Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Final ReportMarymount University 26th St Project Arlington, VA Spring 2010
2010
Benjamin Mahoney Construction Management
Consultant: Mr. James Faust
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 3
Table of Contents
1.0 Acknowledgements ............................................................................................................................. 6
2.0 Executive Summary ............................................................................................................................. 7
3.0 Project Overview ................................................................................................................................. 8
Project Summary ................................................................................................................................... 8
Client Information ................................................................................................................................. 9
Project Delivery System ...................................................................................................................... 10
Organizational Chart ........................................................................................................................... 11
Project Team ....................................................................................................................................... 12
Project Schedule Summary ................................................................................................................. 12
Local Conditions .................................................................................................................................. 15
4.0 Building Systems Summary ............................................................................................................... 18
5.0 Analysis I: Short Interval Production Schedule Development .......................................................... 23
Problem Statement ............................................................................................................................. 23
Proposed Solution ............................................................................................................................... 23
Solution Method ................................................................................................................................. 23
Resources ............................................................................................................................................ 24
Expected Outcome .............................................................................................................................. 24
Introduction to Short Interval Production Scheduling ........................................................................ 24
Project Constraints .............................................................................................................................. 26
SIP Schedule Development ................................................................................................................. 27
Cost & Schedule Impacts .................................................................................................................... 31
Conclusion & Recommendations ........................................................................................................ 31
6.0 Analysis II: MEP Coordination ........................................................................................................... 33
Problem Statement ............................................................................................................................. 33
Proposed Solution ............................................................................................................................... 33
Solution Method ................................................................................................................................. 34
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 4
Resources ............................................................................................................................................ 34
Expected Outcome .............................................................................................................................. 34
MEP Coordination Techniques ............................................................................................................ 35
General Contractor Survey ................................................................................................................. 36
MEP Coordination Survey Results ....................................................................................................... 37
Impacts on the Organization ............................................................................................................... 43
Impacts on the Project Team .............................................................................................................. 44
Conclusions & Recommendations ...................................................................................................... 44
7.0 Analysis III: Green Roof Design ......................................................................................................... 46
Problem Statement ............................................................................................................................. 46
Proposed Solution ............................................................................................................................... 46
Solution Method ................................................................................................................................. 46
Resources ............................................................................................................................................ 46
Expected Outcome .............................................................................................................................. 47
Introduction to Green Roofs ............................................................................................................... 47
Green Roof System ............................................................................................................................. 49
Green Roof Structural Analysis ........................................................................................................... 53
Structural Redesign ............................................................................................................................. 55
Green Roof Mechanical Analysis ......................................................................................................... 56
LEED Analysis ...................................................................................................................................... 59
Cost & Schedule Impacts .................................................................................................................... 61
Life Cycle Cost Analysis ....................................................................................................................... 64
Conclusions & Recommendations ...................................................................................................... 66
8.0 Master of Architectural Engineering Requirement ........................................................................... 67
9.0 Final Conclusions ............................................................................................................................... 68
10.0 Resources ........................................................................................................................................ 69
Appendix A: Critical Path Method Finish Schedule ................................................................................. 70
Appendix B: MEP Coordination Survey ................................................................................................... 72
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 5
Appendix C: Sika Sarnafil Product Data .................................................................................................. 75
Appendix D: Structural Hand Calculations .............................................................................................. 84
Appendix E: Detailed Structural System Estimate .................................................................................. 95
Appendix F: LEED NCv2.2 Credit Scorecard .......................................................................................... 111
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 6
1.0 Acknowledgements
Throughout the course of my Senior Thesis Project, I would like to personally thank all of the individuals that provided me with assistance along the way. Without their guidance and cooperation, I would not have been able to accomplish what I have over the past two semesters.
Dr. David RileyDr. Chris MagentDr. Kevin Parfitt
Mr. Robert HollandMr. Jim Faust
Mr. Craig Dubler
Mr. Erik KanieckiMr. Rami NatourMr. Aaron Galvin
Dr. Ralph KidderMr. Upen Malani
Dr. James Bundschuh
Ms. Bhavna Mistry Lee
Stranix Associates
Pennsylvania State University Faculty
James G. Davis Construction Corp.
Marymount University
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 7
2.0 Executive Summary
This report is intended to provide an in‐depth analysis of the background information relating to the Marymount University 26th Street Project. Areas of investigation include client information, project delivery system, project milestones, key project team members, existing conditions, and major building systems. In addition to the background information, three detailed analysis topics have been investigated.
The analysis topics that were performed during the competition of this senior thesis project include the development of a Short Interval Production Schedule, MEP coordination techniques, and the implementation of a green roof. All of the research topics have been chosen to revolve around the critical industry issue relating to increasing efficiencies.
Analysis I: The first analysis involves implementing Short Interval Production Scheduling into the interior finishes of the Residential Facility. The repetitive nature of the activities involved with this phase of the project provides a perfect opportunity to attempt to bring the efficiencies of the “manufacturing process” to the construction industry. The results of this analysis have determined that the duration for this particular activity could be reduced by ten working days. This shortened duration has the potential to generate a savings of $70,000 in general conditions costs.
Analysis II: The second analysis involves the investigation into the MEP coordination process. All of the MEP coordination on the Marymount University Project was done “traditionally” with two‐dimensional composite drawings. The rise of three‐dimensional coordination has introduced another option but has yet to become widely accepted. The acceptance of the 3D MEP coordination process will be evaluated through a survey of the General Contractor and their subcontractors. The results of this analysis reinforce the fact that the General Contractor is remaining at the forefront of technological advances within the AEC Industry. They have maintained this status through the creation of a new position within their organization that helps to ensure that the 3D MEP Coordination process is managed successfully.
Analysis III: The third analysis involves incorporating a green roof into the design of the facilities at Marymount University. This will require supplementary evaluations on both the structural and mechanical systems of the building. In addition to satisfying both of the structural and mechanical breadth requirements, Analysis III will serve as the M.A.E. requirement. Through the completion of this analysis, it has been determined that the university could potentially see an annual energy savings of $2,700, increase the durability of their roofing membrane, and improve their LEED status from Certified to Silver.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 8
3.0 Project Overview
Project Summary
The 26th Street Project is situated on 1.45 acres and will provide Marymount University with additional dormitory units, a new academic facility, and underground parking. The project site is located at the corner of 26th Street, Yorktown Boulevard, and Old Dominion Drive in Arlington, VA. The residential building will add 62 units, situated in four and five unit suite configurations. The academic building will provide state of the art scientific laboratory space, lecture halls, and office space for Marymount University personnel. The academic and residential buildings will be constructed on top of the four levels of underground parking and separated by outdoor gathering space.
