Upload
edik-ed
View
227
Download
0
Embed Size (px)
Citation preview
7/27/2019 HFC227ea Engineering Manual
1/38
1
Introduction___________________________________________________________
With the Montreal Protocol conference from 1993, manufacturing of
substances with Ozone Depleting Potential (ODP), including Halon 1301
(CBrF3), Halon 1211 (CCIF2Br) and Halon 2201 (CHF2Br), which were used as fire
extinguishing agents, was banned.
HFC227ea as one of the Halon alternatives is a clean and safe fire suppression
agent for use in total flooding automatic systems. Storage and distribution
requirement are similar to Halon or other HFCs fire suppression systems andthe majority of system components are identical. Due to the difference in
agent quantity and discharge characteristics, HFC227ea is not a direc t
replacement (drop-in) for existing Halon 1301 installation. It is rated as Zero
Ozone Depletion (ODP), is electrically non conductive, clean and leaves no
residue.
HFC227ea may consist of a single cylinder or several cylinders combination,
manifold together and connected via a pipe network to a number of
discharge nozzles. System discharge can be activated mechanically or
electrically. Mechanical manual actuation is via a manual pull handle
mounted on cylinder valve. Electrical ac tuation is via a solenoid actuator
which mounted on the side of manual pull actuator and is energized
automatically from detection and alarm control panel.
Health and Safety
Exposure to HFC227ea at the design concentration of 7% and up to 9.0% is
not hazardous to health within a limited egress time. Exposure to higherconcentrations is permissible for a limited period. In accordance with NFPA
2001, Halocarbon clean agent system for spaces that are normally occupied
and designed to concentrations up to the NOAEL shall be permitted. Its Non
Observed Adverse Effec t Level (NOAEL) for cardiac sensitization is 9%. With 9%
concentration level, the maximum human exposure time shall not exceed 5
minutes.
The National Fire Protection Assoc iation (NFPA 2001 Standard on CleanAgent Fire Extinguishing Systems) recommends that unnecessary exposure to
any agent be avoided and that personnel evacuate protected areas as
quickly as possible to avoid the decomposition products of the clean agent.
HFC227ea can decompose at high temperature or under fire to a form of
halogen ac ids which is readily detec ted as a sharp, pungent odor even afterfire extinguished or long before hazardous maximum exposure levels are
reached. Ventilation and openings are required to clear the protec ted areas
after HFC227ea system discharged, no one is allowed to enter the areas
during system discharge or before the area is totally ventilated and safe for
occupancy again. Direct contact with the vaporizing liquid discharge from a
HFC227ea nozzle has a cool chilling effect on objects and in extreme casescan cause frostbite to the skin. Ones should avoid direc t contac t with the
agent.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
2/38
2
WARNING!
The discharge of clean agent systems to extinguish a fire can result in a
potential hazard to personnel from the natural form of the clean agent orfrom the products of combustion that result from exposure of the agent to the
fire or hot surfaces. Unnecessary exposure of personnel either to the natural
agent or to the products of decomposition shall be avoided.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
3/38
7/27/2019 HFC227ea Engineering Manual
4/38
4
HFC227ea contains no chlorine and bromine atoms, presenting no ozone
depletion effect. According to medical findings, as an aerosol propellant,
HFC227ea is used in pharmaceutical metered dose inhalers such as those
used for dispensing asthma medication.
NOTE:
HFC227ea shall not be used on fires involving the following materials unless
they have been tested to the satisfaction of the authority having jurisdiction.
1. Certain chemicals or mixtures of chemicals, such as cellulose nitrate and
gunpowder, those are capable of rapid oxidation in the absence of air.
2. Reactive metals such as lithium, sodium, potassium, magnesium, titanium,zirconium, uranium, and plutonium.
3. Metal hydrides.
4. Chemicals capable of under going auto thermal dec omposition, such as
certain organic peroxides and hydrazine.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
5/38
5
SYSTEM COMPONENTS
This sec tion shows the individual components:
1. HCV Valves 9. Pilot Cylinder c/w Solenoid2. HCV Manual Pull Ac tuator 10. Heat & Smoke Detec tor
3. Discharge Hose 11. Extinguishing Panel
4. Solenoid Ac tuator 12. Sounder
5. Cylinder 13. Alarm Bell
6. Discharge Flashing Light 14. Abort Switch
7. Nozzles 15. Door Warning Sign
8. Manual Pull Box 16. Door Fan Test Equipment
HCV valves
Part no. Part name. Outlet size
SPS1C001HVC20 HVC 20
(for 25L cyl)
1 BSP
SPS1C001HVC40 HVC 40
(for 45 -
130L cyl)
2 BSP
SPS1C001HVC60 HVC 60(for 160 -
230L cyl)
2 1/2 BSP
HCV manual pull Actuator
Part no. Part name.
SPS1C-003-MPAV Manual pull ac tuator
Discharge hoses
Part no. Part name.
1. SPS1C-005-38mm
SPS1C-005-50mm
SPS1C-005-65mm
2. SPS1C-006-8mm
Discharge Hose
Loop Hose
1
2
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
6/38
6
Solenoid Actuator
Part no. Part name.
CO2070-BR-XXX-XX Solenoid Actuator
Cylinders
Part no. Part name.
SPS1C-004-25L
SPS1C-004-45L
SPS1C-004-75LSPS1C-004-100L
SPS1C-004-130L
SPS1C-004-160L
SPS1C-004-190L
SPS1C-004-230L
25L cylinder
45L cylinder
75L cylinder100L cylinder
130L cylinder
160L cylinder
190L cylinder
230L cylinder
Discharge Flashing Light
Part no. Part name.
