Grasim Greenfield and Capex Monitoring

  • Upload
    gunju1

  • View
    222

  • Download
    0

Embed Size (px)

Citation preview

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    1/40

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    2/40

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    3/40

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    4/40

    Fact Files Of Grasim

    GrasimIncorporated on 25Aug 1947

    Textilemanufacturingsuccessfullydiversified intoVSF, cementand chemicals

    Worldlargest

    producer of VSF

    9th largest producer of Cement

    2ndlargest

    producer of causticsoda inIndia

    4th

    largest producer of insulatorsin theworld

    GrasimandGravierarange of fabricssignifythe'power of fashion

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    5/40

    Grasim Cement

    Its first cement plant at Jawad in Madhya Pradesh in mid 1980.Span India, with 11 composite plants, 11 split grinding units, five

    bulk terminals and 69 ready-mix concrete plants.Grasim is also the largest producer of white cement in India, with acapacity of 560,000 tpa as on 30 June 2009. Branded as BirlaWhite.Grasim is a voluntary member of the Cement Sustainability Initiative(CSI), which is the apex for the cement industry globally to establish

    common measures, share best practices and exchange data relating toenvironmental impact.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    6/40

    Project Classification

    GreenFieldproject

    (Add Capacityto Scratch One.)

    ProjectRoute

    BrownFieldProject

    (Add Capacityto Existing.)

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    7/40

    GreenField Project

    The setting up of greenfieldcement projects means startingfrom scratch at a new location /

    site with the land andinfrastructure as available. Thegreenfield plant can be set up asintegrated plant or with splitlocation where clinker can bemanufactured at one location &

    cement grinding and/or packingcan be done at another location.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    8/40

    Influencing FactorsQ uantitative factors

    1. Gestation period2. Investment cost3. Profitability and Financial Viability

    Q ualitative factors

    4. External Environment

    5. Technology6. Design and Engineering7. Project Management

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    9/40

    Quantitative Factors

    1 .Gestation Period

    Site identificationRaw material studiesEIA/EMP studiesPlant technical concept & project reportFinancial closure

    Project implementationStabilization

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    10/40

    Quantitative Factors

    Project Estimated Amount(per ton)

    Specific investment cost for Greenfield project

    Rs. 4800-5100

    Specific investment cost for brownfield project (Up gradation) Rs. 3950-4350

    Specific investment cost for brownfield project (New line)

    Rs. 4500-4800

    2.Investment Cost

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    11/40

    Quantitative Factors

    3 .Profitibility &Financially Viable

    For similar capacity addition the brownfield project shall generallyhave better financial viability due

    to lower gestation period andlower investment levels

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    12/40

    Qualitative Factors

    4 .External Environment

    Land and Infrastructure Fresh acquisition and development isrequired.Limestone new mineable deposit to be identified, investigated andacquiredFuel linkages to be established afreshEnvironment clearance large lead time for data collection

    Market entry barriersFinancing More difficult and rigid terms & conditions.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    13/40

    Qualitative Factors

    5 .Technology

    Raw material availability augmentationComputer Aided Deposit Evaluation (CADE)Quarry Scheduling and Optimization ( QSO)GrindingPyroprocessingImproved equipment

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    14/40

    Qualitative Factors

    6 .Design & Engineering

    LayoutInfrastructure limitationsSafety considerationsEnvironmental considerationsTemptations to have more and more flexibilityEnergy optimizationAgeing of civil structuresAgeing of old equipment proposed to be retained in the upgraded plantRequirements for future growth

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    15/40

    Qualitative Factors

    7 .Project Management

    The project implementation time hasshrunk and the project overruns aresuicidal. The lenders are increasinglyinsisting on detailed planning, efficientmonitoring and control mechanism(time/cost) to avoid/ minimizeoverruns.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    16/40

    Case Objective & Details (Demo)For up gradation of kiln from 10,000 tpd clinker to 12,000 tpd clinker

    Details

    Description Present Proposed

    Kiln Capacity 10,000 tpd clinker 12,000 tpd clinker

    Kiln Speed 2.0 rpm(maximum) 4.0 rpm

    Kiln Slope 3.50% 3.50%

    Kiln Size 7.0 m dia. x 110m length 7.0 m dia. x 110 m length

    Preheater Single string, 4 stagecyclone preheater

    Existing string with 4 stage cyclones askiln string and a new string with 4 stage

    preheater and In Line Calciner (ILC)

    GCT/ECP One GCT and two parallelESPs

    A new GCT/ ESP is required for dedusting the new PH fan.The GCT is

    proposed to be before the new PH fan andit will discharge to the new ESP, where anew ESP fan will vent out the clean air tothe atmosphere through an independentchimney.Its existing GCT & ESP willcontinue to be used.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    17/40

    Case Details Cont..

    Description Present Proposed

    Specific heatconsumption

    880 Kcal/ kg clinker 750 Kcal/kg clinker

    Filling in kiln 9.64% 14.83%

    Fuel firing Kiln : 100% Kiln : 45%

    Precalciner : 55%

    Burner for fuel oil firing

    Kiln : FLS Kiln : FLS Duoflex burner for oil or gas.Precalciner: A new burner of FLS design

    Clinker Cooler Planetary coolers New generation, highefficiency FLS SFcooler with more than73% heat recuperationefficiency.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    18/40

    Case Details Cont..

    Other EquipmentDescription Present Prposed

    Crusher 6000 tph A new crusher of capacity 9000 tph to meet therequirement of this kiln.