Figure 1: Building Footprint
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 9
To complete the construction of the $42,000,000 facility, Marymount University contracted James G. Davis Construction Corporation as the General Contractor in April of 2008. Construction on the 267,000 square foot facility began in February of 2009 and is scheduled to commence in September of 2010.
Client Information
The owner of this project is Marymount University, a catholic university located in Arlington, VA. The university offers associate’s, bachelor’s, master’s, and doctoral degrees, undergraduate and graduate certification, and pre‐professional programs in teaching, law, medicine, and physical therapy. With the addition of the 26th Street Project, Marymount University hopes to attract world class students and faculty.
The 26th Street Project is the most significant construction effort that the university has undertaken in nearly four decades. The project addresses three main concerns that are held by the leaders of the university; expanding academic space, student housing, and parking.
Throughout the construction of this project, the university is very concerned with being an outstanding citizen and neighbor to the surrounding residential communities. Marymount University feels strongly about keeping the local community informed and responding in a timely manner to any issues that may arise affecting the community. In order to keep the lines of communication open at all times, the university has established a project web site with information regarding the project. The web site can be found at www.marymount.edu/26thstreetproject/.
Marymount University feels strongly that the project should be turned over on‐time and under budget. Time is an extremely critical issue as part of this project involves the construction of a new residential facility. If for whatever reason students cannot move in for the start of the fall 2010 semester, the students who are scheduled to move in will be without housing. If this were to occur, the students would be forced to reside in local hotels until the completion of the project.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 10
Project Delivery System
To initiate the Marymount University 26th Street Project, the university entered into an AIA B151, standard form of Agreement between themselves and the architect, Davis, Carter, Scott, LTD. The architect was tasked with contracting the rest of the design consultants that will be a part of the project team. Aiding the owner throughout the duration of the design and construction, Stranix Associates, was brought on as an Owner’s Representative at a fixed fee. Other key members of the project team include the constructors of the project. In this situation, James G. Davis Construction Corporation was awarded the preconstruction and construction services at a Guaranteed Maximum Price. The contractor holds an AIA 121 CMc, Standard Form between the Owner and the Construction Manager where the Construction Manager is the Constructor. As a General Contractor, James G. Davis is responsible for providing the General Liability Insurance, while the owner is responsible for providing the Builder’s Risk Insurance.
Marymount University has not previously undertaken a project of this magnitude and with the assistance of an Owner’s Representative, look to make the project a success. The inexperience of the owner and tight project schedule makes the selection of a General Contractor with a Guaranteed Maximum Price that most appropriate delivery method and contract type for this particular situation. In addition to the General Contractor, the university also has contracted with Construction Manager to act as an Owner’s Representative. The university also chose to hire an Owner’s Representative because of their ability to provide independent advice to the owner on both design and construction related issues.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 11
Organizational Chart
Figure 2: Marymount University 26th Street Project Team Organization Chart
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 12
Project Team
Figure 3: Marymount University Project Team
Project Schedule Summary
James G. Davis Construction Corporation is to be awarded the General Contracting responsibilities for the Marymount University 26th Street Project in April of 2008. This will provide the company with approximately 10 months to complete their preconstruction services. Services that include permit acquisition, procurement of materials, and completion of the Guaranteed Maximum Price contract.
Construction operations are scheduled to commence in February of 2009 when James G. Davis Construction is supplied with the Notice to Proceed from Marymount University. Mobilization of Davis field personnel as well as the Excavation/Demolition Contractor will follow directly after receiving the Notice to Proceed. Major construction activities that are to take place during this time include clearing of the existing parking, undergrounding of overhead utilities, installation of the excavation support system, and major excavation.
Owner: Marymount UniversityOwner's Representative/CM: Stranix Associates
General Contractor: James G. Davis Construction Corp.Architect: Davis, Carter, Scott LTD.
Structural Engineer: Structura, Inc.MEP Engineer: GHT LimitedCivil Engineer: VIKA
Landscape Architect: Lewis Scully GionetLEED Consultant: Sustainable Design Consulting
Cast‐In Place Concrete Subcontractor: Brothers Concrete Construction, Inc.Pre‐Cast Concrete Subcontractor: Arban & Carosi
Mechanical/Plumbing Subcontractor: Tyler Mechanical Contracting, Inc. Electrical Subcontractor: Power Design, Inc.
PROJECT TEAM
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 13
The major excavation/demolition activities are scheduled to kick‐off in May of 2009, placing all of the foundation‐to‐grade activities directly in line with the critical path. This work will involve forming, reinforcing, and pouring the concrete mat foundations, spread footings, foundation walls, shear walls, columns, and floor slabs. The remaining concrete superstructure will be separated into two towers once it reaches the elevation at grade. One tower will be an academic facility, while the other tower will be a residence hall. The structures of both towers are sequenced to be constructed at the same time and are to top‐out in October, 2009.
Both the academic facility and the residence hall will be enclosed with precast architectural concrete panels and aluminum framed windows. This enclosure system will provide the academic facility and the residence hall with a water tight status in December of 2009 and February of 2010, respectively.
The achievement of a water tight status will permit the start of the interior MEP rough‐in and interior finishes in both the academic facility and the residential units. The completion of satisfactory inspections will allow the Marymount University 26th Street Project to achieve its final milestone, substantial completion, in early September of 2010. This will allow Marymount University students and personnel to inhabit their new facilities.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 14
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 15
Local Conditions
The 26th Street Project is located at Marymount University in Arlington, Virginia. The project site is triangular in shape and bordered by Old Dominion Drive, 26th Street, and Yorktown Boulevard.
Figure 4: Aerial view of the Project Site (Davis, Carter, Scott, LTD.)