FAS251-24VDC-STD Discharge Flashing
Light
Nozzle
Part no. Part name.
SPS-1C007-15mm
SPS-1C007-20mm
SPS-1C007-25MM
Nozzle
Nozzle
1 Nozzle
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
7/38
7
Manual Pull Box
Part no. Part name.
CO2072-MS-STD-RD Manual Pull Box
Pilot Cylinder c/w Solenoid
Part no. Part name.
CO205A-CS-001-SP Pilot Cylinder c/w
Solenoid
Optical Smoke Detector
Part no. Part name.
FAS1B-55000-317 Optical Smoke Detec tor
Heat Detector
Part no. Part name.
FAS1B-55000-100 Heat Detec tor
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
8/38
8
Extinguishing Panel
Part no. Part name.
FAS0021P-002-RD Extinguishing Panel
Sounder
Part no. Part name.
FAS4A-Y04-24VDC Sounder
Alarm Bell
Part no. Part name.
FAS194-LA-150-RD Alarm Bell
Abort Switch
Part no. Part name.
FAS258-AB-28V Abort Switch
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
9/38
9
Door Warning Sign
Part no. Part name.
MISC-SPD-DIV Door Warning Sign
Door Fan Test Equipment
Part no. Part name.
SPS xxxxxxxxxx Door Fan Test Equipment
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
10/38
10
SYSTEM DESIGN
Two main elements are critical to HFC227ea system design. The first is the risk
assessment to determine the type of protec tion required, such as what kind of
hazards to protect from, whether an occupied area or a restricted area,ventilation or openings, what kind of building, types of equipments, locations
etc. The second is calculating the quantity of HFC227ea required, determine
cylinder quantity, nozzle quantity, nozzle orifice size, pipe sizes, piping layoutand nozzle location base upon criteria of room sizes, floor height, raised floor
and/or ceiling voids.
Hazard Analysis
An analysis of the hazards is useful and highly rec ommended to carry out bythe contractor/designer/supplier if such location is far too complex and
difficult to visualize and/ or understand under a plan drawing. This enablecontractor to measure and provide an accurate details for designer/supplier
to calculate a precise pre-engineered HFC227ea system for eac h application
in accordance with NFPA 2001 standard.
HFC227ea systems are suitable for use in normal commercial and industrial
environments. The design concentration for Class A & C is 7.17% but differs for
Class B fires. However, the minimum design concentration for flammable
liquids is 9.0% based on commercial grade heptanes. All design
concentration calculations are based on extinguishing concentrations plus an
additional 20% safety factor for Class A & C and a 30% safety factor for Class
B and all manually actuated only systems.
Class A Fires involving solid materials usually of an organic nature, in
which combustion normally takes place with the formation of
glowing embers.
Class B Fires involving flammable liquids or liquefiable solids and
flammable gases.
Class C Fires involving energized electrical equipment where the
elec trical non conductivity of the extinguishing media is of
importance.
Design concentrations are determined by NFPA 2001.
HFC227ea cup-burner value is 6.7% for commercial heptane fuel. Nozzle
distribution test concentration is 6.9%.
Nozzle efficiency factor = nozzle distribution test concentration / cupburnervalue.
= 6.9/6.7 = 1.03
Safety factor: Class A = 1.2
Class B = 1.3Class C = 1.2
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
11/38
11
Minimum design concentrationClass A fire (determine by fire test) 5.8% x 1.03 x 1.2 = 7.17%
Class B fire (commercial grade heptane) 6.7% x 1.03 x 1.3 = 9.0%
Class B fire (other C lass B fuels) cupburner value x 1.03 x 1.3 = no less than
9.0%Class C fire same concentration as Class A fire
Although HFC227ea is tested capable to extinguish fire under Class A, B & C, it
is not effective on the following:
Class A Deep seated fires.
Class D combustible metals.
Chemicals capable of auto-thermal decomposition.
Chemicals capable of rapid oxidation.
Enclosures with hot surfaces >400 C (>752 F).
Volume of Hazard
In order for the design concentration can be achieved and maintained, the
total flooding applications hazard area must be an enclosed space with nosignificant openings. In general, the design is based on an empty area. All
subsequent furniture, fittings or even the large equipment and cabinets
should not be considered in the design calculation as it has a little effect on
the actual concentration and as it is assumed that the internal area is
required to be flood with the agent.
Temperature of Hazard
The extinguishing agent required must be based on the anticipated minimum
ambient temperature in the hazard area. Precaution must be taken that the
calculated concentration for normally manned areas at the anticipatedmaximum ambient temperature in the area does not exceed the
NOAEL/LOAEL values as per the NFPA2001, sec tion 1.5 - Safety
Filled and pressurized cylinders should not be exposed to temperatures other
than the storage / operating temperature range of 0 to 50C (32F to 120F).
This also includes while being transport or storage.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
12/38
12
System Design Procedure
Kindly follow these procedures when designing HFC-227ea systems:-
Hazard analyses and survey of protected area.
Determine the required design concentration for the hazard.
Determine the hazard altitude level and correction factor. (Refer to
Table B)
Calculate the agent quantity to provide required design
concentration at minimum expected ambient temperature in
protected area.
Determine the cylinder size.
Determine the integrity of the protec ted area.
Loc ate nozzles.
