If you can't read please download the document
Upload
vandung
View
213
Download
0
Embed Size (px)
Citation preview
Heavy Component Replacementin Nuclear Power Plants
Steve Sills, Vice President Business Development, SGTDarren Wood, Manager Component Replacements, AREVA
>2 2
Purpose and Process
Goal
Recent successes and lessons learned in AREVA and SGT Heavy Component Replacements
Agenda
IAEA NP-T-3.2 - BackgroundProject OrganizationSteam Generator ReplacementsReactor Vessel Closure Head ReplacementsPressurizer ReplacementsWaste Disposition
Payoff
High level overview Initiate an information exchange
>3 3
IAEA NP-T-3.2Heavy Component Replacement in Nuclear Power Plants:
Experience and Guidelines
Why are we here? Component Aging and Plant License Extension
Most Feasible Solutions Trends Share Lessons Learned
US Market Steam Generators
replaced at 47 units 9 planned Alloy 600 TT tubes unplanned
Reactor Vessel Heads replaced at 37 units 13 planned 19 low-susceptibility unplanned
Pressurizers replaced at 3 CE units
Reactor Coolant Piping 2 planned at B&W units
Experience Base Continues to GrowExperience Base Continues to GrowExperience Base Continues to Grow
>4 4
Project Composition
>5 5
How does the Project Organization impact project success?
Project Management Customer Scope/Contract Business Unit Integration Subcontractor Integration
Engineering Design / Specification Analysis Metrology Services NDE Quality Field Implementation
Component Fabrication Site Installation
Outage Manager Resources
Definitions of Success Safety Radiation dose Schedule Cost / budget performance Human performance
Contributors to Success Dedicated team Strong structure - clear definition of responsibilities and communications
N-3, 2, 1 Walk-downs Leverage technology Robust processes Clear contract
Alignment of goalsStaffing of key positions
Facilitating clear communications
Alignment of goalsAlignment of goalsStaffing of key positionsStaffing of key positions
Facilitating clear communicationsFacilitating clear communications
>6 6
Who is SGT?
50% 50%
Replacements since 2003
Sch
edule p
ressure fro
m decreasin
g Outag
e duratio
ns
Sch
edule p
ressure fro
m decreasin
g Outag
e duratio
ns
Sch
edule p
ressure fro
m decreasin
g Outag
e duratio
ns
SEQUOYAH 1 (W4)
CALVERT CLIFFS 2 (CE)
OCONEE 1 (B&W)
PALO VERDE 2 (CE)
OCONEE 2 (B&W)
PRAIRIE ISLAND 1 (W2)
OCONEE 3 (B&W)
PALO VERDE 1 (CE)
CALLAWAY (W4)
ANO 1 (B&W)
BEAVER VALLEY 1 (W3)
WATTS BAR 1 (W4)
COMANCHE PEAK 1 (W4)
PALO VERDE 3 (CE)
FORT CALHOUN (CE)
ST. LUCIE 2 (CE)
SALEM 2 (W4)
DIABLO CANYON 2 (W4)
DIABLO CANYON 1 (W4)
0 10 20 30 40 50 60 70 80 90
100
110
1202003
20042005
20062007
2008
>8 8
Outage schedules
Each unit is unique different schedule challenges
2 SGs is not half as long as 4 Shortest schedule requires
Commitment by customer Cost is probably higher Plant activities must also be optimized Extensive schedule review and Integration Extensive Planning and mock up training Coordination of cranes & space Clearly establish objectives align incentives
Shorter Outage Trend Continues still raising the bar
Shorter Outage Trend Continues Shorter Outage Trend Continues still raising the barstill raising the bar
>9 9
SGT Just finished Diablo Canyon SGR
Westinghouse four-loop PWR 1,150 MW Outage - January 25, 2009 to March 24, 2009 SGT performed Unit 2 SGR in 2008
Delivery of excellent performance: Safety
Project achieved One Million Safe Hours 12/01/08 730,034 safe hours (w/o lost time)
Unit 1 May 1, 2008 - present
Outage: 2 recordables SGT Dose actual 163.4 goal 165.4
Dose rates 30% higher than Unit 2; Unit 1 actual dose only 15% higher
Schedule 58 d 1 hr B-B 12 hrs ahead of schedule Ready for ILRT 116 hrs early 11 days shorter than unit 2
Quality Document closeout excellent 8 of 8 RCS welds first time quality 28 of 29 large bore secondary welds first time quality
Diablo Canyon Unit 1 Steam Generator Replacement
>10 10
Future Steam Generator Replacement
Lower volume Uncertain schedule
SGR Alloy 600 TT SG tubes
From the experience Extensive lessons learned Refined processes Continuous improvement
>11 11
Keys to Success
One clear vision for the entireentire team Early alignment of expectations and communication of those expectations to project participants
The right team Get the needed mix of skills and experience Ensure clear roles and responsibilities More is not better, it just costs more
Teamwork Help each other be successful What do you need to make it happen Dont accept we cant Treat each other with respect View as one team, top to bottom Communication is critical Teambuilding, including social events for the team Celebrate along the way
>12 12
Keys to Success
Effective Project Management Systems Effective Human Performance, Safety (industrial, radiation and nuclear) and Quality Culture
Detailed Planning Mock-up and proficiency training High Quality Detailed Schedule to Focus Organization Early Involvement of Plant Personnel Formal and Proven Processes / Systems (Project planning, integration and Readiness Review, corrective action, detailed resource planning)
Technology / innovation 3d modeling Metrology laser scanning & precision measurements
Fit-up solution tools Computed Radiography Rigging equipment minimize plant modifications
>13 13
Reactor Vessel Closure Head (RVCH) Replacements
Recent decline in activity High and medium susceptibility heads 35 of 48 replaced Remainder planned
Low-temperature heads 2 of 21 replaced Utilities are monitoring
There is a good experience base to learn from.There is a good experience base to learn from.There is a good experience base to learn from.