The campus of Marymount University is adjacent to numerous areas that are zoned for residential use. This has the potential to create some problems when dealing with the issue of construction parking. On‐site parking is not an option due to the congested nature of the site. On‐street parking is available; however, it is very limited. Also, a majority of on‐street parking spaces are for use by the residents and require a parking permit between the hours of 8:00 AM and 5:00 PM. As a solution to this problem, James G. Davis Construction will provide construction parking at a local shopping mall, Ballston. The mall is roughly two miles from the project site, so a shuttle will serve to transport workers to and from their personal vehicles. This will be the means of construction parking until the structure reaches a point where the below grade parking can be utilized.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 16
Marymount University is considered to be located within the Washington, DC metro area and the project’s construction methods fit into the local preferred methods of construction. A majority of buildings found within this area are constructed with reinforced concrete. This method is preferred in this area over steel structures as a direct result of the benefits they deliver. These benefits include larger floor‐to‐ceiling heights, elimination of fireproofing costs, and elimination of the construction involved in complex connections. The popularity of this construction method also supplies extensive amounts of experience to the field of contractors in the area.
The 1.45 acre site was examined by ECS Mid‐Atlantic, LLC in August of 2005. The scope of their work included drilling four test bores to explore the subsurface soil and ground water conditions. The subsurface soil conditions were determined to be sufficiently dense. This allowed the building to be supported by shallow foundations. Foundation systems that include conventional spread footings and mat foundations. When establishing the elevation of ground water, it was determined that the water table exists between 21’ and 25’ below the existing grade.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 18
4.0 Building Systems Summary
Figure 5: Building System Summary Table
Demolition
The site of the Marymount University 26th Street Project was previously utilized by the university as a surface parking lot. Before any excavation work could begin, all of the asphalt, debris, and vegetation needed to be cleared and grubbed from the 1.45 acre site.
The overall area of excavation is approximately 63,000 square feet and the depth of excavation ranges from 45’ to 25’ deep as a result of the slope of the existing site. Due to the depth of the excavation, roughly 80,000 CY of soils need to be hauled from the site by the excavation contractor. The excavated soils will be directly relocated to numerous other project sites in the Washington, D.C. metropolitan area.
Structural Steel Frame
There is no structural steel incorporated into the frame of the building.
CastinPlace Concrete
The entire superstructure, supporting foundation, and lateral systems consist of steel reinforced, cast‐in‐place concrete. The foundation is comprised of 34”‐54” mat foundations, found along the perimeter of the building, while 32”‐54” spread footings support the interior
YES NO Scope of WorkX Demolition Required
X Structural Steel FrameX Cast‐in‐Place ConcreteX Precast ConcreteX Mechanical SystemX Electrical SystemX MasonryX Curtain WallX Support of Execavation
Building System Summary
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 19
columns. These same columns will support the concrete slab above and any other loads found within their tributary area.
Different areas of the structure will be utilized for different types of occupancy; academic, residential, and storage/garage. Each of the corresponding slabs will have separate design specifications. The storage/garage slabs will have a monolithic thickness of 8” with 5½” drop panels at each of the columns. The residential and academic slabs will incorporate a post‐tensioning system to help manage the tensile loads. The residential slabs will have a monolithic thickness of 7” with 6” drop panel at the columns. Lastly, the slabs found in the academic space will have a monolithic thickness of 9” with 8” drop panels at the columns.
The lateral system consists of reinforced, cast‐in‐place concrete shear walls and grade beams. Concrete shear walls can be found the perimeter of the building and extend up through the four levels of underground parking. Additional lateral support is provided by walls of the four stairwells that span from the lowest garage level up to the roof level. The last component of the later system includes grade beams. The beams provide addition support and tie individual spread footings to each other and to the perimeter mat foundation.
All of the work involved with placing the cast‐in‐place concrete will be performed by Brothers Concrete Construction, Inc. Brothers will utilize the two tower cranes on site to place the concrete via crane and bucket. Brother will utilize the PERI® SKYDECK Aluminum Slab Formwork System for horizontal slabs and PERI® TRIO Panel Formwork for vertical walls and columns.
Figure 1. PERI®SKYDECK (www.peri.ca Figure 7: PERI SKYDECK (www.peri.ca) Figure 6: PERI TRIO (www.peri.ca)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 20
Precast Concrete
The entire exterior façade of the Marymount University 26th Street Project is to be comprised of precast architectural panels. The panels will be connected to the concrete structure with steel embeds. These embeds will be placed into the precast panels and into the edges of the concrete slab. The connections are designed to withstand gravity, lateral, and earthquake loads. The panels will be delivered to the site from an offsite casting plant that the installer, Arban and Carosi, Inc., utilizes. Once the panels arrive on site, they will be laid and set into place by one of the two tower cranes.
Mechanical System
The Mechanical system is comprised of an air‐water system containing both variable and constant volume rooftop air handling units. Along with the primary air that is supplied by the air handling units, the individual fan coil units are supplied with both chilled and hot water. The hot water is to be supplied from boilers found in the G3 Level Mechanical Room and the chilled water is to be supplied from pumps that are located within the G4 Level Mechanical Room. These fan coils units will provide individual control of heating and cooling to separate zones within the building. Also located on the roof, two 500 ton cooling towers help to dissipate the heat that is generated by the system.
Due to the different classes of occupancies of the building, the fire suppression system consists of both a wet and a dry pipe system. The wet pipe system will provide immediate fire suppression to each of the residential units while the dry pipe system services the rest of the building.
Electrical System
Marymount University is supplied with electrical service by Dominion Virginia Power, which services regions of both Virginia and North Carolina. The incoming service is to be stepped
down by a transformer located outside of the building and brought into the building with 3∅, 4
wire, 480/277V. The electrical system will also be accompanied with emergency power
supplied by a 350kW, 3∅, 4 wire, 480V, continuous power supply generator. The diesel
powered generator will be supplied from a 50‐gallon day tank and a 500‐gallon reserve tank.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 21
Masonry
The extent of masonry incorporated into the project at Marymount University is concrete masonry units (CMUs). The CMUs will serve as partition walls that provide a 2‐hour fire rated wall. The CMUs will be non‐load bearing and tie into the concrete structure with No. 5 steel reinforcing bars that are 48” high and spaced on 16” centers.
The mortar that will be used consists of Portland cement, hydrated lime, and aggregate. A mixing station will be located on site to mix the mortar with potable water as it is needed.
Curtain Wall
The curtain wall system found on this project is minimal as the façade is mainly constructed of architectural precast panels. The system consists of aluminum framed operable and non‐operable Low‐E Clear Vision Glass windows. The windows are located throughout the academic and residential facilities to allow daylight to penetrate into the space. Aluminum framed storefront doors are also found where the vestibules and entrances are located.
Support of Excavation
A sheering and shoring system will be utilized as the method of excavation support at Marymount University. The main components of this system include soldier piles, lagging boards, and tiebacks. The sheeting and shoring will not only serve to support the soils outside of the excavated area, but will also serve as one face of the formwork for the foundation walls.