Locate and design pipe work.
Check the percentage agent split at tees.
Identity all pipe lengths, rises, drops, and nozzle.
Note:For flow splits less than 30%, the split shall be done through a side teewith the smaller flow going through the side tee member. The minimum
flow through the side tee member is 10%. The maximum flow through the
tee is 90%. For the flow splits equal to or greater than 30%, the split shall be
done through a bull head tee. The maximum flow through a bull tee is
70%.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
13/38
13
Example: Tee Split Design Diagrams
a) Side Tee Split limits. B) Bull Tee Split limits.
90 70% 70 30%
30 70%
10 30%
c) Side Tee Orientation correct d) Side Tee Orientation incorrect
Correct Incorrect
Tee splits tee splits
e) Bull Tee Orientation correct f) Bull Tee Orientation incorrec t
Correct tee splitsIncorrect
Tee splits
NOTE: Incorrec t orientation of side and bull tee could result in separation of HFC-227ea from the Nitrogen(due to HFC-227ea greater density). The design would a lso be outside the parameters permitted by theca lculation software. Refer to diagram d) and f).
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
14/38
14
Design Calculations
The required agent quantity is based on the volume of protec ted area at the
lowest expec ted ambient temperature and concentration required. To
obtain the minimum agent quantity required, use the following equation:
W = (V/S) x ( C/100 C)
W = weight of Agent required
V = volume of protec ted area
S = spec ific vapour volume
S = 0.1269 + 0.000513 T
C = Required HFC-227ea Design Concentration (% by volume) at Design
Temperature (t).
T = Design temperature in protected area (C)
Design Example
Server Room: 6.3m x 6m x 2.5m(H) = 94.5m
T = 20C for calculation example
(7% required design c oncentration example only)
W = (94.5 0.1373) x (7 (100 -7) ) = 51.81kg
or
94.5m x 0.5483 (flooding factor) = 51.8kg
Note: Refer to table A for flooding factor.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
15/38
15
Table A HFC-227ea Total FloodingQuantity
Temp Specific Weight Requirements of protected space, W/V (kg/m3)
Vapour
Volume Design concentration (by volume)
T S
oC kg/m3 7% 8% 9% 10% 11% 12%
-10 0.1215 0.6169 0.7158 0.8142 0.9147 1.0174 1.1225
-5 0.1241 0.6064 0.7005 0.7987 0.8951 0.9957 1.0985
0 0.1268 0.5936 0.6858 0.78 0.8763 0.9748 1.0755
5 0.1294 0.5816 0.6719 0.7642 0.8586 0.955 1.0537
10 0.132 0.5700 0.6585 0.749 0.8414 0.936 1.0327
15 0.1347 0.5589 0.6457 0.7344 0.8251 0.9178 1.0126
20 0.1373 0.5483 0.6335 0.7205 0.8094 0.9004 0.9934
25 0.1399 0.5382 0.6217 0.7071 0.7944 0.8837 0.975
30 0.1425 0.5284 0.6104 0.6943 0.7800 0.8676 0.9573
35 0.145 0.5190 0.5996 0.6819 0.7661 0.8522 0.9402
40 0.1476 0.5099 0.5891 0.6701 0.7528 0.8374 0.9230
45 0.1502 0.5012 0.5790 0.6586 0.7399 0. 823 0.908
50 0.1527 0.4929 0.5694 0.6476 0.7276 0.8093 0.8929
55 0.1553 0.4847 0.5600 0.6369 0.7156 0.796 0.8782
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
16/38
7/27/2019 HFC227ea Engineering Manual
17/38
17
Table D Equi valent L ength
Diameter
(mm)
90 Elbow
(m)
45 Elbow
(m)
Thru Tee
(m)
Side Tee
(m)
Union
(m)
10 0.4 0.18 0.24 0.82 0.09
15 0.52 0.24 0.3 1.04 0.12
20 0.67 0.3 0.42 1.37 0.15
25 0.85 0.4 0.55 1..74 0.18
32 1.13 0.52 0.7 2.29 0.24
40 1.31 0.61 0.82 2.65 0.27
50 1.68 0.79 1.06 3.41 0.37
65 2.01 0.94 1.25 4.08 0.43
80 2.5 1.16 1.55 5.06 0.55
100 3.26 1.52 2.01 6.64 0.73
125 4.08 1.92 2.56 8.35 0.91
150 4.94 2.32 3.08 10 1.07
Equivalent length table for pipe fittings.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
18/38
18
INSTALLATION INSTRUCTIONS
GENERAL
Prior to installing the HFC-227ea fire suppression system, the installer must be
familiar with the system and have previous experience in installation ofgaseous suppression systems. The installer must refer to the piping and
instrumentation diagram and general arrangement drawings for the system
and c heck that all components are complete and in order. If the installation is
carried out by untrained or inexperience personnel, they may jeopardize the
integrity of the system, their own safety and of others as well as the warranty
of the system.
The instructions in this sec tion as well as information contained in thecomponent data sheets should be read by the installer.
The location of the cylinder bank shall have sufficient floor loading capability,a flat dry floor and walls or solid structures for securing the system. The owner /
client should satisfy themselves in this regard.
All necessary work permits & procedures shall be obtained / established firstto the satisfaction of the client, owner or the local authorities having
jurisdiction.
SAFETY
The HFC-227ea system is filled to a pressure of 25 bars at a reference
temperature of 20oC. The cylinders have the different sizes which could fill withdifferent quantity of agent. Safety precautions must be adhered to in the
handling of the HFC-227ea cylinders.
