Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
42A06NE0014 2.15765 CODY 010
ROYAL OAK MINES INC.
MINTEK CLAIM GROUP
CODY TOWNSHIP
1994 ASSESSMENT REPORT
GEOPHYSICS and DIAMOND DRILLING
P.O. Harvey Project Geologist Eastern Canada Exploration Royal Oak Mines Inc.
November 1994nm*ek94.r|M
CONTE42A06NE0014 2.15765 CODY 01 OC
l .0 Summary and Conclusions l
2.0 Property Location and Access l
Table l Claim List 4*
3.0 Ownership 5
4.0 Past Work 5
5.0 Geology 7
6.0 1994 Program 76.1 Geophysics 76.2 Diamond Drilling 8
7.0 Results - MIN94-1 87.1 Geology 87.2 Geochemistry 8
8.0 Conclusions and Recommendations 9
Table 2 Geochemical Analysis 10
List of References 11
Statement of Qualifications 12
Appendix l Drill Hole MIN94-1Drilling Plan Map, Summary Log, Section, Drill Log, Assay Certificate
Appendix 2 Geophysical Report
Royal OakMines Inc.
Eastern Caruda Exploration Division Tot: (TO1-) .T60-1 141 P.O. (tag 2010 l.i Timmins. Ontario
P4N7X7
.2.15765l August 1994 - *-
Ontario Mining Recorder's OfficesMinistry of Northern Development and Mines
RE: Authorization of Paul Coad, Richard Labine, Peter Harvey, Reno Pressacco and/orDiane Carter to act as agent for Royal Oak Mines Inc. when dealing with the ____ submission of work reports
Tfiis is to certify that Paul Coad, Richard Labine, Peter Harvey, Reno Pressacco and/or Diane Carter are authorized to act as agents for Royal Oak Mines Inc. for the purpose of filing assessment work credits and their distribution for a period of one (1) year or until further notice.l
Yours truly,
ROYAL OAK MINES INC.
Ross F. BurnsVice President, Exploration
RFB/Iha
Royal Oak Mines Inc. is listed on the American and Toronto Stock Exchanges - Symbol RYO
(1)
1.0 Summary and Conclusions
The Mintek claim group is located in central Cody township, about 35 km east of the city of Timmins, Ontario. It lies within the Porcupine Mining Division of Ontario, and is almost entirely covered by the waters of Nighthawk Lake (Figure 1).
During March, 1994, a grid was established on the ice and geophysical surveys consisting of Total Field Magnetics, Horizontal Loop Electromagnetics (HLEM) and Induced Polarization (I.P.) were completed.
These surveys outlined three target areas which meet the minimum criteria for drill testing; an I.P. anomaly and two HLEM conductors. The I.P. anomaly was outlined across three lines and is located near shore on the northwest part of the property. The first HLEM conductor (Conductor A) has a magnetic response and is located in the northern portion of the claim group. The second (Conductor B) is located at the southern portion of the group and may relate to a 12 foot wide shear zone with W/n pyrite encountered in a drill hole immediately south of the property.
The I.P. target was drilled with one hole (MIN94-1) between April 10 and 13, 1994, during rapidly deteriorating ice conditions. Unfortunately, the two HLEM conductors could not be drilled safely during this program.
Nothing in the core of MIN94-1 explained the I.P. anomaly. It is feh that because the hole had 315 feet of overburden, with large boulders between 50-120 feet, the cause of the anomaly is probably due to an overburden response.
Future work on the property will include drill testing the HLEM Conductors A and B.
2.0 Location and Access
The property consists of/2^, claims located on the western part of Nighthawk Lake between Poplar Point and Cemetery Point. It is located in Concessions n and m, Lots 6, 7 and 8 of Cody township, within the Porcupine Mining Division of Ontario (Figure 2). Table l lists the claims.
Access to the property is best attained via water from either the Porcupine Peninsula minesite off Highway 803, or from any of the marinas at Highway 101. Drilling on the westernmost claims on land in 1989-1990 was accessed via swampy muskeg trails originating off the Hydro line located about 5 km to the north of tile property.
OOID
PAS
T PR
ODUC
ER
A
OOID
PRO
DUCE
R O
OO
ID O
CCUR
ENCE
O
COPP
ER Z
MC
OCCU
RENC
E.
——
—
MOH1
HAW
K W
EAK
ROAD
S-
— —
-
PAMO
REX
PROP
ERTY
BOU
NDAR
Y- -
HYDR
A LE
AK P
ROPE
RTY
BOUN
DARY
- - - -
OTHE
R PR
OPER
TIES
f
CON IV
NIGHT HAWK
LAKE
CON
CON
LOT 5
ROYAL OAK MINES INC.MINTEK CLAIM GROUP
CODY TWP.CLAIM SKETCH
: March 1994Drawn: P.G.
Fig. 2Scalt: 1:20.000Inferp: J.C. Grant
NTS:Job No. E-46
(4)
Claim
TABLE l
MINTEK PROPERTY CODY TOWNSHIP LIST OF CLAIMS
Status Record tt1025818
1025819
1025820
1025821
1025822
1025823
1025824
1025825
1025826
1025827
1025828
1025829
1025830
1025831
1025832
1025833
1025834
1025835
1025836
1025837
1025841
1025842
1025843
1025844
/l 987
8/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
28/09/1987
8/09/1987
J09/1987
16/TQ/1987
16/10/1987
28/09/1987
28/09/198*5
(5)
3.0 Ownership
The property is KXW-i owned by Royal Oak Mines Inc., subject to a series of advanced royalty payments to the original property vendors (James Croxall and Matti Kangas) and a G.5% N.S.R. to New Coast Minerals (formerly Mintek Resources Ltd.), as well N.S.R. to Messrs. Croxall and Kangas.
4.0 Past Work
Work on the Mintek claim group, as taken from the Assessment Work files, dates back to 1944 when Cocallen Porcupine Mines Ltd. drilled three holes in the sediments along the west shore of Nighthawk Lake (T-432).
In 1966 Texas Gulf drilled four holes in the area, with one hole (C22-4), drilled immediately south of the property, encountering rhyolite and basalt with a 12 foot wide shear zone at the contact containing S'% pyrite (T-1227).
In 1971 the Ontario Department of Mines published Map 2222 (Leahy, 1971) which shows the geology along the shoreline south of the property. He shows a north-east striking sequence of mafic and felsic volcanics which would continue out under Nighthawk Lake and pass through the claim group. Leahy also noted a copper-zinc showing near Poplar Point within the felsic volcanics.
During the winter of 1982, Comstate (Placer Development T-2374) completed geophysical surveys as well as a series of overburden holes on the ice, which helped to define the general stratigraphy of the property under the lake.
In the fall of 1989, Aerodat Airborne Geophysics did a survey to cover Pamorex*s properties along the Nighthawk Break (Figure 1), including the Mintek Property. Pamorex then followed up on this work by drilling two holes in 1989 (MT89-01 and MT89-02) and two holes in 1990 (MT90-01 and MT90-02). An O.M.I.P. report (Robb, 1990) details the results from holes MT90-01 and MT90-02.
This work, as well as the work completed in 1994, is summarized in Figure 3.
Royal Oak MinesMintek Claim Group
Compilation vMapGeology
2 Mafic Volcanics4 Felsic Volcanics5 Sediments9 Diabase
SymbolsCu.Zn Copper/Zinc Showing
Overburden Hole (Comtate T-2374) Diamond Drill Hole
Tg Texas Gulf (T-1227)MT PamorexC Cocollen (T-432)
feetData from Leohy. 1971 (O.G.S. Map 2222).
Ass*S3fiiant lira and thit report.
(7)
5.0 Geology
The general geology of the Nighthawk Lake area is illustrated on O.G.S. Map 2222 (Leahy, 1971). It shows the western shores of the lake to be underlain by Archean mafic volcanics with a minor amount of felsic volcanics. Sediments which overlie these volcanics to the northwest consist primarily of greywackes and interbedded argjllites. All rock types are cut by late diabase dikes and sills.
*
Considerable drilling has occurred in the sediments along the shoreline between Poplar and Cemetery Points. These holes have all cut greywacke and argillite, with intercalated mafic volcanics, but nothing of economic interest was encountered (Robb, 1991).
The more intriguing geology comes from the shoreline to the south of the property, which shows a mafic/felsic volcanic sequence with a copper-zinc showing. This sequence strikes northeasterly and would pass through the central portion of the Mintek claims. In addition, the hole drilled through this sequence by Texasgulf cut a 12 foot wide shear zone with 807o pyrite (T 1227).
6.0 1994 Program
The objective of the 1994 program was to complete geophysical surveys (magnetics, HLEM and I.P.) to both define broad geological trends beneath the waters of Nighthawk Lake, as well as to outline geophysical anomalies that could indicate areas of sulphide mineralization which would warrant drill testing. The complete geophysical report is included here as Appendix 2.
6.1 Geophysics
The HLEM survey located several conductive zones, the most interesting being Zone A and Zone B (Figure 3).
Zone A, at its northern portion (Lines 48N to 60N), is where the zone is at its strongest, and also has a magnetic correlation.
Zone B is a relatively weak conductor and has no magnetic correlation, but because it may relate to the 12 foot wide shear zone with 8% pyrite that was encountered in the drill hole immediately south of the claim group, h also represents a good drill target.
The I.P. survey returned a response that was strongest on Line 3600N, at 22+OOW, and represents the third target area outlined by this program.
6.2 Diamond Drilling
Due to the late start of the program, only one of the three target areas outlined by the geophysical surveys could be safely drill tested off the ice during April.
Drill hole MIN94-1 was collared on Line 36+OON at 16+00W at an azimuth of 3020 and a dip of-SO0, and targeted to explain the cause of the I.P. anomaly on L36+OON at 22+OOW. The first attempt to drill the hole had to be abandoned. After putting down 95 feet of casing and lowering rods to start drilling, the core barrel deflected off boulders, broke off and was lost down the hole. The drill was then moved 3 feet, and then after putting casing through boulders from 50 to 120 feet, another 195 feet of clay and sand was penetrated before finally reaching bedrock at a total depth of 315 feet. The hole was drilled at -500, which means the vertical depth of overburden at the I.P. anomaly is about 250 feet.
7.0 Results-MIN94-1
7.1 Geology
The hole collared into a rhyolite fragmental unit after 315 feet of casing was put down through overburden. The hole then cored a sequence of rhyolite tufls, fragmental, and massive flows with minor intervals of mafic volcanics between them. These fdsics were variably sericite altered, but no significant mineralization was noted. From 568.5 to 857.0 (end), the hole cored chloritic massive and pillowed mafic volcanic flows.
No interesting mineralization was observed in the core, and nothing in the hole explained the I.P. anomaly.
7.2 Geochemistry
A total of eighteen samples were taken from the core and analyzed for their gold content at Royal Oak's assay lab in Schumacher. All samples returned assays of 0.001 opt Au.
Thirteen of the pulps from these samples were then sent to XRAL Assay Labs in Don Mills, Ontario, for I.C.P. analysis.
The original core logging identified samples 65176,65178,65179,65181,65182 and 65184 as being felsic volcanics. This was confirmed as the I.C.P. showed the
(9)
TiCh value for these six samples as being 5Q.25. However, all six samples had high Na2O values ^2.00) and this, combined with the fact that their average Zr was well below l SO and their average Y was well bdow 20, suggests that these samples are from a suite of primitive felsic volcanics, and have not been altered by a hydrothermal event. These results are shown in Table 2.
8.0 Conclusions and Recommendations
The 1994 program was not able to completely evaluate the value of the Mintek Property. Only one of the three drill holes needed to test the best targets outlined by the geophysical surveys was completed due to the late start of the ice-based program. Two attractive HLEM conductors remain untested, and both need to be drilled to completely evaluate the property.
2-
HO
U
tAM
PU
NO.
NO.
MN
M1
M
l 77
MN
M.1
M
17I
MN
M-1
M
ill
MN
M.1
M
IM
MN
M.1
M
IM
MN
M.1
M
IM
MN
M.1
M
IM
MN
M.1
M
1I7
MN
M.1
M
IM
MN
M.1
M
IM
FROM
.TO
ROCK
TVP
tVCO
MM
ENTt
J1 5
ft*M
4 A
Rhvo
Aii k
VMM
flM
M2
0*40
' 0
Ahyfl
J-W .
Mrtc
Hc
4M.0
474.
0 R
hyM
U.M
MK
47I.0
4M.O
R
HyM
M-M
MM
4M.0
4104
R
hydM
.Hpl
lM
I1I4
4M
4
Rhy
MM
.lic.
BM
M0.
04M
4 *4
Ui.o
NaH
)o
IM44174
iHM
-IM
Uht
127.
0477
4 b
ut.
miu
lx
177.