The system will use a total of 132 soldier piles that are spaced approximately 8’ on center. The vibratory method will be the main means of installation. Once the piles contact bedrock and reach refusal, they will have to be impact‐driven to the proper design elevation.
The amount of excavation will require roughly 26,000 square feet of lagging boards, installed in lifts of roughly 10’, and 188 tie‐backs. Once a lift is completed, the tie‐backs, found at the soldier beams, can be drilled, installed, and grouted. The grout will need to cure for five days from the time of installation. After the five days expires, the tie‐backs will be tested for integrity by a third‐party testing agency. If the tie‐backs are found to meet or exceed the design criteria, excavation can continue below and the process repeats itself until the proper elevation at sub‐grade is reached.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 22
In an effort to keep the site as dry as possible, a dewatering system with 12 dewatering wells will be utilized. The water that is removed from the ground will be pumped into a sediment tank to allow the silt and any other debris to settle out before it is pumped off of the construction site.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 23
5.0 Analysis I: Short Interval Production Schedule Development
Problem Statement
One of the additions to the campus of Marymount University is a Residential Facility. The new facility will provide suite‐style housing for 239 students. There are 62 units situated in four and five person configurations. The interior finishes that are involved with the completion of the Residential Facility are extremely repetitive from unit to unit and from floor to floor.
This particular phase of the project is extremely important to both Marymount University and the entire project team. In order to generate the highest quality of work in the optimal amount of time, the interior finishes schedule will be required to be extremely consistent and predictable.
Proposed Solution
The repetitive nature of the work that is involved with the interior finishes in the residential facility provides an ideal location to implement Short Interval Production Scheduling (SIPS). This particular scheduling technique has traditionally been used in areas that are repetitive in nature.
Solution Method
1. Gain a full understanding of the original finishes schedule. 2. Identify the project milestones and interior finishes timeframe. 3. Establish each of the individual trades that are involved in the sequence. 4. Determine the specific trades that will be driving the critical path of the schedule. 5. Define specific activity durations and basic crew sizes for the specific trades that were
identified to be driving the schedule. 6. Establish the project specific sequence of work for a typical unit. 7. Determine the standardized work durations for all of the activities. 8. Ensure the resources are level to attain consistent work durations. 9. Develop the Short Interval Production Schedule.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 24
10. Compare the SIP schedule duration with the existing detailed CPM schedule. 11. Evaluate the cost implications of any changes in resources.
Resources
Critical Path Project Schedule Marymount University Project Manager and Project Superintendant RS Means Cost Data Penn State Architectural Engineering Faculty Members Contact from PACE Roundtable with previous SIPS experience AE 473: Building Construction Management & Control
Expected Outcome
The development of Short Interval Production Schedule will result in an overall reduction in the project schedule. The work associated with the finishes schedule is extremely repetitive, which in turn will lead to a more efficient workforce. The implementation of this scheduling technique will also help to optimize activity durations, while maintaining the highest quality of work.
The expected benefits of SIPS include optimizing activity durations, while maintaining the highest quality of work. Additionally, the schedule is much more predictable, which makes it easier to track and communicate the progress of the schedule.
Introduction to Short Interval Production Scheduling
Short Interval Production Scheduling (SIPS) is a scheduling technique that is traditionally utilized to construct buildings that involve an immense amount of repetitive activities. The most common applications include high rise office buildings, apartment buildings, and hotels. As previously mentioned, the Residential Facility at Marymount University is much like an apartment building, consisting of four and five person individual units. This particular type of scheduling brings an assembly line approach to the construction industry. This allows trades to increase their efficiency as they move throughout each zone of the building. Each individual trade will work on a given activity, complete the activity, and move to the next unit to repeat
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 25
that same activity. This helps to avoid “trade stacking” and creates a “parade of trades” that ensures that each space is not over loaded with laborers at any given time.
To begin the development of a SIP Schedule, the building must be broken down into sections or zones that involve manageable quantities of work. For the case of Marymount University, one zone is equivalent to one four‐person residential unit. Each unit consists of two bedrooms, each with two occupants, two full bathrooms, a full kitchen, and a common living space. The total square footage for a unit of this size is approximately 860 square feet. Please refer to Figure 8. for a schematic model of an individual unit that can be found in the Residential Facility.
Figure 8: Autodesk Revit Model of a Typical Residential Unit
The next step in the development of a SIP Schedule involves determining which activities will be driving the critical path of the finish schedule and the overall timeframe in which these activities must be completed. After all of these tasks have been accomplished, quantity take‐offs needed to be computed in order to determine the material totals that are present in each zone. The materials that were estimated include gypsum wall board, metal studs, vinyl composition tile, ceramic tile, interior paint, millwork, countertops, and casework. The
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 26
Autodesk Revit Model that is shown in Figure 7. was developed in order to compute the individual quantity take‐offs. Following the computation of quantity take‐offs, the project specific sequence of activities needed to be determined. This is critical, as all of the activities will have a start‐to‐finish relationship with each of their predecessors.
The final step in the process involved resource leveling. This entailed looking at each of the trades and either increasing or decreasing their crew size in an attempt to create an equivalent duration for each of the trades involved in the finish schedule. Resource leveling is as a common practice that helps to avoid “trade stacking”. In the construction industry, “trade stacking” is an issue that is generally accepted, but has the potential to harm production rates. A SIP Schedule will attempt to negate this risk by only allowing a limited quantity of workers in a specific zone, at any given time.
After all of the steps are completed for one individual zone, the results can be extrapolated throughout the remaining zones within the building. The finished product provides an alternative to the traditional Critical Path Method of scheduling and is known as a Short Interval Production Schedule.
Project Constraints
The interior finishes for the Residential Facility at Marymount University must be complete by September 2010, as students are scheduled to move in for the Fall 20101 Semester. The start of the interior finishes is dependent upon the “Building Dry” milestone, which is scheduled to occur on February, 19, 2010. This allows approximately 26 weeks to complete all of the activities involved with finishing each of the six levels of the Residential Facility.