Fall 2009 Diablo Canyon 2 South Texas 1 Palo Verde 2
Spring 2010 South Texas 2 Palo Verde 1
Fall 2010 Diablo Canyon 1
>14 14
Many plants include service structure upgrades when replacing their RVCH
Current Service Structure separate from service structure, roll away, fly remaining to head stand
Integrated Head Assembly fold cable trays, fly entire structure to head stand
Eliminate current rolling missile shield, ductwork and fans
>15 15
Integrated Head Assembly
CRDM Cooling Air Plenum - Easy maintenance access
Easy-disconnect and self-storing tie rods - Schedule and dose savings and safety feature
Integrated Missile Shield - Schedule and dose savings and safety feature
4 low-rpm CRDM Cooling Fans - Longer life / Low Amp Motor - Greater reliability - Reverse current air flow pattern
Personnel access platform - Schedule saving and safety feature
External Ladder- Time saving and safety feature
Permanent, Moveable, Double-door Radiation Shielding - Schedule and dose savings and safety feature-Easy access for inspections and maintenance
Integrated CRDM Cooling Ductwork - Schedule and dose savings and safety feature
Cable Bridges - Personnel access rated
Permanent Tripod - Schedule savings and safety feature
Tripod / Fan Access Ladders-- Easy Access to Lift Eye / Fans
Redesigned, upgraded dome and l-panel insulation- ports for 100% visual inspection and robot access- Schedule and dose savings
Expected 40 hrs outage time savings and 4-6 man-remdose savings. Top Industry Practice Award Winner.
Expected 40 hrs outage time savings and 4Expected 40 hrs outage time savings and 4--6 man6 man--remremdose savings. Top Industry Practice Award Winner.dose savings. Top Industry Practice Award Winner.
>16 16
Applying Lessons Learned Continues to Improve Performance
DC Cook 2 (Fall 2007) RVCH and Service Structure Upgrades
37 days vs 38 planned 11.8 person-rem vs 12.5 Second outage project execution much improved
Customer support resources loaded into schedule
Laydown space planning Suppliers were included as part of site team
St. Lucie 2 (Fall 2007) RVCH, Enhanced Service Structure, Steam Generators
79 days versus 66 planned Total RVCHR dose 5.43 REM Controlled document station inside containment with fax and phone saved significant time
Good coordination / information flow from original equipment manufacturer
Pre-assembly / trial fit in the temporary assembly building
CEDM welding tool performed flawlessly used generator versus off-site power (voltage drops previous outage)
24/7 vendor coverage for analytical support
Fabrication and installation of ductwork
>17 17
Three dimensional models and precision measurement minimize fit-up risks.
>18 18
Pressurizer Replacements Market Status
No additional pressurizer replacements are planned in the US market.
Last AREVA replacement was at Millstone in 2006
Rhingals 4 is planned for 2011 during SGR
Key Lessons Economical for pressurizers with greater than 100 heaters
Civil scope and interference removal just a critical as heavy component scope
Dedicated secondary cranes Proper design of insulation package Foreign material exclusion is a challenge
NDE examination criteria Piping restraints and spring-back
>19 19
Pressurizer Replacements
>20 20
Waste Disposition continues to be a scope and cost that cannot be overlooked.
Replaced components interim onsite storage facilities
Build and license Low-level waste
Disposal cost Component demolition Logistics of removal from reactor building
Shipping container Contamination bag
Successes Detailed waste removal plans Include in outage schedule Planning between disposal and rigging teams
Transportation logistics Mechanism for release of bag Gasket material
>21 21
Conclusions
Every project is different the devil is in the details
Establish a good plan early
Clear communications and alignment of goals between stakeholders is keySecond outages are typically more successfulThe scope is larger than the component replacement
Apply lessons learned
Leverage technology
Precision measurements during early walk-downs3-D modeling Integrated schedules
>22 22
Wrap-Up
Goal
Recent successes and lessons learned in Heavy Component Replacements
Agenda
IAEA NP-T-3.2 BackgroundProject OrganizationSteam Generator ReplacementsReactor Vessel Closure Head ReplacementsPressurizer ReplacementsWaste Disposition
Payoff
Share experiences and improve our performanceEn
j o y th e
Co nfe r e
n c e!