10
GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting December 18, 2013

GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Embed Size (px)

DESCRIPTION

GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting December 18, 2013. Indiana Design Manual. IDM 104-1.03 (3) Utility Coordinator - PowerPoint PPT Presentation

Citation preview

Page 1: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

GANTT CHARTS & SCHEDULES

Chris Hammond, P.E.Transportation Department Manager, United

Consulting

December 18, 2013

Page 2: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Indiana Design Manual IDM 104-1.03 (3) Utility Coordinator

#58. Prepare a Gantt chart for all utility relocation work that reflects the start time, finish time and duration for each independent section of the utility facility relocation work. Ensure the chart has information regarding the geographical direction (east to west) the utilities are operating.

Page 3: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

When should we do Schedules? Schedules now need completed at

3 points in time: Preliminary Stage:At/During PFC Meeting, to estimate how long

Relocations will take….could affect Letting Prior to Work Plan Approved StageTo be sure there is proper summation of Utilities’

Relocations….could affect Contractor Start Date Construction StageBased on actual progress made by each Relocating

Utility….could lead to Contractor “delay” claim

Page 4: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Types of Schedules INDOT now requires a visual

Schedule, such as “Gantt Project” http://www.ganttproject.biz/ Free, public domain software

You may use other programs: MS Project Schedule Excel spreadsheet Others acceptable (key is visual) Keep them as simple and practical as

possible

Page 5: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Gantt Charts Remember these from College?

Various types of Schedules Bar Charts (low complexity) CPM (high complexity) Gantt Charts (mid-level complexity)

Page 6: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Gantt Charts Advantages

Multiple work elements/tasks Tracks “Start” and “Finish” Dates Shows Durations Obvious interconnection/Relationships Visual easy to understand/interpret

Page 7: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Utility Schedule So why is INDOT requiring it?

To determine IF construction can be: Done without conflicts with Utilities Done simultaneous with Relocations

To avoid overlaps: Between Utilities’ Schedules vs. Contractor’s Between various Utilities’ Relocation Schedules

To help: Utilities be aware and coordinate amongst Identify “under-builds” on Aerial Electric lines Facilitate preceding activities, even Pre-

construction (acquire R/W, stake R/W, clear Trees, etc.)

Page 8: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Utility Schedule So what inputs are needed?

Preconstruction schedules of each Utility Relocation schedules of each Utility R/W Clear and R/W Staked Dates Direction each Utility plans to proceed Target Date Contractor wants Utilities

moved Engineer’s MOT Schedule Engineer’s Phasing/Sequencing of CX Contractor’s overall Scehdule

Page 9: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Example Gantt Chart

Page 10: GANTT CHARTS & SCHEDULES Chris Hammond, P.E. Transportation Department Manager, United Consulting

Example Conflict from Gantt Chart