146
Geotechnical Engineering Aspects of Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project TATSUOKA F TATSUOKA, F. Tokyo University of Science 1

GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects ofGeotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

TATSUOKA FTATSUOKA, F.Tokyo University of Science

1

Page 2: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues related to geotechnical engineeringrelated to geotechnical engineering

- Cement-mixed soil- OthersOthers

■ Concluding remarks2

Concluding remarks

Page 3: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Trans-Tokyo Bay Highway

15.1 km-long toll highway3

g g y

Page 4: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Brief historyMay 1971:The technical investigation t t dstarted.

May 1983:The Japanese GovernmentThe Japanese Government approved the construction.

October 1986:The Trans-Tokyo Bay Highway Corporation was established.

M 1989May 1989:The construction started.

December 1997:December 1997:The construction completed; and the highway was opened to

4public on 18th December.

Page 5: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Trans-Tokyo Bay Highway

5

Page 6: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

Kisarazu man-made island

Kawasaki man-made island

Bridge

6

Page 7: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Structure of TTB Highway

・Ukishima access; ・Two 9.5 km-long shield tunnels; ・Kawasaki man-made island; ・Kisarazu man-made island;Kawasaki man made island; Kisarazu man made island;・Bridge

PLAN

PROFILEPROFILE

7

Page 8: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

The starting point of the shield tunnels

8

of the shield tunnels, towards the center of the Tokyo Bay

Page 9: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Steel caisson:1) to start the shield tunnel construction;1) to start the shield tunnel construction;2) the ventilation tower after competition.

Approach fill, retaining shield tunnels.Approach fill, retaining shield tunnels.

9

Page 10: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

10

Page 11: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Structure of TTB Highway

・Ukishima access; ・Two 9.5 km-long shield tunnels;・Kawasaki man-made island; ・Kisarazu man-made island;Kawasaki man made island; Kisarazu man made island;・Bridge

PLAN

PROFILEPROFILE

11

Page 12: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Kawasaki man-made island

Cross-section

12Artist’s view of the completed structure

Page 13: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

A huge offshore diaphragm wall;- 98 m in int. dia.; & 119 m in height; g

13An artist’s view from underground

Page 14: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

A i f di h llA ring space for a diaphragm wall

190 m

14

Page 15: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Kawasaki man-made islandImmediately after

Immediately before the ground excavationImmediately after the end of ground excavation

15

Page 16: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ground improvement by sand compaction pile technology

16

Page 17: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ground improvement by sand compaction pile technology

17

Page 18: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Construction of external and internal steel structures after necessary ground improvement work

18

Page 19: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

19

Page 20: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

20

Page 21: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Filling up the ring space with cement-mixed sand slurry

21

Page 22: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Construction of a diaphragm wall in the cylindrical ring of cement-mixed sand fill and cement mixed in situ soft claycement-mixed in-situ soft clay

22

Page 23: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Filled with mud slurry:

Excavation machine

yWhy the vertical wall can stand without support for a so

23

Excavation machine large depth ?

Page 24: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

24

Page 25: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Excavation of the inside ground

25

Page 26: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Excavation of the inside ground

26

Page 27: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Construction of the internal structure inside the diaphragm wall

27

Page 28: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Structure of TTB Highway

・Ukishima access; ・Two 9.5 km-long shield tunnels;・Kawasaki man-made island; ・Kisarazu man-made island;Kawasaki man made island; Kisarazu man made island;・Bridge

PLAN

PROFILEPROFILE

28

Page 29: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Two 9.5 km-long shield tunnels

29

Page 30: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Two 9.5 km-long shield tunnels

2 2 2 22 2 2 2

Two tubes; constructed Th thi d i th f tThe third one; in the future.

Eight shield tunnel machines worked simultaneouslyt d th t t l t ti i d

30to reduce the total construction period.

Page 31: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Blind typeBlind type using pressurized mud slurryslurry

The world’s largest diameterThe world s largest diameterat the time of construction

14.14 m

31

Page 32: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

32

Page 33: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Development of shield tunnel diameter

33

Page 34: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Blind typeBlind type using pressurized mud slurryslurry

The world’s largest diameter

Pressurized mud slurry

The world s largest diameterat the time of construction

Pressurized mud slurry.Why ? 14.14 m

34

Page 35: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Shield tunnel machine re-assembled to startfrom Kawasaki m-m island

35

Page 36: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Two 9.5 km-long shield tunnels

36

Page 37: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Secondary inner RC liningy g(inside the RC segments)

RC segments

37

Page 38: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Structure of TTB Highway