0-71
14
ImM
.lMM
ln
7114
*717
4 jiM
l aB
ram
t Jam
7174
.711
4 *4
Ul.p
*MM
to*
K
PPM 14
14 04
14 04 04 14 14 1.1 1.1 14 04
1.1
HA 2.M
I.M 1.70
1.0*
241
242
141
14*
1.27
1.12
1.10
141
142
MO IM
0.11
0.41
071
0.44
040
1.00
4.91
1.11
4. M 1.11
1.M
tt 110
I.M I.M 1.4 r
Ml
171
7.M
7.91
179
1.12 1.12
744
P 001
OM
O.M
0.0)
O.M
0.04
O.M
0.02 0.02
0.02
0.01
042
049
K 1.M
1.1)
1.14
1.07
1.11
1.11
041
0.21
0.11
0.11
OJO
04*
O 10)
2M 171
4.U 2.2)
IM Ml
171
7.M
1.11
7.72
741
I.M
(C PPM 44 1.1 122
4.1
1.1
1.0
41.1
42.7
41.2
M.I
M4
41.7
Tl tt OJf
t
0.11
0.11 on 0.21
0.11
0.21
0.44 0.41
040
041
041
MIN
T
coe
REM
VP
PM 5
|
44 4ft
1) 41 4)
M 241
941
141
IM 221
970
IK P
P.'
ir TO
TJU
S-
CR PPM IM
1IF
190
141 M 114
141
911
941
101
9M 112
IM
OPC
R1
VNSH
II
MIN
*4
MN
PPM 79
9
414
940
111
210
IM MO
1990
19M
1MO
1110
1900
1410
y t •1 fi tt 2M 1 70
1.2*
2.44 1.9
9
1.44
2.M
744
IM I.M I.M 1.07
1.11
CO PPM 11
1 ft 11 1 0 12 41 M M M tt
41
Nl
PPM 21 19 19
H II ir 11 M M M 41 49
M
CU PPM 190
91.0 1.1
91.0
91.0 4.1
914
1114 M4
M.1
714
M4
ZN
PPM 714
M.I
44.1
1M.O
41.1
104
41.4
194
(94
17.1
M.7
M4
M4
M PPM •9
•1 O
•1 •1 •1 •1 •1 •1 4 4 4
4
W
PPM
120.
0
914.
0
170.
0
111.
0
111.
0
117.
0
941.
0
1474
1094 M.I
1014 114
ttl
Y PPM 1.1
44 7.1
1.4
4.1
tl
114
114
IM 11.1
MjB
PPM 944
117
117
M.I
9*4
11.9 14 14 24 14 44
14
MO
MPP
M
PPM
4 4.
1
4 40
.1
9 0.
1
9 04
1 "0
.1
1 -0
1
9 O
J
9 04
1 01
t *0
.1*
0.2
t 4.
1
CO PPM •0.1
•0.1
•0.1
•0.1
•0.1
•O.I
•0.1
•0.1
4.1
•0.1
4.1
4.1
M
PPM •10
•10
•10
•10
•10
•10
41*
•10
•10
414
•10
41*
M
PPM 10 10 •1 4 •1 1 4 4 1 1 1
M PPM 20
9
2M Ml
lil
7M IM 4M lil 72 42 42 ir
*
IA PPM 144 7.1 10.1 1.4 74 77 104
44
44
44
44 M
W
PPM •10
•10
•10
•10
•10
• 10
•10
•10 •It
•10
41
0
41
0
PI PPM •9
•9 •9
•1 •9 1 •2 •2 •2 t •t 4
II
PPM 1 •1 •1
•1 •1 •1 •J 4 4 4 4 4
(11)
LIST OF REFERENCES
Leahy, E.J. (1971) Geology of the Night Hawk Lake Area, District of Cochrane, Ontario, ODM GR96, Co. Map-2222
Robb, M.E. (1991) Pamorex Minerals Inc., Timmins Division, Regional Exploration, Nighthawk Lake, Mintek Property, O.M.I.P. Report - 1990
(12)
STATEMENT OF QUALIFICATIONS
I, Peter G. Harvey, of the City of Timmins, Province of Ontario, do hereby certify that:
1 I received a B.Sc. degree (Honours) in Geology from Lakehead University, Thunder Bay, Ontario, in 1985.
2 I have been employed as a geologist by various mining companies in Ontario since 1985.
3 I am the author of this report.
4 I have no direct interest, nor do I have any shares of any company exploring the properties described in this report, nor on any adjacent or surrounding properties.
Dated this 11 th day of /Vo/ 1994, Timmins, Ontario.
Peter G. Harvey Project Geologist Eastern Canada Exploration Royal Oak Mines Inc.
APPENDIX l
Drill Hole MIN94-1
r i-h h h
LOT 6
CON IV
NIGHT HAWK
LAKE
CON
CON
LOT 5
ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GROUPTITLE: DRILLING pLftKl
JU'.., M, IN
SUMMARY LOG
Hole Number:
Date Drilled:
Contractor:
Property:
Township:
Claim No.:
Co-ordinates:
Length:
Survey:
Size:
Casing:
Purpose:
Logged by:
Comments:
MIN94-1
April 10-13, 1994
Mckenzie Drilling Ltd.
Croxall-Mintek
Cody
1025832
NHL Grid -2194.6N, -9128.5E, Az 300, dip -500 Local Grid L3600n, Stn 164OOW
857.01
3 Sperry Sun Tests
BQ
50' NW, 320' BW; 200' BW left down hole
Test I.P. anomaly
P. Harvey
Problems with hole. First attempt drilled 95 feet of BW casing, deflected off boulders and broke. Lost core barrel assembly and 12 feet BW casing. Moved drill 3 feet, put casing through boulders from 50-120 feet and put a total of 50 feet of NW and 320 feet BW casing down hole. BW casing would not pull out; left 200 feet BW casing in hole.
A* 300'
A 10818
/02-S832
GEOLOGY LEGEND
OVB Ovotunfcn
Ma6c Volcanic*
2apl amygdaloid*! pillow lava2h lapilli tuff2m
4r4rit4k
ifayolherhyolite lapilli tufflapilli tuff
Ol
)00 _l
NIGHTHAWK LAKEMINTEK MIN94-1
l" - 100'
ROYAL. OAK MINES INC.
RO
YA
L O
AK
tarn
s m
e.Lo
ggtd
B
y!P
AG
EI
W* v
\'l
l^'l
r fs.
Peg*
•rio,:
?DR
ILL
HOLE
-NO
RTHI
NGE
ATI
NG
ELEV
ATIO
NLE
NGTH
.2BL
QBE
INC
LEAS
E
DIS
T/:P
.^.
3.TO
.
. U
5o
.85
.0 .
AZ
IM• ••
;'3oa
v~^.
Sio
S. IP 3 lo
DIP
*MS
*,V
*.5
.*-
.^5 ."4 Sfe
DIS
Tr-
.;.1-
':?
.'^*J
i
. .-^^
AZI
Mm
flOC
L*'^
' ' ^
.X.t
rf'V
;tt,
V-
-..v
-..•-
DIP
•' . '*
*^V
.
DIS
T •' : f
",'.
AZ
IM•'"
7 -tr
.
-:v-
DIP
. •.-:
-.
;'7
y \ V
'.-i/''
11
\\vJ^
••4M1
AZ
X
."f
i 1 i .
DIP
/rr/
Mrf
Ur/ \
DIS
TA
ZIM
DIP
ROCK
DES
CRIP
TIO
N l I
B/*
l J/F
L^
w3H
!iJaB
l[E]^
.10^
—
——
—..:
m^
——
PAG
E 2
DR
ILL
HO
LEPa
g*
Z- of
C*m
l O
r* l
Tti
t l C
al A
lt l N
orn
PAG
E 2
DR
ILL
HO
LE
niNJ
,
Pag
* -S
of
DIS
T
frS
KffS
frl
5r?i
IdRO
CK D
ESCR
IPTI
ONCo
m l
If*
l T*i
t j C
* j A
lt l N
orn
j
STRU
CTB/
S g*.J/
FJ|
*t
MIN
ER
AL
SG
AN
GU
EM
ET
AL
LIC
tot!
nOX
JWvw
'4 M
IFV,
l SB
! X
l W
dth
MC
OM
MEN
TS
1C
OM
MEN
TS
^
PAG
E 2
DRIL
L HO
LE
HlrJ
Po
q* .
of
DIS
T W
ROCK
DES
CRIP
TIO
NCo
m l
trt
l T
ilt
|C*|
Alt
|M*m
B/S
i|A
iJ/
FM
INE
RA
LS
GA
NG
UE
ME
TA
LL
ICC
OM
MEN
TS
lC
OM
MEN
TS
2
|jg-jI
|',yg
'ITO
OB
9EI.'
?JH
ii?S
M P
PV-
S?5
rT*5"
7^^
* ^ '
',T:;
"^7^
'i'ff
l'iB
Kre
gK
^'^
^f^ "*t' ^
Tf"
.1^
!WJ*
'i.
1^^ \
-.'f
^ff.1*^
.V
J;
3.*
.'.
'\ '
-
.t i
' "*
. '
. "V
'.'"
.V
t- .
' :
i l:r
i'-if
i
"781
.0^
3stU
lH
80
f..9
01
Idb
'O . P
7ofoS
lA
rf.
y**Y
*. j
ssas
sa^':
;ii..';.
i^ j^
jianiH
iB^-
-Jt
S-lS
KSa s
&r.'ia
L\3 c
:.. j f
ciii
l?3B3
HWi.T
Of:-3
El J
Ki'i
aiH
IHIIK
IiSE
a^t
rtT
X3*j
fcML
A~To
t, S
.i 15
f/JD
M^^
";^m
i^jff
iBH
^^t'K
g^ag
^
ROYAL OAK ANALYTICAL LABORATORY
CERTIFICATE OF ANALYSIS
/f-^/fc^r^aa*/ SJt&y-M/'?DATB: rt
SAMPLE NUMBER A*
C- •OO/
77
6
8
9
10
11SK
35-
12
13XX
14 y? -00 J
15.ay J
16
17 92.18 C-19
20
21
22
23
24
- Labie Chief Chemist:
APPENDIX 2
Geophysical Report
42A06NE0014 2 15765 CODY 020
GEOPHYSICAL REPORTFOR
ROYAL OAK MINES INC.ON THE
MINTECK CLAIM GROUPCODY TOWNSHIP
TIMMINS, ONTARIO
PREPARED BY: J. C. Grant, CET,FGAC, April 1994
" 42A06NE0014 2.15765 CODY
TABLE OF CONTENTS
PAGE
INTRODUCTION. . . . .. .. . . . . ... . . . . . . . . . . . . . . . . . . . . . . . . . . l
PROPERTY LOCATION AND ACCESS........ . . . . . . . . . . . . . . . . . l
CLAIM GROUP. . .... . . ... ... . . . . . . . . . . . . . . . . . .. .. . . . . . . . l
PERSONNEL....... . . .. ... .... . . . . . . . . . . . . .. .. .. . . . . . . . . l
GRID LAYOUT. .. . .. . . . .. .. . . .. . . . . . . . . .. . ... .. . . ... .... 2
GEOPHYSICAL PROGRAM.... . ... . . . . . . . . . . . . . . ... ... . . . . . . 2
BASE MAPS.. . .. . . .. . . . . . . . . . . ... . .. .. . . . . . . . . . . . . . . . . . 3
SURVEY RESULTS.. . . . . .. . .. .. . . . . . . . . . . . . . . . . . . . . . . . . . . 3
CONDUCTIVE ZONES..................................... 4
CONCLUSIONS AND RECOMMENDATIONS...... . . . . . . . . . . . . . . . . 5
CONDUCTIVE CHARACTERISTICS TABLE l................... 7
CERTIFICATE
FIGURES l - LOCATION MAP2 - PROPERTY LOCATION MAP3 - CLAIM SKETCH4 - GEOLOGY MAP
MAPS - CONTOURED MAGNETIC SURVEY- MAX MIN II 444 HZ- MAX MIN II 1777 HZ-IP PSEUDO SECTIONS
APPENDIX A - EDA OMNI IV MAGNETIC SYSTEMB - APEX PARAMETRICS MAX MIN II SYSTEM C - EDA IP-4 RECEIVER AND SCINTREX IPC-9 2.5 KW
TRANSMITTER
Page l
INTRODUCTION
The services of Exsics Exploration Limited were retained to lay out a grid and complete a geophysical program over a group of claims which are situated in Concession III lots 6,7, and 8 of Cody Township.
The purpose of the program was to test the property for favourable geological structure which would be target areas for base metal and /or gold deposition.
The program was completed during the latter part of March and the first week of April, 1994.
PROPERTY LOCATION AND ACCESS
The Minteck Property is located in Concession III lots, 6, 7, and 8 of Cody Township. Porcupine Mining Division District of Cochrane in Northeastern Ontario.
The survey grid is situated between Poplar Point and Cemetary Point and is entirely covered by water. Refer to Figures 2 and 3.
Access to the grid during the survey period was ideal. Highway 101 east travels east from the City of Timmins to the junction of Royal Oaks access road which travels south to the Penninsula Mine site on Night Hawk Lake. Figures l and 2.
A fifteen minute skidoo ride will provide acess to the center of the grid area.
CLAIM GROUP
The Mintek property consists of the following claims.
P-1025818 to P-1025837 inclusive 20P-1025841 to P-1025844 inclusive -!
Total Claims 24
Refer to Figure 3, from MNDM Plan Map G-3994 Cody Township
PERSONNEL
The field crews directly responsible for laying out the grid and recording all survey data were as follows:
John Grant Geophysist Timmins, OntarioYvon Col l in Operator Timmins, OntarioRichard Mathieu Operator Timmins, OntarioRobin Mathieu Assisstant Timmins, OntarioDave Clement Helper Timmins, OntarioPaul Otis Helper Timmins, OntarioChris Dube Helper Timmins, Ontario
mumV ' mm* •VAUMK
PROPERTY LOCATION l
EXSICS EXPLORATION LTD.f A BM PM-TXI
IK-Mf-481
ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GROUPTITLE: CODY TWP.
LOCATION MAP Fig. l
March 1994 Scale: NTS:
Drawn: P.G. toterp: J.C. Grant Job No. E-48
4————— ———-.—" r . -•^- i ^""3?* ' "REID l }cARM{aiE
r^n \i'- ?wUJ-
^l^'/pli T4J^j~ ~-^-- .— v^-^mL ^ "^ Vi
—21 , - ^. -y-^'o-KPaiWii.iiliii Fjlh i \*
-NORTHRUPVt**^"
od i
vw.
N
EXSICS EXPLORATION LTD.PA Bw Mlt MN-1X1
T*!MM: 7K-MI-4B1 :
CLIENT: ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GROUPTITLE: CODY TWP.
