Foothill Water Treatment Plant & La Brea Subarea Updates
Public Works Commission
September 10, 2020
1
• Contractor mobilized on August 3, 2020
• Demolition commenced on August 4, 2020
FWTP Project Activities
2
FWTP Project Activities
Protection of existing
facilities
City contractor evacuating
old chemicals in chemical
room 3
• OMF performance test arrived early
• OMF performance test completed early
• Performance test report is under review by Carollo
FWTP Project Performance Test
4
FWTP Project Overview
37 Submittals Processing
9/8/20
Sub. # DescriptionSpec Section/ Ref.
DWG
Date
Received
from
Contractor
Date Forwarded
to City
Date Received
from City
Date Forwarded
to Carollo
Date Received
from Carollo
Date
Returned to
Contractor
Notes/Remarks
00001 Selective Demolition Plan 01 35 21 7/20/20 8/25/20 NET this item was previously approved
00002.1 OMF Proof Pilot Test 46 61 25 8/5/20 8/5/20 8/5/20 8/5/20 NET
00003 Automatic Backwashing Sand Separators 8/5/20 8/5/20 8/5/20 8/5/20 Rejected - see comments (Need Submittal)
00003.1 Automatic Backwashing Sand Separators 9/4/20 9/4/20
00004 Butterfly Valves 510 40 05 64 8/5/20 8/5/20 8/12/20 8/12/20 NET
00005. Concrete Mix Design Class A and C 03 30 00 8/11/20 8/11/20 8/19/20 A&R
00005.1 Concrete Mix Design Class A and C 03 30 00 8/28/20 Under Review
00006 Agreegate Base 31 05 15 8/11/20 8/11/10 8/21/20 8/21/20 NET
00007 Rebar (next centrury) 0320 00 8/12/20 8/12/20 8/27/20 8/27/20 MCN
00008 OMF Filter Assembly 41 61 25 8/18/20 8/18/20 8/27/20 8/27/20 MCN
00009 PVC Water Stop 03 15 00 8/18/20 8/19/20 8/24/20 8/24/20 NET
00010 Trench Grating Imbeds 05 50 00 8/20/20 8/20/20 9/3/20 9/3/20 MCN
00011 Pipe Layout Drawings 40 05 24.01 8/21/20 8/21/20 9/1/20 9/1/20 MCN
00012 BFV Actuators 40 05 64 9/1/20 9/1/20
00013 Baseline Schedule 01 31 17 8/28/20
00014 Pilot Test Report 4 61 256 8/28/20 9/2/20
00015 Metering Pumps and Chemical Skids 43 33 20 8/28/20 8/28/20
00016 WQMP 9/2/20 9/3/20
00017 THHN Wire 26 05 05 9/2/20 9/2/20
00018 Tiger Tanks 01 60 00 9/2/20 9/2/20
00019 Ethernet Cat 6 26 05 05 9/3/20 9/3/20
00020 16 AWG Wire - Plenum Rated 26 05 05 9/3/30 9/3/20
00021 GRC Rigid Conduit 26 05 33 9/3/20 9/3/20
00022 PVC Sch 40 and 80 Conduit 26 05 33 9/3/20 9/3/20
00023 Liquid Tight Flex Conduit 26 05 33 9/3/20 9/3/20
00024 Channel Strut 26 05 04 9/3/20 9/3/20 NET
00025 Clear Pipe Cement 26 05 33 9/4/20 9/5/20 NET
00026 Toggel Switch 26 05 04 9/4/20 9/4/20
00027 Junction Box electrical 26 05 04 9/4/20 9/4/20
00028 Electrical Hardeware 26 05 04 9/4/20 9/4/20
00029 Stud Wedge Anchor 26 24 45 9/4/20 9/4/20
00030 Cable Support 26 50 00 9/4/20 9/4/20
00031 Ground Screw 26 05 26 9/4/20 9/4/20
00032 Locknut steel/plastic insulation bushing 26 o5 33 9/4/20 9/4/20
00033 Threaded Rod 26 05 04 9/4/20 9/4/20
00034 Beam Clamp 26 05 04 9/4/20 9/4/20
00035 LED High Bay Light 26 50 00 9/4/20 9/4/20
City of Beverly Hills - Foothill Water Treatment Plant Pretreatment System
SUBMITTAL LOG9/8/20
RFI # Description
Spec
Section/ Ref.