・Ukishima access; ・Two 9.5 km-long shield tunnels; ・Kawasaki man-made island; ・Kisarazu man-made island;Kawasaki man made island; Kisarazu man made island;・Bridge

PLAN

PROFILEPROFILE

38

Page 39: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Kisarazu man-made island

Shield t ltunnels

39

Page 40: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Structure of TTB Highway

・Ukishima access; ・Two 9.5 km-long shield tunnels; ・Kawasaki man-made island; ・Kisarazu man-made island;Kawasaki man made island; Kisarazu man made island;・Bridge

PLAN

PROFILEPROFILE

40

Page 41: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues related to geotechnical engineeringrelated to geotechnical engineering

- Cement-mixed soil- OthersOthers

■ Concluding remarks41

Concluding remarks

Page 42: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

One of the proposals that were not acceptedp p p

42

Page 43: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Four difficult design factors that controlled the structural form

・A relatively deep sea;

that controlled the structural form

・Heavy shipping routes;

43

Page 44: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

44

Page 45: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Four difficult design factors that controlled the structural form

・A relatively deep sea;

that controlled the structural form

・Heavy crossing shipping routes;・Poor ground conditions; and・A high seismic activity.

Late Holocene very soft clay

Early Holocene sand and clay

45

Page 46: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

46

Page 47: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

47

Page 48: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Four difficult design factors that controlled the structural form

・A relatively deep sea;

that controlled the structural form

・Heavy crossing shipping routes;・Poor ground conditions; and・A high seismic activity.

Late Holocene very soft clay

Early Holocene sand and clay

48

Page 49: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Very high seismic activityIn Tok o Ba areaIn Tokyo Bay area

19231923The Great Kanto Earthquake

49

Page 50: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues related to geotechnical engineeringrelated to geotechnical engineering

- Cement-mixed soil- OthersOthers

■ Concluding remarks50

Concluding remarks

Page 51: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering 1:

Large scale improvement of existing soft clay deposits

related to geotechnical engineering - 1:

Large-scale improvement of existing soft clay deposits by cement mixing in place,

controlling the strength of cement mixed soft clay; and- controlling the strength of cement-mixed soft clay; and - in total 3.77 million m3.

51

Page 52: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ground improvement techniques by cement-mixingused in the TTB Highway projectused in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3

Ordinary DMM Cement: 140 kg/m3

W/C ratio: 100 % Ka asaki m m island 132W/C ratio: 100 % Kawasaki m-m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248W/C ratio: 100 % Kisarazu m m isl 289W/C ratio: 100 % Kisarazu m-m isl. 289

Kawasaki m-m isl. 168

Slurry type cement-mixed Sand: 1 177 kg/m3 Ukishima Access 1 028Slurry type cement mixed Sand: 1,177 kg/m Ukishima Access 1,028sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118

Sea water: 505 kg/m3Sea water: 505 kg/m

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435cement-mixed sand Cement: 100 kg/m3

52

gAnti-segregationadhesive 110 g/m3

Page 53: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

Very soft clay improved by in-situ cement-mixing,achieving a controlledachieving a controlled strength; i.e.,a) strong enough fora) strong enough for

the stability of the structure; and

53b) weak enough for

smooth tunnelling.

Page 54: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

54

Page 55: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Cement mixing in placeof soft clay deposits

55

Page 56: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Haneda airport-restriction to the height of gthe construction plants (50 m)

56

Page 57: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Conventional design for cement-mixed soft clay:

Allowable stress method i th ki tensuring the working stress

evaluated by the elastic theory be smaller than thetheory be smaller than the allowable stress, equal to about 1/6 of unconfinedabout 1/6 of unconfined compressive strength

→ Unduly conservative design for huge masses q – ε1 relations from U & CU TC tests on cement-mixed

g g

clay (aw= 20 %) (Kobayashi & Tatsuoka, 1982).

Page 58: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant effects of drained condition anddrained condition and confining pressure (when drained)drained)

→ The in-situ stress-strain behaviour is largely different from the unconfined compression test

→ Need for triaxial tests

q – ε1 relations from U & CU TC tests on cement-mixed clay (aw= 20 %) (Kobayashi & Tatsuoka, 1982).

Page 59: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Following the principleFollowing the principle of effective stress, as ordinary soilsordinary soils

Peak stress envelops fromPeak stress envelops from U and CD & CU TC tests on uncemented clay and cement-mixed clay (aw= 8 %, 10 %, 14 % & 20 %) (T t k & K b hi(Tatsuoka & Kobayashi, 1983).