PROPERTY LOCATION ^ 2Datt: March 1994Drawn:
Seal t: tSOO.OOOlnterp:J.C. Grant
NTS:Job No. E-
NIGHT HAWK
LAKE-_-.---
LOT 9
EXSICS EXPLORATION LTD.ra. BMUN Q.
7K-2CT-4MI. -481
CUENT: ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GROUPTITLE: CODY TWP.
CLAIM SKETCH Flq. 3Date: March 1994Drawn: P.G.
Scalt: h20.000Interp: J.C. Grant
NTS:Job No. E-48
\"T
___LI__,
NIGHT
VIST v\;\\
EXSICS EXPLORATION LTD. ra. BM m*. MN-IXISrilt O.
OJENT: ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GROUPTITLE: CODY TWP.
GEOLOGY MAP: April 1994
Drawn:Scait: r-l72mHeInterp: J.C. Grant
Fig. 4NTS:Job No. E-48
Page 2
GRID LAYOUT
The baseline was first established on the ice by a transit crew working directly for Royal Oak Mines Inc. The baseline was turned off from a known base station and put in at an Azmuth of 032 degrees from LO+OON to L66+OON.
Cross lines were then turned off of this baseline at 300 foot intervals from LO+00 to L66+OON.
Station intervals along these crosslines were set at 100 foot intervals. In all, a total of 20.69 miles of grid lines were established on the property.
GEOPHYSICAL PROGRAM
This program consisted of a Total Field Magnetic survey, Horizontal Loop, Electromagnetic survey, (HLEM) and an Induced Polarization, (IP) Survey.
The Total Field Magnetic and HLEM Surveys were completed over the entire grid. The IP survey was completed over every second line of the grid beginning on L300MN.
The Magnetic survey was completed using the EDA OMNI IV System. Specifications for this system can be found as Appendix A of this report.
The following parameters were kept constant throughout the survey period.
Field Unit: -EDA OMNI IVBase Unit: -EDA OMNI IVLine Interval: -300 footStation Interval: -50 footBase Station: -Reading interval 10 seconds.Reference Field: -59,000 gammasDatum Subtraction: -58,300 gammasAccuracy: - + J- 0 .5 gammasContour Interval -10 gammas
The HLEM Survey was completed using the APEX Parametrics Max Min II System. Specifications for this system can be found as Appendix B of this report.
The following parameters were kept consistant throughout the survey.
Coil Seperation: -600 footTheoretical Search Depth: -300-400 footSide Seeking Ability: -300 footLine Interval: -300 footStation Interval: -100 footFrequencies Read: -1777 Hz S 444Hz
Page 3
Parmeters Measured: -Inphase and Quadrature componets ofthe secondary field
Accuracy: - -i-/- 1^ Profile Scale: - lcn^ t/- 20% Configuration: -Horizontal Loop Mode
The IP Survey was completed using the EDA IP-4 Receiver and the Scintrex IPC-9 2.5 KW transmitter. Specifications for this system can be found as Appendix C of this report.
The following parameters were kept consistant throughout the survey:
Receiver: -EDA IP-4Transmitter: -Scintrex IPC-9Motor Generator: -8HP Briggs fc StratonElectrode Array -Dipole - DipoleMode: -Time DomainA Spacing: -100 footN Read: -^ 1-4Pulse Time: -2 second on 2 seconds offChargeability Window Plotted: -|3Delay Time: -500 MSIntegration Time: -420 MSPresentation: -Individual line Pseudo Sections
BASE MAPS
The Magnetic and HLEM Survey results were then plotted onto a base map at a scale of 1:200 feet. One base map for the magnetic survey and each of the HLEM frequencies.
The IP data was plotted as single line Pseudo Sections for each line read.
The base maps are included in the back pocket of this report. The Pseudo Sections are also contained in the report as pull outs.
SURVEY RESULTS
The HLEM surveys was successful in locating several electromagnetic trends across the property. Each of these targets will be discussed separately and in detail below. The Magnetic survey will be interpreted along with each zone.
The IP survey was also successful in locating and detailing two target areas which did not appear on the HLEM results.
Again each zone will be discussed in detail below.
During the course of the HLEM survey, it was noted that the lake bottom sediments proved to be highly conductive, suggesting it may be comprised of several layers of thick clay. This is well documented throughout the HLEM survey and is represented by the
Page 4
large spread in readings between the Inphase and Quadrature components for each frequency.
CONDUCTIVE ZONES
Generally the HLEM survey was successful in locating and outlining several conductive zones across the survey grid. The most predominant zones have been labelled Zone A and Zone B and they will be discussed seperately and in detail below. The shorter, questionable features have also been labelled and will be discussed below.
Zone A:
This feature represents the most predominant zone on the grid. It appears to strike parallel to the baseline and extends from L2400N/1100W to L6000N/200W and in fact may extend as far as L6600N/200E, (Labelled Zone D).
The southern extension of the zone is somewhat weaker and has been interupted by several cross structures. These cross structures have been noted by the magnetic survey. One structure appears to parallel Line 3000N and a second structure strikes north-south across lines 2100N to 4500N.
The northern portion of the zone is a stronger more consistent section but again appears to have been interupted by a second north-south cross structure striking across lines 5400N to 6600N. This structure was also well defined by the magnetic survey and may in fact relate to a diabase dike. The northern portion of Zone A, (Zone D) which cuts across L4800N/200W to L6000N/130W lies along the eastern flank of a moderate magnetic unit.
Interpretation of the HLEM data positions the zone at a depth to source of 140 - 170 feet with a conductive range of 5 to 6 MHOS. It also appears to dip slightly grid east to near vertical.
Zone D in fact may be an extension of Zone A which has been faulted and shifted to the northeast. Its conductor characteristics are similar to Zone A, putting Zone D at a depth to source of 75-80 feet and a conductivity range of 5MHOS. The zone also lies along the eastern flank of a moderate magnetic unit.
The IP survey coverage over Zone A and D did not return any encouraging results.
Zone B:
This feature parallels the strike of the Baseline and runs from L600N/300E to L1200N/200E. This feature is somewhat weaker or deeper than Zone A and does not have any direct magnetic correlation.
Page 5
However, this zone may represent the northern extension of a shear zone tested by a drill hole completed by Texas Gulf which did return 8% pyrite in a 12 foot shear zone. This hole was collared to the southeast of LO/BL.
Again, the IP survey did not return any encouraging results across this zone.
Zone C:
This zone represents a somewhat weak, questionable feature parallelling the base line. It strikes from L2700N/2000E to L3600N/2200E, albeit it is somewhat distorted.
The zone has a weak magnetic correlation associated with it but generally follows the western flank of a stronger magnetic unit which most probably is the signature of the diabase dike to the immediate east.
The IP survey across line 3300N did show a moderate conductive zone situated at 2000 to 2100E. The resistivity low and moderate chargeability high suggest that sulphides may be present, however, further work is required before a more definite interpretation can be done.
Zone E:
This zone represents a weak questionable feature first noted on L2400N/2200W and again on L3900N/1900W. The feature appears to follow a weak magnetic unit. The northern extension of thisfeature has an associated magnetic low signature suggesting it may relate to a weak alteration zone.
The IP coverage on the western end of line 3300N detected a moderate IP zone represented by a resistivity low and chargeability high suggesting sulphides. Lines 3000N and 3600N were also read to cover the same IP target. L3600N returned a good IP response and should be tested by drilling.
CONCLUSIONS AND RECOMMENDATIONS
Generally the surveys were successful in outlining several target areas across the grid.
Certainly Zone A represents the best looking target on the grid as it has moderate to good conductivity and moderate magnetic correlation.
Zone B is of interest as it may represent the northern extension of a drilled shear zone known to carry sulphides.
Zone C also represents an interesting structure because of the IP correlation and moderate magnetic correlation.
Page 6
Zone E represents a good sulphide target which was also well defined by the IP survey. The zone also has direct magnetic low association suggesting it may relate to a weak alteration zone with sulphide content.
The magnetic survey also proved the existance of several major cross structures which probably relate to diabase dikes and/or minor faulting.
I would recommed drilling of the IP response located on L3600N, 2200W as well as Zone A. Should either target area return favourable results then Zone B and C should also be followed up.
Respectfully Submitt
John C. Grant,
Page 7
CONDUCTIVE CHARACTERISTICS TABLE I
ZONE LOCATION DEPTH DIP CONDUCT- IP CORR MAG CORRIVITY
A
B
C
D
L24N/11W-L60N/2W
L6N/3W-L12N/2W
L27N/20E-L36N/22E
L63N/2E-L66N/220E
130-170'
n/a
n/a75'
vert
vert
vert
vert
5-6 MHOS
weak
weak
5-6 MHOS
n/a
n/a
direct
n/a
moderate
n/a
moderate
mod-goodNote: Zone D may be an extension of Zone A
E L24N22W-L39N/19W deep vert weak direct mod-low
ABOVE RESULTS ARE BASED ON HLEM 444 HZ RESULTS
CERTIFICATE
I, John C. Grant, hereby certify that:
1) I am a graduate geophysicist (1975) of the three year program in Geological Technology at Cambrian College of Applied Arts and Technology, Sudbury, Campus. I have worked subsequentely as an Exploration Geophysicist for Teck Exploration Limited (5 years), North Bay office, and as Exploration Manager and Geophysicist for Exsics Exploration Limited from 1980 to present.
2) I am a Member of the Certified Engineering Technologist Association since 1984.
3) I am a member of the Geological Association of Canada.
4) I have been actively engaged in my profession for the last seveenteen (17) years, including all aspects of exploration studies, surveys and interpretations.
5) I have no specfic or special interest in the described property. I have been retained as a Consulting Geophysicist, for property appraisal.
John Charles Grant,
APPENDIX
Four Magnetometers in OneSelf Correcting for Diurnal Variations
Reduced instrumentation Requirements
2507o weight Reductionuser Friendly Keypad Operation
universal computer interfaceComprehensive software Packages
Specifications"~)ynamic Range . . .. .18,000 to 110.000 gammas. Rollover display feature
suppresses first significant digit upon exceeding 100.000gammas.
Tuning Method Tuning value is calculated accurately utilizing a speciallydeveloped tuning algorithm
\utomatic Fine Tuning ....±15*^ relative to ambient field strength of last storedvalue
Display Resolution. . . ... 0.1 gammaTocessing Sensitivity .................... ± 0.02 gammastatistical Error Resolution 0.01 gammaAbsolute Accuracy . ± 1 gamma at 50.000 gammas at 230C
±2 gamma over total temperature range standard Memory capacity
Total Reid or Gradient 1.200 data blocks or sets of readings Tie-Line Points .. . . 100 data blocks or sets of readings
^ Base Station 5.000 data blocks or sets of readings )isplav Custonrvdesigned. ruggedized liquid crystal display with an
operating temperature range from -400C to * 550C. Thedisplay contains six numeric digits, decimal point, batterystatus monitor, signal decay rate and signal amplitudemonitor and function descriptors.
S 232 Serial I/O interface 2400 baud. 8 data bits. 2 stop bits, no parity Gradient Tolerance 6,000 gammas per meter (field proven)
-rest Mode .. .. . . A. Diagnostic testing (data and programmable memory)B. Self Test (hardware)
Jensor Optimized miniature design. Magnetic cleanliness isconsistent with the specified absolute accuracy.
Gradient Sensors 0.5 meter sensor separation (standard), normalized togammas/meter. Optional 1.0 meter sensor separation available. Horizontal sensors optional.
Sensor Cable Remains flexible in temperature range specified, includesstrain-relief connector
lycling Time (Base Station Mode) Programmable from 5 seconds up to 60 minutes in 1second increments
Operating Environmental Range . .. ... -400C to * 550C: Q-100% relative humidity; weatherproof~*ower Supply Non-magnetic rechargeable sealed lead-acid battery
cartridge or belt; rechargeable NiCad or Disposable battery cartridge or belt; or 12V DC power source option for base station operation.
"Tattery Cartridge /Belt Life 2.000 to 5.000 readings, for sealed lead acid power supply.depending upon ambient temperature and rate of readings
Weights and Dimensionsinstrument Console only 2.8 kg. 238 x 150 x 250mm NiCad or Alkaline Battery cartridge 1.2 kg. 235 x 105 x 90mm NiCad or Alkaline Battery Belt 1.2 kg. 540 x 100 x 40mm
- Lead-Acid Battery Cartridge .1.8 kg, 235 x 105 x 90mm Lead-Acid Battery Belt 1.8 kg. 540x100 x 40mmsensor 1.2 kg. 56mm diameter x 200mm ^ instruments me
Gradient Sensor 4 Thomcliffe Park Drive
- (0.5 m separation-standard) . 2.1 kg, semTi diameter x 790mm cara3a0M4HtiHi)
Gradient Sensor Teiex: 0525222 EDA TOR(1.0 m separation-optional) 2.2 kg. 56mm diameter x 1300mm cable: instruments Toronto
Standard System complement instrument console; sensor; 3-meter cable, aluminum (416142S 7800sectional sensor staff, power supply, harness assembly. m U.S.A.nnerafinnc m^ni lal EDA Instruments Inc.operaoons manual. 5151 warfl KOM
Base Station Option Standard system plus 30 meter cable wheat Ridge. Colorado
Gradiometer Option Standard system plus 0.5 meter sensorprinted in canada
APPEHDIX B
MAXMIIM IIEIVl
Five frequencies: 282, OO4, 88B, 1777 and 3555 Hz.Maximum coupled C horizontal-loop J operation with reference cable.Minimum coupled operation with reference cable. Vertical-loop operation without reference cable.Coil separations: 25, SO, 1OO,15O, 2OO and SSOm C with cable J or 100,200,300,400, BOO and BOO ft.Reliable data from depths of up to IBOm C BOO ft). Built-in voice communication circuitry with cable. Tilt meters to control coil orientation.
ifc. v;J*
i l-'.fc-' it".
