92
Hamlet of Fallis Drainage Improvement Section 00 01 07 Parkland County SEALS PAGE Issued for Tender Page 1 of 1 DIVISION 01 – GENERAL REQUIREMENTS DIVISION 31 – EARTHWORK DIVISION 32 – EXTERIOR IMPROVEMENTS DIVISION 33 – UTILITIES

Hamlet of Fallis Drainage Improvement Section 00 01 07

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 00 01 07 Parkland County SEALS PAGE Issued for Tender Page 1 of 1 DIVISION 01 – GENERAL REQUIREMENTS DIVISION 31 – EARTHWORK DIVISION 32 – EXTERIOR IMPROVEMENTS DIVISION 33 – UTILITIES

Page 2: Hamlet of Fallis Drainage Improvement Section 00 01 07

SPC-00 01 10 TOC-60638222_new.doc

PARKLAND COUNTY HAMLET OF FALLIS DRAINAGE IMPROVEMENT

AECOM Canada Ltd. 101, 18817 Stony Plain Road NW Edmonton Alberta T5S 0C2

Dated: May 26, 2021

TABLE OF CONTENTS No. of Pages

DIVISION 01 - GENERAL REQUIREMENTS 01 10 00 GENERAL REQUIREMENTS 9 01 29 00 PAYMENT PROCEDURES 11 01 31 19 PROJECT MEETINGS 4 01 32 17 PROJECT MANAGEMENT AND COORDINATION 4 01 33 00 SUBMITTAL PROCEDURES 4 01 35 29.06 HEALTH AND SAFETY REQUIREMENTS 4 01 35 43 ENVIRONMENTAL PROCEDURES 4 01 45 00 QUALITY ASSURANCE / CONTROL 5 01 54 00 EXISTING STRUCTURES AND UTILITIES 2 01 55 26 TRAFFIC CONTROL 3 01 61 00 COMMON PRODUCTS REQUIREMENTS 3 01 74 00 CLEANING 1 01 77 00 CLOSEOUT PROCEDURES 2 01 78 00 CLOSEOUT SUBMITTALS 3 DIVISION 31 - EARTHWORK 31 05 16 AGGREGATES FOR EARTHWORK 3 31 11 00 CLEARING AND GRUBBING 1 31 11 00.01 CLEARING, MULCHING AND TIMBER SALVAGE 3 31 14 13 SOIL STRIPPING AND STOCKPILING 2 31 23 13 EARTHWORKS AND GRADING 3 31 23 33.01 EXCAVATING, TRENCHING AND BACKFILLING 6 31 32 19.01 GEOTEXTILE 2 DIVISION 32 - EXTERIOR IMPROVEMENTS 32 91 19 13 TOPSOIL PLACEMENT 2 32 92 19.13 SEEDING AND SOD 5 DIVISION 33 - UTILITIES 33 42 13 PIPE CULVERTS 3

Page 3: Hamlet of Fallis Drainage Improvement Section 00 01 07

SPC-00 01 10 TOC-60638222_new.doc

PARKLAND COUNTY HAMLET OF FALLIS DRAINAGE IMPROVEMENT

LIST OF DRAWINGS Drawings Bound Separately. Drawing No. Title C-0000 COVER SHEET C-1000 INDEX, AND TOPOGRAPHY C-1100 PLAN AND PROFILE – AREA 3 DITCH C-1101 PLAN AND PROFILE – AREA 5 DITCH C-1102 PLAN AND PROFILE – AREA 6 DITCH C-1103 PLAN AND PROFILE – AREA 7 DITCH C-3000 TYPICAL CROSS SECTIONS C-4000 DETAILS

Page 4: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 1 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

1.0 GENERAL

1.1 General Requirements

.1 The work covered by this Contract shall include, but shall not be limited to, the furnishing of all materials, plant, equipment, tools, implements, machinery, supplies, temporary lighting, water, heating, scaffolding, shoring, temporary works, dewatering, transportation, labour and superintendence necessary for the construction of the work as herein specified and shown on the drawings.

.2 The complete work under this Contract shall be governed by the dictates of good practice

and shall be complete in all details of materials and methods even if not minutely specified. .3 The work shall be properly coordinated with the requirements of all work specified in other

sections. .4 The work includes testing as specified and assistance with start-up and placing of the work in

operation, ready for use by the Owner. 1.2 Description of Work

.1 Work under this Contract covers supply and installation of all materials and construction of the following:

“Parkland County – Hamlet of Fallis Drainage Improvement”

• Install drainage ditch, • Clearing and grubbing, • Tree removal, • Sediment control. • Supply and install 300mm Diameter CSP Culvert, • Road elevation adjustment/resurfacing, • Material testing, • Landscaping work including topsoil and seeding, • Submission of red-line drawings, and as-built survey data/information.

.2 Construction Milestones

• Project Construction Kick-off Meeting: July 05, 2021 • Mobilization to the site of work shall be available: July 07, 2021 • Substantial Performance of the work shall be achieved: September 08, 2021 • The Total Performance of the work shall by achieved: October 08, 2021 • The Warranty Period for this contract is 2 years.

.1 The Contractor will be responsible for adjusting the schedule to accommodate land

ownership agreement transfer and crossing agreements approval.

.2 If physical conditions require certain locations of the work to be conducted in frozen conditions, then the Contractor shall give Notice in writing to the Consultant of such conditions. This Notice shall be given no later than 30 days after mobilization to the place of the Work. The Consultant will promptly investigate such conditions and make a finding. If the Consultant agrees with the conditions the Substantial Performance can be extended for such reasonable time as the Consultant may recommend in consultation with the County and the Contractor. No change in contract price will be granted for any extension to the Substantial Performance date due to these physical conditions.

Page 5: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 2 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

1.3 Contractor’s Project Team

.1 Should key personnel from the Contractor’s team, including the Project Manager and the Superintendent(s), no longer be available to perform the Work due to illness or discontinued employment, provide three alternatives for consideration as replacement for that person. The County will select the replacement from the alternatives.

.2 Key personnel from the Contractor’s team that are still in the Contractor’s employment

cannot be assigned full-time to another project prior to Construction Completion without written consent of the County.

1.4 Work Sequence

.1 Construct work in stages to minimize disruption to traffic. .2 The following are Parkland County’s priority areas:

.1 Area 5 – Cross Street Ditching .2 Area 3 – Laneway Drainage .3 Area 6 – TWP 532 Culvert Improvement .4 Area 7 – Camp Yowochas

1.5 Work Schedule

.1 Provide within ten (10) working days after Contract award, construction bar chart schedule in weekly increments showing anticipated progress stages, significant milestones, inspections by outside parties and final completion of work within time period required by Contract and Bid documents.

.2 Interim reviews of work progress based on work schedule will be conducted as decided by

Consultant and schedule updated by Contractor in conjunction with and to approval of Consultant.

.3 Scheduling shall be in accordance with the General Conditions and General Requirements. .4 All system shutdowns and service interruptions must be approved by and coordinated with

the Owner. Provide a minimum of five (5) days written notice for each interruption. Contractor obligated to provide temporary measure to maintain the system still works during the service interruptions.

1.6 Project Meetings

.1 The Consultant will arrange and set times for project meetings and will record and distribute a record of the meeting.

.2 The Contractor’s project manager, site superintendent and representatives of the

subcontractors shall attend the meetings at the request of the Consultant.

Page 6: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 3 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

1.7 Additional Drawings

.1 The Consultant may furnish additional drawings for clarification in PDF format. These additional drawings have same meaning and intent as if they were included with plans referred to in Contract documents.

1.8 Mobilization and Demobilization

.1 Mobilization shall include transportation to the site of the Contractor's labour, equipment, and materials in readiness to start work and the Contractor shall allow for all his costs in the unit rates.

.2 Demobilization shall include the dismantling and removal from the site of all the Contractor's

equipment and materials, cleanup of the site, and transportation of labour from the site and the Contractor shall allow for all his costs in the unit rates.

1.9 Definition of Trades

.1 For convenience of reference only, the specifications are separated into sections identified by title and a six-digit numbering system.

.2 The separation into sections is not intended to identify responsibility of work. .3 Responsibility as to which trade provides required materials or articles of work rests solely

with the Contractor. .4 In the case of a dispute, it is the Contractor's responsibility to determine which subtrade

supplies and installs required materials or equipment. .5 Extras will not be considered for differences in interpretation of the specifications as to which

trades do the work. 1.10 Permits, Licenses, Certificates and Fees

.1 Utility crossing agreements and regulatory permits and / or approvals are the responsibility of the Consultant to obtain and provide to Contractor before performance of the work. All other permits must be obtained by the Contractor before performance of the work.

1.11 Documents Required

.1 Maintain at job site, one copy each of following:

.1 Latest "Construction Issue" of Contract drawings. .2 Specifications. .3 Addenda. .4 Reviewed shop drawings. .5 Change Orders. .6 Other modifications to Contract. .7 Field test reports.

Page 7: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 4 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

.8 Copy of latest approved work schedule. .9 Manufacturers' installation and application instructions. .10 Up-to-date Record Drawings.

1.12 Examination of Site

.1 Prior to commencing actual construction, check field conditions to obtain actual dimensions required to ensure correct execution of the work, and notify the Consultant, in writing, of all matters which could prejudice proper execution of the work.

.2 Commencement of construction shall constitute acceptance of existing conditions and

verification of dimensions. .3 No extra charges will be allowed for work resulting from conditions which would have been

evident upon a thorough examination of the site.

1.13 Documentation and Photographs

.1 Document the Work’s progress with photographs taken by qualified persons. Submit the photographs to the Consultant for record purposes with each Progress Report.

.2 Prior to commencing the Work, document the preconstruction condition of the Work Site,

accesses, haul routes, storage, laydown and mobilization areas with detailed photographs or video recordings. Upon completion of the Work, document the post-construction condition of the same areas. Submit the photographs to the Consultant for record purposes.

.3 Photographs and video recordings shall be in digital format. Files shall be identified by

number and logged with digital file structure and name. Reference number, location or address, date taken, and description of the work photographed shall be identified. Photographs shall be GPS enabled.

.4 The Consultant and the County reserve the right to take additional photographs to document

any part of the Work at any time.

1.14 Contractor's Use of Site

.1 Use of site: exclusive and complete for execution of work in accordance with General Conditions except as follows:

.1 The Contractor and stored materials shall not interfere with the Owner's access to

the site for operation, maintenance and repair of existing facilities. Provide temporary access to the existing facilities as may be required and move materials as requested by the Owner.

.2 At all times cooperate with the Owner.

.2 The Contractor shall be responsible for site security for the duration of the Contract. Where

security is reduced by work of Contract, provide temporary means to maintain security.

.3 Obtain and pay for use of additional storage or work areas as required. Parkland County has identified Lot D as the potential laydown area. If this laydown areas is being used, it must be kept in a neat and tidy condition and it must be restored to pre-construction condition. Providing sign saying “Fallis Day-Use Parking is Unavailable – Use Wabamun Boat Lunch” at the laydown area, and construction metal fencing to protect the laydown area.

Page 8: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 5 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

.4 All stipulations in the temporary workspace agreements and utility Right-of-Ways must be followed.

1.15 Streets and Roads

.1 The County assumes no responsibility for the condition, repair and maintenance of streets or roads including without limitation, public road, street, highway, private road, rural municipality road, alley, haul route, road allowance, access or structure that the Contractor uses in performance of the Work.

.2 When using existing public or private streets and roads, abide by governing laws and

regulations. This includes obtaining and paying for permits and fees, reporting quantities and following temporary, seasonal and permanent restrictions, following designated routes, performance of required maintenance and repairs. A Parkland County Industrial Haul agreement may be required for the contractor. Payment shall be deemed to be incidental to the prices stated in the Pricing Form.

.1 https://www.parklandcounty.com/en/live-and-play/resources/Documents/--

AGREEMENT-2018-memorandum-revised-March-2018-website-14.pdf 3 Contact the authority having jurisdiction prior to using streets and roads required for

execution of the Work. Upon request, provide evidence to the Consultant and County that suitable arrangements and approvals have been obtained and implemented. Such arrangements and approvals shall be in place a minimum 14 days prior to commencing the Work at the Work Site.

.4 If the Contractor chooses to use access routes across private property, the Contractor shall

make their own arrangements with the Landowner. The Contractor will be held responsible for damages to private property resulting from the Contractor’s operations.

.5 Maintain streets and roads in a condition agreeable to the County and authority having

jurisdiction. The Contractor shall be responsible for damage to streets and roads as a result of their operations.

.6 Restore damage at the Contractor’s own expense in a timely fashion.

1.16 Responsibility Regarding Existing Utilities and Structures

.1 The Contractor shall be responsible for existing utilities and structures in proximity to the Work.

.2 Develop and implement temporary support, protective and other measures required by the

respective utility owner. .3 Within three days request from the Consultant, provide details of the selected means and

methods, which have been approved by the utility owner, for support, protection and meeting of utility owner requirements.

.4 Where existing utilities or other structures are found to be in conflict with the Work and

temporary support, protection or avoidance of the utility or structure is not possible, the Contractor shall notify the Consultant. The Contractor shall then proceed as directed by the respective utility owner.

.5 All system shutdowns and service interruptions must be approved by and coordinated with

the Owner. Contractor obligated to provide temporary measure to maintain the system still works during the service interruptions.

Page 9: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 6 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

.6 All temporary utility shut-downs, service disruptions and traffic accommodations must be pre-approved by the utility owner, Consultant and the County. Provide a minimum of seven days’ notice prior to any proposed shut-downs or restrictions.

.7 Costs incurred for utility service disruption and repair caused by the Contractor’s operation

shall be deemed to be incidental to the prices stated in the Pricing Form. Maintenance of existing utilities and structures repaired or supported are the responsibility of the Contractor for the duration of the Warranty Period.

.8 Where unknown utilities are encountered, immediately notify the Consultant and confirm

findings in writing. .9 Record locations of existing, re-aligned and abandoned utilities indicating horizontal

distances and vertical elevations.

1.17 Co-ordination of Utilities

.1 All co-ordination of utility service provision is to be considered incidental to the Work. 1.18 Existing Appurtenances and Features

.1 Surface features, below-grade features and adjacent properties or lands on and off the Work Site used by Contractor and disturbed by Contractor’s activities shall be reconstructed.

.2 Where reconstruction details are not provided, the Contractor shall restore to at least the pre-

construction condition and in the absence of reliable pre-construction data, to the reasonable satisfaction of the landowner, authority having jurisdiction, the County and Consultant.

.3 Upon completion of construction, existing appurtenances shall be left visible, at the specified

elevation, clean and in proper working condition. Items damaged during construction shall be repaired by the Contractor at their own expense.

.4 Payment for inspection and restoration of existing appurtenances and features shall be

deemed incidental to the prices stated in the Pricing Form, unless specified otherwise.

1.19 Utility Right of Ways

.1 The Owner will obtain Utility Right of Ways and right of entry to construct those works which cross private or public property as shown on the Drawings. The Contractor shall follow all terms and conditions of the agreements. All costs to follow the terms and conditions of the agreement will be considered incidental to the work.

.2 If the Contractor requires Utility Right of Ways or working areas in addition to those obtained

by the Owner, the Contractor shall obtain and pay for them. .3 Damages to adjacent property shall be borne by the Contractor. .4 No work whatsoever shall be performed in Utility Right of Ways or other non-owned property

without written permission from the property owner. No claim shall be made by the Contractor on account of such permission not being granted.

Page 10: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 7 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

1.20 Relics and Antiquities

.1 Give immediate notice to the Consultant if evidence of archaeological finds are encountered during construction and await the Consultant's written instructions before proceeding with the work in this area. The Contractor shall treat any such finding of any evidence that might be archaeological in nature as confidential and ensure that their staff and sub-consultants to not realise any information in this regard to the media, the public by any means or any other party, including social media,

1.21 Remove and Dispose Marginal Materials Offsite

.1 Unsuitable Materials to be removed, hauled and disposal of the unsuitable materials to the Landfill site as chosen by the Contractor.

.2 Obtain all necessary approvals and/or permits, from the Owner of the disposal site, and any

governing authority prior to dumping any materials. .3 No separate payment shall be made for disposal of excess excavated material. 1.22 Noise and Dust Control

.1 Prevent noise from becoming an annoyance to neighbouring landowners at the request of and to the satisfaction of the Parkland County Authority. Required prevention may include, but is not limited to, locating stockpiles to act as sound barriers and using methods of minimizing or reducing noise created by machinery and equipment. Installation of noise monitors shall be required as a condition of this contract. Noise that exceeds the level as specified in the Community Standards Bylaw is and indication that noise may be annoyance; and

.2 ensure compliance with the Environmental Protection & Enhancement Act regarding dust

and air quality. .3 Submit a site-specific Best Management Practices plan in accordance with Specification 01

35 43. 1.23 Contractor Submission Requirements

.1 A list of the documents and information to be submitted by the Contractor is presented in the table at the end of this Section. Please note that this list does not include all required submissions (e.g. samples or shop drawings).

.2 Submit all information and documents by the dates indicated, unless otherwise directed by

the Consultant. .3 The Contractor may not submit more than fifteen (15) submissions requiring review by the

Consultant per week unless these submissions have been reviewed by the Consultant and returned to the Contractor.

1.24 Site Security

.1 Despite what facilities and security as the Owner may or may not have on the existing site, the Contractor will be totally responsible for the security of its own equipment, tools, materials, temporary facilities and the completed and stored works under its care and custody and will take appropriate steps to ensure that security to the extent it does not affect the work of others on the site.