Page 60: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant effects of confining pressure onconfining pressure on the drained peakstrengthstrength

→ Not used in the design gto take into account effects of progressive failure

Normalised drained peak pstrength plotted against σc’ for cement-mixed clay (Kobayashi & Tatsuoka, 1982).

Page 61: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant effects of confining pressure onconfining pressure on the drained residual strengthstrength

→ Used in the design as gthe conservative strength

Normalised drained residual strength plotted

i t ’/ f tagainst σc’/qu for cement-mixed clay (aw= 8 %, 10 %, 14 % & 20 %) (Kobayashi14 % & 20 %) (Kobayashi & Tatsuoka, 1982).

Page 62: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Nearly no effects ofNearly no effects of confining pressure on the undrained peakthe undrained peak and residual strength at low consolidation a o co so da opressure

Normalised undrainedNormalised undrained peak and residual strengths plotted against σc’/qu for cement-mixed clay (Kobayashi & Tatsuoka(Kobayashi & Tatsuoka, 1982).

Page 63: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Large-scale yield stress, qy, divided by qu versus effective confining pressure divided by q from CD TC tests onconfining pressure divided by qu from CD TC tests on cement-mixed clay (Kobayashi & Tatsuoka,1982)

Page 64: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

qr/qu or q /q / (d i d) fqy/qu qr/qu (drained) for

design under static conditionDesign strength in static condition

ADesign strength in zone A was used in the limit equilibrium

qr/qu (undrained)for seismic

the limit equilibrium stability analysis

design

qy/qu (Y1: drained)Normalised drained and undrained residual strengths & drained yield stress plotted against

’/ (T t k & σc’/qu0 σc’/qu (Tatsuoka & Kobayashi, 1983)

Page 65: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

Very soft clay improved by in-situ cement-mixing,achieving a controlledachieving a controlled strength; i.e.,a) strong enough for thea) strong enough for the

stability of the structure; and

65b) weak enough for

smooth tunnelling.

Page 66: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Controlled shear strength of cement-mixed soft clay

qmax (kgf/cm2) (t= 28 days)wn (%) γt (gf/cm3)

Compressive strength after cement mixingmixing

: qu by unconfined compression testsx : qmax by CU TC tests

Original ground:qu (kg/cm2)= 0.044z – 0.88(z= depth; z= 0 m at TP= 0.0).( p )

(m)

66

Page 67: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Too large scatter in the unconfined compressive strength due to effects of sample disturbance, not reliable:Fi l d i i b d th CU TC t t

qmax (kgf/cm2) (t= 28 days)wn (%) γt (gf/cm3)

Final decision based on the CU TC tests.

Compressive strength after cement mixingmixing

: qu by unconfined compression testsx : qmax by CU TC tests

Original ground:qu (kg/cm2)= 0.044z – 0.88(z= depth; z= 0 m at TP= 0.0).( p )

(m)

67Reliable data ?

Page 68: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering 2:

Construction of large embankments by using

related to geotechnical engineering - 2:

Construction of large embankments by using - cement-mixed sand slurry with a controlled strength at the ramp sectionsat the ramp sections.

68

Page 69: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ground improvement techniques by cement-mixingused in the TTB Highway projectused in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3

Ordinary DMM Cement: 140 kg/m3

W/C ratio: 100 % Ka asaki m m island 132W/C ratio: 100 % Kawasaki m-m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248W/C ratio: 100 % Kisarazu m m isl 289W/C ratio: 100 % Kisarazu m-m isl. 289

Kawasaki m-m isl. 168

Slurry type cement-mixed Sand: 1 177 kg/m3 Ukishima Access 1 028Slurry type cement mixed Sand: 1,177 kg/m Ukishima Access 1,028sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118

Sea water: 505 kg/m3Sea water: 505 kg/m

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435cement-mixed sand Cement: 100 kg/m3

69

gAnti-segregationadhesive 110 g/m3

Page 70: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

Embankment ofcement-mixed sand slurry

ithwith:a) a controlled strength;

andand b) a controlled high density

to resist the buoyant 70

yforce of the tunnels.

Page 71: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underwater placement of cement-mixed sand slurry

71

Page 72: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

72

Page 73: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

73

Page 74: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

No previous construction experiences

→Placement test in a ship-building dock; and block-sampling from the deposit to obtain specimens forsampling from the deposit to obtain specimens for laboratory stress-strain tests to evaluate the strength and stiffnessand stiffness

74

Page 75: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

7526 August 1988 ( several years before the actual construction)

Page 76: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

7626 August 1988 ( several years before the actual construction)

Page 77: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Reduction of the strengthby absorbing waterby abso b g ateduring under-waterplacement

77

Page 78: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Reduction of the strength by absorbing waterduring under-water placement, not due to losing the cement conentdu g u de ate p ace e t, ot due to os g t e ce e t co e t

78

Page 79: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Sampling of large samples(30 cm in dia) to evaluate possible large scale effects by possibily siginificant in-h i f h i lhomogeneity of the material placed under water.

