Upload
lw1735
View
212
Download
0
Embed Size (px)
Citation preview
8/13/2019 Gettign the Most Out of the Clean Room Design
1/10
652 2005 ASHRAE.
ABSTRACT
This paper discusses the design of cleanrooms anddescribes a five-step process that developes the informationneeded to identify, clarify, and prioritize cleanroom require-
ments.
INTRODUCTION
When building a cleanroom facility, special attentionshould be given first to the essential tasks for defining clean-room requirements, specifically determining cleanroom areas,building areas, filtration coverage, airflow quantities, powerconsumption, and budget items.
Think of design activities asproblem solvingand program-ming activities asproblem seeking. Programming develops thebody of information needed to identify, clarify, and prioritize thecleanroom requirements. The key to developing a goodprogramming process is being able to manage tremendous
amounts of data. This can be accomplished by creating a matrixof different types of preliminary information. One excellentapproach is an organized, methodical, five-step process called,
problem seeking.Five quantitative project elements are produced during
the programming process.
1. Process Tool List.This initial information platform drivesutilities, areas, and cleanliness levels.
2. Space List. An analysis of functional areas.
3. Utility Matrix.An analysis of services to each of the processtools for including process cooling, exhausts, pure water,gases, and bulk chemicals.
4. Project Budget. The description of anticipated project-
related costs prior to design.5. Project Schedule. The description of project milestone
dates outlining major activities and approval-submittaltargets.
Tools, people, activities, equipment, storage, and efficien-cies generate the area requirements. The numbers of peoplethat will work in the project require workspace, circulationspace, gowning space, offices or desk space, and parking
space.Perhaps the forgotten type of space in any building is stor-
age space. Particularly in a cleanroom, clean storage isrequired for material, chemicals, equipment, WIP storage, andmaintenance.
Beyond this, the efficient use of space in terms of walls,structure, chases, etc., will greatly affect the total area AND,hence, the total cost, of a cleanroom. Another often over-looked space requirement is additional space for new tools orequipment in the near future, say two to five years.
The process of programming is the management of allpreliminary project data. To make this as easy and as organizedas possible, the five-step process called problem seeking hasproven very successful. In each of the following five steps,
different types of information are developed and analyzed.The order is a natural progression of developing data withouthaving to retrace your steps. Validation of the data is always anintegral part of the process and allows for feedback and eval-uation loops.
THE FIVE-STEP PROCESS
Establish Goals
First, establish the objectives for constructing the clean-room. Clearly delineating the project goals is one of the mostoften neglected contributions upper management can make toa project. Originating from upper management, 10 to 20 well-stated objectives will have an extremely positive effect on the
outcome of your cleanroom project. Goals provide a set ofclear expectations for the project team that parallel thecompany's business plan. The goals should deal with each ofthe four considerations of cleanroom design:
Getting the Most Out of a Cleanroom Design
Thomas E. Hansz, AIA
Thomas E. Hanszis president of Facility Planning and Resources, Inc., Pittsburgh, Pa.
DE-05-9-3
2005, American Society of Heating, Refrigerating and Air-Conditioning
Engineers, Inc. (www.ashrae.org). Reprinted by permission from ASHRAE
Transactions, Volume 111, Part 2. The material may not be copied nor distrib-
uted in either paper or digital form without ASHRAEs permission.
8/13/2019 Gettign the Most Out of the Clean Room Design
2/10
ASHRAE Transactions: Symposia 653
FunctionAspects of activities, relationships, people,and operations.
FormPhysical considerations of form, space, and sys-tems.
EconomyAspects of construction costs, life-cyclecosts, and energy.
TimeConcerns the project schedule, expansion, andchange.
Analyze Facts
The second step in the programming process requires
establishing a database of cleanroom information. Accurate
staffing projections for cleanroom personnel should be devel-
oped. Information regarding all manufacturing equipment
should be assembled. Utility bills for the preceding 12 months
will be very useful and should be assembled. In short, all the
information that will give the architects and engineers a thor-
ough knowledge of existing conditions should be assembled
now. At the end of this paper is a suggested list of typical infor-mation that should be given to the programming consultants to
initiate gathering of facts.
For processes using hazardous production materials, an
accurate inventory of chemicals will be required to satisfy the
fire code and building code regulations. Another critical area
of analysis, which should be done during the fact-gathering
step, is the building code analysis. Whatever building code is
in force, your cleanroom will be regulated as to how large an
area it can be, how high the roof can be above it, how many exit
doors will be required, and to some extent what the layout will
be to ensure occupant safety in case an emergency should
arise. Cleanrooms using hazardous production materials
(HPMs) will be required to have separate routes for peoplecirculation and for the movement of HPMs. Exit distances
from any point within the cleanroom may be as short as 75 ft.