J JJ J J J
BPECIFICATIOIMB :
222.444.BBS. 1777and 3555Hz.
Modes of Operation: MAX: Transmitter coil ptens and re ceiver coil plane horizontal (Max-couplBd; Horizcntal-laap mode). Used with refer.cable.
tabilltyt
MIN: Transmitter talandrecen tical
er cai plans ver- (Min-coupled mode).
Used with reference cable.•tt) il pl verti
cal and receiver coil plana hori zontal C Vertical-loop model. Ueed without reference cable . in perallel lir
Coll Separation*:
V.L.
25.5O.10O.150.2OOS25Om (MMm or 10O. SOD. 300. 4OO.6OO and 800 ft. IMMHF1. Coil eeparationB in VL.mode not re- etricted to fixed veluea.
±O.25X toll X normally, depending on conditions, frequencies and coil separation used .
:- 222Hz :22OAtms- 444Hz :SCX3Atms- BBS Hz : 12OAtms- 1V77HZ : BOAtm3- 3555 Hz : SOAtm2
Receiver Batteries: 9V trans, radio type batteries 14). Life: approx. 35hrs. continuous du ty C alkaline. O.S Ah), less in cold weather.
Transmitter Batteries t
at*
Parameters Read: - In-Ph IQuedreture
"Readouts:
compo nents of the secondary field in MAX and MIN modes.
- Tilt-angle of the total field in VL. mode .
- Automatic, direct readout on 9Omm C3.5") edgewise meters in MAX and IS/IIN modea. No null ing or compensation necessary.
- Tilt angle and null in SO mm edge- in VL.mode.
Voice Link i
Indicator Lights:
12V 6 Ah Gel-type rechargeable battery. (Charger supplied).
Light weight 2-conductor teflon cable for minimum friction. Unshield ed. All reference cebtee optional et extra coat. Please specify.
Built-in intercom system for voice communication between re ceiver end transmitter cperetore In MAX end MIN modes. vie re ference cable .
Built-in signal and reference warn ing lights to indicate erroneous readings.
J
Scale Ranges:
Readability:
In-Phese: tSOX.tlDOX by push button switch .
Quadrature: *2OX.±X)OX by push button switch.
Tilt: iTSX slope .NuU(VL-): Sensitivity adjustable
by eeperetion switch. *
In-Phase end Quadrature: O.2S Xto O.5X ; Tilt: 1X .
-4O*Cto*6O*C (-4O-Fto*Wa-F).
Rsoalvsr Weight i 6kg (13 Ibs.)
Transmitter Weight: 13kg (29 Ibs.)
Shipping Weight: Typically 6Okg C135IDS.J. depend ing on quantities of reference cable and batteries included. Shipped in two field/shipping coooo.
Specification* eubject to cnange without notificetion
Ji
J
APEX PAR AM E TO l C S LIMITED2OO STEELCASE RO. E.. MARKHAM. ONT.. CANADA. L3R 1G2
Phone: (4161 495-1612 Cables: APEXPARA TORONTO Telex :O6-96S773 NOROVIK TOR J
APPENDIX C
IPC-9/200W
INDUCED POLARIZATION AND D. C. RESISTIVITY TRANSMITTER
2.0 SPECIFICATIONS
Maximum Output Power
Output Voltage
Output Current
Meter Ranges
Automatic Cycle Timing
Automatic Polarity Change
Pulse Durations
Period Time Stability and Accuracy
Open Loop Protection
Synchronization Output
Internal Power Sources
200W defined as when current is on and into a resistive load.
Switch selectable at nominal settings of 15, 150, 210, 300, 425, 600 or 850 V.
1.5 A maxii
External Power Sources
Switch selectable at 50 mA, 150 mA, 500 mA, 1500 mA full scale with accuracy of *3Z of full scale.
T:T:T:T; on:off:on:off.
Each 2T.
T is switch selectable at l, 2, 4, 8, 16 or 32 seconds.
Crystal controlled to better than 0.002 percent of the selected pulse duration.
High voltage is automatically turned off if the output power is less than 2 W. This can be overridden manually for testing purposes. This protection is not effective at the 15 V output.
Optically isolated, suitable for external synchronization of the IPR-11 multichannel IP Receiver.
Two battery packs are standard, each containing 4 GC 660-1 lead-acid gel-type batteries giving 24 V at 12 Ah.
One Penlite battery, Eveready E91 or equivalent.
24 V DC supply at maximum 10A.
2 -
l
li jiiiiiiji|liii|i i UiUPliiiiP l l lil i^ili**lU*I****ii I ••••I*** t l^tmtKfmil i ll* •ill li •••{•••4 ••••••••••i- 1 i?1112 —
•••l i it ••••l i*
Major Benefits^* Set Dipotes Simultaneously Measured* Ten Windows Available* Choice of Arithmetic or Logarithmic Window Width* Programmable Arithmetic Window Width* High Input Voltage* Weighs Only 8.5 kg.* User Friendly
l1X1 liii
i LIl If
ffi!i!!!i!i!!i!!i!iii!i!ill!!i*
l specifications
l
L
L
Dipoles . ...... .*/ 50? simultaneous input dipoles.Input Voltage (Vp) Range ...... .... Standard: — 8 volt maximum for each dipole— maximum sum of 12 volts from thesecond to the sixth dipole. Additional Setting:— attenuation of up to 40 volts on thefirst dipole. Input Voltage Protection .... ... Up to 1000 volts.Vp Resolution............... .... 1 microvolt.Vp Accuracy . ....... . D.3% typical; maximum I9b over temperature range.Chargeability Resolution.. .... . .... 1 millivolt/volt for Vp greater than 10 millivolts.0.1 millivoltA/olt for Vp greater than 100 millivolts. Chargeability Accuracy .. . . D.6% typical; maximum 29b for Vp greater than10 millivolts over temperature range. Automatic SP Compensation .. .. ± 1 volt with linear drift correction up to1 millivolt/second. Input Impedance .... .. ......... 10 megohm.Sample Rate . . .. ..... .. ... 10 milliseconds.Automatic Stacking ............ .. 1 to 999 cycles.Synchronization . .. . .. .. . Minimum primary voltage level of 40 microvolts.— Rejection Filters . .. ... ... 50 and 60 Hz power line rejection greater than100 dB.Grounding Resistance Check .. . 0.1 to128kiloohms.Compatible Transmitters . .. Any time domain waveform transmitter with a pulse "~ duration of 1.2.4 or 8 seconds and a crystal timingstability of 100 ppm.
. Geometric parameters, time parameter, intensity ofcurrent, type of array, line and station number, dipolelength, window width and delay time (mode 2). . . Two line. 40-character alphanumeric liquid crystaldisplay protected by an internal heater for lowtemperature conditions. . . ... 1800 sets of readings. RS232C Serial I/O Interface ... .. . 500 to 19.200 baud rate.- 7 or 8 data bits. 1 or 2 stopbits; odd. even, no parity, ronsole Power Supply . . .Six-1.5V "D" cell alkaline batteries with auto powersave feature; 20 hours of operation at 200C. pperating Environmental Range . -400C to * 600C; O to 10096 relative humidity;weatherproof.Veight and Dimensions . . 8.5 kg (with batteries). 300 x 200 x 240 mm. Standard System Complement . Instrument console with carrying strap, batteries, data - transfer cable and operations manual, 'isplayed Parameters . . Primary voltage, partial and total decimalizedchangeabilities, running and cumulative average oftotal changeabilities (in fixed modes), standard ~~ deviation of primary voltage and total chargeability.self potential, number of cycles, dipole beingmeasured and contact resistance. Available Options .. .. . Stainless steel transmitting electrodes, coppersulphate receiving electrodes, alligator clips, bridgeleads, multi dipole wire cable, wire spools and softwareprograms.
Programmable Parameters
Display
Vlemory Capacity
EDA Instruments toe 4 Thomdiffe Park Drive Toronto. Ontario Canada Man 1H1 Telex 06 23222 EDA TOR Cable EDAINSTRMTS TORONTO Telephone (416)425 7800 Fax: (416) 425 8155
In USAEDA Instruments me9200 E Mineral AvenueSuite 370Englewood. Colorado. U S A 8O112Telephone (303) 790 2541Fax (303)7902902PRWTED W CANADA
KVISIIVIIV CMKFMILITV
- ____ - ____ tl*BB~ iVtl-en " (BM vlKflhvH
—————— ——————
R3 R 1 N3 R 1i t
R4 R2 R4 N2t t
** 50 2
A \ S**b 73 1 V^X \ ^
103) 43 1 1
S \ 114/ 677 1 1
no/ 81/43 11
93/32 11
68/30 11
91/40 1 , 1
Kl 33 (2) 1
79 \ 49 11
67\ 33 11
K 147 11
tt 31 11
88 47 11
tt 34 11
76 56 It
tt 38 11
78 155 11
MJ 32 11
81/47 11
M 32 11
72 50 11
tt 32 11
90 47 11
70 31 11
76 47 11
/S7 35 11
W 42 j* 1 1
1 48 27 11
601 36 11
l 47 29 01
67 \ 43 . 0^ ^0
X o o
70 0 i
-10 -5 0
-1200V
-1100V
-1000V
- 900V
- 800V
- 700V
- 600V
- 500V
- 400V
- 300V
- 200V
- 100V
ov
- 100E
- 200B 1
1 - 300B j.'
li
H 400B i
QMR6EAB1L1TY PWFtLE E Ei
A B
S 10 15 202 2
J 1 1
1 1 1
1 1
\l
1 1
1f1 1
1 1
1 1
1 1
'1 1
1 1
r 1 1
1 1
1 1
1 1
1 1
0 0
Property i NINTEK CLAIM GROUP
Client s ROYAL OAK NINES INC
Date of Survey i 1/4/94
Operator t RED
Electrode Array i DIPOLE - DIPOLE
Node s TINE DOMAIN
Receiver t EDA IP-4
Transmitter s 8CINTREX IPC-9
Pulee Tiee t 2 Sec on 2 Sec off
Chargeability Window Plotted i *3
Delay Tiae i 90O M
Integration Tiee i 42O M
X8XC8IOIM L-TO.
•e*cr-t: i or*m To*- M — l
a^c: ±±OO
L. I Ml3OO IM
t . *
ii -; \- - \.' "- -r- ' ' fi ^ j ' : - ' !- -f) ••*- ,
f b - ,. . .a r, - : ei'; ,
K i .M x JHINI .*-j : '^ J l '-•';.-t"*J -J
t- ..i I '
-.1 t
lv \ ij
\
HI\!
. oar
.li1 l
M: i -
c
C
C,
OOf
•oa
•otv
oo,
. OO,
O
C,r
X
g l ir-icl-* -to 2OO f
oh*'.HAR6EAB1L": PRO'":: L
•0-8
38
too' ^
100
,no
\SO
to
JO
/DO*
210CW
2000W
* 3 T:; o w t lt
' L li 0:'i W
* l 4 '". L- W
4-i-V'GW
^ )W
i -j "- ' i w
•' 'y i": W
* - ;.l O \y* t* t
*- .i L'O W44
4* :.'i:iw4(
" l-J.'W
h \
f". ..n;.e t s- : MINTEK CIAI^
'.i i e; i r . KiJVAL :)AK MJNf-', IN:
D^te -f Survev ; 25 /J X '94
UpH-r .1 : Rt D
f-.:.;. ••..-00 e At r a-. : D I L'Q:. F D r F' ML E
flc.JH ; i I ME ULMAIN
.-•t-- f?: ,er : FDA I P -4
i r citii .in Mer : b(. :NIPfX IF-i S
pill ^H T i ^e : l' Sec cifi 2 -ye?- off
i har ueabi l 1 1 y Window l-'lottwJ : H3
Oelav I i me- : 5OC' *ns
tiun Time : 42O ins
T I Clfsl LTD
.- t; i --.r ic^ *- M ^^ l i; .r.
j i--- l-f t
L IT5; o *
•00
ICC ,
o)
*c
l!\^/iu
\'
tK- w
l\ l;
l
; f
LE
GE
ND
|l2|
OLIV
INE
DIAB
ASE
fiT
I QU
ARTZ
DI
ABAS
E
Hoi
HURO
NIAN
SE
DIM
ENTS
10*
Ita
lOorg
. IC
cM
ATAC
HEW
AN
DIAB
ASE
FELS
IC
INTR
USIV
E RO
CKS
Ouor
tt po
rphy
ry
SEDI
MEN
TSTH
OLEI
ITIC
VO
LCAN
ICS
a 9 y amt f ST tt l?
Ouo
rti
- ririrt
l, p
9 So
Se fi
Se 57' Si
Sil
5*
Unni
bdM
dod
Arajl
CtO
Cong
lom
orot
o
potp
hynU
o),
Ouor
1l.1i
Ouor
ti no
ko
(qu
Wl-
iyi
porp
hyrll
lo).
Oron
odior
flo1"
""*"
*
•orp
rft-rJ
ul g
rano
dior
ite
liuco
erat
le g
rono
dler
lto
Hom
blon
do o
ViU
Ou
orti
fiord
. Po
rphy
ry
Chot
t
Tuffo
ooou
i-iod
imon
tSW
itono
tond
llotto
Shoo
rfth
oho
Ouo
rti p
orph
yritic
tuf
f
Onp
hltu
fou
r! to
mdo
noto
o lim
likom
lno.
Syin
iwOr
onlll
It
qiio
rtl-n
oh l
yonl
t*Tr
iehy
tt
l IN
TCRM
EDIA
TE-F
ELSI
C VO
LCAN
ICS
OO
OilO
oong
tom
mlo
[J]
MAT
C IN
TRUS
IVE
ROCK
S
taor
thiti
loB
oni.
