39
GE Energy Services – Power Services Installations FRAME 9FA Date : 6/21/08/2022 ERECTION PROCEDURE Rév. : 0 Page : 1/39 9FA Installation SUMMARY 1. Scope of Work 2. Design and Erection Philosophy 3. Reference Documents 4. Environmental and Safety 5. Receiving and Handling of Equipment 6. Equipment Erection Procedure 7. Appendix (List) This document, sole property of our GE Energy. It is strictly confidential. It must not be communicated, copied or reproduced without our written consent.

Frame 9FA Erection Procedure

Embed Size (px)

DESCRIPTION

Site proven erection procedure of Frame 9FA Gas Turbine.

Citation preview

Page 1: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 1/25

9FA Installation

SUMMARY

1. Scope of Work

2. Design and Erection Philosophy

3. Reference Documents

4. Environmental and Safety

5. Receiving and Handling of Equipment

6. Equipment Erection Procedure

7. Appendix (List)

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 2: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 2/25

9FA Installation

1.0 SCOPE OF WORK

The scope of work covered by this instruction describes the basic mechanical field erection procedures required for the installation of the gas turbine unit and related system equipment.

This instruction is not intended to cover the installation details for every listed summary sheet equipment and/or use of the standard and special tools for gas turbine maintenance purposes as defined by MLxxx MLs F066 and 0104. This instruction provides the installation details for the specific gas turbine system equipment only with descriptions on the use of only those special tools required for erection purposes. All other equipment erection instructions are provided within the specific system erection instruction. The descriptions and instructions on use of gas turbine maintenance tools are provided in the Operation and Maintenance manuals.

2.0 DESIGN AND ERECTION PHILOSOPHY

2.1 System Description

The MS 91FA is a single shaft heavy duty 50 Hz (3000 RPM) The gas turbine is shipped as assembled unit, the GT’s withtheir integral base structures. The load couplings, Exhaust ducts, Inlet systems, on-base piping, combustion hardware and other related components are shipped as separate MLs for assembly at site.

2.2 Erection Philosophy and Sequence

2.2.1 Erection Philosophy

The gas turbine unit will be the first equipment to be set relative to the generator unit in line with the power train centerline.

Following the setting and positioning of the gas turbine on the foundation sub sole plates/fixators the exhaust diffuser (ML706) must be installed prior to performing any of the internal alignment checks. The generator an an entire assembly is lowered over it foundation bolts to its supports. The supports can either be soleplates or fixators. Again the unit position is adjusted into line with the power train centerline. All other gas turbine and generator components such as the load coupling, combustion system hardware, on-base piping, collector house and turning gear shall now be assembled prior to final alignment.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 3: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 3/25

9FA Installation

2.2.2 Erection Sequence

The preferred sequence of erection for the gas turbine unit and related components is as follows:

1. Install sub-sole plates and fixators.2. Erect gas turbine/generator lifting fixture.3. Transport gas turbine and generator units from off loading quay to

turbine building and position under lifting frame.4. Lift and set gas turbine unit on station centerlines.5. Lift and set generator unit on station centerlines.6. Equalise and confirm loading on GT and Generator fixators.7. Remove temporary lifting frame.8. Install GT compartment Aft lower wall section.9. Assemble Exhaust Duct structural steel10. Install lower half exhaust duct.11. Install exhaust diffuser.12. Complete Turbine Drop Check.13. Complete assembly of Exhaust Duct.14. Install Inlet duct support steel.15. Install GT compartment to inlet plenum lower seal. 16. Install air inlet plenum lower half and cone.17. Install GT combustion system hardware.18. Install load coupling 19. Complete preliminary GT to Generator alignment.20. Commence installation of all GT on base piping.21. Commence installation of all Generator On base piping.22. Set Gen collector house on foundation. 23. Set turning on foundation24. Preliminary align turning gear.25. Install Gen Terminal Enclosure.26. Set all major skid on foundations.27. Complete erection of air inlet plenum, 28. Commence erection of air inlet duct and filter house.29. Continue erection of GT and Exhaust enclosure.30. Set all off base components. 31. Complete all GT on-base piping.32. Install all GT Interconnection piping.33. Complete all Gen on-base piping.34. Complete Gen off base components.35. Install all Gen interconnect piping. 36. Complete erection of GT and Gen enclosures.37. Complete erection of all major shaft line components.38. Complete assembly of all GT and Gen instrumentation.39. Complete assembly of all GT and Gen Conduit and wiring.40. Complete load coupling to gen final alignment (Lift Oil Available).41. Complete turning gear to gen final alignment.42. Final grout of sub sole plates43. Install anchors and finalize turbine and Gen gib key clearances.44. Install load coupling guardRefer to MS 9FA Basic Field Alignment Instructions ML-411 for other details regarding the final alignment conditions.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 4: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 4/25

9FA Installation

3.0 REFERENCE DOCUMENTS

The installation documentation referred to throughout this erection instruction are standard GE reference ML numbers (ML) and GE internal drawing numbers, where applicable.

The following table lists all required system drawings and related documents for the installation of the equipment and material covered within the scope of this instruction. The latest revisions of these drawings and documents shall be reviewed thoroughly prior to commencing with any of the activities described in this instruction.

The final drawing number reference will be available 2 months before GT shipment. Any of the BHEL supplied systems should be referenced to their drawing list.