Walls surrounding the cleanroom will be required to meet
specified fire resistance.
Cleanroom Concepts
Before the start of design, the project team should exam-
ine concepts applicable to work flow, flexibility, utility distri-
bution, and other such issues. The team should address what
types of changes can be anticipated. Will additional equipment
or improving the classification of contamination control be a
real possibility in the future? The predictability of the cleanenvironment should be examined as well. All this should be at
least addressed if not resolved before the design effort gets
underway.
Production or research engineers should determine prod-
uct contamination sensitivity by this time. If not, it needs to be
a first priority, along with establishing a flow chart identifying
cleanroom functions and their required level of control.
Beyond controlling the particulate counts, the production
process may also require specific temperature, humidity, and
pressure levels with fixed limits of variance. How to provide
the level of control is answered during the design phase. Now
is the time to establish the control criteria.
DETERMINE PROCESS REQUIREMENTS
The Relation of Process to Facility
Cleanrooms in themselves are not aesthetic features but
are adjuncts to specialized activities that must be conducted in
clean environments. Cleanroom concepts are therefore depen-
dent upon the level of cleanliness required and upon the type
and scale of the activity. Each successively cleaner environ-
ment requires stricter operating procedures, or protocols, to
maintain that cleanliness level. The strictest protocols may
require clean buffer zones to isolate the cleanest areas from
less clean environments or from office environments. These
Table 1. Potential Cleanroom Issues
Process Facility People
Equipment Organization Safety
Work flow Flexibility Gowning
Material flow Site services Aesthetics
Automation Functional relations Work socialization
Technology Contamination control Productivity
Process utilities Aseptic conditions Communications
ESD Reliability Interaction
EFI/RFI Redundancy Home base
JIT inventories Vibration Orientation
Energy Waste treatment Facility image
Tool installation Storage Security
Figure 1 The five-step process.
8/13/2019 Gettign the Most Out of the Clean Room Design
3/10
654 ASHRAE Transactions: Symposia
protocols and the nested space configurations have defining
effects on personnel circulation, process flows, material
movement, maintenance activities, new equipment installa-
tion, and old equipment decommissioning.
Materials and equipment must be meticulously wiped
down during their staged entry. Other supplies, which were
produced and packaged in a cleanroom, will be delivered indouble-sealed bag enclosures for protection from the outside
world during shipment and handling. These double-bag enclo-
sures must be wiped and sequentially be removed as they
progress through the staged entry.
Avoiding unnecessary cleanroom traffic, greater quality
control, safety, and lower unit costs for bulk raw materials are
factors that compel facilities to pipe or convey materials to
their cleanroom processes. As usage quantities increase,
frequent handling of chemicals, gases, and process wastes
increase exposure hazards for the workers and contamination
hazards for the cleanroom.
The risks imposed by chemicals and gases vary with
material properties and concentration. The most universallyaccepted procedure for assessing and identifying relative
chemical hazards was developed by the National Fire Protec-
tion Association (NFPA) for safeguarding emergency
response personnel. Published as NFPA Standard 704, this
system of identifying hazards rates each chemical on a scale of
0 to 4 in three hazard categorieshealth, flammability, and
instability. Nearly all chemical containers and tanks are
required to display the NFPA 704 diamond, which identifies
the hazard ratings.
Process Equipment and Process Support Services
A key to developing a meaningful and useful program is
to gather as many facts as possible, especially about the activ-
ities and processes. For example:
What are the processing goals?
What are the hours of operation?
What are the process steps and how does the work flow?
How should work-in-progress be managed?
What are the most critical steps in the process?
What is the philosophy for maintenance and outages?
How should expansion and future changes be accommo-
dated?
THE UTILITY MATRIXFor market-driven products, such as pharmaceuticals and
semiconductors, the clients process assumptions are typically
being refined concurrently with the programming and early
design stages. Frequently complete equipment lists are not
available. In the interim period, data for similar equipment
may be used or assumptions may be made. The important issue
is to develop a comprehensive database to record information
and assumptions and to track the changes as design and
construction proceed. To compound the complexity, major
pieces of equipment frequently have auxiliary or support
equipment. In the concept development phase, optional equip-
ment configurations must be explored for fit, operational func-
tions, and accessibility.
