134
GCI III Bidders Conference Vienna, Austria, 30 March 2016 Arcotel Kaiserwasser Wien BC Organizing Committee: Fernando Araujo, Mensah Solomons, Courtney Linley PM: Fernando Araujo

GCI III Bidders Conference · 2016-04-08 · GCI III Bidders Conference The GCI III TIMELINE Presented by: Fernando Araujo, Chief of Operations Operations Section, IDC Division GCI

  • Upload
    others

  • View
    18

  • Download
    0

Embed Size (px)

Citation preview

GCI III Bidders Conference Vienna, Austria, 30 March 2016

Arcotel Kaiserwasser Wien

BC Organizing Committee: Fernando Araujo, Mensah Solomons, Courtney Linley

PM: Fernando Araujo

Wednesday , March 30 2016

08:30

Registration and Welcome (Badge and Material Distribution)

Introduction, Overview, Timeline

09:30

09:40

09:50

Welcome and Opening Remarks : R. Bell, IDC Director, Project Executive

Introduction, presenters information and conference overview by F. Araujo, PM

The GCI III timeline by F. Araujo, PM

10:00 Coffee Break

Session I: GCI III: Procurement guidelines / the GCI III ToR: Chapters 1-2-5

10:15

11:15

11:30

12:00

The GCI III Procurement Process: Courtney Linley, Acting Chief, Procurement

The current GCI II: A Short overview , Efren Abaya GCI&NO Unit Head, IDC/OPs

The GCI III Statement of Work: Fernando Araujo, Chief Operations , IDC/OPS

Q&A Forum (legal & commercial) Led by Procurement

13:00 Lunch Break (At Hotel Restaurant)

Session II: the GCI III (chapters 3-4): Maintenance, Spares and configuration management- SPT

Engineering and Operations: NMS and Incident Management , Performance monitoring

14:00 The GCI III Site Profile Table, logistics and maintenance: Mensah Solomons, Chief Network and Systems Support, IMS/NSS

14:30 The GCI III: Engineering and design by E. Abaya GCI&NO Unit Head, IDC/OPS

15:15 The GCI III Operations: Performance Monitoring Section 4 : F. Araujo , Chief Operations, IDC/OPS

15:30 Coffee Break

15:45 Q&A Forum (technical ) Led by IDC/OPS and IMS/NSS

16:45 END

GCI III Bidders Conference

Section 1 (Introduction) and Attachment 1 (The Current GCI II)

Presented by:

Efren Abaya, Head, GCI&NO Unit Operations Section, IDC Division

GCI III

Bidders Conference

• To introduce TOR Section 1 (Introduction)

• To introduce TOR Attachment 1 (Technical Description of GCI II)

IDC/OPS Page 2

Purpose

Section 1 – Introduction

Scope and structure of the TOR

Introduction to the Preparatory Commission, Global Communications Infrastructure, International Data Centre, International Monitoring System, and connected networks

Section 2 – Statement of Work

Tasks, deliverables, documentation, activities, reports and schedules to be met

Section 3 – Specification of Requirements

Mandatory and desirable functional, architectural, technical and operational specifications

Section 4 – Service Level Agreement

Key Performance Indicators and metrics; penalty provisions for the project implementation (migration) and post-implementation (operation)

Section 5 – Benchmarking

Optional independent 3rd party benchmark of GCI pricing and service levels from the 3rd year on

Attachment I – Technical Description of GCI II

Attachment II – Site Profile Table (SPT)

Attachment III – Formats and Protocols for Continuous Data CD 1.1

Attachment IV – Formats and Protocols for Messages

IDC/OPS Page 3

GCI III TOR Outline

Preparatory Commission for the Comprehensive Nuclear-Test-Ban Treaty

Organization (PTS/CTBTO or “the Commission”)

Engaged in building up a verification regime including a worldwide

International Monitoring System (IMS) and an International Data

Centre (IDC) in Vienna for the purpose of detecting signs of nuclear

explosions

Global Communications Infrastructure (GCI)

Transports monitoring data in near-real time from IMS stations to the IDC

Transports data and IDC products to Member State National Data Centres

Facilitates remote operation and maintenance of IMS station equipment

International Data Centre (IDC) at the Vienna International Centre (VIC)

Collects, processes, analyzes IMS data and transmits data & products to

Member States (both automated analysis and human analysts)

Data Centre in Vienna is the connection point to the GCI

Possible future backup IDC at another location

IDC/OPS Page 4

TOR Section 1 - Introduction

International Monitoring System (IMS) Facilities

IMS stations & Radionuclide Laboratories (total number: 337)

Send monitoring data continuously or periodically to the IDC

Mix of: staffed or unstaffed/unmanned; normal office environment or remote & harsh environment; easy to difficult/restricted access

Operated by organizations that are independent of PTS/CTBTO (“station operator”), with or without formal contractual arrangement

Network-wise, all stations are TCP/IP devices connected to the GCI

National Data Centre (NDC)

Receives data and IDC products Traffic flow is predominantly from IDC to NDC

Independent organization, separate personnel from the PTS/CTBTO

Considered to be an untrusted node from the network security standpoint

PTS/CTBTO provides the GCI link at no cost to the NDC

CTBTO prefers Internet VPN connection, if possible

IDC/OPS Page 5

TOR Section 1 - Introduction

IDC/OPS Page 6

Distribution of IMS Facilities (Figure 1.2)

Station Operator, CTBTO Contractor

Some provided with a GCI connection for remote access to an IMS facility

Requires bandwidth management

Tsunami Warning Centre (TWC)

Receives selected IDC data Traffic flow is from IDC to TWC

Internet VPN connections

Shared User

“Rides on” the GCI for remote access to the same physical location as an IMS facility; or to receive data from that location

IP protocols may be different from what is used at an IMS facility or NDC

Requires bandwidth management

IDC/OPS Page 8

Section 1 – Other facilities connected to GCI

Independent Subnetwork (ISN) and other networks

Entire network of IMS facilities and communications links operated and maintained by a Member State

Connects to the GCI at one designated communications node

May use satellite or terrestrial communication links

Higher data rates than single IMS facilities or NDCs

Considered to be an untrusted network from the network security standpoint

IDC/OPS Page 9

Section 1 – External networks

See CTBTO web site

http://www.ctbto.org/verification-regime/the-global-communications-

infrastructure/page-1-gci/

• In operation since 2007 until mid-2018 with one GCI Contractor

• 24x365 managed service provided by the GCI Contractor:

Network Operations Centre and Service Management Desk

Network Management System (NMS)

Field Service

Parts replacement (door to door)

• Mix of C-/Ku-band VSATs, terrestrial MPLS and Internet VPN services

Full network: 249 VSATs, 6 terrestrial, 45 VPN

Installed now: 217 VSATs, 6 terrestrial, 32 VPN

• Remote sites in ~100 countries on all continents

• Key Performance Indicator targets:

99.5% availability over 12 months for VSAT links

99.95% availability over 12 months for terrestrial links

IDC/OPS Page 10

TOR Attachment I – Technical Description of

GCI II

IDC/OPS Page 11

Distribution of GCI remote sites

• Backup arrangements to improve link availability

VSAT + Internet VPN

Dual VSAT

Dual MPLS circuits

Dual MPLS + Internet VPN

• Every remote site has cold spares or hot standby equipment for all electronic

equipment, except the UPS

• Challenging sites: Anti-ice heaters in snow areas; Radomes; High wind

antennas; Overvoltage and surge protectors

• TCP/IP network for both user traffic and monitoring/control

• Traffic primarily directed to the International Data Centre (IDC), but remote-

to-remote connections are supported and controlled

• Different classes of traffic with end-to-end traffic prioritization

• Commission manages the private IP allocation plan

• Point of Contacts appointed by the Commission for every site

IDC/OPS Page 12

TOR Attachment I (Description of GCI II)

IDC/OPS Page 13

Some challenges at GCI II remote sites

IDC/OPS Page 14

Some challenges at GCI II remote sites

IDC/OPS Page 15

Some of the challenges faced by GCI II

Thank you!

IDC/OPS Page 16

GCI III Bidders Conference

The GCI III TIMELINE

Presented by:

Fernando Araujo, Chief of Operations Operations Section, IDC Division

GCI III

Bidders Conference

Chapter 1 – Introduction

Introduction to the Preparatory Commission, Global Communications Infrastructure, International Data Centre, International Monitoring System, and connected networks

Chapter 2 – Statement of Work

Project and Services Schedules (2.3)

Chapter 3 – Specification of Requirements

Project Plans

Design Specifications and other documentation

Technical Requirements for transport, NMS and ticketing systems, Network Operations Center

Provisioning, Integration, Validation and Verification

Other support components for a GCI

Chapter 4 – Service Level Agreement

Key Performance Indicators & Penalty provisions

Annex I – Site Profile Table (SPT)

Annex II – Technical Description of Global Communications Infrastructure II

Page 2

GCI III TOR Outline

IDC/OPS Page 3

GCI III Timeline (Procurement)

The planned contract duration will be 11.5 years and subsequent optional annual

extensions up to a total of 5 years. The duration of the contract is broken down in the

following stages:

– Design and Start-of-Service Migration, 1.5 years

– First 5 years of service management after Start-of-Service Migration Complete

– Next 5 years of service management including End-of-Service Migration (if no extension is exercised)

– Optional annual extensions up to 5 years including End-of-Service Migration.

IDC/OPS Page 4

GCI III Timeline (Proposal validity – Contract stages )

The Proposal shall be valid until 31 January 2017.

An extension of validity may, in exceptional

circumstances, be requested by the Commission.

IDC/OPS Page 5

GCI III Timeline (Pre-Migration to Implementation)

IDC/OPS Page 6

GCI III Timeline (Pre-Migration to Implementation)

• 8 Months for migration with two major control points

• 5 months for PIVV (Provisioning, Integration, V&V)

• 4 months for Design

• 2 months planning and review

• 19 months

IDC/OPS Page 7

GCI : a worldwide network

• Not just Project Management but also Change Management

• Introduction of new technology, systems and processes

• People, process, technology

• User perceptions

COVERAGE

CAPACITY

OPERABILITY

IDC/OPS Page 8

GCI II to GCI III

IDC/OPS Page 9

GCI III Timeline Post-Implementation

IDC/OPS Page 10

GCI III Timeline Post-Implementation

• 120 month operation

• 18 months Technology refresh phase

• 4 service reviews

• 12 months for end of service phase

IDC/OPS Page 11

• 225 VSAT and Terrestrial links

IDC/OPS Page 12

GCI III: a graphic reference

Not only Project Management but also Change Management

• Innovative approaches on technology

• Cost Savings

IDC/OPS Page 13

GCI III : The expectations

Thank you!

IDC/OPS Page 14

30 March 2016 Page 1

Request for Proposal No. 2016-0022 for the Provision of the Commission’s Global Communications Infrastructure

Courtney Linley Acting Chief, Procurement Section Preparatory Commission for the Comprehensive Nuclear-Test-Ban Treaty Organization Provisional Technical Secretariat Vienna International Centre P.O. Box 1200 A-1400 Vienna AUSTRIA

30 March 2016 Page 2

RFP Overview

RFP release 17 February 2016

Bidders’ Conference 30 March 2016

Deadline for clarification requests 8 April 2016 (related to ambiguities, omissions or mistakes in the RFP documents only)

Closing Date of RFP 3 May 2016

(17:00 Vienna Time)

Evaluation of Proposals, clarifications, May–Nov, 2016 Additional information, Negotiations and site visits

Notice of award December 2016

Regret letters December 2016

Contract signature and kick-off January 2017

30 March 2016 Page 3

RFP Documents

Letter of Invitation

• RFP Acknowledgement Sheet

Instructions to Invitees

• Appendix 1, List of States Signatories

• Appendix 2, Statement of Confirmation

• Appendix 3, Vendor Profile Form

• Appendix 4, Compliance Matrix of Core Requirements

• Appendix 5, Costing Template

• Appendix 6, RFP Checklist

• Appendix 7, Pro Forma Bid Bond

• Appendix 8, Authorization of Limited Disclosure- for contacting references

30 March 2016 Page 4

RFP Documents

Contract • Annex A, General Conditions of Contract

• Annex B, Contract Price, Options and Payment Schedule [not included, place marker for the final contract]

– Appendix 1 to Annex B (SLA)

• Annex C, Terms of Reference dated 12 February 2016 (TOR), including:

– Attachment 1, Technical Description of GCI II

– Attachment 2, Site Profile Table

– Attachment 3, Formats and Protocols for Continuous Data CD 1.1 (electronic download only)

– Attachment 4, Formats and Protocols for Messages (electronic download only).

