31
GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO SUSTAINABLE WATER PROJECT ENVIRONMENTAL ASSESSMENT EXECUTIVE SUMMARY DRAFT, May 2009 E2170 v3 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

Embed Size (px)

Citation preview

Page 1: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

GOVERNMENT OF THE STATE OF PERNAMBUCO

State Secretariat for Water Resources

PERNAMBUCO SUSTAINABLE WATER PROJECT

ENVIRONMENTAL ASSESSMENT

EXECUTIVE SUMMARY

DRAFT, May 2009

E2170 v3P

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

edP

ublic

Dis

clos

ure

Aut

horiz

ed

Page 2: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

ACRONYMS

ANA National Water Agency APP Environmental Protection Area COBH-Cabiparibe Capibaribe Basin Committee COMPESA Pernambuco State Water and Sanitation Utility CONAMA National Commission for the Environment CPRH State Environment and Water Resources Agency EMP Environmental Management Plan IBGE Brazilian Institute for Geography and Statistics IPA Pernambuco Company for Agricultural Research IPHAN National Institute of Historical and Artistic Heritage MRR Metropolitan Region of Recife NGO Non-Governamental Organization PAC Federal Growth Acceleration Program PER Preliminary Environmental Report PSH-PE Pernambuco Sustainable Water Project SRH State Secretariat for Water Resources WTP Water Treatment Plant WWTP Wastewater Treatment Plant

Page 3: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

PERNAMBUCO SUSTAINABLE WATER PROJECT

FRAMEWORK FOR ENVIRONMENTAL AND SOCIAL MANAGEMENT

INTRODUCTION

GENERAL CHARACTERISTICS OF THE CAPIBARIBE BASIN

LEGAL AND INSTITUTIONAL FRAMEWORK AND COMPARATIVE ANALYSIS WITH IRDB SAFEGUARD POLICIES

ENVIRONMENTAL AND SOCIAL ASSESSMENT OF COUNTERPART WORKS

ENVIRONMENTAL AND SOCIAL ASSESSMENT OF WORLD BANK FINANCED INTERVENTIONS

E A

S A

OVERALL PROJECT EVALUATION

ENVIRONMENTAL MANAGEMENT PLAN

E M P

C

S C S E E

P

C

S JT C

P S

S C

WWTP S M

I MRR  C

E

T U E P

R F

E C M

8. PUBLIC CONSULTATIONS........................................................................................................................26

Page 4: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

1

1. INTRODUCTION

1. This Executive Summary of the Environmental Assessment Report on the Pernambuco Sustainable Water Project (PSH-PE) presents the project’s main potential environmental and social impacts and proposed mitigation measures as succinctly and objectively as possible.

2. A comprehensive Environmental Assessment (EA) was undertaken during the preparation of the PSH-PE; the EA evaluates existing conditions, identifies potential direct and indirect environmental impacts, and proposes measures to mitigate negative impacts and enhance positive impacts. The Environmental Management Plan (EMP) summarizes these measures along with their associated costs, responsibilities, and schedule, and comprises an Environmental Construction Manual. Public consultations were carried out and documented following the disclosure procedures recommended by the Bank’s environmental policy.

3. A Social Analysis was undertaken in conjunction with the Environmental Assessment, and a Resettlement Policy Framework has also been prepared. Project documentation is available at the office of the State Secretariat for Water Resources – SRH, Government of Pernambuco, Av. Cruz de Cabugá 111, Recife – PE, Brazil, and safeguard studies were made available at the InfoShop on May 29, 2009. The Environmental and Social Assessments of the PSR-PE were commissioned by the State Secretariat for Water Resources (SRH), and prepared by the consultant Alexandre Fortes.

4. The proposed Project will be supported by a World Bank specific investment loan (SIL) in the amount of US$190 million. The project development objective is to improve sustainable water supply and sanitation services in the Capibaribe river basin and in the Metropolitan Region of Recife (MRR) – both in appropriate quality and quantity. The PSE-PE will support the Government of Pernambuco’s goal of achieving sustainable economic growth and social development, for which a reliable and efficient management of water resources, as well as adequate irrigation, water supply and sanitation service provision are critical. The project gives priority to investments in the Capibaribe river basin (the main river under State jurisdiction) and in the MRR (42% of the state population and 65% of the State GDP), aiming to provide efficient water supply services and to implement wastewater collection and treatment services, to protect the main water reservoirs targeted for human consumption.

5. Within the scope of designing the PSH-PE, SRH has requested the World Bank to consider the possibility of recognizing some of the sector interventions currently underway as State counterpart contributions under the future loan contract, particularly the works of the Pirapama water supply conveyance system, estimated to cost US$220 million, and currently under construction with resources from state government and from the Federal Growth Acceleration Program (PAC).

6. The project’s concept includes strengthening state water resources management, as well as improving water and sanitation management efficiency and infrastructure, with funding from two sources: (i) ongoing State counterpart civil works funded by the PAC; (ii) World Bank-financed civil works to improve the efficiency of existing water supply systems and to install wastewater systems in selected municipalities in the Capibaribe river basin, for which typologies have been defined.

Page 5: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

2

7. Thus, this report focuses on two distinct sets of documents and works that integrate this project: (i) the social and environmental assessment of works currently under implementation with 100% financing from counterpart funds; and (ii) a framework for environmental and social management of future works to be implemented under the project with financing from the World Bank, including the environmental assessment of subproject typologies and the setting of criteria and procedures for the environmental assessment of subprojects in the project implementation phase. The proposed PSH-PE Project is structured in three components:

8. Component 1 – Water Sector Management and Institutional Development (US$29 million). This component covers the strengthening of institutions and the development of an efficient water resource management model, and supports: (i) integrated water resource management, (ii) water services and infrastructure; and (iii) project management.

9. Component 2 – Improving Efficiency in the Provision of Water Supply and Sanitation Services (US$52 million). This component will support: (i) non-revenue water, which will support activities aimed at reducing technical and commercial water losses and improving COMPESA’s services, sales and operational efficiency in the MRR, and (ii) the implementation of a corporate development program with focus on activities that can improve COMPESA’s financial equilibrium, overall customer satisfaction, staff productivity as well as corporate organization and management.

10. Component 3 – Water Supply and Sanitation Service Expansion (US$320 million). This component is divided into the following sub-components: (a) Pirapama Water Supply System Sub-component, which will support technical assistance and acquisition of goods and works targeted towards increasing water supply availability and reliability in the MRR, and includes the on-going expansion and integration of the Pirapama water supply conveyance system.; and (b) Expansion of services Sub-component, which will finance technical assistance, acquisition of goods and works to expand services and leverage investments in priority areas. This sub-component will support the Government of Pernambuco to protect the main sources of water in the Capibaribe river basin by targeting areas where new sewage collection and treatment services would significantly contribute to the reduction of pollution loads particularly from the municipalities of Vitória de Santo Antão, Salgadinho, Limoeiro, Paudalho and Toritama. This sub-component will also finance technical assistance to support to the Government of Pernambuco in the prioritization of water supply and sewerage investments, as well as in the preparation of regional and municipal water master plans and detailed engineering designs for priority projects.

2. GENERAL CHARACTERISTICS OF THE CAPIBARIBE BASIN

11. The Capibaribe Basin comprises 43 municipalities. According to the Brazilian Institute for Geography and Statistics (IBGE), in the year 2000 this group of municipalities had a population of about 3.5 million inhabitants, which represents about 43% of the population of the State, 87% of which live in urban areas, mostly in the MRR1 on the Lower Capibaribe.

T MRR  C I J B

Page 6: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

3

12. The main districts of twenty seven municipalities are located within the basin, 19 of which are located upstream of the basin’s main reservoirs. Four of those municipalities are located along the banks of the main river (Santa Cruz do Capibaribe, Toritama, Surubim and Limoeiro) and two along the banks of the Tapacurá river (Vitória de Santo Antão and Pombos).