Cleanroom facilities are typically intensive users of
equipment and therefore are large consumers of utilities and
raw materials. Frequently auxiliary or support equipment has
separate utility services. The equipment database should bestructured in a manner that allows utility and raw material
consumption data to be associated with each process tool and
each piece of auxiliary equipment.
This technique has several advantages:
Data may be sorted by equipment to show or to change
basis.
A sort by utility or raw material will give demand at
100% utilization.
As equipment is grouped into areas, a utility sort on the
equipment groupings will indicate use patterns that may
aid distribution decisions.
If process equipment is to be added in phases, the data-base will allow the engineers to study expansion options
for central utility systems.
During the course of the project, as equipment lists are
refined, having a database will allow project managers
to identify scope changes.
Depending on the projects size assembling, these data
can be a huge effort. So, can a project be programmed and
designed without a utility matrix? Perhaps one can, but these
facilities are both complex and expensive. Without sufficient
data, even experienced professionals will have difficulty
guessing and will have no way of knowing whether the esti-
mates are high or low. Too low an estimate will lead to insuf-ficient capacities, and too high an estimate will result in
expensive overbuilding.
There may be as many individual ways to organize the
data as there are people collecting it. Some of the most
successful techniques are:
Supplying special data collection forms for each piece
of equipment to the owners process engineers or equip-
ment users for recording equipment data.
Using the owners anticipated equipment list and exist-
ing engineering database.
Using the owners equipment list and consultants data-
base. Assembling a notebook of data sheets from the owners
equipment operations and maintenance manuals.
Assembling a notebook of vendor-supplied data.
Hard copies are good for record keeping, but when it
comes to sorting, summing, editing, and transferring all or part
of the data, electronic copies have an overwhelming advan-
tage. Some of the methods in the preceding list may involve
handling the data twice, i.e., recording on forms, then entering
into electronic files.
8/13/2019 Gettign the Most Out of the Clean Room Design
4/10
ASHRAE Transactions: Symposia 655
When collecting data, particularly from vendor sources,
make sure that the data represent actual consumption data and
not the nominal service capacity, which does not represent
utility usage. For example, many vendor data sheets list for the
electrical utility requirements the electrical service, 20 amps at
120 volts, rather than the connected load, which may be only
300 watts or 2.5 amps at 120 volts. Accumulated data errors
such as this could dramatically distort demand requirements to
the entire facility.
Once the utility and raw material data have been
collected, one critical task remains. If one were to sum the
flows or consumption of each utility or raw material, the total
demands would be far greater than those actually experienced.
What is missing is an accounting of
down time for scheduled maintenance and cleaning,
idle time for lags in work-in-progress flow,
wait time for process step sequencing, and
unexpected outages or breakdowns.
This accounting is usually incorporated as an efficiency
factor. Since most manufacturing facilities operate around the
clock, the most common basis for evaluation is 24 hours. If the
mean time between failure (MTBF) is over 1000 hours for
minor incidences, nonproductive time due to breakdowns
would be less than one percent, which is negligible. However,
a piece of equipment may need to be shut down once a shift,
or once a day, for shift change, cleaning, or preventive main-
tenance. If such downtime lasted two hours, available uptime
would be 92%. Equipment waiting cumulatively eight minutes
every hour for lags in work flow would be working 87% of the
available time. If the equipment sequentially processes the
work in four steps and the utility of interest is used in only
three of the four steps, the utility would be consumed only
75% of the equipments operating time. As a result the total
utility consumption by this single tool would be 60% (0.92 *
0.87 * 0.75) of the tabulated peak demand.
Considering group equipment operations, if one of six
tools is not operating in sequence with the others, then the
average utility consumption would be 83% of the single tool
usage. Applying this operational diversity factor to the single
tool consumption as illustrated above, the average utility
consumption would be 50% (0.83 * 0.60) of the published util-
ity consumption data.
Working Through Critical Design Issues
The programming process driven by the cleanroom
consultant has the potential to fully describe the project that
will be built. The readiness of the client to participate in the
process, the depth of preparation of participating client team
members, their willingness or ability to answer the hard ques-
tions, as well as their enthusiasm and time commitment to the
processall will affect the result of the programming phase.
This phase is the first iteration, of several, that will take place
as the project unfolds. Most likely changes will be occurring
through the construction process and even after turnover of the
project as a host of good ideas emerge. These are called
change orders.
The information accumulated during the programming
process will be the foundation upon which the development of
construction documents rests. It is the function of the design
team to sort out and interpret the data as it addresses architec-tural, structural, mechanical, plumbing, and electrical issues.