Page 11: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 8 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

.2 Maintain site security by:

.1 Restrict access to the site to those requiring access and limiting visitors and tours. .2 Provide temporary security fencing for open excavations. .3 Report any breaches in security and/or suspicious situations to the Consultant and

Owner (and police if appropriate). 1.25 Work Restrictions

.1 Hours of Work

.1 The hours of work shall comply with County, Provincial, and Federal laws and regulations. At all times, operational noise shall be kept to a practicable minimum for construction operations.

.2 The Consultant shall be informed not less than forty-eight (48) hours in advance if

work is to be carried out, with all approvals in place, beyond the normal hours of work established in the Work Schedule.

.3 Extension of Hours of Work approval from the County or Consultant does not relieve

the Contractor of his responsibility for attaining all required approvals from other governing agencies.

.2 Night Work

.1 Obtain written authorization for all construction activities where noise will occur outside of the normal permitted noise windows as stipulated in Parkland County Community Standards bylaw 03-2012.

.3 Noise .1 Abide by Parkland County Community Standards Bylaw 03-2012.

1.26 Requests for Information (RFI)

.1 Submit formal written requests for information (RFI), in a format agreeable to Consultant, when additional information, clarification or input from Consultant is required.

.2 The Contractor is solely responsible for issuing RFIs in a clear and timely manner. Allow the

Consultant a minimum of seven days to respond. Claims for delays due to the Consultant’s failure to respond to an RFI within minimum response time will not be considered.

.3 Vague, unclear, incomplete and frivolous RFIs will be returned to the Contractor requesting

additional information. .4 If a Contractor finds discrepancies in, or omissions from the Appendices, Specifications or

other documents or has any doubt as to the meaning or intent of any part thereof, he shall at once inform the Consultant, who may send a written instruction or explanation. Every request for an interpretation shall be made in writing.

.5 Discussions at Tender briefings or other oral discussions shall not become part of the Tender

documents unless confirmed by Addenda.

Page 12: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 10 00 Parkland County GENERAL REQUIREMENTS Issued for Tender Page 9 of 9

SPC-01 10 00-General Requirements-60638222_new.doc

1.27 Layout of the work

.1 the Owner shall, in consultation with the Contractor, establish reference points for construction which are necessary for the Contractor to proceed with the work.

.2 The Contractor shall be responsible for paying for all stakes, laying out the Work, shall

preserve and protect the established reference points, and shall not change or relocate the established reference points without the approval of the Consultant.

.3 The Contractor shall advise the Consultant whenever any established reference points is

lost, destroyed, damaged, or requires relocation as result of the Contractor’s operations. The cost to re-establish any reference point that is lost, destroyed, damaged, or requires relocation as a result of the Contractor’s operations, shall be at the Contractor’s expense.

.4 The Contractor shall, before commencing work at any point, satisfy itself as to the meaning

and accuracy of all stakes and instructions. The Contractor shall not have any claim for an allowance based on alleged inaccuracies, or as a result of the Contractor’s failure to read reference points correctly or its failure to interpret instructions correctly.

.5 If the Contractor finds a discrepancy between the drawings and the physical conditions of the

locality or any errors or omissions in the Drawings, Shop Drawings or Specifications or in the layout as given by points of instruction, the Contractor shall advise the Consultant forthwith in writing, and the Consultant shall promptly review same and issue appropriate instructions. Any Work done after such discovery and before further updated instructions are issued by the Consultant shall be done at the Contractor’s risk and any resulting expense will be that of the Contractor’s expense.

2.0 PRODUCTS

.1 Not applicable. 3.0 EXECUTION

.1 Not applicable.

CONTRACTOR SUBMITTAL SCHEDULE Specification

Section Description Date Required 01 10 00 Copies of Permits/Licenses Upon Consultant’s request. 01 10 00 Traffic Haul Safety Strategy (THSS) 10 days from Notice of Acceptance. 01 32 17 Construction Schedule 10 days from Notice of Acceptance. 01 33 00 Material and Shop Drawing Schedule 10 days from Notice of Acceptance. 01 35 43 ECO Plan 10 days from Notice of Acceptance. 01 35 43 Best Management Practices Letter 10 days from Notice of Acceptance.

01 35 29.06 Safety Meeting Minutes Weekly. 01 35 29.06 Accident Reports Promptly after incident. 01 35 29.06 WHMIS Data Sheets Upon delivery of materials to site.

01 55 26 Traffic Accommodation Strategy 10 days prior to undertaking any construction

Notice to Residents 10 days prior to construction Material Testing Report After construction/inspection

01 78 00 Record Drawings (2 sets) At project completion/prior to final inspection.

END OF SECTION

Page 13: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 1 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

1.0 GENERAL 1.1 General

.1 Within the Issued for Quotation documents the term “Tender” will be found and when so, it is intended to mean “Request for Tender”. Payments will be made on the basis of the unit prices and lump sum prices bid in the Tender. Additions and credit to the Work will be assessed based on the prices provided on the Bid Form.

.2 Each unit or lump sum price stated on the Bid Form shall constitute full compensation as

herein specified for each item of Work completed in accordance with the Drawings and Specifications. The Contractor shall be aware that if any cost item is not specifically included as a pay item on the bid form, the onus shall be on the Contractor to ensure that all project costs are built into the unit price and lump sum pay items on the bid form.

.3 Unit and lump sum prices bid shall be full and complete compensation for all work on the

project. Payment will be made for only those unit price and lump sum items listed on the bid forms. All other costs that the Contractor may occur throughout the project shall be built into the unit price and lump sums bid including profit, management, administration, safety, permit and all other general costs which for this project will be considered incidental to the work. For greater clarity, no separate claim shall be issued or payment made for items such as:

.1 Environmental protection, ECO Plan and Erosion and Sedimentation Controls .2 All Survey or quantity calculations .3 Quality Control including Material Testing or Re-testing .4 Site office and Washroom .5 Laydown Yard Setup or Removal or Clean-up .6 Materials Onsite but not yet incorporated .7 Restoration of Surface Features .8 Utility and Infrastructure locating and/or Hydrovacing .9 Permitting, Regulatory Requirements .10 Project Scheduling and Reporting .11 Utility and/or stream crossings .12 Traffic Accommodation Plan The above list of items excluded from separate payment shall not be considered to be complete and Item 1.1.2 above shall govern.

.4 The method of measurement of the quantities for payment and the basis for payment will

be in accordance with the following items of this section. All measurement will be done using generally accepted field survey methods and to the satisfaction of the Consultant.

Page 14: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 2 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.5 When the Contractor provides any survey and/or quantity calculations or modelling, the onus shall be on the Contractor to provide such information in a form and level of detail determined to be acceptable by the Consultant and the Contractor shall provide additional information to justify the quantity or validate the claim to the satisfaction of the Consultant, at the expense of the Contractor.

.6 The Contractor shall provide Schedule of Values for each Lump Sum item to provide a

breakdown of the Sum in enough detail to facilitate continued evaluation of the progress of the work included at the time of bidding. Schedule of Values will be used as the basis for reviewing applications for payment of the lump sum items in terms of validation of Progress Payments. The breakdown of the value of any lump sum item will be subject to the approval of the Consultant, who may require the Contractor to provide additional information to validate the breakdown prior to approval.

.7 Should the Consultant determine that any component within the Schedule of Values does

require justification to demonstrate the reasonableness of the amount, the Contractor shall provide further information to substantiate and justify or revise the amounts to the satisfaction of the Consultant.

.8 The prices bid for various items of work, unless specifically noted otherwise, shall include

the supply of all labour, plant, products, material, and all equipment, machines, tools, transport, necessary to construct the Work in accordance with these specifications.

.9 The prices bid for supply and installation shall be full compensation for supplying,

hauling, handling, storing, installing, cleaning, testing, and placing in service together with all other work subsidiary and incidental thereto for which separate payment is not provided elsewhere.

.10 For this project, no payment will be made for materials onsite that have not yet been

incorporated into the work. .11 Other materials on site, whether existing structures, vegetation, topsoil, gravel, sand or

other excavated or piled materials, are the property of the Owner on which the Work is located. Only those materials specifically noted in these specifications as belonging to the Contractor shall become the Contractor's property.

.12 Cost of utility locates and hydrovacing to verify utilities and other buried infrastructure is

incidental and included in the unit prices. Contractor must not backfill any hydrovac exposed utilities until a record survey is done by the Contractor of the detailed location and elevation of the utility.

.13 Project schedule reporting and updating is to be included in the unit prices. .14 Where there are excess excavated materials, unsuitable materials excavated or materials

of any kind that are excavated but not used in the Work, such materials are not the property of the Contractor unless authorized in writing by the Consultant or specified to be disposed of by the Contractor.

.15 Excess materials shall be hauled and removed offsite at the expense of the Contractor

for drainage ditch installation. No separate payment will be made for this item.

.16 Where tree clearing, excavating, disposal, trenching, or other ground disturbance is involved outside of drainage ditch areas, the prices bid shall include surface restoration including topsoil and seed or gravel and/or asphalt, depending on the location in accordance with the specifications and drawings and to the satisfaction of the Consultant.

Page 15: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 3 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

For greater clarity, any disturbance by the Contractor must be restored and no separate or extra payment will be made in that regard.

.17 The Contractor shall utilize safe trench slopes, shoring, bracing cages or shields, and de-

watering to ensure safe working conditions and include any such provisions in the unit prices bid for any items that require excavation, trenching and/or backfilling. The Contractor shall be responsible to determine the most appropriate means, methods and techniques, including but not limited to whether open trench, box trench or trenchless methods are best utilized at any specific location. No additional or separate payment will be made.

.18 Any item of the work not called for in the specifications or shown on the drawings but

clearly required to meet the intent of design and normally provided for the proper operation of the work shall be provided as if specifically called for in these specifications. No additional payment will be made for this incidental work.

.19 The Contractor shall ensure all work meets any environmental and/or biological

requirements including all required permits and approvals. 1.2 Definitions

.1 Unit price is price per unit of measurement for materials, equipment, services, or a

portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by these specifications are increased or decreased.

.2 Lump Sum price is price to complete the task to include all materials, equipment,

services, labour and all incidental and associated works to execute the task. Payment shall be full or partial depending on the progress of each lump sum item. The contractor shall provide a Schedule of Values to facilitate continued evaluation of the progress.

1.3 Applications For Progress Payment

.1 Submit progress claim to Consultant within seven working days after each month end for each application for payment. Claim to cover work completed during the preceding month. Progress claim to include all labour, equipment used and materials incorporated in Work. All applications for payment shall include all survey and quantity calculations necessary to justify the quantities proposed by the Contractor and all materials testing results with written compliance certification. For any lump sum items, a Schedule of Values of the various parts of the work and support documents shall be included. After approval by the Consultant, the cost breakdown shall be used as the basis for progress payments.

.2 The Onus shall be on the Contractor to provide Survey, Quantity and quality control

information to the Consultant for each item in a professional manner that is clear, well organized, complete and inform and format acceptable to the Consultant. Failure to do so may result in rejection of payment for certain items or the entire monthly claim or a deferral of certain items to the next month’s claims.

.3 The onus shall be on the Contractor to provide documentation with clearly demonstrates

that the materials and workmanship meet the requirements of the drawings and specifications, including survey details and quantity calculations, subject to the satisfaction of the Consultant.

Page 16: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 4 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.4 Submit at least 7 working days prior to the application for payment all testing information that pertains to work that is subject to that specific claim, all of which must include a written compliance certificate from the professional Consultant responsible.

.5 Submit, with the application for progress payment, a letter of clearance or certificate from

Workers’ Compensation Board verifying that all assessments due by the Contractor have been fully paid.

.6 Submit, with the application for progress payment, a current Statutory Declaration

verifying that all Subcontractors, Suppliers, labour and accounts for services, materials, machinery and equipment, and any other indebtedness, which may have been incurred by the Contractor, directly or indirectly, in the performance of the Work have been fully paid by the Contractor except of unpaid holdbacks on such subcontracts and that no lien has been filed against the Contractor, the Project, the premises or any materials supplied to or incorporated into the Work or in respect of anything done under or by virtue of the Contract.

.1 A Statutory Declaration shall be submitted for the second and all subsequent

payment applications. .2 If only one payment application is made for the Work, the Statutory Declaration is

to be submitted with the first payment application. 1.4 Progress Payment

.1 Provided that the Contractor’s application for the payment is complete and includes the necessary backup information, the Consultant shall issue a recommendation for payment within 10 days after the Consultant’s approval of the application for payment and promptly forward claims to the Parkland County for processing.

.2 If the Consultant amends the application, Consultant will give notification in writing giving

reasons for amendment. .3 If the quantities for any unit price item have not been agreed upon between the

Contractor and the Consultant by the necessary cut-off date for a monthly progress payment, the Consultant shall use discretion to either defer payment for any such items or approve payment of a lesser quantity pending finalization of any quantities in question at a later date.

1.5 Change Orders

.1 Complete and promptly return all change price requests issued by Consultant, quoting

unit and/or lump sum prices as requested. Include appropriate supporting documentation to verify prices.

.2 Do not proceed with work affected by price request until authorized to do so by Change

Order approval by the Consultant. .3 Make no change in Work unless Change Order issued. Change Order is only valid when

signed by Consultants and the Contractor.

Page 17: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 5 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

1.6 Deficiency Holdbacks .1 The Consultant shall be at liberty to retain a deficiency Holdback for a value of two times

the estimated value to rectify the deficiency. .2 Deficiency holdbacks may be applied with respect to inadequate or incomplete

compliance reporting and/ or proof of compliance. 2.0 PRODUCTS

.1 Not used. 3.0 EXECUTION

.1 Not used. 4.0 MEASUREMENT FOR PAYMENT CLAUSES 4.1 Bid Schedule

.1 Payment will be made on the basis of the unit prices and lump sum prices bid in the Tender on the Bid Form.

.1 Unit rates will be paid on a unit rate basis following the term in which the work is

completed and as approved by the Consultant. .2 Lump sum items will be paid full or partial depending on the progress of each

lump sum item and as approved by the Consultant. .3 Works should be in accordance with the Drawings, and these Specifications

Division 01 to 33 and Appendices. 4.2 Bid Schedule A - General

.1 Mobilization and Demobilization

.1 Mobilization and demobilization shall include the Contractor's costs of mobilization at the beginning of the project; and the costs of demobilization at the end of the project, including clean up and restoration of all areas disturbed by the Contractor to the satisfaction of the Consultant. This item will be measured and paid as a Lump Sum item, except payment will be issued as indicated below.

.2 Payment Includes: transporting labour, equipment and materials to and from the

site; setting up the site; setting up equipment, temporary facilities and site office; removal of equipment, facilities and site office upon completion of the Work; removal of equipment accesses; site clean-up and closeout works.

.3 Payment will be made by lump sum as follows, as approved by the Consultant:

.1 60% with the first invoice after Contractor equipment, crews and facilities

have arrived on site to commence the Work. .2 40% at issuance of the substantial performance and completion of site

restoration and clean-up.

Page 18: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 6 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.2 Remove Additional Unsuitable Materials and Dispose Offsite. Supply and Install Crushed Gravel (Provisional) .1 Subgrade preparation on culverts and roadways, if recommended by the

Geotechnical Engineer and approved by the Consultant, unstable subgrade soils shall be excavated to the area and depths recommended and approved and replaced with granular base and compacted. Payment will be per cubic metre measured in place. Payment shall be compensation for all labour, materials, equipment, tools and incidentals necessary to complete the work. This is a provisional item and the quantity mentioned in the bid schedule can increase, decrease or may not be used at all.

.3 Dispose Excess Topsoil Offsite (Provisional)

.1 The payment for dispose excess topsoil will be made at the unit price bid per

cubic metre for topsoil stripped, loading, hauling, and disposal offsite. There will be no provision of overhaul payment. This is a provisional item and the quantity mentioned in the bid schedule can increase, decrease or may not be used at all.

.4 Import Clay Fill and Placement with Compaction (Provisional)

.1 The payment for imported suitable clay used for fill lower areas will be measured

and paid at the unit price bid per cubic metre for supplying, hauling the material to the site, placing and compacting, and all other incidentals necessary to complete the work. This is a provisional item and the quantity mentioned in the bid schedule can increase, decrease or may not be used at all.

5 Quality Assurance

.1 As directed by the Consultant and paid by Cash Allowance .2 Quality Assurance will be for independent testing required by the Consultant to

determine if the Work is in conformance with the Contract Documents. These field tests shall be in addition to the mandatory field tests as necessary for Quality Control which are to be paid by the contractor.

.3 Quality Assurance tests as directed by the Consultant shall be paid as per

invoice submitted by the supplier and the laboratory. .4 The Contractor shall pay the testing firm for testing required by the Engineer.

Costs to be reimbursed to the Contractor through Quality Assurance Cash Allowance.

4.3 Bid Schedule B – Drainage Improvement Construction

.1 Topsoil Removal and stockpile Onsite in Lot D for Re-use

.1 The payment for topsoil stripping will be made at the unit price bid per cubic

metre for topsoil stripped, stockpiled onsite in Lot D, tested for re-used. This payment will be full compensation for all operations including all labour, material, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

Page 19: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 7 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.2 Clearing, Grubbing and Offsite Removal .1 The payment for clearing, grubbing, removal of trees less than 100 mm diameter

including roots will be measured and paid at the unit bid price bid per square metres for clearing, grubbing, tree removal, removal and disposal of brush and weeds offsite.

.2 This payment will be full compensation for all clearing, grubbing, mulching,

removal of trees, roots, brush and weeds including all labour, material, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

.3 There will be no additional payment made for obtaining any and all regulatory

permits, nesting survey, it will be considered incidental to work. .4 Measurement and payment shall only be made for clearing and grubbing within

the Road Right of Way and Utility Right of Way. Payment shall not be made for clearing and grubbing within the temporary workspace.

