From “Shelter” to New SafeConfinement

Embed Size (px)

Citation preview

  • 7/31/2019 From Shelter to New SafeConfinement

    1/16

    From Shelter to New Safe

    Confinement

    A. Gora

    Deputy General Director for PersonnelManagement

    SSE Chernobyl NPP, Ukraine

  • 7/31/2019 From Shelter to New SafeConfinement

    2/16

    ChNPPStrategicPlanningService2

    CommissioningCommissioning

    DevelopmentofestablishedChNPPcapacities:September26,1977

    Unit1

    wascommissioned

    December21,1978

    Unit2

    wascommissionedDecember3,

    1981

    Unit3

    wascommissioned

    December21,1983 Unit4

    wascommissioned

    Turbine HallSight on

    turbogenerators

    TG-1,2

  • 7/31/2019 From Shelter to New SafeConfinement

    3/16

    ChNPPStrategicPlanningService3 3

    Accident of Apr il 26, 1986Accident of Apr il 26, 1986

    Accident at Chernobyl NPPUnit 4 occurred on April,26, 1986 at 01:23:40 a.m.(Moscow time)

    It was possible to stopactive release of radioactivesubstances from destroyedreactor only in the end of

    May, 1986

  • 7/31/2019 From Shelter to New SafeConfinement

    4/16

    ChNPPStrategicPlanningService4

    Accident of Apr il 26, 1986Accident of Apr il 26, 1986

    The rate of gamma-radiation dose

    was up to 2,000 R/h

    (20 Sv/h) and

    mainly was determined by

    radiation from reactor breakdown

    itself, inside of which measurable

    values of dose rate amounted to

    50,000 R/h

    (500 Sv/h).

  • 7/31/2019 From Shelter to New SafeConfinement

    5/16

    ChNPPStrategicPlanningService5

    Creat ion of Shelt er Obj ectCreat ion of Shelt er Obj ect

    Designing of protective sarcophagus(Shelter) commenced on May 20,

    1986;

    Construction lasted 206 days andnights from June to November 1986.

  • 7/31/2019 From Shelter to New SafeConfinement

    6/16ChNPPStrategicPlanningService

    6

    New Safe Confinement Creation (NSC)New Safe Confinement Creation (NSC)

    In 2012 it is planned to start production of steelconstructions of NSC Arch.

    Milestones for NSC creation:

    Foundations construction completion

    May,

    2013.

    Main Arch construction assembly November, 2014. NSC Commissioning

    October,

    2015.

  • 7/31/2019 From Shelter to New SafeConfinement

    7/16ChNPPStrategicPlanningService

    7

    ChNPP Units shutdownChNPP Units shutdown

    Chernobyl NPP Unit 3 was finally shutdown on December 15,

    2000 at 13:17 according to the Decree of the President ofUkraine. Plant stopped power generation.

  • 7/31/2019 From Shelter to New SafeConfinement

    8/16ChNPPStrategicPlanningService

    8

    Before the accident Chernobyl NPP generated 150.2 billion kW/h .After the accident 158.6 billion kW/h.In total it was generated 308.8 billion kW/h.

    Unit 1Unit 2Unit 3ShelterObject

    1977 19961978 19911981 20001983 1986

    Chernobyl NPP site from satellite

    ChNPP Units shutdownChNPP Units shutdown

  • 7/31/2019 From Shelter to New SafeConfinement

    9/16ChNPPStrategicPlanningService

    9

    STRESS-TESTSTRESS-TEST

    In 2011 the Chernobyl NPP, the first among Ukrainian NPPs, performedthe targeted unscheduled safety assessment of ChNPP nuclear facilities

    by its own forces taking into consideration the events at Fukushima 1 NPP

    (stress-test).

    The full-scale emergency trainings including personnel actions in case ofaccident and examination of the capabilities of emergency response units

    were conducted.

    Safety Improvement Plan for ChNPP facilities was developed:

    control, collection and return system for ISF-1 leakages was created;

    conditions enabling to connect a mobile diesel generator for ISF-1

    consumers were created, tests were carried out;

    it is planned to conduct psychological training of personnel aimed at

    increasing resistance to psychological stress, development of endurance,

    self-control, mutual supportiveness and interaction;

    system of psychological selection and training of persons involved in

    managing the accidents with severe consequences is being developed

    (similar to system of operational personnel selection).

  • 7/31/2019 From Shelter to New SafeConfinement

    10/16ChNPPStrategicPlanningService

    10

    Spent Nuclear Fuel Management (SNF)Spent Nuclear Fuel Management (SNF)

    At the moment reactors of Units 1, 2 and 3 arecompletely released from nuclear fuel.

