Upload
gunju1
View
222
Download
0
Embed Size (px)
Citation preview
8/8/2019 Grasim Greenfield and Capex Monitoring
1/40
8/8/2019 Grasim Greenfield and Capex Monitoring
2/40
8/8/2019 Grasim Greenfield and Capex Monitoring
3/40
8/8/2019 Grasim Greenfield and Capex Monitoring
4/40
Fact Files Of Grasim
GrasimIncorporated on 25Aug 1947
Textilemanufacturingsuccessfullydiversified intoVSF, cementand chemicals
Worldlargest
producer of VSF
9th largest producer of Cement
2ndlargest
producer of causticsoda inIndia
4th
largest producer of insulatorsin theworld
GrasimandGravierarange of fabricssignifythe'power of fashion
8/8/2019 Grasim Greenfield and Capex Monitoring
5/40
Grasim Cement
Its first cement plant at Jawad in Madhya Pradesh in mid 1980.Span India, with 11 composite plants, 11 split grinding units, five
bulk terminals and 69 ready-mix concrete plants.Grasim is also the largest producer of white cement in India, with acapacity of 560,000 tpa as on 30 June 2009. Branded as BirlaWhite.Grasim is a voluntary member of the Cement Sustainability Initiative(CSI), which is the apex for the cement industry globally to establish
common measures, share best practices and exchange data relating toenvironmental impact.
8/8/2019 Grasim Greenfield and Capex Monitoring
6/40
Project Classification
GreenFieldproject
(Add Capacityto Scratch One.)
ProjectRoute
BrownFieldProject
(Add Capacityto Existing.)
8/8/2019 Grasim Greenfield and Capex Monitoring
7/40
GreenField Project
The setting up of greenfieldcement projects means startingfrom scratch at a new location /
site with the land andinfrastructure as available. Thegreenfield plant can be set up asintegrated plant or with splitlocation where clinker can bemanufactured at one location &
cement grinding and/or packingcan be done at another location.
8/8/2019 Grasim Greenfield and Capex Monitoring
8/40
Influencing FactorsQ uantitative factors
1. Gestation period2. Investment cost3. Profitability and Financial Viability
Q ualitative factors
4. External Environment
5. Technology6. Design and Engineering7. Project Management
8/8/2019 Grasim Greenfield and Capex Monitoring
9/40
Quantitative Factors
1 .Gestation Period
Site identificationRaw material studiesEIA/EMP studiesPlant technical concept & project reportFinancial closure
Project implementationStabilization
8/8/2019 Grasim Greenfield and Capex Monitoring
10/40
Quantitative Factors
Project Estimated Amount(per ton)
Specific investment cost for Greenfield project
Rs. 4800-5100
Specific investment cost for brownfield project (Up gradation) Rs. 3950-4350
Specific investment cost for brownfield project (New line)
Rs. 4500-4800
2.Investment Cost
8/8/2019 Grasim Greenfield and Capex Monitoring
11/40
Quantitative Factors
3 .Profitibility &Financially Viable
For similar capacity addition the brownfield project shall generallyhave better financial viability due
to lower gestation period andlower investment levels
8/8/2019 Grasim Greenfield and Capex Monitoring
12/40
Qualitative Factors
4 .External Environment
Land and Infrastructure Fresh acquisition and development isrequired.Limestone new mineable deposit to be identified, investigated andacquiredFuel linkages to be established afreshEnvironment clearance large lead time for data collection
Market entry barriersFinancing More difficult and rigid terms & conditions.
8/8/2019 Grasim Greenfield and Capex Monitoring
13/40
Qualitative Factors
5 .Technology
Raw material availability augmentationComputer Aided Deposit Evaluation (CADE)Quarry Scheduling and Optimization ( QSO)GrindingPyroprocessingImproved equipment
8/8/2019 Grasim Greenfield and Capex Monitoring
14/40
Qualitative Factors
6 .Design & Engineering
LayoutInfrastructure limitationsSafety considerationsEnvironmental considerationsTemptations to have more and more flexibilityEnergy optimizationAgeing of civil structuresAgeing of old equipment proposed to be retained in the upgraded plantRequirements for future growth
8/8/2019 Grasim Greenfield and Capex Monitoring
15/40
Qualitative Factors
7 .Project Management
The project implementation time hasshrunk and the project overruns aresuicidal. The lenders are increasinglyinsisting on detailed planning, efficientmonitoring and control mechanism(time/cost) to avoid/ minimizeoverruns.
