Group B4 - R&M

Embed Size (px)

Citation preview

  • 7/31/2019 Group B4 - R&M

    1/54

    By:

    Group B4

    8/16/2012

  • 7/31/2019 Group B4 - R&M

    2/54

    Indias electricity requirement

    How to meet? New Power Plants

    Alternate sources of energy

    Improvement of existing power plants - the most cost effective option

    The importance of R&M was recognized by the Government of India way

    back in 1984 when PHASE-I R&M Programme for 34 thermal powerstations in the country was launched by the Central Electricity Authority as

    a Centrally Sponsored Scheme

    The life extension (LE) programme focuses on plant operation beyond their

    original design life after carrying out specific life assessment studies ofcritical components

  • 7/31/2019 Group B4 - R&M

    3/54

    The equipment subjected to fatigue stresses and creep due to high

    temperatures such as turbine rotor and casings, HP piping etc. are

    designed for a given fatigue life of about 25-30 years of operation

    Many equipment/components might become prematurely weak due tovarious operational stresses like frequent temperature and pressure

    excursions, full load trippings, frequent start and stops etc. and

    accordingly there is need to check the remaining life of these

    components after about 20 years of life or 1,60,000 hours of operation

    A detailed condition assessment along with performance evaluation ofvarious systems / sub-systems is carried out to identify the

    modifications / replacements required to enable plant operation for a

    longer period

    It is a good practice to examine whether a plant requires a viablemodernization intervention so that during the extended life the plant

    operates efficiently and delivers the rated or higher capacity with

    improved heat rate

  • 7/31/2019 Group B4 - R&M

    4/54

    Design deficiencies, manufacturing and generic defects

    The Operation and Maintenance (O&M) deficiencies causing prolonged andrepetitive forced outages

    Inadequate and non timely availability of spare parts especially for

    imported equipment

    The quality of coal being supplied has deteriorated as compared to the

    deigned quality. Besides, the coal has high ash content and contained

    stones, boulders, shale and sand

    There is excessive and inadequately trained manpower for the O&M of the

    plant.

  • 7/31/2019 Group B4 - R&M

    5/54

    Extension of life of generation unit by 10-15 years Improvement of availability of the generation unit

    Sustained achievement of near-design (or better) maximum continuousrating (MCR)

    Improvement in energy efficiency of boiler, turbine, generator and

    auxiliaries, resulting in improvement of unit heat rate Achievement of lower secondary oil consumption through reduction in

    number of tripping, faster start-up and stable combustion at even lowerlevels of load.

    Overcome the problem of aging of critical components (leading to lower

    reliability and shorter residual life) and non-availability of critical spares(due to obsolescence).

    Incorporation of advanced control and instrumentation systems.

    Reduction in emissions and improved environmental control.

    Facilitate adoption of improved operations and maintenance practices.

  • 7/31/2019 Group B4 - R&M

    6/54

    A large capacity of about 5,000 MW was installed in 1970s PLF of these units was as low as 40%

    Stabilisation teams comprising engineers from CEA, BHEL, ILK and the

    concerned power utilities were formed.

    Stabilisation Teams identified the problem areas

    teething problems and failures due to inherent design defects

    modifications were carried out free of cost by the manufacturers on all

    the existing units

    the performance of these units substantially improved and got stabilised 160 units of 200/210 MW comprising about 44% of the total thermal

    installed capacity in the country

  • 7/31/2019 Group B4 - R&M

    7/54

    Engineers from CEA, SEBs/Power Utilities, BHEL, ILK and Keltron

    visited various thermal power stations in the year 1984-85 and

    assisted SEBs in identifying areas of attention and formulation of

    R&M Schemes

    CEA formulated a proposal called PHASE-I R&M Programme as aCentrally Sponsored Scheme for R&M of thermal power stations in

    the country

    Central Loan Assistance (CLA) of Rs.500 crores to provide financial

    assistance to the SEBs

    47% of the total investment was made on environmental pollution

    control measures

    Till the formation of Power Finance Corporation (PFC) in April

    1988, funds were managed by CEA

  • 7/31/2019 Group B4 - R&M

    8/54

  • 7/31/2019 Group B4 - R&M

    9/54

    PHASE-II R&M programme for 44 thermal power stations in the country was

    taken up in the year 1990-91 for completion during the 8th Plan period

    Roving Teams constituted for PHASE-II of the programme visited various thermalpower stations and assisted SEBs in the formulation of R&M schemes

    Power Finance Corporation (PFC) was assigned the responsibility to provide loan

    assistance to the SEBs for R&M works.

