Gettign the Most Out of the Clean Room Design

  • Upload
    lw1735

  • View
    212

  • Download
    0

Embed Size (px)

Citation preview

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    1/10

    652 2005 ASHRAE.

    ABSTRACT

    This paper discusses the design of cleanrooms anddescribes a five-step process that developes the informationneeded to identify, clarify, and prioritize cleanroom require-

    ments.

    INTRODUCTION

    When building a cleanroom facility, special attentionshould be given first to the essential tasks for defining clean-room requirements, specifically determining cleanroom areas,building areas, filtration coverage, airflow quantities, powerconsumption, and budget items.

    Think of design activities asproblem solvingand program-ming activities asproblem seeking. Programming develops thebody of information needed to identify, clarify, and prioritize thecleanroom requirements. The key to developing a goodprogramming process is being able to manage tremendous

    amounts of data. This can be accomplished by creating a matrixof different types of preliminary information. One excellentapproach is an organized, methodical, five-step process called,

    problem seeking.Five quantitative project elements are produced during

    the programming process.

    1. Process Tool List.This initial information platform drivesutilities, areas, and cleanliness levels.

    2. Space List. An analysis of functional areas.

    3. Utility Matrix.An analysis of services to each of the processtools for including process cooling, exhausts, pure water,gases, and bulk chemicals.

    4. Project Budget. The description of anticipated project-

    related costs prior to design.5. Project Schedule. The description of project milestone

    dates outlining major activities and approval-submittaltargets.

    Tools, people, activities, equipment, storage, and efficien-cies generate the area requirements. The numbers of peoplethat will work in the project require workspace, circulationspace, gowning space, offices or desk space, and parking

    space.Perhaps the forgotten type of space in any building is stor-

    age space. Particularly in a cleanroom, clean storage isrequired for material, chemicals, equipment, WIP storage, andmaintenance.

    Beyond this, the efficient use of space in terms of walls,structure, chases, etc., will greatly affect the total area AND,hence, the total cost, of a cleanroom. Another often over-looked space requirement is additional space for new tools orequipment in the near future, say two to five years.

    The process of programming is the management of allpreliminary project data. To make this as easy and as organizedas possible, the five-step process called problem seeking hasproven very successful. In each of the following five steps,

    different types of information are developed and analyzed.The order is a natural progression of developing data withouthaving to retrace your steps. Validation of the data is always anintegral part of the process and allows for feedback and eval-uation loops.

    THE FIVE-STEP PROCESS

    Establish Goals

    First, establish the objectives for constructing the clean-room. Clearly delineating the project goals is one of the mostoften neglected contributions upper management can make toa project. Originating from upper management, 10 to 20 well-stated objectives will have an extremely positive effect on the

    outcome of your cleanroom project. Goals provide a set ofclear expectations for the project team that parallel thecompany's business plan. The goals should deal with each ofthe four considerations of cleanroom design:

    Getting the Most Out of a Cleanroom Design

    Thomas E. Hansz, AIA

    Thomas E. Hanszis president of Facility Planning and Resources, Inc., Pittsburgh, Pa.

    DE-05-9-3

    2005, American Society of Heating, Refrigerating and Air-Conditioning

    Engineers, Inc. (www.ashrae.org). Reprinted by permission from ASHRAE

    Transactions, Volume 111, Part 2. The material may not be copied nor distrib-

    uted in either paper or digital form without ASHRAEs permission.

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    2/10

    ASHRAE Transactions: Symposia 653

    FunctionAspects of activities, relationships, people,and operations.

    FormPhysical considerations of form, space, and sys-tems.

    EconomyAspects of construction costs, life-cyclecosts, and energy.

    TimeConcerns the project schedule, expansion, andchange.

    Analyze Facts

    The second step in the programming process requires

    establishing a database of cleanroom information. Accurate

    staffing projections for cleanroom personnel should be devel-

    oped. Information regarding all manufacturing equipment

    should be assembled. Utility bills for the preceding 12 months

    will be very useful and should be assembled. In short, all the

    information that will give the architects and engineers a thor-

    ough knowledge of existing conditions should be assembled

    now. At the end of this paper is a suggested list of typical infor-mation that should be given to the programming consultants to

    initiate gathering of facts.

    For processes using hazardous production materials, an

    accurate inventory of chemicals will be required to satisfy the

    fire code and building code regulations. Another critical area

    of analysis, which should be done during the fact-gathering

    step, is the building code analysis. Whatever building code is

    in force, your cleanroom will be regulated as to how large an

    area it can be, how high the roof can be above it, how many exit

    doors will be required, and to some extent what the layout will

    be to ensure occupant safety in case an emergency should

    arise. Cleanrooms using hazardous production materials

    (HPMs) will be required to have separate routes for peoplecirculation and for the movement of HPMs. Exit distances

    from any point within the cleanroom may be as short as 75 ft.