• Annex D, the Contractor’s Proposal [not included, place marker for the final contract]

• Annex E, Form of Performance Bank Guarantee

30 March 2016 Page 5

Instructions to Invitees

1. GENERAL In addition to a fully compliant baseline solution, Invitees are welcome

to propose alternatives which will result in better and more economical execution of the work, but which shall, however, meet all functional needs and comply fully with the Service Level Agreement of the Terms of Reference

• ELIGIBLE SERVICES AND EQUIPMENT – Origin shall be in one of the State Signatories of the CTBT

• PROPRIETARY INFORMATION – Documents are proprietary to the Commission

• COSTS OF PREPARATION AND SUBMISSION OF THE PROPOSAL

– Invitees shall bear all the costs

• ETHICAL STANDARDS AND CONFLICT OF INTEREST – The Commission reserves the right to reject a proposal if these standards

are not strictly followed

30 March 2016 Page 6

Instructions to Invitees

2. PREPARATION OF THE PROPOSAL

• REQUESTS FOR CLARIFICATION – Only requests for clarification in writing related to ambiguities, omissions

or mistakes in the RFP documents – Following Bidder’s Conference- one final round of clarifications accepted

by 8 April 2016. Responses by the Commission provided by 15 April 2016.

• AMENDMENT OF RFP DOCUMENTS – RFP may be modified by amendment

• LANGUAGE OF THE PROPOSAL – The Proposal and all correspondence and documents relating to it shall be

written in English

• VALIDITY OF THE PROPOSAL – The Proposal shall be valid until 31 January 2017

30 March 2016 Page 7

Instructions to Invitees

3. FORMAT AND SUBMISSION OF THE PROPOSAL (1) – The Proposal and supporting documentation shall be dated and signed by

an official, clearly legally authorized to enter into contracts on behalf of the Invitee

– The Proposal shall be submitted in two (2) sealed envelopes

– One envelope shall contain the Technical Proposal (without prices and commercial terms). The second envelope shall contain the Financial Proposal (with prices and commercial terms)

– One (1) original, seven (7) hard copies, and one (1) CD (e-form- Must be Word, Excel or PDF -Searchable)

– All sealed envelopes shall be clearly marked as explained in the Instructions to Invitees

– If the envelope is not sealed and marked as required by this RFP, the Commission will assume no responsibility for misplacement or premature opening

30 March 2016 Page 8

Instructions to Invitees

3. FORMAT AND SUBMISSION OF THE

PROPOSAL (2)

– The Proposal must be received by the Commission in the Office of the Chief, Procurement Section, by the Closing Date, Tuesday 3 May 2016 (prior to 17:00 Vienna Local Time)

– Attention is drawn to the security arrangements at the site where the Commission is located, the Vienna International Centre, and to the fact that courier or hand delivery will involve access procedures, which must be considered by Invitees before submission

– Except in the case of responding to an RFP clarification, Invitees shall not contact the Commission on any matter relating to the Proposal after its submission and until the award of the Contract

30 March 2016 Page 9

Instructions to Invitees

7. OPENING OF PROPOSAL

• All Technical proposals

• Financial proposals, subject to technical acceptability – Opening of the proposals are done internally

8. EVALUATION

• Technical evaluation

• Financial evaluation (technical acceptable bidders only)

• Potential bidder presentations/ On-site visits following the first

phase of the technical evaluation- at the discretion of the

Commission

30 March 2016 Page 10

Instructions to Invitees

9. CONTRACT AWARD

• Proposal that provides best value for money

30 March 2016 Page 11

Instructions to Invitees

4. GUIDELINES FOR INVITEES (1/4)

• Contract duration – The planned contract duration will be 11.5 years with subsequent optional annual

extensions up to a total of 5 additional years

• Licence application guidance – The Commission will make available a licence inventory and the files before EDC

for use by the successful bidder

– The licence files should serve as reference for conversion of all of these licences

– Because of the Commission’s license fee exemption in certain jurisdictions,

licence fees charged by regulatory authorities shall not be included in the

Financial Proposal

30 March 2016 Page 12

Instructions to Invitees

4. GUIDELINES FOR INVITEES (2/4)

• Reuse of existing equipment – The existing civil works shall be used. Invitees have the option to reuse any or all of

the GCI equipment at all existing sites – If any equipment is reused it shall be clearly stated in the Proposal. – The successful bidder shall take full ownership of this equipment under the Contract

and be responsible for the service of this equipment

• Off-the-shelf – All hardware, software and firmware to be provided in response to this RFP

shall, to the maximum extent practical, be commercially available, off-the-shelf (COTS) and in current production: » Have been formally introduced into the market before the Closing Date of this RFP » May be demonstrated during the evaluation of Proposals to validate that the items meet

all requirements of this RFP » Are sufficiently available to satisfy the delivery requirements of the Contract, as

described in this RFP

30 March 2016 Page 13

Instructions to Invitees

4. GUIDELINES FOR INVITEES (3/4)

• Satellite frequency band – In consultation with the Commission, the Contractor may choose any convenient

frequency band within a region.

• Terrestrial connection – The Terms of Reference implies that sites will be served by satellite

connections. The Invitees are however free to propose terrestrial connections

instead, if this should prove technically desirable and cost effective.

• VPN over Internet – VPN over Internet shall not be a primary service for the Sites unless discussed

and agreed with the Commission. For all other cases, it may be considered as

part of a back-up service, where a back-up service is proposed, or as a last

resort only for a primary service.

30 March 2016 Page 14

Instructions to Invitees

4. GUIDELINES FOR INVITEES (4/4)

• Assistance at the Sites – Considering the wide range of skills of local operators and a large number of

unmanned Sites, GCI Equipment that requires minimal involvement of local operators by maximizing redundancy, built-in-tests, and capability of remote troubleshooting is preferred

– Invitees shall assume in the Proposal and its costing that the local operators of the Sites will only be available to provide access to the Sites

– The Commission has other arrangements in place for a number of Sites and will negotiate the Site maintenance with the successful bidder, as applicable

• Site survey – Invitees are expected to make use of the information in the Commission’s site

survey reports to minimize the number of visits to the sites

– These reports will be made available after the contract kick-off

30 March 2016 Page 15

Instructions to Invitees

5. PROPOSAL

5.1 Technical Volume Statement of confirmation- To be included with the Technical Volume • Section 1 - Company overview: 5 pages • Section 2 - Executive summary: 3 pages • Section 3 - Detailed technical response: 90 pages • Section 4 - Attachments • Section 5 - Compliance matrix (Appendix 4 to the ITI) • Section 6 - Key personnel • Section 7 - Subcontractor(s) • Section 8 - References • Section 9 - Bid Bond (Appendix 7 to the ITI) • Section 10 – RFP Checklist

– The pages refer to maximum. Invitees are encouraged to be concise and keep the number of pages as low as possible

30 March 2016 Page 16

Technical Proposal Content

• Company Overview (5 pages)

− Snapshot/highlights

− Core business description (relevant experience)

− Management overview

− Achievements

− Customers

− Strategic partners

− Deployments

− Size (revenues, employees, net operating income, etc.)