    Raw mill 2000 tph 3600 tphThe following modifications:

    Replacement of the existing two nos.conventional dynamic separator by a suitablydesigned new generation high efficiencydynamic separator.

    Installing a closed circuit roller press in frontof raw mill.

    Cement mill 1160 tph 2660 tphconsidering about 20% margin, it isrecommended to install a new cement mill of cap around 1500 tph

    Power consumption - 100 kWh/t cement

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    19/40

    ResultA debt equity ratio of 70:30 has been considered for projectfinancing.Kiln run days has been considered as 330 days per annum.The plant operating efficiency are considered as follows:

    1st year of operation 9 0%

    2nd year of operation onwards 100%

    The Financial indicators are worked out as follows:IRR on investment 2 0 .82 %

    IRR on equity 31 .94%

    Payback period 4 years 2 months

    Based on the estimates, the total cost for the proposed project works

    out to Rs.657

    2 million for kiln upgradation

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    20/40

    Findings

    SN Parameter GreenField Brownfield

    1 ExternalEnvironment

    - +

    2 Technology + +

    3 Design &Engineering

    + -

    4 ProjectManagement

    + -

    5 Gestation Cost - +

    6 Investment cost - +

    7 Financial Viability - +

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    21/40

    Cement Manufacturing

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    22/40

    Process at Glance

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    23/40

    Process at Glance Cont..

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    24/40

    CAPEX Monitoring

    Capital expenditures(CAPEX) are expenditurescreating future benefits. Acapital expenditure is incurredwhen a business spends moneyeither to buy fixed assets or toadd to the value of an existingfixed asset with a useful lifethat extends beyond the taxableyear

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    25/40

    Process

    Project Sanction

    Prepare Budget for Sanction Amount

    Commitment

    Actual Expenditure

    To Be Spent

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    26/40

    Sanction Budget

    H eads Rs. (in Crore)

    Land & Site Development 154.74

    Civil & Structure Work 400.83

    Plant & Machinery 669.17

    Power Generation 212.38

    Technical Know how Fee 3.75

    Supervision expenses 14.00

    Mis. Fixed Assets 9.66

    Township & Other Amenities 45.72

    Pre operating Expenses 43.57

    IDC 30.56

    Other extra ordinary expenses 36.05

    Spares 45.00

    Total 1665.43

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    27/40

    Commitment

    H eads Rs. (in Crore)

    Land & Site Development 133.10

    Civil & Structure Work 318.65

    Plant & Machinery 634.18

    Power Generation 208.14

    Technical Know how Fee 3.73

    Supervision expenses 13.14

    Mis. Fixed Assets 4.50

    Township & Other Amenities 26.03

    Pre operating Expenses 27.29

    IDC 40.88

    Other extra ordinary expenses 12.89

    Spares 39.97

    Total 1462.50

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    28/40

    Actual Budget

    H eads Rs. (in Crore)

    Land & Site Development 132.32

    Civil & Structure Work 344.97

    Plant & Machinery 584.96

    Power Generation 171.79

    Technical Know how Fee 3.77

    Supervision expenses 1.95

    Mis. Fixed Assets 4.50

    Township & Other Amenities 24.27

    Pre operating Expenses 27.29

    IDC 40.88

    Other extra ordinary expenses 22.73

    Spares 6.88

    Total 1386.32

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    29/40

    Surplus/Deficiet Budget

    H eads Rs. (in Crore)

    Land & Site Development 22.43

    Civil & Structure Work 55.50

    Plant & Machinery 83.44

    Power Generation 40.59

    Technical Know how Fee -00.02

    Supervision expenses 12.50

    Mis. Fixed Assets 5.50

    Township & Other Amenities 21.45

    Pre operating Expenses 16.59

    IDC -10.32

    Other extra ordinary expenses 13.32

    Spares 38.12

    Total 298.63

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    30/40

    Findings & Learning's

    The Plant & Machinery consisted of around 40% amount of the totalsanction amount i.e. its the major part of the project.In front of total sanction amount, company is place the order for Rs.1462.49 Cr. as on 31 st July, 08 i.e. they commitment for around88% sanction amount.Out of the commitment amount they make the payment Rs. 1366.32Cr. as on 31 st July, 08.The sanction amount for IDC is Rs. 30.56 Cr. while the company paidRs. 40.88 Cr as on 31 st July, 08 i.e. they make excess payment of Rs.10.32 Cr for IDC. These expenses increase due to project timeextended.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    31/40

    Findings & Learning's

    The Technical Know how fee budget is Rs. 375 lacks while company paid Rs.377 lacks as on 31 st July, 08. i.e. they make excess payment but there is traveling expenses include for Rs.1 Cr. thats why the payment exceed as per budgeted amount.I observed that the sanction amount for the project was revised due tothe following reasons - There is an unexpected Pilling Work incurred after working

    started on the project. The steel prices increasing continuously, currently the steel price

    in the market is Rs. 52000 par ton as the inflation rate increasecontinuously.

    The labour cost increase as per company standard rate.

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    32/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    33/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    34/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    35/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    36/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    37/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    38/40

    SAP

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    39/40

    References

    I M Pandey Financial Management.www.adityabirla.comwww.adityacement.comFinancial Management

    By M.Y. Khan & P.K. Jain

    Annual Reports of Grasim Industries Ltd.2007-082008-09

    www.birlagroup.comwww.grasim.com

  • 8/8/2019 Grasim Greenfield and Capex Monitoring

    40/40

    Grasim Industries Limited

    Thank you