8/8/2019 Grasim Greenfield and Capex Monitoring
16/40
Case Objective & Details (Demo)For up gradation of kiln from 10,000 tpd clinker to 12,000 tpd clinker
Details
Description Present Proposed
Kiln Capacity 10,000 tpd clinker 12,000 tpd clinker
Kiln Speed 2.0 rpm(maximum) 4.0 rpm
Kiln Slope 3.50% 3.50%
Kiln Size 7.0 m dia. x 110m length 7.0 m dia. x 110 m length
Preheater Single string, 4 stagecyclone preheater
Existing string with 4 stage cyclones askiln string and a new string with 4 stage
preheater and In Line Calciner (ILC)
GCT/ECP One GCT and two parallelESPs
A new GCT/ ESP is required for dedusting the new PH fan.The GCT is
proposed to be before the new PH fan andit will discharge to the new ESP, where anew ESP fan will vent out the clean air tothe atmosphere through an independentchimney.Its existing GCT & ESP willcontinue to be used.
8/8/2019 Grasim Greenfield and Capex Monitoring
17/40
Case Details Cont..
Description Present Proposed
Specific heatconsumption
880 Kcal/ kg clinker 750 Kcal/kg clinker
Filling in kiln 9.64% 14.83%
Fuel firing Kiln : 100% Kiln : 45%
Precalciner : 55%
Burner for fuel oil firing
Kiln : FLS Kiln : FLS Duoflex burner for oil or gas.Precalciner: A new burner of FLS design
Clinker Cooler Planetary coolers New generation, highefficiency FLS SFcooler with more than73% heat recuperationefficiency.
8/8/2019 Grasim Greenfield and Capex Monitoring
18/40
Case Details Cont..
Other EquipmentDescription Present Prposed
Crusher 6000 tph A new crusher of capacity 9000 tph to meet therequirement of this kiln.
Raw mill 2000 tph 3600 tphThe following modifications:
Replacement of the existing two nos.conventional dynamic separator by a suitablydesigned new generation high efficiencydynamic separator.
Installing a closed circuit roller press in frontof raw mill.
Cement mill 1160 tph 2660 tphconsidering about 20% margin, it isrecommended to install a new cement mill of cap around 1500 tph
Power consumption - 100 kWh/t cement
8/8/2019 Grasim Greenfield and Capex Monitoring
19/40
ResultA debt equity ratio of 70:30 has been considered for projectfinancing.Kiln run days has been considered as 330 days per annum.The plant operating efficiency are considered as follows:
1st year of operation 9 0%
2nd year of operation onwards 100%
The Financial indicators are worked out as follows:IRR on investment 2 0 .82 %
IRR on equity 31 .94%
Payback period 4 years 2 months
Based on the estimates, the total cost for the proposed project works
out to Rs.657
2 million for kiln upgradation
8/8/2019 Grasim Greenfield and Capex Monitoring
20/40
Findings
SN Parameter GreenField Brownfield
1 ExternalEnvironment
- +
2 Technology + +
3 Design &Engineering
+ -
4 ProjectManagement
+ -
5 Gestation Cost - +
6 Investment cost - +
7 Financial Viability - +
8/8/2019 Grasim Greenfield and Capex Monitoring
21/40
Cement Manufacturing
8/8/2019 Grasim Greenfield and Capex Monitoring
22/40
Process at Glance
8/8/2019 Grasim Greenfield and Capex Monitoring
23/40
Process at Glance Cont..