    Walls surrounding the cleanroom will be required to meet

    specified fire resistance.

    Cleanroom Concepts

    Before the start of design, the project team should exam-

    ine concepts applicable to work flow, flexibility, utility distri-

    bution, and other such issues. The team should address what

    types of changes can be anticipated. Will additional equipment

    or improving the classification of contamination control be a

    real possibility in the future? The predictability of the cleanenvironment should be examined as well. All this should be at

    least addressed if not resolved before the design effort gets

    underway.

    Production or research engineers should determine prod-

    uct contamination sensitivity by this time. If not, it needs to be

    a first priority, along with establishing a flow chart identifying

    cleanroom functions and their required level of control.

    Beyond controlling the particulate counts, the production

    process may also require specific temperature, humidity, and

    pressure levels with fixed limits of variance. How to provide

    the level of control is answered during the design phase. Now

    is the time to establish the control criteria.

    DETERMINE PROCESS REQUIREMENTS

    The Relation of Process to Facility

    Cleanrooms in themselves are not aesthetic features but

    are adjuncts to specialized activities that must be conducted in

    clean environments. Cleanroom concepts are therefore depen-

    dent upon the level of cleanliness required and upon the type

    and scale of the activity. Each successively cleaner environ-

    ment requires stricter operating procedures, or protocols, to

    maintain that cleanliness level. The strictest protocols may

    require clean buffer zones to isolate the cleanest areas from

    less clean environments or from office environments. These

    Table 1. Potential Cleanroom Issues

    Process Facility People

    Equipment Organization Safety

    Work flow Flexibility Gowning

    Material flow Site services Aesthetics

    Automation Functional relations Work socialization

    Technology Contamination control Productivity

    Process utilities Aseptic conditions Communications

    ESD Reliability Interaction

    EFI/RFI Redundancy Home base

    JIT inventories Vibration Orientation

    Energy Waste treatment Facility image

    Tool installation Storage Security

    Figure 1 The five-step process.

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    3/10

    654 ASHRAE Transactions: Symposia

    protocols and the nested space configurations have defining

    effects on personnel circulation, process flows, material

    movement, maintenance activities, new equipment installa-

    tion, and old equipment decommissioning.

    Materials and equipment must be meticulously wiped

    down during their staged entry. Other supplies, which were

    produced and packaged in a cleanroom, will be delivered indouble-sealed bag enclosures for protection from the outside

    world during shipment and handling. These double-bag enclo-

    sures must be wiped and sequentially be removed as they

    progress through the staged entry.

    Avoiding unnecessary cleanroom traffic, greater quality

    control, safety, and lower unit costs for bulk raw materials are

    factors that compel facilities to pipe or convey materials to

    their cleanroom processes. As usage quantities increase,

    frequent handling of chemicals, gases, and process wastes

    increase exposure hazards for the workers and contamination

    hazards for the cleanroom.

    The risks imposed by chemicals and gases vary with

    material properties and concentration. The most universallyaccepted procedure for assessing and identifying relative

    chemical hazards was developed by the National Fire Protec-

    tion Association (NFPA) for safeguarding emergency

    response personnel. Published as NFPA Standard 704, this

    system of identifying hazards rates each chemical on a scale of

    0 to 4 in three hazard categorieshealth, flammability, and

    instability. Nearly all chemical containers and tanks are

    required to display the NFPA 704 diamond, which identifies

    the hazard ratings.

    Process Equipment and Process Support Services

    A key to developing a meaningful and useful program is

    to gather as many facts as possible, especially about the activ-

    ities and processes. For example:

    What are the processing goals?

    What are the hours of operation?

    What are the process steps and how does the work flow?

    How should work-in-progress be managed?

    What are the most critical steps in the process?

    What is the philosophy for maintenance and outages?

    How should expansion and future changes be accommo-

    dated?

    THE UTILITY MATRIXFor market-driven products, such as pharmaceuticals and

    semiconductors, the clients process assumptions are typically

    being refined concurrently with the programming and early

    design stages. Frequently complete equipment lists are not

    available. In the interim period, data for similar equipment

    may be used or assumptions may be made. The important issue

    is to develop a comprehensive database to record information

    and assumptions and to track the changes as design and

    construction proceed. To compound the complexity, major

    pieces of equipment frequently have auxiliary or support

    equipment. In the concept development phase, optional equip-

    ment configurations must be explored for fit, operational func-

    tions, and accessibility.