ML GAS TURBINE SYSTEM DESCRIPTION GE REF REV0103 Locking Rotor for Shipping0103 Shipping Attachment Arr0103 Support, GT Shipping0301 O/L GT PKG Conn-Elec0302 Outline:Purch MTD devices0306 Outline, Mechanical Gas Turbine & Load0313 Outline, GT PKG Conn - Piping0314 Notes, GT PKG Conn Outline Piping0323 Outline, Foundation Interface Gas Turb

Package0323 Outline, Foundation Interface Gas Turb

Package0323 Outliner, Foundation Interface Access & LF/AA

Module0323 Outliner, Foundation Interface Turb Enclosure0323 Outliner, Foundation Interface Exht Diffuser0323 Outliner, Foundation Interface Inlet Plenum Arr0323 Outline, Foundation Interface Exht Barrier Wall0323 Outliner, Foundation Interface Pipe Supports0323 Gen Inst. Instruc. For fixators on Turb Gen

Equip0323 Turbine Generator FDN Interface GEK-1069570323 Turbine Generator FDN GEK-633830326 O/L Water Injection Skid BHEL0326 O/L Fuel Gas Absolute Separator Coalescing

Filter Interface0326 10 Ton, 4 Zones Lp CO2 Storage Unit BHEL0326 Outline, Pressurizing Vent Fan0326 Outline Distillate Fuel Spool Piece BHEL0326 Outline, Water Wash Skid BHEL0326 Outline, Air Processing Skid BHEL0326 O/L Water Injection Skid BHEL0330 Outline 9F Gte with 89 SS, Right Entry BHEL0330 Gas Auxiliary Monitoring Outline BHEL0330 Control Panel O/L0330 Panel Layout

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 5: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 5/25

9FA Installation

0330 Static Start Heat exchanger Installation Inst BHEL0330 Outline for LS2100/SS BHEL0330 Outline-Foundation Interface0330 Warm Back Up Syst Ex2100 Multi Bridge

LineupBHEL

0401 Turbine Connection Diagram0401 Cables Configurations0403 Generator Protection Panel-Gas Unit BHEL0406 Gas Turbine Arrangement 0407 Weights & C.G - Gas Turbine- 9FA0408 Outline WT&CG Exhaust Diffuser0408 Outline, Weight&C.G. GT Package0408 Stator Handling BHEL0408 Inlet Plenum0408 Inlet0408 Shipping Dimensions0408 Lift&C.G. Diagram Filter Mod/Acoustic Hoods0408 Lift&C.G. Diagram Filter Transition0410 Instruction, Alignment-Factory0411 Basic Field Alignment Instructions0412 Data, Temp & Heat Rad0414 Device Summary0415 DIAG, CONT DEVICE - TURB0416 DIAG,SCH PP-LUBE OIL0417 DIAG,SCHEM-CLG &SLG AIR0418 DIAG,SCHEM PP-TRIP OIL0419 DIAG, SCHEM PP CTRL AIR 0420 DIAG,SCHEM PP-COOLING WATER0421 DIAG,SCHEM PP-STRT MNS0422 DIAG,SCH PP-FUEL GAS0424 DIAG, SCHEM PP-LIQUID FUEL0425 DIAG,SCH PP ATOM AIR0426 P & ID FIRE PROTECT SYS 0432 DIAG,SCHEM PP-INLET AIR HTG0434 DIAG,SCHEM PP-HYD SUPPL0435 Cable Installation Data, Speedtrc 0436 DIAGRAM,FLOW-HEATING&VENT0438 INSTRUCTIONS, CLEANING&PAINTING0438 Instruction, Lube Oil Selection0438 Symbols, Piping0438 Cable Instl Data, Turbine Control0438 Process and Instrum Diagram (P&ID)0438 Air Venting Procedure Liquid Fuel Syst0438 Syst & Comp Cleanliness Requirements0438 Instructions, Cleaning & Painting0438 Instruction, Test Preparation-C02 Syst0438 Sealing Instructions, Cable Gland0438 Index, Customer Drawings0438 Human-Machine Interface for Speedtronic GEH-6126 Vol I

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 6: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 6/25

9FA Installation

0438 Human-Machine Interface for Speedtronic GEH-6126 Vol II0438 Speedtronic, Mark VI GEH-6421 Vol I0438 Speedtronic, Mark VI GEH-6421 Vol II0438 Ex 2100 Excitation Control GEH-66310438 Ex 2100 Excitation Control GEH-66320438 Power System Stabilizer GEH-66760438 LS 2100 Static Starter Control GEH-66780438 LS 2100 Static Starter Control GEH-66790438 Speedtronic, Mark VI TMR GEI-1004720438 HMI Time Synchronization GEI-1005130438 GE Indus Syst Standard Messages for

SpeedtronicGEI-100516

0438 LS 2100 Static Starter Control GEI-1005390438 Cooling Water Recommendations GEI-410040438 Specification For Fuel Gases GEI-410400438 GT Liquid Fuel Specifications GEI-410470438 Requirements For Water/Steam Purity in GT GEK-1019440438 C60 Breaker Management Relay GEK-1064060438 G60 Generator Management Relay GEK-1064110438 T60 Transformer Management Relay GEK-1064160438 Turbine-Generator Foundation Interface GEK-1069570438 GT Compressor Washing GEK-1071220438 Partial Discharge Analysis System GEK-1072200438 Basic Combined Cycle Start-up Procedure GEK-1075380438 Standard Field Performance Testing Philosophy GEK-1075510438 Plant Instrument Air System GEK-1107270438 GT & Accessory Equipment Preservation GEK-281560438 Recommendations For Storage of Liquid Fuels GEK-281630438 Lubricating Oil Recommendations for GT GEK-325680438 Generator Protection GEK-755120438 Heavy-Duty GT Operating & Maintenance

