Henrik Bacher Elomatic

Embed Size (px)

Citation preview

  • 8/10/2019 Henrik Bacher Elomatic

    1/35

    C O N S U L T I N G & E N G I N E E R I N G

    How to Choose and Integrate Best

    System that Fulfills Your Requirements

    Henrik BachrVP Consulting & Engineering

    Elomatic Oy

    www.elomatic.com

    4th Ballast Water Management Summit

    11-12.4 2011, Amsterdam, The Netherlands

  • 8/10/2019 Henrik Bacher Elomatic

    2/35

    C O N S U L T I N G & E N G I N E E R I N G

    Objectives of the presentation

    General overview of BW treatment technologies, system selection and

    installation considerations

    Focus on retrofits;

    - the choise of system is more challenging in retrofits

    - many key considerations are applicable for NBs just as well.

    - in NBs however this is one system out of several to be designed and

    installed, the degrees of freedom are higher, shipyard responsibility

    Neutral approach, no supplier preference nor technology ranking

  • 8/10/2019 Henrik Bacher Elomatic

    3/35

    C O N S U L T I N G & E N G I N E E R I N G

    Marine Mechanicaldesign

    Processindustry

    CADMATIC3D

    software

    A multidisciplinaryconsultancy &engineering company

    Finnish, privatelyowned

    Abt. 650 employees

    11 Offices in 5countries

  • 8/10/2019 Henrik Bacher Elomatic

    4/35

    C O N S U L T I N G & E N G I N E E R I N G

    Marine

    From conceptual development to detail design of all disciplines

    From cruise vessels to working craft

    From newbuildings to conversions and

    retrofits

    Our clients include shipowners,

    operators shipyards, equipment

    suppliers and many more in the

    maritime cluster

  • 8/10/2019 Henrik Bacher Elomatic

    5/35

    C O N S U L T I N G & E N G I N E E R I N G

    Contents

    1. General considerations and challenges

    2. BWT technology

    3. Vessel specific considerations and

    indicators

    4. The process of choosing solutions

    5. The role of design & engineering

    6. Installation aspects

    7. Conclusions

    1. General considerations and challenges

    2. BWT technology

    3. Vessel specific considerations and

    indicators

    4. The process of choosing solutions

    5. The role of design & engineering

    6. Installation aspects

    7. Conclusions

  • 8/10/2019 Henrik Bacher Elomatic

    6/35

    C O N S U L T I N G & E N G I N E E R I N G

    Why do we need BW treatment? What is behind the

    convention ?

    S.Saesmaa/ Finnish Environmental Institute

  • 8/10/2019 Henrik Bacher Elomatic

    7/35

    C O N S U L T I N G & E N G I N E E R I N G

    General considerations and challenges

    Each ship is unique and should be dealt with as such

    This is a must; investments are inevitable (return on investments?)What makes the BW treatment system topic so special

    Amount of ships to be dealt with; up to 70.000

    Number of questions mark concerning the convention and

    interpreatations + regional/local requirements (US)

    Technology, installation and operational challenges

    This is no rocket science

  • 8/10/2019 Henrik Bacher Elomatic

    8/35

    C O N S U L T I N G & E N G I N E E R I N G

    General considerations and challenges

    Special vessels; practical solutions for a.o. barges, semisubmersibles, dredgers

    etc. are needed

    Industry tendency; leave the retrofit to the last minute to be sure of what to doand a (false) expectation for a broader competition and thus lower prices

    Critical issues;

    - equipment supply

    - engineering capacity

    - installation capacity

    Abt. 20 retrofits/day during the coming years

    Ships to be converted

    Year 2012 2013 2014 2015 2016 2017 2018 2019No of ships 1700 3000 3000 6000 6000 16000 14000 14000