    Cleanroom facilities are typically intensive users of

    equipment and therefore are large consumers of utilities and

    raw materials. Frequently auxiliary or support equipment has

    separate utility services. The equipment database should bestructured in a manner that allows utility and raw material

    consumption data to be associated with each process tool and

    each piece of auxiliary equipment.

    This technique has several advantages:

    Data may be sorted by equipment to show or to change

    basis.

    A sort by utility or raw material will give demand at

    100% utilization.

    As equipment is grouped into areas, a utility sort on the

    equipment groupings will indicate use patterns that may

    aid distribution decisions.

    If process equipment is to be added in phases, the data-base will allow the engineers to study expansion options

    for central utility systems.

    During the course of the project, as equipment lists are

    refined, having a database will allow project managers

    to identify scope changes.

    Depending on the projects size assembling, these data

    can be a huge effort. So, can a project be programmed and

    designed without a utility matrix? Perhaps one can, but these

    facilities are both complex and expensive. Without sufficient

    data, even experienced professionals will have difficulty

    guessing and will have no way of knowing whether the esti-

    mates are high or low. Too low an estimate will lead to insuf-ficient capacities, and too high an estimate will result in

    expensive overbuilding.

    There may be as many individual ways to organize the

    data as there are people collecting it. Some of the most

    successful techniques are:

    Supplying special data collection forms for each piece

    of equipment to the owners process engineers or equip-

    ment users for recording equipment data.

    Using the owners anticipated equipment list and exist-

    ing engineering database.

    Using the owners equipment list and consultants data-

    base. Assembling a notebook of data sheets from the owners

    equipment operations and maintenance manuals.

    Assembling a notebook of vendor-supplied data.

    Hard copies are good for record keeping, but when it

    comes to sorting, summing, editing, and transferring all or part

    of the data, electronic copies have an overwhelming advan-

    tage. Some of the methods in the preceding list may involve

    handling the data twice, i.e., recording on forms, then entering

    into electronic files.

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    4/10

    ASHRAE Transactions: Symposia 655

    When collecting data, particularly from vendor sources,

    make sure that the data represent actual consumption data and

    not the nominal service capacity, which does not represent

    utility usage. For example, many vendor data sheets list for the

    electrical utility requirements the electrical service, 20 amps at

    120 volts, rather than the connected load, which may be only

    300 watts or 2.5 amps at 120 volts. Accumulated data errors

    such as this could dramatically distort demand requirements to

    the entire facility.

    Once the utility and raw material data have been

    collected, one critical task remains. If one were to sum the

    flows or consumption of each utility or raw material, the total

    demands would be far greater than those actually experienced.

    What is missing is an accounting of

    down time for scheduled maintenance and cleaning,

    idle time for lags in work-in-progress flow,

    wait time for process step sequencing, and

    unexpected outages or breakdowns.

    This accounting is usually incorporated as an efficiency

    factor. Since most manufacturing facilities operate around the

    clock, the most common basis for evaluation is 24 hours. If the

    mean time between failure (MTBF) is over 1000 hours for

    minor incidences, nonproductive time due to breakdowns

    would be less than one percent, which is negligible. However,

    a piece of equipment may need to be shut down once a shift,

    or once a day, for shift change, cleaning, or preventive main-

    tenance. If such downtime lasted two hours, available uptime

    would be 92%. Equipment waiting cumulatively eight minutes

    every hour for lags in work flow would be working 87% of the

    available time. If the equipment sequentially processes the

    work in four steps and the utility of interest is used in only

    three of the four steps, the utility would be consumed only

    75% of the equipments operating time. As a result the total

    utility consumption by this single tool would be 60% (0.92 *

    0.87 * 0.75) of the tabulated peak demand.

    Considering group equipment operations, if one of six

    tools is not operating in sequence with the others, then the

    average utility consumption would be 83% of the single tool

    usage. Applying this operational diversity factor to the single

    tool consumption as illustrated above, the average utility

    consumption would be 50% (0.83 * 0.60) of the published util-

    ity consumption data.

    Working Through Critical Design Issues

    The programming process driven by the cleanroom

    consultant has the potential to fully describe the project that

    will be built. The readiness of the client to participate in the

    process, the depth of preparation of participating client team

    members, their willingness or ability to answer the hard ques-

    tions, as well as their enthusiasm and time commitment to the

    processall will affect the result of the programming phase.

    This phase is the first iteration, of several, that will take place

    as the project unfolds. Most likely changes will be occurring

    through the construction process and even after turnover of the

    project as a host of good ideas emerge. These are called

    change orders.

    The information accumulated during the programming

    process will be the foundation upon which the development of

    construction documents rests. It is the function of the design

    team to sort out and interpret the data as it addresses architec-tural, structural, mechanical, plumbing, and electrical issues.