ConsiderationsGER-3620

0438 Gas Fuel Clean-Up Syst Design Considerations GER-39420438 Determination of Hazardous Area Extent GET-8591

0440 DIAG,SCHEM-LOAD EQUIPEMENT0442 DIAG,SCHEM-TB & CPRSR WSHG0444 ONE LINE DIAGRAM0445 WIRELIST FIELD WIRING0445 LIST, INTERCONNECTION WIRING0461 DIAG,SCH PP-WATER WASH UNIT

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 7: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 7/25

9FA Installation

0462 DIAG,SCH PP-WTR INJ SYS0463 CABLE SUMMARY0469 DIAGRAM SCH PP IGV0471 DIAG,FLOW-INLET & EXHAUST 0474 DIAG,SCHEM PP-HAZ GAS DETECTION0474 DIAG,SCHEM PP-HAZ GAS DETECTION0475 Instructions, Conduit Sealing0475 Sealing Instructions, Cable Gland0477 DIAG,SCHEM PP-FUEL PURGE0492 SCHEM PERFORMANCE MONITOR0546 Pick-Up Arr. Magnetic-HP0548 ACTUATOR ARRANGEMENT557T Pressure Transducer Arrangement557T Pressure Transducer Arrangement0623 ARR,THERMOCOUPLE, EXHAUS0637 THERMOCOUPLE ARR REMOVABL0701 Chamber Arrangement Combustion0706 Turbine Exhaust Diffuser0706 Diffuser-Aft Assy0706 Diffuser Assy Exhaust0706 FRAME ASSY, EXH *9F0706 Diffuser-Outer0706 Diffuser-Aft Assy0706 Diffuser Assy, Exhaust0706 Support-Aft Diffuser0726 TUNING systeme0726 TUNING systeme0905 Piping Lube Oil Feed and Drain bearing N°10905 Piping Lube Oil Feed and Drain bearing N°10906 Piping Lube Oil Feed and Drain interconnection0907 Piping Lube Oil Feed and Drain bearing N°20907 Generator Requisition Summary0909 Piping Cooling and Sealing Air0909 Piping Cooling and Sealing Air0909 Piping Cooling and Sealing Air0915 Piping Cooling Water turbine.0918 Piping, FUEL/NOZ,PRG0920 Piping Arrangement False Start Drain0924 Piping Arrangement Air Extraction0924 Piping Arr, Air Extract 0924 Piping Arr, Air Extract 0953 Piping, Compressor-Wash 0961 PPG, FUEL-OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 8: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 8/25

9FA Installation

0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL0961 TUBING ASSY, FUEL OIL PURGE0962 Piping Arrangement Fuel Gas System 0964 PPG FIRE-PRO, TB 0964 PPG FIRE-PRO, TB0965 Piping Arrangement ATMG / AIR0968 Piping Arr, water injection0969 Piping Arr, Lube-Oil Intco0969 Piping Arr, Control Oil Interconnect0969 PP ARR, LIQUID FUEL INTCON0969 PP ARR COOLING WTR INTCON0969 PP ARR FALSE START DR INT0969 PP ARR, WATER INJECT INTCO 0969 PP ARR, LIQ FL PURGE0972 Piping Arr, Cooling Air 0976 Piping Exhaust Plenum0979 Piping Arr, Inlet Plenum Drain 0987 Piping , turbine Performance Monit0987 Piping , turbine Performance Monit0995 Piping , Fire Prot Exhaust 1103 CONDUIT ARR TURB COMPT1105 CONDUIT ARR FIELD WIRING1105 CONDUIT ARR FIELD WIRING1105 FIELD TEST INSTRUCTIONS ELECTRICAL

CE1107 CONDUIT ARR,TURB HTG1107 Plant Instrument Air System GEK-1107271113 CONDUIT ARR TURB LTG1118 CONDUIT ARR,WHL SP TC1127 CONDUIT ARR-FLAME DET1140 CONDUIT ARR FIRE DET 1155 JUNCTION BOX ARRANGEMENT1159 CONDUIT ARR TURB LOW LEVEL1159 CONDUIT ARR TURB LOW LEVEL1160 CONDUIT ARR EXHAUST AREA-T1160 CONDUIT ARR EXHAUST AREA1213 IGNITION EXCITER ASSEMBLY1311 Guard, Coupling-Load Assembly1319 Coupling Solid Output1603 Foundation Bolting Arrangement1604 Bolting and Doweling Arr1604 Bolting and Doweling Arr1612 Outline, inlet Plenum1612 Inlet Erection Drawing 1612 Extension, Inlet Plenum1612 Extension, Test Fixture1612 Cone, Inlet Plenum1612 Arr, Inlet Transition

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 9: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 9/25