Once the “Building Dry” milestone is achieved, the building should be free from any unwanted moisture and all of the interior work can be put into place without the risk of being damaged. The only activities that can take place before this milestone is achieved include framing interior walls, MEP rough‐ins, and in‐wall quality inspections. A detailed Critical Path Method Finish Schedule can be found in Appendix A.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 27
SIP Schedule Development
For the purposes of Marymount University, the SIP Schedule was generated for the finish activities for the G3 Level, which is one level above the lowest G4 Level, through the 3rd Level. Both the occupancy and the number of units vary from level to level. This ensured that the number of zones for each level would vary from floor to floor, as the zone determination is a function of occupancy. Figure 9. displays how the occupancy and number of zones changes from level to level within the Residential Facility.
As mentioned previously, the entire material estimate was determined with the use of an Autodesk Revit 3D Model. Only after the quantities were estimated could RSMeans be utilized to determine daily production rates and the corresponding crew sizes. In most cases, the crew sizes needed to be adjusted in order to achieve activity durations as close as possible to the others. For a SIP Schedule, this is necessary to ensure that each trade can continually move from zone to zone without interruption from the crew that was previously in that zone. Figure 10. displays all of the individual quantities that were estimated and the corresponding durations and crew sizes.
Figure 10: Material Take‐Offs
Line Number Material Material Description Quantity Unit Crew Mult.Daily Output
Total Duration
Matrix Duration
092900 Gypsum Board (Walls) 4' x 8' x 1/2" 5581.0 SF 2 4 775.0092900 Gypsum Board (Ceil.) 4' x 8' x 5/8" 456.0 SF 2 4 765.0054000 Lightweight Metal Studs 20 ga., 3 5/8", LW 1903.0 SF 1 10 175 1.09 2096519 Vinyl Composition Tile 12" x 12" x 1/16" 715.4 SF 1 Tilf. 1 500 1.43 2093000 Ceramic Tile 1' x 1' Tiles 118.6 SF D7 1 82 1.45 2099123 Paint Primer/Finish Coat 3806.0 SF 1 Pord. 3 650 1.95 20622133 Millwork Arch. Wood Moulding 250.0 LF 1 Carp. 1 2501236230 Countertops 24" P‐Lam. 13.2 LF 1 Carp. 2 301232231 Casework Manuf. Wood Casework 22.8 LF 2 Carp. 1 40
1.95
1.79
Quantity Take‐Offs
2
2
Level Zones OccupancyG3 5 26G2 7 36G1 7 36L1 9 42L2 12 53L3 12 53
Totals 52 246
Building Zones
Figure 9: Level Zones & Occupancy
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 28
Now that all of the zones and the activities have been identified, the project sequence for the entire building could be determined. The sequence and a legend for the SIP Schedule for the G3 Level through the 3rd Level is shown in Figure 11.
Figure 11: Sequence and Color Key
Number Color Critical Activity
1 Frame Metal Studs
2 Rough‐In MEP
3 Preform In Wall QC
4 Hang/Tape/Finish GWB
5 Prime Walls
6 Point‐Up Drywall
7 Paint Final Coat
8 Install Ceramic Tile
9 Install Plumbing Fixtures
10 Install Millwork & Countertops
11 Install VCT & Carpet
YEARWEEK
DATE
DAY M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F M T W R F
LEVELG3 Level ◊
Zone 1Zone 2Zone 3Zone 4Zone 5
G2 LevelZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 7
G1 LevelZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 7
1st LevelZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 7Zone 8Zone 9
2nd LevelZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 7Zone 8Zone 9Zone 10Zone 11Zone 12
3rd LevelZone 1Zone 2Zone 3Zone 4Zone 5Zone 6Zone 7Zone 8Zone 9Zone 10Zone 11Zone 12
23
Compe
tition Date ‐ 8
/2/2010
242010
27 28
Building Dry Milestone
3 4 5 6 7 8 9 10 11 21 22
6/28/2010
7/5/2010
6/7/2010
25 26
7/26/2010
8/2/2010
7/12/2010
7/19/2010
*Holiday ‐ Fourth of July
*Holiday ‐ Mem
orial D
ay
12 13 14 15 16
5/24/2010
5/31/2010
18 19 20
6/21/2010
6/14/2010
4/12/2010
4/19/2010
2/8/2010
2/15/2010
17
3/1/2010
3/8/2010
2/22/2010
4/5/2010
3/15/2010
3/22/2010
3/29/2010
4/26/2010
5/3/2010
5/10/2010
5/17/2010
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 31
Cost & Schedule Impacts
After completing the Short Interval Production Schedule, it was determined that this sequence of activities could be completed in 24 weeks. When comparing the SIP Schedule to the current Critical Path Schedule, it was calculated that the SIP Schedule would save 2 weeks. This would be equivalent to shortening the duration of this same sequence of activities by ten working days.
Conclusion & Recommendations
By implementing a Short Interval Production Schedule into the Residential Facilities Interior Finishes Schedule, the University would potentially be provided with a schedule that has a total duration which is two weeks shorter than their current schedule. The SIP Schedule will allow the work associated with the interior finishes begin in mid February, 2010 and commence in early August, 2010. The schedule acceleration is possible due to the repetitive nature of the work that is associated with the interior finish activities.
Through previous interactions with the Marymount University Project Team, it was established that two of their major concerns with the Interior Finishes Schedule involve maintaining the highest possible production rates through the entire duration of the interior finishes schedule, while never sacrificing quality. This scheduling technique proves to be a viable option to ensure that these two concerns are addressed.
The Short Interval Production Schedule not only serves as a technique to accelerate the schedule, but it also provides the Project Team with an additional two weeks of float. It may seem as though this amount of time may be insignificant, but it ensures that any unforeseen delays or stoppages of work will not affect the achievement of the Substantial Completion Milestone.
The Substantial Completion Milestone is extremely critical to both Marymount University and the Project Team, as students are scheduled to be moving into the Residence Hall in early September 2010. To ensure that the Project Team meets this milestone, the university has chosen to include a stringent liquidated damages clause into the contract with the General Contractor. The schedule acceleration that is provided by the SIP Schedule warrants that James G. Davis will avoid incurring the costs associated with the liquidated damages.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 32
In conclusion, the Short Interval Production Schedule has the potential to generate results that will be beneficial to Marymount University and the Project Team, alike. The potential benefits are outlined in Figure 12. below.
Figure 12: Results of a Short Interval Production Schedule
Result of SIP Schedule Benefit
Decrease the overall Project Schedule by 10 working Days.
Eliminating 2 Weeks of General Condition costs ($35,000/Week). This will generate a total savings of $70,000.
The total duration for the Interior Finish Schedule is reduced by nearly
8%.
