38
GNANAMANI COLLEGE OF ENGINEERING DEPARTMENT OF CIVIL ENGINEERING PLANNING, ANALYSIS & DESIGNING OF BUS STAND PROJECT MEMBERS: GIRIPRASAD.K JAYAKUMAR.M PANDIYARAJAN.P SAYEDNISHAN BASHA PROJECT GUIDE: Mr. VIGNESH.R

FULL.docx

  • Upload
    vidhya

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

GNANAMANI COLLEGE OF ENGINEERINGDEPARTMENT OF CIVIL ENGINEERING

PLANNING, ANALYSIS & DESIGNING OF BUS STAND

PROJECT MEMBERS:GIRIPRASAD.KJAYAKUMAR.MPANDIYARAJAN.PSAYEDNISHAN BASHAPROJECT GUIDE:Mr. VIGNESH.R

Abstract:

Bus-stand is an essential component of urban transport facilities which defines the beginning or end of the line for the transportation system. It normally requires a size-able land in a strategic part of an urban area. A well planned or managed bus-terminal will act as catalyst to the social and economic development of the surrounding areas. On the other hand, bus-terminal is an asset to an area as it may act as catalyst to economic and social development of the surrounding areas. However, poorly planned and sited terminal for buses may generate traffic problems as well as deteriorating the quality of life of the affected surroundings. This project focuses mainly the structural design of whole bus terminal. As with engineering and operational aspects of terminal facilities the focus would be on the design to fulfill traffic capacity requirement and operational efficiency to operators and passengers. The proposed far side terminating bas terminal model which located outside city centre may have added advantages such as reducing unnecessary congestion and improving the environment.Objectives: This project have following main objectives:Conducting research on the existing bus terminal of a city and proposing a new model of busterminal according to findings

1. Architectural planning of whole bus-terminal2. Planning and design of complete bus-terminal3. Design of a steel garage for bus repairing house and bus storage4. Design of pavement5. Material estimation of the whole project6. Car parking managementDescription of the Project:

At first i conducted a survey in poorly planned and constructed Bus-terminal which is located in one of the major city in Bangladesh. After surveying i found the following conditions1. The ticket counters are situated here and there and sometimes it creates a irritating situation to search expected ticket counter among the passengers.2. In terms of waiting area, mostly it is strategic because the plan at bus-terminal is properly well managed and not suitable for the users and customers.3. Information on trips and services are well managed.4. Public facilities such as toilets, telephone are inadequate.5. Lack of facilities for staff such as office and control room, storage of personal belongings, rest room, toilets and so on.6. Lacking of proper as well as modern repairing house and bus storage garage.I designed a complete bus-terminal including a terminal building design, a steel garage design by using roof truss system and the rigid pavement design of terminal area and finally gave some feedback to improve car parking management.SLAB DESIGNSLAB1:Side ratio:Ly/Lx=11.19/5.375 =2.08>2Hence it is one way slab.Effective depth:Span/Basic value=5.375/25 =215mm.

d =215+20 =235mm.Effective span:Effective span=d + clear cover =0.215+5.375 =5.59m.Load calculation:Self weight of slab=0.235*1*25 =5.875KN/m2Floor finish =1.5KN/m2Live load =4KN/m2Total load =11.375KN/m2Design load =11.375*1.5 =18KN/m2.Bending moment:Mu=WL2/8 =18*5.592/8 =70.3KN.m.Maximum shear =WL/8 =18*5.59/8 =12.57KNm.Depth required:Mu=Q*b*d2 d=dreq=160mm.dprovide=drequiredHence it is safe.Main reinforcement: Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]70.3*106=0.87*415*Ast*215[1-415*Ast/20*1000*215] Ast=1002.7mm2.Spacing:Main reinforcement=3d or 300mm =3*215 or 300 =645 or 300 =300mm.Distribution reinforcement=5d or 450mm =5*215 or 450mm =1075 or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*5.59 =0.559m.Check for shear:v=vu/b.d =12.57*103/1000*215 =0.058N/mm2.Percentage of steel=Ast*100/b.d =1002.7*100/1000*215 =0.466.From IS456:2000 pg.no:73c=0.46From IS456:2000 pg.no:72 clause 40.2.1.1K=1.12K*c=1.12*0.46 =0.51.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.