Architectural Issues
The clean facility is intended to house a process. The
layout of the facility is based on personnel interaction with
material flow and includes raw materials entering the clean-
room, work in progress, and finished products leaving the
cleanroom. Depending on the scope of the project, the design
team may examine raw material receiving, storage, and trans-
port to the clean facility, as well as finished product transport,
storage, and shipping.
Walls/Floor/CeilingAfter the facility layout has been determined, the materi-
als of construction must be specified. Wall options include
stick built using a drywall system on steel studs. This has been
around for years and continues to be quite popular due to its
relatively low cost. A variety of coatings and cladding is avail-
able for the gypsum panels to make them suitable for even the
more stringent cleanrooms. Modular systems permit quick
installation and have a full array of cleanroom-compatible
materials for the most stringent applications. Windows are
generally incorporated into the wall system to permit super-
vision from the outside, as a safety feature, and to support
marketing during the plant tour, which invariably includes apeek into the cleanroom. Windows should be flush to the wall
on the clean side to prevent accumulation of particles. Designs
are available for flush windows on both sides of the wall, a
particularly useful feature for windows between adjacent
clean spaces.
Floors on grade are frequently covered with a high solids
epoxy finish applied to an appropriately prepared concrete
surface. Vinyl tiles and vinyl sheeting, with standard, static
dissipative or conductive characteristics are also used,
depending on the application. Generally in Class 100 and
more stringent cleanrooms, a raised floor is considered.
A raised floor system should be a forged aluminum
construction perforated to permit airflow from the cleanroomto the return plenum space below the floor. A grating type
panel may be used in which case the finish may be anodized
or powder coated. A perforated panel will usually have a stan-
dard, static dissipative or conductive high-pressure laminate
applied to it as a wearing surface.
The most common cleanroom ceilings use an inverted
T support grid made of extruded aluminum. The nominal
2 ft 4 ft system supports filters, blank panels, and lights. In
health science-related facilities, the ceiling may be of mono-
lithic design, employing a water-resistant drywall construc-
8/13/2019 Gettign the Most Out of the Clean Room Design
5/10
656 ASHRAE Transactions: Symposia
tion and epoxy paint to eliminate as many contamination
collecting seams as possible. Lights are typically fluorescent
fixtures specifically designed for cleanroom application. In
more stringent cleanrooms, the lighting may be integrated into
the grid system to minimize air turbulence within the clean-
room. The blank panels are frequently made of the same mate-
rial as the walls or may be specifically designed with lowshedding characteristics for use in the cleanroom.
Entry/Exit
Getting people and material into and out of the cleanroom
is an important aspect of the facility design. Doors are of a non-
shedding solid, half-glass or full-glass construction. They
typically have sealing on all four edges to minimize loss of
clean air from the facility.
Personnel generally enter through a gowning room,
which acts as an airlock. Airlocks are used between clean and
unrated areas as well as between higher- and lower-rated areas
to maintain pressure differentials of the clean spaces. The
gowning room will be large enough to accommodate all or
most of the workforce using the cleanroom, while airlocks are
commonly only large enough for one or two people to pass
through at a time.
Material may need to be removed from its packaging and
otherwise prepared before entering the cleanroom. A material
airlock will facilitate such handling. Non-clean material-
handling equipment would move the material into the airlock.
Cleanroom personnel would remove the packaging and
prepare the material for entry into the cleanroom. For material
leaving the cleanroom, a similar material airlock can be used.
Depending on the layout of the facility, one material airlock
might serve for entering and leaving material. The use of amaterial airlock and following the protocol associated with its
use can result in a major source of outside contamination being
kept out of the cleanroom.
Structural Issues
There may be significant structural challenges when the
decision is made to retrofit an existing building to house a
cleanroom facility. It is common that the space required for all
the ancillary equipment described above is lacking. It becomes
necessary to think in terms of equipment mezzanines or roof-
mounted equipment. This requires an analysis of the building
to ensure that the structure can be modified to accommodatesuch loads.
It is not uncommon to install equipment, suspended from
the roof structure, above the cleanroom. While some buildings
have a robust overdesign associated with them and can support
additional weight, others are designed to the basic building
code for a specific occupancy and cannot support additional
weight. In such cases, a ground-supported structure must be
imposed on the cleanroom design. In some cases, the walls
then become load bearing. In other designs, support columns
are integrated into the wall system to support the ceiling. In
either case, footings may have to be cut into the existing
concrete floor, adding to schedule and cost impact.