9FA Installation

1617 Outline Load Compt.1617 LOAD COMPT 1623 DUCT ARRANGEMENT1627 Acoust Barrier1634 Outline Offbase Enclosure1634 GT Enclosure Vendor instruction 1635 Duct Arrangement Cooling and sealing air1637 Nameplate Arr, Corp Signature1643 Outline , Press vent Fan1643 Compart Pressurization Inlet Air Filter Syst1643 Fan, Vent Enclosure general Arrangementt1643 Outline Grating Arrangement1643 Erection and Installation Manual1643 Structure support1643 High foundation1643 PID 1643 Diagram elementary1645 Outline GT Comp Grating Arrangement1648 Crane, Overhead (1 Ton) Outline1652 Access Ladder Thermocouple4007 SCH FG COALESCING FILTERA035 O/L Water Injection Skid enclosureA035 O/L Water Injection SkidA037 Inlet Bleed Heat Manual Stop ValveA037 Inlet Bleed Heat Manual Control ValveA040 Inlet Air Filtration, Erection & Install ManualA040 Air Filter System-General Arrangement A040 Foundation Arrangement & Load TablesA040 Piping Schematic (P&ID) Air Filter A040 Elementary Diagram – Turbine Inlet FilterA040 Hoist Installation KitA040 Screw Conveyor KitA040 Unistrut Kit, Pneumatic/ElectricalA040 Control Box GDXA040 Connection Kit, Compressed AirA040 Module Wiring KitA040 Lighting KitA040 Receptacle KitA040 Pressure Sensing Kit, Panel MountA040 Cover Enclosure KitA040 Pressure Switch KitA040 Hoist Electrical KitA040 Hoist Control KitA040 Screw Conveyor Electrical KitA040 Fire Hazard Sign KitA040 Lifting & CG, Diagram TransitionA040 Transition KitA040 Transition Gasket KitA040 Hatch Kit

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 10: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 10/25

9FA Installation

A040 Lift & CG Diagram, Filter Mod/Acoustic HoodsA040 Temporary Bracing Kit, Uni-ModA040 Lift Frame Kit, GDX Uni-ModA040 Inlet Hood Connection Kit, AcousticA040 Pulse Hopper KitA040 Module Hardware Erection Kit A040 Module Gasket Erection KitA040 Door Access Assembly, LHA041 Inlet Duct Installation Instructions A041 Inlet Duct WT CGA041 Inlet duct arrangementA042 Exhaust DiffuserA042 Exhaust Diffuser installation instructionA042 Exhaust DiffuserA059 36’ PEEC-MKVI W/PED INTERF. OUTLINEA059 PEECC OUTLINEA059 Universal Load Table For Cese MLsA059 PEECC Ordering DrwgA068 CO2 Fire Protection Unit-10 TON, 4 zones

LPCO2 Storage UnitA068 Fire Protect SystA068 Low Pressure CO2- Fire Protection Skid A073 Standard Req For Vndr DwgA073 Gear, Turning A073 M412 Technical ManualA073 Turning Gear Outline DwgA073 Turning Gear manual instructionA111 Outline & InterfaceA111 Generator Terminal EnclosureA125 Piping Arr, Lube Oil Feed FlushA125 Instruc Flushing GT Lubricant Oil SystA130 Air Processing SkidA130 O/L Air Processing SkidA130 Outline Drwg Air Process UnitA130 Diagram, schem PP Control AirA130 APU Skid Element Connect DiagramA132 Cooling Fan Module instruction AssemblyA132 Cooling Fan ModuleA140 LS 2100 Load Commutated Inverter GT Static

StarterA140 Plate&Frame Static Start Heat Exchanger

OutlineA140 DC Link Reactor Outline for 9F Static StarterA140 Shielding Policy A140 Static Starter KWH Curve, Harmonic

Analysis&Cable SummaryA151 Install Instruct & Drwgs Gen Arr/Assy DrwgsA157 LS 2100 CompartmentA160 Elec, Elem-Accy Module

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 11: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 11/25

9FA Installation

A160 Cool Wtr Vndr Supld CmptsA160 Fuel Gas, Vndr Supld CmptsA160 Hyd Sply, Vndr CmptsA160 Lube Oil, Vndr Supld CmptsA160 Fuel Purge, Vndr Supld CmpA160 Acc. Module General ArrangementA160 Acc. Module L.O. Gauge PanelA162 Vlv Assy, Trip Relay-HpA162 Valve Assy, Bypass-FoA162 Outline, Arrgt VNDR SPLD CMPTA162 Elec Elem, VNDR SPLD CMPTA162 Atomizing air, VNDR SPLDA162 COOL WATER, VNDR SPLD CMPTSA162 Liquid Fuel, VNDR SPLD CMA162 Lube Oil, VNDR SPLD CMPTSA162 Fuel Purge, VNDR SPLD CMPA162 Trip Oil, VNDR SPLD CMPTSA187 Inlet Air Heating Piping Design StandardE025 Outline Water Wash Skid enclosureE025 Outline, Washer Wash SkidE025 Diag, Schem PP-Water WashG015 Outline Fuel Gas Coalescing FilterG015 PID Fuel Gas Coalescing FilterG015 Diagram connection Fuel Gas Coalescing FilterSpec Bolt & Stud Torquing GE-248A4158Spec Welding –General Spec P8A-AG1Spec Welding – Fab of GTRB PP P8A-AG3Spec Leak Test &Blow-Down Procedure Liquid Fuel

Purge358A8851

Spec Hydrostatic Test, Fuel Gas Piping 372A2947Spec Pneumatic Test, Instruction 372A1391Spec Leak Test&Blow-Down Procedure, Liquid Fuel 360A7448Spec Piping Insulation / Heat Retention Material 355A7453Spec Material and Process Traceability 362A3678