    Architectural Issues

    The clean facility is intended to house a process. The

    layout of the facility is based on personnel interaction with

    material flow and includes raw materials entering the clean-

    room, work in progress, and finished products leaving the

    cleanroom. Depending on the scope of the project, the design

    team may examine raw material receiving, storage, and trans-

    port to the clean facility, as well as finished product transport,

    storage, and shipping.

    Walls/Floor/CeilingAfter the facility layout has been determined, the materi-

    als of construction must be specified. Wall options include

    stick built using a drywall system on steel studs. This has been

    around for years and continues to be quite popular due to its

    relatively low cost. A variety of coatings and cladding is avail-

    able for the gypsum panels to make them suitable for even the

    more stringent cleanrooms. Modular systems permit quick

    installation and have a full array of cleanroom-compatible

    materials for the most stringent applications. Windows are

    generally incorporated into the wall system to permit super-

    vision from the outside, as a safety feature, and to support

    marketing during the plant tour, which invariably includes apeek into the cleanroom. Windows should be flush to the wall

    on the clean side to prevent accumulation of particles. Designs

    are available for flush windows on both sides of the wall, a

    particularly useful feature for windows between adjacent

    clean spaces.

    Floors on grade are frequently covered with a high solids

    epoxy finish applied to an appropriately prepared concrete

    surface. Vinyl tiles and vinyl sheeting, with standard, static

    dissipative or conductive characteristics are also used,

    depending on the application. Generally in Class 100 and

    more stringent cleanrooms, a raised floor is considered.

    A raised floor system should be a forged aluminum

    construction perforated to permit airflow from the cleanroomto the return plenum space below the floor. A grating type

    panel may be used in which case the finish may be anodized

    or powder coated. A perforated panel will usually have a stan-

    dard, static dissipative or conductive high-pressure laminate

    applied to it as a wearing surface.

    The most common cleanroom ceilings use an inverted

    T support grid made of extruded aluminum. The nominal

    2 ft 4 ft system supports filters, blank panels, and lights. In

    health science-related facilities, the ceiling may be of mono-

    lithic design, employing a water-resistant drywall construc-

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    5/10

    656 ASHRAE Transactions: Symposia

    tion and epoxy paint to eliminate as many contamination

    collecting seams as possible. Lights are typically fluorescent

    fixtures specifically designed for cleanroom application. In

    more stringent cleanrooms, the lighting may be integrated into

    the grid system to minimize air turbulence within the clean-

    room. The blank panels are frequently made of the same mate-

    rial as the walls or may be specifically designed with lowshedding characteristics for use in the cleanroom.

    Entry/Exit

    Getting people and material into and out of the cleanroom

    is an important aspect of the facility design. Doors are of a non-

    shedding solid, half-glass or full-glass construction. They

    typically have sealing on all four edges to minimize loss of

    clean air from the facility.

    Personnel generally enter through a gowning room,

    which acts as an airlock. Airlocks are used between clean and

    unrated areas as well as between higher- and lower-rated areas

    to maintain pressure differentials of the clean spaces. The

    gowning room will be large enough to accommodate all or

    most of the workforce using the cleanroom, while airlocks are

    commonly only large enough for one or two people to pass

    through at a time.

    Material may need to be removed from its packaging and

    otherwise prepared before entering the cleanroom. A material

    airlock will facilitate such handling. Non-clean material-

    handling equipment would move the material into the airlock.

    Cleanroom personnel would remove the packaging and

    prepare the material for entry into the cleanroom. For material

    leaving the cleanroom, a similar material airlock can be used.

    Depending on the layout of the facility, one material airlock

    might serve for entering and leaving material. The use of amaterial airlock and following the protocol associated with its

    use can result in a major source of outside contamination being

    kept out of the cleanroom.

    Structural Issues

    There may be significant structural challenges when the

    decision is made to retrofit an existing building to house a

    cleanroom facility. It is common that the space required for all

    the ancillary equipment described above is lacking. It becomes

    necessary to think in terms of equipment mezzanines or roof-

    mounted equipment. This requires an analysis of the building

    to ensure that the structure can be modified to accommodatesuch loads.

    It is not uncommon to install equipment, suspended from

    the roof structure, above the cleanroom. While some buildings

    have a robust overdesign associated with them and can support

    additional weight, others are designed to the basic building

    code for a specific occupancy and cannot support additional

    weight. In such cases, a ground-supported structure must be

    imposed on the cleanroom design. In some cases, the walls

    then become load bearing. In other designs, support columns

    are integrated into the wall system to support the ceiling. In

    either case, footings may have to be cut into the existing

    concrete floor, adding to schedule and cost impact.