13. The main water supply reservoirs in the basin are:

• The Jucazinho Reservoir

The Jucazinho reservoir, inaugurated in 1999, has a maximum capacity of 327.04 million cubic meters, and is used mainly for flood control purposes. Jucazinho currently supplies the cities of Casinhas, Frei Miguelinho, Salgadinho, Santa Maria do Cambuca, Surubim, Cheus, Vertente do Lerio, Vertentes, Caruaru, Cumaru, Passira and Riacho das Almas, serving a population of about 353,000 inhabitants.

• The Carpina Reservoir

The Carpina and the Jucazinho reservoirs, together, constitute the flood control system of the upper-mid and mid-Capibaribe river.

Initially the main purpose of the Carpina dam, inaugurated in 1978, was the control of downstream flooding. In 2003, COMPESA started using the Carpina reservoir for water supply to the municipality of Feira Nova, with a population of about 15,500 inhabitants. A pipeline from this reservoir to the Glória do Goitá and Limoeiro systems is currently under construction.

• The Tapacurá Reservoir

This reservoir was built in 1973 in the municipality of São Lourenço da Mata, with the purpose of supplying water to the municipalities of Camaragibe, Jaboatão dos Guararapes, Recife and São Lourenço da Mata, and enabling flood control on the Lower Capibaribe.

The reservoir supplies water to the population of the following cities: Camaragibe (170,000 inhabitants) and part of the cities of Recife (900,000 inhabitants), Jaboatão (150,000 inhabitants) and São Lourenço (23,195 inhabitants) (Source: Compesa, 2008).

14. These reservoirs currently are in a stage of hyper-eutrophication due to the flourishing of algae and the presence of cyanobacteria, mostly as the consequence of the current total absence of wastewater treatment in municipalities located upstream in the drainage basin.

15. Of the 19 municipalities located upstream from the reservoirs, only Vitória do Santo Antão counts with a partial wastewater collection system (without treatment). In all other cities, especially the six that are located along the banks of the Capibaribe and Tapacurá rivers, wastewater drains into the water bodies, without any treatment.

Page 7: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

4

The Capibaribe River Basin

3. LEGAL AND INSTITUTIONAL FRAMEWORK AND COMPARATIVE ANALYSIS WITH IBRD SAFEGUARD POLICIES 16. The assessment of the PSH-PE components was designed so as to simultaneously consider: (i) compliance with World Bank environmental safeguard policies, as a condition for the signature of the Loan Agreement; and (ii) strict compliance with and attention to federal, state and municipal legal requirements, especially with regard to rules and procedures for the environmental licensing of the actions foreseen under the Project.

17. During project preparation, infrastructure interventions have been grouped into two sets: (i) state counterpart interventions associated to works being built with financing from the federal Growth Acceleration Program (PAC); and (ii) the World Bank-funded works aimed at improving the efficiency of existing water supply systems and the implementation of wastewater systems in selected municipalities in the Capibaribe river basin.

18. For the second set of interventions, neither conceptual nor detailed engineering designs are available at this stage. Hence, this report had taken a dual approach to assess the project:

(i) Environmental and social assessment of the counterpart works under execution – the Pirapama water supply system; and

(ii) Design of an Environmental and Social Management Framework, involving the environmental and social assessment of the typologies of wastewater subprojects and the definition of criteria and procedures for the environmental and social assessment of subprojects during the implementation of the PSH-PE.

19. Within the scope of the World Bank’s safeguard policies, the proposed project is classified as category A. As such, this report evaluates with- and without-project scenarios,

Page 8: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

5

identifies potential direct and indirect environmental impacts associated with the project and other alternatives, develops mechanisms and measures to avoid, minimize and/or mitigate negative impacts, and presents an Environmental Management Plan with specific activities, budgets and responsibilities to ensure the implementation of these mitigating measures.

20. The following safeguard policies are triggered:

(i) OP 4.01 Environmental assessment (ii) OP 4.04 Natural Habitat (iii) OP 4.36 Forests (iv) OP 4.12 Involuntary Resettlement (v) OP 4.11 Physical and Cultural Resources (vi) OP 4.37 Safety of Dams (for the counterpart works)

Environmental Licensing for Project Interventions

21. PSH-PE interventions will be the object of environmental licensing according to the relevant applicable environmental legislation at the federal and the state levels. For example, each intervention for the implementation of basic sanitation systems, as determined by the environmental legislation, shall fulfill a specific environmental licensing practice, complying with document, process and timeframe requirements associated to the rules and procedures established by the licensing body – the State Agency for Environment and Water Resources (Agência Estadual de Meio Ambiente e Recursos Hídricos – CPRH).

22. As for the wastewater systems, the CPRH licensing process requires the presentation of a Preliminary Environmental Report (PER). In addition, the terms of CONAMA Resolution 377/06 on the adoption of simplified licensing procedures for the development of medium and small wastewater systems (which covers most PSH-PE interventions) must be taken into account.

Granting of water rights

23. The granting of water user rights is one of the water resource management instruments foreseen under Federal Law No. 9433 of January 8, 1997, whereas the competence for managing and granting licenses lies with National Water Agency (ANA) in the case of federal rivers, and the Secretariat for Water Resources (SRH) in the case of rivers under state jurisdiction and underground aquifers. The granting of licenses is closely linked to the Water Resource Plans and the classification of water bodies.

4. ENVIRONMENTAL AND SOCIAL ASSESSMENT OF WORKS ALREADY UNDER IMPLEMENTATION WITH COUNTERPART FUNDS 24. The Pirapama water supply system aims to ensure regular public water supply to the MRR, particularly to the southern and central areas, the most populated ones, which represents about 50% of the overall system capacity that currently supply the municipalities of Recife, Jaboatão and Cabo de Santo Agostinho.

Page 9: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

6

25. The works forthis system started in the late 1980’s and were suspended after a few years mostly due to lack of funds. Works for the Pirapama Dam which has the capacity to provide flows of 5.13 m3/s, were resumed in 2000 and completed in 2001.

26. This is a gravity-type dam, with capacity for 61 million cubic meters of water, comprising: (i) one water intake provided by an underwater tower; (ii) one bottom discharge through 2-meter diameter steel pipes.

27. The Pirapama water supply system, using water from the Pirapama Dam, is made up by the following units, which are currently under construction (See outline – Figure 5.1 below):

28. Intake Pumping Station, located next to the dam, receives water coming out of the intake located downstream from the dam through a 2-meter diameter pipe, with a pumping capacity of 5.13 m3/second up to the Water Treatment Plant – WTP. It has six motor-pump sets with 1600 cv power, one of which acts as a reserve pump.

29. Bulk Water Main in 1,700 millimeter carbon steel pipes, that are 3,580 meters long.

30. Water Treatment Plant – a complete conventional WTP initially designed with four 1.28 m3/s modules. The current WTP project will make use of the partially-built facilities, the works of which have been suspended as of 1994.

31. Potable Water Main designed as a 1,700 millimeter pipe, with a length of about 19,500 meters. This pipeline is located mostly within the area of domain of BR-101, a federal highway.

32. Cabo de Santo Agostinho Sub-main, with 800 millimeter pipe connecting the pipeline to the existing Cabo reservoir, currently being expanded.

33. Ponte dos Carvalhos Sub-main, with 800 millimeter pipe connecting the pipeline to the existing Ponte dos Carvalhos reservoir, currently being expanded.

34. Expansion of the Cabo and Ponte dos Carvalhos Service Reservoirs for a capacity of 13,500 m3 and 17,000 m3, respectively.

