3
Foundation for roller press in a cement plant A case study J.D. Buch The paper describes roller press structure in a cement mill of a cement plant. When provision of press is planned along with mill building, it is possible to provide suitable structural arrangement. This provision is sometimes made in an existing mill or in mill structure already under construction. In such a case, limitations are imposed on planning of supporting structure. Since the introduction of press is a new develop- ment, there is still a lack of reliable machine load data and vibration constraints. A case study of such a foundation in recently-constructed cement plant is given with recommen- dations on proposed structural arrangement. A roller press is installed in front of grinding installations to cut down energy consumption in the grinding unit. Installa- tion of a roller press before rolling mill or cement mill in cement plants is now becoming a common feature. In a roller press, clinker material is subjected to extreme pressure between opposing rollers for a short time, Fig 1. One roller is fixed and other roller can move by about 50 mm laterally (perpendicular to rotating axis) to adjust space for size of material to be rolled between the rollers. This movement is achieved by hydraulic/pneumatic supporting system and keeps roller gap or pressure constant. Each roller is driven by an electric motor through a gear reducer. The products dis- charged from roller press are compacted cakes of irregular size. Case study In a certain cement plant, it was decided to provide a roller press after column and mill foundations of a cement mill were J. D. Buch, M.S.E. (USA), B.E. (Hons.), F.I.E., Engineering Associate with Fig 1 Roller press in a cement plant where clinker is ground under Kothari and Associates, G-65, Connaught Circus, New Delhi 110 001. high pressure October 1992 * The Indian Concrete Journal 559

Foundation for roller press in a cement plant A case studydspace.cusat.ac.in/jspui/bitstream/123456789/1434/1/Foundation for... · Foundation for roller press in a cement plant A

Embed Size (px)

Citation preview

Foundation for rollerpress in a cement plantA case study

J.D. Buch

The paper describes roller press structure in a cement mill ofa cement plant. When provision of press is planned along withmill building, it is possible to provide suitable structuralarrangement. This provision is sometimes made in an existingmill or in mill structure already under construction. In sucha case, limitations are imposed on planning of supportingstructure. Since the introduction of press is a new develop-ment, there is still a lack of reliable machine load data andvibration constraints. A case study of such a foundation inrecently-constructed cement plant is given with recommen-dations on proposed structural arrangement.

A roller press is installed in front of grinding installations tocut down energy consumption in the grinding unit. Installa-tion of a roller press before rolling mill or cement mill incement plants is now becoming a common feature.

In a roller press, clinker material is subjected to extremepressure between opposing rollers for a short time, Fig 1. Oneroller is fixed and other roller can move by about 50 mmlaterally (perpendicular to rotating axis) to adjust space for sizeof material to be rolled between the rollers. This movement isachieved by hydraulic/pneumatic supporting system andkeeps roller gap or pressure constant. Each roller is driven byan electric motor through a gear reducer. The products dis-charged from roller press are compacted cakes of irregularsize.

Case studyIn a certain cement plant, it was decided to provide a rollerpress after column and mill foundations of a cement mill were

J. D. Buch, M.S.E. (USA), B.E. (Hons.), F.I.E., Engineering Associate with Fig 1 Roller press in a cement plant where clinker is ground underKothari and Associates, G-65, Connaught Circus, New Delhi 110 001. high pressure

October 1992 * The Indian Concrete Journal

559

.96 0 0

Roller— press

millCement

Pozzolona Clinker

.18 500

.16500

.1 5 0 00

t of press

81 5 k N

9800

.2610

0.00

Sec iron

. 23 500

«21900

11 500

13500

'2,I

800 1345

In

- - —

2540 5235

(400 x 600).. 400

_o 1r 0"--- o

I 120 x 1 20 4 ---- .4-4

, through x II pockets 81 II I I°.I (10 Nos.) 25 I (880 x 650) I?, g

7

1

t of milland roller Ipress

1I I — L —=r1I1= I

o,..,0 .0-11 M

I1

=UM i,,, .

o

---,

L - - -311111==. .toI 1

260

I-

(830 x 650) !