.3 Tree Removal

.1 The payment for tree removal for tree larger than 100 mm diameter will be made,

shall be the actual number of trees removed and disposed of to accommodate the proposed works. The consultant will be flagging the trees that require removal. Payment shall include removal of existing trees, loading, hauling, including dumping fees if any, restoration of disturbed surfaces, dust control, maintenance and cleanup of site, equipment, tools and incidentals required for the removal and disposal of existing trees at locations to be determined by the Contractor.

.2 Measurement and payment shall only be made for clearing and grubbing within

the Road Right of Way and Utility Right of Way. Payment shall not be made for clearing and grubbing within the temporary workspace.

.3 Permit and nesting survey will be incidental to the tree removal work.

.4 Install Drainage Ditches

1 The payment for drainage ditch will be made at the unit price bid per linear metres for excavating drainage ditches to the pre-topsoil grades and compacting.

2 Removal of marginal material and dispose to a contractor selected disposal site.

3 All side slopes to be finished to allow topsoil and seeding and maintenance of slopes.

4 This payment will be full compensation for all operations including all labour,

material, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

Page 20: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 8 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.5 Supply and install 300mm Diameter CSP Culvert

.1 Supply and install 300 mm diameter CSP Culvert will be measured and paid as a lump sump for the culvert has been installed for the diameters, lengths and materials as shown in the Bid Form. Payment shall be compensation in full for excavation of minimum of 450mm depth of peat, granular material for culvert bedding and backfill compacted in place, dewatering, beveled end, filter fabric, roadway restoration to existing condition, remove and restore existing fence, and other work incidental to complete the installation.

.6 Road Elevation Adjustment at Culvert

.1 Road elevation adjustment at culvert will be measured and paid as a lump sump

for costs involved roadway elevation adjustment to the proposed grades shown on the drawings in Area 6 & 7 (at TWP Road 532 culverts), and all labour, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

.2 Payment shall include field fit grade adjustments with additional of granular

material at the road surface to achieve a minimum side slope from centre line for positive drainage at intersections and cross streets to the satisfaction of the Consultant.

.3 Roadway structures, compaction requirements, and material testing must follow

the Parkland County Engineering Design Standards.

.7 Install Topsoil from Onsite Lot D Stockpile .1 Placement of minimum 100 mm depth of reused topsoil from onsite stockpile or

depth match existing, whichever is greater for sod areas will be measured in square metres, determined by field measurements.

.2 Placement of minimum 150 mm depth of reused topsoil from onsite stockpile or

depth match existing, whichever is greater for hydroseed areas will be measured in square metres, determined by field measurements.

.3 Topsoil Requirements

.1 It shall be free of subsoil, clay lumps, stones, live plants and other roots,

sticks, or other extraneous matter.

.4 The bid price shall include hauling, stockpiling, removal and disposal of all weeds, roots and lumps and stones larger than 25 mm in diameter and fine grading/rolling.

.8 Supply and Install Hydroseed over Topsoil

.1 Payment for hydroseeding shall be measured in square metres, as determined

by surface area specified. Areas of blending beyond the limits of construction will not be measured for payment. This payment will be full compensation of mobilization, supplying hydroseed, preparing the surface, hydroseeding and harrowing the designated areas; and all labour, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

.2 Unit price shall include repair the grass areas until the end of warranty period.

Page 21: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 9 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.9 Supply and Install Sod over Topsoil

.1 Payment for sod shall be measured in square metres, as determined by surface area specified. Areas of blending beyond the limits of construction will not be measured for payment. This payment will be full compensation of mobilization, supplying sod, preparing the surface, sodding and harrowing the designated areas; and all labour, equipment, tools and incidentals necessary to complete the work to the satisfaction of the Consultant.

.2 Unit price shall include repair the grass areas until the end of warranty period.

.10 Supply and Install Road Delineator

.1 Construction of delineator shall be measured for payment by the unit including all labour, material, equipment, tools and all incidental work necessary to complete the work.

.2 Install delineator in accordance with manufacturer’s instructions.

.11 Cleaning Existing Culvert after Construction

.1 Payment for cleaning existing culvert after construction will be measured and

paid as a lump sump costs involved cleaning, removing and disposing of sediment, remove and dispose existing beveled end, supply and install new beveled ends, including all labour, equipment, tools and all incidental work necessary to complete the work.

4.4 Non-Payment and Incidental Items

.1 Activities for which no specific Pricing Form item is provided, but which are necessary to complete the Work in accordance with the Contract Documents and maintain and repair the Work, shall be deemed incidental to the prices stated in the Pricing Form.

.2 This includes the following activities, which shall be deemed incidental to the prices

stated in the Pricing Form. No separate measurement and payment shall be made for these items. Note that this list is not intended to be exhaustive.

.1 Examination of site conditions; providing documentation and photographs; use of

the Work Site and haul routes; protection and restoration of property; obtaining easements, right of way, approvals, permits and agreements; responsibilities regarding existing infrastructure; utility protection, locating, and coordination; coordinating, managing and providing service interruptions and shutdowns; protection of the Work; removal and disposal of materials; noise and dust control; maintaining documentation; abiding by work restrictions.

.2 Providing, submitting and arranging for product substitutions. .3 Providing project management and coordination; schedules, progress reports

and notifications; attending meetings, calls and discussions; addressing public concerns and complaints; managing personnel and supplies; coordinating transportation; supervision to complete the Work.

.4 Providing submittals and product data; delivery, storage and handling.

Page 22: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 10 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.5 Providing and implementing safety measures; notices; safety program; task hazard assessments; safety meetings; emergency management plan; equipment; accident reports.

.6 Providing environmental procedures; temporary surface drainage and pumping;

temporary erosion control products; site clearing; pollution control; managing spills.

.7 Providing quality control and assisting with quality assurance; demonstration

testing; visual inspections. .8 Providing security; access; detours and accommodation to private property;

protection, maintenance and clean-up of haul routes; temporary facilities, controls and works; parking; temporary utilities; water supply; signs and notices; traffic control; temporary fencing.

.9 Providing sign saying visitors can not park at the laydown area, and construction

metal fencing to protect the laydown area. .10 Remove and reinstall existing “kids at play” sign. .11 Providing equipment; transportation; documentation; replacement of defective

products, equipment and articles; delivery, handling, storage and protection; quality and workmanship.

.12 Providing on-going cleaning; record documents; completion and acceptance

procedures; warranty; visual warranty inspections; correction of deficiencies; removal and replacement of rejected work; repair of damaged assets.

.13 Plugging, blocking and isolating; providing redundancy; monitoring; handling

water and wastewater to prevent damage and improper discharge; preventing discharge of debris; removing and disposal of debris; capturing and disposing of water and wastewater from the Work.

.14 Any items not specifically shown on the bid form shall be included in the unit

prices or lump sum prices bid for other items.

.3 Dewatering of Excavation

.1 Dewatering excavation during construction will be not measured and paid separately. The cost shall be covered under the unit price of drainage ditch and culvert installation. The work shall include but not limited to the procurement, construction, operation, maintenance, and removal of equipment and temporary structures to permit workable conditions in all excavations.

.4 Hydrovac

.1 No payment will be made to hydrovac utilities that require physical locating

before crossing; such as gas lines and any other shallow utilities.

.2 Hydrovacing utilities shown on the drawings or located by 3rd party utility owners are considered incidental and no payment will be made.

Page 23: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 29 00 Parkland County PAYMENT PROCEDURES Issued for Tender Page 11 of 11

SPC-01 29 00-Payment Procedures-60638222_new.docx

.5 Quality Control

.1 Quality Control testing shall be completed by the Contractor and all costs to complete quality control testing shall be included as incidental to the Contract and shall not be paid as an extra. Quality Control includes, but is not limited to, density testing, sieve analysis, and Marshall Density.

.6 Traffic Control Including Traffic Accommodation Plan

.1 No payment will be made for all costs involved in providing traffic control and

road maintenance. This includes but is not limited to: .1 Traffic control or diversion work intended to be used for the period of the

work. .2 Site Maintenance including cleaning the site and restoring disturbed

areas. .3 Removal and disposal of mud and debris from streets and sidewalks

within the project boundary, and outside the project boundary when tracking of mud or debris from the construction site occurs. (Haul routes).

.7 Bird Nesting Surveys

.1 No Additional and Separate Payment for this Item. Contractor shall ensure that

bird nest surveys have been completed in accordance with the regulations and requirements of the Migratory Bird Act and all Territorial and Federal legislation and requirements.

.8 Erosion and Sedimentation Control .1 No Additional and Separate Payment for this Item. The cost of this task should

be Included in other pay items.

.9 Survey Layout

.1 No Additional and Separate Payment for this Item. The cost of this task should be Included in other pay items.

END OF SECTION

Page 24: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 31 19 Parkland County PROJECT MEETINGS Issued for Tender Page 1 of 4

SPC-01 31 19-Project Meetings-60638222.docx

GENERAL

Administrative

Pre-Construction Meeting

Introductions.

Confirmation of official representative of participants in the Work (Contractor’s Superintendent, Contractor’s Project Manager, Contractor’s Safety Professional, Contractor’s Scheduler and Quantity Surveyor, Contractor’s Foreman, the Resident Consultant and Owner).

Identification of Sub-Contractors.

Responsibilities of the Contractor, and the Consultant.

Lines of communication including contact list.

Page 25: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 31 19 Parkland County PROJECT MEETINGS Issued for Tender Page 2 of 4

SPC-01 31 19-Project Meetings-60638222.docx

Site safety plan and procedures, site restrictions and hours of operation.

Occupational health and safety relationships and responsibilities. Submittal of Site Safety Manual and implementation of Site orientation program.

ECO plan, Environmental responsibilities, Sustainable issues compliance and coordination.

Permitting requirements and applicable local regulations.

Schedule of Work, progress scheduling, and schedule reporting requirements.

Schedule of submittals.

Start-up submittals.

Requirements and schedule for, laydown area, utilities, fences.

Delivery schedule of major and key equipment.

Site security and arrangements for Consultant and Owner access to the Site.

Document Management Procedures (method of tracking and filing requests for information (RFIs), COs, etc., procedures used for logging record drawing information, and other document related issues).

Submittal procedures and schedule.

Change Order procedures.

Record Drawings.

Operation manuals and maintenance data.

Acceptance, warranties.

Monthly progress payments, administrative procedures, holdbacks.

Protocols for communication, reporting, inspection, etc.

Inspection and testing agencies or firms.

Ambiguities or questions of interpretation identified in these specifications.

Material Testing

Daily Issue Meetings (As Required)

Page 26: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 31 19 Parkland County PROJECT MEETINGS Issued for Tender Page 3 of 4

SPC-01 31 19-Project Meetings-60638222.docx

Progress Meetings

Review approval of minutes of previous meeting.

Old business.

Occupational health and safety incidents, records and procedures.

Schedule (provide a 1-week ‘look-ahead’ schedule – Refer to Section 01 32 17 – Project Management and Coordination).

Document Management Issues.

Submittal status.

Requests for information.

Proposed Contract modifications.

Change Order status.

Site coordination.

Quality control.

Site cleanliness.

Work planned for next period.

Erosion and Sedimentation Control Measures.

Other action items.

Totals of all personnel currently on Site associated with the Contract, broken down by trade and Sub-Contractor including all staff.

Page 27: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 31 19 Parkland County PROJECT MEETINGS Issued for Tender Page 4 of 4

SPC-01 31 19-Project Meetings-60638222.docx

Totals of all major equipment currently on Site, over a two thousand dollar replacement value, broken down by type and Subcontractor.

Site Administration / Contract Coordination Meetings

Special Meetings

PRODUCTS

EXECUTION

END OF SECTION

Page 28: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 32 17 Parkland County PROJECT MANAGEMENT AND COORDINATION Issued for Tender Page 1 of 4

SPC-01 32 17-Proj MgmntandCoord-60638222.docx

1.0 GENERAL

1.1 Summary

.1 Section includes administrative and procedural requirements for planning, monitoring, and documenting the progress of construction during performance of the Work, including the following:

.1 Pre-Construction Meeting.

.2 Construction Progress Meetings.

.3 Work Schedules.

.4 Construction Progress Reports.

.5 Notifications to Affected Parties.

.2 The Contractor has the obligation and responsibility at all times to plan and monitor all of its activities, anticipating and scheduling its staff, materials, plant and Work methods in a manner that is likely to ensure completion of the Work in accordance with the terms and conditions of the Contract and at a rate that will allow it to be completed within the Contract Time.

1.2 Definitions

.1 “Day”: shall be defined as a calendar day not working day.

1.3 Submittals

.1 Startup Work Schedule

.1 Submit, within 7 days after Notice of Award, a preliminary schedule indicating planned operations.

.2 Work Schedules

.1 Submit an updated Work Schedule prior to each Construction Progress Meeting or application for payment, whichever occurs earlier.

.3 Construction Progress Reports

.1 Submit a written report on actual progress with each Work Schedule. More frequent reports may be required should the Work fall behind the accepted Work Schedule.

.4 Notifications to Affected Parties

.1 Submit a notification template for Consultant and County review a minimum 7 days prior to distributing.

Page 29: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 32 17 Parkland County PROJECT MANAGEMENT AND COORDINATION Issued for Tender Page 2 of 4

SPC-01 32 17-Proj MgmntandCoord-60638222.docx

1.4 Pre-Construction Meeting

.1 The Consultant will chair a pre-construction meeting to review items stated in the preliminary meeting agenda below and establish a working understanding between the parties as to their relationships during performance of the Work. The meeting shall be attended by the following at a minimum:

.1 The County

.2 Consultant

.3 Contractor

.2 Refer to Section 01 31 19 Project meetings

1.5 Construction Progress Meetings

.1 Attend Construction Meetings, which will be held at least bi-weekly. Construction Meetings will be held more frequently if required. Construction Meetings will generally cover health and safety, contract administration and other construction related issues.

.2 The Contractor shall be represented at the meeting by at least one person of sufficient authority within the Contractor’s organization to make binding decisions for the work being discussed.

.3 At a minimum, present the following at each Construction Meeting:

.1 Contractor’s Contract Work Schedule as a hard copy in graphical format comparing original planned progress to actual progress updated to at least within one week of the meeting date.

.2 Brief Contract Progress Report in writing.

.3 Discuss upcoming high risk work activities and Contractor’s risk mitigation measures.

.4 Discuss recent near misses and incidents that occurred since previous meeting and corrective actions taken by Contractor.

.4 Record of Meeting:

.1 Within seven days after each meeting, the Consultant will prepare and distribute record of meeting of the Construction Meeting to the County and Contractor.

.2 The County and Contractor shall review the record of meeting and report any discrepancies or omissions in the record of meeting directly to Consultant within three days of receiving them, otherwise the record of meeting will be deemed correct.

.5 Conference Calls:

.1 Periodic progress conference calls between construction meetings will be chaired by the Consultant to be attended by the Contractor and the County. Meeting minutes may be prepared by Consultant, but the Contractor is not required to

Page 30: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 32 17 Parkland County PROJECT MANAGEMENT AND COORDINATION Issued for Tender Page 3 of 4

SPC-01 32 17-Proj MgmntandCoord-60638222.docx

provide a status update to the Contract Work Schedule or Contract Progress Report unless specifically requested by Consultant prior to the conference call.

1.6 Work Schedule

.1 The Work Schedule shall include the complete sequence of construction activities, in a graphical component and format agreed upon with the Consultant and the County, suitable for displaying planned scheduling and actual progress including but not limited to the following:

.1 Monthly cash flow schedule conforming to the Contract Work Schedule.

.2 Dates for mobilization and demobilization.

.3 Dates for each Construction Milestone.

.4 Dates for each major element of construction.

.5 Final clean up task by Work Site location.

.6 Changes since previous submission, including major changes in scope, activities modified since previous submission, revised projections of progress and completion and other identifiable changes.

.7 Date of Substantial Performance of the Work.

.8 Typical shift length in days and hours of work per day.

.9 Number of planned productive working days on the Work Site.

.2 Provide sub-schedules and look-ahead schedules to define portions of Work that the Consultant deems as critical within five days following a request by the Consultant.

.3 The Consultant will conduct reviews of the Work’s progress based on the Work Schedule.

.4 Maintain an up-to-date schedule in conjunction with and to the approval of the Consultant.

.5 Do not change the Work Schedule without approval from the Consultant.

.6 The County reserves the right to withhold reasonable progress payments amounts in the event Contractor fails to provide a suitable Work Schedule and subsequent status reports within the time periods required.

1.7 Contract Progress Report

.1 Contract Progress Reports shall accompany the Work Schedule, in a narrative report that shall include but not be limited to the following:

.1 A description of current and anticipated delaying factors, if any.

.2 Impact of the delaying factors identified.

.3 Proposed corrective actions to achieve the Work Schedule.

.2 Should operations fall behind the Work Schedule to an extent that completion of the Work within the Contract Time appears doubtful, the Contractor shall, at no change in Contract Price, take corrective action to get back on plan.

Page 31: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 32 17 Parkland County PROJECT MANAGEMENT AND COORDINATION Issued for Tender Page 4 of 4

SPC-01 32 17-Proj MgmntandCoord-60638222.docx

1.8 Notification to Affected Parties

.1 Prior to commencing the Work, provide notifications to affected parties.

.2 Develop and deliver a written notice to affected landowners, residents, business owners and any other party affected by the Contractor’s activities in performing the Work a minimum of three days prior to commencing operations near the affected property.

.3 Coordinate service interruptions and shutdowns with the County. Provide a minimum five days written notice to the County for planned interruptions and shutdowns.

.4 The Contractor could potentially affect various parties in numerous ways, and it is the Contractor’s responsibility to determine the potential effects of their operations, including without limitation noise, access to properties, visual effects, utility service disruption and drainage. Implement reasonable measures to address and mitigate the effects of their activities.

.5 The written notification shall include the following at a minimum:

.1 Contractor name.