Some safety precautions to follow are: -
1) The transport cap shall always be screwed onto the cylinder whenever
the cylinder is moved, being loaded or unloaded.
2) Always use suitable lifting gear, (forklift, truck or hoist) when loading or
unloading cylinders. Do not offload the cylinders by dropping them to
the ground.
3) Use a suitable cylinder trolley to move the cylinders. Do not roll them on
the ground.
4) At site, if the cylinders are not to be installed immediately, store either
on their sides with wedges to prevent them from rolling or secure themusing ropes or belts in an upright position. The storage area must be dry
and in a place where they will not be damaged.
5) Do not remove the screwed cylinder transport cap from the cylinder
unless the cylinders are securely held in position by its clamps orbrackets.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
19/38
19
6) Never attempt to remove a cylinder valve from a pressurized cylinder.
7) Do not use extreme force (hammers, long levers, pipe wrench, etc.) on
any part of the valve or actuating components.
8) Cylinders, valves, and actuating components SHALL NOT BE drilled,
braised, welded, machined or stamped. The only permitted processes
are cleaning and painting of the cylinders.
9) In the event of any abnormalities such as jammed or deformed valves,
cracks or other apparent weaknesses, keep away and inform the
appropriate engineer.
10)Heavy protective gloves (preferably textile or leather) should be worn
at all times for the manual handling of cylinders to minimize the risk ofhand injury. During discharge, all connected parts of the cylinder and
valve are likely to bec ome very cold and there is a risk of "frostbite" if
any of the parts are handled at that time with unprotected hands,
particularly if hands are wet.
11)Safety footwear shall always be worn at all times.
HFC-227ea System Installation Procedures
1) The following drawings and instructions should be as a minimum bein the possession of the installer :-
a) P & I Diagram
b) Piping Isometric
c) Piping Plan
d) Cylinder Bank Assemblye) Electrical Wiring Diagram
f) Installation Procedures, this sec tion.
g) Material List
Material Preparation.
a) Prior to carrying out the assembly and installation, check that all
the required materials have arrived at site and they are in good
condition.
b) Ensure that the protected areas and cylinder storage areas
matches the drawings in layout and size. Inform the projec t
manager of any discrepancies.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
20/38
20
Transport and Storage of Materials
The cylinders must be fitted with transport caps whenever they are moved or
when they are not connected to the manifold.
When the cylinders and associated equipment arrive on site, they shall bestored in a dry room within a temperature range of 0oC and 50oC until they
are needed for installation.
When storing the cylinders, secure them so that they cannot fall or roll.
Avoid exposing the cylinders from sunlight and heat.
NOTE:
The cylinders must not be dropped or rolled when transporting or moving
them. A suitable trolley should be used to move the cylinders.
Installation of the low pressure pipe distribution network
The low pressure pipe network begins after the manifold. The pipes used shall
be Sch. 40 ASTM A-106A or other equivalent standards which can
accommodate the maximum pressure calculated in the network. Refer to
table E.
1) Piping should be installed in accordance with good commercialpractice. Screwed pipe should be cleaned of oil and swarf.
Screwed joints should be sealed using PTFE on the male threads.
Care should be taken to avoid possible restrictions due to foreign
matter, faulty fabrication or improper installation. The piping system
should be securely supported with due allowance for agent thrustforces and thermal expansion/contraction, and should not be
subjected to mechanical, chemical, vibration, corrosion or other
damages. Where explosions are likely, the piping system should be
attached to supports that are least likely to be displaced. A
galvanized steel pipe is recommended as they are less likely to
corrode within a short period of time. If rust flakes or particles arepresent within the pipe, they may come loose during a discharge
and may be able to block off the orifices in the nozzles thus
jeopardizing the release. Also the rust c loud / spray may ruin the
ceiling tiles, or may damage sensitive equipment within the
enclosure. Special coatings or corrosion resistant materials must be
used in corrosive environments.
2) After installation of the pipe work it is recommended to flush the
pipe work in order to remove dirt / particles, sealing material,
cutting burrs, etc. as well as to verify that flow is continuous and
that the piping is unobstructed. Flushing should be performed priorto the pressure testing of the pipe work and after any rectification
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
21/38
21
work on the pipe network. If water is used for flushing, ensure that
the pipe work is blown dry to minimize internal corrosion of the
piping. If gaseous media is used, (compressed air, nitrogen, etc.)
ensure that the pipe work has not been sealed off in any way.
Make sure that no one is in any of the rooms in which the pipe workis to be flushed. Where necessary, filter bags should be used to
collect any dirt or particles being blown out of the pipe work
espec ially if there is equipment in the room.
3) The pipe work should be leak tested prior to installing the discharge
nozzles. Leak testing of the distribution pipe work should be carried
out as follows :-
a) Verify that all manifold check valves are fitted onto themanifold. Plug off the nozzle points using suitable plugs.
b) Connec t the nitrogen test supply cylinder assembly to the
manifold.c) Make sure that no one is in any of the rooms in which the
pipe work is to be tested.
d) Slowly pressurize the distribution pipe network to 3 bar.
e) Check the pipe network for leaks. If there are no leaks,proceed to pressure test the pipe work to 3 bar for about 10
minutes. Any pressure drop should not exceed 20% of the
test pressure.
f) Release the pressure slowly after testing.
g) If rectification work was carried out, flush the pipe works first
prior to pressure test the pipe work again.