ML GENERATOR SYSTEM DESCRIPTION BHEL REF REVSpec Piping Instruction Spec Generator Pipe Welding Instruction.Spec GE Instruction For Pipe SupportsG2MA Hydrogen Gas Dryer O/L Dual Tower G1J2 Float Trap O/LG1D0 Liquid Level Detector, OutlineB6D Piping Connections-GeneratorGIH Outline-Hydrogen Cabinet

G1E0 Outline-H2 ManifoldG1F0 Outline-CO2 ManifoldB7P Arrangement-Generator Lagging SupportA1CJ Stator HandlingG1G O/L, H2&CO2 Control Valves

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 12: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 12/25

9FA Installation

C908 Haz Area Map –Gen FLG/FLGA1BO Outline, Generator MechanicalA1D Electrical Connection Outline

G4JG Generator Piping OutlineG4JO Generator close Piping G4JO Piping bearing oil drainG4JO Piping bearing oil drainG4J0 Piping bearing oil feedG4J0 Piping seal oil drainG4J0 Piping seal oil feedG4J0 63 QT block porting valve assyG2FO P & ID Gas PipingG4BO P & ID Seal Oil G1C2 O/L Seal Oil SkidC902 Electrical Data, GeneratorG1JB C.T. Junction BoxG1V0 O/L Humidity SensorD6B Shipping Dimensions

G4JX BDE Loop Seal O/LG2RA Valve BallG2C0 Diag Elect Connection Seal Oil SystemC909 Equip Residual Risk SummaryC907 Generator Requisition SummaryG2B0 Diag, Cust Elect Conn Gen Gas AuxC900 Excitation System Model ConstantsG1P0 O/L Gen Gas Monitoring System

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 13: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 13/25

9FA Installation

4.0 ENVIRONMENTAL AND SAFETY CONCERNS

4.1 General

The Erection Team shall follow all site safety instructions and procedures as required for the execution of the scope of work covered by this instruction. In addition, the GE site safety manual and standards shall be followed as a minimum requirement.

4.2 Safety

4.2.1 Site safety instructions shall apply.

4.2.2 The installation of the gas turbine unit and system components requires work being performed from ground level to heights of approximately 10 meters. Safety precautions such as those detailed in the GE Safety Manual, available from the GE Technical Advisor on site, should be observed as minimum requirements.

5.0 RECEIVING, HANDLING AND STORAGE OF EQUIPMENT

5.2 Inventory of Equipment

A detailed inventory of all material shall be performed by the Installer against the shipping packing lists provided. In the event of either a quantitative or qualitative discrepancy, Report shall be issued. All discrepancies shall be reported immediately to the GE Technical Advisor on site for verification and assistance in initiating any corrective action and/or claims.

NOTE: All material and equipment packed in the Summary Sheet container, whether applicable for this instruction or not, shall be inventoried at this time.

5.3 Storage of Equipment and Materials

The Equipment and/or materials defined in this instruction can normally be stored in an outdoor lay down area with suitable cribbing to elevate the equipment above ground and with adequate weather protection provided (i.e., tarps). Other specific storage and/or preservation instructions from the Owner and/or GE's Technical Advisor on site, if applicable, shall also apply. All material received shall be stored and arranged to accommodate correct order of installation. Refer to the specific equipment erection instructions for other details regarding special storage requirements.

NOTE: The material and equipment packed in the Summary Sheet container is categorized for identification and stored on shelves within the container. This container, with all contents, is normally positioned in the vicinity of the gas turbine unit foundation pedestal during the time of erection.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 14: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 14/25

9FA Installation

6.0 EQUIPMENT ERECTION PROCEDURE

The following instruction outlines the detailed erection procedures to be followed for the scope of the work covered by this document. Reference to the required installation inspection sheets, data record forms in the Plan, is provided throughout the procedures and is indicated following each activity All damages, design discrepancies, defects and modification work shall be reported immediately to the GE Technical Advisor on site for verification and assistance in initiating any corrective action and/or claims.

6.1 Preliminary Work

Prior to commencing with any of the erection activities described herein, the following preliminary work activities must be completed.

6.1.1 Review Erection Documentation

6.1.1.1 Review all erection documentation as referenced in Section 4.0 of this instruction.

6.1.1.2 Review and understand all safety and environmental information and documentation as referenced in Section 5.0 of this instruction.

6.1.1.3 Ensure that all Data Record Sheets are available as required.

6.1.1.4 Verify that all documentation as referenced in 6.1.1.1, 6.1.1.2, and 6.1.1.3, above, has been thoroughly reviewed and understood.

6.1.2 Preparation of Work Area

6.1.2.1 Ensure that turbine hall building, foundations, turbine foundations, building structural steel, etc., have been completed

6.1.2.2 Ensure that the work area is clear of all debris, equipment and material that may cause injury to personnel, interference with the installation effort or damage to the equipment being installed.

6.2 Foundations Interface Checks

It is critical that the foundation and support areas be thoroughly inspected prior to setting the gas turbine and generator unit in place. These inspections are required to verify that the foundation has been properly formed with all required anchor bolts, grout pockets, restraining blocks, jacking posts, conduit stub-ups and cable pits for installation of the equipment covered by this instruction.

6.2.1 Inspect/Verify Foundation Interface, Embedment and Support Areas

6.2.1.1 Verify that all required foundation embedment, fixators and sole plates for the gas turbine/generator equipment have been installed.