It was found after TC testsIt was found after TC tests on these large samples and small samples that it was notsmall samples that it was not the case.

79

Page 80: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

80

Page 81: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Triaxial testing system for 30 cm-dia. specimens

81

pat the University of Tokyo.

Page 82: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Triaxial testing system for small specimens

82

for small specimensat the University of Tokyo.

Page 83: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Use of LDT with small and large specimens

8312 cm H x 5 cm D 60 cm H x 30 cm D

Page 84: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Membrane

Pseudo-hinge

Phosphor bronzestrain-gaged strip

LDT Instrument leadwire

TerminalGage leadwireActive e.r.s.g.

B'

Heart of LDT(includes electric resistance strain gages, PB strip

(Front)

Teflon tube protection

D' C

A

No. 2

No. 1

Front face (tension side)

terminals, wiring, sealant)

Scotch tape used to fix wireon the specimen surface

(Front)

C'

A'

B

DNo. 3

p

Instrument Leadwire (Back)

Back face (compression side)

No. 4

LDT; Local deformation transducer (Goto et al 1991)

Membrane Surface

84

LDT; Local deformation transducer (Goto et al., 1991).

Page 85: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Dr. Goto,S.; the inventor of LDT (local deformation transducer)LDT (local deformation transducer)

Institute of Industrial Science,University of Tokyo,y y ,1986

85

Page 86: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Summary of results from CD TC tests on large core samples of slurry type cement-mixed sand (Uchida et al., 1993) - Significant effects of consolidation pressure

Page 87: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Summary of results from CU TC tests on large core samples of slurry type cement-mixed sand (Uchida et al., 1993) - Insignificant effects of consolidation pressure

Page 88: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Essentially no scale effects on the peakeffects on the peak strength !

But large scale effects on the stiffness → Why?

C i f ’ t ll

on the stiffness → Why?

Comparison of q-’externally measured axial strains from CU TC tests using small andCU TC tests using small and large core samples from the same mass of slurry type y ypcement-sand constructed in the full-scale field

d t l t t tunderwater placement test (Tatsuoka et al., 1997).

Page 89: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Essentially no scale effects on the peakeffects on the peak strength !

But large scale effects on the stiffness → Why?

C i f ’ t ll

on the stiffness → Why?

Comparison of q-’externally measured axial strains from CD TC tests using small andCD TC tests using small and large core samples from the same mass of slurry type y ypcement-sand constructed in the full-scale field

d t l t t tunderwater placement test (Tatsuoka et al., 1997).

Page 90: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

A typical CU TC test on a large core sample of slurry type cement-mixed sand (Tatsuoka & Shibuya 1991)type cement mixed sand (Tatsuoka & Shibuya, 1991).

Page 91: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1
Page 92: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1
Page 93: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

A typical CU TC test on a small core sample of slurry type cement-mixed sand (Tatsuoka & Shibuya 1991)type cement mixed sand (Tatsuoka & Shibuya, 1991).

Page 94: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1
Page 95: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Einitial: the value that had been reported by an geotechnical consultant

b t i i l t t f ll i th ti t th t ti→ by triaxial tests following the common practice at that time→ a significant underestimate (about 1/10) of the true value of

small-strain stiffness to be used in deformation analysis ofsmall-strain stiffness to be used in deformation analysis of the cement-mixed soil in the field

Page 96: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

The first case where:

1. LDT was used for a practicalcase; and

2 th l ti d l f2. the elastic modulus from triaxial tests exhibits nearly the same value with thatthe same value with that from the field shear wave velocity.

96

Page 97: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

The Young’s modulus valuethat had been obtained by

t h i l lt ta geotechnical consultant:Einitial = 0.3 Gpa(by conventional drained TC(by conventional drained TC tests)

Thi l id blThis value considerablyunderestimates the true elastic modulus:elastic modulus: E0= 3.0 GPa

and also the value at theoperating strain !

Th i i h fThe engineers in charge of the TTB Highway project could become confident with

97

could become confident with the use of this material for this project !