The following tables show the maximum allowable pressure (psi) for steel pipe
with threaded end connection as well as rolled grooved or welded end
connections.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
22/38
22
Table E
Maximum Allowable Pressure (psi) for steel pipe with threaded end
connections
Schedule Nom. Wall Grade A-106C A-53BA-53B A-53A
Pipe A-106B A-106A
Size Thickness Type Seamless Seamless ERW Seamless
40 1/2" 0.109 2593 2222 1896 1778
3/4" 0.113 2234 1915 1634 1532
1" 0.133 2026 1736 1482 1390
11/4" 0.140 1782 1528 1304 1222
11/2" 0.145 1667 1429 1220 1144
2" 0.154 1494 1280 1093 1025
21/2" 0.203 1505 1193 1100 1032
3" 0.216 1392 1096 1018 954
4" 0.237 1278 1022 935 876
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
23/38
23
Table F
Acceptable Fittings Maximum Pipe Size
Class 300 malleable/ductile iron up to 3" NPS1,000-lb rated ductile iron / forged steel > 3"
Class 300 flanged joints All
Source: NFPA2001 - 2004 Edition
Note: Other fittings manufactured to equivalent standards / codes can be
used so long as they can withstand the working pressure.
Installation of the Discharge nozzle
1) Install the appropriate nozzles with the correc t orifice sizes in their
designated locations as per the piping isometric drawing & plan.
2) Screw the discharge nozzles into their fittings, using PTFE tape to
make a tight seal. Use a spanner to make the nozzles hand tight.
A. Miscellaneous1) Install the entrance warning signs on all entry doors into the
protected area.
2) Install the manual release warning signs adjacent to the cylinder
equipped with the manual release.
3) Check the integrity of the protected area for excessive openings
which could result in unacceptable leakage of the c lean agent.
NOTE 1: A fan integrity test may be used to ascertain the integrity ofthe enclosure.
NOTE 2: A discharge test is usually notencouraged for HFC gases todetermine the performance of the system.
4) Check the interconnections between the actuation device and
the control panel, as well as the pressure switches and the audio &
visual alarms plus equipment and ventilation systems shutdown.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
24/38
24
Pipe Hangers/Support
The maximum distance between hangers/support should not exceed the
distances as stated in table G. Piping shall be sec urely supported using solid
supports, giving due allowance for thrust forces and thermal expansion and
contrac tion and should not be subjected to mechanical, chemical, vibrationor other influence unless special prec autions are made.
Adequate hanger/support shall be provided for nozzles and their reactive
forces such that in no case shall the distance from last hanger/support be
more than 300mm.
Table G Hanger Spacing
Pipe Size
(mm)
Maximum Spacing
(m)
10 1
15 1.5
20 1.8
25 2.1
32 2.4
40 2.7
50 3.4
65 3.5
80 3.7100 4.3
150 5.2
Electrical Clearance
When exposed electrical conductors are present in the protected enclosure,
safety clearance no smaller than those listed in Table H shall be provided,
where practicable between electrical conductors and all parts of the systemthat may be approached during maintenance. Where these clearances
cannot be achieved, warning notices shall be provided and a safe system of
maintenance work shall be adopted.
Minimum clearance from any on or about the permanent equipment where
a person may be required to stand (measure from the position of the
feet).Section clearance to the nearest unscreened live conductor in air.
Ground clearance to the nearest part not at earth potential of an insulator
supporting a live conductor.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
25/38
25
Table H Safety Clearance
Maximum Rated
Voltage
(KV)
Minimum Section
Clearance
(m)
Minimum Ground
Clearance
(m)15 2.6 2.5
33 2.75
44 2.9
6 3.1
88 3.2
110 3.35
132 3.5
165 3.8
220 4.3275 4.6
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
26/38
26
System Operation
General
The SRI HFC-227ea fire suppression system must be used in conjunction with a
detection and control system in order for the extinguishing system to operateautomatically. Some issues must be addressed before deciding on the bestdetection system. They are:-
a) the speed of detection required
b) what phenomenon to detect, e.g. Smoke, heat, flame, gas, fuel mist,
etc.
c) Relative acceptability of unwanted alarms
d) Cost effectiveness
Generally, all gaseous extinguishing systems requires a detection and control
system to operate automatically. Detectors are needed to sense the fire,while the control system would give the signal to all visual & audio alarms,
shutdown auxiliary equipment, and activate the suppression system.
Detection Speed
A gas extinguishing system's speed of extinguishment is usually moredependant on the response time of the detection system, rather than the
discharge time of the gas. There is a wide variety of detec tion and controltechnologies available in order to cover the different types of fire risks.
However, the technologies differ greatly in cost, and as such it is important to
select a system that offers the client the optimum and cost-effec tive fire
protection system.
Types of Detectors
The types of detectors commonly used in gaseous fire extinguishing systems
are smoke detectors and heat detectors. For certain special hazards, flame
detectors and gas detectors are used.
Smoke detectors are available in several types, optical, aspirated and air
aspiration system. The first two types are widely available at reasonable prices
and are c ommonly used. Aspirated type is slightly more expensive but their
response time is faster. For an even faster response time an air aspiration
system can be used. However, they are much more expensive and are moresuited for clean room environments. Generally, the more sensitive the
detec tors, the more prone they are to false alarms.