    Mechanical Issues

    Cleanrooms are a special case of general air-conditioning

    design and require that certain practices be followed to ensure

    that the operating facility is cleaner and under more stringentcontrol than the typical human comfort conditioned space.

    Cleanliness

    Selection of cleanliness classification is the domain of the

    client and/or process consultant. The cleanliness level should

    not be greater than required to meet the objectives of the

    project. The concept that if class 10,000 is good, then class

    1,000 is better will be very costly in terms of airflow, filtra-

    tion, and air-conditioning first cost as well as ongoing operat-

    ing cost. Facilities with small specific-class rooms can be less

    costly than a large single-class space rated at the most stringent

    level.

    Airflow

    Air change rates into the hundreds of changes per hour

    dictate that air-moving equipment, and therefore energy to

    move the air, be much higher than the standard air-condition-

    ing application. The final selection of air change rate is based

    on the best guess by designer and client as to the need for

    high or lower airflow. An evaluation of the process and the

    potential of the process to generate contaminants within the

    cleanroom typically determine this. A contaminating process

    will require higher airflow than a more benign process. The

    mechanical system designer is challenged to find a place fornumerous large air handlers or fans and devise the routing of

    an extensive duct system.

    Filtration

    Air entering a cleanroom is usually filtered by HEPA

    (high-efficiency particulate, air) filters or ULPA (ultra-low

    penetration, air) filters. The most widely used HEPA filter has

    an efficiency of 99.97% on 0.3-micron particles and is speci-

    fied for the pharmaceutical and health-related industries as

    well as some mid-class cleanrooms in other industries. The

    most common ULPA filter has an efficiency of 99.9995% on

    0.12-micron particles and finds wide use in sophisticatedmicroelectronics facilities of class 10 and class 1. While some

    less stringent applications allow filters to be installed in air

    handlers or ductwork remote from the cleanroom, the most

    common site for the filters is in the ceiling of the cleanroom

    housed in a framework compatible with the ceiling system.

    Air Pattern

    It is not enough to introduce clean air into the cleanroom.

    The air should be introduced in a manner that captures and

    removes from the cleanroom particles that are considered

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    6/10

    ASHRAE Transactions: Symposia 657

    contaminants to the process. The most efficient scheme has

    100% of the ceiling covered with filters. Note that even when

    an inverted T grid ceiling has all 100% filter coverage, only

    about 85% of the ceiling has air flowing through filter media

    due to the width of the grid and filter frames. The air moves

    straight down through a perforated raised floor. This is called

    unidirectional airflow and permits particles generated within

    the cleanroom to be captured by the airflow streamlines and

    removed from the room without impinging on a critical

    surface within the room. Many class 100 and most, if not all,

    class 10 and class 1 cleanrooms are designed in this way.

    Temperature

    The temperature to be maintained in the cleanroom is

    driven by either comfort or process need. Comfort can gener-

    ally be met by maintaining a temperature of 722F in clean-

    rooms where lab coats or smocks are worn. In the more

    stringent cleanrooms, where full bunny suits are worn, a

    temperature specification as low as 662F would be appro-

    priate.Care should be taken when specifying temperature values

    and tolerances as a result of a perceived need by the process.

    High or low temperature values can be costly to maintain.

    Even more costly can be the need to hold a tight tolerance

    when not really needed. A 1F tolerance is more costly than

    a 2F tolerance. A F tolerance is more costly yet. This

    becomes even more evident if the need is to maintain a tight

    tolerance throughout the entire cleanroom, 24 hours per day,

    year-round, with widely fluctuating outside air conditions and

    process equipment heat generation. High first cost, high oper-

    ating cost, and many out of spec periods can result.

    Probably the most common approach to maintaining

    temperature in larger cleanroom installations is by using

    chilled water for cooling and hot water for heating. In smaller

    cleanrooms direct expansion cooling and electric heat are

    used. A characteristic of cleanroom design that separates it

    from standard construction is the fact that practically all clean-

    rooms require cooling year-round. This is due to the high inter-

    nal heat gain created by moving large amounts of air coupled

    with the heat generated by process equipment in operation. An

    additional factor is the generally high rate of exhausts, and,

    therefore, need for conditioned makeup air, present in many

    cleanroom facilities. The cooling system should be designed

    to operate round the clock 365 days a year.

    Humidity

    Many of the remarks relative to temperature control apply

    to humidity control as well. The selected value and tolerance

    should be realistic to the application. Comfort can be realized

    over a range of 30% to 65% RH if the temperature is held at

    a comfortable level. The only reason for a tighter tolerance is

    if the process requires it. Humidity control is costly. In dry

    areas, humidification drives the cost. In wet areas, dehumidi-

    fication is the driver. In most areas both humidification and

    dehumidification equipment must be incorporated into the

    mechanical system if a tolerance such as 5%RH is required.

