Heavy Component Replacement in Nuclear Power Plants€¦ · Heavy Component Replacement in Nuclear Power Plants ... Component Fabrication Site Installation ... Spring 2010 South Texas

  • Upload
    vandung

  • View
    213

  • Download
    0

Embed Size (px)

Citation preview

  • Heavy Component Replacementin Nuclear Power Plants

    Steve Sills, Vice President Business Development, SGTDarren Wood, Manager Component Replacements, AREVA

  • >2 2

    Purpose and Process

    Goal

    Recent successes and lessons learned in AREVA and SGT Heavy Component Replacements

    Agenda

    IAEA NP-T-3.2 - BackgroundProject OrganizationSteam Generator ReplacementsReactor Vessel Closure Head ReplacementsPressurizer ReplacementsWaste Disposition

    Payoff

    High level overview Initiate an information exchange

  • >3 3

    IAEA NP-T-3.2Heavy Component Replacement in Nuclear Power Plants:

    Experience and Guidelines

    Why are we here? Component Aging and Plant License Extension

    Most Feasible Solutions Trends Share Lessons Learned

    US Market Steam Generators

    replaced at 47 units 9 planned Alloy 600 TT tubes unplanned

    Reactor Vessel Heads replaced at 37 units 13 planned 19 low-susceptibility unplanned

    Pressurizers replaced at 3 CE units

    Reactor Coolant Piping 2 planned at B&W units

    Experience Base Continues to GrowExperience Base Continues to GrowExperience Base Continues to Grow

  • >4 4

    Project Composition

  • >5 5

    How does the Project Organization impact project success?

    Project Management Customer Scope/Contract Business Unit Integration Subcontractor Integration

    Engineering Design / Specification Analysis Metrology Services NDE Quality Field Implementation

    Component Fabrication Site Installation

    Outage Manager Resources

    Definitions of Success Safety Radiation dose Schedule Cost / budget performance Human performance

    Contributors to Success Dedicated team Strong structure - clear definition of responsibilities and communications

    N-3, 2, 1 Walk-downs Leverage technology Robust processes Clear contract

    Alignment of goalsStaffing of key positions

    Facilitating clear communications

    Alignment of goalsAlignment of goalsStaffing of key positionsStaffing of key positions

    Facilitating clear communicationsFacilitating clear communications

  • >6 6

    Who is SGT?

    50% 50%

  • Replacements since 2003

    Sch

    edule p

    ressure fro

    m decreasin

    g Outag

    e duratio

    ns

    Sch

    edule p

    ressure fro

    m decreasin

    g Outag

    e duratio

    ns

    Sch

    edule p

    ressure fro

    m decreasin

    g Outag

    e duratio

    ns

    SEQUOYAH 1 (W4)

    CALVERT CLIFFS 2 (CE)

    OCONEE 1 (B&W)

    PALO VERDE 2 (CE)

    OCONEE 2 (B&W)

    PRAIRIE ISLAND 1 (W2)

    OCONEE 3 (B&W)

    PALO VERDE 1 (CE)

    CALLAWAY (W4)

    ANO 1 (B&W)

    BEAVER VALLEY 1 (W3)

    WATTS BAR 1 (W4)

    COMANCHE PEAK 1 (W4)

    PALO VERDE 3 (CE)

    FORT CALHOUN (CE)

    ST. LUCIE 2 (CE)

    SALEM 2 (W4)

    DIABLO CANYON 2 (W4)

    DIABLO CANYON 1 (W4)

    0 10 20 30 40 50 60 70 80 90

    100

    110

    1202003

    20042005

    20062007

    2008

  • >8 8

    Outage schedules

    Each unit is unique different schedule challenges

    2 SGs is not half as long as 4 Shortest schedule requires

    Commitment by customer Cost is probably higher Plant activities must also be optimized Extensive schedule review and Integration Extensive Planning and mock up training Coordination of cranes & space Clearly establish objectives align incentives

    Shorter Outage Trend Continues still raising the bar

    Shorter Outage Trend Continues Shorter Outage Trend Continues still raising the barstill raising the bar

  • >9 9

    SGT Just finished Diablo Canyon SGR

    Westinghouse four-loop PWR 1,150 MW Outage - January 25, 2009 to March 24, 2009 SGT performed Unit 2 SGR in 2008

    Delivery of excellent performance: Safety

    Project achieved One Million Safe Hours 12/01/08 730,034 safe hours (w/o lost time)

    Unit 1 May 1, 2008 - present

    Outage: 2 recordables SGT Dose actual 163.4 goal 165.4

    Dose rates 30% higher than Unit 2; Unit 1 actual dose only 15% higher

    Schedule 58 d 1 hr B-B 12 hrs ahead of schedule Ready for ILRT 116 hrs early 11 days shorter than unit 2

    Quality Document closeout excellent 8 of 8 RCS welds first time quality 28 of 29 large bore secondary welds first time quality

    Diablo Canyon Unit 1 Steam Generator Replacement

  • >10 10

    Future Steam Generator Replacement

    Lower volume Uncertain schedule

    SGR Alloy 600 TT SG tubes

    From the experience Extensive lessons learned Refined processes Continuous improvement

  • >11 11

    Keys to Success

    One clear vision for the entireentire team Early alignment of expectations and communication of those expectations to project participants

    The right team Get the needed mix of skills and experience Ensure clear roles and responsibilities More is not better, it just costs more