Mechanical Issues
Cleanrooms are a special case of general air-conditioning
design and require that certain practices be followed to ensure
that the operating facility is cleaner and under more stringentcontrol than the typical human comfort conditioned space.
Cleanliness
Selection of cleanliness classification is the domain of the
client and/or process consultant. The cleanliness level should
not be greater than required to meet the objectives of the
project. The concept that if class 10,000 is good, then class
1,000 is better will be very costly in terms of airflow, filtra-
tion, and air-conditioning first cost as well as ongoing operat-
ing cost. Facilities with small specific-class rooms can be less
costly than a large single-class space rated at the most stringent
level.
Airflow
Air change rates into the hundreds of changes per hour
dictate that air-moving equipment, and therefore energy to
move the air, be much higher than the standard air-condition-
ing application. The final selection of air change rate is based
on the best guess by designer and client as to the need for
high or lower airflow. An evaluation of the process and the
potential of the process to generate contaminants within the
cleanroom typically determine this. A contaminating process
will require higher airflow than a more benign process. The
mechanical system designer is challenged to find a place fornumerous large air handlers or fans and devise the routing of
an extensive duct system.
Filtration
Air entering a cleanroom is usually filtered by HEPA
(high-efficiency particulate, air) filters or ULPA (ultra-low
penetration, air) filters. The most widely used HEPA filter has
an efficiency of 99.97% on 0.3-micron particles and is speci-
fied for the pharmaceutical and health-related industries as
well as some mid-class cleanrooms in other industries. The
most common ULPA filter has an efficiency of 99.9995% on
0.12-micron particles and finds wide use in sophisticatedmicroelectronics facilities of class 10 and class 1. While some
less stringent applications allow filters to be installed in air
handlers or ductwork remote from the cleanroom, the most
common site for the filters is in the ceiling of the cleanroom
housed in a framework compatible with the ceiling system.
Air Pattern
It is not enough to introduce clean air into the cleanroom.
The air should be introduced in a manner that captures and
removes from the cleanroom particles that are considered
8/13/2019 Gettign the Most Out of the Clean Room Design
6/10
ASHRAE Transactions: Symposia 657
contaminants to the process. The most efficient scheme has
100% of the ceiling covered with filters. Note that even when
an inverted T grid ceiling has all 100% filter coverage, only
about 85% of the ceiling has air flowing through filter media
due to the width of the grid and filter frames. The air moves
straight down through a perforated raised floor. This is called
unidirectional airflow and permits particles generated within
the cleanroom to be captured by the airflow streamlines and
removed from the room without impinging on a critical
surface within the room. Many class 100 and most, if not all,
class 10 and class 1 cleanrooms are designed in this way.
Temperature
The temperature to be maintained in the cleanroom is
driven by either comfort or process need. Comfort can gener-
ally be met by maintaining a temperature of 722F in clean-
rooms where lab coats or smocks are worn. In the more
stringent cleanrooms, where full bunny suits are worn, a
temperature specification as low as 662F would be appro-
priate.Care should be taken when specifying temperature values
and tolerances as a result of a perceived need by the process.
High or low temperature values can be costly to maintain.
Even more costly can be the need to hold a tight tolerance
when not really needed. A 1F tolerance is more costly than
a 2F tolerance. A F tolerance is more costly yet. This
becomes even more evident if the need is to maintain a tight
tolerance throughout the entire cleanroom, 24 hours per day,
year-round, with widely fluctuating outside air conditions and
process equipment heat generation. High first cost, high oper-
ating cost, and many out of spec periods can result.
Probably the most common approach to maintaining
temperature in larger cleanroom installations is by using
chilled water for cooling and hot water for heating. In smaller
cleanrooms direct expansion cooling and electric heat are
used. A characteristic of cleanroom design that separates it
from standard construction is the fact that practically all clean-
rooms require cooling year-round. This is due to the high inter-
nal heat gain created by moving large amounts of air coupled
with the heat generated by process equipment in operation. An
additional factor is the generally high rate of exhausts, and,
therefore, need for conditioned makeup air, present in many
cleanroom facilities. The cooling system should be designed
to operate round the clock 365 days a year.
Humidity
Many of the remarks relative to temperature control apply
to humidity control as well. The selected value and tolerance
should be realistic to the application. Comfort can be realized
over a range of 30% to 65% RH if the temperature is held at
a comfortable level. The only reason for a tighter tolerance is
if the process requires it. Humidity control is costly. In dry
areas, humidification drives the cost. In wet areas, dehumidi-
fication is the driver. In most areas both humidification and
dehumidification equipment must be incorporated into the
mechanical system if a tolerance such as 5%RH is required.