SLAB 2:Side ratio: Ly/Lx=9.69+1.50/5.03=22Drequired Hence it is safeMain reinforcement: Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]53.59*106=0.87*415*Ast*201.2[1-415*Ast/20*1000*201.2] Ast=804.37mm2.Spacing:Main reinforcement=3d or 300mm =3*201.2 or 300 =300mm Distribution reinforcement=5d or 450mm =5*201.2 or 450mm =450mm. Curtailment:Curtailment=0.1*Effective span =0.1*5.2512 =0.525m.Check for shear:v=vu/b.d =42.563*103/1000*201.2 =0.21N/mm2.Percentage of steel=Ast*100/b.d =804.37*100/1000*201.2 =0.39.From IS456:2000 pg.no:73c=0.4272From IS456:2000 pg.no:72 clause 40.2.1.1K=1.1576K*c=1.1576*0.4272 =0.49.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.SLAB3:Side ratio:Ly/Lx=11.19/10.52 =2.16>2Hence it is one way slab.Effective depth:Span/Basic value=5.26/25 =210.4mm.

d =210.4+20 =230.4mm.Effective span:Effective span=d + clear cover =0.230+5.26 =5.49m.Load calculation:Self weight of slab=0.230*1*25 =5.76KN/m2Floor finish =1.5KN/m2Live load =17KN/m2Design load =18KN/m2.Bending moment:Mu=WL2/8 =17*5.492/8 =64.05KN.m.Maximum shear =WL/8 =17*5.49/8 =46.66KNm.Depth required:Mu=Q*b*d2 d=dreq=160mm.dprovide=drequiredHence it is safe.Main reinforcement: Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]64.05*106=0.87*415*Ast*210.4[1-415*Ast/20*1000*210.4] Ast=928mm2.Spacing:Main reinforcement=3d or 300mm =3*215 or 300 =300mm.Distribution reinforcement=5d or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*5.49 =0.549m.Check for shear:v=vu/b.d =46.66*103/1000*210.4 =0.22N/mm2.Percentage of steel=Ast*100/b.d =928*100/1000*210.4 =0.44.From IS456:2000 pg.no:73c=0.45From IS456:2000 pg.no:72 clause 40.2.1.1K=1.14K*c=1.14*0.46 =0.51.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.SLAB4:Side ratio:Ly/Lx=11.19/7.43 =1.50drequiredHence it is safe.Main reinforcement:Longer span Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]107.66*106=0.87*415*Ast*300[1-415*Ast/20*1000*300] Ast=1074mm2Shorter span:Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]55.41*106=0.87*415*Ast*300[1-415*Ast/20*1000*300] Ast=531mm2.Spacing:Main reinforcement=3d or 300mm =300mm.Distribution reinforcement=5d or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*7.43 =0.743m.Check for shear:v=vu/b.d =106.54*103/1000*300 =0.35N/mm2.Percentage of steel=Ast*100/b.d =531*100/1000*300 =0.177From IS456:2000 pg.no:73c=0.30From IS456:2000 pg.no:72 clause 40.2.1.1K=1.10K*c=1.1*0.30 =0.30.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.SLAB5:Side ratio:Ly/Lx=4.5/3.345 =1.345drequiredHence it is safe.Main reinforcement:Longer span Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]11.42*106=0.87*415*Ast*140[1-415*Ast/20*1000*140] Ast=234mm2Shorter span:Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]6.31*106=0.87*415*Ast*140[1-415*Ast/20*1000*140] Ast=127mm2.Spacing:Main reinforcement=3d or 300mm =300mm.Distribution reinforcement=5d or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*3.345 =0.3345m.Check for shear:v=vu/b.d =21.95*103/1000*300 =0.156N/mm2.Percentage of steel=Ast*100/b.d =127*100/1000*140 =0.09From IS456:2000 pg.no:73c=0.28From IS456:2000 pg.no:72 clause 40.2.1.1K=1.3K*c=1.3*0.28 =0.117.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.SLAB6:Side ratio:Ly/Lx=4.5/3.23 =1.393drequiredHence it is safe.Main reinforcement:Longer span Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]8.59*106=0.87*415*Ast*130[1-415*Ast/20*1000*130] Ast=189mm2Shorter span:Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]4.80*106=0.87*415*Ast*130[1-415*Ast/20*1000*130] Ast=104mm2.Spacing:Main reinforcement=3d or 300mm =300mm.Distribution reinforcement=5d or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*3.23 =0.3230m.Check for shear:v=vu/b.d =21.19*103/1000*130 =0.163N/mm2.Percentage of steel=Ast*100/b.d =104*100/1000*140 =0.074From IS456:2000 pg.no:73c=0.28From IS456:2000 pg.no:72 clause 40.2.1.1K=1.30K*c=1.3*0.28 =0.117.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.SLAB7:Side ratio:Ly/Lx=9.46/9.46 =1drequiredHence it is safe.Main reinforcement:Longer span Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]72.82*106=0.87*415*Ast*380[1-415*Ast/20*1000*380] Ast=628mm2Shorter span: Mu=0.87.fy.Ast.d[1-fy.Ast/fck.b.d]72.82*106=0.87*415*Ast*380[1-415*Ast/20*1000*380] Ast=628mm2.Spacing:Main reinforcement=3d or 300mm =300mm.Distribution reinforcement=5d or 450mm =450mm.Curtailment:Curtailment=0.1*Effective span =0.1*9.46 =0.946m.Check for shear:v=vu/b.d =62.80*103/1000*380 =0.163N/mm2.Percentage of steel=Ast*100/b.d =628*100/1000*380 =0.014From IS456:2000 pg.no:73c=0.28From IS456:2000 pg.no:72 clause 40.2.1.1K=1.0K*c=1.0*0.28 =0.28.v< K*cHence it is safe.Hence for main reinforcement provide 10mm at 300mm c/c.Hence for distributive reinforcement provide 8mm at 450mm c/c.DESIGN OF COLUMN FOOTINGAssuming safe bearing capacity =200 KN/M2Axial load on footing =70 KN =105 KNAdd 10% as footing req =Total load/SBC =115X103/200x103=0.578 m2Provide 5 size of footing =1100x1100 =1200x1200 =1300x1300 =1400x1400 =1500x1500Total load on footing with its self.wtUp word soil pressure =--------------------------------------------------- Area of footing 105x103 = --------------- x1500 =105 KN/M2 1500 Factored moment Soil pressure x area x centre of area = 105x(1 0.49/2)x0.375/2 =14.86 KN.mTO FIND DEPTH (d):d =14.86 x 106 / 2.074 x 490d =120mmFinal d =120+40+40Min Asc < Asc provide

