Grid-connect PV Design Project

Embed Size (px)

Citation preview

  • 8/19/2019 Grid-connect PV Design Project

    1/12

    SYDNEY 5 KW PV SYSTEM

    Q1. COMPONENT SELECTION

    a. 

    Product List

    b.  i. Reasons for Choice

    Panels

     

    Poly-crystalline technology is most researched type in industry, and if roof space is not short (as in

    this instance), then it proves more cost-effective than mono.

      Trina is rated Tier-1 manufacturer, globally ranked no. 1 panel supplier. This should assure the client

    of yield performance (provided she is ready to pay premium price).

      250 W is exact factor of 5 kW, resulting in a whole number of 20 (i.e. 5000 / 250 = 20). Using another

    module wattage (e.g. 265 W), would not provide a whole number and some power would be lost as

    we round down on quantity of modules.

      Panel dimensions of 1650 mm x 992 mm mean that 20 such panels easily fit into the shade-free zone

    (see layout diagram provided later).

    Inverter

     

    Fronius is a well-reputed Austrian manufacturer, and this should help the client get some peace of

    mind on long-term reliability/warranty of the product.

      It is assumed that client has 1-phase grid supply and she does not require a system larger than 5 kW,

    so a single-phase inverter is chosen.

      The chosen inverter is single-MPPT, which is fine in this case because all panels on the client’s roof

    will have the same direction and tilt.

      5 kW inverter rating will match the quantity of panels installed (Fronius IG 60 has max output 5000

    WAC and is available in Australia). There is no compulsion to undersize (e.g. 4 kW), as it will not offer

    noticeable price savings, so clipping losses and inverter over-heating are best avoided in the long

    term.

     

    The inverter has HF transformer, which provides galvanic isolation between DC and AC sides, as well

    as keeping the device efficient, light-weight. Drawback is high-frequency noise.

    Mounting

      360Rack is Australian-made, so the company’s local presence would mean lower costs and quicker

    stock availability, as well as any follow-up warranty claims.

      L-foot bracket mounts are suitable for tiled roof and can sit flush.

      Module thickness range of 31 –50 mm means the chosen Trina panels are compatible (35 mm).

      Item design incorporates latest Australian standards (AS-5033, AS-1170).

      Anodized stainless steel material and galvanized screws render this product electrochemically similar

    to aluminium frames of solar modules.

    Item Brand Model Qty Type

    Panel Trina TSM-PC05A (250W) 20 Polycrystalline

    Inverter Fronius IG 60 HV (5 kW) 1 Separated

    Mounting 360Rack Tile-roof kit as needed Mid/end clamps, earth plates, rails,

    tile hooks

  • 8/19/2019 Grid-connect PV Design Project

    2/12

     

    b.  ii. Inverter-Array Matching

    Site Data

    Panels Data (Trina Solar Honey 250 W polycrystalline TSM-250-PC05A) 

    Property at STC Symbol Value

    Max power PMP  250 W

    Open-circuit voltage V OC   34.8 VMax power voltage V MP  30.3 V

    Short-circuit current ISC   8.79 A

    Max power current IMP  8.27 A

    Max fuse rating IREV   15 A

    Temperature coefficient of power ϒ MP  -0.41 % / K

    Temperature coefficient of voltage αOC  -0.32 % / K

    Temperature coefficient of current βSC  0.053 % / K

    NOTE: Temperature coefficient of power is given in % above, and so can be approximated straight away as

    temperature coefficient for VMP without further conversion.

    Inverter Data (Fronius 5 kW IG 60 HV) 

    Property Symbol Value

    Min start-up voltage V in-min  170 V

    Min MPP voltage V MPP-min  150 V

    Max MPP voltage V MPP-max   400 V

    No. of MPPT inputs / DC inputs - 1 / 5

    Max DC input current Iin-max   35.8 A

    Max DC input power Pin-DC   5,380 W

    Max AC output current Iout-max   21.7 A

    Voltage Matching 

    Step 1: Minimum string length by VMP

    Sub-step Calculation Result

     Adjust module V MP to max temperature V MP x {1 – [ϒ MP x (T max  –  T STC )]} 30.3 x {1 – [0.0041 x (70 – 25)]} = 24.71 V

