

    Ensure that all pressurized equipment is isolated or safe from release.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    31/38

    31

    TESTING AND COMMISSIONING

    PRE - COMMISSIONING CHECK LIST

    1) Check that all pipes and fittings are in accordance with the

    correc t specifications as shown on the General ArrangementDrawings. Chec k that the systems are installed in

    accordance to the drawings. Any deviations from the

    original design should be incorporated into "As Built". Check

    that all remedial works (if any) have been completed.

    2) Check that all discharge nozzles with the appropriate orifice

    size are fitted in their designated locations.

    3) Check all pipe supports and brackets to ensure that the

    system pipe work is firmly sec ured in position.

    4) Check all cylinder supports and brackets to ensure that the

    cylinders are firmly secured in place.

    5) Check all fittings and hoses are tightened and secured.

    6) Check the cylinder pressure. The pressure may vary

    depending on the ambient temperature.

    COMMISSIONING PROCEDURES

    Testing the ac tuation of the system can be broken down into 2 separate

    functional tests; electrical and mechanical.

    WARNING:BEFORE CARRYING OUT ANY FUNCTIONAL TESTS, MAKE SURE THAT THEACTUATION DEVICE IS REMOVED FROM THE CYLINDER VALVE.

    Electrical Actuation

    1) Make sure that the actuation device is disconnected from the

    valve.

    2) From the control panel, initiate a fire condition. This will start a time

    delay prior to simulate a 24V DC output to the actuation device

    connection. Depending on the local authority requirements the

    delay can be adjusted at the control panel from 0 to 60 seconds.

    Normally the delay is set at 30 sec onds.

    3) Use the multi meter to measure if there is 24V DC output from the

    panel. Make sure to reset the control panel first prior to connecting

    the actuation device again.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    32/38

    32

    Mechanical Actuation

    1) The manual / pneumatic ac tuator is fitted to the top of the

    cylinders valve.

    2) Pull the safety pin out and operate the manual release lever.

    NOTE: ONCE THE TESTING AND COMMISSIONING HAS BEENCOMPLETED, REINSTALL THE ACTUATION DEVICE BACK ONTO THECYLINDERS VALVE.

    Commissioning Forms and Certification

    The Testing and Commissioning forms / checklist and Acceptance report shallbe duly completed, and all necessary signatories obtained. A copy is to be

    given to the relevant party.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    33/38

    33

    Testing and Commissioning Check List for HFC-227ea System. (Sample)

    Item Description Yes No Remarks

    Piping

    1 Check that the correct pipe schedule

    and fittings were used. Refer to

    isometric drawings for spec ifications.

    2 Check that the pipe routing and size

    correlate with the pipe plan and piping

    isometric drawings. Any major

    modifica tions to be noted and handed

    over to the project engineer for

    verification of calculation.

    3 Check that the piping network aresecurely fastened to a solid and stable

    structure using appropriate supports.

    Check that all bolts are tighten properly.

    4

    Check that the piping network has

    been flushed / dried out and pressure

    tested. Test report to be issued by

    the installer.

    5 Check that all discharge nozzles are

    Installed securely and are notobstructed.

    Verify that each nozzle with the correc t

    orifice size is installed at the correc t

    location as per piping isometricdrawing.

    Cylinders

    6

    Check that the number, their volume

    and filling pressure correspond with the

    project specification

    7 Check that they are not damage, the

    Paint has been repaired.

    8Check that the wall brackets aresecurely fastened to a solid and stable

    structure. Check that all bolts are

    tighten properly.

    9 Check that all cylinder clamps are

    mounted properly and all bolts are

    securely fastened.

    10 Check that each cylinder has been

    labeled and the label has been filled

    correctly.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    34/38

    34

    Item Description Yes No Remarks

    11 Check that the cylinder transport caps

    are available for transport of the

    cylinders for refilling.

    Manifolds

    12 Check that the manifold arrangement is

    ac cording to drawings.

    13 Check that the manifold brackets are

    securely fastened to a solid and stable

    structure. Check that all bolts are

    tightened properly.

    14 Check that the manifold is securelyfastened to the brackets.

    15 Check that the manifold assembly is

    securely fitted to the distribution pipe

    network.

    Accessories

    16 Check that the discharge hose(s) has a

    smooth bending, are not stretched,

    compressed or kinked.

    17 Check that the discharge hose(s) has

    been securely fixed onto the discharge

    valve outlet and at the manifold check

    valve.

    18 Check that pressure on each cylinder

    is within the acceptable range.

    19

    Check that the pressure gauge

    orientation is correct, i.e. The dial gauge

    face is facing outwards.

    20

    Check that the pneumatic actuating

    hoses are connected properly to

    the pneumatic actuators on each

    slave cylinders. Tighten using a spanner

    until it stops.

    21

    Check that there is a plug installed on

    the pneumatic actuator at the last slave

    cylinder to close the actuating line.

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    35/38

    35

    WARNING :

    BEFORE CARRYING OUT ANY FUNCTIONAL TESTS, MAKE SURE THAT

    THE ACTUATION DEVICE IS REMOVED FROM THE CYLINDER VALVE.

    Item Description Yes No RemarksAccessories

    22 Check that the actuation device

    wiring is properly terminated.

    23 Check the function of the manual /

    pneumatic actuator if fitted. Replace the

    seal tag a fter completion of test.