6.2.1.2 Verify all foundation and support areas for correct location, size, elevation and potential interferences of grout pockets, anchor bolts,

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 15: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 15/25

9FA Installation

pits, embedded conduit, piping and height restrictions with respect to the equipment to be installed.

6.2.1.3 Clean as required the foundation sub-sole plates and embedded restraining blocks and apply a light grade machinists oil.

6.2.1.4 Verify that all foundation interface checks per 6.2.1.1, 6.2.1.2 and 6.2.1.3 have been carried out. Complete installation report sheet. “Foundation Anchor Bolt Position”.

6.2.2 Preparation of Foundation, Packers and Shims

6.2.2.1 Transfer all equipment centerline and elevation references to foundation and support areas and record data. Verify that all critical datum’s are established with chalk line or wire as required in accordance with ML 0323.

6.2.2.2 Prepare gas turbine foundation bolting arrangement material ML 1603

6.2.2.3 Verify that all foundation checks per 6.2.2.1 and 6.2.2.2 have been carried out as required. Complete installation report Sheet.“Sub sole Plate & Fixator Checks”.

6.3 Preparation of Equipment for Installation

6.3.1 Remove all general shipping braces, saddles, bolsters, shipping covers, packing and supports as required to permit unrestricted installation of the equipment.

NOTE: Do not remove any braces or supports that may be installed for stiffening purposes for lifting and handling of the equipment. Do not remove the shipping covers on the gas turbine inlet casing and exhaust frame at this time. These covers shall remain in place until it is absolutely necessary to remove for erection of the associated components.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 16: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 16/25

9FA Installation

6.3 Mechanical Erection

6.3.1 Installation of the GT & Generator - ML 1603Prepare all contact surfaces before lowering turbineClean sub sole platesFit guard sleeves on anchor bolts to protect themCheck thickness of all shims with micrometerPrepare standards packets Added or remove shims to compensate for height differences as marked on sub soles plates - After turbine installation on the foundation align on axis REMOVING ROTOR BLOCKING SUPPORT ML 103

6.3.2 Transport, lift and set gas turbine unit and base assembly onto foundation pedestal and foundation plates. Verify that the gas turbine unit and base is initially set with respect to the established site datum’s i.e; centerline line of GT anchor pin and axial shaft-line to within + 0.125 in. (+ 3.18 mm)

6.3.3 Transport, lift and set Generator unit assembly onto foundation supports. Verify that the generator unit is initially set with respect to the established site datum’s i.e; centerline line of GT anchor pin and axial shaft-line to within + 0.125 in. (+ 3.18 mm) and data recorded.

6.3.4 Erect gas turbine exhaust diffuser in accordance with manufacturers instructions ML A042

6.3.5 Complete GT turbine Drop Check. Complete installation inspection sheet.“Turbine Drop Check”

6.3.6 Confirm position of exhaust duct relative to exhaust diffuser and commence field assembly in accordance with manufacturers specification. Complete installation inspection sheet.“Exhaust diffuser to exhaust duct alignment Sheet”

6.3.7 Erect inlet plenum ML 1612 structural support steel, and preposition lower inlet plenum to GT compartment enclosure seals. Install and assembly inlet plenum lower half and confirm correct elevation, axial and transverse location. Install the lower half inlet cone piece and extensions in accordance with the manufacturers instructions.

Install combustion hardware in accordance GE combustion assembly drawing ML 0701.

6.3.8 Install gas turbine load coupling ML 1319 in accordance with Riverhawk bolting assembly instructions. Prior to assembly ensure load coupling male and associated female rabbit dimension.

Record coupling bolt elongation data on installation report sheet .“Coupling Bolt Stretch Data”.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 17: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 17/25

9FA Installation

6.3.9 With the load coupling (spool piece) installed and measuring from the coupling flange, set the preliminary gas turbine to generator cold alignment, Ref to field alignment instruction ML 0411. Adjustments are made utilizing the adjustable fixators under the gas turbine sub-sole plates. During the elevation and slope adjustments, ensure that the loading of each fixator remains consistent.

6.3.10 When preliminary alignment has been accomplished it is now possible to remove the GT Base axial beams and continue with installation of the combustion hardware. Any further alignment changes can be accomplished by sliding the generator.

6.3.11 Set the generator collector house on foundation and complete preliminary alignment checks

6.3.12Set turning gear on foundation ML A073 and complete preliminary static alignment as outline on ML 0411 field alignment instruction

6.3.13 Install generator terminal enclosure as outline

6.3.14 Complete assembly of air inlet plenum in accordance with the vendor erection instructions. ML 1612

6.3.15 Commence erection of air inlet duct support steel and assembly of inlet duct in accordance with vendor assembly instructions ML A041

6.3.16 Commence pre-assembly of inlet filter house modules at ground level. Following lift and position all module in accordance with vendor field erection instructions. ML A040

6.3.17 Set all major skid on foundation ML A160 / A162 / A035 / E025 / A068

6.3.18 Continue erection of GT ML 1634 and exhaust enclosures ML 1627 in accordance with vendor erection instructions

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 18: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 18/25

9FA Installation

6.4 PIPING INSTALLATION

Assembly all on base GT and module interconnection piping in accordance with the respective PED requirements. Complete weld mapping, NDT and pressure testing as necessary. Confirm all material, personnel and plant traceability records as necessary. Refer to each system specific assembly drawing to identify the system PED category and testing requirements.