Heat detectors are normally available in 3 types, rate of rise (ROR), fixed
temperature or a combination of both ROR and fixed temperature. Heat
detec tors are less prone to false alarms and are cheaper compared to smokedetectors. However, in most cases, a fire may well be underway before the
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
27/38
27
heat detector operates. In high risks or sensitive areas using a gaseous
extinguishing system, the delay of a heat detector would cause fire damages
which might be unacceptable to the client.
Flame detectors are employed where flammable liquids or powders are
present since fires spread very rapidly. Flame detectors are available in 2types, ultra-violet (UV) and infrared (IR) flame detec tor. UV flame detector
respond faster compared to the IR flame detector. UV detectors can be
blinded by dirt or grease while IR detectors can be blinded by water.
Consideration must be given to incorporate a monitoring system on these
detec tors to give a fault alarm if they are blinded.
Detector Spacing
Currently, there is no one internationally recognized standard for detector
spacing therefore the detec tor requirements shall be based on the respective
countries' standard or as required by the loc al authority having jurisdiction.
There is a general consensus that while the detec tors used for fire alarms can
be installed at its maximum area coverage, those used for triggering gas
suppression systems should be reduced or halved. This is bec ause detectorsinstalled at the maximum approved spacing for fire alarm use could result in
excessive delay in agent release, especially when more than one detection
device is required to be in alarm before automatic actuation results.
Detector Location
Detec tors should be placed in a protected enclosure with the following aims:
1) to give the detectors the best chance to detect a fire quickly, and
2) to reduce the risk that the detec tors give a false alarm.
To make sure that the detec tors can sense a fire, do:-
1) locate them at least 1 m from all obstructions.
2) assure a free passage of smoke to the detectors. Install detectors in a
cable floor as well as the main room if the cable floor should also beprotected.
3) evaluate the impact of the ventilation systems on detectors; they
sometimes either prevent the smoke reaching the detection chamber
or else contaminate detectors in air currents with dust.
Conventional detectors should be installed in crossed zones, where each
zone is made up of detectors installed diagonally to each other. In any case
a minimum of two detec tors must operate before the gas is released
automatically.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
28/38
28
Typical Sequence
The following is a typical sequence of events (details may vary according to
local prac tice or regulations):-
a) A detector goes into alarm
b) Visual and audible pre-alarm is given
c)The ventilation system is automatically switched off
d) A second detec tor goes into alarm, confirming the fire condition.
e) Visual and audible fire alarm is given and the time delay is started.
f) Any automatic closing of doors or openings is initiated.
g) After the preset delay, a signal is sent to the elec tric actuator to
release the gas.
h) A visual alarm is given, indicating the release of the gas.
Other possible events which could alter this sequence are:
a)The release signal may be manual; it will have the same effect as the
second (confirmation) detection signal.
b)There might be an Abort or Hold switch to prevent a discharge, forexample when people are present in the enclosure.
All control panels normally would have a fac ility for adjusting the time delay
but the range may vary from 0 60 seconds depending on the local
requirements.
It is not the intention of this sec tion to recommend any particular makes of
detec tors and control systems since each countries have their own standards
and regulations. As such, the proposed detec tion and control system shall
have the approval of the Local Authority having J urisdiction.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
29/38
29
Condition During a Fire
The users fire and safety instruction to personnel should include advice on theconditions prevailing during the discharge on a HFC-227ea system. This
advice is intended to prepare the personnel for the situations likely to arise
and therefore minimize the risks of panic. Three major conditions prevailduring HFC-227ea systems discharge of which personnel should be made
aware:
HFC-227ea Concentration
HFC-227ea total flooding systems greater than 9% design conc entration
should only be used with manual actuation in normally occupied areas. A
normally occ upied area is defined as an area intended for occupancy.
Any area protected by HFC-227ea system should be evac uated prior to startof system discharge. Where egress of normally occupied areas cannot be
accomplished within one minute, HFC-227ea total flooding systems shall be
designed not to exceed 9% concentration.
Refer to NFPA 2001, clause 1.5.1.2 for additional information.
HFC-227ea Decomposition
HFC-227ea decomposes when exposed to temperatures exceeding 482C.
The rate of this decomposition is dependent upon the size of the area whereextreme temperatures are found, and also upon the length of HFC-227ea
exposure time.
To avoid decomposition, the HFC-227ea systems are designed to discharge
and extinguish the fire quickly. (NFPA 2001, clause 5.7.1.2 Discharge time)
Hydrogen Fluoride is the most toxic decomposition product. This materialgenerates a sharp acrid odour, which is easily detected and acts as a
warning and a good safeguard to personnel.
HFC-227ea Discharge Condition
HFC-227ea has a low boiling point; consequently the discharge is very cold at
the point where it leaves the nozzle. Care should be taken to avoid working
within 1 meter of HFC-227ea discharge nozzles.
The velocity of discharge of HFC-227ea from a discharge nozzle is very high,
care should be taken to insure that objects which may become dangerousprojectiles are secured or removed from the protected area.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
30/38
30
Actions Following a Fire
General
These notes are only applicable to the protected area(s) protec ted by a
HFC-227ea fire extinguishing system. Where such a system may form part of,or combine with other forms of fire protection systems then composite
instruction for all systems are necessary to ensure the safety of personnel and
property following a fire. The organization will have appointed, or nominated,a responsible person to act as a Fire Officer or Safety Officer to look after
the safety issue. Actions following a fire should be coordinated and/or
direc ted by the officer.
Ac tions Immediately Following a Fire
These ac tions should, at a minimum, include the following:
Advise the Fire Brigade or police if appropriate.
Organize a roll call of employees and any visitors.