Page 98: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Shear modulus vs shear strain relations from monotonic and cyclic loading triaxial tests on core samples (30 cm in diameter) from test fills of slurry type cement-mixed sand (Tatsuoka & Shibuya, 1991).

Page 99: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Strains in the cement-mixed fill lower than 0.05 % (estimated by FEM earthquake response analysis) →by FEM earthquake response analysis) Nearly linear behaviour at small strainsImportance of elastic modulus &d its accurate measurementsp

99

Page 100: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Evaluation of the stress-strain properties of cement-mixed soil filled in the field

to confirm whether fills of cement-mixed soilto confirm whether fills of cement-mixed soil as considered at the design stage were actually constructedactually constructed

100

Page 101: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underwater placement work of slurry type cement-i d d Uki hi A d Kimixed sand at Ukishima Access and Kisarazu man-

made island (Uchida et al., 1993).

Vessel conveying materials(capacity: 1 000 2 000 m3)

Vessel having a mixing l t ( d ti it

Vessel having Tremmie piles(capacity: 3,000 ton)(capacity: 1,000 – 2,000 m3) plant (production capacity:

450 m3/hour)

( p y , )

V l d l Lift (m)

TP 0.0 m

Vessel carry mud slurry(capacity: 2,000 m3)

( )

Mound produced on the sea bed

Page 102: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Rotary core tube sampling at th Uki hi A Original shore

14 m

the Ukishima Access;a) to obtain undisturbed

samples; and

Original shore protection works

y

5 m

N2N1samples; andb) to measure shear wave

velocities.Steel caisson

Toky

o Ba

yH

ighw

ay

N2N1

Shield tunnels*

Tran

s H

S1S2

(*) th t i thi(*) the top one in this figure has not been

constructed)

102

Page 103: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Comparison of elastic the Young’s moduli from triaxial compression tests (E0) and those from field shear wave velocities p ( 0)(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access

E and E are similar !E0 and Ef are similar !

103

Page 104: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Comparison of elastic the Young’s moduli from triaxial compression tests (E0) and those from field shear wave velocities p ( 0)(Ef) in the fill of cement-mixed sand (slurry type), Ukishima Access

E0 and Ef are similar !

104

Page 105: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Completed Kawasaki man-made island

193 mFilling of slurry type Cement-mixed sand

Upper RC slab

189 m98 m

TP 5 mOuter jacket

TP – 6 m

35 m 2.8 m 2.8 m4 m

2.8 m 2.8 m 35 m4 m Filling Outer jacket

Inner wall

TP 5 mTP 0 m TP 0m

46.7

m

Slab

TP – 28 m

SCPDMM

Steel pipe sheet pile

TP – 41.7 mSCP

DMM

Steel pipe sheet pile

74.2

m

m

Bottom RC slabTP – 73 m 6

m

21.

5 m

Bottom RC slab

Continuous diaphragm wall (L= 119 m)

Thickness= 2.8 mThickness= 2.8 m 90 m98 m4 m 4 m

TP - 114 m

Page 106: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Filling up the ring space with cement-mixed sand slurry,Kawasaki man-made island

106

Page 107: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

A typical test result on an undisturbed sample of cement-mixed sand (slurry type)of cement mixed sand (slurry type)

3 200

MPa

) LDT

Pa)

stre

ss, q

(M

1.5

External100

tress

, q (k

P

Dev

iato

r

CU TC (σc’= 127 kPa) CU TC (σc’= 127 kPa)Dev

iato

r st

Axial strain ε (%)0 0.5 1.0

0

Axial strain (LDT) ε1 (%)0 0.005 0.01

0D

107

Axial strain, ε1 (%) Axial strain (LDT), ε1 (%)

Page 108: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Initial Young’s modulus, E0, based on locally measured axial strains vs initial Young’s modulus, Einitial, based on externally

d i l t i f CU TC t t f imeasured axial strains from CU TC tests of specimens prepared in the laboratory and core sample from Kawasaki man-made island slurry type cement-mixed sand (Tatsuoka etman-made island, slurry type cement-mixed sand (Tatsuoka et al., 1997).

Confirmation that the external axial strain measurement in TC tests is

l li blutterly unreliable to accurately evaluate the stiffness at small strains ofstiffness at small strains of cement-mixed soil.

Page 109: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Comparison of elastic the Young’s moduli from triaxial gcompression tests (E0) and those from field shear wave

l iti (E ) i th fill fvelocities (Ef) in the fill of cement-mixed sand (slurry type) Kawasaki man-madetype), Kawasaki man-made island

E0 and Ef are similar !