35. Construction of the Jordão Service Reservoir, a type supported with capacity for 90,000 m3.

36. An environmental and social analysis of the existing and under construction works for the Pirapama water supply system was carried out, including on-site inspections, and the main findings are the following:

Page 10: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

7

OP 4.01 – Environmental Assessment

37. An environmental assessment was undertaken in the first phase of the implementation of Pirapama works, with the preparation of an Environmental Impact Assessment of the Pirapama dam in 1989 by COMPESA and a consulting firm named Aquaplan. In 2001, the Pirapama water production system was assessed in a preliminary environmental report undertaken by the consortium HagaConsult.

38. All of the construction works already received the corresponding Installation License (IL) issued by the State Environment and Water Resources Agency (CPRH) and the Water Rights have been granted by SRH.

39. The environmental license conditionalities to be met regarding mitigation and compensatory measures, have already been included in the PAC financing package and are being executed by COMPESA. Such measures amount to R$4 million, as shown on the table below.

Table 1 – Environmental Compensation Resources

ITEM COMPENSATION ACTIONS AMOUNT (R$)

1 Detailed technical design of compensation measures 50,000.00

2Demarcation with landmarks of the permanent preservation strip (100 m) around the reservoir

160,000.00

3Reforestation of 120 hectares per year around the lake, totaling 360 hectares, in the environmental protection area (APP)

3,200,000.00

4 Rehabilitation of areas used for pit disposal of excavated material. 450,000.00

5Compensating vegetation suppressed from raw water systems and treated water main

50,000.00

6 Monitoring of water quality 90,000.00

TOTAL 4,000,000.00

Page 11: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

8

40. Items 1 to 4 in Table 1 above refer to the implementation of complementary environmental measures related to the construction of the Pirapama dam and reservoir, concluded in 2001. Main measures include (i) the demarcation of the 100-meter environmental protection area (APP) surrounding the reservoir’s banks, and (ii) reforestation of about 360 hectares in that area, which is already owned by COMPESA.

41. The current implementation of works counts with an informal environmental management system that includes environmentally sound construction procedures. SRH and COMPESA currently are negotiating with the construction consortium the adoption of the procedures stated in the construction environment manual, especially items regarding:

(i) Formalization of environmental management/oversight actions; (ii) Social communication actions for the works, with communications and ombudsman

services. (iii) Inclusion of recuperation actions in the work area; and (iv) Inclusion of recuperation actions in the areas used for disposal of excavated material.

Overall Environmental Impacts

42. The Pirapama water system integrates a set of water production systems for the MRR and, once implemented, will represent an estimated additional 50% of the water availability for the population. In general terms, the positive impacts of its implementation are highly significant. Once the water production system is in operation, it is expected that the result of the interventions will be highly positive and permanent, ensuring the adequate supply of water and a significant improvement in the quality of life of the population living in the MRR.

43. Negative impacts, on the other hand, are localized, reversible and temporary, deriving mostly from activities that are inherent to the execution of the works and can be minimized through the adoption of preventive measures, contemplating the appropriate planning of interventions and appropriate procedures during its execution.

44. Some of these measures are being adopted during the preparation of detailed designs of the interventions, which aim to avoid occupied areas and preserved natural environments. COMPESA and the technical-environmental team of the works contractor normally carry out regular environmental monitoring of works execution. Actions aimed at strengthening these procedures, as detailed in the environmental construction manual, are being adopted by SRH and COMPESA.

45. With regard to the Bank’s environmental safeguards, the adoption of additional measures by COMPESA and SRH, the scheduled interventions and the actions adopted within the scope of counterpart interventions, are in line with the procedures recommended by the World Bank.

OP 4.04 – Natural Habitats 46. Most areas used for implementing these works are anthropized, with low population density. The location of interventions were conceptualized with the goal of avoiding – as much as possible – affecting natural areas with vegetation and does not interfere with areas of conservation.

Page 12: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

9

47. On the stretches of the conveyance system, the interventions will need to suppress 3 hectares of secondary forest vegetation, including a stretch of an environment preservation area (APP) along the Jaboatão River. The appropriate authorization has already been issued by CPRH and compensation measures established by the environmental agency are being implemented.

OP 4.12 – Involuntary Resettlement 48. The construction of the Pirapama water supply system, which is under execution with financing provided by the government and constitutes the project counterpart financing, has affected 294 families, including 202 families that had to be moved to other locations and 92 processes of land acquisition. The resettlement of families was required for the construction of the Jordão elevated water storage facility, as well as for the expansion of the main water distribution system. The land acquisition was required also to expand the main water transportation system. The table below presents the resettlement and land acquisition undertaken.

Pirapama System Number of

families resettled Number of parcels of land acquired

Elevated water reservoir - Jordão 138 - Water main transportation network 63 92 Elevated water reservoir – Ponte de Carvalho 1 - Total 202 92

49. When the construction of the Pirapama system was interrupted in the mid to late 1990s, several families informally occupied the areas that were allocated to the construction of this system and were formally owned by COMPESA. Once the construction restarted, COMPESA reassessed the engineering designs aiming at reducing the number of houses requiring removal from the project areas. The updated designs were able to reduce the number of houses requiring removal, but still entailed the removal of 202 houses and the acquisition of 92 parcels of land.

50. In order to undertake the removal of housing, COMPESA opted for designing and implementing a broader social program, which would assist the families living in these houses to take this opportunity to also improve their living conditions. The main principle supporting this program was one of offering a very favorable financial compensation for the families’ assets, which would allow these families to purchase a house of higher value and better quality. Integrated with this financial mechanism, the social team of COMPESA put in place a social program to assist the families in the removal process. COMPESA also contracted additional social workers to cope with the increased demand for social assistance.

51. The main principles of the social and resettlement programs were: (i) qualified social professionals should provide support to the families during the removal process; (ii) the asset valuation criteria should allow the families to purchase a new house of better quality than the house they currently lived in; (iii) the process of resettling the families should allow them to take informed decisions and to voice their concerns; and (iv) safety measures should be in place to protect the families once they receive the financial compensation for their houses.

52. The socio-economic profile of the families assisted are as follows:

(i) The average income of the 202 families assisted is among the lowest within the metropolitan area.

(ii) Formal unemployment is extremely high, reaching 43% of the active adults.

Page 13: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

10

(iii) For the unemployed, the informal sector is the only possible alternative for some income generation.

(iv) Among those with regular employment, 10% are retirees. (v) Among those employed, unskilled labor prevail. (vi) The average income corresponds to one minimum salary (about US$160/month). (vii) The lack of appropriate infrastructure services further deteriorates the quality of

life in the area. (viii) There is no formal water or sewerage service. (ix) Water is collected from public taps and improperly stored.

53. Asset valuation criteria: The method adopted for assessing the value of the assets ensured that the financial compensation amount would allow each family to choose to move to a house of better quality. As a preliminary evaluation indicated that a large percentage of those houses requiring removal had an extremely low market value, COMPESA opted for a increasing the value by adding the amount equivalent to a 12-month rental in the area.

54. The valuation method took into consideration the type of construction, the structures status of conservation, and number of inhabitants, among others, in order to arrive at a valuation consistent to market values and allow for the families to purchase another property to move into. The calculations were done according to local civil construction guidelines, and the value paid varied between R$120 to R$150 per square meter. The valuation also included the potential value of fruit trees and existing constructions within the lot occupied. Assessments carried out in the area indicated that this mechanism would allow the families to afford a house of good quality. The compensation value varied from about US$2,500 to US$11,000. In addition, the families also received compensation to cover the expenses related to the process of moving to a new house.