  • 7/31/2019 Group B4 - R&M

    10/54

    9th Plan R&M Programme was taken up in 127 units at 29 thermal powerstations

    25 nos. of thermal units which had already completed their designed life

    were planned for LE works based on Residual Life Assessment (RLA)

    studies during the 9th Plan

  • 7/31/2019 Group B4 - R&M

    11/54

    The CEA has identified 106 thermal units in consultation with SEBs/State

    Generation Corporations for LE during the 10th Plan so as to extend their

    economical life by another 15-20 years and to recapture /up-rate their capacities by

    implementing comprehensive R&M schemes based on RLA studies.

    Another 57 units of 14270 MW capacity which are comparatively new also needsome R&M work to sustain/improve their performance.

  • 7/31/2019 Group B4 - R&M

    12/54

    During the 11th Plan, 53 units with a total capacity7,318 MW are programmed to be taken up for LE.Another 76 units with a capacity of 18,965 MW wouldbe taken up for R&M

  • 7/31/2019 Group B4 - R&M

    13/54

    Life extension works have been identified on 72 thermal units of total

    capacity 16532 MW

    30 units (5860 MW) from state sector and 42 units (10672 MW) from central

    sector

    R&M works have been identified on 23 units (4971 MW) during the 12th

    Plan, out of this 11units (4050 MW) are from NTPC, 9 units (291 MW) are

    from NEEPCO and rest are from state sector

  • 7/31/2019 Group B4 - R&M

    14/54

    R&M of TG Replacement of most of the Buckets, Nozzle Plates, Diaphragms, all TG

    Bearings, Labyrinth Seals, ESV Parts, Control Valve parts, Governor parts Turning Gear parts Steam seal, Condenser Tubes R&M of C&I

    Spare Gen. Rotor R&M of Electrical

    Replacement of Static Excitation System , Power & Control cables. Replacement/ Retrofit of HT/LT Switchgear Augmentation of H2 plant

    R&M of BOP Renovation of Cooling Towers Augmentation of Ash Handling New AWRS New Railway Siding inside the plant New Coal Handling Plant R&M of Switchyard

    SomeExamples

  • 7/31/2019 Group B4 - R&M

    15/54

  • 7/31/2019 Group B4 - R&M

    16/54

  • 7/31/2019 Group B4 - R&M

    17/54

    The methodology adopted for life assessment can be categorized into:

    Operational data, standard material based on properties. Methods based on past service examinations or past service tests on

    the actual components.

    The RLA program may be carried out as follows:

    Site study, collection of data and assessment of actual conditions.

    Finalization of action plan for carrying out detailed study and tests.

    Various NDE and Destructive tests on components and equipmentsof the boiler to meet the scope.

    Analysis of results & report.

  • 7/31/2019 Group B4 - R&M

    18/54

    For the operating part : The operating parameters like pressure & temperature Incidents, events of failure & repair statistics Condition of plant facility by number of starts/stops & service

    hours

    For the maintenance part :

    Review of component replacement & repair Review of component geometry

    For the inspection part : Non destructive testing results where the most important are :

    Wall & internal oxide thickness measurement by ultrasonics Metallographic examination by replication Stress measurements by strain gages

    Destructive material testing like failure analysis, isostress creeptesting

    Boiler

  • 7/31/2019 Group B4 - R&M

    19/54

    NDE & DE Tests: Scope of condition assessment of Boiler

    VT Visual Testing

    FOB Fiber Optic Boroscope

    DIM Dimension Measurement

    MT Magnetic particle testingPT Dye penetrant

    UTG Ultrasonic thickness testing

    UFD Ultrasonic Flaw Detection

    IRIS/ UT Internal Rotary InspectionSystem / Submerged UT

    HB Insitu Hardness MeasurementIMG Insitu Metallography

    ICA Insitu Chemical Analysis (PMI)

    OSM Oxide Scale Measurement

  • 7/31/2019 Group B4 - R&M

    20/54

    Following information are required to be collected regardingthe set whose life is to be estimated:

    The drawings of critical components viz. rotors, casings,valves & valve chests, guide blade carriers, steam inlet &

    exhaust connections etc. Materials of various critical components as mentioned

    above & their test certificates including NDT results likedefectograms etc.