− Quality certifications

30 March 2016 Page 17

Technical Proposal Content

• Executive Summary (3 pages)

− How does the technical proposal

» Address the requirements

» Meet the time constraints

− Project management methodology

− Service management approach

− Major subcontractors

− Key differentiators

− Demonstrable benefits/advantages

30 March 2016 Page 18

Technical Proposal Content

• Detailed Technical Response (90 pages) − Project Management

− Quality Assurance

− Project Schedule

− Service Migration

− Service Availability

− Service Operation and Management

− Network Operations Centre

− Security Plan

− Network Engineering

− Design Scalabilty

− Site Provisioning

− Power Consumption

− Licensing and Regulatory

− Risk Register

30 March 2016 Page 19

Technical Proposal Content

• Attachments (draft versions)

− Project Management plan

− Quality Assurance plan

− Risk Management Plan

− Project Implementation plan

− Communication Plan

− High Level Design Document

− Project Implementation Plan

− Service Migration Plan

− Training Plan

− Security Plan

30 March 2016 Page 20

Instructions to Invitees

5.2 FINANCIAL VOLUME (1) − Proposal shall be in US dollars and/or in euros and shall be submitted

strictly in accordance with the format of the Costing Template

Section 1 – Statement of Confirmation- To be submitted with Technical Volume

Section 2 - Best customer Confirmation Section 3 – Costing Template(s)- USD, EURO or both

– Firm fixed prices until 30 June 2023 – Ceiling prices for 1 July 2023 until 30 June 2028 and optional annual

extensions – Options, firm fixed until 30 June 2023, thereafter ceiling prices – Service Review (2021 and 2026)

» Contractor provides conversion proposals for 2023-2028 period and optional annual extensions » Commission reviews Contractor’s performance and conversion proposals and examines

competitive situation

– Optional annual extensions » 1 year service extensions up to 5 years » 12 months notice period prior to each extension

30 March 2016 Page 21

Instructions to Invitees

5.2 FINANCIAL VOLUME (2) • Section 4 - Payment Profile Requirements

– Milestone payment schedule during Design and Start-of-Service Migration Phase

» To be proposed by Invitee and negotiated with the Commission

− The remainder of the cost incurred during the Design and Start-of-Service Migration Phase shall be evenly spread over the first five (5) years of full service management, starting when the Start-of-Service Migration is completed.

− Quarterly payments after Start-of-Service Migration Phase » Payment for a given quarter may vary, but shall represent at least the service cost of that

quarter

30 March 2016 Page 22

Instructions to Invitees

5.2 FINANCIAL VOLUME (3)

• Financing details – Applicable interest rate

– Total mark-up for interest charges

– Other financial assumptions

• Ownership – Contractor will remain owner of equipment

– Contractor shall dispose of the equipment at the end of the Contract by arranging for return shipment of all equipment

– Commission shall have right to take over ownership at the expiry of the Contract without charge

30 March 2016 Page 23

Instructions to Invitees

5.2 FINANCIAL VOLUME (4)

• Performance Bank Guarantee – As defined in the Contract

– Template attached as Annex E

• Delivery Duty Unpaid (DDU) door-to-door – Proposal shall include the costs of the equipment/goods, packing and

handling, insurance, transportation and freight, customs clearance (if applicable) and delivery to the office of the Commission or the Sites.

30 March 2016 Page 24

Instructions to Invitees

5.2 FINANCIAL VOLUME (5)

• Taxes – Austrian companies shall list VAT separately

– EU companies shall exclude VAT due to VAT exemption status of the

Commission (EU VAT directive No. 77/388/EC)

– Non EU companies shall list VAT separately, if applicable

• If, in spite of the Commission’s exemption status, taxes,

custom duties, or licence fees are to be paid, these will be

reimbursed based on actual expenditure. – Subject to prior approval by the Commission

– Proof of expenditure to be provided

– No burdening with administrative costs

30 March 2016 Page 25

Flow of Costing Data

30 March 2016 Page 26

Costing Template: Key cost elements (1)

• Information – Glossary: Description of the required input

• T1 - Budget summary: Summary of the costs reported in Table 1 to 6

• T2 - Programme management: Includes of costs related to Programme Management

• T3a - Satellite site summary: Costs relating to installation, operation and maintenance of the Sites

• T3b - Site equipment: Cost all equipment to be installed and maintained at a given site

• T3c - Basic equipment package: Cost of basic sets of equipment grouped into packages that could be applied to several sites.

30 March 2016 Page 27

Costing Template: Key cost elements (2)

• T4a - Primary satellite network gateways: Cost relating to the installation, operation and maintenance of the primary satellite network gateways

• T4b - Site Back-up service (if proposed): Cost relating to the installation, operation and maintenance of a back-up service if proposed

• T5 - Terrestrial connections: Cost relating to the installation, operation and maintenance of the terrestrial connections including back-up if proposed

• T6 - Network management and control: Cost relating to the network management and control

• T7a - Options for satellite and terrestrial sites: Additional information and cost of options described in the response to the RFP

• T7b - Cost for installation of new sites, decommissioning and relocation of existing sites: For sites not foreseen in the TOR

• T7c - Summary of labour costs: Daily labour costs for various professional categories

30 March 2016 Page 28

• Tables shall not be modified or edited unless specified − Enough space has been provided to take into account specific proposals

• Cells are colour coded − Green cells are empty and shall be filled (if applicable)