109

Page 110: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering 2:

Construction of large embankments by using

related to geotechnical engineering - 2:

Construction of large embankments by using - cement-mixed sand slurry with a controlled strength at the ramp sections; andat the ramp sections; and

- dry cement-mixed sand at the flat place of Kisarazu man-made islandKisarazu man made island.

110

Page 111: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ground improvement techniques by cement-mixingused in the TTB Highway projectused in the TTB Highway project

Cement-treatment method Mixing proportion Construction site Volume; 1,000 m3

Ordinary DMM Cement: 140 kg/m3

W/C ratio: 100 % Ka asaki m m island 132W/C ratio: 100 % Kawasaki m-m island 132

Low strength-type DMM Cement : 70 kg/m3 Ukishima Access 1,248W/C ratio: 100 % Kisarazu m m isl 289W/C ratio: 100 % Kisarazu m-m isl. 289

Kawasaki m-m isl. 168

Slurry type cement-mixed Sand: 1 177 kg/m3 Ukishima Access 1 028Slurry type cement mixed Sand: 1,177 kg/m Ukishima Access 1,028sand (*: 80 kg/m3 in the Cement: 100 kg/m3* Kisarazu m-m isl. 351original design) Clay : 110 kg/m3 Kawasaki m-m isl. 118

Sea water: 505 kg/m3Sea water: 505 kg/m

Dry mixture type Sand: 1,330 kg/m3 Kisarazu m-m isl. 435cement-mixed sand Cement: 100 kg/m3

111

gAnti-segregationadhesive 110 g/m3

Page 112: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underwater placement of dry mixture of cement-mixed sand(Ki d i l d)(Kisarazu man-made island):a lower cost and a low quality

112

Page 113: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underwater placement of dry mixture of cement-mixed sand (Ki d i l d)(Kisarazu man-made island): a new method to minimize the segregation of material during placingof material during placing

Special double-chute

113

Page 114: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underwater placement of dry mixture of cement-mixed sand(Ki d i l d)(Kisarazu man-made island)

114

Page 115: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Comparison of elastic the Young’s moduli from triaxial compressionptests (Eo) and those from field shear wave velocities (Ef) at the fill f t i dfill of cement-mixed sand (dry type), Kisarazuman-made islandman-made island

E0 and Ef are similar !115

Page 116: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Summary of elastic Young’s moduli of the cement-treated soils in the TTB Project

E d fi d f t i lEmax defined for strains lessthan 0.001 % from triaxial compression tests using LDTs on undisturbed samples (kgf/cm2)

116Ef from field shear wave velocity Vs (kgf/cm2)

Page 117: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

RCTBS+DC

Slurry Dry

Cement-treated soilDMM

RCT=rotary coringDC=direct coringBS=block samplingTS=fixed-piston thin-wall sampling

G values from

BS+DC

RCT Kazusa

Sedimentary soft rock Kobe Sagara

Miura

Uraga-A

RCT rotary coring

Uraga-B

Tokoname

G0 values from CU TC tests 5000

BS+DC

Local axial strain measurements

s)

versus 1000Range for Soft rocks andC t t t d il

Pa)

or s

oftro

cks

Gf from field shear wave

Cement-treated soils(BS+DC) and clays

{2(1

+ν)}

(Man

d 0.

42 fo

field shear wave velocities 100

G0=

E 0/{5

for c

lays

Pleistocene clay site

(1:2)(1:

1)(ν=0

.5

TSBS

Tokyo bay

Osaka bay

OAP

Suginami

11710 100 1000 5000

10

Gf=ρ(Vs)vh2 (MPa)

Page 118: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Summary of E0 versus qpeak relations from triaxial tests, TTB project (Tatsuoka et al., 1997).

Page 119: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

The strength and deformation characteristics* of cement-mixed soil could be made similar withouta large difficulty to those of natural sedimentary soft rock.

(* should be measured accurately)

1000010,000

10000

10,0001000

E0/q

peak= 1,000

MPa

)

E0/qpeak= 1,0001,000

MPa

)

1000

Pa)

1,000

MPa

)100

E0/qpeak= 100E o (M

E0/qpeak= 100100

E 0(M

100E0/qpeak= 1,000

E0/qpeak= 100

E 0 (M

E0/qpeak= 1,000 E0/qpeak= 100

100

E 0(M

0.1 1 10 10010

Sedimentary softrocks

q (MPa)

Sedimentary soft rocks10

0.1 1 10 100

0.1 1 10 10010

Cement-mixed soil

p

qpeak (MPa)

Cement-mixed soils

E0/qpeak 100

100.1 1 10 100

qpeak (MPa)qpeak (MPa)