6.4.1 ASSEMBLING OIL SUPPLY AND RETURN PIPE WORK ML 0905 / 0907 / 0969

For end bearing n° 1 Drawing For end bearing n° 2 Drawing Sealing plates return bearing n°2 Drawing ML 1635

1) Fit on he bearing 1 and 2 internal pipe work before final assembly2) Adjust and connect pipe work to bottom of lower oil supply and return3) Welding specification.GE Drawing P8A-AG1 / GE Drawing P8A-AG34) Cleaning & Painting Specification GE Drawing 362A35625) Bolting specification GE Drawing 248 A 4158

6.4.2 COOLING AND SEALING AIR PIPEWORK ML 0909 1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .GE Drawing GE P8A-AG1 / GE P8A-AG3 4) Bolting specification .GE Drawing 248 A 4158

6.4.3 SUPPLY AND RETURN IGV OIL PIPEWORK ML 0969M

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification GE Drawing P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification GE Drawing 362A35625) Bolting specification GE Drawing GE-248 A 4158

6.4.4 INTERCONNECTION OIL SUPPLY AND RETURN PIPEWORK ML 0906 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification N° GE P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification N° 362A35625) Bolting specification N° GE-248 A 4158

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 19: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 19/25

9FA Installation

6.4.5 COOLING WATER PIPEWORK ML 0915 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification N° 362A35625) Bolting specification N° GE-248 A 4158

6.4.6 FALSE START DRAIN PIPEWORK ML 0920 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Tubing fittings instruction N° 215A44354) Welding specification .N° GE P8A-AG1 / GE P8A-AG35) Cleaning & Painting Specification N° 362A35626) Bolting specification N° GE-248 A 4158

6.4.7 AIR EXTRACTION ATOMIZING PIPEWORK ML 0924

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification N° 362A35625) Bolting specification N° GE-248 A 4158

6.4.8 ATOMIZING AIR PIPEWORK ML 0965

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification N° 362A35625) Bolting specification N° GE-248 A 4158

6.4.9 WATER INJECTION PIPEWORK ML 0968 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Tubing fittings instruction N° 215A44354) Welding specification .N° GE P8A-AG1 / GE P8A-AG35) Cleaning & Painting Specification N° 362A35626) Bolting specification N° GE-248 A 4158

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 20: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 20/25

9FA Installation

6.4.10 LIQUID FUEL PURGE PIPEWORK ML 0918 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Tubing fittings instruction N° 215A44354) Welding specification .N° GE P8A-AG1 / GE P8A-AG35) Leak test instruction N° 358A88516) Cleaning & Painting Specification N° 362A35627) Pipe insulation N° 355A74538) Bolting specification N° GE-248 A 4158

6.4.11 FUEL OIL PIPEWORK ML 0961 / 0969

1) Fasten pipe work supports2) Adjust and install pipe work3) Tubing fittings instruction N° 215A44354) Liquid fuel leak test / blow down procedure N° 360A74485) Welding specification N° GE P8A-AG1 / GE P8A-AG36) Cleaning & Painting Specification N° 362A35627) Bolting specification N° GE-248 A 4158

6.4.12 FUEL GAS PIPEWORK ML 0962 1) Fasten pipe work supports2) Adjust and install pipe work3) Hydrostatic test N° 372A29474) Pneumatic test N° 372A13915) Welding specification .N° GE P8A-AG1 / GE P8A-AG36) Bolting specification .N° GE-248 A 41587) Cleaning & Painting Specification N° 362A3562

6.4.13 COOLING AIR PIPEWORK ML 0972 1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Bolting specification .N° GE-248 A 41585) Cleaning & Painting Specification N° 362A3562

6.4.14 EXHAUST DRAIN PIPEWORK ML 0976 1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG3 5) Bolting specification .N° GE-248 A 41586) Cleaning & Painting Specification N° 362A3562

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 21: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 21/25

9FA Installation

6.4.15 INLET PLENUM DRAIN PIPEWORK ML 0979 1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Bolting specification .N° GE-248 A 41585) Cleaning & Painting Specification N° 362A3562

6.4.16 TUBING PERFORMANCE MONITORING PIPEWORK ML 0987 / 557T 1) Fasten pipe work supports2) Adjust and install pipe work3) Tubing fittings instruction N° 215A44354) Cleaning & Painting Specification N° 362A3562

6.4.17 FIRE PROTECTION PIPEWORK ML 0964 / 0995

Bearing N° 2 N° 119E84141) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification .N° GE P8A-AG1 / GE P8A-AG34) Cleaning & Painting Specification N° 362A35625) Bolting specification N° GE-248 A 4158

6.4.18 Install all generator on base piping, off base modules and interconnection piping in accordance with the respective PED requirements. Complete weld mapping, NDT and pressure testing as necessary. Confirm all material, personnel and plant traceability kept as necessary. Refer to each system specific assembly drawing to identify the system PED category and testing requirements. All documentation supplied by BHEL.

GENERATOR INTERCONNECTION OIL SUPPLY AND RETURN PIPEWORK

1) Fasten pipe work supports2) Adjust and install pipe work3) Welding specification 4) Cleaning & Painting Specification 5) Bolting specification

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 22: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 22/25

9FA Installation

6.5 GT INSTRUMENTATION

Commence installation of GT on base control instrumentation, cabling and conduit at roughly 80% mechanical completion. Follow GT compartment conduit assembly outlines as close as possible, All compartment wall glands needs to be closely monitored in relation to positioning of control junction boxes etc.