55. Social support methodology: In early 2008, before the works of the Pirapama Water Supply system re-started, COMPESA’s social team, strengthened by the hiring of additional social workers, carried out meetings with the families to discuss the resettlement objectives and criteria. Regular meetings were held since the preliminary information campaigns until the effective compensation for the families’ assets. The methodology included the elaboration of a cadastre per family, in which the assets were evaluated and discussed with the family and detailed information and pictures were included. The constant presence of the social team in the area facilitated the interlocution with the families and the provision of timely clarification.

56. Based on the consultations carried out, one important procedure was adopted regarding precautions needed when the family was to receive the compensation. The families indicated that they would like to be closely assisted at this specific moment because of fear of being robbed. This assistance was provided, as well as information on available houses in the neighborhood for those that requested such information. The high rate of crime and violence in the area was taken into account, and strongly influenced the methodology adopted for the social support. A sample of the questionnaire used is in the project files.

57. Monitoring: Monitoring campaigns to evaluate the living conditions of those resettled have been carried out as part of the social methodology. This monitoring includes surveying affected families to capture information on their current living conditions. The results indicate that the living conditions have improved significantly with respect to the quality of the houses.

Page 14: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

11

The cadastre and picture of the original houses compared to the new houses clearly demonstrate the improvements achieved. Many families have opted to buy a new house in the same neighborhood and they were able to choose a better location and house standard. Other families opted for returning to their city of origin or moving to another city. Those have not been covered by the post resettlement monitoring.

Land acquisition 58. The land acquisition program undertaken in 92 areas does not prevent the families from using the affected areas. The families received financial compensation in case the area was being used for activities such as agriculture. Once the construction is concluded, the families will be allowed to use the area again. Some restrictions may apply to protect the pipes installed underground. One example of these restrictions is that no large tree with deep roots can be planted in the right-of-way. With exception of one case, the land ‘acquired’ constitutes just one portion of the total area formally or informally owned by the family. The exception case refers to one producer that was growing bananas along the one kilometer of right-of-way, which is being used by COMPESA, but formally belongs to the state energy company. This producer has received approximately US$70,000 in financial compensation and has legally bought some land where he is developing a farm. This approach for restoration of livelihoods is consistent with OP 4.12 as COMPESA has to a significant extent pursued options to minimize involuntary resettlement and an adequate participatory process was followed for the implementation of compensatory measures that ensured adequate compensation for the land acquired.

59. Additionally, the production system comprises a stretch of the main connecting the Jordão reservoir to the Recife water network (Alça dos Anéis de Recife) (see figure). The detailed designs are currently being prepared and the works are likely to start in May 2009. This stretch also includes several illegal occupations, but with different characteristics from those on the areas under construction. These are areas of public and private domain and do not fit into OP 4.12, article 15“c”. COMPESA estimates are that 100 to 120 families will need to be resettled. For this purpose, COMPESA is preparing a Resettlement Plan in accordance with OP 4.12 requirements.

OP 4.11 – Physical and Cultural Resources

60. According to the Pirapama water supply system’s preliminary environmental report, the location of construction activities avoided historical and cultural sites.

OP 4.37 – Safety of Dams

61. Works for the Pirapama dam were concluded in late 2000, and the reservoir was filled up in 2001. The construction of the dam and the reservoir were subject to detailed environmental impact assessment and report, commissioned by COMPESA and prepared by the consulting firm Acquaplan in 1999. All required environmental licenses were issued by the State Environment Agency CPRH and the water rights were granted by SRH. Since 2008, the Pirapama reservoir is providing an average of 1.0 m3/s of bulk water to increase de production of the Gurjaú water system. The dam has been in operation since 2001 with no reported safety incidents. However, considering that the Pirapama dam is about 20 meters high and a significant withdrawal is expected to start on October 2010, the dam will be evaluated by an Independent Dam Safety

Page 15: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

12

Panel, to be commissioned by SRH prior to the beginning of any works related to the Pirapama water system, that are to be financed with loan proceeds, particularly the non-revenue water investment activities under Component 2.

5. ENVIRONMENTAL AND SOCIAL ASSESSMENT OF FUTURE WORLD BANK-FINANCED INTERVENTIONS

5.1 Environmental Assessment of typologies

62. An Environmental and Social Management Framework was prepared for the various sub-project typologies that involve physical interventions and that will be financed by the PSH-PE under components 2 and 3. Such interventions are analyzed in the tables below, at the conceptual level.

Component 2 – Improving Efficiency in the Provision of Water Supply and Sanitation Services

Activities Actions Proposed Interventions

Installation of telemetric and macro-metering devices

Sectorization of networks with substitution of pipes and repair of reservoirs, etc.

Implementation of flow and pressure control in water networks and reservoirs

Non-Revenue Water

Sectorization, pressure management and network renewal works

Substitution of networks and renovation of pipes, reservoirs, etc.

63. In general terms, the non-revenue water activities foresee small interventions in existing systems and will have no additional interference with the natural environment. According to federal and state environmental legislation, the actions and interventions above are not subject to environmental licensing.

64. The positive impacts, on the other hand, have a more permanent nature and will mostly occur during the operation stage. The table below presents the main impacts (positive and negative) of this type of intervention and its significance, as well as mitigation measures for the negative impacts and the corresponding environmental programs that will be part of the Environmental Management Plan of the overall project, as well as of each selected intervention.

65. As shown in the table below, negative impacts are localized, transitory and of reduced relevance, deriving mostly from activities related to the works. The mitigation of such impacts comprise, mostly, of appropriate care during the execution of the works, involving good engineering practices. During the operation stage of the interventions, most impacts are positive, relevant and permanent. It features a strong positive environmental bias by trying to reduce the consumption of treated water, either by reducing losses and/or promoting its rational use, thus reducing the volume to be adducted and making water available for other uses.

Page 16: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

13

Component 2 – Positive and Negative Impacts, Mitigation Measures and Environmental Programs Positive Impacts

Planning and Construction Phase

Strengthening community-based mobilization Moderate

Employment generation and increased income for the local population Moderate

Operation Phase

Improved sanitary conditions Significant

Improved health conditions for the population Significant

Improved housing standards Significant

Enhancing self-esteem among the population Significant

Consolidation of new cultural and environmental approaches Significant

Negative Impacts

Planning and Construction Phase Mitigation Measures

Environmental Programs

Generating expectations and insecurity among the population

Relatively insignificant

Actions for dissemination of project information and social communication

Social communication

Alterations in the quality of life of the resident population in areas located close to the construction sites (increased noise, dust and traffic; closing of access roads; circulation of people that are foreign to the community, etc.)

Moderate Planning of works and appropriate construction procedures

Environmental Construction Manual

Interference upon existing urban infrastructure and equipment

Relatively insignificant

Coordination with service concessionaires and responsible agencies

Environmental Construction Manual

Suppression of vegetation Relatively insignificant

Appropriate construction methods and recuperation of the affected vegetation

Environmental Construction Manual

Generation of sediments Relatively insignificant

Appropriate construction planning and methods

Project criteria Environmental Construction Manual

Deterioration of environmental, urban and landscape conditions

Relatively insignificant

Planning of works and appropriate construction methods

Environmental Construction Manual

Generating waste – pit disposal areas Relatively insignificant

Disposal of waste in properly licensed areas

Environmental Construction Manual

Accidents risks Relatively insignificant

Planning of works and safety procedures

Environmental Construction Manual

Page 17: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

14

Component 3 – Water Supply and Sanitation Service Expansion

Subcomponent Actions Interventions Proposed

Implementation of collection system (household sewer, networks and trunk sewers) Implementation of transportation system (interceptors, booster stations and pumping lines)

Full implementation of the wastewater system, including wastewater treatment plants

Implementation of Wastewater Treatment Plan - WWTP Expansion of collection sewer networks

Expansion of trunk sewers and interceptors

Implementation of booster stations

Services Expansion

Expansion of infrastructure of existing wastewater systems

Expansion and/or implementation of WWTP

66. The table below presents the main positive and negative impacts of the typologies highlighted above and their relevance, as well as mitigation measures for negative impacts and the corresponding environmental programs to be included in the PSH-PE Environmental Management Plan and for each selected development. The table shows that most negative impacts are localized, temporary and of reduced or moderate significance, deriving, mostly, from activities associated to the execution of the works.