    Factor in voltage drop V MP-75oC  x (1 – VD) 24.71 x (1 – 0.03) = 23.96 V

     Add inverter min voltage margin V in-min x 1.1 170 x 1.1 = 187 V

    Round up after division 187 / 23.96 = 7.80 Min 8 modules per string

    Parameter Symbol Value

    STC temperature T STC   25 oC

    Voltage drop (max assumed for sizing) VD 3 %Inverter min voltage safety margin - 1.10

    Inverter max voltage safety margin - 0.95

    Min cell temperature T min  0 oC

    Max cell temperature T max   70 oC

  • 8/19/2019 Grid-connect PV Design Project

    3/12

     

    Step 2: Maximum string length by VMP

    NOTE: The method used here will be by VMP and not VOC because there is no compulsion to have longer strings

    (i.e. urban regulations in NSW prohibit 1-phase supply from having a larger solar array than 5 kW and client is

    not pressed for roof space). Thus, and it would be advantageous to size shorter strings that always operate in

    the MPP range. Using MPPmax  of inverter also means the calculation will automatically be below V in-max  of

    inverter. 

    Sub-step Calculation Result

     Adjust module V MP to min temperature V MP x {1 + [ϒ MP x (T STC  –  T min)]} 30.3 x {1 + [0.0041 x (25 – 0)]} = 33.41 V

    Reduce inverter max voltage margin V MPP-max  x 0.95 400 x 0.95 = 380 V

    Round down after division 380 / 33.41 = 11.37 Max 11 modules per string

    Current Matching 

    Step 3: Maximum no. of string inputs to inverter 

    Sub-step Calculation Result

     Adjust module ISC  to max temperature ISC  x {1 + [βSC x (T max  –  T STC )]} 8.79 x {1 + [0.00053 x (70 – 25)]} = 8.99 A

    Compare to Iin-max  and round down 35.8 / 8.99 = 3.98 3 string inputs

    Power Matching 

    Step 4: Total no. of modules 

    Sub-step Calculation Result

    Compare max input to module W (STC) Pin-DC  / PMP  5380 / 250 = 21.52

    Limitation by regulation Nominal power max 5 kW 20 modules in system

     Array Configuration 

    Step 5: Module combinations

      No. of modules per string = 8 – 11

     

    No. of modules in array = 20  Max no. of strings = 3; for simple symmetry, I shall use 2 strings (as 20 divides evenly into 2 not 3)

    From above, various configurations can be attempted as below.

    String 1 String 2 Total modules Satisfy V, I, P matching?

    8 12 20 No

    9 11 20 Yes

    10 10 20 Yes

    While any of the last 2 combinations is fine, for simplicity and balance, a 10 + 10 combination would be preferred.

     Array Classification 

    Step 6: Maximum system voltage 

    10 modules per string means maximum PV system voltage (under cold conditions):

    V max-array  = 10 x V OC  x {1 + [αOC  x (T STC  –  T min)]} = 10 x 34.8 x {1 + [0.0032 x (25  – 0)]} = 375.84 = 376 V

    This is less than 600 V, classed as LV by Clause 3.1 of AS-5033: 2014 for unrestricted domestic installations.

    c. 

    System Expansion 

    Not applicable to Sydney home scenario.

  • 8/19/2019 Grid-connect PV Design Project

    4/12

    Q2. DESIGN DETAILS 

    a.  Roof vs Ground Mounting 

    Not applicable to Sydney home scenario.

    b.  BOS Equipment Specifications 

    Item Discussion Standards and Calculations Sizing Result

    IP rating All enclosures should ideally be rated to IP-66

    as recommended by CEC, even though AS-

    5033 requires only IP-55. All enclosures,

    conduits and inverter should be UV-resistant. 

    CEC installer guidelines

    AS-5033 Clause 4.3.3.1 

    IP-66 (proof to dust and powerful water jets)

    rating for DC isolator/combiner boxes (at string-

    ends) and inverter

    String

    protection

    Each string fed into separate DC input of

    inverter but internal isolation not specified, so

    we presume that inputs share single-MPPT in

    parallel.