    Tankers > 100.000 tdw existing abt. 1400

    NB's abt. 500

    Bulkers > 100.000 tdw existing abt. 750

    NB's abt. 700

  • 8/10/2019 Henrik Bacher Elomatic

    9/35

    C O N S U L T I N G & E N G I N E E R I N G

    The BWM Convention Regulation B-3

    Built BW m 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

    < 2009 1500-

    5000

    < 2009 5000

    2009 5000

    2012 >5000

    D1/D2D1/D2 D2D2

    D1/D2D1/D2 D2D2

    D2D2

    D1/D2D1/D2 D2D2

    D2D2

    Source TraFi

    D-1 standard; BW exchange

    D-2 standard; BW treatment

    First intermediate or renewal survey after theanniversary date of delivery of ship, whichever first

  • 8/10/2019 Henrik Bacher Elomatic

    10/35

    C O N S U L T I N G & E N G I N E E R I N G

    BW treatment technology

    Abt. 50 manufacturers of BW technologies on the market

    11 systems are approved under the IMO G8 (no active substances)

    27 systems have basic approval according to G9 (active substances)

    18 systems have final G9 approval

    Type approval by flag administration 12 systems at least

    Additional 3 applications for basic and final approval which could not be handled

    in MEPC 61 will be handled in MEPC 62 (July 11 -15, 2011) and additional

    applications and approvals are expected during 2011

    MEPC 62 will focus on ships with BW capacity > 5000 m3

    MEPC 62 will approve guidelines for other methods as well as upscaling of

    systems

  • 8/10/2019 Henrik Bacher Elomatic

    11/35

    C O N S U L T I N G & E N G I N E E R I N G

    BW treatment technology

    - Mechanical filtration (28)

    - Hydrocyclone (3)

    - Chemical enchantment (coagulation/flocculation)

    - Mechanical filtration (28)

    - Hydrocyclone (3)

    - Chemical enchantment (coagulation/flocculation)

    Disinfection

    Physical pretreatment and solid/liquid separation

    Residual controlResidual control

  • 8/10/2019 Henrik Bacher Elomatic

    12/35

    C O N S U L T I N G & E N G I N E E R I N G

    BW treatment technologySource IMO

    G9

  • 8/10/2019 Henrik Bacher Elomatic

    13/35

    C O N S U L T I N G & E N G I N E E R I N G

    Source IMO

    G9

  • 8/10/2019 Henrik Bacher Elomatic

    14/35

    C O N S U L T I N G & E N G I N E E R I N G

    Source IMO

    + RWO CleanBallast, Unitor BWTS

  • 8/10/2019 Henrik Bacher Elomatic

    15/35

    C O N S U L T I N G & E N G I N E E R I N G

    BW treatment technology

    Combinations of technologies are also adopted

    Supplier focus on various capacity ranges (100 7000 m3/h, even >10.000m3/h)

    Serial or parallel installation to increase capacity

    Modular solutions/distributed equipment

    Operational modes

    - ballasting, ballasting & discharging, filter bypass on deballast, during voyage

    - neutralization of chemicals prior discharge

    Operational costs- major factor for most systems; power (large consumers are eg. elctrolytic and

    advanced oxidation processes)

    - chemical systems; chemicals

  • 8/10/2019 Henrik Bacher Elomatic

    16/35

    C O N S U L T I N G & E N G I N E E R I N G

    Installations and experience

    Abt. 350 systems sold/installed

    Abt. 200 vessels, mostly NBs

    Retrofits limited, abt. 10 % of the sold/installed systems

    Retrofits include ao. car carriers, bulkers, tankers, passenger vessels,

    container vessels, special craft

    Several systems (suppliers) have accumulated running hours and someexperience have been gained

  • 8/10/2019 Henrik Bacher Elomatic

    17/35

    C O N S U L T I N G & E N G I N E E R I N G

    Which BWT solution for my ship ?

    The ideal objective: max benefit to lowest

    (overall) cost

    Each ship is individual

    There exists no standardized general best

    solution

    A thorough system comparison and

    consequence analysis is the starting point

  • 8/10/2019 Henrik Bacher Elomatic

    18/35

    C O N S U L T I N G & E N G I N E E R I N G

    General considerations in selecting BWT solutions

    Ship type & size

    Tanker , bulker, container, car

    carrier , passenger etc.