− Orange cells contain formulas and shall be neither filled nor edited

− Grey cells are empty and shall be neither filled nor edited

• Non-recurring costs (NRC) and recurring costs (RC) − NRC should be reported during each migration phase, in accordance with

the installation plan, except for sites whose installation may occur after the

end of the first migration phase

− RC should be reported in accordance with the installation plan and for the

remainder of the contract

Costing Template: Filling the cells

30 March 2016 Page 29

Contract

MAIN SECTIONS 1. Definitions 2. Aim of the Contract 3. Responsibilities of the Contractor 4. Responsibilities of the Commission 5. Contract Price and Terms of Payment 6. Penalties 7. Contractor’s Claims and Remedies 8. General provisions

Annexes A. General Conditions of Contract B. Contract Price, Options, and Terms of Payment C. Terms of Reference D. Contractor’s Proposal E. Form of Performance Bank Guarantee

30 March 2016 Page 30

Contract Penalties (1/2)

If Contractor fails to deliver at the dates specified

1. Initial Project Planning Phase: US$5 000 for each day of delay

2. Project Design and Technical Review Phase: US$10 000 for each day of delay

3. Provisioning, Integration, Validation and Verification Phase: US$10 000 for each day of delay

4. Network Implementation and Migration Phase: US$10 000 for each day of delay

30 March 2016

Migration Schedule

Page 31

30 March 2016 Page 32

Contract Penalties (2/2)

If Contractor fails to meet Quality of Service

• Unit of penalty shall be based on the sum of inbound and outbound

committed information rates (CIRs) in the Site Profile Table using TOR Table 4.9 (minimum US$2 000 up to 50 kbps, thereafter adding USD500 for every 10 kbps increment of CIR).

• For unavailability of Network Management Data, the unit of penalty shall be US$1 000. If more than one system is used for Network Management, unavailability on any of the systems is subject to penalties.

30 March 2016 Page 33

Contract Changes (Clause 8.3)

• Changes to the Contract, to Annex B and to Annex C may be requested by either Party and shall be implemented by a formal amendment of the Contract in accordance with Clause 8.3

• In case the change is requested by the Commission the possible additional cost/saving shall be borne by/credited to the Commission. In case the change is requested by the Contractor the possible additional cost shall be borne by the Contractor

• All changes leading to de-scoping of Work shall lead to a corresponding Contract Price decrease for the Commission

• The pricing for changes to the Contract shall not exceed the unit pricing of the original Proposal of the Contractor (Annex D). If market prices have decreased the Commission shall receive the full benefit.

30 March 2016 Page 34

Contract Compliance

Invitees shall provide the Commission with a statement that

they have carefully reviewed the Contract and Annexes and

are in full agreement with their terms and conditions

30 March 2016 Page 35

Benchmarking

Due to the length of the Contract and the many potential

changes in the industry over the contract period, the

Commission reserves the right, as indicated in Section 5 of

Annex C (Terms of Reference) to contract an independent

3rd party (reasonably acceptable to the Contractor) to

benchmark costs and service levels for the Work under the

Contract. Should it be determined that costs and levels are

not in line with the market, the Commission shall inform

the Contractor in writing.

GCI III Bidders Conference

Section 2 the Statement of work

Presented by:

Fernando Araujo, Chief Operations Section, IDC Division

GCI III

Bidders Conference

• To introduce significant sections on TOR Section 2

IDC/OPS Page 2

Purpose

Statement of Work.................................................................................................................................. 17 2.1. Scope of Section ..................................................................................................................... 17 2.2. Documentation ........................................................................................................................ 17 2.3. Project and Services Schedules ............................................................................................. 19

2.3.1. Initial Project Planning Phase .................................................................................... 20 2.3.2. Project Design and Technical Review Phase ............................................................ 21 2.3.3. Provisioning, Integration, Validation and Verification Phase ..................................... 21 2.3.4. Network Implementation and Migration Phase .......................................................... 22 2.3.5. Service Operation and Management Phase .............................................................. 22 2.3.6. Training Courses ........................................................................................................ 24

2.4. Key Personnel 24

Section 1 – Introduction

Scope and structure of the TOR

Introduction to the Preparatory Commission, Global Communications Infrastructure, International Data Centre, International Monitoring System, and connected networks

Section 2 – Statement of Work

Tasks, deliverables, documentation, activities, reports and schedules to be met

Section 3 – Specification of Requirements

Mandatory and desirable functional, architectural, technical and operational specifications

Section 4 – Service Level Agreement

Key Performance Indicators and metrics; penalty provisions for the project implementation (migration) and post-implementation (operation)

Section 5 – Benchmarking

Optional independent 3rd party benchmark of GCI pricing and service levels from the 3rd year on

Attachment I – Technical Description of GCI II

Attachment II – Site Profile Table (SPT)

Attachment III – Formats and Protocols for Continuous Data CD 1.1

Attachment IV – Formats and Protocols for Messages

IDC/OPS Page 3

GCI III TOR Outline

IDC/OPS Page 4

TOR Section 2 - Documentation

M 2.2.1

The Contractor shall provide all required documentation at

least 15 days prior to the associated meeting or review

unless otherwise agreed with the Commission.

M 2.2.2 The Contractor shall provide the minutes of meetings on the

next working day at the latest.

M 2.2.3 The Contractor shall provide all documentation in accordance

with Table 2.1.

Table 2.1. Document Life Cycle and Delivery

Project Management

Design

PIVV

Provisioning

Implementation

Verification

Validation

Operated by organizations that are independent of PTS/CTBTO (“station operator”), with or without formal contractual arrangement

Network-wise, all stations are TCP/IP devices connected to the GCI

Operational Procedures

Periodic reporting

Monthly – Quarterly

Quality Management

Security Documentation -

IDC/OPS Page 5

TOR Section 2 - Documentation

Overall package: 24 documents (Review/Approval)

IDC/OPS Page 6

TOR Section 2 - Documentation

IDC/OPS Page 7

TOR Section 2 – Project and Service Schedules

M 2.3.1

The Contractor shall perform all tasks and provide all

deliverables and documentation in accordance with the

schedules in Figure 2.1 and Figure 2.2.

M 2.3.2

The Contractor shall record the start, completion and approval

dates for each task, deliverable and document. These records

shall be available to the Commission upon request.