67. Appropriate concept and design criteria can greatly minimize the occurrence of such interferences. In the case of natural habitats, the expansion or implementation of wastewater systems (interceptors, pumping stations and treatment stations) almost always present interferences with APPs. Considered by the legislation as public use interventions, such interferences may be authorized by the environmental agency and minimized through the use of appropriate construction techniques and the later recuperation of the area where the intervention took place.

68. There are a few conservation units in the Capibaribe river basin but they do not overlap with the any of the five municipalities selected to benefit from wastewater system to be financed by the Project.

69. The possibility of interfering with cultural heritage sites will be analyzed during the design of works and respective environmental assessments so as to adopt recovery procedures or, as the case may be, by implementing chance-find procedures, as regulated by the National Institute of Historical and Artistic Heritage - IPHAN.

70. The project design and its execution should avoid any possibility of interference with commercial activities. Likewise, the project development should avoid the need to resettle families. In case there is a need to displace families, a specific plan must be designed, in compliance with the Resettlement Framework stated under the PSH-PE Environmental Management Plan – EMP.

71. Additionally, the project design must consider alternatives for the location of WWTPs in relation to the urban area. Such alternatives must take into account predominant winds and a minimum distance of 500 meters from homes and/or planned urban areas. In case that is not feasible, the WWTP design must foresee a minimum distance of 100 meters from edifications and the appropriate treatment of gases with the elimination of odors.

Page 18: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

15

Positive and Negative Impacts, Mitigation Measures and Environmental Programs for Component 3

Positive Impacts Negative Impacts Mitigation MeasuresEnvironmental Programs

Proposed in EMPPlanning and Construction Phase Planning and Construction Phase

Strengthening of communitymobilization

ModerateGenerating expectations andinsecurity among the population

ModerateActions for the divulging of theproject and socialcommunication

Social communication

Generation of employmentopportunities and increase inincome for local population

Moderate

Alterations in the quality of life ofthe resident population in areaslocated close to the constructionsites

ModeratePlanning of works andappropriate constructionprocedures

EnvironmentalConstruction Manual

Operational PhaseInterference upon existing urbaninfrastructure and equipment

Relativelyinsignificant

Coordination with serviceconcessionaires and responsibleagencies

EnvironmentalConstruction Manual

Improvement in sanitaryconditions

Significant Eventual losses to local businessesRelativelyinsignificant

Environmental ConstructionManual and socialcommunication

EnvironmentalConstruction Manual andsocial communication

Improved quality of water ofthe recipient body

SignificantInterference in PermanentPreservation Areas - APPs

ModerateProject criteriaEnvironmental ConstructionManual

Project criteriaEnvironmentalConstruction Manual

Interference in Conservation UnitsRelativelyinsignificant

Feasibility studies andengineering design must avoidinterference

Criteria for FeasibilityStudies and engineeringdesign

Attraction of investments tothe region

Significant Suppression of vegetationRelativelyinsignificant

Environmental ConstructionManual

EnvironmentalConstruction Manual

Improving environmental andurban conditions in the region

SignificantInterference with cultural andarcheological heritage sites

Relativelyinsignificant

Adoption of reporting andchance finding procedures

EnvironmentalConstruction Manual

Generation of sedimentsRelativelyinsignificant

Environmental ConstructionManual and monitoring

EnvironmentalConstruction Manual andmonitoring

Consolidation of new culturaland environmentalapproaches

SignificantUse of areas for disposal ofexcavated material.

ModerateUse of licensed mines andrecuperation of degraded areas

EnvironmentalConstruction Manual

Improved quality of life forthe population

SignificantGenerating waste – pit disposalareas

ModerateDisposal of waste in properlylicensed areas andreconstitution of areas used

EnvironmentalConstruction Manual

Expansion of wateravailability

Significant Risk of accidentsRelativelyinsignificant

Planning of works and safetyprocedures

EnvironmentalConstruction Manual

Enhancing self-esteem amongthe population

SignificantIncreased traffic of heavymachinery in the region

Relativelyinsignificant

Proper planning of worksEnvironmentalConstruction Manual

Page 19: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

16

Positive Impacts Negative Impacts Mitigation MeasuresEnvironmental Programs

Proposed in EMP

Enhancing value of land ModeratePossibility of displacement andresettlement of families

Moderate Resettlement frameworkProject criteriaResettlement policy

Operation Phase

Generation of odor by WWTP ModerateAppropriate location forWWTP and/or providing fortreatment of gases

Monitoring

Generation of sludge by WWTP ModerateAppropriate treatment and finaldisposal

Monitoring

Page 20: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

17

72. The WWTP expansion or implementation design must include the assessment, treatment and final destination of sludge, its treatment and final destination, both currently and in the future. All project criteria must be stated in the PSH-PE Environmental Management Plan –EMP.

73. With regards to the operation stage, the majority of impacts at that stage are positive, relevant and permanent. It also features a strong environmental bias by attempting to improve the quality of water streams, leading to an improvement of water availability in the intervention area and in associated ecological conditions (aquatic fauna and flora), thus allowing for the sustainable use of water resources.

5.2 Social Analysis

74. The main characteristics of the municipalities in the Capibaribe river basin have been analyzed, as well as social indicators for eight municipalities located along the main river course and its main affluent, the Tapacurá river. In general terms, the analysis performed allows for the following considerations:

(i) The Capibaribe river basin concentrates a major part of the population of the State. (ii) The average per capita income of the area’s population, in the year 2000, was of

about 0.7 minimum wages, whereas 59% of the people lived with less than ¼ of a minimum wage per month on average in these municipalities.

(iii) The average child mortality rate (up to five years of age) in these municipalities is considered high (60 per 1,000) if compared with the state average of 54 per 1,000 and the nation-wide average of 39 per 1,000.

(iv) The municipalities that have been selected for implementation of wastewater systems feature a population with high social vulnerability and major deficits in sanitation services, without any wastewater collection or treatment systems.

(v) There is a high demand for improving environmental health conditions for the low income population, thus reducing their social vulnerability.

(vi) The low income population will benefit from the social tariffs adopted by COMPESA, which provides subsidies of up to 60% to those paying the minimum tariff.

(vii) The PSH-PE foresees the implementation of intra-household sewers for the low income population which, together with the subsidies above, will allow for the connection of this population to the new systems.

6. OVERALL PROJECT EVALUATION 75. From a more encompassing and strategic point of view, the set of proposed actions to be funded by the PSH-PE will positively affect a series of policies, plans and programs at the regional and metropolitan levels. They mostly address water conservation issues by considering both quality recuperation – which includes interventions for the de-pollution of rivers and springs – and quantity conservation interventions, through the control of losses in water supply systems. The whole set of interventions, in general terms, is expected to act as the inducer for actions and strategies associated to the water resources and sanitation plans (watershed plans,

Page 21: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

18

state and municipal sanitation plans, etc.), thus contributing to the strengthening of sector management tools.

POSITIVE EFFECTS

a) Improvement in the Quality of Water and the Environment 76. The treatment of causal factors – such as the withdrawal of affluent loads to the Capibaribe river and its affluent rivers through the implementation of wastewater systems with the appropriate treatment of effluents – is a key element to enabling a sizable improvement to the quality of water, thus leading to an effective reduction of expenditures with chemicals, and improving the water availability (in both quantity and quality), with direct effects upon the quality of life of the population residing in the region covered by the PSH-PE.