.2 Project name.

.3 Date notification delivered to affected party.

.4 Contractor contact person name and 24-hour contact information for Contractor’s contact person.

.5 Description of the activities that will affect the party and their property and mitigation measures the Contractor will employ.

.6 Accurate start and end dates for the activities that will affect the party and their property.

.7 Provide copies of the written notification to the County and Consultant for their records, and as evidence that the notification was delivered to the affected parties.

2.0 PRODUCT

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 32: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 33 00 Parkland County SUBMITTAL PROCEDURES Issued for Tender Page 1 of 4

SPC-01 33 00-Submittal Procedures-60638222.docx

1.0 GENERAL

1.1 Administrative

.1 Submit to the Consultant submittals listed for review. Submit promptly and in orderly sequence to not cause delay in Work. Failure to submit in ample time is not considered sufficient reason for extension of Contract Time and no claim for extension by reason of such default will be allowed.

.2 Do not proceed with Work affected by submittal until review is complete and the Consultant has approved proceeding with the work that is the subject of the submittal. The onus shall be on the Contractor to provide each submittal as early as possible and on a schedule that permits reasonable opportunity for the Consultant to review and comment such that construction delays do not occur.

.3 Present shop drawings, product data, samples and mock-ups in SI Metric units.

.4 Where items or information is not produced in SI Metric units converted values are acceptable.

.5 All submittals shall be in PDF format unless otherwise requested by the Consultant.

.6 Review submittals prior to submission to Consultant. This review represents that necessary requirements have been determined and verified, or will be, and that each submittal has been checked and coordinated with requirements of Work and these specifications. Submittals not professionally stamped, signed, dated and identified as to specific project will be returned without being examined and considered rejected.

.7 Notify Consultant in writing at time of submission, identifying deviations from requirements of these specifications stating reasons for deviations.

.8 Verify that field measurements and affected adjacent Work are coordinated.

.9 Contractor's responsibility for errors and omissions in submission is not relieved by any Owner’s or the Consultant’s review of submittals.

.10 Contractor's responsibility for deviations in submission from requirements of these specifications is not relieved by the Consultant’s review.

.11 In addition to PDF copies, keep one reviewed paper copy of each submission on site.

1.2 Shop Drawings and Product Data

.1 The term "shop drawings" means drawings, diagrams, illustrations, schedules, performance charts, brochures and other data which are to be provided by Contractor to illustrate details of a portion of Work.

.2 Submit drawings stamped and signed by Professional Consultant or Architect registered or licensed in Alberta, Canada.

Page 33: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 33 00 Parkland County SUBMITTAL PROCEDURES Issued for Tender Page 2 of 4

SPC-01 33 00-Submittal Procedures-60638222.docx

.3 Indicate materials, methods of construction and attachment or anchorage, erection diagrams, connections, explanatory notes and other information necessary for completion of Work. Where articles or equipment attach or connect to other articles or equipment, indicate that such items have been coordinated, regardless of Section under which adjacent items will be supplied and installed. Indicate cross references to design drawings and specifications.

.4 Allow five (5) working days for Consultant’s review of each submission.

.5 Adjustments made on shop drawings by the Consultant are not intended to change Contract Price. If adjustments affect value of Work, state such in writing to the Consultant within two working days and prior to proceeding with Work.

.6 Make changes in shop drawings as Consultant may require, consistent with these specifications. When resubmitting, notify the Consultant in writing of revisions other than those requested.

.7 Accompany submissions with transmittal memorandum or letter, in duplicate, containing:

.1 Date.

.2 Project title and number.

.3 Contractor's name and address.

.4 Identification and quantity of each shop drawing, product data and sample.

.5 Other pertinent data.

.8 Submissions include:

.1 Date and revision dates.

.2 Project title and number.

.3 Name and address of:

.1 Subcontractor.

.2 Supplier.

.3 Manufacturer.

.4 Contractor's stamp, signed by Contractor's authorized representative certifying approval of submissions, verification of field measurements and compliance with these specifications.

.9 After the Consultant’s review, distribute copies.

.10 Submit PDF copies of shop drawings for each requirement requested in specification Sections and as the Consultant may reasonably request.

Page 34: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 33 00 Parkland County SUBMITTAL PROCEDURES Issued for Tender Page 3 of 4

SPC-01 33 00-Submittal Procedures-60638222.docx

.11 Submit PDF of product data sheets or brochures for requirements requested in specification Sections and as requested by the Consultant where shop drawings will not be prepared due to standardized manufacture of product.

.1 Submit PDF copies of Operation and Maintenance Data for requirements requested in specification Sections and as requested by the Consultant

.2 Supplement standard information to provide details applicable to project.

.3 If upon review by the Consultant no errors or omissions are discovered or if only minor corrections are made, copies will be returned, and fabrication and installation of Work may proceed. If shop drawings are rejected, noted copy will be returned and resubmission of corrected shop drawings, through same procedure indicated above, must be performed before fabrication and installation of Work may proceed.

.12 The review of shop drawings by Consultant is for sole purpose of ascertaining conformance with general concept.

.1 This review shall not mean that Consultant approves detail design inherent in shop drawings, responsibility for which shall remain with Contractor submitting same, and such review shall not relieve Contractor of responsibility for errors or omissions in shop drawings or of responsibility for meeting requirements of construction and these specifications.

.2 Without restricting generality of foregoing, Contractor is responsible for dimensions to be confirmed and correlated at job site, for information that pertains solely to fabrication processes or to techniques of construction and installation and for co-ordination of Work of sub-trades.

1.3 Environmental Construction Operations Plan

.1 Contractor to submit 10 days prior to the work commencing an acceptable ECO Plan accordance with the Alberta Transportation manual title “Environmental Construction Operations (ECO) Plan Framework”

.2 The ECO Plan shall be reviewed by the Consultant.

.3 Work is not permitted to begin by the Contractor until the ECO Plan has been reviewed and deemed acceptable.

.4 Refer to section 01 35 43 Environmental Procedures.

1.4 Photographic Documentation

.1 Submit electronic copy of colour digital photography in jpeg, standard resolution or PDF.

.2 Take daily photographs of all utility, underground work and building foundation work.

.3 Take photographs of site conditions before, during, and after construction. Take photographs of any unique or unusual items.

Page 35: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 33 00 Parkland County SUBMITTAL PROCEDURES Issued for Tender Page 4 of 4

SPC-01 33 00-Submittal Procedures-60638222.docx

.4 Photographs to be submitted on USB stick. All photographs to be labelled with meaningful titles and the date that the photo was taken. The naming convention for photographs shall be to the satisfaction of the Consultant.

.5 Assemble photographs in descriptive folders and submit to the Consultant on a monthly basis. The folder organization and naming convention shall be subject to the approval of the Consultant.

1.5 Certificates and Transcripts

.1 Immediately after award of Contract, submit Workers' Compensation Board status.

.2 Submit transcription of insurance immediately after award of Contract.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 36: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 29.06 Parkland County HEALTH AND SAFETY REQUIREMENTS Issued for Tender Page 1 of 4

SPC-01 35 29 06-HealthandSafetyReq-60638222.docx

1.0 GENERAL

1.1 References

.1 Canada Labour Code, Part 2, Canada Occupational Safety and Health Regulations.

.2 Province of Alberta.

.3 Occupational Health and Safety Act, R.S.A. - Updated 2013.

.4 Section 01 55 26 Traffic Control.

1.2 Occupational Health and Safety Act

.1 The Contractor shall be the Prime Contractor for the purposes of this project. The Prime Contractor is responsible to ensure that all contractors working on the worksite comply with the Occupational Health & Safety Act and applicable regulations.

.2 The Contractor shall comply and ensure that all the Subcontractors comply with all applicable legislation. The Contractor shall enforce all the applicable safety rules and regulations to all individuals who will be on the site.

.3 The Contractor warrants that the Contractor shall comply with all requirements of the Occupational Health & Safety Act as well as the relevant legislation in conducting work under this Contract.

1.3 Supervision

.1 The Contractor shall advise the Consultant in writing of the person or persons who will ensure compliance with applicable safety legislation. This list should include the site superintendent plus as many representatives as the Contractor determines are required to ensure appropriate supervision and the subsequent safe performance of all jobs on the site. Provision should be made to include twenty-four (24) hour emergency telephone number(s) on this list.

1.4 Audit/Inspections

.1 The Contractor shall conduct frequent inspections to ensure compliance with legislation. Any unsafe conditions or work practice observed shall be corrected as soon as possible. In the event of an imminent danger situation, Section 27 of the Occupational Health and Safety Act shall be followed. All reports provided by outside agencies (i.e. Alberta Government Health & Safety, etc.) shall be copied and a copy provided to the Consultant within twenty-four (24) hours following the inspection.

1.5 Action and Informational Submittals

.1 Submit in accordance with Section 01 33 00 - Submittal Procedures.

.2 Submit site-specific Health and Safety Plan: Within Seven (7) days after date of Notice to Proceed and prior to commencement of Work. Health and Safety Plan must include:

Page 37: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 29.06 Parkland County HEALTH AND SAFETY REQUIREMENTS Issued for Tender Page 2 of 4

SPC-01 35 29 06-HealthandSafetyReq-60638222.docx

.1 Results of site specific safety hazard assessment.

.2 Results of safety and health risk or hazard analysis for site tasks and operation.

.3 Submit one (1) copy of Contractor's authorized representative's work site health and safety inspection reports to Consultant bi-weekly, including minutes of safety toolbox meetings.

.4 Submit copies of reports or directions issued by Federal, Provincial and Territorial health and safety inspectors.

.5 Submit copies of incident and accident reports.

.6 Submit WHMIS MSDS - Material Safety Data Sheets to the Consultant.

.7 The Consultant will review Contractor's site-specific Health and Safety Plan and provide comments to Contractor within 3 days after receipt of plan. Revise plan as appropriate and resubmit plan to Consultant within 3 days after receipt of comments from Consultant.

.8 The Consultant’s review of Contractor's final Health and Safety plan should not be construed as approval and does not reduce the Contractor's overall responsibility for construction Health and Safety.

.9 Medical Surveillance: where prescribed by legislation, regulation or safety program, submit certification of medical surveillance for site personnel prior to commencement of Work, and submit additional certifications for any new site personnel to Consultant.

.10 On-site Contingency and Emergency Response Plan: address standard operating procedures to be implemented during emergency situations.

.11 Emergencies: In the event of emergency call 911.

.12 The Contractor shall ensure that their Safety and Emergency Response Plans include considerations and action planning including wildlife and potential wildfires.

1.6 Filing of Notice

.1 File Notice of Project with Provincial authorities prior to beginning of Work.

1.7 Safety Assessment

.1 Perform site specific safety hazard assessment related to project.

1.8 Meetings

.1 Pre-construction meeting to include a Health and Safety meeting with Consultant at least 10 days prior to commencing any work.

Page 38: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 29.06 Parkland County HEALTH AND SAFETY REQUIREMENTS Issued for Tender Page 3 of 4

SPC-01 35 29 06-HealthandSafetyReq-60638222.docx

1.9 Regulatory Requirements

.1 Comply with the specified standards and regulations to ensure safe operations on site.

1.10 General Requirements

.1 Develop written site-specific Health and Safety Plan based on hazard assessment prior to beginning site Work and continue to implement, maintain, and enforce plan until final demobilization from site. Health and Safety Plan must address project specifications.

.2 The Consultant may respond in writing, where deficiencies or concerns are noted and may request re-submission with correction of deficiencies or concerns.

1.11 Responsibility

.1 Be responsible for health and safety of persons on site, safety of property on site and for protection of persons adjacent to site and environment to extent that they may be affected by conduct of Work.

.2 Report all accidents to Owner immediately.

.3 Comply with and enforce compliance by employees with safety requirements of these specifications, applicable federal, provincial, territorial and local statutes, regulations, and ordinances, and with site-specific Health and Safety Plan.

.4 Contractor is required to supply all task specific related PPE. Minimum PPE is hard hat, CSA steel toed boots, and visibility vest.

.5 The Contractor shall ensure that all of the workers working on behalf of the Contractor have completed bear awareness training.

1.12 Compliance Requirements

.1 Comply with Occupational Health and Safety Act, General Safety Regulation, Alberta Reg.

.2 Comply with R.S.Q., c. S-2.1, an Act respecting Health and Safety, and c. S-2.1, r.4 Safety Code for the Construction Industry.

.3 Comply with latest Occupational Health and Safety Regulations.

.4 Comply with Canada Labour Code, Canada Occupational Safety and Health Regulations.

1.13 Unforeseen Hazards

.1 When unforeseen or peculiar safety-related factor, hazard, or condition occur during performance of Work, follow procedures in place for Employee's Right to Refuse Work in accordance with Acts and Regulations of Province having jurisdiction and advise Consultant verbally and in writing.

Page 39: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 29.06 Parkland County HEALTH AND SAFETY REQUIREMENTS Issued for Tender Page 4 of 4

SPC-01 35 29 06-HealthandSafetyReq-60638222.docx

1.14 Posting of Documents

.1 Ensure applicable items, articles, notices and orders are posted in conspicuous location on site in accordance with Acts and Regulations of Province having jurisdiction, and in consultation with Consultant.

1.15 Correction of Non-Compliance

.1 Immediately address health and safety non-compliance issues identified by authority having jurisdiction or by Consultant.

.2 Provide Consultant with written report of action taken to correct non- compliance of health and safety issues identified.

.3 Consultant may stop Work if non-compliance of health and safety regulations is not corrected.

1.16 Site Security/Public Safety

.1 The Contractor shall ensure that access or movement at or adjacent to the worksite does not present hazards.

.2 This may involve the use of fencing, barricading, lighting, signing, hoarding, locked covers over openings, workers on watch, "authorized entry only" provision, or other means as appropriate. The Contractor shall ensure that authorized personnel have access to the site.

.3 The Consultant may request the Contractor to institute a means of identifying authorized workers on the site to assist in site security. Adverse weather conditions may require an increased awareness of public security and safety.

1.17 Work Stoppage

.1 Give precedence to safety and health of public and site personnel and protection of environment over cost and schedule considerations for Work.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 40: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 43 Parkland County ENVIRONMENTAL PROCEDURES Issued for Tender Page 1 of 4

SPC-01 35 43-Environmental Procedures-60638222.docx

1.0 GENERAL

1.1 Toxic and Hazardous Substances and Materials

.1 Contractor shall not cause, bring, permit or suffer to be brought any toxic or hazardous substances or materials onto the Place of the Work or any part thereof, except to the extent that such toxic or hazardous substances or materials are required by the Contract Documents.

.2 Upon becoming aware of any toxic or hazardous substances or materials at the Place of the Work, the Contractor shall promptly give written notice to the Owner, with a copy to the Consultant, of the presence of such toxic or hazardous substances or materials, and

.1 Comply with all lawful orders or reasonable requests from the Owner, the Consultant or any government authority relating to such toxic or hazardous substances or materials;

.2 Where the toxic or hazardous substances or materials were introduced to the Place of the Work by the Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the Contractor shall, at its own cost, undertake and complete all removal and remedial actions necessary to contain, remove and clean-up such toxic or hazardous substances or materials to the reasonable satisfaction of the Owner, the Consultant and all appropriate regulatory authorities

1.2 Fires

.1 Fires and burning of rubbish on site not permitted.

1.3 Disposal of Wastes

.1 Do not bury rubbish and waste materials on site unless approved by Consultant.

.2 Do not dispose of waste or volatile materials, such as mineral spirits, oil or paint thinner onto ground or into waterways, storm or sanitary sewers.

1.4 Drainage

.1 Provide temporary drainage and pumping as necessary to keep excavations and site free from water.

.2 Do not pump water containing suspended materials into waterways, sewer or drainage systems.

.3 Control disposal or runoff of water containing suspended materials or other harmful substances in accordance with local authority requirements.

1.5 Site Clearing and Plant Protection

.1 Protect grass, trees, shrubbery, plants, fences, poles and other surface structures on site and adjacent properties unless their removal is shown on the drawings or authorized by the Consultant.

Page 41: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 43 Parkland County ENVIRONMENTAL PROCEDURES Issued for Tender Page 2 of 4

SPC-01 35 43-Environmental Procedures-60638222.docx

.2 Do not cut any trees without the written permission of the Consultant.

.3 All existing grass, trees and shrubbery disturbed by the work shall be restored to equal or better condition than prior to construction. No extra payment will be provided for this work.

.4 Minimize stripping of topsoil and vegetation.

1.6 Pollution Control

.1 Maintain temporary erosion and pollution control features installed under this contract.

.2 Control emissions from equipment and plant to local authority’s emission requirements.

.3 Cover dry materials and rubbish to prevent blowing dust and debris and install silt fences around stockpiles to prevent siltation.

.4 Tightly seal against corrosion and rust all containers of fuel, hazardous or toxic chemicals.

.5 Vehicle and equipment maintenance shall occur in designated areas. Contain and handle all maintenance fluids in accordance with the current National Fire Code of Canada. Spillage on the ground is prohibited.

.6 Hoses and equipment for transfer of fuels and other hazardous fluids shall be in good condition, properly functioning with approved check valves and shall be attended by a qualified person for the duration of transfer of fuels or hazardous fluids.

.7 Greasy and oily rags and oil waste shall be contained in approved, sealed containers. Remove from the worksite and dispose of this material in accordance with the most stringent of applicable Federal, Provincial and Municipal Regulations.

.8 Abide by the Alberta Board of Health Regulations 572-57-5 as amended 262-61 regarding air pollution.

.9 The use of oil for dust control is prohibited. Use only fresh water.

.10 Comply with any Local, Provincial or Federal Noise Bylaws or Regulations.

1.7 Spillages

.1 Report immediately to the Consultant any accidental spill of chemicals, liquid or dry.