PROVISION OF LATERAL TIESGreater of the following largest dia bar =1/4 x 16 =6mm = 6 mmSay lateral ties =6 mm

PITCHLe Ast of the followingLe Ast lateral dimensions 16 x smallest dia =16 x 10 = 160mm48 x dia of laterals ties = 48 x 6 = 288mm

TO FIND ASTMu =0.87 x fy x Ast x d[1-Ast x fy/bd x fck]14.86 x 106 = 0.87 x 415 z Ast x 120[1-Ast x 415/490 x 120 x 15]Area of resisting shear force = 1x 0.11 = 0.11 mDESIGN OF COLUMNRECTANGULAR COLUMN:Column size 660*490Working load=1500KNDesign load=2250KNPu=(0.4 fckAsc)+(0.67fy Asc)Let Ag=660x490=323400mm2Asc required:Ac=Ag-AscAc=323.4x103- Asc2250x103=0.4 x 15 x (323.4 x 103-Asc) + ( 0.67 x 415 Asc)Asc=1271.82mm2Provide 6 nos 20mm dia providedAsc provided=6 x 202 x /4=1884.95 mm2% Ast=100 x Asc /Ag=0.582%Min Asc=0.8 x 1884.95=1507.96mm2Max Asc=6% of Asc=6 x 1884.95=11309.7mm2CHECK:Min Asc