    If a tolerance of 2%RH is required, particular care must be

    taken with the controls as well as the means of adding and

    removing moisture from the air.

    Pressurization

    Controlling pressure differential between clean andunrated spaces is one of the characteristics of cleanrooms.

    Typically, the pressure of the most stringent space is the high-

    est. It is maintained at a pressure of .02 inches of water column

    (in.w.c.) above an adjacent less stringent clean space or .05

    in.w.c. above an adjacent unrated space. Higher differentials

    will work as well; however, if it gets too high, noise problems

    develop and there can be difficulty in opening doors or keeping

    doors closed. It also contributes to higher operating cost.

    Where containment is required, and the pressure in a

    cleanroom must be lower than an adjacent space, care must be

    taken to ensure the space is tight and contaminants do not enter

    the space. A room within a room approach may be appro-

    priate. A single pass configuration may also be used. Suchrooms should be as small as possible and still support the

    process.

    Exhaust and Makeup Air

    In order to maintain positive pressurization, the amount of

    air introduced into the cleanroom must exceed the amount

    leaving. The amount leaving is typically equal to exfiltration,

    that is, leakage through doors, and other cracks due to the posi-

    tive pressure plus the amount leaving by design through vari-

    ous process exhaust systems. It is important, therefore, to

    identify all process equipment along with exhaust values asso-

    ciated with it before designing the cleanroom mechanical

    system. Generally, a value of 2 air changes per hour for exfil-

    tration when added to the total exhaust will allow the designer

    to proceed with the design of the makeup air system.

    Acoustics and Cleanroom Sound

    This is a topic that tends to generate excitement during the

    design phase but that disappears as a significant concern once

    the cleanroom is in operation. The high volume of air move-

    ment, coupled with the hard reflective nonshedding surfaces

    that are characteristic of cleanrooms, brings with it sound

    levels that are typically unacceptable in commercial work.

    Designers unfamiliar with cleanrooms tend to specify sound

    levels on the order of NC50 to NC55. These are very difficult,and costly to achieve, if they are in fact achievable. A more

    realistic specification of NC60 to NC 65 can be achieved by

    mechanical designers familiar with cleanroom applications at

    a reasonable cost and is well within the OSHA-specified levels

    for comfort in the workplace.

    Plumbing Issues

    In this tutorial,plumbingis the heading under which all

    piping activity is gathered. Actual installation in the field may

    be accomplished by a variety of subcontractors depending on

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    7/10

    658 ASHRAE Transactions: Symposia

    their skills and practice common in the project locale. A single

    designer or a number of specialty designers, depending on

    how the engineering office is organized and the complexity of

    the project, may address design issues.

    HVAC Piping

    HVAC-related piping for chilled water, hot water, steam,or potable (city) water has to be installed between the source

    and air handlers, makeup air units, and humidifiers. Drain

    lines for the equipment must also be installed. Generally, this

    piping work is done early in the cleanroom construction

    process before a cleanroom protocol has been put into effect.

    Frequently there is a requirement for the lines to be oversized

    to accommodate future expansion of the facility. Additional

    shutoff valves may be installed to facilitate installation of

    additional equipment at a future date. Where possible it is

    advisable to avoid running water or other liquid lines over the

    cleanroom to prevent damage to process equipment in the

    event of a leak.

    Process Piping

    Process piping is designed to carry process-cooling water,

    deionized water, hazardous gases, bulk gases, and specialty

    chemicals as well as specialty drain systems. Materials of

    construction include PVC, PVDF stainless steel, and copper,

    typically provided highly cleaned and protected from contam-

    ination and installed in accordance with strict guidelines. The

    issues surrounding process piping is that the piping preserves

    the high degree of cleanliness and delivers the fluids to the

    point of use in a safe manner. Bulk gas facilities are laid out to

    minimize piping runs and to facilitate bulk delivery by suppli-

    ers on a regular basis. DI water systems must be designed with

    sufficient water velocity to prevent buildup of organic contam-

    inants and be smooth with no interior edges for contaminants

    to accumulate. Piping conveying hazardous chemicals is

    commonly double contained and provided with extensive leak

    detection systems. The process piping requirements are suffi-

    ciently complex as to require firms specializing in the design

    and installation of such systems to be employed.

    Fire Protection

    Sprinkler systems and fire protection are also a specialty

    unto themselves. The cleanroom sprinkler system may be as

    simple as extending drops down from an existing piping

    system to the cleanroom ceiling. It may be significantly more

    complex depending on the flammable agents being usedwithin the facility. The presence of expensive process equip-

    ment in the clean space usually suggests that sprinkler systems

    above the ceiling be dry until needed. The airflow patterns

    within the cleanroom makes standard means of sensing a fire

    less effective. Careful development of the system, in conjunc-

    tion with the fire marshal and insurance company representa-

    tives, is recommended.