.2 Report immediately to the Consultant all spills of fuel whether contained in a dyke or otherwise.

.3 Identify the spill, take all safety precautions before approaching it, determine the source of the leak, attempt to stop the flow, and contain the escaped material.

.4 Report the spill to the appropriate environmental authority if required.

Page 42: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 43 Parkland County ENVIRONMENTAL PROCEDURES Issued for Tender Page 3 of 4

SPC-01 35 43-Environmental Procedures-60638222.docx

1.8 Inspection

.1 Provide required facilities and services to assist environmental inspection of the Contractor’s construction site.

1.9 Work Adjacent to Waterways

.1 Do not fuel, lubricate or otherwise service equipment where spillage may enter waterways.

.2 Do not operate construction equipment in waterways.

.3 Do not use waterway bed for borrow material unless approved by the Consultant.

.4 Do not dump excavated fill, waste material or debris in waterways.

1.10 Environmental Construction Operations Plan

.1 An ECO plan is a project-specific plan that identifies and mitigates the potential environmental impacts of construction. Contractors are responsible for developing and implementing ECO Plans for their projects. ECO plans cover the following topics:

.1 Project setting, activities and schedule

.2 Applicable permits, approvals and regulations

.3 Potential environmental impacts and controls

.4 Hazardous materials and waste management

.5 ECO Plan implementation procedures

.6 Environmental emergency response procedures

.2 Contractor to submit 10 days prior to the work commencing an acceptable ECO Plan accordance with the Alberta Transportation manual title “Environmental Construction Operations (ECO) Plan Framework”

.3 The ECO Plan shall be reviewed by the Consultant.

.4 Work is not permitted to begin by the Contractor until the ECO Plan has been reviewed and deemed acceptable.

2.0 PRODUCTS

.1 Not applicable.

3.0 EXECUTION

3.1 Clearing and Grubbing

.1 The Contractor shall understand the wildlife sensitivity concerns associated with Clearing. Grubbing and/or tree removal.

Page 43: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 35 43 Parkland County ENVIRONMENTAL PROCEDURES Issued for Tender Page 4 of 4

SPC-01 35 43-Environmental Procedures-60638222.docx

.2 Construction sequencing shall aim to minimize construction activities and avoid ground disturbance activities between the peak nesting period of May 1 to August 31. Should construction activities be forecasted to occur during the peak nesting period, contractor shall complete Bird Nesting Surveys as required to facilitate construction. Contractor shall ensure that bird nest surveys have been completed in accordance with the regulations and requirements of the Migratory Bird Act.

END OF SECTION

Page 44: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 45 00 Parkland County QUALITY ASSURANCE CONTROL Issued for Tender Page 1 of 5

SPC-01 45 00-Quality Assurance Control-60638222.docx

1.0 GENERAL

1.1 Related Documents

.1 Particular requirements for testing to be carried out by local survey firm or testing laboratory designated by the Consultant or the Owner are specified under various Sections.

1.2 Inspection and Testing of Work

.1 Work included: From time to time during progress of the work, the Owner and the Consultant may require that Quality Assurance Testing be performed to determine that materials and workmanship provided for the work meet the specified requirements. This Quality Assurance work is in addition to and does not replace the Contractor’s responsibility for Quality Control.

.2 Related Work Specified Elsewhere: Requirements for testing may be described in various sections of these specifications. Where no testing requirements are described, but the Owner decides that testing is required, the Owner may require testing to be performed under current pertinent standards for testing.

1.3 Independent Quality Assurance

.1 Owner will appoint, in consultation with the Consultant, and reimburse Contractor for services of an Independent Testing Laboratory or Agency or Quality Assurance Survey to perform whatever Quality Assurance Testing is deemed necessary by the Consultant to confirm the compliance of the work within the Contract Documents.

.1 Submit receipts and proof of payment to Consultant for approval.

.2 Payment will be made only for tests requested and approved by Consultant, supported by proof of payment as described in Clause 1.3.1.1.

.2 Owner will not pay for or reimburse Contractor for any services related to testing of the following:

.1 Inspection and testing required by laws, ordinances, rules, regulations or orders of public authorities.

.2 Inspection and testing performed exclusively for Contractor's convenience.

.3 Testing, adjustment and balancing of conveying systems, mechanical and electrical equipment and systems.

.4 Mill tests and certificates of compliance.

.5 Tests specified to be carried out by Contractor.

.6 Inspection and testing for the preparation of concrete or pavement mix designs.

.7 Aggregate testing to meet specified gradations.

Page 45: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 45 00 Parkland County QUALITY ASSURANCE CONTROL Issued for Tender Page 2 of 5

SPC-01 45 00-Quality Assurance Control-60638222.docx

.8 Additional tests specified in Clause 1.3.3.

.9 The Contractor’s responsibility for layout of the Work.

.10 The Contractor’s responsibility for Quality Control for the Work.

.3 Where tests by designated testing laboratory reveal work not in accordance with Contract requirements, the Contractor shall pay costs for additional tests as Consultant may require to verify acceptability of corrected work.

.4 Where tests are called prematurely or the testing laboratory is delayed by the Contractor, the Contractor shall pay all additional costs incurred.

.5 Payment will be made under the Quality Assurance Cash Allowance identified in the Bid Form.

1.4 Laboratories/Agencies

.1 Notify the Consultant a minimum of one full Business day in advance of operations to allow for assignment of laboratory personnel and scheduling of test.

.2 Independent Testing Agencies will be approved by the Owner for the purpose of testing portions of the work. Costs of such services will be recovered from the Quality Assurance Cash Allowance.

.3 The cost of transportation (including shipping charges) shall be borne by the Contractor and not recoverable from the Quality Assurance cash allowance for materials testing.

.4 The Contractor and Subcontractor mark-up for the Engineering Quality Assurance Cash Allowance shall be included in the Contractor’s contract price. The Contractor shall not be allowed to recover the costs of any tests or retests, which indicate the result does not exceed the minimum specified.

.5 such as pipe, aggregates, and fittings. The cost of such testing will not be recoverable from the Quality Assurance Cash Allowance.

1.5 Contractor Responsibility for Quality Control

.1 It is the Contractor’s responsibility to carry out whatever quality control surveys, inspections, and testing is required as outlined in each Section to ensure that the Work is in conformance with the Contract Documents and its associated costs.

.2 The Contractor cannot rely on the surveys, inspections or testing that will be carried out by the Independent Survey or Testing Agency for quality assurance by the Consultant; the intention of this testing is for determination by the Consultant of satisfactory completed work for Progress Payment.

.3 All costs required to ensure quality control shall be borne by the Contractor.

Page 46: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 45 00 Parkland County QUALITY ASSURANCE CONTROL Issued for Tender Page 3 of 5

SPC-01 45 00-Quality Assurance Control-60638222.docx

1.6 Access to Work and Plant

.1 Allow the Testing Agencies access to all portions of Work on site and manufacturing and fabrication plants, as may be necessary to carry out their work. Cooperate to provide reasonable facilities for such access.

1.7 Procedures for Inspection and Testing

.1 If Work is designated for special tests, inspections, or approvals in the Contract Documents, or by the Consultant’s instructions or the laws or ordinances of the Place of the Work, give the Independent Testing Agency timely notice requesting inspection. Inspection by the Independent Testing Agency will be made promptly. Arrange for inspections by other authorities and give the Consultant timely notice of the date and time.

.2 Submit necessary samples and/or materials required for testing, as specifically requested in the Specifications. Submit with reasonable promptness and in an orderly sequence, so as to cause no delay in Work.

.3 Provide workers and facilities to obtain and handle samples and/or materials on-site. Provide sufficient space to facilitate the storage and curing of test samples.

.4 If defects are revealed during testing, the appointed agency will request additional testing to ascertain full degree of defects. Correct defects and irregularities as advised by the Consultant. Pay costs for retesting.

.5 The Contractor shall correct defects and irregularities and pay all costs for all additional testing.

1.8 Covered Work

.1 If the Contractor covers or permits to be covered work that has been designated for inspections or approvals before they are made, uncover such work, have the inspections or tests satisfactorily completed, and make good such work.

.2 The Consultant may order any part of the work to be examined if such work is suspected to be not in accordance with the Contract Documents. If, upon examination, such work is found not in accordance with the Contract Documents, correct such work and pay for cost of examination and correction. If such work is found in accordance with the Contract Documents, the Owner shall pay the cost of examination and replacement.

1.9 Rejected Work

.1 Defective work, whether the result of poor workmanship, use of defective products or damage through carelessness or other acts of omission of the Contractor, and whether incorporated in the work or not, which has been rejected by the Consultant as failing to conform to the Contract Documents shall be removed promptly from the work and replaced or re-executed by the Contractor in accordance with the Contract Documents at the Contractor’s expense.

Page 47: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 45 00 Parkland County QUALITY ASSURANCE CONTROL Issued for Tender Page 4 of 5

SPC-01 45 00-Quality Assurance Control-60638222.docx

.2 Other work destroyed or damaged by such removals, replacement or re-execution shall be made good promptly at the Contractor’s expense.

1.10 Reports

.1 Submit a copy of inspection and test reports promptly to the Consultant for all requested Quality Assurance Testing as requested by the Consultant.

1.11 Tests and Designs

.1 Furnish to the Consultant test results and mix designs as specifically requested in the Specifications.

.2 The cost of test results and mix design shall be borne by the Contractor.

1.12 Reference Standards

.1 Within the test of the Specifications, reference may be made to the following standards:

ACI - American Concrete Institute AISC - American Institute of Steel Construction ANSI - American National Standards Institute ASTM - American Society of Testing and Materials AWWA - American Water Works Association CAN - National Standard of Canada CEC - Canadian Electric Code (published by CSA) CGA - Canadian Gas Association CGSB - Canadian Government Specification Board CISC - Canadian Institute of Steel Construction CLA - Canadian Lumberman’s Association CPCA - Canadian Painting Contractors Association CPCI - Canadian Prestressed Concrete Institute CRCA - Canadian Roofing Contractors Association CSA - Canadian Standards Association DIN - Deutsches Institut Normung EEMAC - Electrical and Electronic Manufacturer’s Association of Canada EIB - Electrical Inspection Branch FMEC - Factory Manual Engineering Corporation IEEE - Institute of Electrical and Electronic Consultants IPCEA - Insulated Power Cable Consultants Association NAAMM - National Association of Architectural Metal Manufacturers NACE - National Association of Corrosion Consultants NBC - National Building Code NEMA - National Electrical Manufacturers Association NFPA - National Fire Protection Association NWTI - National Wood Tank Institute of the USA TTMAC - Terrazzo, Tile and Marble Association of Canada ULC - Underwriters Laboratories of Canada

Conform to the latest version of such standards available at the time of bidding, in whole or in part, as specified.

Page 48: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 45 00 Parkland County QUALITY ASSURANCE CONTROL Issued for Tender Page 5 of 5

SPC-01 45 00-Quality Assurance Control-60638222.docx

.2 If there are questions as to whether any product of system is in conformance with applicable standards, the Consultant reserves the right to have such products or systems tested to prove or disprove conformance with the Contract Documents, or by the Contractor in the event of non-conformance.

.3 The referenced standard and any amendments in force on the day of receipt of bids shall be applicable to the work during the duration of the Contract.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 49: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 54 00 Parkland County EXISTING STRUCTURES AND UTILITIES Issued for Tender Page 1 of 2

SPC-01 54 00-Existing Structures and Utilities-60638222.docx

GENERAL

Requirements Included

COORDINATION

Coordination

WORKMANSHIP

Location of Structures and Utility Works

Page 50: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 54 00 Parkland County EXISTING STRUCTURES AND UTILITIES Issued for Tender Page 2 of 2

SPC-01 54 00-Existing Structures and Utilities-60638222.docx

Protection of Structures and Utilities

Emergency Situations

Access Maintained

Support of Structures and Utility Works

END OF SECTION

Page 51: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 55 26 Parkland County TRAFFIC CONTROL Issued for Tender Page 1 of 3

SPC-01 55 26-Traffic Control-60638222.docx

GENERAL

Reference Standard

Protection of Public Traffic

Place equipment in position to present minimum interference and hazard to travelling public.

Keep equipment units as close together as working conditions will permit and preferably on the same side of travelled way.

Do not leave equipment on travelled way overnight.

Informational and Warning Devices

Page 52: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 55 26 Parkland County TRAFFIC CONTROL Issued for Tender Page 2 of 3

SPC-01 55 26-Traffic Control-60638222.docx

Checking signs daily for legibility, damage, suitability and location. Clean, repair or replace to ensure clarity and reflectance.

Removing or covering signs which do not apply to conditions existing from day-to-day.

Traffic control signage should be removed and salvaged if it can be reused as part of the construction works. Any other traffic control signage can be removed and disposed of outside the part in a recognized disposal site.

Any informational and interpretation signage should be salvaged and taken to a location designated by the Owner for reuse.

Control of Public Traffic

Restricted Activity on Roads

Prior to closing any lanes the Contractor is to provide an alternate access with approval of the Owner. For all closures the Contractor is to obtain lane closure permits prior to closing.

The Contractor is to maintain one lane of traffic in a single direction at all times during underground utility construction. Contractor to use construction methods to minimize work zone area influence and to minimize traffic disruption.

Traffic signs shall be erected and maintained to ensure safety of workers and public as required in Section 1.3.

When public traffic is required to pass working vehicles or equipment which may block all or part of travelled roadway.

When it is necessary to institute one-way traffic system through construction area or other blockage where traffic volumes are heavy, approach speeds are high and traffic signal system is not in use.

Page 53: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 55 26 Parkland County TRAFFIC CONTROL Issued for Tender Page 3 of 3

SPC-01 55 26-Traffic Control-60638222.docx

When workers or equipment are employed on travelled way over brow of hills, around sharp curves or at other locations where oncoming traffic would not otherwise have adequate warning.

Where temporary protection is required while other traffic control devices are being erected or taken down.

For emergency protection when other traffic control devices are not readily available.

In situations where complete protection for workers, working equipment and public traffic is not provided by other traffic control devices.

PRODUCTS

EXECUTION

END OF SECTION

Page 54: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 61 00 Parkland County COMMON PRODUCTS REQUIREMENTS Issued for Tender Page 1 of 3

SPC-01 61 00-Common Products Requirements-60638222.docx

GENERAL

Requirements Included

Products and Materials

Products, materials, equipment and articles (referred to as Products throughout the specifications) incorporated in the Work shall be new, not damaged or defective, and of the best quality (compatible with specifications) for the purpose intended. If requested, furnish evidence as to type, source and quality of Products provided.

In the event that the Contractor proposes to substitute alternate or equal products, the Consultant shall deduct any consulting costs that may be incurred by Owner related to the evaluation or consideration of any proposed alternative products, including a 25% administration fee.

Immediately upon signing Contract, review Product delivery requirements and anticipate foreseeable supply delays for any items. If delays in supply of Products are foreseeable, notify the Consultant of such, in order that substitutions or other remedial action may be authorized in ample time to prevent delay in performance of Work.

In the event of failure to notify the Consultant at commencement of Work and should it subsequently appear that Work may be delayed for such reason, the Consultant reserves the right to substitute more readily available products of similar character, at no increase in Contract Amount. The onus shall be on the Contractor to demonstrate and document that reasonable best efforts have been used by the Contractor to secure alternative sources of supply before seeking approval of any alternates or substitutes.

Handle and store Products in a manner to prevent damage, adulteration, deterioration and soiling and in accordance with manufacturer's instructions when applicable.

Store packaged or bundled Products in original and undamaged condition with manufacturer's seals and labels intact. Do not remove from packaging or bundling until required in the Work.

Page 55: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 61 00 Parkland County COMMON PRODUCTS REQUIREMENTS Issued for Tender Page 2 of 3

SPC-01 61 00-Common Products Requirements-60638222.docx

Store products subject to damage from weather in weatherproof enclosures.

Remove and replace damaged Products at own expense and to the satisfaction of the Consultant.

Contractor to identify proposed location for stockpiles. Stockpiles must be either located offsite in designated areas approved by Consultant or stockpiled on site in a manner such that stockpile is fenced off from public traffic and while maintaining traffic flow under modified traffic restrictions as detailed in this contract. All stockpiles should be maintained on an ongoing basis to provide a safe condition and to the satisfaction of the Consultant.

Pay costs of transportation of Products required in the performance of Work.

Manufacturer’s Instructions

Workmanship

Execute work by workers experienced and skilled in the respective duties for which they are employed. Notify Consultant immediately if required Work is such as to make it impractical to produce required results.

Do not employ any unfit person or anyone unskilled in their required duties. The Consultant reserves the right to require the dismissal from the site, workers deemed incompetent, careless, insubordinate or otherwise objectionable.

Decisions as to the quality or fitness of workmanship in cases of dispute rest solely with the Consultant, whose decision is final.

Ensure co-operation of workers in laying out Work. Maintain efficient and continuous supervision.

Be responsible for co-ordination and placement of openings, sleeves and accessories.

Page 56: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 61 00 Parkland County COMMON PRODUCTS REQUIREMENTS Issued for Tender Page 3 of 3

SPC-01 61 00-Common Products Requirements-60638222.docx

Adequately protect Work completed or in progress. Work damaged or defaced due to failure in providing such protection is to be removed and replaced, or repaired, as directed by the Consultant, at no increase in Contract Amount.

Ownership

PRODUCTS

EXECUTION

END OF SECTION

Page 57: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 74 00 Parkland County CLEANING Issued for Tender Page 1 of 1

SPC-01 74 00-Cleaning-60638222.docx

1.0 GENERAL

1.1 Project Cleanliness

.1 Maintain Work in tidy condition, free from accumulation of waste products and debris.

.2 Remove waste materials from site at daily regularly scheduled times or dispose of. Do not burn waste materials on site.