Cobb
nO
uutl
oobb
roPo
gmol
oldo
l go
bbto
Lom
prifi
hvri
htlru
ihro
oro
ccio
Nlp
iiiln
g-lv
pi d
iobo
io t
iht
ULTR
AMAF
IC
INTR
USIV
E RO
CKS
Uniu
bdlvi
dod
Sirp
ontln
liod
d.0n
ti-pi
ndot
it*PV
ri'tn
o-ho
tnbl
ondl
Cirb
onot
llod
Tril
c-m
ogni
iiU
4r
4ich
;r; 7n C tt •tin
Doelt
o tu
ff!Oo
olu
pyro
olol
tlci
Aggl
omor
olo-
broo
iloDo
elto
wpM
I lu
ffDo
etli
mai
irn
flov
Into
rmod
Ml-t
ohb
t.Kh
yoH
lo-u
ndlff
orai
iHin
c.M
orm
odM
o-flM
o Ir
tilit
Shoo
rM
ourn
rhy
ollli
Khyo
CU
luff
Rhyo
lllo l
opM
luf
fKh
yoW
o og
gtom
orat
o(q
uorti
-oyo
por
phyr
ltk)
j^H
OM
-po
rprv
riuj
dono
toi
Pnm
il.vt
do
noto
i Cv
ornd
CAL
C-A
LKAL
IC
MAF
IC V
OLC
ANIC
S (M
AFI
C-
INTE
RMED
IATE
VO
LCAN
ICS)
3 Jo Jm I"
.le
.lorn
3|
ib
Jih
lu'f.
BrK
illC
orbo
nollio
dA
mpM
DoH
lillO
' P
illo
* b
rt
ufl
mou
rn,
poly
iulu
rod,
Uf.d
oU.o
kor
nolM
o to
rture
d pw
Wot
ltlo
hom
olM
io n
on
M t
atm
* bo
iolU
e ko
mol
liUo
(Ion
oo
Mltl
o ko
mol
lito
Corb
onm
llod
porM
oirlK
kom
olM
l
i ko
moU
to
Coi
bono
lilol
booo
ltle u
mol
Mo
IRON
FO
RMAT
ION
IFl r. Sv ITcM
ir,.
0*14
0
Bond
od I
ron
form
otlo
nCM
orlto
-rloh
Orop
Utta
SULP
HIDE
SDI S
i us
sus
OXID
ESH
I O
AV
Sln
iMr
Uoow
vl
tulp
nldn
Moo
nillto
(W
-lOO
t; O
uorlt
orth
ent!
vi4nin
g
ALTE
RATI
ON
ThoM
okb
nvwi
iono
on
mod
ofto
r liln
wogy
, .f
3m,o
Wou
M do
rurto
o m
ourn
oot
o-or
ul*
mon
e vo
lconl
o (ri
toh
ii lo
rtonl
lod
CM
orilli
Cotto
n Cg
nono
to01
0 fu
m
l IK
lo
b te
l V 1
1
(t
ruoho
lUo
TokT
oiV
Orap
niuo
"m
woo
oui
SaM
tt
Woo
ctwd
Cp
ldoto
Sorp
onttn
lnd
aom
puto
r op
ooo
porm
ruj.
uio
lor
TEXT
URE
mg .i K, bnd
Fm bMki
Clin
o gm
notf
Prkw
xv f
rogm
onto
ll lo
Mon
lo f
no/n
onto
ll O
vartl
oriy
rlt
Suor
tt lo
Wip
or p
hync
2.15765XRAL XRAL Laboratories
A Division of SGS Canada Inc.
1885LesieS*oet Don Mite. Ont Canada MSB 3J4 Telephone (416) 44&5T55 Fax (416)44^4152 Tetex 06996947
CERTIHCATE OF ANALYSIS REPORT 27503
TO: ROYAL OAK MINES INC. ATTN: PETER HARVEY P.O. BAG 2010 TMCENS, ONTARIO P4N 7X7
CUSTOMER No.
DATE SUBMITTED 27-May-94
2226
REF. FILE 18507-L3 TOTAL PAGES 4
13 PULPS P.O. P04963 Proj. MINTEK
BB PPMHA % MS % AL % P t K %CA %se PPMTI % V PPM GR PPM MN PPM R % OO PPM KX PPM CO PPM
ICP ZCP ICP ICP ICP ICP ICP ICP ICP ICP ICP ICP ICP ICP ICP ICP
DETECTIONLIMIT
.5
.01
.01
.01
.01
.01
.01
.5
.012.1.2..01
1.1..5
METHOICOOK80-190-190-190-190-190-190-190-190-190-190-190-190-190-190-190-1
ra PPMAS PPM SOL PPM T PPM ZR PPM MO PPM AC PPM CD PPM SB PPM SB PPM BA PPM LA PPM W PPM PB PPM BI PPM
METHOI
ICPICPICPICPICPICPICPICPICPICPICPICPICPICPICP
) DBTECTIOHLIMIT
.53..5.1.5
1..1
1.10.5.1..5
10.2.3.
MBTHOiCODE90-190-190-190-190-190-190-190-190-190-190-190-190-190-190-1
*** UNLESS INSTRUCTED OTHERWISE WE WILL DISCARD PULPS IN 90 DAYS ** AND REJECTS IN 30 DAYS FROM THE DATE OF THIS REPORT
DATE 14-Jun-94 CERTIFIED BY
Member of Ihe SGS Group (800616 Gtnfrate deJcflD H. Opocbcccic, Cjcncnl Msn&gcr
iXRAL
PAGE l of 4
14-Jun-94 REPORT 27503 HEP. FILE 18507-L3
SAMPLE
nortaxtaxtaxtax
taxtaxtaxtaxtax
taxtaxtax
D KmD HIM
94-194-194-194-194-1
94-194-194-194-194-1
94-194-194-194-194-1
6517665177651786517965181
6518265184651856518665187
6518865189651906517665190
BE PPM ICP
80-1
1.31.0
.81.0
.9
.91.01.31.11.1
1.0.9
1.21.41.2
HA %ICP
80-1
2.681.982.702.052.41
2.922.552.351.271.12
1.101.431.622.691.48
MB %ICP
80-1
1.04.22.41.79.44
.891.004.263.814.58
3.163.263.951.053.68
XL %
ICP 80-1
9666
.10
.60
.64
.477.13
67766
56797
.78
.06
.29
.73
.92
.92
.26
.44.26.20
P %ICP
80-1
.05
.04
.04
.03
.04
.04
.04
.02
.02
.02
.02
.02
.02
.05
.02
K %ICP
80-1
1.651.513.132.343.97
1.912.16
.58
.28
.19
.16
.20
.061.65
.05
CA % ICP
80-1
3.032.561.784.332.23
1.562.195.717.368.11
7.727.095.943.115.57
SC PPM ICP
80-1
4.83.53.8
12.24.6
3.66.0
45.342.745.2
34.839.848.75.0
44.9
2.15765
D - QUALITY COBTROL DUPLICATE
Member of the SGS Gmvp (SodM GMnMe de Surveibnce)
XRAL 14-Jim-94 REPORT 27503
PACE 2 of 4
KEF. FILE 18507-L3
SIMPLE
MIB 94-1
MD! 94-1
Mn 94-1MI* 94-1Mn 94-1
Mn 94-1Mn 94-1Mn 94-1Mn 94-1Mn 94-1
Mn 94-1Mn 94-1
Mn 94-1D Mn 94-1D Mn 94-1
6517665177
651786517965181
6518265184651856518665187
6518865189
651906517665190
TI % ICP 80-1
.25
.18
.19
.24
.21
.18
.21
.44
.43
.40
.31
.38
.45
.26
.42
V PPM ICP 80-1
5844459349
4358
243246241
19922927060
249
GR PPM
ICP 80-1
196
167
120
141
86
114149221249309
239192164197165
MN PPM
ICP 80-1
722
434
240
595
270
130
300
1220
1260
1360
1110
1200
1430
730
1340
FE %
ICP 80-1
2.80
1
1
2
1
1
2
7
6
6
.79
.29
.44
.22
.44
.36
.34
.86
.99
5.69
6827
.07
.31
.89
.75
CO PPM
ICP 80-1
11
8
5
16
5
91241
3839
3435451142
HI PPM
ICP 80-1
25
12
12
26
16
17
19
555564
4542532350
CD PPM
ICP 80-1
12.0
21.0
8.8
29.0
26.0
4.521.311599.385.1
78.888.3
11812.3
103
2.15765
D - CONTROL DUPLICATE
Member of the SGS Group (SocM* G*n6rate de Surname)
XRAL 14-Jtm-94 27503
PAGS 3 of 4
FILE 18507-L3
SAME
MnMnMnMnMn
MnMnMnMnMn
MnMnMn
D MnD Mn
'LE
94-194-194-194-194-1
94-194-194-194-194-1
94-194-194-194-194-1
6517665177651786517965181
6518265184651856518665187
6518865189651906517665190
ra PIH
80
718044
10645
1048836367
5565805574
PMCP-1
.3
.8
.5
.1
.5
.4
.8
.3
.1
.7
.9
.3
.3
.6
AS PPMICP
80-1
OO0oo
ooooo
•oo0o0
SR PPM ICP
80-1
520314170153165
16724514710296.1
10161.869.2
53363.7
X PPM ICP
80-1
6.14.84.77.15.4
4.66.2
15.915.016.8
13.114.517.56.5
16.4
ZR PPM ICP
80-1
24.015.733.433.750.9
29.416.39.03.52.4
1.4<.S1.4
24.2.9
MO PPM ICP
80-1
44422
53223
33222
AC PPMICP
80-1
••C.IK.I<.l
.5
.3
•C.I•C.I
.2
.5
.2
<.l.2
<.l•C.I•C.I
CD PPMICP
80-1
tttt•tttttt
tttt•CI
tt•tt
^•Ci
tt•tttt
2.157C5
D - QUALITY COHTROL DUPLICATE
Member of the SGS Group (Soctttf Gfrrfnte de Suraailonce)
i.XRAL 14-Jun-94 REPORT 27503
PAGE 4 of 4
RKF. FILE 18507-L3
SAW
MnMnMnMnMn
MnMnMnMnMn
MnMnMn
D Mno Mn
•LE
94-194-194-194-194-1
94-194-194-194-194-1
94-194-194-194-194-1
6517665177651786517965181
6518265184651856518665187
6518865189651906517665190
SB PPM ICP
80-1
CIO00OOCIOCIO
CIOCIOOOOOCIO
OOOOOOOO00
SB PPM ICP
80-1
1010
6C5C5
C56
C5C5
5
5•C5
86
C5
BA PPM ICP
80-1
203268641515766
389499111
7242
425717
20111
LA PI II
80
147
1087
710
C•c<•c•c
12C
PMCP-1
.8
.1
.9
.4
.3
.7
.5
.5
.5• 5
.5
.5
.5
.6
.5
W PPM ICP
80-1
00CIOOOCIO00
CIOCIOCIOOO00
OOCIOOO00OO
PB PPM ICP
80-1
C2C2C2C2•C2
3C2C2•C2•C2
•C2•C2•C2•C2•C2
BI PPM ICP
80-1
5OOO•C3
O0ooo
•C3OOOo
O - OmLITT CORROL DOPLICUB
Member of Ihe SOS Group (SodM Generate de Surveilance)
CoH III2.15765
Larl Lor t,
/0258V/
HIM *H-I -SO0
I02S81Z
I02S82&
'V.
MSB
/02583V I02S851/
•feet
CLIENT: ROYAL OAK MINES INC.PROPERTY: MINTEK CLAIM GR PUP. CODYTITLE: DRILLING Pi-AM
Ministry ofNorthern Developmentend Mines
Ontario
Report of Work Conducted After Recording Claim
Mining Adwiyto.
PeoMnal Information cc*ected on this fonn Is obte^this coBoctton should be dkecled to the Provincial Manager. Mining Lands. MMstry of Northern Daxstepmenl and Mhws. Fourth Floor. 19* Cedar Street.Sudbury. Ontario. P3E 6AS. telephone (705) 670-7264.
Instruction*: - Please type or print and submit in duplicate.- Refer to the Mining Act and Regulations for re*
Recorder.- A separate copy of this form must be complete- Technical reports and maps must accompany t- A sketch, showing the dakns the work is assig
6 5
42A06NE0014 2.15765 CODY 900CtontNo.———————
/Sb^-Z^Telepnone No.
Hdder(s)
f i fmsMp/Area U or A Pan*.UMng DMHorT
Deles Work Performed
From: H^-L To: Ae* JoWoffc Performed (Check One Work Group Only)
WorkGroup TypeGeotechnical Survey
/Physical Work. IndudinQ DrflNng J-',-Rehabilitation
Other Authorized
Assays
Assignment from
Total Assessment Work Claimed on the Attached Statement of Costs 2-\ ,
Note: The Minister may reject for assessment work credit al or part of the assessment work submitted if the recorded holder cannot verify expenditures claimed in the statement of costs within 30 days of a request for verification.
Persons and Survey Company Who Performed the Work (Give Name and Address of Author of Report)Address•'i
i -e rt 7*ip'-y/ja.//.... /.t/ 33 ( ' riv**-* ;
(attach a schedule If necessary)
Certification of BeneflcM Interest * See Note No. 1 on reverae aklertify that at th* time the work was partormwt. the cWrrw covered In this work
by th* current recorded holder.
Cai lineation of Work Reportcertify thai l heve a personal knootedge of the tacts set forth in this Work report, having performed the work or witnessed same during and/or after
Ms completion and annexed report Is true.
1C Q s j- a^*.'