    Thermodynamic cycle and strength design data. Stressdistribution in various critical components as envisagedduring design stage.

  • 7/31/2019 Group B4 - R&M

    21/54

    The effectiveness of the calculations made for RLA depends

    upon the accuracy of this data.

    The observations during planned shut downs provide lot of

    information on equipment's condition

    Maintenance Planning Division of the power plant utilizes this

    information for preventive maintenance and replacements

    History cards covering the replacements done during routine

    maintenance / forced outages and planned overhauls are

    reviewed so that present status of the equipment is assessed andequipment degradation trend is formulated.

  • 7/31/2019 Group B4 - R&M

    22/54

    After thorough cleaning of the rotor surface and blading, followingexaminations are carried out :

    Visual examination of the rotor surface, moving blades andshrouds for any abnormality.

    Boroscopic examination of rotor bore

    Magnetic particle examination and/or dye penetration test of therotor with special emphasis on the inlet zone, blades and shrouds.

    Ultrasonic test of accessible areas of the rotor for internal defectsto ascertain major flaws and how far they have grown frominitial stage of manufacture.

    Special attention is given to inlet zone of the rotor. Hardness and Microstructure testings at steam entry and exit

    sides

    Natural Frequency Measurement of free standing blades of LPmotor.

  • 7/31/2019 Group B4 - R&M

    23/54

    All stationary components viz. turbine casings & guideblades, high temperature inlet & exhaust connections, stop& control valves, strainer housings, U, I, & L- seal rings,gland seal bodies etc. are cleaned thoroughly and followingexaminations are carried out :

    Visual examination of the component with specialemphasis to the transition zones and welded areas forcrack, corrosion, erosion or any other defect

    Magnetic particle inspection and/or dye penetration test to

    detect surface and sub-surface cracks Ultrasonic examination for internal defects

    In-situ microstructure examination and hardness test

  • 7/31/2019 Group B4 - R&M

    24/54

    High temperature fasteners

    All the fasteners of high temperature zone will be checked fordetection of cracks by MPI / DPT / UT.

    Sample survey of turbine inner casing joint plane fasteners ofhigh temperature zone is carried out by destructive test onsample studs to determine mechanical properties and impactvalues

    Microstructure examination is also carried out

    Bearings

    All turbine bearings are checked visually for any damage, byDP test for cracks, and by UT for babbit bondage.

  • 7/31/2019 Group B4 - R&M

    25/54

    Remaining life of steam turbine components. Immediate replacement of a component is required or

    it can be replaced after a prescribed period.

    Repair of a particular component

    Change in steam parameters at the inlet, if required. De-rating of steam turbine.

    Alterations in the mode of future operation of the set.

    Alterations in the material of certain components Need for more often inspections.

    Proposals for R & M.

  • 7/31/2019 Group B4 - R&M

    26/54

    Use of improved blade profile which result into reduction inthe aerodynamic flow losses e.g. profile loss, secondary flowloss & tip leakage loss.

    More uniform flow distribution.

    Optimization of flowpath.

    Improvement in shaft sealing system.

    Reduction in pressure drops.

    Reduced friction losses.

    Optimization of inlet & exhaust section geometry of valves &casings.

    Optimization of exhaust loss.

  • 7/31/2019 Group B4 - R&M

    27/54

    The boiler itself may be changed to membrane water wall type. Modified furnace bottom sealing system may be retrofitted to

    avoid air ingress.

    New bottom ash handling system may be retrofitted

    Modified up graded materials have been envisaged to meetbetter reliability in performance and reduction in boiler tubeleakages.

    Better soot blowing system to obtain a clean boiler surface.

    New design coils with fins to minimize flow flue gas velocity

    to reduce erosion failure. Replacement of existing design of economiser coil to provide

    for better expansion to meet high ash content of presently usedIndian coal .