    By AS-5033 Clause 3.3.4, not required because

    (n – 1) x ISC  = (2 – 1) x 8.79 = 8.79 < IREVERSE  = 15 A Not required

    String

    disconnection

    Supplied by module manufacturer, marked

    “no-load break” and only accessible with tool .

    AS-5033 Clause 4.4.1.3   Plug-and-socket, non-load-breaking

     1 per panel

     Voltage rating ≥ string maximum (376 V)

     Current rating ≥ CCC string cable (see below)

    String cable No downstream protection, inverter back-

    feed current 0, so string cable to carry short-

    circuit from other strings (total 2 strings in

    system).

    To avoid inductive loops, two cores of DC (-ve

    & +ve) will run together in series; modules areplaced in row along entire roof length. VD of

    3% is permissible along each string (fed

    directly to inverter, no separate array cable).

    AS-5033 Clause 4.3.6

    CCC ≥ In + (1.25 x ISC-mod ) x (n – 1)

    = 0 + (1.25 x 8.79) x (2 – 1) = 10.99 A

    Longest DC core length (worst case scenario) to

    inverter near switchboard is 18 m (roof) + 6 m(height) + 8 m (house) = 32 m, so

    CSA ≥ (2 x LDC  x IMP x ρCu) / (VD x V MP-string)

    = (2 x 32 x 8.27 x 0.0183) / (0.03 x 10 x 30.3)

    = 1.07 mm2 

     CCC ≥ 11 A & CSA ≥ 1.07 mm2 so 1.5 mm2 cable

    is sufficient (can carry 21 A as seen from

    standard cable tables)

     Voltage rating ≥ string maximum (376 V) 

     

    Stranded copper cable

     Inductive loops to be minimized by running both

    cores (-ve & +ve) together PVF-1 (UV-rated) compliant or housed in UV-

    resistant conduit through external run to

    inverter

    Sub/array

    protection

    Each string fed into inverter directly, so no

    sub-array exists; also no external energy

    source (battery bank or generator).

    AS-5033 Clause 3.3.5.3   Sub-array/array does not exist as such because

    each string is fed into inverter directly

     Additional protections at sub-array/array level

    are not applicable

  • 8/19/2019 Grid-connect PV Design Project

    5/12

    DC

    disconnection

    switches or

    isolators

    No line-of-sight from PCE to array and

    separation > 3 m, so required on each end of

    both strings (as there is no common array

    cable). Labeled for simultaneous operation to

    fully isolate array. Functional earthing not

    specified by panel manufacturer, and inverter

    is separated.

    AS-5033 Clause 4.4.1.3

    AS-5033 Clause 4.4.1.4 

    AS-5033 Clause 4.4.1.5

    AS-5033 Appendix B

    No overcurrent protection, so switch rating

    1.25 x ISC-mod  = 1.25 x 8.79 = 11 A

    Equipotential earthing, so per pole rating

    0.5 x V max-array  = 0.5 x 376 = 188 V

     2-pole DC isolator in 1-pole configuration

     2 isolators per string (both ends, so total 4)

     Readily available, load-breaking

     Voltage rating ≥ 188 V per pole  e.g. 200 V

     Current rating ≥ 11 A per pole e.g. 15 A

    Combiner 2 string cables (2-core each) kept separate

    from each other up to inverter, but joined to

    4-core DC cable at combiner box for ease ofinstallation.

    Rating of 4-core DC cable will be same as string

    cable specified above Combiner box to house DC switch of each string

     2 x 2-core string cables joined to 1 x 4-core

    common cable up to inverter

    AC cable Inverter installed next to switchboard

    (southern side, shaded from direct sun) so

    connecting cable length taken as 3 m. Max 1%

    VR. Power factor is assumed at 0.95.