6.5.1 CONDUIT & INSTRUMENTATION COMPT TURBINE ML 1105 / 1155

Installation of electrical conduits.Installation of the junction box.Installation Fire detectors.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.2 CONDUIT& INSTRUMENTATION TURBINE HEATING ML 1107

Installation of electrical conduits.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.3 CONDUIT & LIGHTING COMPT TURBINE ML 1113

Installation of electrical conduits.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.4 CONDUIT & TURBINE WHL SP TC ML 1118

Installation of electrical conduits.Installation TC wheel space.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.5 CONDUIT FLAMME DETECTOR ML 1127

Installation of electrical conduits.Installation flame detector.Instrumentation to be wire to the junction box. Check the continuity of the wires.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 23: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 23/25

9FA Installation

6.5.6 CONDUIT & FIRE DETECTION ML 1140

Installation of electrical conduits.Installation Fire detectors.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.7 CONDUIT & INSTRUMENTATION TURBINE LOW LEVEL ML 1159

Installation of electrical conduits.Installation of junction box.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.5.8 CONDUIT & INSTRUMENTATION EXHAUST SIDE ML 1160

Installation of electrical conduits.Installation of junction box, thermocouples.Instrumentation to be wire to the junction box. Check the continuity of the wires.

6.6.1 Complete erection of GT, exhaust, load and generator enclosures pay particular attention to compartment interface seals and acoustical panels.See ML 1617 / 1634 / 1643

6.6.2 Complete assembly of all remaining shaft-line component, fan modules, gas conditioning equipment, customer interconnection piping and cabling.

6.6.3 Complete GT and Generator lube oil, seal oil, lift oil and control oil flush, utilizing flushing hardware supplied under ML A125 and in accordance with the appropriate cleanliness specification.

Instruction 362A3595

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 24: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 24/25

9FA Installation

6.6.4 Following lube oil flush reinstatement and upon availability of lift oil system, commence load shaft run out checks. Upon confirmation that load shaft run out data meets specification, record data on installation inspection sheet.“Load Coupling Spool Piece Run out”

6.6.5 Commence finally alignment of the GT to the Generator, moving the generator as the preferred option to the GT. Upon successful completion of the alignment to GE spec record alignment data. Complete installation inspection sheet.“Final Alignment Load Shaft to Generator”

6.6.6 With the gas turbine to generator alignment complete now commence final alignment of the turning gear to generator shaft by rotation and repositioning the turning gear as necessary. Upon successful completion of the alignment to GE spec record alignment data. Complete installation inspection sheet. “Final Alignment Turning Gear to Generator”

6.6.7 With all final alignment complete, finalize the axial retaining shim, gib key clearances and anchors locations in accordance with instruction outlined on ML 1603 & 1604 drawing instructions. Complete installation inspection sheet.“Axial Centre line Support Clearances”

6.6.8 Finalise position of collector housing assembly and record fan blade clearance.Complete installation inspection sheet.“Collector Ring and Fan Blade Clearances”

6.6.9 Finalize speed pickup gap setting and install load coupling shaft guard.Complete installation inspection sheet. “Speed Pickup Gaps”

6.6.10 Confirm all motor to pump final alignments in accordance with appropriate vendor coupling requirements. Complete installation inspection sheet.Final Alignment Aux Lube Oil Pump 1.Final Alignment Aux Lube Oil Pump 2.Final Alignment Emergency DC Lube Oil Pump. Final Alignment Aux Seal Oil Pump.Final Alignment Emergency DC Seal Oil Pump.

6.6.11 Complete grouting of gas turbine sub sole plates and remove all alignment jacking beams.

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.

Page 25: Frame 9FA Erection Procedure

GE EnergyServices – Power

Services Installations

FRAME 9FA

Date : 6/17/04/2023

ERECTION PROCEDURE Rév. : 0Page : 25/25

9FA Installation

6.7 Equipment Painting

The gas turbine base and other related components are factory painted with one coat inorganic zinc, Carboline CZ11, followed by an epoxy top coat. Scuff marks, scratches and other damage to the primer or finish coat incurred during transportation to site and on-site handling or welding will require touch-up primer painting only. A final coat of paint is not required for the gas turbine, base and related components. All enclosures, inlet plenum, duct and filter house have been factory coated with exterior primer coat. Refer to GE drawing 357B9917 when selecting a suitable top coat paint.

6.5.1 Complete touch up painting per Instruction P6C-AG25 as found in Tab D of this instruction. Verify that all scratches and damage to exposed painted surfaces have been repaired.

6.8 Construction Conformity File

6.6.1 As a prerequisite to the system Commissioning activities and following erection of all gas turbine system components, through erection activity 6.3.1 to 6.6.11 a complete system installation inspection must be performed to verify any outstanding work. Complete final installation inspection and record any punch list MLs.

6.6.2 Verify that all Installation inspections sheets and other construction quality documentation has been completed in accordance with the project plan and filed in the Construction Conformity File.

7.0 APPENDIX (INSTRUCTION SPECIFIC)

Installation Inspection Sheets.

Related GEK’s, GEI’s and TIL’s

This document, sole property of our GE Energy. It is strictly confidential.It must not be communicated, copied or reproduced without our written consent.