    Ship type & size

    Tanker , bulker, container, car

    carrier , passenger etc. Trading pattern, routes

    World wide traffic, short sea shipping,regular line service, operating areas

    (seas)

    Trading pattern, routes

    World wide traffic, short sea shipping,regular line service, operating areas

    (seas)

    Operational aspects

    Reliability, safety, servicerequirements

    Operational aspects

    Reliability, safety, servicerequirements

    Economical aspectsInitial capex, operational costs

    Economical aspectsInitial capex, operational costs

    Technical aspects

    Physical, material

    Technical aspects

    Physical, material

    Performance, ballast needs

    Capacity and flow rate requirements

    Performance, ballast needs

    Capacity and flow rate requirements

    Compliance!

  • 8/10/2019 Henrik Bacher Elomatic

    19/35

    C O N S U L T I N G & E N G I N E E R I N G

    Technical/operational considerations and key aspects

    Performance considerations

    Required time to be effective

    Performance considerations

    Required time to be effectiveCapacity

    Ballast pumping and treatment rates

    Capacity

    Ballast pumping and treatment rates

    Maintenance

    Crew training and workload

    Accessibility

    Maintenance

    Crew training and workload

    Accessibility

    Power requirements

    Additional need, existing capacity

    Power requirements

    Additional need, existing capacity

    Technology

    Footprint , weight, gas safeequipment

    Technology

    Footprint , weight, gas safeequipment

    Existing BW system

    No of systems, integration

    Existing BW system

    No of systems, integration

    Installation aspects

    Alterations in existing structures

    Component location flexibility

    Installation aspects

    Alterations in existing structures

    Component location flexibility

    Corrosion

    Tanks, material selection

    Corrosion

    Tanks, material selection

  • 8/10/2019 Henrik Bacher Elomatic

    20/35

    C O N S U L T I N G & E N G I N E E R I N G

    Technical issues

    Examples of technical matters needed to be worked out in close cooperation

    between all parties

    - bypass options (emergency if the BWT inoperable)

    - backflushing filters

    - vent lines from the BWT system (termination on deck or in the engine

    room spaces depending on gas to be ventilated)

    - ballast pump capacity and powering requirement (av. 30 40 % increasein demand)

    - use of alternative piping materials (class issue)

    - corrosion risks (material issues, coatings)

    - sampling ports- Safe Return to Port issues

  • 8/10/2019 Henrik Bacher Elomatic

    21/35

    C O N S U L T I N G & E N G I N E E R I N G

    Technical issues cont.

    Special tanker considerations

    - fore and aft BW systems

    - pipes from BW tanks adjacent to cargo tanks not into the engine room- on deck installations currently under discussion (pump head requirements

    increase)

    - limitations of electrical components in the cargo pump room (except for

    explosion free lights) pre/ post 2007, zone 1 (IEC 60092 502)- possibility to re-class hazardous area from pre to post 2007 standards

    - BW pump capacity, 10.000 m3/h or more

  • 8/10/2019 Henrik Bacher Elomatic

    22/35

    C O N S U L T I N G & E N G I N E E R I N G

    Automation, control and monitoring

    - BWT system requirements

    - automation and control equipment for monitoring and adjusting treatmantdosages and/or intencities

    - a continuous self-monitoring function during the period in which the system

    is in operation

    - recording of functioning and failure + data storage- alarms

    - audible and visual alarm signals in all stations from which BW

    operations are controlled in case of system failure

    - visual alarm whenever the BWT systemis in operation for purposes ofcleaning, calibration, or repair

    - by pass alarm in case of emergency bass pass activation

  • 8/10/2019 Henrik Bacher Elomatic

    23/35

    C O N S U L T I N G & E N G I N E E R I N G

    Automation, control and monitoring

    - control system location options

    - local panel- ECR

    - CCR

    - integration to existing automation and/or BW systems,

    - operation and control

    - alarms

  • 8/10/2019 Henrik Bacher Elomatic

    24/35

    C O N S U L T I N G & E N G I N E E R I N G

    The solution evaluation processScore sheet System A B C D

    Operation Principle Filter Filter Filter Electro-

    UV UV Cl lysis

    Score scale: 0-10,

    10 being the best Weight factor

    Performance and capacity

    Purification

    Filter min. particle size (m) 0,1 4 8 6 10Disinfection performance (technology) 0,3 9 9 7 9