The principal implementation phases are:

Initial project planning phase; (~8 weeks)

Design and technical review phase; (~12 weeks)

Provisioning, integration, validation and verification phase; (~20 weeks)

Implementation and acceptance phase. (8 months)

IDC/OPS Page 8

TOR Section 2 – Reports –Service Operation

Tasks, Deliverables and

Meetings Frequency Action/Venue

Operational Status Review Twice a week Teleconference

Operational Escalation

Meetings As required Teleconference

Service Status Review Twice a month Teleconference

Periodic Performance

Review Monthly

8 teleconferences (video)

4 on-site at the Commission premises

Planning and Approval

Meeting Quarterly Commission premises

Mid-Year Review Yearly (July) Commission premises

Annual Review Yearly

(January) Commission premises

IDC/OPS Page 9

TOR Section 2 - Training

Tasks and Deliverables

Not Later

Than

[months]

Action/Venue

Satellite and Terrestrial

Technology Seminar

(specific to the

solutions employed

for the GCI)

EDC + 4

EDC + 8 Commission premises (5 days)

GCI Overview and

Stakeholders

Workshop

ICD + 6

ICD + 36

ICD + 72

Commission premises (2 days)

Station Maintenance

Training (on-site) -

1 day of training at each site after

commissioning and 2 hours of refresher

training at each maintenance visit

Training Reports

1 week after

course

completion

Approval

International Monitoring System (IMS) Facilities

IMS stations & Radionuclide Laboratories (total number: 337)

Send monitoring data continuously or periodically to the IDC

Mix of: staffed or unstaffed/unmanned; normal office environment or remote & harsh environment; easy to difficult/restricted access

Operated by organizations that are independent of PTS/CTBTO (“station operator”), with or without formal contractual arrangement

Network-wise, all stations are TCP/IP devices connected to the GCI

National Data Centre (NDC)

Receives data and IDC products Traffic flow is predominantly from IDC to NDC

Independent organization, separate personnel from the PTS/CTBTO

Considered to be an untrusted node from the network security standpoint

PTS/CTBTO provides the GCI link at no cost to the NDC

CTBTO prefers Internet VPN connection, if possible

IDC/OPS Page 10

TOR Section 2 - Activities

Thank you!

IDC/OPS Page 11

International Monitoring System Overview

Global Communications Infrastructure Overview

Global Communications

Infrastructure

International

Data Centre

International

Monitoring System

Geostationary

Satellites

VSAT: 220 links commissioned (32 links to be commissioned)

Terrestrial: 8 links (including 2xDSL)

VPN: 37 links commissioned (8 links to be commissioned)

• Site Surveys

• Civil Works

• Site Configuration and Network Planning

• Logistics Assistance and Arrangements for GCI Infrastructure

• VSAT Commissioning

GCI Site Commissioning Activities

.

• GCI VSAT/VPN Installations

• GCI Configuration Updates

• Preventive and Corrective Maintenance for GCI Link/s

• Spare Parts and Replacement for GCI Infrastructure

• GCI Infrastructure & Power Improvements

• GCI Link Redundancy & Availability Improvement

• Site Relocation Assistance

Key GCI Support Activities

Current Components of GCI at the Stations

VSAT Antenna

Antenna Mount

Rx Tx

Block

UpConverter

(BUC)

Low Noise Block

DownConverter

(LNB)

DCPM

DC Site Power

UPS

AC Site Power

24V DC

5V DC

CTBTO Devices

VSAT Antenna

Antenna Mount

Rx Tx

Block

UpConverter

(BUC)

Low Noise Block

DownConverter

(LNB)

iDirect Modem

Type-2

Installation Type-4

Installation

Internet Type-3B

Installation

BGAN System

Type-1

Installation

Type-3A

Installation

Type 1

+

Type 2

iDirect Modem

IPSec

VPN

Type-5

Installation MPLS

Cisco Router

Short-term

solution

Considerations for

various site conditions

• High Wind Antenna

• Radome

• Anti-Ice equipment

• IF Filter

• RF Filter

• Voltage Stabilizer

• UPS

GCI II Satellite Locations and Bands

Independent Sub-Networks (ISNs)

Station Groups

Committed Information Rate for the GCI

Transmit Bandwidths in Site Profile Table

Committed Information Rate for the GCI

Receive Bandwidths in Site Profile Table

On-Site Inspection (OSI)

• On-site inspections are conducted to verify States Parties’ compliance with the Comprehensive

Nuclear-Test-Ban Treaty (CTBT).

• An on-site inspection is launched to establish whether or not a nuclear explosion has been carried

out.

• If an event detected by the IMS (or by other means) raises concerns about violation of the basic

obligations of the CTBT, an OSI may be conducted to clarify whether a nuclear explosion has

taken place.

• Inspection could take place when the Treaty entry into force.

• An inspection area of up to 1000 square kilometres would be searched by a team of inspectors.

• Initial period of up to 25 days for the various non-intrusive detection techniques.

• Further, for a continuation period of up to 60 days, for more intrusive measurements.

GCI implementation for OSI

• GCI for On-site inspection must be deployed within 6 days when required.

• Sufficient bandwidth must be allocated and provisioned by the GCI Contractor for the collected

data to transport to IDC throughout the OSI exercise period.

• The scope of the exercise can vary from Small, Medium, to Large depends on the mandate

• On-site inspection may take place anywhere around the world.

• Flyaway kit with detailed standard operating procedures and instructions

• Deploy transportable and easy to maintain equipment (e.g. GATR, BGAN, etc.)

On-Site Inspection: IFE14

GCI Maintenance Pictures: PS26

(Torodi, Niger)

GCI Maintenance Pictures: AS002

(Ushuaia, Argentina)

GCI Maintenance Pictures: AS055

(Chichijima/Ogasawara, Japan)

GCI Maintenance Pictures: HA03

(Juan Fernandez Island, Chile)

GCI Maintenance Pictures: HA08

(Diego Garcia)

GCI Maintenance Pictures: IS51

(Bermuda Island)

GCI Maintenance Pictures: RN33

(Schauinsland/Freiburg, Germany)

GCI Maintenance Pictures: RN37

(Okinawa, Japan)

GCI Maintenance Pictures: RN39

(Kiritimati, Kiribati)

GCI Maintenance Pictures: Tristan Da Cunha

GCI III Bidders Conference

TOR Section 3: GCI III Engineering and Design

Presented by:

Efren Abaya, Head, GCI&NO Unit Operations Section, IDC Division

GCI III

Bidders Conference

• To present on overview of portions of Section 3 specifying engineering and

design of GCI III

• Background

The technical proposal is expected to present a clear understanding of the GCI III requirements and to describe in detail the proposed system design, migration plans in the first 1-1/2 years, and service management for the 10-year duration of the operations phase