For Office Use Only
r^. %/yrMice for AmenQflents Sent
0941 (OMtl)
i!
f|aO
00
S
M
VA
0
VA00
OVA00
o
o VACP-c
s*.oSJ
VA OQ-C.
N" VACd3
[J\
Q^
S
oS"
en-c
Ci M VA
NVA V*-C
toiseto /02.S831M VA00U
oNVA
(A
/0ZS636
VA
/O 256 M S 02,5 8 33 1015032-N
00VM
\A
t '025623 1 015 8 22 /02-S817 \ I02.582J* NVA
VA
l &2QSZOI (02-5621 1l -TZ0S-ZO/I t
?i ^0 sjA
^5
N
00
1"
81!
ClMfn Nuniotr (sea Note 2)
Co f**i
iir i
1
S
f l t t.i ii -t^i c, 't -c
8 c ' * ' fKl
?
f O f' ' t o ' f f -c.
C 0 0-C
8 O 0
uqaosmjuo •uoqiMOM toan)*A
r*
f T1o c•b jrf?
S
Credits you are claiming in this report mavbe cut back. In order to minimize the adverse effecte of such deletions, plasso Indtoate from which claims you wish to priorize the daJetion of credits. Ploaso mark (c*) one of the fdowing!1. O'Credte are to be cut back starting wttt the daim Mad last, working backwards.2. D Credits are to be cut back equaty over all claims contained hi thte report of work.3. l—l Ci edits are to be cut back aa priorized on the attached appendix.
hi the event that you have not specified your choice of priority, option one wM be implemented.
to the mining
2: Nwoffchaab
recofded transfers, option agi
\-eA6v {\***ti*l carWy that the worded holder had a bwwfcW Maraet ki ttw patented or laaaad land at ttt fern tha work waa parionnad. 18"ff.
Ontario
Ministry ofNorthern Developmentand Mines
Ministers du Devetoppement du Nord et des mines
Statement of Costs for Assessment Credittrtat des coOts aux fins du credit devaluationMining Act/Loi sur tes mines
Transaction No.M* de tiansactton
Personal information collected on this form is obtained under the authority of the Mntng Act. This information wM be used to maintain a record and ongoing status of the mining daim(s). Questions about this coBoctton should be directed to the Provincial Manager. Minings Lands. Ministry of Northern Development and Mines. 4th Floor. 159 Cedar Street. Sudbury. Ontario P3E 6A5. telephone (705) 670-7264.
Les renseignements personnels contemn dans la presenle fbrmute sont recue*s en vertu de la Lot eur lea mine* el serviront a ter* a four un regbtre des concessions minieres. Adreanr toute question sur la coftece de ces
^ - m; ,^ ,, WHf M a. i H A. B jtkinaT ••*Mta*BBMBBikl *4*BaB ftaBBW^MBBVB. •••••Mlamva* fl**b*M4A*^ *4|.rensotgnofiNHits au cnei provwic-si oes lorrans nvraefs. mvnsiere ou Devetoppement du Nord et des Mtoes. 159. rue Cedar. 4" etage. Sudbury (Ontario) P3E 6A5. telephone (705) 670-7264.
1. Direct Costs/CoOts directs
Type
Wages
Contractor's and ConauHanfa Fee* DroNsde ['entrepreneuret de I'expert- conseB
SuppNesUaad FoumHuree utttteoes
Equipment Rental Location dea*a^ke^aWe^a4 IfVBnSJVWI
Description
Labour Main-d'oeuvreField Supervision Supervision sur to terrain
Typ* . JXa mo*A -P -l/.v^
r
(i(ct.h" Ax'iyt'f/Us,Ty
Typ*
Type
Amount Montan!
3fll5
li WSI16
1 80
Total Direct Cost* Total des coOts directs
Totals Total global
33/r
I1.80I
2i,m
2. Indirect Costs/CoOts Indirect** * Note: When ctamUng RehabMatton work mdbed costs are not
Pour teremboursement des travaux de lenabaUatton. tes coOts mdirBCls w sonl pn ttdniissMos 6n t*v*t QU9 trsvsux d'evaluatton.
Type
Tran latkMi
FOOO MM
DescriptionTyp*
Amount Montant
Sub Total of Indirect Coste Total partial de* eoots
Amoonl AHowflbto (not 29rA of Dvoct CootB)i 4A vaV afti *tv vV vN
Total VahM of Asa raMof Dkwl and
Totals Total global
Note: The recorded holder will be required to verify expenditures claimed in this statement of costs within 30 days of a request for verification. If verification is not made, the Minister may reject for i an or part of the assessment work submitted.
Note : Le tHuteJre enregisM sera tonu de varftar tea dale present etat des coots dans las 30 Jours sufcant urn demande a cet effet. Si la verification n'est pas effectuee. to mMUre peut rafeter tout ou une partie des travaux d*evaJuanon priainHa.
FINng Discounts Remises pour depot
1. Work filed within two years of completion is claimed at lOtWfc of the above Total Value of Assessment Credit.
1. Les travaux deposes dam tes deux i rembourses a 100 * da la vateur l
i suivant tour achevement sont irneratenneaducrtdtd'^aiuaiun.
2. Work filed three, four or five years after completion is claimed at 50*M) of me above Total Value ol Assessment Credit. See calculations below:
Total Value of Assessment CredN Total Assessment Claimedx 0.50
2. Les travaux deposes trois. quatre ou dnq ans apres tour achevement sont rembourses a 50 H de la vateur totate du credit d'evakiation susmenttonne. Voir tes cateuls d-dessous.
Vateur Mate du credtt d' •Hen tad ideax 0.50
Certification Verifying Statement of Costs Attestation de I'etat des cofltsl hereby certify:that the amounts shown are as accurate as possible and these costs were incurred white conducting assessment work on the lands shown on the accompanying Report of Work form.
that as jr?rf, Age(Record*) HoMerf, Agent. Position in Company)
to make this certification
J'atteste par la presente :que tes montants mdiques sont to plus exact passable et que ces depenses ont ete engegees pour effectuer toe travaux d'evahratton sur tos terrains indiques dans la formuto de rapport de travail cHoint.
t am authorized Et qu'a Hue de to suis autorise
0212 (DM1) Nota : Dans cette formote. torsqul dtelgne des au sen* neulre.
MMstry ofNorthern Development•no Min09
Ontario
Report of Work Conducted After Recording Claim
Pefejriatlnlbriiiatloncceactedonttitolbrmtooetalrta^into coftecHon should be dkected to the Provincial Mana0sr. MMng Lands. MJntotry of Northern Development and Mhws. Fourth Floor. 150 Cedar Street.Sudbury. Ontario. P3E 6A5. tetophons (705) 670-7264. - - -. IS 1? 6 5Instructions: - Please type or print and submit in duplicate.
- Refer to the Mining Act and Regulations for requirements of filing assessment work or consult the Mining Recorder.
- A separate copy of this form must be completed for each Work Group.- Technical reports and maps must accompany this form in duplicate.- A sketch, showing the claims the work is assigned to, must accompany this form.
Recorded HoMei(8)C'At: Jf/A/cS
ftelT- 7X7
Mining DMakm
(M or Q Plan No.
Pelee Workr9iwOf1tt9O
From: l To: 5*Work Performed (Check One Work Group Only)
WorkGroup
^^ Geotechnical Survey
Physical Work. IndudkiQ Drflling
RehabiRtatkxi
Other Authorized Work
Assays
Assignment fromDA^^WUA no^ww
Type
6*yV'/'"'.^ S,"^y* Ht-r' 1, Vfa. tP
RECEIVEDDEC Z 9 1994
MINING LANfMuunm^,
Total Assessment Work Claimed on the Attached Statement of CostsNote: The Minister may reject for assessment work credit aN or part of the assessment work submitted H the recorded
holder cannot verify expenditures claimed in the statement of costs within 30 days of a request for verification.Persons and Survey Company Who Performed the Work (Give Name and Address of Author of Report)
Name Address
it/6*) 6* rV/v/ 7X7n[.C.
Certification of Beneftetal Interest * See Note No. 1 on reverae aklel certify that at the time the work was performed, the claims covered In this work report war* recanted In the current tower's name or held under a banafldal totorwl by lha current racordi lg '/f
CerUflcaUoii of Work Reportl certify that l have a personal knowtodoa oJ the facts art forth In thto Work report rwving (Mriomwd trw work or Us oomptatlon and annexed r port to true.
Penon d tifylng
-r,— .^ ? QJ-
For Office Use Only
li -L lIIS9SZO/ -1
V
o"H ^ Cfi
8
o NCoX
^n CO
LhSSlOI -ij
M
CD
11
IhSSto/ - - |O^S8HC1
t* vi
*M -* i I1 M
Ml OQ W
I02S8M is 8 st o/N V) (Bo* t*
"X.
KCQSif
N
CO
1 1
1015621 \
1^^
^ft
CO
1 bZQStOI
f H 1 i ^^i ^^^^i
o \rCDQQ
8!!fi ||
CQ cil"|
irr 00
fi
^
^rS- -^m
W
-8
V*\nO
w
•Ct0C)
VA)VA 3
U (ft \f\
(M MA
CO
-to o
'
S : i
S
as
x u\ \n"1
s S*
Credits you are claiming in this report maybe cut back. In order to minimize the adverse effects of such deletions, please mdteato from which claims you wish to (HHM&A the deletion of credits. Please mark f.***) one of the foaowing!1. El Credits are to be cut back starting with the claim Dated last, working backwards.2. D Credits are to be cut back equaty over ei claims contained hi this report of work.3. D Credits are to be cut back as prtorized on the attached appendbc.
In the event that you have not specified your choice of priority, option one wM be implemented.
1:101
Note 2: Ift
i unrecorded tranefere, i
l certify Out ttw wanted holder tad a bWMftcW mtMMl ki the patented l tend at Vw tbm tt* work WM perfomml.
Ministry ol
OntarioMinteieredu
du Nof dd0s
Statement of Costs for Assessment Creditfetat des coOts aux fins du credit devaluationMining Act/Lol sur les mines
ava^ a^lAnojri
Personal information collected on this form is obtained under the authority of the Mning Act. This information wM be used lo maintain a record and ongoing status of the mining daim(s). Questions about this collection should be directed to the Provincial Manager. Minings Lands. Ministry of Northern Development and Mines. 4th Floor. 159 Cedar Street. Sudbury. Ontario P3E 6A5. telephone (705) 670-7264.
Les renseignements personnels contenus dans la presente tormute son! recueMs en vertu de la Lot sur lea mines et servhont a tenir a Jour un regisrre des concessions minieres. Adresser loute quesilon sur la coftoco de ces renseignements au chef provincial des terrains miniers. mMstere du Devetoppement du Nord et des Mines. 159. rue Cedar. 4* Mage. Sudbury (Ontario) P3E 6A5. telephone (705) 670-7264.
1. Direct Costs/Couts directs 2. Indirect Costs/Couts indirect*Type
Wages SatoJres
Contractor'8 and Consultant's Fee* Drone de
et de ('expert-COtWttN
SuppOeeUeed FoumNure* utMaeea
Ea^MpffVMH•ft^k^^^tinvffHM Location itomm*^A*t^WaVVWIVI
Description
Labour Main-d'oeuvreField Supervision Supervision sur to terrain
Typ* 6r,A Survey
(jta^l'i'ied ^fif-4
Type
Type
Amount Montant
/,l 70
x, ne
Total Direct Costs Total des couts directs
Totals Total global
7.0,3*0
2(,,U6
:Wh( claiming RehabflMaUo irktmfirecti ats are notallowable as assessment work.Pour le retnboui semen! des travaux de rsnabHNation. lescoOls indirects ne sort pas admtssMes en tant que travauxd'evalualion.
Type
Transportation Transport
Food and Lodging Hour f Hine 6t
*a — a-**^— — *| , — — — jmnfOmfmmn W M•^a^BMM^tflaW^AIdMBuvfiKKNnzviionMOMsfvMtlOtl d
DoscnptionTyp*
Sub Total of bwNf Total partM des coott
Amount AtowaMe (not greater than 2CH of DinNOfltaWlf 4l0HH98sW9 ffi 9XCVOMK p0B 20 T( 096 1
[TotBl of Dtfvcf w*o AetowHMi) v vWkMBQ indirect COM) fToM tin M
Amount Montant
vet Costsindlrscts
9oSta Jfcetts)totfttcnMn
Totals Total global
** ~*~- " n
* * - v^ -
-- -
t*.***Note: The recorded holder wiH be required lo verify expenditures daimed in
this statement of costs within 30 days of a request for verification. If verification is not made, the Minister may refect for assessment work an or part of the assessment work submitted.
Note : Le Mulaireenieojsfce sera tenu de verifier les depito present etat des couts dans tes 30 Jours suivant une demande a eel effet. Si la verification n'est pas effectuee. to mMstre paul refeter lout ou une partie des travaux d'evaluation presenMs.
PINfiQ Dlicountii
1. Work filed within two years of completion is daimed at tOTWfc of the above Total Value of Assessment Credit.
Remises pour depot
1. Les travaux deposes dans tes deux ana suivant tour achevement sort
2. Work filed three, four or five years after completion is claimed at 504fc of the above Total Value of Assessment Credit. See calculations below:
Total Value of Assessment CredH Tom Assessment Claimedx 0.50
2. Les travaux deposes trois. quatre ou dnq arts apres tour achevement sont rembourses a 50 46 de la valour totale du credit d'evaluation susmentkmne. Voir tes calcuts ci-dessous.