  • 7/31/2019 Group B4 - R&M

    28/54

    Since mills were designed for a better coal and the same

    coal was not available, major modifications may be

    carried out in milling system and combustion control

    equipments to meet the fuel demand and combustion

    requirements.

    New low Nox burner to meet environmental norms.

    Ceramic lines/ pulverized lines to get better life and

    reduce the leakages. New burners to get better life and utilizing latest

    technologies.

  • 7/31/2019 Group B4 - R&M

    29/54

    Since the combustion and quantity of fuel burned haschanged due to deterioration in coal quality, modification

    of flue gas ducts, supports, ash handling system may

    require to be retrofitted and the sizing of the fans may also

    be reworked and modified. Induced draft fans with either hydraulic coupling or with

    VVF drives are envisaged.

    Better secondary air control.

    Retrofitting dry ash evacuation system to achieve 100%

    ash utilization may also be considered.

  • 7/31/2019 Group B4 - R&M

    30/54

    Air preheater

    Retrofitting of latest technology with more advanced design In place of tubular, modular design is now preferred.

    Better flow modelling to achieve uniform velocity.

    Separation of primary air and secondary air to gain the betterheat requirements.

    Rotary air heater with modified sector plates

    Better static seals

    Double lip rotary seal

    More expansion and better sealing to cater for load variation

    Better flow modelling to avoid flow channelling Better expansion joints to avoid excessive ID fan loading

  • 7/31/2019 Group B4 - R&M

    31/54

    To meet the latest environmental norms for Suspended

    Particulate Matter (SPM):

    New modified ESP to be retrofitted

    New fields to be added Advance corona based microprocessor based control

    system to be introduced

    Advanced rectifiers to collect more ash

    Increase the retention time to achieve better efficiency

    Retrofitting new advanced spike electrodes, rotating

    electrodes to achieve the environmental norms

  • 7/31/2019 Group B4 - R&M

    32/54

    Introducing advanced blade design to reduce the surface andexit losses, modified shaft sealing, reduction in bearing lossesand optimization of admission and exhaust sections,improvement in regenerative feed water heaters and controlvalves.

    New turbine internals with modified blades or the retrofittingof LP turbine may be considered.

    There can be an increase of about 1.8 to-3.8 MW increase byretrofitting the LP turbine by utilizing the thermodynamicenergy of buoyancy steam.

    In order to attain the best result in the LP turbine, latest designtapered and forward leaning guide can be used which help toavoid the flow separation in the root area and lead to betteroutput.

  • 7/31/2019 Group B4 - R&M

    33/54

    By redesigning the exhaust, the exit pressure losses can bereduced and better output has been achieved.

    Technologically the cylindrical design blades i.e. with aconstant profile over the entire length of blades areretrofitted with newly developed 3D blades using CFDmodelling.

    This development of blade profiles has led to reduction insecondary losses and increase in power output andefficiency- these blades are known as Tx blades.

    The frequency control regime would require frequent loadvariation capability. The control system (electro-hydrauliccontrol system) has been modified.

    Modification or re-tubing of condenser and introducingonline tube cleaning mechanism are recommended.

  • 7/31/2019 Group B4 - R&M

    34/54

    Generator Normally, rewinding is considered with class F

    insulation to meet new temperature limits

    Control system

    New control valves and actuators retrofitting Incorporation of new DCS system

    Retrofitting the On-line optimization system

    Modification of BOP

    Necessary modifications to ensure systemcompatibility

  • 7/31/2019 Group B4 - R&M

    35/54

    Efficacy of RLA studies . Selection of optimal design options for repair, restoration and

    replacement.

    Packaging concept-Turnkey or Multiple packaging

    Guarantees, penalties, scope growth, cost overrun and delays to watchinterest of all concerned.

    Long delivery schedule for major components of turbine especiallyforgings & castings.

    Addressing of Balance of plant generic issues and proper assessment.

    Shortage of energy (difficulty in getting shutdowns). Long term debt for R&M to keep cost of generation low.

    Establishing techno-economic viability.

    Complexity in complying environmental concerns.

    Regulatory mechanism needs to be conducive for R&M

  • 7/31/2019 Group B4 - R&M

    36/54

    There have been steep breakthroughs in Power planttechnology which have brought considerable enhancement inefficiencies & reliability.