77. The recovery of water supply reservoirs also will provide for additional gains in environmental quality, enhancing health conditions and the balance of natural phenomena, maintaining aquatic life and the associated ecological processes (aquatic fauna and flora), thus allowing for the sustainable use of water resources in the Capibaribe river basin.

b) Improvement of the Infrastructure Network

78. The PSH-PE is in line with the Millennium Development Goals, through the improvement and expansion of water supply and sanitation infrastructure and services in highly populated areas, which is the case of the Capibaribe river basin. As such improvements under the proposed project, therefore, are evident and absolutely focused on the global improvement of health, environmental and urban development indicators.

c) Improvement of the Quality of Life of the Population and of Socio-economic Indicators

79. The process of construction of the proposed infrastructure promotes gains in terms of access to adequate public sanitation services, expanding the possibilities for access to wastewater systems, with direct impact upon the health of the beneficiary population. In addition, the poor will also benefit from the social tariffs adopted by COMPESA, which provide subsidies of up to 60% to those paying the minimum tariff, and also subsidizes the implementation of intra-household sewers.

d) Attracting investments and private capital, thus enhancing the competitiveness of these regions, in comparison to other urban centers

80. Enhanced water availability in the Capibaribe river basin can further promote and attract business activities and capital, thus strengthening the regional network of businesses, services, trade, etc., promoting the region’s economic and environmental sustainability. It should ne noted that the industrial textile hub in Toritama may also benefit from the development of industrial reuse of treated wastewater, which will allow for reduced costs of industrial water.

e) Consolidation of strategies for regional sustainable development and the protection of springs

81. The de-pollution of water courses in association with greater local and regional water availability complies with the requirements and guidelines established by national, state and regional environmental and water resource policies. In general terms, that represents a major

Page 22: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

19

progress towards the much-desired economic, social, environmental and institutional sustainability.

NEGATIVE EFFECTS

82. There are no relevant negative effects identified as the consequence of implementing this Project at the regional level. The main negative impacts refer to the local level, deriving mostly from actions related to the execution of the works and that can be mitigated through the adoption of appropriate project design and execution criteria and procedures. For that end, the adoption of criteria for the design and environmental assessment of planned interventions is foreseen, as well as the adoption of a Construction Environment Manual.

83. As mentioned earlier, the PSH-PE is an initiative that is closely linked to environmental recuperation and to improving the quality of life of the population of the Capibaribe watershed. Therefore, it is a set of actions and measures that aim to mitigate, minimize or compensate the existing socio-economic impacts, as well as to avoid new critical or negative situations, capable of jeopardizing the sustainability of this environmentally sensitive region.

84. Even though the Program initially did not foresee investments in developments that may require involuntary resettlement, the program must contemplate a conceptual framework that may take into account the adoption of appropriate technical and socio-economic actions, if necessary.

7. ENVIRONMENTAL MANAGEMENT PLAN 85. The PSH-PE Environmental Management Plan – EMP contemplates a set of actions and interventions aimed at ensuring the improvement of water resources in the Capibaribe river basin and at preventing, minimizing and compensating environmental and social impacts caused by project works and/or activities. Those interventions have a cost estimate of US$5.4 million. The EMP is organized into environmental and social policies and programs, a summary of which is presented below. The table also indicates the costs which are included in the project’s financing, as well as the institution accountable for each one of them.

Programs Costs (US$) Responsible

Agency or Body

Project Environmental Management Included in Project Management Costs

UGP & COMPESA

Criteria and procedures for the environmental assessment of projects

Included in Project Management

UGP

Social communication and sanitary and environmental education program

156,000 COMPESA

Adhesion campaign and program for the elimination of storm water infiltration into sewerage connections and of illegal sewer connection into storm water systems

Included in construction costs

COMPESA

Compensatory measures program 510,000 SRH/CPRH

Study on quality of water and alternatives for overcoming the eutrophication of the Jucazinho, Tapacurá and Carpina reservoirs.

120,000 SRH

Page 23: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

20

Pilot study on the reuse of lagoon effluents by agriculture 240,000 COMPESA

Strengthening of the monitoring of water quality in the Capibaribe watershed

175,000 CPRH

Strengthening of the watershed’s environmental management

500,000 CPRH

STP sludge management 250,000 COMPESA

Integrated operation of reservoirs and water collection for MRR and the Capibaribe river basin

325,000 SRH/COMPESA

Watershed environmental plan 2,900,000 SRH/CPRH

Toritama Environmental Plan 300,000 SRH/CPRH

Implementation of Resettlement framework Included in construction and management costs

SRH/COMPESA

Implementation of Environmental Construction Manual Included in construction costs

COMPESA

7.1 Institutional Arrangements for Environmental Management

86. The environmental management of the PSH-PE will be performed by UEGP and by the COMPESA Office for Engineering and Environment. The UEPG will be responsible for coordinating the Project’s social and environmental actions, COMPESA’s Engineering and Environment Office will be in charge of providing inspection, follow-up and guidance to the execution of mitigation measures required under the environmental licenses and the recommendations of the environmental assessments undertaken, which are specific for each sub-project; for the environmental oversight of the works, following up on the implementation of the Environmental Construction Manual.

87. In order to fulfill these tasks, the UEGP structure will include an environment expert in its team and count on the support of the environment consultants of the company supervising the works to be hired by COMPESA, who shall be summoned to act whenever necessary. The company supervising the works also shall count with a team for the environmental construction oversight, which will be responsible to ensure the application of the Environmental Construction Manual. This team will act in accordance with the guidelines of the COMPESA Office for Engineering and Environment and the Environmental Construction Manual.

88. The costs of such management activities are included under Component 1 – Management and Institutional Development. The specific costs of mitigating measures for each subproject shall be stated under the corresponding subprojects, as an integral part of the proposed intervention, whenever required by the licensing bodies.

89. Below the Project’s main Environmental Management tasks are presented:

• Coordination of Environmental Management, carried out by UEGP, that will be responsible for the socio-environmental actions of the project, in due coordination with

Page 24: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

21

the COMPESA’s Office for Engineering and Environment and with CPRH – the State Environment Agency.

• Environmental Oversight of Works, carried out by the work supervision company, who will be accountable for the inspection, follow-up and guidance of environmental actions related to the Environmental Construction Manual – ECM and the mitigation measures established by the environmental licenses and in the EMP.

• Environmental Planning of Works. The actions for the environmental planning of works are the responsibility of the construction companies, who must comply with the Environmental Construction Manual and implement the mitigation measures stated in the environmental licenses and in the works’ Bidding Documents.

7.2 Criteria and procedures for detailed project design and environmental assessment

90. The EMP sets technical-environmental criteria to be observed by COMPESA during project design and in their assessment by UEGP. UEGP shall adopt socio-environmental procedures during the execution of the project, involving the following stages:

• Phase A – Detailed Engineering Design (Concept and Engineering Designs) for Components 2 and 3. During the detailed engineering design, the following procedures must be complied with:

9 Socio-environmental criteria for the drafting of designs; 9 Environmental licensing for projects; 9 Outreach communication and consultation; 9 Environmental report, in compliance with the Bank’s environmental and social

safeguards.

• Phase B – Project Implementation (works). Procedures regarding the Environmental Oversight of Works shall be adopted during the implementation of the project (works).

91. During the PSH-PE execution, it is mandatory that all works planned under the project undertake environmental studies in strict compliance with national and state legislation, the environmental licensing rules and the environmental guidelines of the World Bank, based on detailed information contained in the feasibility studies and detailed designs to be prepared during this phase. To that effect, in addition to the environmental documents required for the environmental licensing of each intervention, an environmental assessment shall be prepared aimed at analyzing the compliance to the World Bank environmental and social safeguards.