If a tolerance of 2%RH is required, particular care must be
taken with the controls as well as the means of adding and
removing moisture from the air.
Pressurization
Controlling pressure differential between clean andunrated spaces is one of the characteristics of cleanrooms.
Typically, the pressure of the most stringent space is the high-
est. It is maintained at a pressure of .02 inches of water column
(in.w.c.) above an adjacent less stringent clean space or .05
in.w.c. above an adjacent unrated space. Higher differentials
will work as well; however, if it gets too high, noise problems
develop and there can be difficulty in opening doors or keeping
doors closed. It also contributes to higher operating cost.
Where containment is required, and the pressure in a
cleanroom must be lower than an adjacent space, care must be
taken to ensure the space is tight and contaminants do not enter
the space. A room within a room approach may be appro-
priate. A single pass configuration may also be used. Suchrooms should be as small as possible and still support the
process.
Exhaust and Makeup Air
In order to maintain positive pressurization, the amount of
air introduced into the cleanroom must exceed the amount
leaving. The amount leaving is typically equal to exfiltration,
that is, leakage through doors, and other cracks due to the posi-
tive pressure plus the amount leaving by design through vari-
ous process exhaust systems. It is important, therefore, to
identify all process equipment along with exhaust values asso-
ciated with it before designing the cleanroom mechanical
system. Generally, a value of 2 air changes per hour for exfil-
tration when added to the total exhaust will allow the designer
to proceed with the design of the makeup air system.
Acoustics and Cleanroom Sound
This is a topic that tends to generate excitement during the
design phase but that disappears as a significant concern once
the cleanroom is in operation. The high volume of air move-
ment, coupled with the hard reflective nonshedding surfaces
that are characteristic of cleanrooms, brings with it sound
levels that are typically unacceptable in commercial work.
Designers unfamiliar with cleanrooms tend to specify sound
levels on the order of NC50 to NC55. These are very difficult,and costly to achieve, if they are in fact achievable. A more
realistic specification of NC60 to NC 65 can be achieved by
mechanical designers familiar with cleanroom applications at
a reasonable cost and is well within the OSHA-specified levels
for comfort in the workplace.
Plumbing Issues
In this tutorial,plumbingis the heading under which all
piping activity is gathered. Actual installation in the field may
be accomplished by a variety of subcontractors depending on
8/13/2019 Gettign the Most Out of the Clean Room Design
7/10
658 ASHRAE Transactions: Symposia
their skills and practice common in the project locale. A single
designer or a number of specialty designers, depending on
how the engineering office is organized and the complexity of
the project, may address design issues.
HVAC Piping
HVAC-related piping for chilled water, hot water, steam,or potable (city) water has to be installed between the source
and air handlers, makeup air units, and humidifiers. Drain
lines for the equipment must also be installed. Generally, this
piping work is done early in the cleanroom construction
process before a cleanroom protocol has been put into effect.
Frequently there is a requirement for the lines to be oversized
to accommodate future expansion of the facility. Additional
shutoff valves may be installed to facilitate installation of
additional equipment at a future date. Where possible it is
advisable to avoid running water or other liquid lines over the
cleanroom to prevent damage to process equipment in the
event of a leak.
Process Piping
Process piping is designed to carry process-cooling water,
deionized water, hazardous gases, bulk gases, and specialty
chemicals as well as specialty drain systems. Materials of
construction include PVC, PVDF stainless steel, and copper,
typically provided highly cleaned and protected from contam-
ination and installed in accordance with strict guidelines. The
issues surrounding process piping is that the piping preserves
the high degree of cleanliness and delivers the fluids to the
point of use in a safe manner. Bulk gas facilities are laid out to
minimize piping runs and to facilitate bulk delivery by suppli-
ers on a regular basis. DI water systems must be designed with
sufficient water velocity to prevent buildup of organic contam-
inants and be smooth with no interior edges for contaminants
to accumulate. Piping conveying hazardous chemicals is
commonly double contained and provided with extensive leak
detection systems. The process piping requirements are suffi-
ciently complex as to require firms specializing in the design
and installation of such systems to be employed.
Fire Protection
Sprinkler systems and fire protection are also a specialty
unto themselves. The cleanroom sprinkler system may be as
simple as extending drops down from an existing piping
system to the cleanroom ceiling. It may be significantly more
complex depending on the flammable agents being usedwithin the facility. The presence of expensive process equip-
ment in the clean space usually suggests that sprinkler systems
above the ceiling be dry until needed. The airflow patterns
within the cleanroom makes standard means of sensing a fire
less effective. Careful development of the system, in conjunc-
tion with the fire marshal and insurance company representa-
tives, is recommended.