    AS-4777.1

    CEC installer guidelines

    CCC ≥ max inverter output current Iout-max = 21.7 A

    CSA ≥ (2 x L AC x Iout-max  x ρCu x cosφ/ (VR x VAC)

    = (2 x 3 x 21.7 x 0.0183 x 0.95) / (0.01 x 230)

    = 0.98 mm2 

     

    Stranded copper cable

     PVF-1 compliant or laid in UV-resistant conduit

     Voltage rating ≥ mains supply 230 Vrms so 400 V

     

    CCC ≥ 21.7 A & CSA ≥ 0.98 mm2 means 2.5 mm2,

    2-core cable CSA is sufficient (can carry 28 A as

    seen from standard cable tables)

    AC CB /

    disconnector

    Inverter in line of sight, so AC breaker to be

    installed inside switchboard.

    Rating > max inverter Iout-max = 21.7 A

    Rating < CCC of AC cable = 28 A

    Voltage rating > 230 V

     

    Load-breaking circuit breaker

     Lockable in off position

     Rated 25 A, 400 V

    c. 

    Earthing Requirements   Module manufacturer does not require functional earthing, and inverter is separated so per pole voltage rating of DC disconnection switch (isolator) is 0.5

    of array maximum voltage.

      Only protective earthing is required. This is achieved by equipotential bonding between exposed conductive parts of array (e.g. PV frames, mounting rails)

    using piercing washers (WEEB) to connect the system to earthing cable.

      It is advisable that lightning protection rod be incorporated into earthing system. According to AS-3000, minimum cable size for earthing would then be 16

    mm2. AS-5033 Clause 3.4.3 also mandates earth fault alarm to be visual or audible. This is generally implemented by inverter.

  • 8/19/2019 Grid-connect PV Design Project

    6/12

    d.  Site Plan 

    Site shading zone was drawn on graph paper (to scale), and scan is attached below.

    Steps to calculate shading given below:

      Effect of Tree-A only is significant (remaining 2 trees do not affect roof)

      Tree 10 m high, but roof 6 m high (at lowest edge) so 10  – 6 = 4 m (i.e. height of obstruction)

      For each hour of day given in shade table, hypotenuse is constructed to scale on graph paper from

    given perpendiculars for 1 m tall object (e.g. E & S), and multiplying length by 4

      For example, Tree-A is west of roof, so its shadow would be longest when sun is low in western sky

    (late afternoon). At 4 pm, shade table for 1 m object in Sydney gives 5 E, 3.7 S. Thus shadow angle is

    tan-1 (3.7/5) = 36.5o south of east and shadow length over roof = 4 x √ (52 + 3.72) = 24.88 m

    Site layout was sketched in MS Visio software, and is pasted below. Module layout rules are:

      Edge zone 0.2 m from all sides, inter-module spacing 0.02 m

      Roof length 18 m, subtract edge zones 18 – (2 x 0.2) = 17.6

      Module width 0.992 m, add spacing 0.992 + 0.02 = 1.012 m

      Max no. of modules in bottom row = 17.6 / 1.012 = 17.39 (subject to shading)

      Shading from trees (8 am to 4 pm) checked by shading table using graph paper. Largest shading zone

    experienced from Tree-A late afternoon (4 pm), making lower diagonal half of roof unusable

      20 modules including 0.02 inter-spacing (1.67 m x 1.012 m) can be fit in shade-free region in 2 rows

    of 14 + 6; however, electrically strings are wired as 10 + 10 as sized previously

  • 8/19/2019 Grid-connect PV Design Project

    7/12

     

    Site Layout: TOP VIEW  

    Combiner box

    Inverter

    AC CB inside switch board

    Earth pit

    Lightning rod

    Earthing cable 1-core, 16 mm2, connects

    PV array & lightning rod to s take

    String DC isolator

    String A has 10 modules

    (outlined in black)

    String B has 10 modules

    (outlined in blue)

    Module junction box

    (back of each panel)

    DC string cable 2-core, 1.5 mm2

    DC string cable 4-core, 1.5 mm2 (strings still

    separate but common cable for ease of install)

    AC cable 2-core, 2.5 mm2

    Shade zone of trees

    (8 am to 4 pm)

     

    C

    Azimuth 20o 

    E of N

    Intermodular spacing

    0.02 m

  • 8/19/2019 Grid-connect PV Design Project

    8/12

     

    Site Layout: SIDE VIEW  

    e.  Electrical Schematic  

    System schematic was drawn in MS Visio, and is given below. Note that as discussed previously by AS-5033

    standards, DC string isolators are provided on each side (inverter and rooftop) as inter-distance > 3 m.