8/8/2019 Grasim Greenfield and Capex Monitoring
24/40
CAPEX Monitoring
Capital expenditures(CAPEX) are expenditurescreating future benefits. Acapital expenditure is incurredwhen a business spends moneyeither to buy fixed assets or toadd to the value of an existingfixed asset with a useful lifethat extends beyond the taxableyear
8/8/2019 Grasim Greenfield and Capex Monitoring
25/40
Process
Project Sanction
Prepare Budget for Sanction Amount
Commitment
Actual Expenditure
To Be Spent
8/8/2019 Grasim Greenfield and Capex Monitoring
26/40
Sanction Budget
H eads Rs. (in Crore)
Land & Site Development 154.74
Civil & Structure Work 400.83
Plant & Machinery 669.17
Power Generation 212.38
Technical Know how Fee 3.75
Supervision expenses 14.00
Mis. Fixed Assets 9.66
Township & Other Amenities 45.72
Pre operating Expenses 43.57
IDC 30.56
Other extra ordinary expenses 36.05
Spares 45.00
Total 1665.43
8/8/2019 Grasim Greenfield and Capex Monitoring
27/40
Commitment
H eads Rs. (in Crore)
Land & Site Development 133.10
Civil & Structure Work 318.65
Plant & Machinery 634.18
Power Generation 208.14
Technical Know how Fee 3.73
Supervision expenses 13.14
Mis. Fixed Assets 4.50
Township & Other Amenities 26.03
Pre operating Expenses 27.29
IDC 40.88
Other extra ordinary expenses 12.89
Spares 39.97
Total 1462.50
8/8/2019 Grasim Greenfield and Capex Monitoring
28/40
Actual Budget
H eads Rs. (in Crore)
Land & Site Development 132.32
Civil & Structure Work 344.97
Plant & Machinery 584.96
Power Generation 171.79
Technical Know how Fee 3.77
Supervision expenses 1.95
Mis. Fixed Assets 4.50
Township & Other Amenities 24.27
Pre operating Expenses 27.29
IDC 40.88
Other extra ordinary expenses 22.73
Spares 6.88
Total 1386.32
8/8/2019 Grasim Greenfield and Capex Monitoring
29/40
Surplus/Deficiet Budget
H eads Rs. (in Crore)
Land & Site Development 22.43
Civil & Structure Work 55.50
Plant & Machinery 83.44
Power Generation 40.59
Technical Know how Fee -00.02
Supervision expenses 12.50
Mis. Fixed Assets 5.50
Township & Other Amenities 21.45
Pre operating Expenses 16.59
IDC -10.32
Other extra ordinary expenses 13.32
Spares 38.12
Total 298.63
8/8/2019 Grasim Greenfield and Capex Monitoring
30/40
Findings & Learning's
The Plant & Machinery consisted of around 40% amount of the totalsanction amount i.e. its the major part of the project.In front of total sanction amount, company is place the order for Rs.1462.49 Cr. as on 31 st July, 08 i.e. they commitment for around88% sanction amount.Out of the commitment amount they make the payment Rs. 1366.32Cr. as on 31 st July, 08.The sanction amount for IDC is Rs. 30.56 Cr. while the company paidRs. 40.88 Cr as on 31 st July, 08 i.e. they make excess payment of Rs.10.32 Cr for IDC. These expenses increase due to project timeextended.
8/8/2019 Grasim Greenfield and Capex Monitoring
31/40
Findings & Learning's
The Technical Know how fee budget is Rs. 375 lacks while company paid Rs.377 lacks as on 31 st July, 08. i.e. they make excess payment but there is traveling expenses include for Rs.1 Cr. thats why the payment exceed as per budgeted amount.I observed that the sanction amount for the project was revised due tothe following reasons - There is an unexpected Pilling Work incurred after working
started on the project. The steel prices increasing continuously, currently the steel price
in the market is Rs. 52000 par ton as the inflation rate increasecontinuously.
The labour cost increase as per company standard rate.
8/8/2019 Grasim Greenfield and Capex Monitoring
32/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
33/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
34/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
35/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
36/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
37/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
38/40
SAP
8/8/2019 Grasim Greenfield and Capex Monitoring
39/40
References
I M Pandey Financial Management.www.adityabirla.comwww.adityacement.comFinancial Management
By M.Y. Khan & P.K. Jain
Annual Reports of Grasim Industries Ltd.2007-082008-09
www.birlagroup.comwww.grasim.com
8/8/2019 Grasim Greenfield and Capex Monitoring
40/40
Grasim Industries Limited
Thank you