Electrical and Energy Issues
The electrical designer is responsible for meeting the
high-energy needs of the clean facility. In addition to standard
lighting and convenience outlets, the electrical design must
include power for the extensive air-handling and cooling/heat-
ing equipment as well as process equipment. There is a
requirement for specific UV light filtration in certain micro-
electronic processes. Outlets for process equipment must be
selected based on the specific power needs of the equipment.
Where hard wiring is required, termination means must be
identified. In most cases, process equipment will be installed
over a period of time so provision for future connections
should be addressed.
In most cases, the cleanroom is the critical part of a manu-
facturing operation. Downtime is measured in hundreds of
thousands if not millions of dollars per hour. One challenge to
be faced by the electrical designer is to minimize the likeli-
hood of such downtime. This can be done by providing redun-
dant power circuitry to the facility from the power company.
As a standby, an emergency generator with quick-acting
changeover control mechanism is part of the electrical design
scheme. Since it is not practical to provide emergency power
to the entire facility, the electrical designer must identify thoseloads that are safety-related and are key to safe shutdown of
key process equipment. The emergency circuitry can then be
designed to overlay the standard circuits within the facility.
Redundancy can also extend to specific process and
process support equipment. Here again the electrical designer
must identify equipment that will be provided with a backup.
Dual chilled water pumps, dual exhaust fan motors, backup DI
water system pumps, and hazardous waste lift station pumps
are examples of a requirement for a rapid changeover control
scheme in the event of primary motor failure.
Lighting
Much fine work is done in cleanrooms and there is a
tendency to specify high lighting levels, i.e., 100 ft-candles
(1000 lux) with resulting high-energy input and high contri-
bution to cooling load as result. Use of task lighting for fine
work and a general specification of 70-80 ft-candles lowers the
cooling load and reduces cost by reducing the number of light-
ing fixtures. An added benefit for more stringent cleanrooms
is that the systems employing integral lighting into the ceiling
grid can be used as they can more easily provide this lower
level of light.
RENOVATION CONSTRAINTS
Retrofitting an existing operational cleanroom carries an
uncommon set of issues and concerns. Addressing these issues
in advance of construction will ensure a successful retrofit
project while maintaining targeted production and existing
yield levels. It is unrealistic to expect to maintain optimum
production levels during retrofit; however, proper planning
and sequencing of work will ensure a minimum of unexpected
events that affect budget, time, and facility operation. Cost
versus benefit analysis must be evaluated for each sequential
step of work to evaluate its practicality. Budget and schedule
success cannot merely be evaluated by the lowest cost basis or
8/13/2019 Gettign the Most Out of the Clean Room Design
8/10
ASHRAE Transactions: Symposia 659
shortest construction duration but more by the optimum
compromise of schedule, cost, and lost production time and
yield. Careful up-front planning and scheduling must be fore-
most in thought and mindset.
Specific Concerns
Demolition and disposal of hazardous materials oftenmay be of concern in older facilities. Materials such as asbes-
tos and items contaminated by process chemicals require
disposal in compliance with local regulations.
Maintenance of fire exit conditions and sprinkler systems
during renovation often requires re-routing of piping systems,
temporary disablement of sprinkler zones, and temporary
egress corridors. In these areas of concern, local codes and
code officials should be consulted in the planning stages to
understand what work can be accomplished during normal
work hours, what must be accomplished during off hours, and
what must be accomplished during shutdown periods. Both
EHS and insurance requirements tend to dictate the extent ofthese temporary measures.
Material, equipment, and worker access must be
addressed in planning to ensure production workers can access
operational areas in a timely fashion and construction workers
are not burdened with time-consuming access criteria to
construction sites. Temporary access corridors and gown
rooms often save significant time entering and exiting clean
space for production workers. Separate construction entrances
may seem to be a luxury during planning but often pay for
themselves in work production in just a short period of time.
Lay down and storage space for materials and compo-
nents must be integral to renovation plan and schedule. Properprovisions for material handling will significantly cut labor
cost and the potential for contamination generation. Constant
movement and shifting of materials puts them at risk to
damage and ultimately can compromise a projects comple-
tion. Careful planning and construction management allows
for just-in-time deliveries and ease of staging of materials for
installation, requiring the minimum amount of staging area
and maximum amount of flexibility.