    Electrical and Energy Issues

    The electrical designer is responsible for meeting the

    high-energy needs of the clean facility. In addition to standard

    lighting and convenience outlets, the electrical design must

    include power for the extensive air-handling and cooling/heat-

    ing equipment as well as process equipment. There is a

    requirement for specific UV light filtration in certain micro-

    electronic processes. Outlets for process equipment must be

    selected based on the specific power needs of the equipment.

    Where hard wiring is required, termination means must be

    identified. In most cases, process equipment will be installed

    over a period of time so provision for future connections

    should be addressed.

    In most cases, the cleanroom is the critical part of a manu-

    facturing operation. Downtime is measured in hundreds of

    thousands if not millions of dollars per hour. One challenge to

    be faced by the electrical designer is to minimize the likeli-

    hood of such downtime. This can be done by providing redun-

    dant power circuitry to the facility from the power company.

    As a standby, an emergency generator with quick-acting

    changeover control mechanism is part of the electrical design

    scheme. Since it is not practical to provide emergency power

    to the entire facility, the electrical designer must identify thoseloads that are safety-related and are key to safe shutdown of

    key process equipment. The emergency circuitry can then be

    designed to overlay the standard circuits within the facility.

    Redundancy can also extend to specific process and

    process support equipment. Here again the electrical designer

    must identify equipment that will be provided with a backup.

    Dual chilled water pumps, dual exhaust fan motors, backup DI

    water system pumps, and hazardous waste lift station pumps

    are examples of a requirement for a rapid changeover control

    scheme in the event of primary motor failure.

    Lighting

    Much fine work is done in cleanrooms and there is a

    tendency to specify high lighting levels, i.e., 100 ft-candles

    (1000 lux) with resulting high-energy input and high contri-

    bution to cooling load as result. Use of task lighting for fine

    work and a general specification of 70-80 ft-candles lowers the

    cooling load and reduces cost by reducing the number of light-

    ing fixtures. An added benefit for more stringent cleanrooms

    is that the systems employing integral lighting into the ceiling

    grid can be used as they can more easily provide this lower

    level of light.

    RENOVATION CONSTRAINTS

    Retrofitting an existing operational cleanroom carries an

    uncommon set of issues and concerns. Addressing these issues

    in advance of construction will ensure a successful retrofit

    project while maintaining targeted production and existing

    yield levels. It is unrealistic to expect to maintain optimum

    production levels during retrofit; however, proper planning

    and sequencing of work will ensure a minimum of unexpected

    events that affect budget, time, and facility operation. Cost

    versus benefit analysis must be evaluated for each sequential

    step of work to evaluate its practicality. Budget and schedule

    success cannot merely be evaluated by the lowest cost basis or

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    8/10

    ASHRAE Transactions: Symposia 659

    shortest construction duration but more by the optimum

    compromise of schedule, cost, and lost production time and

    yield. Careful up-front planning and scheduling must be fore-

    most in thought and mindset.

    Specific Concerns

    Demolition and disposal of hazardous materials oftenmay be of concern in older facilities. Materials such as asbes-

    tos and items contaminated by process chemicals require

    disposal in compliance with local regulations.

    Maintenance of fire exit conditions and sprinkler systems

    during renovation often requires re-routing of piping systems,

    temporary disablement of sprinkler zones, and temporary

    egress corridors. In these areas of concern, local codes and

    code officials should be consulted in the planning stages to

    understand what work can be accomplished during normal

    work hours, what must be accomplished during off hours, and

    what must be accomplished during shutdown periods. Both

    EHS and insurance requirements tend to dictate the extent ofthese temporary measures.

    Material, equipment, and worker access must be

    addressed in planning to ensure production workers can access

    operational areas in a timely fashion and construction workers

    are not burdened with time-consuming access criteria to

    construction sites. Temporary access corridors and gown

    rooms often save significant time entering and exiting clean

    space for production workers. Separate construction entrances

    may seem to be a luxury during planning but often pay for

    themselves in work production in just a short period of time.

    Lay down and storage space for materials and compo-

    nents must be integral to renovation plan and schedule. Properprovisions for material handling will significantly cut labor

    cost and the potential for contamination generation. Constant

    movement and shifting of materials puts them at risk to

    damage and ultimately can compromise a projects comple-

    tion. Careful planning and construction management allows

    for just-in-time deliveries and ease of staging of materials for

    installation, requiring the minimum amount of staging area

    and maximum amount of flexibility.