Prevent unauthorized personnel from entering the protected area.
In the case of deep seated fires, the protected area should be kept
tightly closed for at least 60 minutes after discharge of HFC-227ea
extinguishing agent. It is important that the fire be completely
extinguished before ventilating the area. Before permitting any one toenter the area, ventilate thoroughly or ensure self-contained breathingequipment is used.
Do not enter the protected area in which fire has been extinguished
with an open flame or lighted cigarette as the possible presence of
flammable vapours may cause re-ignition or explosion.
Should it be necessary to enter a area containing HFC-227ea or
decomposition products the following precautions should be taken;
Use a fresh air mask or self contained breathing equipment.
Do not use a filter mask or canister type mask.
Do not enter area unless you are under observation from outside the
area, or tethered by a lifeline.
Ensure that all pressurized equipment is isolated or safe from release.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
31/38
31
TESTING AND COMMISSIONING
PRE - COMMISSIONING CHECK LIST
1) Check that all pipes and fittings are in accordance with the
correc t specifications as shown on the General ArrangementDrawings. Chec k that the systems are installed in
accordance to the drawings. Any deviations from the
original design should be incorporated into "As Built". Check
that all remedial works (if any) have been completed.
2) Check that all discharge nozzles with the appropriate orifice
size are fitted in their designated locations.
3) Check all pipe supports and brackets to ensure that the
system pipe work is firmly sec ured in position.
4) Check all cylinder supports and brackets to ensure that the
cylinders are firmly secured in place.
5) Check all fittings and hoses are tightened and secured.
6) Check the cylinder pressure. The pressure may vary
depending on the ambient temperature.
COMMISSIONING PROCEDURES
Testing the ac tuation of the system can be broken down into 2 separate
functional tests; electrical and mechanical.
WARNING:BEFORE CARRYING OUT ANY FUNCTIONAL TESTS, MAKE SURE THAT THEACTUATION DEVICE IS REMOVED FROM THE CYLINDER VALVE.
Electrical Actuation
1) Make sure that the actuation device is disconnected from the
valve.
2) From the control panel, initiate a fire condition. This will start a time
delay prior to simulate a 24V DC output to the actuation device
connection. Depending on the local authority requirements the
delay can be adjusted at the control panel from 0 to 60 seconds.
Normally the delay is set at 30 sec onds.
3) Use the multi meter to measure if there is 24V DC output from the
panel. Make sure to reset the control panel first prior to connecting
the actuation device again.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
32/38
32
Mechanical Actuation
1) The manual / pneumatic ac tuator is fitted to the top of the
cylinders valve.
2) Pull the safety pin out and operate the manual release lever.
NOTE: ONCE THE TESTING AND COMMISSIONING HAS BEENCOMPLETED, REINSTALL THE ACTUATION DEVICE BACK ONTO THECYLINDERS VALVE.
Commissioning Forms and Certification
The Testing and Commissioning forms / checklist and Acceptance report shallbe duly completed, and all necessary signatories obtained. A copy is to be
given to the relevant party.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
33/38
33
Testing and Commissioning Check List for HFC-227ea System. (Sample)
Item Description Yes No Remarks
Piping
1 Check that the correct pipe schedule
and fittings were used. Refer to
isometric drawings for spec ifications.
2 Check that the pipe routing and size
correlate with the pipe plan and piping
isometric drawings. Any major
modifica tions to be noted and handed
over to the project engineer for
verification of calculation.
3 Check that the piping network aresecurely fastened to a solid and stable
structure using appropriate supports.
Check that all bolts are tighten properly.
4
Check that the piping network has
been flushed / dried out and pressure
tested. Test report to be issued by
the installer.
5 Check that all discharge nozzles are
Installed securely and are notobstructed.
Verify that each nozzle with the correc t
orifice size is installed at the correc t
location as per piping isometricdrawing.
Cylinders
6
Check that the number, their volume
and filling pressure correspond with the
project specification
7 Check that they are not damage, the
Paint has been repaired.
8Check that the wall brackets aresecurely fastened to a solid and stable
structure. Check that all bolts are
tighten properly.
9 Check that all cylinder clamps are
mounted properly and all bolts are
securely fastened.
10 Check that each cylinder has been
labeled and the label has been filled
correctly.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
34/38
34
Item Description Yes No Remarks
11 Check that the cylinder transport caps
are available for transport of the
cylinders for refilling.
Manifolds
12 Check that the manifold arrangement is
ac cording to drawings.
13 Check that the manifold brackets are
securely fastened to a solid and stable
structure. Check that all bolts are
tightened properly.
14 Check that the manifold is securelyfastened to the brackets.
15 Check that the manifold assembly is
securely fitted to the distribution pipe
network.
Accessories
16 Check that the discharge hose(s) has a
smooth bending, are not stretched,
compressed or kinked.
17 Check that the discharge hose(s) has
been securely fixed onto the discharge
valve outlet and at the manifold check
valve.
18 Check that pressure on each cylinder
is within the acceptable range.
19
Check that the pressure gauge
orientation is correct, i.e. The dial gauge
face is facing outwards.
20
Check that the pneumatic actuating
hoses are connected properly to
the pneumatic actuators on each
slave cylinders. Tighten using a spanner
until it stops.
21
Check that there is a plug installed on
the pneumatic actuator at the last slave
cylinder to close the actuating line.
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
35/38
35
WARNING :
BEFORE CARRYING OUT ANY FUNCTIONAL TESTS, MAKE SURE THAT
THE ACTUATION DEVICE IS REMOVED FROM THE CYLINDER VALVE.