We cannot ignore cost when evaluating the upgrade of a
facility, nor do we suggest it should be last on your list of
concerns. Simply, this issue becomes the most complicated to
evaluate. In the process of facility renovation, while maintain-
ing operation, cost is not necessarily equal to price, as we
previously addressed when discussing the issue of production
window of opportunity. Actual cost must include price of the
work along with lost production, potential for lost yield, and
inconvenience. In reality, often actual cost cannot fully be
detailed until well after the project is complete.
The only true preventive steps you can take are to care-
fully select your contractor and base your decision not only on
their price but also on their experience, reputation, proposed
schedule, and operational plan to complete the work.
Implementing the Renovation Plan
The first step requires that we survey the existing facility
to determine how closely documented plans reflect actual
existing conditions. Identifying the level by which we can rely
on the facility plans will significantly affect the aggressiveness
of the schedule, material stock requirements, and man loading.
At the same time we are surveying the existing conditions,
we must survey acceptable components within the market-
place to match existing facility conditions where required and
understand their availability to meet schedule and perfor-
mance requirements. Material selection may depend more on
its availability to meet the required schedule than anything
else. We must set performance criteria and prioritize price,
product, and delivery issues.
A detailed sequence of work to be performed now must be
documented and incorporated into a preliminary schedule.
The preliminary schedule must then be compared with the
production requirements of the facility and other potential
events that would require schedule flexibility. In areas ofschedule conflict, the team must determine priorities and
adapt requirements appropriately. This part of the work is the
most critical to overall project success. Consideration has to be
given to squeezing or expanding construction task durations to
match schedules and maintain a cooperative interface. Overall
project duration must be measured considering holiday sched-
ules, manpower availability, man loading within a confined
workspace, and, most importantly, continued operation of the
facility.
A potential significant cost issue, which depends greatly
on our schedule flexibility and confidence in the documenta-
tion of the existing conditions, is excess material stock. What
and how much excess stock material we require must beweighed with potential for restocking, the associated charges
and the critical nature of certain sequences along with lead
time availability of potential shortfall products. Local sourc-
ing of as many materials as possible must be achieved to prop-
erly plan for possible contingencies.
Construction area separation must be maintained at all
times. Consideration should be given above the ceiling, in duct
systems, plenums, return walls, conduit, and below the floor to
ensure contamination spread from demolition is both minimal
and contained.
The window of down time for work has now opened.
Removal or protection of existing equipment and curtainingoff of the actual construction area can now be achieved. This
action must be performed with painstaking detail to eliminate
potential for compromise of the existing operational facility
and delays in restarting production or yield percentage in the
renovated area. Whenever and wherever possible, equipment
should be removed or isolated from the construction area.
Demolition should occur in accordance with a sequential
plan with materials removed from the controlled area and
properly disposed of. A slow deliberate process should be
utilized to minimize contamination generation; hazardous
8/13/2019 Gettign the Most Out of the Clean Room Design
9/10
660 ASHRAE Transactions: Symposia
materials should be identified in advance and removed accord-
ing to regulations.
Contamination-generating materials should be properly
bagged upon removal and immediately removed from the crit-
ical environment. A staging area for outgoing and incoming
materials should be established. Personnel should be badged
and identified as critical environment workers and noncriticalenvironment workers. The established acceptable protocol
should be identified and maintained at all times.
Products identified as salvageable and slated for re-instal-
lation or re-use should be identified immediately upon
removal to the staging area and be cleaned and wrapped for
storage. When re-installing they should be unwrapped and
cleaned with the accordance of the incoming material proto-
col.
With demolition complete, re-installation of the salvaged
materials and new material installation can now begin. All
materials should be treated as new and follow the incoming
material protocol. Construction should occur under a build
clean protocol that is equal to or exceeds that of the operatingfacility. Final (super) clean should occur prior to removal of
temporary construction barriers. Equipment should then be
moved in through the staging area under the incoming material
protocol and set in place under operating protocol conditions.
PRINCIPLES FOR CONTROLLING COSTS
Design to the appropriate level of contamination control
required.
Design for changing conditions.
Design utilities to be easily connected and disconnected.
Design utilities to flow at adequate rates, constant pres-
sure, and typical levels of purity.
Place much of the process equipment outside of the
clean environment.
Control entry and egress of people, material, and equip-
ment.
Provide for ease of maintenance, access, and periodic
inspections.
Manage each of the disciplines to the approved project
budget throughout the design and the constructionphases.
8/13/2019 Gettign the Most Out of the Clean Room Design
10/10