    Teamwork Help each other be successful What do you need to make it happen Dont accept we cant Treat each other with respect View as one team, top to bottom Communication is critical Teambuilding, including social events for the team Celebrate along the way

  • >12 12

    Keys to Success

    Effective Project Management Systems Effective Human Performance, Safety (industrial, radiation and nuclear) and Quality Culture

    Detailed Planning Mock-up and proficiency training High Quality Detailed Schedule to Focus Organization Early Involvement of Plant Personnel Formal and Proven Processes / Systems (Project planning, integration and Readiness Review, corrective action, detailed resource planning)

    Technology / innovation 3d modeling Metrology laser scanning & precision measurements

    Fit-up solution tools Computed Radiography Rigging equipment minimize plant modifications

  • >13 13

    Reactor Vessel Closure Head (RVCH) Replacements

    Recent decline in activity High and medium susceptibility heads 35 of 48 replaced Remainder planned

    Low-temperature heads 2 of 21 replaced Utilities are monitoring

    There is a good experience base to learn from.There is a good experience base to learn from.There is a good experience base to learn from.

    Fall 2009 Diablo Canyon 2 South Texas 1 Palo Verde 2

    Spring 2010 South Texas 2 Palo Verde 1

    Fall 2010 Diablo Canyon 1

  • >14 14

    Many plants include service structure upgrades when replacing their RVCH

    Current Service Structure separate from service structure, roll away, fly remaining to head stand

    Integrated Head Assembly fold cable trays, fly entire structure to head stand

    Eliminate current rolling missile shield, ductwork and fans

  • >15 15

    Integrated Head Assembly

    CRDM Cooling Air Plenum - Easy maintenance access

    Easy-disconnect and self-storing tie rods - Schedule and dose savings and safety feature

    Integrated Missile Shield - Schedule and dose savings and safety feature

    4 low-rpm CRDM Cooling Fans - Longer life / Low Amp Motor - Greater reliability - Reverse current air flow pattern

    Personnel access platform - Schedule saving and safety feature

    External Ladder- Time saving and safety feature

    Permanent, Moveable, Double-door Radiation Shielding - Schedule and dose savings and safety feature-Easy access for inspections and maintenance

    Integrated CRDM Cooling Ductwork - Schedule and dose savings and safety feature

    Cable Bridges - Personnel access rated

    Permanent Tripod - Schedule savings and safety feature

    Tripod / Fan Access Ladders-- Easy Access to Lift Eye / Fans

    Redesigned, upgraded dome and l-panel insulation- ports for 100% visual inspection and robot access- Schedule and dose savings

    Expected 40 hrs outage time savings and 4-6 man-remdose savings. Top Industry Practice Award Winner.

    Expected 40 hrs outage time savings and 4Expected 40 hrs outage time savings and 4--6 man6 man--remremdose savings. Top Industry Practice Award Winner.dose savings. Top Industry Practice Award Winner.

  • >16 16

    Applying Lessons Learned Continues to Improve Performance

    DC Cook 2 (Fall 2007) RVCH and Service Structure Upgrades

    37 days vs 38 planned 11.8 person-rem vs 12.5 Second outage project execution much improved

    Customer support resources loaded into schedule

    Laydown space planning Suppliers were included as part of site team

    St. Lucie 2 (Fall 2007) RVCH, Enhanced Service Structure, Steam Generators

    79 days versus 66 planned Total RVCHR dose 5.43 REM Controlled document station inside containment with fax and phone saved significant time

    Good coordination / information flow from original equipment manufacturer

    Pre-assembly / trial fit in the temporary assembly building

    CEDM welding tool performed flawlessly used generator versus off-site power (voltage drops previous outage)

    24/7 vendor coverage for analytical support

    Fabrication and installation of ductwork

  • >17 17

    Three dimensional models and precision measurement minimize fit-up risks.

  • >18 18

    Pressurizer Replacements Market Status

    No additional pressurizer replacements are planned in the US market.

    Last AREVA replacement was at Millstone in 2006

    Rhingals 4 is planned for 2011 during SGR

    Key Lessons Economical for pressurizers with greater than 100 heaters

    Civil scope and interference removal just a critical as heavy component scope

    Dedicated secondary cranes Proper design of insulation package Foreign material exclusion is a challenge

    NDE examination criteria Piping restraints and spring-back

  • >19 19

    Pressurizer Replacements

  • >20 20

    Waste Disposition continues to be a scope and cost that cannot be overlooked.

    Replaced components interim onsite storage facilities

    Build and license Low-level waste

    Disposal cost Component demolition Logistics of removal from reactor building

    Shipping container Contamination bag

    Successes Detailed waste removal plans Include in outage schedule Planning between disposal and rigging teams

    Transportation logistics Mechanism for release of bag Gasket material

  • >21 21

    Conclusions

    Every project is different the devil is in the details

    Establish a good plan early

    Clear communications and alignment of goals between stakeholders is keySecond outages are typically more successfulThe scope is larger than the component replacement

    Apply lessons learned

    Leverage technology

    Precision measurements during early walk-downs3-D modeling Integrated schedules

  • >22 22

    Wrap-Up

    Goal

    Recent successes and lessons learned in Heavy Component Replacements

    Agenda

    IAEA NP-T-3.2 BackgroundProject OrganizationSteam Generator ReplacementsReactor Vessel Closure Head ReplacementsPressurizer ReplacementsWaste Disposition

    Payoff

    Share experiences and improve our performanceEn

    j o y th e

    Co nfe r e

    n c e!