    Fuel is only in cooling pools of Units 1 and 2.

    To reduce risks during New Safe Confinementconstruction, spent nuclear fuel was transferred fromcooling pools of Unit 3 to Interim Spent Fuel StorageFacility (ISF-1).

    In order to improve nuclear safety, it was proposed totransport SNF from Units 1 and 2 to ISF-1 for storage.

    In November 2011, the State Nuclear RegulatoryInspectorate of Ukraine agreed the Decision to placeall conditioned SNF from Units 1, 2 and 3 to ISF-1.

    Works on spent nuclear fuel transportation fromcooling pools of Units 1 and 2 to ISF-1 werecommenced.

  • 7/31/2019 From Shelter to New SafeConfinement

    11/16ChNPPStrategicPlanningService

    11

    The Final State ofDecommissioning NPP can be changed

    The Final State ofDecommissioning NPP can be changed

    "Green field" status

    "Brown spot" status

    Developedindustrial site

    ChNPP is located at the territory of Exclusion

    Zone contaminated with radioactive

    substances as a result of accident in 1986.

    Thats why decommissioning of Chernobyl

    NPP up to the "green field" status is

    unreasonable.

    A brown spot is a condition of ChNPP industrial

    site when its territory and buildings can berestricted released from the regulating control.

    Reuse of ChNPP site as National operator of

    NPP units decommissioning, SNF and RAW

    management is the most desirable final state: a fast and cheap way to reach decommissioning

    objectives

    using financial and technical resources and

    qualified staff of ChNPP more effectively;

    solving problems of nuclear industry.

  • 7/31/2019 From Shelter to New SafeConfinement

    12/16

    ChNPPStrategicPlanningService12

    SSE ChNPP Emergency Preparedness

    System SSE ChNPP Emergency PreparednessSSE ChNPP Emergency Preparedness

    SystemSystem

    The Main Tasks of ChNPP Emergency

    Preparedness and Response System

    Assurance of preparedness to eliminate accidentsand emergencies at SSE Chernobyl NPP facilities; Response to accidents and emergencies at the SSEChernobyl NPP facilities;

    Implementation of measures on protecting the NPP

    personnel and environment.

  • 7/31/2019 From Shelter to New SafeConfinement

    13/16

    ChNPPStrategicPlanningService13

    SSE ChNPP Emergency Preparedness

    System SSE ChNPP Emergency PreparednessSSE ChNPP Emergency Preparedness

    SystemSystem

    Emergency organizational structures of SSE Chernobyl NPP includes:

    Emergency Manager at industrial sites of SSE Chernobyl NPP

    facilities

    (EMS);

    Coordination and Management Body

    EMS Staff Office or SSE Chernobyl

    NPP

    Commission on the Issues of Emergencies (as a synonym);

    Standing Management Body

    Emergency Preparedness and Response

    Department (EP&RD);

    SSE Chernobyl NPP

    emergency teams and units:

    Radiation control unit; Dosimetric survey unit;

    Physical protection assurance unit;

    Personnel sanitary treatment unit;

    Transport unit, etc.;

    Teams for elimination of equipmentfailures.

  • 7/31/2019 From Shelter to New SafeConfinement

    14/16

    ChNPPStrategicPlanningService14

    SSE ChNPP Emergency UnitsSSE ChNPP Emergency UnitsSSE ChNPP Emergency Units

    The Main Tasks of NPP Emergency Units are:

    Actions on preventing beyond-design-basis accidents and

    eliminating their consequences;

    Measures on personnel protection;

    Recommendations on population protection.

    A General Director is an Emergency Manager at the ChNPP

    industrial site.

  • 7/31/2019 From Shelter to New SafeConfinement

    15/16

    ChNPPStrategicPlanningService15

    SSE ChNPP Emergency UnitsSSE ChNPP Emergency UnitsSSE ChNPP Emergency Units

    The Main Functions of EMS:

    Primary and subsequent classification of an accident;

    Notification of personnel and external organizations;

    Initiation of Emergency Plan;

    Management of actions on accident containment and elimination;

    Coordination of actions of external organizations involved into

    emergency and rescue operations;

    Provision of information to a Ministry of Emergencies management,

    regulatory body, authorities and mass media;

    Decision-making on Emergency Plans ending.

    The SSE ChNPP personnel is contained in protective shelters

    having -radiation dose rate 0,5 mSv/h.

    The SSE ChNPP personnel is evacuated having -radiation dose

    rate 1 mSv/h.

  • 7/31/2019 From Shelter to New SafeConfinement

    16/16

    ChNPPStrategicPlanningService16

    Thank you for attention!