    However, for inverter output, only one AC CB is provided in main-switchboard because inverter is within

    line-of-sight (installed next to it).

    Lightning rod

    Earth pit Earth cable 1-core, 16 mm2,

    connects PV array, enclosures

    and lightning rod to ground stake

    AC CB inside

    switch board

    Inverter

    AC cable, 2-core,

    2.5 mm2 

    DC string cable 4-core, 1.5 mm2 

    (strings still separate but common

    cable for ease of install)

    String DC isolator

    (1 per string)

    PV module

    PV junction box

    (1 per module)

    Mounting rails ( > 5 cm

    gap of module from roof)

     

    m

    20o

    2

    1 2

    1  10

     10

    A

    N

    Mainsfuse

    Netmeter

    MEN

    House loads

    Mainsswitch

    Solar CB25 A, 400 V

    Main switchboard Inverter Fronius IG 60 HV (5 kWac)

    DC isolators, 2-pole15 A, 200 V

     Array Trina TSM-PC05A (250 Wdc x 20)

    (inverterside)

    (rooftopside)

    DC isolators, 2-pole15 A, 200 V

    10 PV modulesx 2 strings

    AC cable, 2-core,2.5 mm2, 3 m

    DC cable, 4-core,1.5 mm2, 14 m

    String cable, 2-core,1.5 mm2, 18 m

    MPPT 1

    MPPT 2

    Equipotential earthing 

    rid

  • 8/19/2019 Grid-connect PV Design Project

    9/12

    Q3. SYSTEM PERFORMANCE 

    a.  Operating Assumptions 

    i.  Shadows have been sketched to scale from 8 am to 4 pm, and panels placed in shade-free area. In reality

    however, sunlight is present outside of these hours as well, especially during summer and so some

    degree of shading in weak light hours can occur. In addition, shading table provides an average, whereas

    shadows are longer in winter than summer. Over time, trees also tend to grow. Due to these reasons,

    1% shading loss is still assumed despite placing panels in shade-free zone.

    ii.  It is assumed that system owner is conscious of metropolitan pollution and will regularly wash panels,

    so dirt factor of 3% is assumed (as for sites with frequent rain).

    iii.  Panel-bearing roof of house is at azimuth of 20o east of north and 20o tilt.

    iv.  Average ambient at site is 23oC.

    b. 

    Loss Calculations 

    Type Discussion / Calculation Result

    SYSTEM LOSSES

    Tolerance Panel specs state manufacturing tolerance 0/+3 so no de-rating in worst case  f MM = 100%

    Dirt Modules are tilted, and owner washes them regularly as discussed in operating

    assumptions above

     f dirt  = 97%

    Inverter Max efficiency rating specified by manufacturer is 94.3% ηinv  = 94.3% 

    Temperature Average ambient at site is 23oC; panel specifications state NOCT = 44oC (when

    ambient is 20oC),

    so average cell temperature is 44 + (23 – 20) = 47oC

    and de-rating is (T avg –  T STC  ) x ϒ MP = (47 – 25) x 0.41% = 9.02%

    Note:  Practical factors such as metal roof thermal properties, panel-roof gap

    due to mounting etc. can mean temperature rise is even higher

     f temp = 91% 

    Volt Drop On DC side, cable has been sized slightly better than that required for 3%

    voltage drop. So a maximum of 3% is taken for average operating conditions.

    Similar argument is true for AC side, where sizing was done for max 1% drop.

    Total cable drop factor for power derating is 0.97 x 0.99 = 0.9603

    Note: Actual drop calculations can also be performed on chosen sizes and

    lengths using VD coefficient from cable tables, and adjusting VMP  for average

    cell temperature.

     f VD = 96% 

    IRRADIATION LOSSES

    Shading Shade-free zone but some factor considered as discussed in operating

    assumptions above

    Hshade = 99%

    Tilt &

    Orientation

    Site azimuth 20o east of north with 20o tilt, whereas optimum orientation is true

    north (0o) with latitude tilt (~30o). Horizontal irradiation data of design task

    adjusted by tilt/orientation factors of CEC tables for Sydney (see below).

