Upload
augustus-barker
View
214
Download
0
Embed Size (px)
Citation preview
Florida High Speed Rail Authority Update for
Orange County Board of County Commissioners
April 7, 2009
OUTLINE
Timelines and Federal Processes Florida’s Strong Position - Previous
HSR Work Approach for Florida Response to
Stimulus FDOT Participation
High Speed Rail on National Agenda
Competition for High Speed Rail start-up around the US
Federal Bills: October ’08 Bill: $1.5 billion over 5 yrs (not yet
appropriated)
Stimulus ’09 Bill: $8 billion added – 100% Federal Funding – no State match required (fully funded)
Future additional Bills anticipated due to national importance placed by Obama Administration
CORRIDORS COMPETING FOR BILLIONS OF $FEDERAL
Federal High Speed Rail Corridors*
Northeast Corridor California Corridor Empire (NY) Corridor Pacific Northwest
Corridor South Central
Corridor Gulf Coast Corridor
*others may emerge
Chicago Hub Network
Florida Corridor Keystone (PA)
Corridor Northern New
England Corridor Southeast Corridor
Florida’s Strong Position
Over the past 10 years…1998: Florida Overland eXpress
Tampa-Orlando-Miami environmental and engineering
2004: Florida High Speed Rail Authority PD&E for Tampa-Orlando Feasibility study for Orlando-Miami
Approximately $30 million invested in both these efforts
Review of Tampa-Orlando Corridor Two major components of FHSRA
work:
PD&E for Tampa-Orlando corridor
Procurement of Design-Build-Operate-Maintain & Finance vendor
NEPA Work Completed
FRA Record of Decision (ROD) completes NEPA ROD required to advance into Final Design
2001 2002 2003 2004 2005
FHSRA created
March ‘02: Notice of Intent
April ‘02: Advance Notification and Scoping
October ‘03: Draft EIS and Public Hearings
Impacts of DBOM&F proposals assessed
July ‘05FEIS signed by FRA and FHSRA
Project put on holdFEIS signedNo ROD issued
Design-Build-Operate-Maintain & Finance- DBOM&F RFP issued October 2002 Investment Grade Ridership Study Issued Nov
2002 Beachline (then Beeline) route:
Total riders: 2.4 to 2.8 million; Revenue: $39 -$42 mill Greeneway route:
Total riders: 3.8 to 4.1 million; Revenue: $54- $56 mill
Both proposing teams committed to covering Operations & Maintenance costs based on inclusion of the Choice and Captive markets
DBOM&F SUBMITTALS
FLUOR-BOMBARDIER Jet-Train Technology – Gas Turbine Double track Disney to OIA, single track to Tampa Firm Fixed price of $2.056 Billion
GLOBAL RAIL CONSORTIUM Electric TGV Technology Double track entire system Firm Fixed price of $2.4 Billion
F-B was ranked first on 6-2 vote Negotiations proceeded until August 2004
Orlando-Miami Feasibility – FHSRA 2002
Key Findings for Tampa-Orlando-Miami: Operating Ratios (2020)Will revenues from system cover O&M costs?
For 180+mph: Operating Revenue: $531 mill O&M Costs: $174 mill RATIO: 3.05
Benefit-Cost Ratios (30 year NPV)Do Benefits to Society for building this system
justify the costs? For 180+mph: RATIO 1.95
Conclusion:
Overall benefits of this system greatly exceed costs
APPROACH TO RESPONSE
Highlights of Proposed Response:Corridor: Tampa-Orlando-MiamiP3 Approach“Green” Technology Includes Stimulus component –
“shovel ready” CREATES JOBS!
Corridor Definition
Tampa-Orlando-Miami Corridor is logicalMuch work done on entire corridorEntire corridor is designated by FRAPhasing to logical intermediate stationsProvides 180+ mph capabilityReasonable total length (310 miles)
compared to other competing corridors: LA - San Francisco is almost 400 miles Boston - DC is 440 miles
Public Private Partnership
Private partner is critical for successLeases system for long termShares profits in excess of defined
thresholds A single system approach is logical
Single technologyOne set of standards that is interoperable
statewideWILL REQUIRE ASSUMPTION OF O&M
RISK BY PRIVATE PARTNER
Stimulus Approach
Sequence of work:Define Minimum Operating Segment (MOS)
with FRA within the Tampa-Orlando corridorObtain Record of Decision for MOSStart construction of MOS Incrementally add segments onContinue environmental work on next
segments GOAL: MOS can start construction in 18
months
Board Meeting of April 2
FDOT Letter of Assistance Offered to take over the application process for
stimulus funds to use in-house resources FHSRA accepted offer, with three requests:
$4 million federal funds available to FHSRA from 4 years ago - FDOT to report status in 2 weeks
FDOT to provide progress report at future meetings FHSRA requested that “institutional memory”
available be used
Sunrail: FHSRA passed a support resolution 4-1