5
HAN Update HAN Update AMIT/RMS AMIT/RMS February 2012

HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

Embed Size (px)

DESCRIPTION

HAN Project - Milestones Key Milestones: – Developed the HAN Support Model Based on the Input of the Market Participants, Key Drivers: – Foster consistency across the TDSP territories – Standardize ‘Pairing’ time across the TDSP territories – Pro-active notification to the market – Define Service Level Objectives (SLO’s) – Create robust /detailed documentation, both technical and functional ‘How Too’ – Reviewed and Secured Buy-In of the HAN Support Model with the JDOA Stake-holders – In Process, Reviewing the HAN Support Model with the Market Participants – Scheduled Periodic HAN Task Force Meetings – Under-way is the Development of the HAN Documentation with a Q1 Completion (Initial Phase): – HAN Starter-Kit – HAN User Guide – Technical API

Citation preview

Page 1: HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

HAN Update AMIT/RMSHAN Update AMIT/RMS

February 2012

Page 2: HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

HAN Core Support TeamHAN

CoordinatorJay Foliano

OncorRobert Smith

CNPTBD

AEPJerry

Young

TNMPBobby

Roberts

PUCTRebecca

Reed

-RMS/AMIT – 11/7/11

Coordinators

Vendors/MFG

REPS/3rd Party

Page 3: HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

HAN Project - Milestones• Key Milestones:

– Developed the HAN Support Model Based on the Input of the Market Participants, Key Drivers:– Foster consistency across the TDSP territories– Standardize ‘Pairing’ time across the TDSP territories– Pro-active notification to the market– Define Service Level Objectives (SLO’s) – Create robust /detailed documentation, both technical and functional ‘How Too’

– Reviewed and Secured Buy-In of the HAN Support Model with the JDOA Stake-holders

– In Process, Reviewing the HAN Support Model with the Market Participants

– Scheduled Periodic HAN Task Force Meetings

– Under-way is the Development of the HAN Documentation with a Q1 Completion (Initial Phase):– HAN Starter-Kit– HAN User Guide– Technical API

Page 4: HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

HAN Project

Next Steps:– Revise the HAN Support Model Based on Market

Participants Input– Present any Revisions of the HAN Support Model to

the JDOA Stake-Holders for Buy-In– Present the HAN Support Model to AMIT Steering

Committee for Review, Input and Buy-in– Publish the HAN Documentation, Q1 – Conduct a Market Participant & TDSP Workshop to

Define the HAN Model Detailed Requirements

Page 5: HAN Update AMIT/RMS February 2012. HAN Core Support Team HAN Coordinator Jay Foliano Oncor Robert Smith CNP TBD AEP Jerry Young TNMP Bobby Roberts PUCT

Contact Information:

Jay FolianoEmail: [email protected]: C-919-906-4101

Andrea O’FlahertyEmail: [email protected]: C-214-663-2543