92. Such assessment shall be collated into specific reports to be submitted to the World Bank for approval and the issuing of a “No Objection” statement, prior to continuing with studies, bidding procedures, start of works, etc.

93. Due to the specific environmental assessments to be carried out by the development, mitigation and compensation or enhancement measures shall be indicated, which will integrate an environmental management plan specific for the development and included in the project costs.

Page 25: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

22

7.3 Social Communication and Sanitary and Environmental Education

94. The purpose of this activity is to contribute to the implementation of the project by involving the population that is either directly or indirectly affected by the interventions, as well as those living in areas of project influence. The communication plan is geared toward actions that are related to the co-existence of the population with the works to be implemented, which should be developed in an integrated fashion to the proposed objectives can be achieved. UEGP and COMPESA are responsible for this activity.

7.4 Program for adhesion to the wastewater system and elimination of illegal connections

95. This program plans to carry out information and education interventions, aiming to promote the value of treated water and of the appropriate destination of domestic wastewater. For this purpose, it will raise the awareness and inform the population about the importance of households adhering to the system, provide guidance on how to use it correctly, and the deadline for doing so, in order to ensure the benefits from the implementation of domestic wastewater collection and treatment services materialize. On that occasion, clients will be informed about the financial costs generated by the maintenance of services to be delivered.

96. After households have been connected to the wastewater collection network, clients will receive instructions on the system’s proper use, so as to ensure its durability, as well as the quality of services being delivered. During this stage, the message on the project benefits (by completing the works and the adhesion of households to the network) will be re-enforced to beneficiaries, encouraging the adoption of appropriate system maintenance procedures. This activity is the responsibility of COMPESA.

97. The population benefiting from the implementation of water supply services also must be made aware of the importance of using water rationally, as well as of maintaining and conserving public installations.

98. With regard to the elimination of illegal connections, the project has two main goals: (i) the identification, registration and transfer to the wastewater collection network of the whole sewer (household connection) that is connected to the rainwater drainage systems; and (ii) the identification, registering and elimination of any rainwater that may flow into the wastewater collection network.

7.5 Compensatory measures program

99. Comprises the allocation and use of US$450,000, which represent 0.5% of the planned wastewater systems works to be implemented in the Capibaribe river basin, in accordance with the SNUC Act, which establishes this minimum percentage as environmental compensation to be invested in Conservation Units. According to negotiations held with CPRH, the value of environmental compensation shall be proposed for destination to State Conservation Units, including areas in the caatinga biome. The definition of the allocation is the responsibility of the Council for Environmental Compensation. SRH and CPRH must agree on the destination of funds.

Page 26: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

23

7.6. Study of the quality of water and alternatives for minimizing the eutrophication of the Jucazinho, Tapacurá and Carpina

100. A more in-depth analysis of the data on water quality of the Capibaribe river basin and of preliminary eutrophication simulation studies shows a rather severe picture in regard to the evolution of eutrophication of reservoirs that supply the Capibaribe river basin, with a high incidence of cyanobacteria, especially in Carpina and Tapacurá.

101. The results of the existing simulation indicate the need to remove 89%, 64% and 73% of phosphorus from cities located upstream from the Tapacurá, Jucazinho and Carpina reservoirs, respectively, in order to reduce existing eutrophication tendencies. Nevertheless, the simulation only considered the volume of domestic wastewater, without considering the volume deriving from the drainage of urban, and agricultural areas, in addition to areas with vegetation and the industrial load.

102. Therefore, the performance of a more detailed and in-depth study of the river basin is being proposed, with a simulation of the quality of water on along the basin and of the eutrophication of reservoirs. In addition to an assessment of the operational capacities and characteristics of each reservoir, these simulations also must analyze several alternatives for reducing the volume of phosphorus, including for farming areas, and alternatives for wastewater treatment typologies, with the nutrient removal, including implementation, operation and maintenance costs, as well as non-structural alternatives (e.g., operation of reservoirs).

7.7 Pilot Study on the re-use of effluents

103. As one of the treatment alternatives to be considered for some cities in the river basin – where treatment will be performed through the use of lagoons – is the re-use of effluents for farming activities. An in-depth study on its technical, economic and environmental feasibility is being proposed. Its results should include technologies to be adopted (micro-sprinkler, drip irrigation, etc.) and the removal of nutrients, in addition to benchmarks for implementation and operation costs. Reuse of treated wastewater may also be considered and assessed for industrial use, particularly for the Toritama textile industrial hub.

104. This study should be carried out by COMPESA, either at the WWTP of Vitória de Santo Antão or of Toritama, with support from the university or of the Pernambuco Agronomic Institute. This study should be undertaken immediately after loan agreement is signed with the World Bank.

7.8 Strengthening water quality monitoring in the Capibaribe river basin

105. One of the project objectives is to improve the water quality monitoring system of the Capibaribe river basin, with a view to use it as an instrument for environmental management and water resource management, costs are estimated at US$ 175.000,00.

7.9 Strengthening of Environmental Management in the river basin

106. This activity comprises the structuring of an integrated unit for environmental Management – IUEM of the Capibaribe and Ipojuca river basins. The objective is improve the operational structure of the Integrated Management Unit in the Municipality of Caruaru for the

Page 27: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

24

effective environmental control (licensing, inspection and monitoring) within the area of the Capibaribe and Ipojuca river basins, with special attention to (i) the textile and clothes manufacturing industries at the “Jeans Hub” established in the municipalities of Caruaru, Belo Jardim, Toritama, Riacho das Almas and Santa Cruz do Capibaribe; (ii) to the disciplined use and occupation of land, especially for those developments and activities located at the banks of the aforementioned rivers; and (iii) the sanitation projects foreseen under the Hydro-environmental Plans.

7.10 WWTP Sludge Management

107. The sludge generated from the operation of the wastewater treatment plants to be implemented in the watershed must be properly disposed of. One of the alternatives is use by agriculture, as long as it meets existing technical and environmental standards. The rehabilitation of existing and building of new wastewater collection networks and wastewater treatment plants will follow the Brazilian technical design standards and CPRH and CONAMA standards for the quality of discharged effluent and sludge disposal, including continuous monitoring of treated wastewater and sludge reuse. In addition, proposed standards will be in line with IFC/World Bank Group Environmental, Health and Safety Guidelines for wastewater and Environmental Water Quality. Only small- and medium-sized wastewater treatment facilities will be built, which reduces the technical complexity of these interventions. The current program intends to support COMPESA’s efforts by means of an agreement to be signed with the Pernambuco Company for Agricultural Research (IPA) for the development of studies and research on the agricultural and forest use of WWTP sludge.

108. The main objective of this agreement is to identify and characterize the criteria for the agricultural and forest use and management of the WWTP sludge and to prepare a Manual on the Use and Management of Bio-solids in the State of Pernambuco. The agreement is estimated to last for a 2-year period, with planned costs of US$250,000.

7.11 Integrated operation of reservoirs and other surface water sources for the MRR and the Capibaribe river basin

109. To be defined under Component 1 – Management and Institutional Development. A summary of this program is included herein due to its importance to the recuperation of the quality of water at the reservoirs/dams in the river basin.

7.12 Environmental plan for the river basin

110. Under the PROÁGUA program, a study regarding the Environmental Plan for the Capibaribe river basin is currently being prepared. The study will comprise a diagnosis, the identification of sustainable scenarios and tendencies, elaboration of investment plans, and development of a systematized database, aimed at the revitalization and reversal of the degradation processes under way in the river basin, in order to improve the quality and quantity of water available.