12501,1050i1050 1490iI

TT

n11,1o 0

rl— 260 "'

.(400 x 600) fig 0 -- - 0._

.

— t of roller press

-r--I

I

0Qco

Fig 2 General arrangement under mill hopper area at +9.8 m level(case study)

constructed. The arrangement under the mill hopper area wasrevised. The general arrangement is shown in Figs 2 and 3.

Roller press is mounted at +9.8m level floor in front of themill and below mill hopper. Rollers are mounted on a steelframe bolted to reinforced concrete beam-column frames. Fourreinforced concrete columns of size 800mm x 800mm in M-20mix (28-day characteristic cube strength = 20 MPa) areprovided upto +9.8m level only to support roller press floor.Since provision of press was made after a part constructionwas complete, it was not possible to isolate this area fromcement mill structure. It was also not possible to providecolumns right under roller framing beams, since free space onground floor was not available. For designing +9.8m slab, thesuppliers gave the following load data :

For rollers mounted on 10 bolts,vertical load on each bolt = 81.5 kN

Total vertical load = 815 kN

Lateral force along centre line ofpress (that is along axis perpen-dicular to rotating axis of press) = 163 kN

The horizontal force of 163 kN is due to horizontal motionof the movable roller, which is prompted by the feed materialswhen pressed through the roll gap. This force is independentof roller speed. The structure was designed and constructedfor these loads. Before the roller erection, suppliers informedthat the supporting structure should withstand 2 to 10 Hz

fluctuation of horizontal motion of the movable roller.

Since press structure was a part of mill floor at +9.8 m level,lateral stiffness was very large and horizontal natural frequen-cy would be much larger than the specified range. This there-fore did not cause any concern. However, the vertical naturalfrequency of the already-constructed supporting structurewas 7.4 Hz. In order to keep this frequency at about 20 percentaway from the specified range, vertical deflection of the sup-porting beam had to be reduced from 0.51 cm to 0.17 cm toincrease natural vertical frequency value from 7.4 Hz to 12 Hz.Since it was not possible to increase beam stiffness, the onlyalternative was to reduce beam span by providing additionalcolumn supports. This also was an operational obstruction.

It was explained to suppliers that the hydraulic system,operating roller movement, will partly absorb oscillations andthe supporting structure may not be subjected to such widerange of oscillations. The suppliers agreed to accept the struc-

Fig 3 A cross-section of the general arrangement under millhopper area (case study)

560 The Indian Concrete Journal * October 1992

4 Nos120x120x503 deep

— 6 Nos120 x170throughpocket

5000 5000

(t_ of roller press

(750 x 850)

1490 1050 1050 1300

00

Fig 4 Roller press installed at +9.8 m level in a cement mill.Moveable roller and hydraulic system can be seen

ture to withstand oscillations in 2-5 Hz range.

No modification in structure was made and additionalcolumns were not provided. The press is installed and is in

Fig 5 Enlarged view of hydraulic/pneumatic supporting systemfor keeping roller gap constant

Fig 6 Recommended arrangement : (I) isolation joint (ii) columnsdirectly under roller frame

operation. No significant vibrations are so far reported in the

structure. Figs 4 and 5 show photographs of the installed

press.

ConclusionDue to movement of roller, there is a wide range

of oscillations, though suppliers should not

specify this on adhoc basis.

It is advisable to isolate press supporting struc-

ture from the main structure of the mill to prevent

transfer of vibrations to the main structure. It is

also advisable to provide supporting columns

directly under the beams on which rollers are

mounted. Such arrangement is provided in a

plant where roller press was planned along with

the mill building, Fig 6.• • •

1 Non-receipt of JournalWe have been receiving a number of complaints from sub-scribers/agents regarding non-receipt of the Journal. Tillnow, we have promptly attended to these complaints.

However, henceforth it has been decided not to entertaincomplaints which are received late. We therefore requestout subscribers to send their complaints within a period ofone month after the publication of a particular issue. Forsubscription agencies, this period would be two months.

The replacement copy/copies would be supplied onlyonce. This practice would be followed strictly.

— Circulation Manager

October 1992 n The Indian Concrete Journal 561