.3 Clear snow and ice as required. Pile snow in designated areas only.

.4 Make arrangements with and obtain permits from authorities having jurisdiction for disposal of waste and debris.

.5 Provide on-site containers for collection of waste materials and debris.

.6 Waste containers must be secure and prevent animals and public from accessing.

.7 Wash, clean and sweep all roads and parking areas prior to each inspection by the Consultant.

1.2 Final Cleaning

.1 When Work is Substantially Performed remove surplus products, tools, construction machinery and equipment not required for performance of remaining Work.

.2 Remove waste products and debris, and leave Work clean and suitable for occupancy.

.3 Prior to final review remove surplus products, tools, construction machinery and equipment.

.4 Broom clean and wash exterior walks, steps and surfaces; rake clean other surfaces of grounds.

.5 Mop clean and wipe down any interior areas affected by the work.

.6 Remove dirt and other disfiguration from exterior surfaces.

.7 Sweep and wash clean paved areas.

.8 Restore and clean up all disturbed areas including, but not limited to, site trailer locations and stockpile areas.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 58: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 77 00 Parkland County CLOSEOUT PROCEDURES Issued for Tender Page 1 of 2

SPC-01 77 00-Closeout Procedures-60638222.docx

1.0 GENERAL

1.1 Administrative Requirements

.1 Acceptance of Work Procedures:

.1 Contractor's Inspection: Contractor: conduct inspection of Work, identify deficiencies and defects, and repair as required to conform to these specifications.

.1 Notify Consultant in writing of satisfactory completion of Contractor’s inspection and submit verification that corrections have been made.

.2 Request Consultant’s inspection.

.2 Consultant’s Inspection:

.1 Consultant and Contractor to inspect Work and identify defects and deficiencies.

.2 Contractor to correct Work as directed.

.3 Completion Tasks: submit written certificates that tasks have been performed as follows:

.1 Work: completed and inspected for compliance with these specifications.

.2 Defects: corrected and deficiencies completed.

.3 Equipment and systems: tested, adjusted and fully operational.

.4 Certificates required by Utility companies: submitted.

.5 Operation of systems: demonstrated to the Consultant.

.6 Work: complete and ready for final inspection.

.7 All Submittals have been provided

.4 Final Inspection:

.1 When completion tasks are done, request final inspection of Work by Consultant, and Contractor.

.2 When Work incomplete according to Consultant, complete outstanding items and request re-inspection.

.5 Declaration of Substantial Performance: when Consultant considers deficiencies and defects corrected and requirements of Contract substantially performed, make application for Certificate of Substantial Performance.

Page 59: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 77 00 Parkland County CLOSEOUT PROCEDURES Issued for Tender Page 2 of 2

SPC-01 77 00-Closeout Procedures-60638222.docx

.6 Commencement of Lien and Warranty Periods: date of Owner's acceptance of submitted declaration of Substantial Performance is to be date for commencement for warranty period and commencement of lien period unless required otherwise by lien statute of Place of Work.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 60: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 78 00 Parkland County CLOSEOUT SUBMITTALS Issued for Tender Page 1 of 3

SPC-01 78 00-Closeout Submittals-60638222.docx

1.0 GENERAL

1.1 Administrative Requirements

.1 Pre-warranty Meeting:

.1 Convene meeting one week prior to contract completion with Consultant, to:

.1 Verify Project requirements.

.2 Review warranty requirements.

.2 Consultant shall establish communication procedures for:

.1 Notifying the Contractor of any construction warranty defects.

.2 Determine priorities for the type of defects.

.3 Determine reasonable response times.

.3 The Contractor shall provide contact information for the bonded and licensed company engaged by the Contractor for warranty work action: provide name, telephone number and address of company authorized for construction warranty work action.

.4 Ensure that a copy of this contact is located within local service area of warranted construction, is continuously available, and is responsive to inquiries for warranty work action.

1.2 Action and Informational Submittals

.1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures.

.2 Provide evidence of source and quality of all products supplied.

1.3 As-Built Documents and Samples

.1 Maintain, at site for Consultant one record paper copy and a PDF version of:

.1 Contract Drawings.

.2 Specifications.

.3 Addenda.

.4 Change Orders and other modifications to Contract.

.5 Reviewed shop drawings, product data, and samples.

.6 Field test records.

.7 Inspection certificates.

Page 61: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 78 00 Parkland County CLOSEOUT SUBMITTALS Issued for Tender Page 2 of 3

SPC-01 78 00-Closeout Submittals-60638222.docx

.8 Manufacturer's certificates.

.2 Store record documents and samples in field office apart from documents used for construction.

.1 Provide files, racks, and secure storage.

.2 Maintain duplicate PDF records in an onsite location and also an offsite location, to help guard against the loss of information.

.3 Label record documents and file in accordance with Section number listings in List of Contents of this Project Manual.

.1 Label each document "PROJECT RECORD" in neat, large, printed letters.

.4 Maintain record documents in clean, dry and legible condition.

.1 Do not use record documents for construction purposes.

.2 Keep record documents and samples available for inspection by Consultant.

1.4 Recording Information on Project Record Documents

.1 Record information on a set of drawings, printed by the Contractor for that purpose.

.2 Use felt tip marking pens, maintaining separate colours for each major system, for recording information.

.3 Record information concurrently with construction progress.

.1 Do not conceal Work until required information is recorded.

.2 The Contractor shall scan all of the record drawing sheets on a weekly basis and provide PDF copies to the Consultant as a means to safeguard the information and to have a record of updates as the project unfolds.

.4 Contract Drawings and shop drawings: mark each item to record actual construction, including:

.1 Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements.

.2 Measured locations of internal utilities and appurtenances, referenced to visible and accessible features of construction.

.3 Field changes of dimension and detail.

.4 Changes made by change orders.

.5 Details not on original Contract Drawings.

Page 62: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 01 78 00 Parkland County CLOSEOUT SUBMITTALS Issued for Tender Page 3 of 3

SPC-01 78 00-Closeout Submittals-60638222.docx

.6 References to related shop drawings and modifications.

.5 Specifications: mark each item to record actual construction, including:

.1 Manufacturer, trade name, and catalogue number of each product actually installed, particularly optional items and substitute items.

.2 Changes made by Addenda and change orders.

.6 Other Documents: maintain manufacturer's certifications, inspection certifications, field test records, required by individual specifications sections.

.7 Provide digital photos, if requested, for site records.

.8 The Contractor shall be responsible to scan all record drawings that are marked up onsite to PDF and provide in a well-organized and labelled fashion to the Consultant prior to the final closeout of the project.

2.0 PRODUCTS

.1 Not used.

3.0 EXECUTION

.1 Not used.

END OF SECTION

Page 63: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 05 16 Parkland County AGGREGATE FOR EARTHWORK Issued for Tender Page 1 of 3

SPC-31 05 16-Aggregates for Earthwork-60638222.docx

GENERAL

Action and Informational Submittals

PRODUCTS

Materials

Greatest dimension to exceed 5 times least dimension.

Culvert bedding material shall meet the following gradations:

Well rounded or fractured gravel:

Sieve Size (µm) Percent Passing (By Weight) 10,000 100 5,000 95 - 100 2,500 80 - 100 1,250 50 - 85 630 30 - 65 315 10 - 30 160 2- 10

Source Quality Control

Page 64: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 05 16 Parkland County AGGREGATE FOR EARTHWORK Issued for Tender Page 2 of 3

SPC-31 05 16-Aggregates for Earthwork-60638222.docx

EXECUTION

Preparation

Process aggregate uniformly using methods that prevent contamination, segregation and degradation.

Blend aggregates, as required, including reclaimed materials that meet physical requirements of specification is permitted in order to satisfy gradation requirements for material and, percentage of crushed particles, or particle shapes specified.

Use methods and equipment approved in writing by Consultant.

Stockpiling sites to be level, well drained, and of adequate bearing capacity and stability to support stockpiled materials and handling equipment.

Material should be stockpiled on existing asphalt surfaces. Obtain Consultant approval prior to stockpiling in vegetated areas.

Stockpile aggregates on ground but do not incorporate bottom 300 mm of pile into Work.

Separate different aggregates by strong, full depth bulkheads, or stockpile far enough apart to prevent intermixing.

Do not use intermixed or contaminated materials. Remove and dispose of rejected materials within 48 hours of rejection.

Stockpile materials in uniform layers of thickness as follows:

Maximum 1.5 m for coarse aggregate and base course materials.

Maximum 1.5 m for fine aggregate and sub-base materials.

Page 65: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 05 16 Parkland County AGGREGATE FOR EARTHWORK Issued for Tender Page 3 of 3

SPC-31 05 16-Aggregates for Earthwork-60638222.docx

Maximum 1.5 m for other materials.

Uniformly spot-dump aggregates delivered to stockpile in trucks and build up stockpile as specified.

Do not cone piles or spill material over edges of piles.

Do not use conveying stackers.

Cleaning

Leave Work area clean at end of each day.

Leave any unused aggregates in neat compact stockpiles.

END OF SECTION

Page 66: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 11 00 Parkland County CLEARING AND GRUBBING Issued for Tender Page 1 of 1

SPC-31 11 00-Clearing and Grubbing-60638222.docx

GENERAL

Definitions

Clearing shall consist of cutting, piling, removal or otherwise disposing of trees, brush vegetative growth and logs above the ground surface.

Grubbing shall consist of removal or otherwise disposing of all objectionable material below the ground surface including roots, brush, stumps and buried debris. Grubbing shall consist of removal or otherwise disposing of all objectionable material to a depth of 0.6 m below the ground surface including roots, brush, stumps and buried debris.

Protection

PRODUCTS

EXECUTION

END OF SECTION

Page 67: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 11 00.01 Parkland County CLEARING, MULCHING AND TIMBER SALVAGE Issued for Tender Page 1 of 3

SPC-31 11 00 01-Cleaning_MuchingandTimberSalvage-60638222_new.doc

1.0 GENERAL 1.1 Definitions .1 Tree Clearing:

Tree Clearing shall consist in general of cutting, piling, removing or otherwise disposing of trees, brush, stumps, logs and roots as designated by the Consultant.

. .2 Mulching:

Mulching shall include the complete disposal of the standing timber or snags, brush, shrubs, and any slash, waste wood or wood debris. Areas that require clearing shall utilize this mulching standard.

.3 Timber Salvage

No timber salvage required. All clearing Debris should be removed offsite. 1.2 Regulatory Requirements

.1 The Contractor shall familiarize himself with all applicable federal and provincial legislation and regulations concerning environmental protection and shall conduct his activities in accordance with such legislation and regulations, including, but not limited to, the provincial Environmental Protection and Enhancement Act and Water Act, and the federal Fisheries Act and Navigable Waters Protection Act.

The Contractor shall comply with the conditions of all environmental approvals, permits,

licenses and authorizations issued for the project that pertain to the Contractor’s work. The Contractor shall obtain any further environmental approvals, permits, licenses and/or authorizations for his temporary works as may be required for the Contractor’s work.

In the event of conflicting statements between the various Acts, Authorizations, Permits, and

Codes of Practice, the more stringent requirement shall apply

.2 The Contractor shall adhere to Provincial and local bylaws regarding disposal of merchantable timber in the area.

.3 Federal and provincial regulations provide for the conservation of migratory birds (federal

Migratory Birds Convention Act) and non-migratory birds (provincial Wildlife Act), and the protection of their nests and eggs. Tree clearing in areas where birds may be nesting should take place before March 1. The Contractor will review these areas with the consultant and the time of award and adjust his schedule accordingly.

.4 Should construction activities be forecasted to occur during the peak nesting period of May 1

to August 31, contractor shall complete Bird Nesting Surveys as required to facilitate construction. Contractor shall ensure that bird nest surveys have been completed in accordance with the regulations and requirements of the Migratory Bird Act.

Page 68: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 11 00.01 Parkland County CLEARING, MULCHING AND TIMBER SALVAGE Issued for Tender Page 2 of 3

SPC-31 11 00 01-Cleaning_MuchingandTimberSalvage-60638222_new.doc

1.3 Protection

.1 The Contractor shall prevent damage to fencing, trees, landscaping, natural features, benchmarks, existing buildings, utility lines, site appurtenances, water courses and root systems of trees which are to remain. All damage incurred shall be repaired by the Contractor at his expense.

.2 The Contractor shall apply tree paint approved by Consultant, to cuts or scars suffered by

vegetation designated to remain. 2.0 PRODUCTS

.1 The Contractor shall supply all labour, materials and equipment required for clearing, and mulching.

3.0 EXECUTION .1 General

The Contractor shall cut trees and brush, remove all roots, and remove, pile and mulch all trees (except trees to be preserved), brush, stumps, logs and roots within the limits of the right-of-way (ROW), and also from such areas as may be required for off-take ditches, channel changes, easements, borrow excavations, stockpile areas, access and haul roads, etc., as required by the Consultant. All underbrush and down trees protruding into the ROW are to be disposed of in the same manner. Timber, brush, stumps, logs or roots shall not be piled upon the ROW, and the limits of the ROW shall be left in proper condition for fencing. All tree branches extending into the ROW, which hang within 6 m of the ground, shall be cut off close to the trunk in a neat and workmanlike manner. Where the Contractor fails to observe clearing and mulching restrictions and limitations and causes damage to property beyond areas as indicated on the Drawings or as designated by the Consultant, such damages shall be the Contractor’s liability and shall be corrected immediately at the Contractor’s expense. The Contractor shall leave the ground surface in condition suitable for immediate topsoil stripping and grading operations.

.2 Preservation of Trees

The Consultant may require the Contractor to preserve certain trees within the ROW. Underbrush, down timber, snags and roots shall be removed from the vicinity of such preserved trees to a clear space within the ROW, and there mulched.

.3 Dangerous Trees

The Consultant may require the Contractor to cut down unsafe trees which are located outside the areas designated for clearing.

Page 69: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 11 00.01 Parkland County CLEARING, MULCHING AND TIMBER SALVAGE Issued for Tender Page 3 of 3

SPC-31 11 00 01-Cleaning_MuchingandTimberSalvage-60638222_new.doc

.4 Disposal of Clearing Debris by Mulching

The Contractor shall dispose of clearing debris by chipping and mulching debris and spreading it on site as directed by the Consultant. No burning of materials will be allowed until prior written approval is obtained from the Owner and the Authorities. Mulching shall mean the following:

• Mulching may include but not be limited to the following example operations, flail

operations, rotary grinding operations, pulverizing operations, rotary or alternative cutting operations, chipping operations and or any other type of treatment which will meet the final requirements of the work required.

• Mulching methodologies used by the Contractor shall achieve the following requirements:

• All materials shall lay flat to the soil. In cases of convoluted or mixed material the height protruding above the soil level shall not exceed 0.3 metres and will not exceed a single stem protrusion;

• No single portion of the mulched material will be longer than 0.5 metres and shall not exceed 70 mm in diameter. Exceptions for large diameter woody materials, which upon mechanical manipulation, resist break-up into a size of less than 70 mm showing evidence of debarking, may be considered by the Consultant. When the contractor mulches the woody material on site, there is no minimum residual height requirement, but when the Contractor stockpiles the mulched material and spreads out later to a maximum residual height for all material shall be 70 mm;

• The Contractor shall undertake fringe clean-up operations to remove displaced materials in adjacent timber; including tangled or hung-up material, leaning or broken material, or any material displaced by the mulching process. This also includes any material damaged by the mulching process within proximity to the cleared area deemed to be a safety hazard by the Consultant;

• Roadways and adjacent lands shall be inspected for a minimum of 20 metres from the edge of the property or border of the area cleared by the mulching operation. Materials deposited on adjacent lands by the clearing or mulching process shall be returned to the ROW and must meet minimum mulching standards;

• Burial of material will not be allowed; • All stumps shall be reduced to ground level through the mulching process, or using

any other acceptable means acceptable to the Consultant; • Mulching operations shall not incorporate or mix mulched materials into the subsoil.

In cases where topsoil is limited, surface mulching operations shall not be allowed to mix topsoil and subsoil horizons.

.6 Control of Equipment

The Contractor shall carefully control all equipment and work operations so that his operations do not extend beyond the designated working limits unless otherwise specifically authorized by the Consultant.

END OF SECTION

Page 70: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 14 13 Parkland County SOIL STRIPPING AND STOCKPILING Issued for Tender Page 1 of 2

SPC-31 14 13-Soil Stripping and Stockpiling-60638222.docx

GENERAL

Definitions

PRODUCTS

EXECUTION

Page 71: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 14 13 Parkland County SOIL STRIPPING AND STOCKPILING Issued for Tender Page 2 of 2

SPC-31 14 13-Soil Stripping and Stockpiling-60638222.docx

END OF SECTION

Page 72: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 13 Parkland County EARTHWORKS AND GRADING Issued for Tender Page 1 of 3

SPC-31 23 13-Earthworks and Grading-60638222.doc

1.0 GENERAL 1.1 Definitions

.1 Common Excavation: “Common Excavation” means the excavation of on-Site soils required as structural fill by these specifications, excluding Topsoil and Subsoil Stripping, Borrow Area Excavation, Rock Excavation, and Excavation to stockpile or offsite disposal.

.2 Earthwork: Earthwork means excavating of all types, backfilling, filling, compacting, grading

and related work. .3 Waste Excavation is the work involved in excavation, disposing and levelling in designated

locations those materials determined to be unsuitable or unstable by the Consultant and cannot be removed by conventional earthmoving equipment.

.4 Import Clay: Suitable clay to be sourced and supplied by the Contractor in the construction

for fills to be approved by the Engineer. 1.2 Protection

.1 The Contractor shall be responsible for locating and protecting all existing underground and surface structures, utility pipelines, overhead lines and poles, fences, water and sewer mains, building services, cables, culverts, sidewalks and other works. All damage incurred shall be repaired by the Contractor at his expense.