    Therefore, for old plant vintages it may be worthwhile toconsider mega R&M schemes to bring these plants up to the

    contemporary state of the art plants in terms of efficiency,reliability, etc.

    Typically, such mega R&M may include up rating, re-powering, higher process parameters resulting in enhancedefficiency, improved operational safety, reliability, advanced

    diagnostics, etc. Mega R&M typically consists of replacements of major

    equipment / systems of the plant at marginally higher cost &longer shutdowns of the Units are inherent.

  • 7/31/2019 Group B4 - R&M

    37/54

    Renovation of Every plant is a unique challenge and is plant specific/utility specific and solutions are to be customized to suit specific needs.

  • 7/31/2019 Group B4 - R&M

    38/54

    ESCO is an organization engaged in a performance based contract with a clientfirm to implement measures which reduce energy consumption and costs in a

    technically viable manner

    Advantages of ESCO Business Model:

    Reduction of Fossil Fuel consumption

    Potential for generating Carbon Credits which can lead to increased revenue

    Increases Process Industries profitability & also its share value

    Enables the Process Industries to retain long term Employees & attract qualitynew recruits

    Enables sharing of financial risks

  • 7/31/2019 Group B4 - R&M

    39/54

    In 2006, an ESCO association, the Indian Council for Promotion of EnergyEfficiency Business (ICPEEB) was founded.

    Until now, ESCO promotion measures have been implemented throughsupport from international agencies, mainly USAID

    In India there was technical training via USAID

    The overall energy efficiency investment market size under ESCO system ofperformance contract in India has been estimated by the ADB Study project

    team at Rs. 14000 crores and has the potential to save about 54 billion units ofelectricity annually

    On the financial front, low interest financing has been implemented, but manymeasures that should be considered, such as subsidies, tax incentives, and aloan guarantee system, are left .

    Further, along with private sector activities, government organizations alsoneed skill development. Strengthening of policies is also needed.

    Low interest financing programs have been in India by the World Bank, ADB,JBIC, and USAID

  • 7/31/2019 Group B4 - R&M

    40/54

    Bleeding EdgeTechnology

    EMC Contract BOOT/ BOT if

    required

    Long term finance Innovative Lending

    All ESCO services Land and otherinfrastructure

    Capital, if required Long term

    commitment

    Customer ESCO

    Equipment/

    TechnologyPartner

    Financial

    Institutions

  • 7/31/2019 Group B4 - R&M

    41/54

    In order to create a sense of credibility amongst the prospective agencies that are likelyto secure the services of an ESCO as well as the financial institutions, a process ofrating ESCOs was taken up through CRISIL (Credit Rating and Information Services of

    India Ltd.) and ICRA (Investment Information and Credit Rating Agency of IndiaLtd.)

    CRISIL and ICRA present the criteria for grading and a summary of the gradingassigned to the ESCOs and their comparable scores on the parameters for assessment

    A set of criteria was devised to evaluate : Business Risk Factors- essentially track record and market position in ESCO/energy

    management businesses Organizational Risks- ability of the management to gear up for ESCO contracts Financial Risks- financial strength of the company to invest in ESCO projects

    A 100 point scale has been devised based on the above parameters with a 20% weight-age given toBusiness Risks, 40% weight-age to Organizational Risks and 40% to Financial Risks

    The parameters for assessment include:

    Years in the ESCO/energy management business.

    Number and nature of energy audits carried out till date.

    Client Profile

    Number of different industries served.

  • 7/31/2019 Group B4 - R&M

    42/54

    Order book strength as measured by ratio of current order book/previous years turnover.

    Number of energy management projects completed.

    Certification and quality systems. Technology tie-ups.

    Patents held by the company.

    R&D facilities.

    Constitution, ownership structure and parentage.

    Management evaluation and quality of organizational structure, internal control andsystems.

    Employee strength in terms of numbers, qualification and experience.

    Number of certified energy auditors.

    Maximum number of projects handled at a time.

    Annual turnover from the ESCO/energy management business.

    Profit margins of the ESCO business.

    Overall financial strength as reflected by the capital structure and debt servicingindicators like net cash accruals/total debt

    Receivables management.

