Fort Nelson Progress Pictures Week 16 • Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10

Fort Nelson Progress Pictures Week 16

  • Upload
    viet

  • View
    68

  • Download
    3

Embed Size (px)

DESCRIPTION

Fort Nelson Progress Pictures Week 16. Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10. Fort Nelson Progress Pictures. Steelwork installed to tapered wall and foundation for flank wall 4 and starter bars. Fort Nelson Progress Pictures. - PowerPoint PPT Presentation

Citation preview

Page 1: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures Week 16

• Shuttering completed from C6 – C8 and wall poured on Friday 26/11/10

Page 2: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures• Steelwork installed to

tapered wall and foundation for flank wall 4 and starter bars.

Page 3: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures• Gas meter house

demolished, foundation excavated from C1 – C5 and 50% blinded, 3no column bases excavated

Page 4: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures Water tank downstand

beams poured, tanks sanded up and insulation and volclay installed.

Page 5: Fort Nelson Progress Pictures Week 16

Fort Nelson Progress Pictures

2no underpins excavated and poured.