Item Description Yes No RemarksAccessories
22 Check that the actuation device
wiring is properly terminated.
23 Check the function of the manual /
pneumatic actuator if fitted. Replace the
seal tag a fter completion of test.
Room / Enclosure
24 Verify the room sizes, compare actual
volume with project information. Seevolume input used in the calculation.
25 Verify that vents / pressure relief
arrangement where required is installed
in accordance with system requirements.
Check against results from flow
calculation information or calculations
based on the room integrity test / door
fan test.
26
Ensure that the room(s) has been cleaned
up.
General
27 Ensure that all doors into the protected
area has been provided with a warning
label / signage.
28 Ensure that the operating instructions
has / will be given.
29 Ensure that the operation and
maintenance manual has / will be given.
Commissioning Engineer's Name : Signature :
Installer / Contractor's Name : Signature :
Completion Date :
Client :
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
36/38
36
HFC-227ea FIRE SUPPRESSION SYSTEM
CERTIFICATE OF INSTALLATION, COMMISSIONING AND ACCEPTANCE (SAMPLE)
CLIENT :
SITE ADDRESS :
WORK UNDERTAKEN :
CONTRACT NO :
We hereby certify that in carrying out this work the methods, materials andcomponents used comply with the specifications and standards as listed in thecontract.
Other than the deviations listed below :-
Design Concentration :
Fan Test Result : PASSED FAILEDNOT
APPLICABLE
All commissioning procedures as per checklist have been carried out.
Commissioning Engineer's Name : Signature :
Installer / Contractor's Name : Signature :
Date :
We confirm that the work has been carried out to our complete satisfaction and is
accepted in good working order. A copy of the Operation and Maintenancemanual, as-built drawings and operating instructions have been supplied and
received.
Client's Representative Signature :
Name and Position :
Date :
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
37/38
37
MAINTENANCE
The system shall be maintained on a regular basis, at least on an annual basis
or as otherwise spec ified by the loc al authority having jurisdiction.
Maintenance of the system shall include the following:-
A. Protected Area / Enclosure Check1. Survey the protec ted area to verify that it has not changed from
what the system was designed to protect. While surveying, look
for different fuels, new equipment, blocked open doors or
dampers, new penetrations or gaps which may lead to loss of
the hazard integrity, etc.B. Discharge Nozzles
1. Check all nozzles to make certain they are in place and have
not been tampered with. Check the nozzles for corrosion or
damage, and that they are not obstructed internally or
externally.C. Distribution Pipe Network
1. Check the condition of the piping to make certain that it is
properly secured in the hangers, the brackets are not loose andall fittings are connected tightly.
D. Signage1. Check all warning nameplates throughout the area. Ensure that
they are in place, mounted securely, readable and are not
damaged.
IMPORTANTPrior to carrying any maintenance on the system, the system should be
inhibited electrically by the control panel (if available). For multiple cylinders
system, the actuating hose must be disconnected from the slave cylinder.
Thereafter, remove the actuation device from the master cylinder. For single
cylinder systems, proceed to remove the actuation device once the system
has been inhibited electrically if so equipped. (Ref. Fig. 7.5 - (7) for details)
E. Cylinders check1. Chec k the cylinder bracketing. Ensure that the cylinders are
secured in the brackets. Check for corrosion, damage or missingcomponents. For the packaged type, check the frame and
plates for damage or corrosion as well as loose or missing
components.2. Check the condition of all cylinders. Check for signs of damage
or corrosion and check the c ylinders' last hydro test dates.(NFPA 2001 states "Cylinders continuously in service without
discharging shall be given a complete external visual inspection
every 5 years or more frequently if required. The visual inspec tion
shall be in accordance with Compressed Gas Association
Pamphlet C-6, Section 3; except that the cylinders need not be
emptied or stamped while under pressure").
PDF created with pdfFactory trial version www.pdffactory.com
http://www.pdffactory.com/http://www.pdffactory.com/http://www.pdffactory.com/7/27/2019 HFC227ea Engineering Manual
38/38
3. Check storage cylinder pressure gauge and ambient
temperatures; compare this pressure to the temperature
correction chart to determine temperature corrected pressure.
If the cylinder correc ted pressure shows a pressure loss of more
than 10%, the cylinder should be removed for weighing, allmeasurements and actions shall be recorded.
F. Components CheckMake a visual inspection of the systems components, distributionpiping and nozzles. Check the immediate vicinity of all
equipment to ensure that no accidental damage or tampering
has occurred.
G. Specialized Maintenance DutiesCylinder Hydrostatic Pressure Testing
Providing cylinders are submitted to a full external inspec tion
every 12 months from the date of introduction, the allowable
interval period before the first periodic inspection and
hydrostatic pressure test is 20 years.
Any cylinder that is discharge between 10 years and 20 years of
being introduced into service shall be submitted to a full
periodic inspection and a hydrostatic pressure test before being
refilled. The interval between the first and second periodicinspection and hydrostatic pressure test may not exceed 10
years. Subsequent retests are not to exceed 5 years. (NFPA
2001)
Finally
Carry out a final visual inspection of the system and the
protected area to ensure that all equipment has been
reinstalled and reconnected properly. Ensure that any
associated control/indication panel is displaying normal
operation. Complete the maintenance log book, recording
work carried out and parts used. Inform the responsible personthat the work is complete and that the system is back on
operation mode.