    Annual irradiation comparison is:

    Site PSH / Optimum PSH = 1870.8 / 1936.5 = 96.6 %

    Htilt  = 97% 

  • 8/19/2019 Grid-connect PV Design Project

    10/12

     

    Total system yield is now calculated as follows:

    1.  Array rating 5 kW

    2.  Annual irradiation = Site tilted global irradiation x Hshade = 1870.8 x 99% = 1852.1 kWh/m2/year

    3.  System efficiency = f MM x f dirt   x ηinv  x f temp x f VD = 100% x 97% x 94.3% x 91% x 96% = 79.9%

    4.  Expected average yearly yield = 5 x 1852.1 x 79.9% = 7,399 kWh/year

    c.  GHG Avoidance 

    In NSW, each kWh of PV energy offsets 1.06 kgCO2 according to design data given. So GHG emissions

    avoided per year due to this system are:

    7,399 x 1.06 = 7,842.9 kgCO2/year = 7.84 ton-CO2/year

    Q4. ITEMS AND CONCERNS LIST

    a.  Components List

    Equipment

      Inverter: Fronius IG HV 60

      Panels: Trina TSM-PC05A (250 W) x 20

      Mounting: 360Rack sub-items

    i.  Anodized aluminium rails (2080 mm per 4 panels) with integrated cable clamps and

    earthing lugs

    ii.  End-clamps (2 per long-edge of last panel on either side of strings) with T-bolts and nuts

    iii.  Mid-clamps with earthing washers (2 per long-edge between panels)

    iv.  Rail joiners with earthing washers

    v.  Tile mount brackets (hooks) and galvanized 17-10x40 roof screws, fixed on to truss, batten

    or rafter under colorbond roof

    GHI

    kWh/m2 /d  

    Days GHI  

    kWh/m2 /mo 

    Site factor

    N 20o , tilt 20o 

    Site TGI  

    kWh/m2 /mo 

    Optimal

    N 0o , tilt 30o 

    Optimal Irr. 

    kWh/m2 /mo 

    Formula   A B A x B C A x B x C D A x B x D

     Jan 6.5 31 201.5 100% 201.5 96% 193.4

    Feb 5.7 28 159.6 105% 167.6 104% 166.0

    Mar 4.7 31 145.7 113% 164.6 117% 170.5

     Apr 3.6 30 108.0 124% 133.9 134% 144.7May 2.7 31 83.7 137% 114.7 155% 129.7

     Jun 2.4 30 72.0 142% 102.2 163% 117.4

     Jul 2.6 31 80.6 141% 113.6 160% 129.0

     Aug 3.4 31 105.4 130% 137.0 143% 150.7

    Sep 4.6 30 138.0 117% 161.5 124% 171.1

    Oct 5.6 31 173.6 107% 185.8 108% 187.5

    Nov 6.2 30 186.0 101% 187.9 99% 184.1

    Dec 6.6 31 204.6 98% 200.5 94% 192.3

     Annual Total   1658.7 1870.8 1936.5

  • 8/19/2019 Grid-connect PV Design Project

    11/12

      Cabling

    i.  1.5 mm2  2-core, DC-type for string connection to DC isolator (normally provided by

    manufacturer between modules)

    ii.  1.5 mm2 4-core, DC-type for joining with 2 panel strings while keeping them independent

    iii.  2.5 mm2 2-core, AC-type to connect inverter with switchboard

    iv.  16 mm2 1-core, earthing between lightning rod, panel assembly and earth stake

      Switchgear

    i. 

