    ChineseorEuropean?Capitalandoperatingcostimplicationsfor

    newcementplantprojects

    MarkMu'erManagingDirector

    JAMCEMConsul7ng

  • 7/28/2019 Global Cem Power 2012 Mutter

    3/20

    Disclaimer

    Noulteriormo7vetryingtopresentabalancedcase

    Basedonpersonalexperienceplusexperiencesofthosewhohavebuilt,commissionedandoperatedcementplants.

    Bothtypesofsupplierarereceivingsignificantorders

    Chinesesuppliedplantsnowhaveahistory

    Aimistoassistcementmanufacturersintheirdecisionmakingprocess

  • 7/28/2019 Global Cem Power 2012 Mutter

    4/20

    ChineseorEuropean?.....

    Historyofcementplantsupply

    Iden7fica7onofothercostswithChinesesuppliedplants

    Comparisonoftotalcapitalcostsforprojects

    Calcula7onofNPVandIRRforvariousscenario

    Conclusions

  • 7/28/2019 Global Cem Power 2012 Mutter

    5/20

    Historyofsupply

    Tradi7onalcementsuppliershavegenerallybeenEuropean

    Technicaldevelopments1920s-LepolgratepreheaterPolysius

    1930s-CyclonepreheaterpatentedbyFLS

    1950s-CyclonepreheatersinstalledbyKHD

    1990s-CoolerfixedinletdevelopedbyIKN

  • 7/28/2019 Global Cem Power 2012 Mutter

    6/20

    Historyofsupply

    Li'leknownofChinesecementindustryun7l1990s

    MajorplayersinvestinChinesemarket

    Chineseequipmentsuppliersentertheglobalmarketin2000s

    Achievedsignificantmarketshareinshort7me

    MixandmatchofEuropeanandChinesesupply

  • 7/28/2019 Global Cem Power 2012 Mutter

    7/20

    ReviewofChineseplants

    Widerangeofviews

    Posi7ves:

    Highlysa7sfied

    Chinesesuppliershighlywillingandobliging

    Plantstendedtoreachtheirguaranteedperformancelevels

    Nega7ves:

    Poorinstalla7on

    Weakdocumenta7on

    Delayedstart-up

    Failureofkeyequipment

    Whysuchdifferencesinviews?

  • 7/28/2019 Global Cem Power 2012 Mutter

    8/20

    OtherCosts

    Sa7sfiedcustomersappeartohaveiden7fiedweaknessesinChinesesupply

    Areasthatneedtobeaddressedtoincreasethechancesofsuccessfulproject

    TechnicalReview

    Contractdefini7on

    ProjectmanagementEquipmentinspec7ons

    Documenta7onandtraining

  • 7/28/2019 Global Cem Power 2012 Mutter

    9/20

    Othercosts

    Technicalreview

    Toensurethat

    -equipmentspecifica7onsarecorrect-fullrawmaterialinves7ga7onsarecomplete

    -materialshandlingdesigninadequate

    -equipmentdesignmeetslocalstandards

    Cost:$0.5million

  • 7/28/2019 Global Cem Power 2012 Mutter

    10/20

    Othercosts

    Contractdefini7on

    Toensurethat:

    -thetermsandcondi7onsofthecontactarelegallydefined-realis7c7me-scaleandmilestonesareputinplace

    -penal7esforbreachofcontractareputinplace

    Cost:$2million

  • 7/28/2019 Global Cem Power 2012 Mutter

    11/20

    Othercosts

    Projectmanagement

    Toensurethat:

    -theClienthasateamtomonitorandsupervisetheinstalla7onoftheplant

    -qualityofinstalla7oniscorrect

    -noshort-cutsaretakenforexampleinHealthandSafety,

    loadtes7ngetc.

    -projectmilestonesaremet-risksareiden7fiedandmanaged

    Cost:$6million

  • 7/28/2019 Global Cem Power 2012 Mutter

    12/20

    Othercosts

    Equipmentinspec7ons

    Toensurethat:

    -equipmentismanufacturedtospecifica7on-correctequipmentisshippedtosite

    -QAsystemsareadequate

    -manufacturerss7cktotheirQAsystems

    Cost:$1million

  • 7/28/2019 Global Cem Power 2012 Mutter

    13/20

    Othercosts

    Documenta7onandtraining

    Toensurethat:

    -theClientreceivesafullsetofworkingdocumentsfortheplant

    -theplantpersonnelareadequatelytrainedintheopera7on

    andmaintenanceoftheplant

    Cost:$0.5million

  • 7/28/2019 Global Cem Power 2012 Mutter

    14/20

    Othercosts

    Item Cost

    Technical review $0.5 million

    Contract definition $2 million

    Project management $6 million

    Equipment inspections $1 million

    Documentation andtraining

    $0.5 million

    Total $10 million

    Therearenomiracles,thebigplayers(cementequipmentsuppliers)are

    managingtherisksandasacustomerwearepayingapremiumforthoserisks.

    Thisiswherethesavingsare,ifyourenotreadytomanagethoserisks,itis

    be'ertodealwiththebigplayers

  • 7/28/2019 Global Cem Power 2012 Mutter

    15/20

    Capitalcostcomparison

    Parameter Value

    Clinker capacity 3000 tpd

    Design runtime 90%

    Clinker factor 0.85Cement capacity 1,160,000 tonnes

    Cost per tonne Total costEuropean $150 $174 million

    Chinese $112.5 $130.5

    Chinese plus others $140.5

  • 7/28/2019 Global Cem Power 2012 Mutter

    16/20

    CalculationofNPVandIRR

    Comparisonofcapitalcostsdemonstratesthepoten7alsavingwithChinesesupply

    Useoffinancialanalysistoaiddecisionmakingprocess

    Createanumberofdifferentscenariotoevaluatefinancialimpact

    Otherfactorsmustalsobeconsidered

  • 7/28/2019 Global Cem Power 2012 Mutter

    17/20

    CalculationofNPVandIRR

    Parameter European Chinese 1 Chinese 2 Chinese 3

    Capital cost ($ million) 174 140.5 140.5 140.5

    Kiln runtime (%) 90 90 80 80

    Margin ($/tonne) 30 30 30 25

    Plant life (years) 30 30 30 30

    NPV ($ million) 217.6 251.1 207.6 149.6

    IRR (%) 20 25 22 18

  • 7/28/2019 Global Cem Power 2012 Mutter

    18/20

    CalculationofNPVandIRR

    Run7meandmarginclearlyhavingamajorimpact

    Otherscenariocanbeconsidered-Shorterplantlife

    -Addi7onalcapitalthroughoutplantlife

    -Furtherreduc7oninmargin

    Financialanalysisshouldbejustoneofthetoolsinthedecision

    makingprocess

  • 7/28/2019 Global Cem Power 2012 Mutter

    19/20

    Conclusion

    Chinesesuppliedplantswouldappeartobethecheaperplant

    Addi7onalcostsneedtobeaddedbackintotheChinesesuppliedprice

    Scenarioanalysiscanassistinthedecisionmakingprocesswhenchoosingasupplier

    Otherfactorsmustbeconsidered-Availabilityofcapital

    -Costoffuelandlabour

    -Sparepartsstrategy

  • 7/28/2019 Global Cem Power 2012 Mutter

    20/20

    ChineseorEuropean?Capitaland

    operatingcostimplicationsfor

    newcementplantprojects

    MarkMu'erManagingDirectorJAMCEMConsul7ng