    Financial flexibility arising from access to cash-flows/profits from other business.`

  • 7/31/2019 Group B4 - R&M

    43/54

    A 100 point scale has been devised based on the above parameterswith a 20% weight-age given to Business Risks, 40% weight-age toOrganizational Risks and 40% to Financial Risks

  • 7/31/2019 Group B4 - R&M

    44/54

  • 7/31/2019 Group B4 - R&M

    45/54

    CRISIL has assigned a CRISIL-BEE Grade 1 to Honeywell Automation IndiaLimited, which indicates Very High ability of the graded energy servicecompany to undertake energy efficiency projects.

  • 7/31/2019 Group B4 - R&M

    46/54

  • 7/31/2019 Group B4 - R&M

    47/54

    Out toBid

    Client develops the project

    Bidding required as required by the government (in case of agovernment funded project)

    RFQ Interested ESCOs submit their corporate resumes, business

    profiles and initial plan

    Short-listing

    3-5 companies are shortlisted by the client

    RFP

    Shortlisted ESCOs are asked to give detailed explanation ofthe project Minimum six weeks of time to compile the report

    Proposals are reviewed by the client ESCO with best possible solution for energy project is

    selected

  • 7/31/2019 Group B4 - R&M

    48/54

    Feasibility Studies and Analysis Engineering Designs

    Providing or Arranging Financing

    Project and Construction Management Purchase and Installation of Equipment

    Training

    Maintenance of Efficiency Measures

    Monitoring of Project Performance

    Administration Services

  • 7/31/2019 Group B4 - R&M

    49/54

    The International Performance Measurement and Verification Protocol (IPMVP) is thestandard M&V guideline for determining actual savings created by an energymanagement program

    IPMVP Option A Retrofit Isolation: Key Parameter Measurement Savings aredetermined by field measurement of the key performance parameter(s) which define theenergy use of the ECMs affected system(s). Parameters not selected for fieldmeasurement are estimated.

    IPMVP Option B Retrofit Isolation: All Parameter Measurement Savings aredetermined by field measurement of the energy use of the ECM-affected system.

    IPMVP Option C Whole Facility Savings are determined by measuring energy use at

    the whole facility or sub-facility level.

    IPMVP Option D Calibrated Simulation Savings are determined through simulationof the energy use of the facility, or of a sub-facility. The simulation model must becalibrated so that it predicts an energy pattern that approximately matches actualmetered data.

  • 7/31/2019 Group B4 - R&M

    50/54

    The savings in energy costs are often used to payback the capital investment of the project over afive- to twenty-year period

    A common way to calculate energy savings is to

    measure the flows of energy associated with theECM, and then to apply spreadsheet calculationsto determine savings.

    Large capital improvement like Up-gradation of Mechanical and ElectricalSystems can be financed through energy savings project

  • 7/31/2019 Group B4 - R&M

    51/54

  • 7/31/2019 Group B4 - R&M

    52/54

    As per the statistics of the Rashtrapati Bhawan, during January-June 2009, 78.95 Lakh

    units of electricity was consumed in the President's Estate. Due to the energy efficient

    measures, the corresponding electricity consumption from Jan-June 2010 has come

    down to 64.03 Lakh units, which is a reduction of 14.92 Lakh units saving more than

    Rs. 90 Lakh

    Honeywell Automation India Limited awarded the project for implementing ECM

    Energy consumption reduction by 23% and Earnings as 60% of the savings

    Energy efficiency has been introduced largely in the areas of efficient lighting and in

    the use of star rated air-conditioning systems

    ISO 14001:2004 certification which sets the standards for Environmental Management

    Systems that are now in place in the 340 acre President's Estate

  • 7/31/2019 Group B4 - R&M

    53/54

    http://www.fepc.or.jp/ http://www.cea.nic.in/reports/planning/report_85_pul_coal.p

    df

    http://www.cea.nic.in/thermal_rnm.html

    http://www.fujielectric.com/company/tech/pdf/r51-3/r51-3.pdf

    ACCREDITED ENERGY SERVICE COMPANIES byBureau of Energy Efficiency, Ministry Of Power

    Current state of ESCO activities in Asia: ESCO industrydevelopment programs and future tasks in Asian countries byChiharu Murakoshi and Hidetoshi Nakagami, JyukankyoResearch Institute, Japan

  • 7/31/2019 Group B4 - R&M

    54/54