Cement-mixed soil having t ll d t th d peak

qpeak (MPa)119

a controlled strength; made intentionally weak

Page 120: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Strength of cement-mixed soil: between soil and concrete

1,000

Manus clay (TC; Jardine 1985)Artificially produced materials

100Manus clay (TC; Jardine, 1985)London clay (TC; Jardine, 1985)

Sand (monotonic torsional shear, n= 0.5)Sand (monotonic drained TC)

Gravel (monotonic drained TC)S d il ( i d i d TC)

10

Pa)

Sandy silt (monotonic drained TC)

Cement-mixed sand in TTB highway project (core samples from full-scale tests)

dry type

1E 0(G

P slurry type

E0/qpeak= 1,000

0.1

Steel (SS41)Hard rock core

(ultrasonic for E0)Concrete

0.01

ConcreteMudstone (Sagamihara)*

Mudstone (Sagara)*Sand/mudstone (Sagara)**: Sedimentary soft rock

E0/qpeak= 100

1200.01 0.1 1 10 100 1,000qpeak (MPa)

: Sedimentary soft rock

Page 121: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues related to geotechnical engineeringrelated to geotechnical engineering

- Cement-mixed soil- OthersOthers

■ Concluding remarks121

Concluding remarks

Page 122: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering 3:

Construction of shield tunnels;

related to geotechnical engineering - 3:

;a) Consecutively in very stiff cement-mixed soil and very soft

clay at a very shallow depth

122

Page 123: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

A sudden large change Two tunnelsfrom Ukishimag g

in the cutting torque ofshield machine (tonf-m)

from Ukishima

123

( )

Ring number (one ring= 1.5 m)

Page 124: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Ukishima access

Very soft claywith a very thin overlaying soft clay

A danger of floating up

overlaying soft clay

A danger of floating up of the tunnels by large buoyant force acting to the tunnels,g ,compared to a small surcharge; prevented by placing weight i th t l d f l

124in the tunnels and careful tunnelling work.

Page 125: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering - 3:

Construction of shield tunnels with the world’s largest diameter;

related to geotechnical engineering 3:

g ;a) successively in stiff cement-mixed soil and very soft clay at avery shallow depth; andb) underground connection of shield machines with the help of

ground freezing to shorten the drive of each tunnel.

Locations of tunnel connection

125

Page 126: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Two 9.5 km-long shield tunnels

126

Page 127: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Underground connection of shield machines with the help of ground freezing

Longitudinal section

Cutting faceCutting face gg

Second arrived First arrived

Freezing pipe

shield tunnel shield tunnel

Frozen zone

Freezing pipe

127

Frozen zone

Page 128: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Significant design and construction issues related to geotechnical engineering - 4:related to geotechnical engineering 4:

A huge offshorediaphragm wall;

98 m in int dia ; &- 98 m in int. dia.; &- 119 m in heightfor Kawasakiman-made island.

An artist’s view128

An artist s viewfrom the beneath

Page 129: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Construction of the internal structure inside the diaphragm wall

129

Page 130: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Construction of the internal structure

130

Page 131: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Deep well system to avoid the ground failure by seepage Drainage wells

Observationwellsthe ground failure by seepage g wells

Diaphragmwall

A-sandy layer

Thin clay layer

layer

B-sandy layer

Thick clay layer C-sandy layer

131

layer

Page 132: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Drainage wellsObservation

wellsg wells

Diaphragmwall

A-sandy layer

Thin clay layer

layer

B-sandy layerA serious seepage accident;

Thick clay layerC-sandy

layer

accident;

Start of unusual ground 132

c c ay ayelayergwater spouting 14th Nov. 1993

Page 133: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Time histories of ground water spouting and water depth inside the diaphragm wall

Amount ofDepth of waterinside theAmount of

spouting ground water(m3 per day)

diaphragm wall(m)

First stage Second stage

Depth ofwater in theIncrease in the

rate of ground

Amount ofspoutingground water

diaphragmwall

rate of groundwater spouting

ground water

Start of unusualspouting of

Start of pouringsea water intothe inside of thespouting of

ground waterthe inside of thediaphragm wall

133Date for a period from 14 November to 4th December 1993

Page 134: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Time histories of ground water spouting and water depth inside the diaphragm wall

Amount ofDepth of waterinside theAmount of

spouting ground water(m3 per day)

diaphragm wall(m)