IDC/OPS Page 2

Purpose

RFP Checklist

Draft level documents included in the Technical Proposal:

(1) Program Management Plan (2) Quality Assurance Plan (3) Project Implementation Plan

Terrestrial Core Network Infrastructure Teleport Infrastructure Generic Site Provisioning and Activation Site Provisioning and Activation (site-by-site)

(4) Risk Management Plan (5) Communication Plan (6) High Level Design Document (7) Training Plan (8) Security Plan (See ToR Sections 3.14.2 & 3.14.3)

IDC/OPS Page 3

Instructions to Invitees, Appendix 6

Chapter 1 – Introduction

Scope and structure of the TOR

Introduction to the Preparatory Commission, Global Communications Infrastructure, International Data Centre, International Monitoring System, and connected networks

Chapter 2 – Statement of Work

Tasks, deliverables, documentation, activities, reports and schedules to be met

Chapter 3 – Specification of Requirements

Mandatory and desirable functional, architectural, technical and operational specifications

Chapter 4 – Service Level Agreement

Key Performance Indicators and metrics; penalty provisions for the project implementation (migration) and post-implementation (operation)

Chapter 5 – Benchmarking

Optional independent 3rd party benchmark of GCI pricing and service levels from the 3rd year on

Attachment I – Technical Description of GCI II

Attachment II – Site Profile Table (SPT)

Attachment III – Formats and Protocols for Continuous Data CD 1.1

Attachment IV – Formats and Protocols for Messages

IDC/OPS Page 4

GCI III TOR Outline

GCI connections to remote sites (IMS facilities, NDCs, etc.) (Section 3.6)

VSAT

Terrestrial dedicated circuit(s)

Internet VPN connections

Transportable station (Section 3.6.9)

Complete list of 305 remote sites is in Attachment 2 (Site Profile Table or

SPT)

Instructions to Invitees (ITI) section 4(g): TOR implies that sites will be served

by satellite connections. The Invitees are however free to propose terrestrial

connections instead, if this should prove technically desirable and cost effective

Core network specifications:

Terrestrial core network infrastructure (Section 3.4)

Teleport infrastructure (Section 3.5)

GCI III will co-exist with GCI II for the migration period. Transfer of remote

sites must be automatic and transparent

IDC/OPS Page 5

TOR Chapter 3 – Specification of Requirements

ITI section 4(e): HW, SW and firmware shall, to the maximum extent practical,

be:

• Recent model/release

• Supported for at least 3 to 5 years

• Commercially available, off-the-shelf (COTS)

All these to be described in the High Level Design bid document (Section M

3.3.1.3)

IDC/OPS Page 6

TOR Chapter 3 – Specification of Requirements

Most important is that end-to-end service must be engineered and designed to

meet the SLA service availability requirements in TOR Section 4.2

• Satellite remote sites: 99.5% within a one year period

• Terrestrial remote sites: 99.95% within a one year period

Service availability must be maintained during the migration of every remote

sites, and during the service operation

• M 3.9.4.12 - SLA penalties shall apply for any outages exceeding a cumulative 8 hours of downtime for a remote site during its transfer from GCI II to GCI III

IDC/OPS Page 7

TOR Chapter 3 – End-to-end service

Remote site redundancy, without single point of failure (M 3.6.3.1)

• Both VSAT remote sites and terrestrial remote sites

Backup medium (Internet VPN, VSAT, BGAN, terrestrial lines, etc.) with

automatic failover

• DC conversion equipment should be redundant (M 3.6.4.23)

Cold spares to be kept onsite in the custody of the GCI Point of Contact

Mix of AC and DC remote sites; mix of different AC and DC service voltages

For satellite remote sites, GCI III will be built on the existing civil works

infrastructure or even existing antenna mount; possible to re-use the VSAT

antenna if it is fit for purpose

IDC/OPS Page 8

TOR Chapter 3 – Remote sites (Sec. 3.6)

• The entire supporting network infrastructure used to transport data between

the various teleports and the IDC.

Shall support the transport of IPV4 and IPV6 (Sec. 3.4.1)

• Without restrictions on the kind of user traffic transported (TCP or IP protocols, IP addresses, pings, network monitoring

Redundant network elements and circuits, without single point of failure, with

automatic failover (Sec. 3.4.4)

• In addition, Internet VPN backup

• Geographic diversity of prime and backup circuits

Configured cold spares to be kept onsite

Support contracts for HW and SW

Support Quality of Service (QOS)

Fully redundant connection at the IDC, with routing protocol

IDC/OPS Page 9

TOR Chapter 3 – Terrestrial Core Network

Infrastructure (Section 3.4)

Redundant teleport elements and subsystems, without single point of failure

• Backup connectivity to the Internet

Cold spares to be kept onsite

Spare antenna onsite or at a backup teleport

Scalable and can easily accommodate future growth

Physical and logical security measures (M 3.5.4.3)

• Perimeter fence, gates and barriers • Access control • Video surveillance • Alarm systems

IDC/OPS Page 10

TOR Chapter 3 – Teleport Infrastructure

(Section 3.5)

Capacity, for both current needs and for uture growth

Exclusively non-pre-emptible and restorable satellite capacity

Easy to license in the various countries where satellite remote sites are deployed,

or re-use existing licenses if possible

IDC/OPS Page 11

TOR Chapter 3 – Space Segment (Section 3.5.5)

Network Management System (Section 3.7.2)

Monitors all network elements of the GCI from the IDC end to the remote site end

Monitors and measures compliance with the SLA (See M 4.2.1.11)

Commission staff shall have (read-only) access to the Contractor’s NMS

Trouble Ticketing System

Commission staff shall have (read-only) access to the Contractor’s ticketing system

Configuration Management System (M 3.10.2.1)

Online, interactive logistics tracking system (M 3.6.2.12)

Security requirements (Section 3.14), particularly M 3.14.16 & .17

Follow industry best practice

Mandatory: Stateful firewall, IPSec encryption, logs, DOS/DDOS mitigation

Desirable: two-factor authentication, jamming resistant coding, IDS/IPS

IDC/OPS Page 12

TOR Chapter 3 – Specification of Requirements

M 3.7.2.5.1 - The NMS of the Contractor shall have the ability to automatically

open trouble tickets in the trouble ticketing system of the Contractor.

M 3.7.2.1 – The Commission shall have access to the (Contractor’s) NMS system

at all times.