A shorter activity duration will ensure that any unforeseen delays or stoppages of work will not affect the overall project
schedule.Potential to generate early project
completion.Ensures that any of the costs that are associated with the
Liquidated Damages are avoided.Repetitive nature of the work
associated with the interior finish activities optimizes durations.
Bringing an "assembly line approach" to the construction industry allows laborers to work at optimal levels of efficiency, while maintaining a high quality of work.
Schedule can be utilized as a tool that provides visual aid.
Creates a schedule that is much more predictable, easier to communicate and track the progress.
Short Interval Production Schedule Results
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 33
6.0 Analysis II: MEP Coordination
Problem Statement
As with most projects, the coordination of the mechanical, electrical, and plumbing systems are extremely problematic. This remains true for the coordination of the MEP systems at Marymount University. All of the equipment and components required extensive amount of coordination, both vertically and horizontally, to avoid clashes in the field. The MEP coordination was done traditionally by incorporating each of the individual trades into one drawing.
To help eliminate overlooking major conflicts within the MEP coordination process, the industry has begun to adopt the practice of three dimensional MEP coordination. This practice will help to increase the efficiency of MEP coordination meetings, increase the productivity in the field, and help to ensure the project remains on schedule. However, the project team and Marymount University chose to disregard this option.
Proposed Solution
Conduct interviews with the Marymount University Project Team to establish why this practice was not utilized on the project. The participants of the study will include the Project Manager, who was a major part of the MEP coordination process, Project Executive, and Vice President.
Figure 13:3D Model (www.mediacad.net)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 34
Additionally, other participants of the interview will include representatives from each of the major trades involved in the coordination process.
Solution Method
1. Acquire the Meeting Minutes from all of the MEP coordination meetings. 2. Obtain the MEP coordination drawings. 3. Model all of the components in a specific area of the building. 4. Identify the key subcontractors involved with MEP coordination. 5. Generate a questionnaire that will be distributed to some PSU AE faculty members to
test the questions. 6. After the test is complete, determine which questions will be included in the final
interview. 7. Interview the appropriate members of the project team. 8. Compile the results and establish any common themes. 9. Evaluate the cost and schedule impacts of 3D MEP coordination.
Resources
MEP Coordination Meeting Minutes MEP Coordination Drawings AE 473: Building Construction Management & Control Autodesk Revit & Autodesk Navisworks
Expected Outcome
The results of the survey should present some of the challenges and motives as to why this practice was not utilized on the project. Even though the participants are a small representative sample of the industry, it is felt that the results will provide a realistic sample of the industry. The positive cost and schedule impacts that are expected to be generated will provide the project team with a more efficient MEP coordination practice to consider in the future.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 35
MEP Coordination Techniques
Over the past few decades, the construction industry has been utilizing one method of coordinating the mechanical, electrical, and plumbing systems within a building. The “Traditional” Method, or 2D Coordination, involves compiling all of the individual trades’ drawings into one composite drawing, then reviewing the two‐dimensional drawings for clashes. This process has the potential to take an exorbitant amount of time and is far from perfect. The clashes that are missed in the coordination process have the potential to generate change orders and negatively impact the project schedule.
Technology within the Architecture, Engineering, and Construction Industry has created an alternative to this outdated form of clash detection. The alternative process, known as 3D MEP Coordination, involves utilizing three‐dimensional modeling software accompanied with clash detection software. This process has proven to be much more efficient, especially as building architecture continues to get increasingly sophisticated. Figure 14. and Figure 15. below displays how challenging it can be to identify clashes when utilizing two‐dimensional coordination.
Figure 14: 2D MEP Coordination ‐ Figure 15: 3D MEP Coordination ‐ Hershey Medical Center (PSU CIC) Hershey Medical Center (PSU CIC)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 36
The impacts of utilizing this type of MEP Coordination have both immediate and long term benefits. All of the impacts that are associated with 3D MEP Coordination are outline below.
Initial Benefits:
Efficient Coordination of a sophisticated MEP System. Provides a 3D Model that can be easily visualized.
Ensures that every member of the Project Team is one the same page. Tradesmen can see an area prior to installation.
Increased interaction between individual trades. All of the individual detailers interactively work in one large room.
Long‐Term Benefits:
3D Model can be utilized for digital fabrication of equipment. Evaluating problematic areas in 3D promotes increased productivity in the field. Decreasing the amount of clashes simultaneously decreases the total number of RFI’s and Change Orders.
The Owner is provided with a higher quality product. In the end, the Owner is provided with a physical model that will serve as a 3D As‐Built of the system.
Even with all of these enticing benefits, 3D MEP Coordination has yet to become a standard practice within the Construction Industry. As part of my research, I was looking to determine the reasons as to why this practice has yet to become “Industry Standard”, and more specifically, why the General Contractor is not utilizing it more frequently.
General Contractor Survey
To help understand why this has yet to become an “Industry Standard, a survey title “MEP Coordination” was disturbed to various professionals within James G. Davis Construction. The purpose of this survey was to collect information pertaining to the utilization of 3D MEP Coordination within the organization. The survey can be found in its entirety within Appendix B.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 37
MEP Coordination Survey Results
In total, ten total responses where gathered thorough the course of the survey. The diversity of the respondents ranged from entry‐level Project Engineers to Senior Vice Presidents. This was done purposefully in an attempt to establish if there are any differing opinions within the organization’s corporate ladder. To ensure that the participants of the survey were as honest as possible, the survey was designed to be anonymous. However, each participant was asked to provide their current position and total years of experience with the organization. This information can be found in Figure 16.
Figure 16: MEP Coordination Survey Participants
The first half of the survey was developed to encourage the participants to provide their personal opinions regarding traditional, two‐dimensional, MEP coordination, while the second half of the survey involved questions regarding 3D MEP Coordination. Through this section of the survey, the participants were asked to provide information regarding their basic knowledge of the 3D MEP Coordination process and various advantages/disadvantages of the 3D MEP Coordination Process.
When dealing with past Project Teams, the participants were first asked to provide the resources that feel are most involved with the 2D MEP Coordination process. An overwhelming majority responded that Project Managers are the most common participants involved with this particular process. Additionally, it was determined that a Foreman representing each of the
Num. Current PositionYears of
Experience1 Senior Project Manager 122 Project Engineer 33 Project Manager 134 Virtual Construction Manager 25 Project Engineer 46 Project Executive 117 Senior Vice President 328 Project Engineer 119 Project Executive 1210 Senior Vice President 19
Survey Participants
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 38
major contractors, along with a CAD Technician are commonly involved in the MEP Coordination Process. After analyzing the results, it was determined that this process is very exhaustive of resources and any delays in this process will waste both time and money of the multiple parties involved. A detailed response breakdown to this question can be found below in Figure 17.
