Upload
nguyentruong
View
213
Download
0
Embed Size (px)
Citation preview
8/20/2019 G - Engineering Design
1/111
Engineering Safety
G - Engineering Controls
Layers of Safety
PPE
EMERGENCY RESPONSE
PHYSICAL
SAFEGUARDS
OPERATING PRACTICES
CONTROL STRATEGY
ENGINEERING
PRACTICES
TECHNOLOGYOP CONDITIONS
Stages of safety
Research Phase Engineering Phase Operating Phase
Conception Approval Startup
E f f e c t i v e n e s s i n R i s k
R e d u c t i o n
Inherent
SafetyEngineered
SafetyProcedural
Safety
Appraise Select Define Execute Operate
~ 4 years 25+ years
8/20/2019 G - Engineering Design
2/112
• Intensification – Less inventory• Substitution – Lower hazard materials
• Attenuation – Reduce operating severity
• Simplification – Simplify design
Inherently safer systems are less likely toincur serious process incidents.
Inherent Safety Principles
Typical 30-year old platform design
Single platform
Some risers beneathaccommodation module
No subsea check or block valveson import / export pipelines
Limited fire and blast proofing
Wind-walls
All piping in carbon steel
Large hydrocarbon inventories.
8/20/2019 G - Engineering Design
3/113
Inherently Safer Design PhilosophyHAZARD ELIMINATION is better than
PREVENTION is better than
CONTROL is better than
MITIGATION is better than
EMERGENCY RESPONSE
AND
PASSIVE controls are more reliable than
ACTIVE controls are more reliable than
OPERATIONAL or PROCEDURAL controls.
Inherently safer design: Tangguh
No hydrocarbon
processing to reduce leaks
and inventories
Open layout and grateddecks to increase gas
dispersion
No helicoptersphi losophy to
minimise hazards
No platform power
generation to avoid
hazardous storage and
operations
NUI with no overnight
accommodation to avoidpersonnel exposure
CRA piping to eliminate
corrosion
Topsides rated for
WHSP to simplify andavoid overpressure
Export riser locatedwithin structure
Corrosion resistant well flowlines
8/20/2019 G - Engineering Design
4/114
Which is inherently safer?
Stainless steel wet gas line
Carbon steeldry gas line
• Balance of process / maintenance, ergonomics andsafety vs. economics.
• Process incidents with widespread effects willdictate maximum spacing.
• Industry spacing guidelines are a bare minimum.
• Industry spacing is generally based on firescenarios.
• Separate large inventories from potential ignitionsources.
Layout and Spacing
Layout and Spacing
Property Line
Maintenance
&
Warehouse
TankageBlock
Flare
N
S
W E
Prevailing Wind
Mid Tier
Pelletizing
And
Packaging
Lower Tier
Unimproved Land
Upper Tier
Main Road
Cooling
Tower
Ethylene
Low Pressure
Polyethylene
Ethylene
Glycol
Offices
Offices
Parking
Control
Room
Gate Gate
Process
Block
Offices
Office
Block
8/20/2019 G - Engineering Design
5/115
Layout and Spacing
Systematic evaluation of building occupant risk as aresult of various external hazards.
Building poses risk to occupants because of:
1. People congregated near hazards
2. Structural integrity
3. Internal hazards
Facility Siting Studies
8/20/2019 G - Engineering Design
6/116
• Examine strength of buildings – How blastresistant?
• Examine other physical hazards resulting fromdamage to buildings. i.e. Glass, toxic vapors intoducting, office furniture.
• Is a plan in place to evacuate and relocatepersonnel in an emergency?
• Is the facility suitable for shelter-in-place?
Facility Siting Studies
Major Concerns?
• Cover glass windows with protective film.
• Remove windows.
• Remove light temporary buildings.
• Relocate personnel.
• Apply structural modifications.
-------------------------------------------------------
• Demolish / replace with more robust structure.
• Erect new blast resistant structure.
Strategy for existing buildings
8/20/2019 G - Engineering Design
7/117
• Grading should slope away from fuel sources orcritical equipment.
• Sewer system should be sized to handle– storm runoff, or– firewater, and– maximum release from major equipment
failure.
• Multiple catch basins reduce the travel time /distance and reduce the surface area for apotential fire.
Drainage
• Need to segregate incompatible materials.
• Sewer design must recognize plugging potential.provide means of clearing.
• Sewers must not permit the passage of flammablevapor (use traps).
• Integrated approach to layout, grading and sewersis required.
• May impact relief system sizing.
Drainage
System Isolation
• An essential safeguard for any hazardousprocess
• Permits safe inspection and maintenance
• Prevents the interaction of hazardous and nonhazardous materials
• Isolates energy sources from hazardousmaterials
• Reduces the size of a hazardous release –isolatable inventories
8/20/2019 G - Engineering Design
8/118
Process Plant and Equipment
• Commit to quality engineering standards
• Material selection to match conditions
• Design to full range of service conditions
• Quality control during fabrication andconstruction
• Operate within safe operating envelope• Routine inspection and maintenance
Engineering Design
SAFE – RELIABLE - SUSTAINABLE
Krechba
Case History – CH13
8/20/2019 G - Engineering Design
9/119
Case History 13-Krechba
2004 – BP Krecha (In-Salah) Gas Gathering Center,Algeria• Two nearly identical gas processing trains that treat
gas from remote production centers.• Facility provides glycol dehydration and CO2 removal
to sales gas spec for export via pipeline to Hassi R’Mel.
• Plant was in final stages of commissioning.• 6 in (150 mm) line taking gas off the top of the glycol
contactor to the flare header failed catastrophically .• Wind was blowing away from the plant and gas did not
ignite.
What Happened
• Train 1 had been flowing gas for a couple ofweeks, Train 2 was brought on stream the day ofthe incident.
• Within hours of start-up, problems with the CO2plant resulted in gas being diverted to flare.
• During Train 1 start-up, the flare system seemedexcessively noisy.
• As Train 2 started to send gas to flare thesituation became worse.
• Within hours the 6 in (150 mm) line taking gasoff the top of the glycol contactor to the flareheader failed catastrophically at the header.
Damage Details
8/20/2019 G - Engineering Design
10/1110
Why It Happened
• The 6 in (150 mm) line connecting the glycolcontactor to the flare header was too small (itshould have been 12 in (300 mm)).
• The under-design caused sonic velocities resultingin excessive vibration and very rapid fatiguefailure.
• Design failed to appreciate the importance of theblow down system to the safety of operations.
• No follow through on PHSSER/HAZOP findings.• Commissioning team did not adequately respond to
excessive noise and vibration in the blow-downsystem.
Major Lessons Learned
• The basis of design and pipingcalculations for the system mustconsider all operating modes.
• A sound design QA/QCprocedure must be available andfully utilized.
• Project HAZOP reviews mustinclude all systems, and allHAZOP recommendations mustbe closed out beforecommissioning.
E n g i n e e r i n g S y s t e m s T r a i n i n g / C o m p e t e n c y
P r e - s t a r t u p S a f e t y R e v i e w s
8/20/2019 G - Engineering Design
11/1111
• Determined by inventory requirements and holdupconsiderations.
• Limited by transportation systems.
• Large size equipment is more prone to failure fromlocalized stresses.
• Difficult to establish process control within allparts of large complex systems.
• Difficult to establish equilibrium in large vesselsand reactors.
Equipment Sizing