    DC isolators x 4 (15 A, 200 V, 2-pole, load-breaking) one on either end of each of DC string

    cables (i.e. on roof and near inverter)

    ii.  AC isolator (25 A, 400 V, load-breaking)

    Tools

      Impact driver with 10 mm magnetic hex bit, to tighten roofing screws

      13 mm ratchet spanner, to tighten mount M8 lock nuts (min. torque 15 Nm)

      Cordless angle grinder with ceramic disc to cut groove into tile for bracket to sit flush

      Measuring tape and chalk, for initial layout markings

      Bubble meter (to check horizontal level of mounting)

     

    Winch, to assist in lifting panels to roof

      Safety harness tied to rope and anchor on roof

      Ladder

      Cordon to secure area on ground against passer-bys

     Accessories 

      Signage:

    i.  “Solar DC Cables” for cable conduits 

    ii.  “Hazardous DC Voltage” for string isolator/combiner box 

    iii.  “PV Array DC Isolator” for string DC disconnection switch 

    iv. 

    “Shutdown Procedure” next to inverter 

    v.  “Warning Dual Supply” inside switchboard, indicating solar and grid sources

    vi.  “Solar Array on Roof” next to switchboard 

      Mounting plates and brackets for inverter

      Cable ties and tags

      Conduits: UV-rated (PVF-1) for carrying DC cable from roof array to inverter, and from inverter to

    switchboard

      Dektite rubber flashing to seal vertical penetrations made in roof for DC cable conduit if required,

    for pathway to inverter

      Lightning rod

    b.  Safety Concerns

      Risk assessment form must be completed on arrival at worksite

      Panels can act as wind sail and push person off balance

      Panel edge can cause bruise or cut if handled carelessly

      Harness to be used on roof for safety at height, and area below to be cordoned off to protect

    passerbys against falling objects

      Safety gear to be worn includes helmet, gloves, rubber shoes, sunglasses for protection against

    bright light, mechanical injury or DC shock

     

    Installation not to be undertaken in rainy or windy conditions, to prevent injury from instability orDC shock

      Hat and sunscreen to be worn for protection against dehydration, with regular water and rest

    breaks taken

  • 8/19/2019 Grid-connect PV Design Project

    12/12

     

    Q5. APPROXIMATE COSTING

    The following costing is approximate, based on prevalent market conditions (as of March, 2016). Currency used in

    Australian Dollar, and values are assumed to include GST.

    Item Discussion ResultPanels Trina are at higher end of market, and would cost ~ $ 0.89 /W

    So 5,000 W x 0.97 = $ 4,450

    $ 4,450

    Inverter Fronius 5 kW inverter would be approx. $ 2,000 $ 2,000

    Balance of System Cabling, mounting kit, breakers, isolators, signage is expected to

    cost around $ 800

    $ 800

    Installation Installers would charge around $ 80 per panel as a metric for

    total system cost

    So 20 panels x $ 80 = $ 1,600

    $ 1,600

    Height Access Difficulty fee charged by installers on double-storey houses $ 150

    Net Metering To be done by L2 electrician by purchase of net meter from grid

    owner; market rate including service charges is ~ $ 500

    $ 500

    Total $ 9,500

    Note that this is the upfront system price BEFORE application of STC point-of-sale discounts (also known as

    PV rebates).

    Q6. ECONOMIC BENEFITS

    a. 

    RECOne STC (small-scale technology certificate) is issued for each MWh of clean energy that a system shall

    produce over 15 years, based on the average performance determined per kW of installed capacity, and

    the available Peak Sun Hours (PSH) in a given area. For Ms Architect, post-code NSW 2000 is used (Sydney).

    It can be seen from REC Registry website, that this post-code falls in sunlight Zone 3, and awards 103 STC

    to 5 kW PV system.

    Spot market price (March 2016) of STC is very high, at $ 39.85 (indicating there are more buyers than sellers,

    hence a deficit of new systems being installed).

    Thus Ms Architect would receive rebates of $ 39.85 x 103 = $ 4,104 on her upfront cost.

    b. 

    Grid Savings

      Energy yield (from Question 3) = 7,399 kWh/year 

      Self-consumption savings = 70% x 7,399 kWh/year x $ 0.22/kWh = $ 1,139 

      Export income (from feed-in) = 30% x 7,399 kWh/year x $ 0.06/kWh = $ 133  

      Expected yearly benefit $ 1,139 + $ 133 = $ 1,272