2.0 PRODUCTS

.1 The Contractor shall supply all labour, materials and equipment required for site grading. 3.0 EXECUTION 3.1 Grading

.1 Grading shall include the removal and/or satisfactory placement of all materials necessary for the construction and preparation of embankment, slopes, drainage works, alignment, grade and cross-section shown on the Drawings or as required by the Consultant. Grade to elevations and dimensions indicated on Drawings within a tolerance of plus or minus 15 mm.

.2 Contractor will be responsible for grading areas adjacent to pavement where required to

ensure no pooling on pavement surfaces. .3 Conditions requisite for the completion of grading work will be a roadway or other works

which are smooth and compact over the entire width, firm side slopes with regular shoulder lines, clean side ditches, satisfactory approaches, intersections and entrances, and smooth back slopes. All soft and yielding material in the roadway, if so directed shall be removed and replaced with acceptable material, and all loose stones, clods, weeds, trash, etc. shall be removed from the roadway, side slopes, ditches and back slopes. All improperly compacted material shall be excavated, brought to optimum moisture content if required, and recompacted at the Contractor's own expense. On the side slopes and back slopes, and in the bottom of ditches, all projecting boulders must be removed or broken off at least flush with the lines and grades, and the resultant cavities, if any, backfilled.

.4 Sequence, schedule and perform excavation and fill placement operations to make the best

use of all excavated material, and to minimize the volume of import material.

Page 73: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 13 Parkland County EARTHWORKS AND GRADING Issued for Tender Page 2 of 3

SPC-31 23 13-Earthworks and Grading-60638222.doc

.5 Locate and protect utility lines, survey reference points, instrumentation, fencing, and other facilities.

.6 Remove and dispose of all snow, surface ice, and excess water prior to starting the

excavation. .7 Prior to commencing excavation:

.1 Contact all affected utility companies regarding exact location and current status of

all utilities, voltage of underground and overhead power lines and pressure of natural gas lines.

.2 Notify Consultant if any utility lines have been omitted from or incorrectly indicated

on Drawings. .3 Identify known underground utilities. Stake and flag locations. Identify and flag

surface and aerial utilities. .4 Expose utilities to be crossed to confirm horizontal and vertical alignment of existing

utilities. .5 Expose existing utility lines by hand excavation or hydrovac to confirm location

before machine digging within 600 mm of lines or as stated in the crossing agreement, whichever is more strict.

.6 Maintain and protect existing above and below grade utilities which pass through

work area. Protect active utility lines exposed by excavation, from damage. Hand excavate to final elevations and dimensions.

.7 Maintain and protect all existing features as noted in the drawings. .8 Where existing pipes, ducts or other underground services intersect a trench,

support trench in a manner approved by Utility. .9 Where existing overhead line poles are adjacent to excavations, temporarily support

poles in a manner approved by Utility.

3.2 Embankment .1 Embankment shall be constructed by depositing, shaping and compacting acceptable

excavated materials. The embankments shall be constructed above the natural ground or other level as required by the Consultant, in conformity with the lines, grades and cross-sections shown on the Drawings.

.2 All suitable material from excavations shall be used in forming embankments or shall be

otherwise disposed of as the Consultant may require. .3 Embankment shall be formed of suitable unfrozen material. Stumps, roots, trees, rubbish,

sod, topsoil or other unsuitable material shall not be placed in the embankment. .4 Embankment material shall not be placed on frozen earth, snow or ice, nor shall frozen soils,

ice or snow be placed in any embankment. However, on approval of the Consultant, embankment material may be placed on the existing ground surface if frost penetration is 0.10 m or less. Any frozen material in the embankment shall be removed and disposed of at the Contractor's expense before proceeding with further embankment construction.

Page 74: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 13 Parkland County EARTHWORKS AND GRADING Issued for Tender Page 3 of 3

SPC-31 23 13-Earthworks and Grading-60638222.doc

.5 Road surface to be adjusted with additional of granular material to achieve a minimum 0.6% side slope from center line for positive drainage.

.6 Embankment shall be constructed so that after settlement is complete the required grade

and cross-section is attained at all points. If at any time before final acceptance of the work the embankment settles below the required grade, it shall be brought back to the required grade by the Contractor.

3.3 Compaction

.1 All material placed in embankments shall be spread and bladed smooth in successive layers, not to exceed 0.15 m in depth when compacted and to the full width of the cross-section. Each layer shall be compacted by means approved by the Consultant to a minimum of 98% Standard Proctor Density, except that under roadways and parking areas, the top 1.0 m shall be compacted to 100% of Standard Proctor Density. Materials placed in the upper 0.3 m of embankments shall not contain rock which has a diameter larger than 0.10 m. The material in each layer shall be compacted at the optimum moisture content plus or minus 2%, unless otherwise required by the Consultant. In case of controversy, the degree of compaction and/or moisture content will be determined by in situ density testing before the succeeding layer is placed.

.2 Nominal compaction is required for ditches and swale bottoms to 95% standard Proctor

Maximum Dry Density (SPMDD). .3 Compaction over the entire surface area of each layer shall be obtained by equipment to

meet the specified density requirements. Hauling equipment will not be accepted in lieu of compaction equipment. Compaction to the specified density shall be obtained uniformly throughout each layer.

.4 Where the embankment to be placed traverses muskeg or yielding ground and it is not

possible to place the initial embankment lift in a 0.15 m compacted depth, the Contractor may, upon approval of the Consultant, construct the first embankment lift to a depth sufficient to support the construction equipment. All embankment to be constructed above this support will be constructed in 0.15 m compacted depths, as herein before specified.

.5 Where moisture content tests indicate that material being used for embankment is above

optimum moisture content, the material shall be thoroughly worked until its optimum moisture content is reached.

.6 Where moisture content tests indicate the material for embankment is below optimum

moisture, water shall be added. The material shall be thoroughly disced and broken down, water added in amounts as required, and the material thoroughly worked to mix the water uniformly throughout the soil prior to commencing compaction operations. The type of water hauling and spraying equipment used shall be satisfactory to the Consultant.

END OF SECTION

Page 75: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 1 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

1.0 GENERAL 1.1 References

.1 ASTM C117, Test Method for Material Finer Than: 0.075 mm Sieve in Mineral Aggregates by Washing.

.2 ASTM C136, Method for Sieve Analysis of Fine and Coarse Aggregates. .3 ASTM D698, Test Methods for Moisture Density Relations of Soils and Soil Aggregate

Mixtures Using 2.49 kg Rammer and 304.8 mm Drop. .4 ASTM D1557, Test Methods for Moisture Density Relations of Soils and Soil-Aggregate

Mixtures Using 4.54 kg Rammer and 457 mm Drop. 1.2 Definitions

.1 Common excavation:

.1 Common excavation: excavation of materials of whatever nature, which are not included under definitions of rock excavation.

.2 Trenching for the purposes of installation of culvert, drainage or other below

ground infrastructure or utilities shall not be considered common excavation and shall be incidental to the installation, with no separate payment.

.2 Washed Gravel:

.1 Washed, crushed or screened stone or gravel consisting of hard and durable

particles meeting the following gradation limits and free from sand, clay, cementitious, organic and other deleterious material.

Sieve Size (mm) Percent Passing by Mass

25 100 5 Maximum 10

0.08 Maximum 2

.3 Native Backfill:

.1 Native backfilling shall consist of replacing the excavated material in even layers not exceeding 150 mm in depth and compacting each layer by mechanical means to 98% Standard Proctor Density, unless a higher density is specified in other sections.

.4 Topsoil:

.1 The top layer of soil containing organic material capable of supporting good

vegetative growth and suitable for use in top dressing, landscaping and seeding.

.5 Bedding Material:

.1 In accordance with Section 31 05 16 - Aggregates for Earthwork.

Page 76: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 2 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

1.3 Protection of Existing Features

.1 Existing buried utilities and structures: .1 Prior to commencing any excavation work, notify applicable Department or

authorities and Consultant; establish location and state of use of buried utilities and structures. Clearly mark such locations to prevent disturbance during work. Markings must be maintained throughout construction.

.2 Maintain and protect from damage, water, sewer, gas, electric, telephone and

other utilities and structures encountered. All damage incurred shall be repaired by the Contractor at his expense.

.2 Existing buildings and surface features:

.1 Maintain and protect from damage existing buildings, trees and other plants,

lawns, fencing, service poles, wires, rail tracks, paving, survey bench marks and monuments which may be affected by work. All damage incurred shall be repaired by the Contractor at his expense.

1.4 Safety Requirements

.1 The Contractor will be required to observe all applicable sections of the Alberta Regulations 271/76 made under the Occupational Health and Safety Act covering worker safety in trenches and excavations.

.2 Refer to Sections 01 35 29.06 Health and Safety Requirements.

1.5 Samples

.1 At least 2 weeks (14 days) prior to commencing work, inform Consultant of proposed source of granular materials.

.2 The Contractor shall provide a sieve analysis of the material for the Consultant's

approval. .3 Sand and gravel shall be approved by the Consultant before being used.

2.0 PRODUCTS 2.1 Stabilizing Base Gravel

.1 Stabilizing base gravel shall be well graded gravel consisting of hard durable particles free from clay lumps, cementation, organic material, frozen material and other deleterious materials.

.2 The material shall meet the following gradations:

Screened Rock

Sieve Size(µm) Percent Passing (by weight) 40,000 100 25,000 90 – 100 20,000 20 – 55 10,000 0 – 5

Page 77: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 3 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

2.2 Filter Fabric

.1 In accordance with Section 31 32 19.01 - Geotextile.

2.3 Class 1 Backfill Material

.1 Material for Class 1 backfill shall consist of sound, hard, durable, uniformly graded pit-run or crushed gravel and shall not contain organic or soft materials, materials that break up when alternately frozen and thawed or wetted and dried, or other deleterious materials. When compacted near the optimum moisture content to not less than 98% of the maximum dry density corrected for the stone content as determined by ASTM D698, the material shall have a minimum bearing ratio as defined by ASTM D1883, of fifteen percent (15%).

3.0 EXECUTION 3.1 Site Preparation

.1 The Contractor will be required to strip organic material, clear and grub, remove weeds and grasses as specified or as required by the Consultant prior to excavation. Avoid intermixing of subsoil fill materials with organic material and from other forms of contamination. Stripped material to be stockpiled on site for use in site restoration.

.2 The Contractor shall separate and remove all rocks in excess of 20 mm, tree roots and

topsoil so that those materials are not present within the soils which need to be compacted during backfilling or subgrade preparation and no separate or additional payment will be made for such separation and removal.

3.2 Trenching

.1 Trench width:

.1 Excavation must not interfere with normal 45° splay of bearing from bottom of any footing.

.2 For trench excavation, unless otherwise authorized by Consultant in writing, do

not excavate more than 30 m of trench in advance of installation operations and do not leave open more than 10 m at end of day's operation.

.3 The Contractor shall confine his activities to the immediate area of the trench. All

activities outside trench boundaries shall be performed so as not to damage other existing features.

.2 All excavated material shall be piled at least 1.0 m clear of the trench top to prevent

material from falling back into the excavation. The material shall be piled in such a manner that it will not endanger the work or obstruct other work or rights-of-way. Sufficient clear space must be left on one side of the trench to accommodate the Consultant's stakes.

.3 The trench shall be excavated so that the pipe can be laid to the alignment, grade and

depth required.

Page 78: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 4 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

.4 Trench Rock Excavation: .1 Where excavation is made in rock or where excavation is made in a material

which cannot provide an even, uniform and smooth surface; or where large stones are encountered in the trench, such material shall be removed to provide a clear distance between any part or projection of such material and the surface of all pipe and fittings of not less than 150 mm for 600 mm outside diameter pipe or less, and 200 mm for pipe having an outside diameter greater than 600 mm. The subgrade shall then be made by backfilling with an approved material compacted in 75 mm layers at the Contractor’s expense. The finished subgrade surface shall be shaped by hand tools to provide a uniform and continuous support for the pipe.

.2 Blasting for excavation will be permitted only with the approval of the Consultant

and only when proper precautions are taken for the protection of persons or property. The Contractor's method of procedure in blasting shall conform to provincial statutes and municipal ordinances.

.5 The subgrade shall provide a uniform and continuous support for the pipe and fittings on

solid undisturbed ground. Any over excavation by the Contractor below the required grade shall be backfilled at his expense with an approved compacted material.

3.3 Unstable Subgrade

.1 Where the subgrade of the trench is unstable or will not properly support the pipe, or

where it contains materials harmful to the pipe such as ashes, cinders, refuse, vegetable or organic material, the Contractor shall excavate such material to the width of the trench, depth and length ordered by the Consultant and dispose of the material as directed. The subgrade shall then be made by backfilling with an approved stabilizing gravel compacted in 75 mm layers. The finished subgrade surface shall be shaped by hand tools to provide a uniform and continuous support for the pipe.

.2 The stabilization gravel shall be wrapped in the non-woven geotextile as specified. The

non-woven geotextile shall be overlapped a minimum of 300 mm at all joints to provide a full, continuous wrap and shall be smooth and free of tension, stress, folds, wrinkles or creases.

3.4 Shoring

.1 When close sheeting is required, it shall be so driven as to prevent adjacent soil from

entering the trench either below or through such sheeting. The Consultant reserves the right to order the sheeting driven to the full depth of the trench or to such additional depths as may be required for the protection of the work.

.2 Trench bracing may be removed when the backfilling has reached the respective level of

such bracing. Sheeting shall be removed as the backfilling proceeds. Backfilling of holes left by sheeting below the trench bottom shall be carefully compacted, and thereafter backfilling and withdrawal of sheeting shall proceed together. No voids shall be left in the backfill by the withdrawal of the sheeting.

.3 When a cage or shield is used in the trench instead of shoring, special care shall be taken to ensure that there is no lateral or longitudinal movement of the pipe when the cage is moved. The cage shall be raised vertically so that the bottom member is clear of the crown of the pipe before the cage is pulled forward in the trench.

Page 79: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 5 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

.4 The Contractor shall utilize safe trench slopes, shoring, bracing cages or shields, and de-watering to ensure safe working conditions and include any such provisions in the unit prices bid for any items that require excavation, trenching and/or backfilling.

3.5 Trench Drainage

.1 Gutters, storm water ditches or natural drainage channels shall not be obstructed. Satisfactory provisions shall be made for alternate drainage where this is impractical.

.2 The trench shall be so drained that the workmen may work safely and effectively. All

water encountered in trenches shall be pumped or bailed out, and in no case shall the pipe be used as a drain for such water. Contractor will be required to replace bedding material at these encountered locations, incidental to the original rate. It is essential that the discharge of the trench dewatering pumps be conducted away from the site of the work and into natural drainage channels, drains or storm sewers.

3.6 Backfilling

.1 Bedding and initial backfilling shall be as specified for the particular pipe installed. .2 General backfilling:

.1 Class 1 backfill as defined in Section 1.1 - Definitions shall be used. .2 No boulders, rock, ice, snow, organic material or debris shall be permitted in the

trench. These unsuitable materials shall be hauled and disposed of offsite. .3 All surplus excavated material shall also be hauled away or disposed of as

directed by the Consultant. In the event of deficiency of backfill material, suitable material shall be supplied by the Contractor at his expense. Supplied material shall be approved by the Consultant prior to importing to site.

.4 All trenches shall be backfilled as the work proceeds and no more than 30 m

shall be left open at the end of a day’s work. All open trenches to be fenced off to prevent wildlife entrapment.

.3 Culvert backfilling:

.1 Backfill with suitable engineering fill such as well-graded sand and gravel. Placement of backfill material should not exceed 150 mm in compacted thickness.

.4 Boardwalk backfilling:

.1 Backfill with suitable engineering fill such as well-graded sand and gravel. Backfill should be free from gravel sizes or larger than 100 mm in diameter, and free from frozen, organic, or other deleterious materials.

3.7 Backfill Compaction

.1 The Contractor shall be responsible for adequate compaction of the trenches and for the correction of settlement during the maintenance period of the Contract. Mechanical compaction equipment shall not be used until there is sufficient cover to prevent damage to the pipe.

Page 80: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 23 33.01 Parkland County EXCAVATING, TRENCHING AND BACKFILLING Issued for Tender Page 6 of 6

SPC-31 23 33 01-Excavating Trenching & Backfilling-60638222.docx

.1 Trenches shall be compacted in 150 mm layers to 98% of Standard Proctor Density. Under roadways and parking areas, the top 1.0 meter shall be compacted to 100% of Standard Proctor Density.

.2 Culvert and boardwalk compaction is required at the bottom 150 mm thick lift of

backfill and top 300 mm backfill which is 95% of standard SPMDD within ±2% optimum moisture content (OMC), and in accordance with Parkland County Engineering Design Standards.

.2 The type of compaction equipment shall be chosen with regard to minimizing the

vibration effect on nearby buildings and utilities. The Contractor shall inspect the condition of buildings prior to construction. The Consultant shall have the right to request the Contractor to replace any equipment causing unacceptable vibrations. The Contractor is responsible for any damage caused to buildings due to construction.

3.8 Testing Backfill Compaction

.1 Compaction results shall be based on a minimum of one density test per culvert. unless a greater degree of testing is required under Section 01 45 00 - Quality Assurance and Quality Control. Additional tests may be called for by the Consultant as deemed necessary.

.2 If a density test indicates insufficient compaction at any depth, then two more densities,

where are proportionally representative of trench length, shall be taken at that depth. If the average of these tests is below the required density, the trench shall be re-excavated and re-compacted to meet the specified density.

.3 This testing in no way relieves the Contractor of his maintenance responsibilities with

respect to settlements as specified. The Contractor shall repair any settlement and damaged surface improvements due to the settlement, which occurs during the maintenance period.