Figure 17: MEP Coordination ‐ Resources
Following the question regarding the resources involved with the MEP Coordination Process, the participants were asked to provide their professional opinion on the turn‐around time they typically see with 2D composite drawings. Based off of the statistics gathered in Figure 18., it was determined that a majority of the participants feel that the average turn‐around time is roughly two to four weeks. However, it should be noted that this duration is highly dependent on the project size and complexity. Additional knowledge that was gained from this survey question includes ensuring that the project schedule is capable of accommodating the time for
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 39
this process to occur. It is critical that the composite MEP Coordination Drawings become “approved” in a reasonable amount of time. Additionally, any delays incurred by this process need to be accounted for within the overall project schedule.
Figure 18: MEP Coordination Turn‐Around Duration
The final question in the first half of the survey aimed at determining if a project’s budget has money allocated for the purposes of MEP Coordination. The outcome of this question wasn’t very informative as it resulted in a fifty‐fifty split. Those who answered “yes” to the question were then asked to provide an approximate budget value as a percentage of the overall project cost. The responses to this question were also fairly inconsistent; however, the value was generally less than 1.0%. The results of this question reinforce the fact that each Project Team within the organization has an individual way of establishing and maintaining their budget.
As mentioned above, the second half of the survey was intended to gauge the participant’s knowledge regarding 3D MEP Coordination practices. The first question of this section asked if the individuals were aware if any trades currently were using three‐dimensional modeling software to generate their specific components or equipment. The statistics in Figure 19.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 40
confirm that members within the organization are aware that multiple trades are beginning to model in 3D.
Figure 19: Trades Modeling in 3D
The basis for the next question of the survey was to establish reasons as to why 3D MEP coordination was not pursued on previous projects, from a Project Management standpoint. To answer this question, the participants were provided with four possible selections that included potential cost increase, additional time requirements, experience of project team members, and limited amount of resources. The resources include items such as computer software, computers, workspaces, etc. In addition to the four selections, the participants were also given the option to provide an alternative selection that was not listed.
The results of this survey question provide evidence that the members within the organization feel that a limited amount of resources has been a major contributor to not pursing 3D MEP Coordination on past projects. For a complete breakdown of this question, please refer to Figure 20.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 41
Figure 20: Reasons for not pursuing 3D MEP Coordination
In an attempt to establish trends involving individual trade participation, the participants were asked to identify which trades they feel would be most likely accept or reject the change to 3D MEP Coordination. Through the results of this question, it was determined that the Mechanical Contractor would be most likely to accept this change, while the Fire Protection Contractor would be most likely to resist this change. The results of this survey question can be found in Figure 21. and Figure 22.
Figure 21: Trades Most Likely to Accept the Change to 3D Coordination
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 42
Figure 22: Trades Most Likely to Resist the Change to 3D Coordination
One of the final questions of the survey asked the participants to cite specific examples of advantages and disadvantages of utilizing 3D MEP Coordination over traditional, 2D Coordination. This was an open ended question with no pre‐determined answers. However, there were common trends that continued to appear among all of the answers provided. Some of the common themes have been outlined below.
Advantages:
Reduces the possibility of major cost and schedule delays in the field because all of the major clashes have been resolved.
Allows for more materials to be pre‐fabricated, which provides a more efficient installation process.
The owner is provided with an accurate “As‐Built” Model. Model can be used as a visualization tool that provides contractors with a clearer understanding of space allocation.
Disadvantages:
More time is consumed up front to create an accurate model, which ultimately increases costs.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 43
At this time, not all trades have the capability of modeling in 3D. 3D Coordination process is very technical and requires training of inexperience team members.
The final question of the survey asked the participants if they felt that they were experienced enough to successfully lead the 3D MEP Coordination process on a future project. The results of this question yielded impressive results, as 80% of the participants feel that they can successfully lead the 3D MEP Coordination Process. An interesting fact about this statistic is that only one out of the ten participants has previously been on a project that utilized 3D Coordination. This reinforces the fact that the organization has been taking active measures to keep up with this form of technology.
Impacts on the Organization
After speaking with a representative from James G. Davis, it has been determined that the organization is currently beginning to utilize 3D MEP Coordination on projects of significant size. At this time, James G. Davis is coordinating three projects with the use of three‐dimensional modeling software.
Not only have they begun to utilize these new technologies, but they have also launched an educational program that is structured to provide their employees with the appropriate knowledge base to successfully manage this process. Currently, there are eleven employees within the organization that have completed this educational program. Once completed, these former Project Engineers, Assistant Superintendants, and Layout Engineers titles have changed to Integrated Construction Engineers (ICEs).
An Integrated Construction Engineer is becoming an integral part of a Project Team, as their main role has become guiding Project Teams throughout the 3D MEP Coordination Process. The position of an ICE has not been transformed into an overhead position, as they remain intact within Vice Presidential Groups and continue to be associated with specific projects.
For the Integrated Construction Engineer position to be successful, individuals at James G. Davis feels as though it is imperative that ICEs stem from various backgrounds. This is a result of the previous experience that was gained by the ICE’s in previous roles within the organization. Previous Project Engineers have knowledge in areas such as managing RFI’s and other aspects
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 44
of project management, while Assistant Superintendants and Layout Engineers are competent in managing contractors and verifying field installations.
Through the development of this employee training program, it is obvious that James G. Davis is committed to being at the forefront of technological advances within the AEC Industry.
Impacts on the Project Team
Within the organization’s development of the position of an Integrated Construction Engineer, it can be suggested that the Marymount University Project Team would have seen significant benefits from this newly created role. An ICE would have allowed the Project Team to utilize 3D MEP Coordination, which would have made this process much more efficient. Additional reasons supporting this assumption are summarized below.
Intricate MEP System required to support Laboratory Equipment Experienced Project Engineer managing the coordination process Sheet Metal Contractor & Mechanical Contractor have all components modeled in 3D. Tight Project Schedule
The entire Marymount University Project Team including the Project Management Personnel, the Field Supervision Staff, and the Contractors would have benefited from 3D MEP Coordination. The potential impacts on the Project Team have been outlined below.
The Project Management Personnel would have seen a reduction in the number of RFI’s and Change Orders.