M 3.7.2.5.3 - The Commission shall have access to the trouble ticketing system of

the Contractor. The access shall be guaranteed for at least 5 concurrent users of

the Commission.

M 3.7.2.5.4 - The trouble ticketing system of the Contractor shall integrate with

the (currently JIRA) based internal trouble ticketing system of the Commission.

Desirable integration scenarios:

• Commission’s JIRA trouble ticket system can read & display tickets held in

the Contractor’s system

• Commission’s JIRA system may be the user interface to update tickets in the

Contractor’s system (if Commission is given write access)

IDC/OPS Page 13

Contractor’s NMS & Trouble Ticket System

M 3.7.2.4.1 – The Commission shall reserve the right to operate its own NMS,

which shall be provided with all access necessary to monitor the performance and

status of data from the GCI.

• The GCI shall permit access to GCI equipment for the Commission’s

monitoring or provide traps, NetFlows, etc. as requested.

• This is independent of the Contractor’s own monitoring system, to which the

Commission will also have access

IDC/OPS Page 14

PTS/CTBTO NMS

M 3.6.4.8 – additional equipment as follows for the purpose of minimizing

outages and reducing manual intervention

De-icing equipment;

Radomes;

High wind antennas;

Corrosion resistant mounts and antennas;

Animal deterrent kits and measures;

Lightning protection equipment;

Armoured and shielded cables;

Equipment enclosures;

Other ruggedized equipment.

Read the Site Profile Table (Attachment 2)

IDC/OPS Page 15

Equipment for harsh environments

M 3.6.4.25 (DC site)

M 3.6.4.29 (VSAT and terrestrial site)

“As part of the bid the Contractor shall quantify the expected average and

maximum power consumption for the GCI equipment at a … remote site.”

• At some remote sites, the electrical power supply is very limited. The

Commission wishes to evaluate the power drawn by the proposed equipment.

• Examples of power sources

• Solar cells

• Diesel generator

• Batteries to cover days when commercial AC power is out

IDC/OPS Page 16

Power consumption

M 3.6.6.10

The Commission shall provide the Contractor with the IP addressing plan. The

Contractor shall comply with and implement the IP addressing plan.

• Commission wishes to retain the IP addresses used by or assigned to IMS station or NDC equipment or any other user equipment.

• GCI III IP addresses within the network cannot conflict with IP addresses used within GCI II

• Static Network Address Translation (NAT) used in a few remote sites

M 3.6.6.13

The Commission shall provide the Contractor with the naming convention for the

GCI III network. The Contractor shall comply with the naming convention as

provided by the Commission.

• Names used in the NMS and trouble ticketing system, and in correspondence and reports, must match the names in the Site Profile Table

IDC/OPS Page 17

IP address and routing; Naming

Section 3.6.7 (Capacity, Performance and Quality of Service)

• GCI III shall classify and prioritize different kinds of traffic

• For example, IDC has operational and test receivers. IMS data sent to an operational receiver has priority over data to a test receiver.

• For example, IMS data going to the IDC has priority over software updates or downloads.

• Queuing and prioritization only significant when capacity is oversubscribed

• SPT specifies sufficient capacity for every remote site

• Commission may use some relatively high bandwidth applications, for

example, VOIP

IDC/OPS Page 18

Quality of Service (QOS) & capacity management

Thank you!

IDC/OPS Page 19

GCI III Bidders Conference

Chapter 4: SLA

Presented by:

Fernando Araujo, Chief Operations Section, IDC Division

GCI III

Bidders Conference

IDC/OPS Page 2

Distribution of IMS Facilities (CTBTO website)

IDC/OPS Page 3

Distribution of IMS Facilities: Different challenges

• To introduce main point on TOR Chapter 4

IDC/OPS Page 4

Purpose

Section 1 – Introduction

Scope and structure of the TOR

Introduction to the Preparatory Commission, Global Communications Infrastructure, International Data Centre, International Monitoring System, and connected networks

Section 2 – Statement of Work

Tasks, deliverables, documentation, activities, reports and schedules to be met

Section 3 – Specification of Requirements

Mandatory and desirable functional, architectural, technical and operational specifications

Section 4 – Service Level Agreement

Key Performance Indicators and metrics; penalty provisions for the project implementation (migration) and post-implementation (operation)

Section 5 – Benchmarking

Optional independent 3rd party benchmark of GCI pricing and service levels from the 3rd year on

Attachment I – Technical Description of GCI II

Attachment II – Site Profile Table (SPT)

Attachment III – Formats and Protocols for Continuous Data CD 1.1

Attachment IV – Formats and Protocols for Messages

IDC/OPS Page 5

GCI III TOR Outline

Service availability is the principal quantitative measure of network and

service performance.

Tasks that require specific actions to be taken by the Contractor include the

following:

• Identification and resolution of critical, major, minor and redundancy failures;

• Computation of SLA penalties;

• Replacement of spare equipment;

• Escalation of incidents in accordance with established procedures;

• Planned maintenance;

• Resolution of non-conformance issues;

• Notification of planned service outages;

• Delivery of network monitoring data;

• Response to change requests from the Commission;

• Response to requests for information from the Commission.

IDC/OPS Page 6

TOR Chapter 4 - KPIs

• M 4.2.1 The Contractor shall comply with all of the SLA metrics

• M 4.2.1.4 The Contractor shall guarantee that the service availability for all satellite

remote sites is equal to or greater than 99.5%.

• M 4.2.1.5 The Contractor shall guarantee that the service availability for terrestrial

remote sites and all other connections to the terrestrial core network infrastructure is

equal to or greater than 99.95%.

IDC/OPS Page 7

TOR Chapter 4 – Service Availability

IDC/OPS Page 8

TOR Chapter 4 – Table 4.1

IDC/OPS Page 9

TOR Chapter 4 – Exemptions to the SLA

IDC/OPS Page 10

TOR Chapter 4 – Major Failures

IDC/OPS Page 11

TOR Chapter 4 – Critical Failures

IDC/OPS Page 12

TOR Chapter 4 – Network Monitoring

IDC/OPS Page 13

Distribution of GCI remote sites

Note also SLA requirements for:

• Replacing spares within 15 days (M 4.2.3.5.1)

• Using alternative technology as a remedial action

• Definitions of cumulative service outage, continuous service outage and

regional service outage

IDC/OPS Page 14

Other SLA requirements

Thank you!

IDC/OPS Page 15