DWG
Date
Received
from
Contractor
Date
Forwarded
to City
Date Received
from City
Date
Forwarded
to Carollo
Date Received
from Carollo
Date
Returned to
Contractor
Notes/Remarks
1 Steel Pipe Thickness 7/10/20 7/10/20 7/10/20 7/10/20 Closed
2RO Membrane Elements Warranty and
Design Criteria46 63 25 TBD 8/3/20 8/3/20 Closed
3 Automatic Backwashing San Separators 7/22/20 7/22/20 7/27/20 7/27/20 Closed
4 SOG Trench Construction Joint 7/23/20 7/23/20 7/31/20 7/31/20 Closed
5 OMF Influent PH Sample Tap M03 7/23/20 7/23/20 7/27/20 7/27/20 Closed
6 SAC Tank Piping 7/23/20 7/23/20 7/27/20 7/27/20 Closed
7 Location of V345 FEFIT116 V930-1 7/23/20 7/23/20 7/27/20 7/27/20 Closed
8 Job Trailer Location 7/24/20 7/24/20 7/27/20 7/27/20 Closed
9 Rotary Lobe Blower 8/5/20 8/5/20 8/6/20 8/6/20 Closed
10 OMF Controls Clarifications 8/5/20 8/5/20 8/12/20 8/12/20 Closed
11 Painting of Pipe 8/5/20 8/5/20 8/12/20 8/12/20 Closed
11.1 Painting of Pipe City to select colors
12 CMLC Clarifications 8/6/20 8/6/20 8/12/20 8.12.20 Closed
13 Conversation Room Curtains 8/6/20 8/6/20 8/6/20 8/7/20 Closed
14 Key to Door by Rollup 8/6/20 8/6/20 8/18/20 Closed
15 Flush Tank Diameter 8/12/20 8/12/20 see 15.1
15.1 Flush Tank Diameter 8/17/20 8/17/20 8/17/20 8/17/20 Closed
16 Equipment Pad Anchor Bolts 8/12/20 8/12/20 8/21/20 8/21/20 Closed
17 FRP Tank Design 8/12/20 8/12/20 8/18/20 8/18/20 Closed
18 Rebar Embedment 8/17/20 8/17/20 8/24/20 8/24/20 Closed
19 Conservation Room Wall 8/17/20 8/28/20 Closed
20 FRP Inline Mixer Materials 8/17/20 8/17/20 8/18/20 8/18/20 Closed
21 Pipe Size at Treated Water Line 8/17/20 8/17/20 8/18/20 8/18/20 Closed
22 Capping SW Line into Clearwell 8/17/20 8/17/20 8/18/20 8/18/20 Closed
23 Steel Tank Clarifications 8/17/20 8/17/20
24 P638 Pipe Support Bracing 8/21/20 8/21/20 8/24/20 8/24/20 Closed
25 SHC Duplex Skid Design 8/19/20 8/24/20 8/28/20 8/28/20 Closed
26 Ready Mix Concrete Alkali Reactivity 8/20/20 8/20/20 8/24/20 8/24/20 Closed
27 10 BWS OMF Pipe Support 8/21/20 8/24/20 8/31/20 8/31/20 Closed
28 MCC-WTF Breaker Swap 8/21/20 8/21/20 8/24/20 8/24/20 Closed
29 Fire Alarm & Strobe 8/21/20 8/21/20 8/24/20 9/1/20 Closed
30 Unknown pipe stub up 8/26/20 8/26/20
31 Pipe Material Support 8/26/20 8/26/20 8/28/20 8/28/20 Closed
32 Acid Eyewash Station 8/26/20 8/26/20 8/28/20 8/28/20 Closed
33 FRP RW on Clearwell 8/27/20 9/1/20 Closed
34 Column Protection Slab Conflict 9/1/20 9/1/20
35 Equipment Pads Outside Demo Limits 9/1/20 9/3/20 Closed
36 Existing valves Reused? 9/4/20 9/4/20
37 Pipe Support needed? 9/4/20 9/4/20
38 Trench Grating support/width 9/4/20 9/4/20
City of Beverly Hills - Foothill Water Treatment Plant Pretreatment System
RFI LOG
38 RFI’s Processing
• Work Completed: $513,475
• Percent Work Completed: 5.18%
• Work Schedule is On Time
5
FWTP Project Schedule
6
La Cienega Well No. 1 (LCW-1)
Drilled 16-inch pilot hole
to 500 ft. with no drilling
additives
Collected water quality
samples from two
discrete zones in the
open boreholes
Installed water level
monitoring devices in La
Cienega Carwash
monitoring wells
(DDW request)7
La Cienega Well No. 1 (LCW-1)
Reamed borehole to 26-
in diameter to 475 ft.,
constructed well with
460 ft. of 14-inch
stainless steel well
casing and louvered
well screen
Filled annular space with high quality, high
silica content, well rounded filter pack to 190 ft.
Installed
cement seal
from 190 ft. to
ground surface
8
La Cienega Well No. 1 (LCW-1)
• Mechanical development completed (to remove remnant drilling fluid)
• Test pump installed
– Pumped at 130 gpm (max. rate to sewer) for 1.5 hours, ~12 ft. of drawdown – promising news
• Upcoming Work
– Discharge line installation to storm drain
– Pumping development (to remove fine particles and sand)
– Pumping tests, including packer test
9
16” Ductile Iron Pipe Installation
La Brea Subarea Transmission Main
10
La Brea Subarea Transmission Main
Slipline 18” PVC Fused Joints 11
La Brea Subarea Transmission Main
Slipline 18” PVC Fused Joints 12
13
La Brea Subarea Transmission Main
Wench for Slipline
Demolition of Sand Pit Site
• Bid date 8/20/20
• Award scheduled for 9/15/20
• Construction: TBD
14
La Brea Subarea Overview
LCW NO. 1 - DRILLING
• Budget: $950,230
• Work Billed: $600,941
• Percent Work Completed: 75%
• Work Schedule is On Time
TRANSMISSION MAIN
• Budget: $8,000,000
• Work Billed: $3,157,704
• Percent Work Completed: 50%
• Work Schedule is On Time
SAND PIT SITE – DEMOLITION
• Budget: $402,050
• Award Project: 9/15/20
15
LCW NO. 1 – EQUIPPING: TBD
• In design
• Pending results of drilling
SAND PIT – TEST WELL: TBD
• In design
• Pending completion of demo
La Brea Subarea Development Project Timeline
16