    Zoo plankton [per/ m3] (limit 10) 0,2 6 8 6 6

    Photyplankton [per/ml] (limit 10) 0,2 6 8 6 6

    Vibrio Cholerae [per/100ml] (limit 1) 0,1 6 10 6 6

    Escherichia col i [per/100ml] (lim it 250) 0,1 6 10 6 6

    Intestinal Enterococci [per/100ml]

    (limit 100)

    0,1 6 10 6 6

    Total 7,3 9,7 6,9 7,9

    Process

    Flow rate per unit and maximum flow 0,5 8 9 7 6

    Energy consumption (kw/m3) 0,6 10 5 7 8

    Chemical consumption (mg/l) 0,7 10 10 5 10

    Pressure loss [bar] 0,5 4 4 7 10

    Working pressure 0,1 5 6 6 6

    Ex-class 0,3 8 3 7 8

    Supply water (l/min) 0,1 8 8 4 8

    Total 22,7 18,8 17,8 23,6

    Total Technology Subscore 30 28,5 24,7 31,5

    Score sheet System A B C D

    Operation Principle Filter Filter Filter Electro-

    UV UV Cl lysis

    Score scale: 0-10,

    10 being the best Weight factor

    Dimensions and modular izat ion

    Size of the 250-334 m3/h u 0,4 7 2 4 7

    Footprint of 250-334 m3/h 0,6 7 3 2 1Size for 2000m3/h unit [m3 0,4 8 2 5 8

    Footprint of 2000 m3/h uni 0,6 6 3 7 7

    Modularization 0,8 7 7 4 5

    Weight in operation [kg] 0,1 8 5 6 6

    Total Size Subscore 20,2 11,3 12,8 15,4

    Total Size Score 8,5 5 6 7

    Equipment cost

    Equipment cost [] 0,8

    Instal lat ion cos t

    installation cost 0,5 3 2 3 3

    Instal lat ion tim e

    installation time 0,3 3 2 2 2

    Operational cos ts

    operational costs 0,8 6 4 3 8

    Reliability

    Support network 0,8 8 6 8 4

    References 0,6 4 2 3 8

    certificate/imo compliance 0,5 5 3 3 5

    Total Reliabili ty Subscore 11,3 7,5 9,7 10,5

    Total Reliability Score 9 7 7,5 8

    Lead tim e

    Lead time

    TOTAL SCORE 48 36 34 47,5

  • 8/10/2019 Henrik Bacher Elomatic

    25/35

  • 8/10/2019 Henrik Bacher Elomatic

    26/35

    C O N S U L T I N G & E N G I N E E R I N G

    The retrofit process

    Solution & consequenceevaluation, comparisons,preliminary (basic) design

    Solution & consequenceevaluation, comparisons,preliminary (basic) design

    Supplier selectionSupplier selection

    Basic design & eng.Basic design & eng.

    PlanningPlanning

    InstallationInstallation

    Testing &

    Commissioning

    Testing &

    Commissioning

    LogisticsLogistics

    ProcurementProcurement

    General ,

    Technical,

    Operational

    considerations

    General ,

    Technical,

    Operational

    considerations

    Individual contracts

    Turn key (yard or supplier)

    EPCM

    Individual contracts

    Turn key (yard or supplier)

    EPCM

    Detail designDetail design

  • 8/10/2019 Henrik Bacher Elomatic

    27/35

    C O N S U L T I N G & E N G I N E E R I N G

    The role of design & engineeringA ship specific optimum solution requires a deep cooperation

    between shipowner, BWT supplier and the design &

    engineering party

    The design role include

    - basic system arrangement and equipment location

    - integration to existing systems and tie in points

    - necessary modifications to the existing vessel

    - maintenance access as well as installation access and

    routes (component size, existing hatches, working openings)

    - classification & flag authority issues and approvals- general naval architecture issues

    The detail design can commence once all approvals are in

    place

  • 8/10/2019 Henrik Bacher Elomatic

    28/35

    C O N S U L T I N G & E N G I N E E R I N G

    The role of design & engineering cont.Only a thorough design can guarantee a

    good result; the more you design and plan

    the more you will control and influence

    (=reduce) costs and avoid surprises.