.4 The cost of all initial testing will be borne by the Department and the Contractor is

responsible for the costs of any re-testing for areas where initial testing failed. Non-conformity with the specified density or moisture content shall constitute sufficient grounds for rejection of the work.

3.9 Tree Clearing and Protection

.1 The Owner objective is to minimize the damage or removal of healthy trees during the installation of any improvements under this contract. The Contractor shall become fully aware of the working area constraints and bid accordingly. The Contractor shall not remove any trees in any area without prior approval of the Consultant.

END OF SECTION

Page 81: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 32 19.01 Parkland County GEOTEXTILE Issued for Tender Page 1 of 2

SPC-31 32 19 01-Geotextile-60638222.docx

1.0 GENERAL

1.1 Action and Informational Submittals

.1 Submit in accordance with Section 01 33 00 Submittal Procedures.

.2 Submit manufacturer's instructions, printed product literature and data sheets for geotextiles and geomembranes and include product characteristics, performance criteria, physical size, finish and limitations at least 10 days prior to commencing any work.

.3 Samples:

.1 Samples of material are not required as a standard submission, however samples may be requested by Consultant

1.2 Delivery, Storage and Handling

.1 Deliver, store and handle materials in accordance with Section 01 61 00 - Common Product Requirements.

.2 Store geotextiles and membranes in a dry location and in accordance with manufacturer’s recommendations.

.3 Replace defective or damaged materials with new.

2.0 PRODUCTS

2.1 Materials: Geotextile

.1 Geotextile: non-woven synthetic fibre fabric, supplied in rolls.

.1 Width: 3.8 m minimum.

.2 Length: 110 m minimum.

.3 Composed of polypropylene fibers.

.2 Physical properties:

.1 Grab tensile strength and elongation: to ASTM D4632.

.1 Breaking force: minimum 912 N.

.2 Elongation at future: 50%.

.2 Hydraulic properties:

.1 Apparent opening size (AOS): to ASTM D 4751, 180 micrometres.

.2 Permitivity: to ASTM D 4491, 1.4 pers.

.3 Thread for sewn seams: equal or better resistance to chemical and biological degradation than geotextile.

Page 82: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 31 32 19.01 Parkland County GEOTEXTILE Issued for Tender Page 2 of 2

SPC-31 32 19 01-Geotextile-60638222.docx

3.0 EXECUTION

3.1 Examination

.1 Verification of Conditions: verify that conditions of substrate previously installed under other Sections or Contracts are acceptable for geotextile or geomembrane material installation in accordance with manufacturer's written instructions.

.1 Visually inspect substrate in presence of Consultant.

.2 Inform Consultant of unacceptable conditions immediately upon discovery.

3.2 Installation

.1 Construction shall be as per Manufacturer’s instruction.

.2 Place geotextile material by unrolling onto graded surface in orientation, manner and locations indicated and retain in position with pins.

.3 Place geotextile material smooth and free of tension stress, folds, wrinkles and creases.

.4 Place geotextile material on sloping surfaces in one continuous length from toe of slope to upper extent of geotextile.

.5 Protect installed geotextile material from displacement, damage or deterioration before, during and after placement of material layers.

.6 After installation, cover with overlying layer within 4 hours of placement.

3.3 Cleaning

.1 Progress Cleaning: clean in accordance with Section 01 74 00 - Cleaning.

.2 Final Cleaning: upon completion remove surplus materials, rubbish, tools and equipment in accordance with Section 01 74 00 - Cleaning.

END OF SECTION

Page 83: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 91 19.13 Parkland County TOPSOIL PLACEMENT Issued for Tender Page 1 of 2

SPC-32 91 19 13-Topsoil Placement-60638222.docx

1.0 GENERAL

1.1 Definitions

.1 Topsoil:

.1 The top layer of soil containing organic material capable of supporting good vegetative growth and suitable for use in top dressing, landscaping and seeding.

.2 Weeds:

.1 Includes, but not limited to, dandelions, jimsonweed, quackgrass, horsetail, morning glory, rush grass, mustard, lambsquarter, chickweed, crabgrass, Canadian thistle, tansy, ragwort, Bermuda grass bindweed, bent grass, perennial sorrel, brome grass, red root, pigweed, buckweed, scentless chamomile, toadflax, foxtail and perennial sow thistle.

2.0 PRODUCTS

2.1 Topsoil

.1 Topsoil to be free of subsoil, clay lumps, stones, live plants, roots, sticks or other extraneous matter.

3.0 EXECUTION

3.1 Topsoil

.1 The Consultant shall approve the subgrade prior to placing topsoil.

.2 Do not place topsoil when either topsoil or subgrade is frozen, excessively wet, extremely dry, or in a condition inhibiting proper grading, cultivation, or compaction.

.3 Spread topsoil uniformly on prepared subsoil to achieve a minimum compacted or settled depth of 100 mm for sodded areas and 150mm for hydroseed areas, unless otherwise stated.

.4 Remove stones larger than 50 mm, weeds, roots and other foreign matter.

.5 When loading topsoil from a stockpile, do not leave a vertical face at end of day’s work.

.6 Scarify subgrade prior to installing topsoil.

.7 Broadcast soil additives on subsoil base prior to topsoil installation if required from soil test results.

.8 Do not mix topsoil and subsoil during loading and hauling.

.9 Install dry topsoil during dry weather over approved dry unfrozen subgrade.

.10 Manually spread topsoil around trees and plants to prevent damage by grading and levelling equipment.

.11 Float the area until surface is smooth. Cut smooth and flush areas adjacent to catch basin rims. Remove all lumps, rocks, roots and other debris from the finished material and from the site.

Page 84: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 91 19.13 Parkland County TOPSOIL PLACEMENT Issued for Tender Page 2 of 2

SPC-32 91 19 13-Topsoil Placement-60638222.docx

.12 Fine grade to eliminate rough or low areas and to ensure positive drainage.

.13 Compact topsoil with suitable rollers to the satisfaction of the Consultant.

.14 Final topsoil grades for seeded areas shall be flush to finished grade at surface structures, i.e. manholes, sidewalks and curbs.

.15 For sodding, the final grade of compacted topsoil shall be 25 mm below finished grade of adjacent work such as walk, curb and manhole and 25 mm below crown of adjacent turfed area.

.16 When abutting an existing turfed area, cut the existing turf so as to form a straight or non-jagged joint with the new seeded or sodded area.

.17 The Consultant shall approve topsoil preparation prior to seeding or sodding.

3.2 Clean-Up

.1 Clean soil and debris resulting from work done under this section off roadway, walkway and surrounding areas at the end of each working day or as reviewed by the Consultant.

END OF SECTION

Page 85: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 92 19.13 Parkland County SEEDING AND SOD Issued for Tender Page 1 of 5

SPC-32 92 19 13-Seeding and Sod-60638222.docx

1.0 GENERAL

1.1 Definitions

.1 Topsoil:

.1 The top layer of soil containing organic material capable of supporting good vegetative growth and suitable for use in top dressing, landscaping and seeding.

.2 Weeds:

.1 Includes, but not limited to, dandelions, jimsonweed, quackgrass, horsetail, morning glory, rush grass, mustard, lambsquarter, chickweed, crabgrass, Canadian thistle, tansy, ragwort, Bermuda grass bindweed, bent grass, perennial sorrel, brome grass, red root, pigweed, buckweed, scentless chamomile, toadflax, foxtail and perennial sow thistle.

1.2 Product Delivery, Storage and Handling

.1 Delivery grass seed in the original containers, tagged with identification as to the analysis of seed mixture, percentages of seed, year of seed production, net weight and date.

.2 Deliver seed to site only when required.

1.3 Substitution

.1 The Consultant will review requests by the Contractor for substitution of seed mixes.

2.0 PRODUCTS

2.1 Seed Mixture

.1 Certified Canada No. 1 mixture, free of disease, weed seeds or foreign matter, minimum germination of 75%, minimum purity of 97%. All seed must be from a recognized seed firm, meeting the requirements for the Seeds Act for Canada No. 1 Seed. Seed shall be certified No. 1 grade. A germination test and/or weed seed analysis may be requested and all lawn seed must comply with federal and provincial seed laws. The seed shall consist of the following mix:

Blue Grass 80% Fescue 10% Rye Grass 10%

2.2 Sod

.1 Certified No. 1 cultivated turf sod; with strong fibrous root system, thick and healthy growth and delivered 24 hours from the time of cutting. Sod showing signs of deterioration due to age or lack of moisture will be rejected. Sod must be free of stones, burns, dry or bare spots, tears and delivered moist, cut in strips of uniform width and thickness and comprised of the appropriate mix as specified in the Municipality/City Standards.

Page 86: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 92 19.13 Parkland County SEEDING AND SOD Issued for Tender Page 2 of 5

SPC-32 92 19 13-Seeding and Sod-60638222.docx

2.3 Binder

.1 Use Turfmaster Hydro Seal or equivalent compatible binder additive at the manufacturer’s recommended rate, sufficient to mix a consistent slurry.

.2 Binder shall be mixed and supplied by a supplier approved by the Consultant and shall have tested rates or purity.

2.4 Mulch

.1 Material shall be wood cellulose fibre containing no contaminants.

.2 Fibre shall be supplied by a recognized supplier and shall have a certified weight and composition.

.3 Minimum application rate is 16.0 kg of air-dry fibre per 100 m².

.4 Fibre shall be measured as it is fed into the seeder.

2.5 Fertilizer

.1 Use standard commercial fertilizers, with guaranteed chemical analysis.

.2 Fertilizers shall be clearly labelled and furnished in unopened moisture proof containers.

.3 Fertilizer shall be granular water-soluble type completely synthetic slow release with 35% of nitrogen content in water insoluble form.

2.6 Water

.1 Clean and free of any substance that may inhibit vigorous growth of grass.

2.7 Equipment

.1 Cultivators: capable of scarifying, discing or harrowing.

.2 Dry Seeders: of the “Brillion” type, capable of rolling and covering the seed with 3 mm to 6 mm of soil; or of the cyclone type, with flexible wire mat drag.

.3 Hydro Seeders: capable of thoroughly mixing water, seed, fertilizer and pulverized wood fibre and of uniformly spraying the mix at designated rate.

.4 Rollers: of suitable size and mass.

3.0 EXECUTION

3.1 Planting Season

.1 Grass Seeding: recommended season May 1 to September 15.

.2 Sod Laying: recommended season May 1 to September 30.

Page 87: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 92 19.13 Parkland County SEEDING AND SOD Issued for Tender Page 3 of 5

SPC-32 92 19 13-Seeding and Sod-60638222.docx

3.2 Preparation

.1 Remove weeds and debris from topsoil already in place.

.2 Examine the site, verify the grades and check that the topsoil has been placed as specified.

.3 The work shall be done in calm weather, during the recommended grass seeding season for the type of seed mixture supplied.

.4 Notify the Consultant prior to the start of the seeding operations.

.5 Cultivate existing topsoil as per Section 32 91 19.13 - Topsoil Placement. Apply additional topsoil as required to obtain minimum required depths of topsoil. Additional topsoil shall be spread evenly and lightly compacted.

.6 Apply fertilizer according to manufacturer’s instructions.

.7 Apply fertilizer with spreader at designated rate and mix thoroughly into the upper portions of topsoil.

.8 Float and level out the finished topsoil surface.

3.3 Mechanical Seeding

.1 Do not seed when prepared topsoil is covered with frost, snow or standing water. Proceed with seeding operations only during favourable weather conditions in accordance with sound horticultural practices.

.2 Slopes flatter than 3 horizontal to 1 vertical: apply seed by mechanical dry spread (Brillion or Cyclone type) at a rate of 24 kg/1,000 m². Apply in two passes, each pass at a rate of 12 kg/1,000 m² at 90 degrees to each other. Lightly roll seeded area.

.3 Hand broadcast seeding is unacceptable under any conditions except for site specific repair work and pre-approved work in naturalization areas.

.4 Spread fertilizer evenly at a rate of 75 kg/1,000 m2.

.5 Thoroughly harrow the site after fertilizing, on ground flatter than 3:1 (H:V).

.6 Sow the seed at a rate specified for the seed type, in two directions, 50% in one direction and remaining 50% of seed at right angles to first seeding pattern.

3.4 Hydroseeding

.1 Mix seed with water, mulch and fertilizer in the following suggested quantities to cover 4,000 m²:

.1 Grass Seed: 80 kgs Fibre Mulch: 640 kgs

.2 Water: 6,400 litres Fertilizer: 140 kgs

.2 Hydro seeding should not be carried out in wind velocities causing seed mix to be blown.

Page 88: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 92 19.13 Parkland County SEEDING AND SOD Issued for Tender Page 4 of 5

SPC-32 92 19 13-Seeding and Sod-60638222.docx

.3 Measure quantities of materials to be fed into the seeder by weight.

.4 Application rates:

.1 Grass seeds 2.0 kg per 100 m² or as specified for the seed type.

.2 Water 160 L/100 m².

.3 Mulch 16 kg/100 m² or sufficient to apply the specified amount of seed and fertilizer per 100 m².

.4 Use 3.5 kg/100 m² fertilizer.

.5 Thoroughly mix seed, fertilizer, mulch, binder (if specified) and water in a slurry and uniformly apply in one operation. Apply seed and fertilizer mixture than cover with an approved mulch.

3.5 Seed Germination, Dry Seed and Hydro Seed Applications

.1 If seed fails to germinate within four growing months, re-cultivate and re-seed until germination takes place.

.2 Approximately six weeks after germination apply supplementary fertilizer 27-14-0, at a rate determined by topsoil analysis or such other fertilizer as may be deemed appropriate by the Consultant.

3.6 Cutting Sod

.1 Cut sod by approved methods in accordance with the recommendations of the Landscape Alberta Nursery Trades Association (LANTA).

.2 Handle sod carefully when loading and installing to prevent tearing or breaking.

3.7 Sodding on Slope 3 Horizontal to 1 Vertical and Flatter

.1 Lay sod evenly in staggered row, with edges and ends butted tightly. Blend edges of sod with existing grass or cultivated areas.

.2 Where sod butt joins surface paving, i.e. manhole, sidewalk or curb, position sod turf crown flush with finished hard surface.

.3 Top dress seams as required with topsoil. Water the sod and upper 100 mm of topsoil with water spray. Do not cause erosion.

.4 Let sod and soil dry out sufficiently to prevent damage, then roll sod with a roller to ensure good bond between sod and soil and to smooth out humps and depressions.

.5 Immediately after rolling, saturate sod and upper 100 mm of soil with fine spray. To prevent grass and soil from drying out, continue adequate watering for 8 to 10 days after laying or until roots are well established.

.6 Four weeks after laying and following initial cutting, apply organic supplementary fertilizer 27-14-0, at a rate determined by topsoil analysis or such other fertilizer as may be determined by the Consultant.

Page 89: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 32 92 19.13 Parkland County SEEDING AND SOD Issued for Tender Page 5 of 5

SPC-32 92 19 13-Seeding and Sod-60638222.docx

3.8 Sodding on Slope 3 Horizontal to 1 Vertical or Steeper

.1 If sodding occurs on any slope steeper than 3 horizontal to 1 vertical, sod may be pegged, 25 per 10 m², with short wooden pegs to prevent sod from slipping. Pegs to be pounded flush with ground.

3.9 Warranty

.1 All grass shall have a two-year warranty period from issuance of the Substantial Performance or until the issuance of the Final Acceptance Certificate.

.2 Areas showing deterioration, bare spots or thin areas shall be re-seeded at the Contractor’s expense during the two-year warranty period.

3.10 Maintenance

.1 Maintenance shall include all measures necessary to establish and maintain seeded areas in an acceptable, vigorous and healthy growing condition for a period of two (minimum) year from the issuance of a Substantial Performance or until the issuance of the Final Acceptance Certificate. Maintenance shall include:

.1 Replacing areas that show root growth failure, deterioration, bare or thin spots or which have been damaged by any means.

.2 Top dressing and rolling to repair ruts or erosion.

.2 The Consultant will review the use of herbicides for weed control. They shall be applied in accordance with the manufacturer’s recommendations by a licensed applicator. Damage resulting from the Contractor’s improper use of herbicides shall be remedied at the Contractor’s expense.

3.11 Final Inspection

.1 Final inspection of seeded or sodded areas will be made prior to the end of the warranty period.

.2 At the time of inspection all the areas shall be alive and in a healthy satisfactory growing condition, free from weeds.

3.12 Clean-Up

.1 Clean roadway, walkway and surrounding areas of soil, seed and other debris resulting from work done under this section at the end of each working day or as reviewed by the Consultant.

END OF SECTION

Page 90: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 33 42 13Parkland County PIPE CULVERTSIssued for Tender Page 1 of 3

GENERAL

Related Sections

ACTION AND INFORMATIONAL SUBMITTALS

Submit manufacturer's instructions, printed product literature and data sheets for pipes and backfill and include product characteristics, performance criteria, physical size, finish and limitations at least 10 days prior to commencing any work.

DELIVERY, STORAGE AND HANDLING

Store materials in accordance with manufacturer's recommendations.

Store and protect pipes from damage.

Replace defective or damaged materials with new.

PRODUCTS

Corrugated Steel Pipe

Page 91: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 33 42 13Parkland County PIPE CULVERTSIssued for Tender Page 2 of 3

Culvert Granular Bedding

Culvert Backfill

EXECUTION

Trenching and Excavation

Culvert Bedding

Page 92: Hamlet of Fallis Drainage Improvement Section 00 01 07

Hamlet of Fallis Drainage Improvement Section 33 42 13Parkland County PIPE CULVERTSIssued for Tender Page 3 of 3

Laying Pipe Culverts

Culvert Backfill

END OF SECTION