111. This plan will feature an investment plan for the river basin, containing feasible proposals aimed at reversing the degradation process of natural resources currently under way in the Capibaribe river basin. As such, it will give priority to improving the quality and quantity of

Page 28: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

25

water so as to ensure social, economic and environmental sustainability, always including the effective participation of the community, by means of a social and environmental agenda for mobilization and environmental education. A draft Environmental Plan is scheduled to be completed by the end of 2009. The proposed project has allocated about US$2.9 million to be invested in the interventions proposed by the Investment Plan.

7.13 Toritama Urban Environment Plan

112. This plan consists in the drafting of a Regional Environmental Assessment Study that will analyze the accelerated and disorderly process of urban and population growth of the municipality of Toritama, mostly due to the implementation/consolidation of the local clothing manufacturing hub (Productive Local Arrangement) in the region known as Agreste Pernambucano and its environmental sustainability, due to the region’s natural and socio-economic characteristics.

113. For this purpose, the Urban Environmental Assessment Study shall assess the infrastructure conditions of the clothing sector and the industrial contamination of the soil and water resources that are verified today. The study shall complement and provide further details on the actions planned under the Environmental Plan to be prepared for the river basin, thus allowing for the appropriate design of physical interventions and the institutional coordination to be carried out by PSH-PE, focusing on wastewater and the control of industrial pollution. The study should also consider the possibility of reuse of treated wastewater from WWTP by the local clothing manufacturing hub.

7.14 Resettlement Framework

114. In order to ensure the implementation of wastewater infrastructure receives appropriate treatment in case the settlement of population and/or compensation for businesses and land is required, the EMP provides a framework for resettlement.

115. This Resettlement Framework covers the following content: (i) characteristics, objectives and rationale of developments associated to the need for displacement; (ii) foundations and guidelines of the Service Policy; (iii) criteria for eligibility; (iv) legal framework; (v) institutional arrangements for resettlement; (vi) mechanisms for serving communities and public consultations; (vii) costs and timeframes; (viii) proposal for ex-post monitoring and evaluation methodology; (iv) definition of minimum content for preparing a Resettlement Plan.

116. There is a local office next to the construction mobilization area aimed at providing support to the affected families in an easily accessible location, next to the community and with experts available full time, every day of the week. It is also through this local office that the community counts with a team and customer service structure to deal with possible complaints from the population. This structure is capable of not only receiving the complaints but also to forward them and present adequate responses given pre-established deadlines.

117. The foreseen mechanism for resolving complaints, includes the following decision levels: (i) a large portion of the complaints are expected to be resolved locally; at this level the main actors are: the families residing in the area, the social workers and the COMPESA engineers; (ii) when the complaints are not resolved at the local level, the project coordination unit located at

Page 29: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

26

the premises of the COMPESA is involved in the process; (iii) the complaints that are not resolved by COMPESA will be referred to the Overall Project Management Unit located at the state level (SRH and COMPESA), more specifically to the social responsibility unit at COMPESA and to its ombudsman, (iv) as a last resort, pending unresolved complaints can be referred to the World Bank.

118. Therefore, complaint resolution will initially be addressed through the presence of social workers at the local office on the construction site, with the possibility that the person/family lodging the complaint can have access to COMPESA’s social responsibility unit and ombudsman, in order to try to negotiate an adequate solution internally. It is important to note that COMPESA is subject to independent regulation by the Pernambuco State Regulatory Agency, and that this institution also has its own ombudsman office. Therefore, in case a negotiated solution is not agreed upon at COMPESA’s level, there is still the possibility of referring the complaint to the ombudsman office of the Pernambuco Sate Regulatory Agency. The social work to be undertaken will include making the communities aware of the above mentioned recourse mechanisms.

7.15 Environmental Construction Manual

119. So as to ensure that the works do not cause environmental degradation, a document has been prepared to be adopted as a guide on appropriate environmental practices to be complied with by contracted companies for the execution of wastewater works. This document – the Environmental Construction Manual – will be incorporated into the bidding processes so that the companies may be aware of its conditions beforehand and it will become a contract requirement. Its implementation is the responsibility of UEGP, COMPESA and the construction companies.

120. The Environmental Construction Manual contemplates:

9 The Project’s socio-environmental management system, already described under item 1 of the EMP.

9 Environmental actions and rules regarding the implementation and management of works, which covers a plan for living with the works: (i) construction sites; (ii) risk management and emergency actions on the construction site; (iii) environmental education for workers and code of conduct at the construction site; (iv) on-site health and safety; (v) waste management and disposal; (vi) noise control; (vii) equipment patio; (viii) traffic control; (ix) service roads.

9 Environmental actions and rules related to construction activities, depending on the type of selected developments.

9 A plan for the control and rehabilitation of areas used for disposal of excavated material.

8. Public Consultation

121. The first public hearing on the PSH-PE was held on September 2, 2008, in Recife, to provide input to the Terms of Reference for contracting the Project Environmental Assessment report, to be financed by the World Bank. The Hearing was held at the Capibaribe Basin Committee (COBH-Capibaribe), which called a special meeting for this end and enjoyed significant member participation. The Hearing comprised the presentation of the PSH-PE

Page 30: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

27

Concept and the minutes of the terms of reference for the social and environmental assessment. Participants were divided into three groups: (i) defining the current situation; legal and institutional framework; and (iii) social and environmental assessment. Results were presented and discussed with the whole group and resulted in the consolidation of the terms of reference for the contracting and drafting of the PSH-PE Environmental Assessment Report.

122. The Second Public Hearing on the PSH-PE was held by the State Water Resources Office (SRH) on April 16, 2009. This second hearing sought to discuss once more the concept of the PSH-PE, present intervention priorities, particularly in the Capibaribe river basin, and present the Project Environmental and Social Assessment Study.

123. The announcement of the Public Hearing was made directly by SRH, which invited participants in from the first hearing, members of COBH-Capibaribe, officials from other basin committees in Pernambuco and mayors’ offices. The Executive Secretariat of the Capibaribe Basin Committee (COBH-Cabiparibe) invited all its members through Announcement no. 15 (March 31) and no. 18 (April 13). The latter announcement included the draft Executive Summary.

124. Additionally, SRH kept an announcement on the public hearing on its website since April 7, also making available the executive summary and the full version of the Draft Environmental and Social Assessment.

125. Fifty-one people took part in the Public Hearing, among them members of COBH/Capibaribe and other entities and NGO invited, especially mayors’ offices.

126. The hearing was organized to include the presentation of the Pernambuco Sustainable Water concept and the environmental and social assessment undertaken, discussion with the whole group, organization of issues raised, and presentation of results panel. The hearing had intense participation from those present and made it possible to clarify many issues which concerned participants, with queries fully answered by the commission of consultants and managers. In sum, the foci of the main themes addressed in the Hearing were the following items:

(i) Water quality in the Capibaribe river and the eutrophication of reservoirs used for public water supply, with the need for removing phosphorus and possible agricultural re-use;

(ii) The issue of Toritama, with the need for carrying out regional and sectoral studies (jeans production chain) and the possibility of reusing treated effluents in the industrial process.

(iii) The Hydro-Environmental Plan being developed (raised as a separate issue not directly integrated into the Basin Plan) and the need for greater clarity as to its necessary coordination with local/regional plans and with the programs suggested in the Project Environmental Management Plan.

(iv) The strategic project bank, and the need to develop sanitation projects (water supply and sewage) which comply with the requirements and guidelines of different sources of financing.

(v) Application of the “social fee”, necessary in sewage service provision.

Page 31: GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat ...documents.worldbank.org/curated/en/... · GOVERNMENT OF THE STATE OF PERNAMBUCO State Secretariat for Water Resources PERNAMBUCO

28

(vi) The need for constant institutional coordination, especially between UEGP, CPRH and COBH-Cabibaribe, throughout PSH implementation.

(vii) The need for coordination between the many PGA programs during PSH-PE execution, to be carried out by UEGP.