Vatour Mate du credR d'evaluation Evx 0.50 -
alton Mate idea
Certification Verifying Statement of Costs
l hereby certify:that the amounts shown are as accurate as possible and these costswere incurred white conducting assessment work on the lands shown
Attestation de I'etat des coOts
J'atteste par la presente :que tes montants indiques sont te plus exact possible et que cesdepenses ont et6 engagees pour effectuer tes travaux d'evaluationon ine a
that as
to make
ccompanying nepon ui nore lorm. sur IBS lw rains muiquas uans HI rormuw OB roppon OB navan o-jomi.^ y
'leolvsjj S T 1 am a,ithnri,orf Et nii'A trtra da 1 to mis airtnrM(ftocorcM Holder. Agent PmMon in Company)
this certification
(Mutohe •rWflJMM. ivpreNdtont. poM9 Mwpt
11 7\ faire cette attetann. .77^rf^^^^/
TL "i i i
dan* to eompagnto)
A/^ /? 'f/Nota : Dans cette tormuto. torsqu'l dMgne des | , tomaaeulneet uMtoAauems i
OntarioMinistry ofNorthern Developmentand Mines
Ministers duDeveloppement du Nord et des Mines
January 17, 1995
Geoscience Approvals Office 933 Ramsey Lake Road 6th Floor Sudbury, Ontar io P3E 6B5
(705) 670-5853 (705) 670-5863
Our File: 2.15765 Transaction /: W9460.00256
W9460.00257
Mining RecorderMinistry of Northern Developmentand Mines60 Wilson Avenue1st FloorTimmins, OntarioP4N 2S7
Dear Sir/Madam:
Subject: APPROVAL OF ASSESSMENT WORK CREDITS OH MINING CLAIMS
1025818 at al. IN CODY TOWNSHIP
Assessment work credits have been approved as outlined on the report of work form for the submission. The credits have been approved under Section 14 (Geophysical) and Section 16 (Drilling) of the Mining Act Regulations.
The approval date is January 13, 1995.
If you have any questions regarding this correspondence, please contact Steven Beneteau at (705) 670-5855.
ORIGINAL SIGNED BY
Ron C. GashinskiSenior Manager, Mining Lands Section Mining and Land Management Branch Mines and Minerals Division
SBB/jl
cc: Resident Geologist Timmins, Ontario
Assessment Files Library Sudbury, Ontario
NOTICE TO THOSE CONCERNED:
RE:" ROYAL OAK MINES INC. ; O& o t ^'7 fMINTEK CLAIM GROUP * . * ** * O Z)CODY TOWNSHIP1994 ASSESSMENT REPORTGEOPHYSICS AND DIAMOND DRILLING"
Incorrect information was written in this report concerning the size of the Mintek Claim Group. The property consists of 34 mining claims, not 24 as indicated in the original report. Figure 2 (page 3) in the report is therefore wrong, the correct claim group sketch is included here. Table l (page 4) is also wrong, the correct list of claims is also included here.
The M.N.D.M. form "Report of Work Conducted After Recording Claim" is also wrong, as the work was only spread out over 24 claims. This form has been redone to reflect the proper size of the claim group. n\
Peter Harvey
IV CONC.
NIGHT HAWK LAKE
— ——u
f ——— 1————
\-——i————-t-———
MINTEK CLAIMS CODY TWR
TABLE l
MINTEK PROPERTY CLAIM STATUS
CLAIM NO.
102581810258191025820102582110258221025823102582410258251025826102582710258281025829102583010258311025832102583310258341025835102583610258371025838102583910258401025841102584210258431025844102584710258n810258491025850102585110258521025867
TWP.
CODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODYCODY
STATUS
STAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKEDSTAKED 'STAKEDSTAKEDSTAKEDSTAKEDSTAKED
RECORDED DATE
'28/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8728/09/8716/10/8716/10/8716/10/8716/10/8716/10/8728/09/8728/09/8716/10/8716/10/8716/10/8716/10/8716/10/8716/10/8728/09/87
Aerial Cobltwoy Boundary
Oldrlcl,
MAP SYM80L06Y
Piptlin*(ik**( *r
Roilrood
Ooiitlt Trccl
Approsiflior*
Let, ConctMign
Park 6aun4t'| ——————
Bridg* y -*oa4, Mllr**4
Building ^Chlmn*y oCliff, Pit.Pilt r T T rContour* — M —
Control Point*
vtrllld
Culvirt FolliOfukK lint rivtr
Fwnct, Wall
O 100 OZ
l-
(CcAvtrtictiofl ffotufil, l • It )
Floodtd Landi-ockMar*h or Swamp *Matt ^Mint Htad From* aOutcrop •...-
Rood
Acittl (no* at 4* ••mltnintt t t
Trail, 6*(li R*** Iptrlaft oiltf)
Rapid*D*ubll III!•K* r*pi*t
Otnftl* liAt rittr• irk •ultlpl* r**i*(R***rvoir f*1*")0"
Riv6r, Str6orn, Canal
**tt***l-iftthon tf dp*
Hack
Spot Elevation
Tower 9 t
TranimiMlon Lin*
P,l.n. - ^
Tgnntl ^-J———-^
Utility Pol*i ' Wharf ,0eck, Pitr Woodtd A rea
AREAS WITHDRAWN FROM DISPOSITIONM.R.O. - MINING RIGHTS ONLY 8.R.O. - SURFACE RIGHTS ONLY M.+ S. - MINING AND SURFACE RIGHTS
Dworlptlon OnltrNo. Dm Oltpodtlon FIU
© W 88/78 10/8/76 8 R O 16639
© APPLICATION PENDING UNDER PUBLIC LANDS ACT NOTICE RECEIVED ftS-MAR-SO (SNOWMOBILE TRAIL)
r H|s TWP is SUBJECT TO FOREST ACTIVITY IN 1994/9b' FURTHER INFORMATION AVAILABLE ON FILE
•r* . I*I*J
MATHESON TWP.
48*32
887 50
200
^"" xJ l-
* lv*^ i _ ,. — _ _ — -4
)? W \Roma Lake{- i /--.. \ , P "~*IB
, A ""J0, i . .
197*6 li r* 9066tl-.' —li ' —-- — y
*- "—————.•fet-1-TTT? P IOTSISO .T ' nl *?(
T B O ft 4 i VA0AAA.
~ -l—t^-
iPCemetery f'omt
IP - ) V -X? IIOOOOS 948ie'3 ! . X 4 UNITS
! 1161452
UNITS
? UNITS H8I460
WATER LOT No. 17
LO. 10759
1r- --J^-,-1
HAWK
| P ^4610 | P V84609 | O P /246O8 | P 7246O7 I P
1031*38 j '031834
r:
~- - LC
*-' V, AJ
BURN ISLAND
l P 10307^6030788 | P I0307/
836 7QOO m N
CARMAN TWP.
LEGENDHIGHWAY AND ROUTE No OTHER ROADS TRAILSSURVEYED LINES
TOWNSHIPS, BASE L INES, ETCLOTS MINING CLAIMS PARCELS ETC
UNSURVEYED L INESLOT LINESPARCEL BOUNDARYMINING CLAIMS ETC
RAI'LWAY AND RIGHT OK WAY UTILITY LINES NON PERENNIAL STREAM FLOODING OR FLOODING HK.HTS ; SUBDIVISION OR COMPOSITE PLAN RESERVATIONS ORIGINAL SHORELINE MARSH OR MUSKEG MINES TRAVERSE MONUMENT
l t t
DISPOSITION OF CROWN LANDS
TYPE OF DOCUMENT
PATFNT SURFACE 4 MINING RIGHTS SURFACE RIGHTS ONLY .. MINING RIGHTSONLY .
LEASE SURFACE 8, MINING RIGHTSSURFACE RIGHTSONLY.. . ...MINING RIGHTSONLY ....
LICtNCE OF OCCUPATION ..... ...,ORDER IN COUNCIL ....RESERVATIONCANCELLED _. . . ,,SAND ft GRAVEL . ..,...... ....... ...
SYMBOL
0..... e
By
.... oc
ONOTE MINING RIGHTS IN PARCfcLS PATENTED PRIOR TO MAY 6
1913 VESTED IN ORIGINAL PATENTEE 6V THE PUBLIC LANDS ACT RSO 19)0 CHAP 300 SEC 63 SUBSEC 1
SOOM*lr*t
1000 — M*lr*(
10 10 20 30 40 SO 60 70halo* Ch*lnt
500 O 1000 2000 3000 4000 5000—i -———— - - -i i————————i F**l
SCALE 1:20 000GRID ZONE - l 7
NOTESTHE WHOLE OF MOOSE ISLAND IS ATTACHED TO THE TOWNSHIP OF CODY (FILE 23642)
FLOODING RIGHTS RESERVED TO ELEVATION 9O35' (TfiNO RAILWAY DATUM) ON NIGHT HAWK LAKE AND THAT PORTION OF THE FREDERICK HOUSE RIVER BETWEEN NIGHT HAWK LAKE AND FREDERICK HOUSE LAKE TO ONTARIO HYDRO
y J
THE. INFOMMAIION THAI APPPARS ON THIS MAP lA 1 , BtEN COMPILED
FROM VARIOUS bOURCHS AND ACCURACY IS NOT GUARANTFED THOSE WISHING TO STAKE MIN ING CLAIMS SHOUl D CON bULT WITH THE MINING RECORDER MINISTRY OF NORTHERN DEVELOP MENT AND MINES, FOR AH DITIONAl INFORMATION ON THF STATUS OF THE l ANDS SHOWN HFHEUN
TOWNSHIP
CODYMMR ADMINISTRATIVE DISTRICT
TIMMINSMINING DIVISION
PORCUPINELAND TITLES/ REGISTRY DIVISION
COCHRANEMinistry ofNaturalResources
LandManagement
B t dnehOntario
ORIGINAL COMPILATION
JULY 1984
REVISEDACTIVATE MARCH ,'4.
-3994
U, OC J*
(M
Oofto
Ulo l ;
l y f
U)
\
\
h- to L ^
l ^ ' ~ ——— *^ , , ^r l ,_ J.————,. - •gp.gi^r——~ ~"—'——"~ — —f ~ " ——"~ ~T
JBT i0 m (t,/u? in in ir
rtt^a^s^M*—91 : /J i i i i
35 o) ro
E. f"*a~-*. ^!A A
t 6/fc 5 yV */ * ^-—^
t-rT^tFTTir^^- R
5—8^"
lil
1 1V t
. t •t*
t,; '-"afm* ,n i, . ^avofw. r •**
\ l '/V'OON
din
-P- ^Ti
in*
1 t — *i.-ih"CM
1
CMm4
^^••^•^^ * ^ ' ^
CMl
CMin*
—— ** '
in-CM
1
CMin*
~^iKi
rLin*
CMl
. L CMin•f
-^--XL ^CM TT -*y--itinin•f
i ico inin CD* *
~ia--^lv -^in db ODCD CD CD\* 4 4 \
-'CM (VI1 i
i
CM Is-in ro
•fr -t\
1025831 s'TE
1- rroU)
— * — "^
"-T-. iinCD
~~— - ---4™,
CMCD
- •**.
4tii
CMCD
'^30**'l
— r ~OCD
^^^^s. *** ^1^^"**
CM li
CD^*
— -*— — ^^"CM iio~
••M-- r^~1 r
CMSj"
— .. —— si -.:, -j*s
1 *.
a
L. Ib + OON
l l ' 11 H)M
T" "
CMin•f\ i V) in in in* \ ^
1
CDin4
1Oin•f
t H
Y
i
en -ienCJl
JO 100
l l l
l l l
l'U
LEGEND
PwMttriu Mw-Mbi HL**p Survey
PRtaUEMCY: 1 777 Hi
C Grant E: lcm-20%
tXSKS EXPLORATION LTDC u h,.. IHHU I'lN I X]
li Mollhiijtti hlily. lilhiniii!. (In! i, 1M
Ml N !
'lMM'f K
/v MINI (* INI
MI: i in- M /MMi O'' C l Wl
MAX MIN II HzII 't.- Mm ...ile ' .M H')'
n! ri |i M -.fi l i
Nl',
No l 'If
o o(SJrO
OO-i-GO (M
O O
t sj
l
r i
i ti i
tUJ
IUOt ^
*ID
—*-
l (,6*-i)(il,
l b'S. (H)! l
L
*J 1C* a.
0)t
(T)-h
mA"
CO4
."f"'" l
* U)Is-
*
N- . CM
i
O IP4
COro1
f0 MS^ofji ^isF4
—x.
4 ,-- *----x-
Ostin xt4
—i. — ^
Q
l*r*v ^-H*-*^"**
roiio in
roi,o m
CMii
o m
ro
oroiiST CO•f
603
i i
O
'
*- ~
Is-
roir— ^
CMin•v^*k^.>^^
* 1*"" —
f
— x
r- ro i
r CMin4
^^m
i
- -*--
COK)
ll
CMin4
1
— —— M - ' "
( )
ST1l
ro in4
MriMMMk
i.n~--*j — ~efi~~ 0*4 o, ^ ox^u) in u m K^XcnCM CM CM OJ CM IM L*T rO vt S" oit st Si" \O
' 1 1 l 1 l ..--''l 1 1 iTT. 1 1 1V. ' , ^f" - . ,Xf,
in in in ^--"To . in 4 LH Is VA\n m Is-tp co co r- r- r ip up st r* ro ro st4 4 ^4 * * 4 4 ^ -f 4 \ 4 4 4
-'- -' - ^ . -A ———— -^
1 ' ^*^:"K) ip i ) ( ) 1 i ) it) i-*-- m ob *KN - 1: st St vt u) in I in sl^-'-^l ro CM CM pr;" "^r ——— 1 ——— 1~—-~. i ill --^' l l \ ,1 , ' Y---— -t; ' ' , ' 1-, i
CM CM CO if) 10 lin — l - O O CO o Kin in vt m ro IKI \r J co N r- CD Kf4illilfti4 (f
MikaaiMUi^M^ki^^A^ii^.^j^ . ^- — . ••IUII^M^M^ . — u - J - ^ .^n^.. V
in ro CM i
St CD
co4
ii
CM
CMii
O 00
inmi
-4
,oo
l M* DON
NK J l T HA WK
l.AKLL bhOON
Iron \Pi" —0 J)
(14001 JJ
L 48+OON
S-r^)
ii ,.
inro-j-
^M—
roii^\f4
—p -CM
ll .