    3D design may be an advantage

  • 8/10/2019 Henrik Bacher Elomatic

    29/35

    C O N S U L T I N G & E N G I N E E R I N G

    Supporting design tools laser scanningWhat is laser scanning?

    Measuring method to get 3D data (accuracy 0,1 5 mm)

    Point cloud created by laser scanner

    Point cloud edited to engineering format as a 3D model

    Why laser scanning?

    When documentation is poor or only old system drawings

    are available

    Ensures the present as built status with high accuracy

    Creates an ideal basis for the retrofit design

    Enables use of todays design tools

    Need for ship visits is reduced

    Design errors are reduced

    New components can be delivered as prefabricated units

    Potential to reduce total costs

    Laser scanning point cloud

    3D Basic model

    Retrofit design model

  • 8/10/2019 Henrik Bacher Elomatic

    30/35

    C O N S U L T I N G & E N G I N E E R I N G

    Supporting tools laser scanning cont.

    Example of a recent laser scanning raw data (contains also numerical information)

  • 8/10/2019 Henrik Bacher Elomatic

    31/35

    C O N S U L T I N G & E N G I N E E R I N G

    Installation considerationsOut of service - drydocking or alongside

    - Justified in combination with a scheduled

    drydocking

    - When large working/transportation

    openings are needed in the hull

    - When new hull overboard penetrations are

    needed

    - Preparatory and finalization work can be

    done while in service in order to minimize

    down time

    - Advantages; infrastructure, logistics, labor

    & material in case of surprises

    - Disadvantages; loss of earnings (unless

    streamlined with a scheduled drydock)

    C O N S U L T I N G & E N G I N E E R I N G

  • 8/10/2019 Henrik Bacher Elomatic

    32/35

    C O N S U L T I N G & E N G I N E E R I N G

    Installation cont.In operation

    - Possible if a drydock is not needed; several

    retrofits carried out prove that

    - Requires extensive planning

    - A high degree of prefabrication is needed

    - Logistics may be a challenge and needs strict

    management (depending on trading pattern)- Solutions to enable the minimizing of hot work

    - Special solutions should be considered (pipe

    couplings etc.)

    - The design is in a key position- Disadvantage; poor coverage against

    surprises (material, special workforce etc.)

    C O N S U L T I N G & E N G I N E E R I N G

  • 8/10/2019 Henrik Bacher Elomatic

    33/35

    C O N S U L T I N G & E N G I N E E R I N G

    Alternatives to ballast solutionsWhy ballast?

    Immersion (propeller, bow), trim (optimum running condition, avoid

    slamming), load distribution (strength), stability, anti-heeling

    Ballast free and alternative designs

    - Various concepts have been developed/are under development

    - Reduced ballast need (simpler BWT system)- Storm only ballast

    - Flow-through designs (VLCC:s)

    - Ballast free designs through special hull form

    DNV/ Making Waves

    C O N S U L T I N G & E N G I N E E R I N G

  • 8/10/2019 Henrik Bacher Elomatic

    34/35

    C O N S U L T I N G & E N G I N E E R I N G

    ConclusionsThe BW convention is expected to enter into force within a reasonable future

    There is no general best solution each ship is individual

    There is a number of proven technologies on the market

    A thorough pre-design/evaluation study pays off

    Retrofit installations including logistics needs to be planned in detail with high

    priority

    Design capacity, equipment supply and installation capacity may become critical

    C O N S U L T I N G & E N G I N E E R I N G

  • 8/10/2019 Henrik Bacher Elomatic

    35/35

    C O N S U L T I N G & E N G I N E E R I N G

    Thank you for listening

    Q & A

    [email protected]