First stage Second stage

Depth ofwater in theIncrease in the

rate of ground

Amount ofspoutingground water

diaphragmwall

rate of groundwater spouting

ground water

Start of unusualspouting of

Start of pouringsea water intothe inside of thespouting of

ground waterthe inside of thediaphragm wall

134Date for a period from 14 November to 4th December 1993

Page 135: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Sea water poured to reduce the hydraulic gradient in the ground inside and immediately below the the diaphragm wall

135

Page 136: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Restart of constructionRestart of constructionafter a delay of six months

136

Page 137: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

137

Page 138: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Geotechnical Engineering Aspects of Trans-Tokyo Bay Highway Project

■ History and structure of Trans-Tokyo Bay Highway

■ Four difficult design factors

■ Significant design and construction issues related to geotechnical engineeringrelated to geotechnical engineering

- Cement-mixed soil- OthersOthers

■ Concluding remarks138

Concluding remarks

Page 139: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Brief historyMay 1971 (25):The technical investigation started.

May 1983 (37):The Japanese GovernmentThe Japanese Government approved the construction.

October 1986 (40):October 1986 (40):The Trans-Tokyo Bay Highway Corporation was established.

May 1989 (43):The construction started.

December 1997 (51):December 1997 (51):The construction completed; and the highway was opened to

139

and the highway was opened to public on 18th December.

Page 140: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

CONCLUDING REMARKS-1

The Trans-Tokyo Bay Highway was constructed;a) in a relatively deep sea;a) in a relatively deep sea;b) crossing heavy shipping routes;c) under poor ground conditions; andc) under poor ground conditions; and d) with a high seismic activity.

Several geotechnical engineering design and construction problems had to be solved for theconstruction problems had to be solved for the success of the project.

140

Page 141: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

CONCLUDING REMARKS-2

The ground improvement by four types ofcement-mixing technologies solved a number ofcement-mixing technologies solved a number ofpotential technical problems;

1) in-situ cement mixing of very soft clay;a) conventional type deep mixing method (DMM);a) conventional type deep mixing method (DMM);

andb) low strength-type DMM;b) low strength-type DMM;

and2) embankment using;2) embankment using;a) slurry type cement-mixed sand; andb) dry mixture type cement-mixed sand

141

b) dry mixture type cement-mixed sand.

Page 142: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

CONCLUDING REMARKS-3

Successful construction of shield tunnels with the world’s largest diameter, govercoming several difficult technical problems, including:ga) successive tunnelling in very stiff cement-mixed

soil and very soft clay;y yb) a very shallow depth in a very soft clay with

a danger of floatation of the tunnels; and gc) underground connection of shield machines with

the help of ground freezing to reduce the shield tunnel drive.

142

Page 143: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

CONCLUDING REMARKS-4

The construction of an offshore diaphragm wall with an int. dia. of 98 m and a height of 119 m was delayed g ya half year by a serious seepage accident in the groundinside the diaphragm wall.p g

a) The accident would have become a fatal one for the )success of the project if relevant measures were not taken promptly. y

b) The accident might have not taken place if the hydraulic gradient in the ground inside and immediately below the diaphragm wall had been made substantially lower, for example, by making the

143bottom of the diaphragm wall substantially deeper than the actual one.

Page 144: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Thank you very much for your attentions !Thank you very much for your attentions !

144

Page 145: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

Terima kasih atas perhatian anda !Terima kasih atas perhatian anda !

Home page:145

Home page: http://geotle.t.u-tokyo.ac.jp/index-j.html

Page 146: GeotechnicalEngineeringAspectsofGeotechnical Engineering ... TransTokyoBayHigyway PP.pdf · Trans-Tokyo Bay Highway Project TATSUOKA FTATSUOKA, F. Tokyo University of Science 1

REFERENCES・Uchida K Shioi Y Hirukawa T and Tatsuoka F (1993) “TheUchida,K., Shioi,Y., Hirukawa,T. and Tatsuoka,F. (1993), The Trans-Tokyo Bay Highway Project - A huge project currently under construction”, Invited Paper, Proc. of Transportation , p , pFacilities through Difficult Terrain, Balkema, pp.57-87.

・Tatsuoka,F., Uchida,K., Imai,K., Ouchi.T. and Kohata,Y. (1997), “Properties of cement-treated soils in Trans-Tokyo Bay HighwayProperties of cement-treated soils in Trans-Tokyo Bay Highway project”, Ground Improvement, Thomas Telford, Vol.1, No.1, pp.37-58. pp

T t k F (2010) “C t i d il i T T k B・ Tatsuoka, F. (2010): “Cement-mixed soils in Trans-Tokyo Bay Highway project”, Soils and Foundations, Vol.50, No. 6, pp.785-804

146

804