IPmt
"VSCM
11
, r
cp4
0
ro
UD s
m
O)Mi
ihip
ii
CMCP4
— T
i
K)m4
1
1
St4
1i
IMKl4
1
doro4
"U)^ U) v]
— -^ \ ^^*
0
in
roii m IP4
^XCMi^^ r-4
ro004
in004
1J
-—tfV 004
•- -eg —i
— irr "004
~3T^i i—l; — "ro
CD4
"ST ^-:^\ro , r*? ^
-X. — — x —~ —-* — _—M-
.** -^ -* '
U)rOi
iij)~004
f-
roi i
— fQ— N4 ^
oi i
CO-V* ——
roii
-CTCO
r-
in ^
Lf'si
1 .1
•it•nTMr/4O 00 — CM
-W^---;
1. iIs-m
i" r ' '
ro in
i aa
Kr t1'"
)
tm*
flD- —— ifi.- ~~ CO
_. a . —
l J
00 O CMr- r-4 4
\
\ VMxi" '
1C
l CM ^^"ft-*i 4rIS/1b N VT
roN IP-f T
r- ? 9
m cp en
^•~ 1^^, l 1?* Ujl *
COoo ci)
I0?5fl2ft-rii-,
o in
CM CM
J——.
i---*-'
o 4
CM
•Q S* ^-.-41"-•—M — -
rM ——— i —— ' —— JC-
\\ t
CMro-Ju-
in ro
in roi
' — i —CMro t
A-tNx* —
•—-T''
'^Ss7\Y C J
CM r- in ro mCMN 00 CM Is-
in in \ K
MTV—4
i J^Ofr-
ro"ip o
W LO
CM
en.w— --
CMCO
cS"
o ro in CO
VV T
O)*~-1
0in4-
en— *— -io m4
CM-T--L
Oin4
' ~~**f ,
11 *"
COM"4
' CMi
0st4
CMi
TCMsr4
CM i
CM *4
CM \ CM
-\CM UT st tf4 4
\\
\\
L CM
Q . in (N O 00CO U) inf -i- 4
,. CM
LP
1025836
ro CM
th"" IT)
OIfci-1
-i-CMm
^4- ^— ,'
-. - — *
CMinj.
CM1
,. — - i - -
o in4
CMirOin4
m'i
(M st4
10
x.
sa.— .
ro
c^J^ O op^ 00 ^~~tf
—— —— *v-
004IV-
•f i
CMen4
QO,-— IsrrCOmi
— 44Vin*U)r4
•-" /'
rvjrAD/in
' 47
t
1
rrot
x "
OroiihK)4
* * —
lhK)4
* — ,
yiJC" l
l\
C3sii
•*- c —^
V 1\ C) (M\ vt St
t '— V--"0- - -^L .
1r-st4
-^ ^^
st-t- ~~i
i
Si4
. - -
CM in r^ "62 CM in mrororoiANfinmst4 4 * ^\ * 4 t 4
^1
1inM4
*f
- 10T
ir*)vi4
. - —
1
*J*fc?inin
y. o, ii
m oSi LO
4 4
\— •-Z\*n\-- - ~-r/ M v '01 i.i
m ' o \nxt CM fc
lx^
i
in4
101HT
tMl
S*vi11)
l
St1- -*— -~
1
inx 4
IVJ1
~r
U)Vi
t
1\l
-^ * -— " —
TKi-- CM
1l
Lf) St
v 4
_ . - — *"
**-^
CM ii
ro st4
"ooCM
!IM St4
-* -^
00 CM
l,ro st4
S^"IXIK)
11
OSt4
7li
•w ^-^r-O) "~
IM iiinvt4
, ^ * --"'
•-^1
1
r in4
-^
-^1
m ip4
* i ' /A ^-1N (\| ivj/Xl",li) ^VHU lOvS -*f'"--NTr^r i
x*-IM
F30 CM-8-
t*t
1025842 "
- I U - 'ID
\ '
U) U)4
i ( ) M
t
I
li)ro4
r- mfr
iID st4
1 —0in4
O iO4
—— 1 ' "
CM U)4
uTU")4
vi -v-u) m cjU) Lf) IT)444
9*OON
l
lU)St
*
N iin -stt
ii rost*
IUstt
ll
00stt
O CMir) ini 4
K)/ 1 .M t 1-
b*()ON N7-
iU)
. |V ) ^^^-*; — "
— —— .J. . —— -1 4
--^ ' , 1
esr- .rsi ^(ffIP or m444
-^i^^ju^^rT i ^f
. lSi CM CMin in m
t t 4
C^-*^)7 ~ *^J -sCM CM (S|
1 1 11 1 '
tt) m iost st si4 1 1
* —— - " —— —— ————— ——— MV
,sj 1** *)1 1 11 '
u ) r- iQ^LU v IQ in
m\ \v \
i\i ^^rVx Qff~-ivi^---*T4 j v^ Jtr-^-r^ j^/^ i*""i V0 t.^ U3Nr r- in
1 1 1
,, * — -^^
~~ctf m4
~~CP^
"-J ——
lNm4
1 1
i
00 00Vt St4 4
\C\'~J1 \J (
* *^^MH *-^^^
Q ^OJ
1^ f"Nini
^^^W^BJ^j^
-et-' r^i
i
lvlU)
i
T^Ch-
uv4 \
~-ti)— — 1
-d--..a r-m4
1t
inin•f
^ iM 7)(\ i•TJhl^^l' ii- *
CMl
-l00*f
1^••Mj^gj^^M•HPiffj— * " — - j-if JC^l
1i
l )U)4
?
V^-
in•f
\V
n!T^J-•rr-m4
1
1
inin4
1*
,il*—' wO^
CMlr
00 ^t
*tfPt'
:iW'-arCM
i
(i)Mi
ro4l-.X"'
" CMm*
^ .* —^ j-tiT)4
1 — Kr i
omt
-^PCM
11
CMm*
*"-*^r
CM1
(I)vi
i
r-'"-~ r
CMv ^* iin4
j * *^ ''^
m ~~T'
iCMm4
^
r*-f*V"CM\
CMin*
"^""W — ~-CM
11COin*
^3P--T*J
1
/Mu ii
l)-.T-in4
- -^ 1
1
CMini
— *h-CM
11IAO
irK4
tk L ~-|H| .CM
iihini
ii
- L-T^r-iriIDt
Tf*
ii
U)U)t
^tfa-CMi
Cim4
—-' (
*. *~l
1ro (D
i
L)--hi•fiILi
i
03 vj
IM
*r~
r-m4
•""""c
Cc.
Jv -* ""
))
IP --1
r-in4
0)-Ti
inU)4
.-*IJ1
CMm4
- l^-I
in*O4
"tC ~l
p^in4
15T6in•f
CMl
lCOst4
T*)~-
I
iCM LO4
-T^.-,
l
l
CMin4
-I**--
l
rL in4
~™~~
l 1in in4
rCMLf)4
U)U)4
U)l/)t
Om t r*)
ro-i CMo ro
r- m
rO ii
CM ST4
Sin4
"^gtr;ii COin4
in in4
-iL-
1
OCO t
CM U)4
— Q--^-w- J1
m in4
\m
X
iiin in4
"to
L 0*00 r-ir } " i ' . * . '
OC) *^(1)i M (-1
OC.)r
* jCM
lil
l AllliMI III! l l l / O
16-C
O'A
'
4+3
2K-3
l -3
2 O
r 3d
f 6
331-2
f -3
2 (
1-2
33-,
t-5
'45
' '(2
j :^
Bt-
ro
+29^-
6
f *311
*7*
*3Q
|H[3
!,, J
-! ^
O
ui 4^ •f O
O
enO
) o •f c o
O
l * i
enen
en 4 O o
35
-jr6
i *35 rd
t36r it
36^'
-3
' *3
5J!
-3
+ 364-2
f ii i
i i i35
^ -
-
-35
*-
-36
r-\
'\
i '
i1
i i
36 f"
!*36fQ
l l
j-
-35f
*2
l
3B*-
'3
- *3
sf*
; "O
-3
5^-
i -
-35
--5
' '
" '
'i'
^.33
^ -i
: *3
9f *
' x
\ [
i
|
*35J
-i
l
,•3
^- -
5l
37^-2
.
.co
f *2
-
-35^-
2
- *
3d
--5
\ l
' ^-^
* i
35-^
5
*3S
ijO
t3^
- i-
^^S
t,
—
i i ' i ^5f
*tto
|
H\
1 "'
1 \
1 '
* *3
3- *
-6
; ^3
^- *
^ :
*42-
^
' ^
-3~
\ - 2
-3
3-i
-5
-
-±ti.A
35 -
*-5
^
*^7
4l-A
^^ ^
^ *^
y
r T
Q
tt'
1 &
MH
O,'
-zoo
f4
.i i^^^
^i"s
? r.
T7-2
H
/- r
1 0 0
/ -
1 1
^
li
-3
J , .
- tf
.—
— ' —
——
——
—
^
^ j
' /'
if -6
;V
3^f-
! '
*37^.
2i
f '
; '
11
'-d
)b -
-o
. .^
r
.-li
r w
r '
* \
*3i-
-5
-33f
c- ^
7 '
i-
-36i
— 2
; *3
7*-*
2'
'X\
^-^4 —
——
——
— 3
^V
4i
1-'
l,3
7^-4
.,-
- ^3
5 45
__
!X'
D^^
-'0
; *4
0^
*^
' *^
M-
^7
* Jr
(Lj*
- '
^33-
v7;
' V
' 1
, x
' ^
A-
-'
. ,/ .
^
\-j
L -
- i
. .
; .
\
^
: *33
-jl-
4
-8
; -3
5-1-
3^
-39^*
2
l
32-O
OW
l
W 0 N444xi-fc-r"
\4 4 4
CV)4
**m4
CM ^ NJ.-^- ————CO 00 0ro m tf4 4 4
in-j — .3- sr4
tf1
'f -a
N 4
CM N4 4
sr-,e ' f m4 4
•HO 25819
L 5KOON
L 39+OON
L 36+OON*
L 33+OON
L 30*OON
L 27+OONI025822
————~f——\L ^ JTL ^ g|S S"" ri!?r TT K) 10 in rn L 24+OON* 4 4 *
L 3+OON
L 0*00
EXSICS EXPLORATION LTDP.O. Box HIO, P4N-7X1Suitt 13, Holiingv Bid). Tkmiiinf OntTtltphont: 705-2*7-4151
OAK MINES INCROYALGROUPCLAIMMINTEK
CODY TWP.
MAX MIN II 444 HzDate: March I994 Scale: l"-200'Drawn: P.G. Interp: J.C. Grant Job No. E-46 ~|
32+O
OW
28+O
OW
24+O
OW
774
^
20+O
OW
V
IG +
OO
W
728
718 \
714
\71
57
78
5
i 71
4-l
714
773
780
782
4-C
OW
69
3^
69
5^
686
683
)67
9
820
823
669^
66
^3
735 \\
LU OO4-OD
Lu Oo•f C\J
LJ Oo•*- (D
LJ OO
4-
CJCM
i
/j t DON
u o o4-(M ro
Luo o•f CDro
LJ o ofo
L 39-nOON
GOtOuN
cvj en trcvi en in cvj/— oo oo ro ooo o* o o^ 01
i Vi.OON
l ai*ooN
J* ro^cg oo ro V 01 r- r- ^^V
IS r-
L 48+OON
N im 10 m\ rorororocMCMCM?J o/oo (r* ro oo^o tnaiO) O)
L 45+OON
f * ** ^afex Jr*. i
L 42+OON
ro en oo w en in— ,CD N N (Dfororororo/rvjcvjcvicvi c\o en en en oo
1025826
o o ^ m LOCM CM CM .t ^P, O ID CD
m CM/GO sr oro CM o CMID/in m in inID 10 LO U) UU)ID ID ID
ro'ro In O/.CM in O O
8 iL 18 + OON
CD CM o N ID in ro ro in CM OVID ro CM CM CM ro in — -. N oo ADNNNlDU)U)U)U)tDNNU)lDCDU)U)U) IDXO N 00 00 00/OLO ci) ID (D ID U3/UP ID ID U) 10 U)r———l——————r—————Jt———.—.—————l—————r-
L 15 + OON
L 12+OON
en otp (X) Ip ID/b (b Cb tb ID'ID' ID'^D
CM — — CMro ro roID ID
L 3^00N
u o o
L 36+OON
L 33+OON
L 30^00N
L 27+OON
L 24^-OON
?UOON
NICiHJ HAWK LAKE
LU OO*
ci)
U O O
o o
uooL 0+00
•4O
LU OO•fCO
LU O O
LJ OO-U)
LJ OOfa(M
LUo o*
(\J
LEGENDInttrummt: EDA OMNMVParomttro Mtaturtd: Earth's total magnetic fUldAccuracy: */- l nano-tttlasDiurnal*: Corrected by batt station recorderContour Interval: 0,10,20,30,40,50...Reference Field: 59,000Datum Subtracted: 58,300
EXSICS EXPLORATION LTD.P O Box 1880, P4N-7X1Suite 13. Hollinger Bldg. Timmins OntTelephone 70S 267-41S1
CLIENT ROYAL OAK MINES INC.PROPERTY MINTEK CLAIM GROUPTITLE CODY TWP.
CONTOURED MAGNETOMETER SURVEY
Date March I994Drawn P G
Scale: r^Interp J.C. Gran!
NTSJob No E-48
i;,