    We cannot ignore cost when evaluating the upgrade of a

    facility, nor do we suggest it should be last on your list of

    concerns. Simply, this issue becomes the most complicated to

    evaluate. In the process of facility renovation, while maintain-

    ing operation, cost is not necessarily equal to price, as we

    previously addressed when discussing the issue of production

    window of opportunity. Actual cost must include price of the

    work along with lost production, potential for lost yield, and

    inconvenience. In reality, often actual cost cannot fully be

    detailed until well after the project is complete.

    The only true preventive steps you can take are to care-

    fully select your contractor and base your decision not only on

    their price but also on their experience, reputation, proposed

    schedule, and operational plan to complete the work.

    Implementing the Renovation Plan

    The first step requires that we survey the existing facility

    to determine how closely documented plans reflect actual

    existing conditions. Identifying the level by which we can rely

    on the facility plans will significantly affect the aggressiveness

    of the schedule, material stock requirements, and man loading.

    At the same time we are surveying the existing conditions,

    we must survey acceptable components within the market-

    place to match existing facility conditions where required and

    understand their availability to meet schedule and perfor-

    mance requirements. Material selection may depend more on

    its availability to meet the required schedule than anything

    else. We must set performance criteria and prioritize price,

    product, and delivery issues.

    A detailed sequence of work to be performed now must be

    documented and incorporated into a preliminary schedule.

    The preliminary schedule must then be compared with the

    production requirements of the facility and other potential

    events that would require schedule flexibility. In areas ofschedule conflict, the team must determine priorities and

    adapt requirements appropriately. This part of the work is the

    most critical to overall project success. Consideration has to be

    given to squeezing or expanding construction task durations to

    match schedules and maintain a cooperative interface. Overall

    project duration must be measured considering holiday sched-

    ules, manpower availability, man loading within a confined

    workspace, and, most importantly, continued operation of the

    facility.

    A potential significant cost issue, which depends greatly

    on our schedule flexibility and confidence in the documenta-

    tion of the existing conditions, is excess material stock. What

    and how much excess stock material we require must beweighed with potential for restocking, the associated charges

    and the critical nature of certain sequences along with lead

    time availability of potential shortfall products. Local sourc-

    ing of as many materials as possible must be achieved to prop-

    erly plan for possible contingencies.

    Construction area separation must be maintained at all

    times. Consideration should be given above the ceiling, in duct

    systems, plenums, return walls, conduit, and below the floor to

    ensure contamination spread from demolition is both minimal

    and contained.

    The window of down time for work has now opened.

    Removal or protection of existing equipment and curtainingoff of the actual construction area can now be achieved. This

    action must be performed with painstaking detail to eliminate

    potential for compromise of the existing operational facility

    and delays in restarting production or yield percentage in the

    renovated area. Whenever and wherever possible, equipment

    should be removed or isolated from the construction area.

    Demolition should occur in accordance with a sequential

    plan with materials removed from the controlled area and

    properly disposed of. A slow deliberate process should be

    utilized to minimize contamination generation; hazardous

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    9/10

    660 ASHRAE Transactions: Symposia

    materials should be identified in advance and removed accord-

    ing to regulations.

    Contamination-generating materials should be properly

    bagged upon removal and immediately removed from the crit-

    ical environment. A staging area for outgoing and incoming

    materials should be established. Personnel should be badged

    and identified as critical environment workers and noncriticalenvironment workers. The established acceptable protocol

    should be identified and maintained at all times.

    Products identified as salvageable and slated for re-instal-

    lation or re-use should be identified immediately upon

    removal to the staging area and be cleaned and wrapped for

    storage. When re-installing they should be unwrapped and

    cleaned with the accordance of the incoming material proto-

    col.

    With demolition complete, re-installation of the salvaged

    materials and new material installation can now begin. All

    materials should be treated as new and follow the incoming

    material protocol. Construction should occur under a build

    clean protocol that is equal to or exceeds that of the operatingfacility. Final (super) clean should occur prior to removal of

    temporary construction barriers. Equipment should then be

    moved in through the staging area under the incoming material

    protocol and set in place under operating protocol conditions.

    PRINCIPLES FOR CONTROLLING COSTS

    Design to the appropriate level of contamination control

    required.

    Design for changing conditions.

    Design utilities to be easily connected and disconnected.

    Design utilities to flow at adequate rates, constant pres-

    sure, and typical levels of purity.

    Place much of the process equipment outside of the

    clean environment.

    Control entry and egress of people, material, and equip-

    ment.

    Provide for ease of maintenance, access, and periodic

    inspections.

    Manage each of the disciplines to the approved project

    budget throughout the design and the constructionphases.

  • 8/13/2019 Gettign the Most Out of the Clean Room Design

    10/10