    Room / Enclosure

    24 Verify the room sizes, compare actual

    volume with project information. Seevolume input used in the calculation.

    25 Verify that vents / pressure relief

    arrangement where required is installed

    in accordance with system requirements.

    Check against results from flow

    calculation information or calculations

    based on the room integrity test / door

    fan test.

    26

    Ensure that the room(s) has been cleaned

    up.

    General

    27 Ensure that all doors into the protected

    area has been provided with a warning

    label / signage.

    28 Ensure that the operating instructions

    has / will be given.

    29 Ensure that the operation and

    maintenance manual has / will be given.

    Commissioning Engineer's Name : Signature :

    Installer / Contractor's Name : Signature :

    Completion Date :

    Client :

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    36/38

    36

    HFC-227ea FIRE SUPPRESSION SYSTEM

    CERTIFICATE OF INSTALLATION, COMMISSIONING AND ACCEPTANCE (SAMPLE)

    CLIENT :

    SITE ADDRESS :

    WORK UNDERTAKEN :

    CONTRACT NO :

    We hereby certify that in carrying out this work the methods, materials andcomponents used comply with the specifications and standards as listed in thecontract.

    Other than the deviations listed below :-

    Design Concentration :

    Fan Test Result : PASSED FAILEDNOT

    APPLICABLE

    All commissioning procedures as per checklist have been carried out.

    Commissioning Engineer's Name : Signature :

    Installer / Contractor's Name : Signature :

    Date :

    We confirm that the work has been carried out to our complete satisfaction and is

    accepted in good working order. A copy of the Operation and Maintenancemanual, as-built drawings and operating instructions have been supplied and

    received.

    Client's Representative Signature :

    Name and Position :

    Date :

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    37/38

    37

    MAINTENANCE

    The system shall be maintained on a regular basis, at least on an annual basis

    or as otherwise spec ified by the loc al authority having jurisdiction.

    Maintenance of the system shall include the following:-

    A. Protected Area / Enclosure Check1. Survey the protec ted area to verify that it has not changed from

    what the system was designed to protect. While surveying, look

    for different fuels, new equipment, blocked open doors or

    dampers, new penetrations or gaps which may lead to loss of

    the hazard integrity, etc.B. Discharge Nozzles

    1. Check all nozzles to make certain they are in place and have

    not been tampered with. Check the nozzles for corrosion or

    damage, and that they are not obstructed internally or

    externally.C. Distribution Pipe Network

    1. Check the condition of the piping to make certain that it is

    properly secured in the hangers, the brackets are not loose andall fittings are connected tightly.

    D. Signage1. Check all warning nameplates throughout the area. Ensure that

    they are in place, mounted securely, readable and are not

    damaged.

    IMPORTANTPrior to carrying any maintenance on the system, the system should be

    inhibited electrically by the control panel (if available). For multiple cylinders

    system, the actuating hose must be disconnected from the slave cylinder.

    Thereafter, remove the actuation device from the master cylinder. For single

    cylinder systems, proceed to remove the actuation device once the system

    has been inhibited electrically if so equipped. (Ref. Fig. 7.5 - (7) for details)

    E. Cylinders check1. Chec k the cylinder bracketing. Ensure that the cylinders are

    secured in the brackets. Check for corrosion, damage or missingcomponents. For the packaged type, check the frame and

    plates for damage or corrosion as well as loose or missing

    components.2. Check the condition of all cylinders. Check for signs of damage

    or corrosion and check the c ylinders' last hydro test dates.(NFPA 2001 states "Cylinders continuously in service without

    discharging shall be given a complete external visual inspection

    every 5 years or more frequently if required. The visual inspec tion

    shall be in accordance with Compressed Gas Association

    Pamphlet C-6, Section 3; except that the cylinders need not be

    emptied or stamped while under pressure").

    PDF created with pdfFactory trial version www.pdffactory.com

    http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/
  • 7/27/2019 HFC227ea Engineering Manual

    38/38

    3. Check storage cylinder pressure gauge and ambient

    temperatures; compare this pressure to the temperature

    correction chart to determine temperature corrected pressure.

    If the cylinder correc ted pressure shows a pressure loss of more

    than 10%, the cylinder should be removed for weighing, allmeasurements and actions shall be recorded.

    F. Components CheckMake a visual inspection of the systems components, distributionpiping and nozzles. Check the immediate vicinity of all

    equipment to ensure that no accidental damage or tampering

    has occurred.

    G. Specialized Maintenance DutiesCylinder Hydrostatic Pressure Testing

    Providing cylinders are submitted to a full external inspec tion

    every 12 months from the date of introduction, the allowable

    interval period before the first periodic inspection and

    hydrostatic pressure test is 20 years.

    Any cylinder that is discharge between 10 years and 20 years of

    being introduced into service shall be submitted to a full

    periodic inspection and a hydrostatic pressure test before being

    refilled. The interval between the first and second periodicinspection and hydrostatic pressure test may not exceed 10

    years. Subsequent retests are not to exceed 5 years. (NFPA

    2001)

    Finally

    Carry out a final visual inspection of the system and the

    protected area to ensure that all equipment has been

    reinstalled and reconnected properly. Ensure that any

    associated control/indication panel is displaying normal

    operation. Complete the maintenance log book, recording

    work carried out and parts used. Inform the responsible personthat the work is complete and that the system is back on

    operation mode.