The Field Supervision Staff would have been provided with a visual tool that could assist them in conveying information to the contractors they are managing.
The Contractors would have be provided with a higher level of confidence that their individual systems can be installed as coordinated, thus allowing a more streamlined and efficient installation process.
Conclusions & Recommendations
Through the results of the survey, it has been established that a large majority of James G. Davis employees have the appropriate knowledge base to successfully manage the 3D MEP Coordination Process. Employees are fully aware that the MEP Coordination process is very
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 45
exhaustive of both time and resources. Additionally, they are aware of the initial and downstream benefits that are associated with 3D MEP Coordination.
If a given Project Team feels strongly that their project would benefit from this technology, it is strongly recommended that they should seek assistance from an Integrated Construction Engineer or the Virtual Construction Manager. This would help to ensure that the 3D MEP Coordination process goes as fluid as possible. Other recommendations to Project Teams that wish to utilize 3D MEP Coordination on their projects have been outlined below.
To avoid delays within the project schedule, start the 3D process as soon as possible 3D Modeling should be incorporated into each trade’s scope of work A Building Information Modeling Trailer should be located on site General Contractor / Construction Manager should fully manage the Coordination Process
A clearly defined order to coordination should be established by the GC/CM If at all possible, the Designer / Engineer should be involved in the Coordination Process A Foreman from each trade involved in Coordination should be involved in resolving clashes
After analyzing the results of the survey and speaking to individuals within the organization, it is strongly believed that if the Marymount University 26th Street Project were to have been awarded to James G. Davis in April, 2010, as opposed to April 2008, 3D MEP Coordination most definitely would have been utilized. This is due to the fact that James G. Davis has made a serious commitment to keeping up with technology by developing their new role of an Integrated Construction Engineer.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 46
7.0 Analysis III: Green Roof Design Structural Breadth/Mechanical Breadth
Problem Statement
The implementation of a green roof will help further enforce the university’s commitment to sustainability. Altering the design of the current white, thermoplastic polyolefin (TPO), fully adhered, roofing membrane will generate additional LEED points in both the sustainable sites and energy categories of LEED New Construction Version 2.2.
Proposed Solution
Design a green roof that will help to increase the thermal efficiency of the building envelope, improve storm water management, and increase the durability of the roof. Additionally, these objectives will help Marymount University achieve LEED points.
Solution Method
1. Research various types to green roofs to determine which is the most appropriate. 2. Investigate all of the potential advantages and disadvantages of each type. 3. Select the most appropriate green roof for Marymount University. 4. Redesign the current concrete roof structure to meet the newly introduced loads of the
green roof. 5. Evaluate the thermal efficiencies and resize the mechanical equipment accordingly. 6. Determine which LEED New Construction Version 2.2 points have been achieved. 7. Assess the cost and schedule implications of a green roof addition.
Resources
Structural drawings for the roof White TPO roof product data Whole Building Design Guide (www.wbdg.org) AE 597D: Sustainable Building Methods AE 404: Building Structural Systems in Steel & Concrete
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 47
AE 310: Fundamental of HVAC
Expected Outcome
The addition of a green roof is expected to increase the thermal performance of the building’s envelope, thus reducing the loads on the HVAC system. However, this system will carry significant schedule impacts and most likely be more expensive than the specified white TPO roof. These negative cost and schedule impacts are anticipated to be offset by the extended lifecycle and increased thermal efficiencies of a green roof.
Introduction to Green Roofs
To begin the selection process of a green roof system for Marymount University’s 26th Street Project, the benefits of both intensive and extensive green roofs were thoroughly investigated. This was done to ensure that the university is receiving the highest quality alternative to their current white TPO roofing system.
Some of the benefits that the university would be looking to gain from this design change include notable energy savings, prolonged lifespan, as well as additional square footage of usable area. These three items are highly critical to the university as they are undertaking the construction of their new academic and residential facilities. Due to the occupancy of these two buildings, the university will expect them to be operational for nearly twenty four hours a day, seven days a week, for years to come.
Figure 23. displays the characteristics of the two different types of green roof systems that were analyzed.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 48
Figure 23: Types of Green Roofs (Sika Sarnafil)
As it is shown in Figure 24., extensive green roofs contain a much thinner soil medium, thus introduce minimal superimposed dead loads on the roof structure, require minimal maintenance, and cost less. However, this type of roofing system eliminates the potential for creating an inhabitable space and has lower levels of plant diversity. When evaluating an intensive green roof system, it can be seen in Figure 25. that they involve a much thicker soil medium which often ranges from six inches up to several feet thick. Due to the additional thickness of this system, it will introduce significant superimposed dead loads. However, it is capable of sustaining a wide variety of plant live, including shrubs and small trees.
Figure 24: Extensive Green Roof (Sika Sarnafil) Figure 25: Intensive Green Roof (Sika Sarnafil)
After evaluating all of the basic characteristics, the advantages of each system needed to be analyzed to ensure that the correct system was selected for the purposes of Marymount University. Figure 26. outlines the advantages of both extensive and intensive green roofs.
Characteristic Extensive IntensiveDepth of Growth Medium > 6" < 6"Accessibility Mostly Inaccessible Mainly AccessibleFully Saturated Weight 12 ‐ 35 lb/sf 50 ‐ 200 lb/sfPlant Diversity Low GreatestInstalled Cost $18 ‐ 20/sf < $20/sfMaintenance Minimal Highest
Types of Green Roofs
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 49
Figure 26: Advantages by Green Roof Type (Sika Sarnafil)
After analyzing all of the potential advantages and disadvantages of each type of green roof system, it was determined that an extensive green roof would be most appropriate for Marymount University.
The lightweight system will have minimal impact on the existing Post‐Tensioned roof deck.
The system will require no irrigation, as all of the vegetation will be indigenous to the area.
Any additional maintenance costs incurred by the green roof will be minimal and comparable to the existing roofing system.
The soil cover ensures that the underlying waterproofing membrane is not degraded by exposure to ultra‐violet light.
The growth media provides an additional insulating value, which has the potential to lower the buildings energy costs.
A thinner growth media depth is still capable of reducing stormwater run‐off by 50%.
Green Roof System
The green roof manufacturer that was selected to be most appropriate for this specific application was Sika Sarnafil, Inc. Sarnafil was chosen over their competitors due to their proven success on rooftops throughout Europe over the past three decades. As result of their
Extensive IntensiveLightweight Greater diversity of plant
Suitable for large areasBest insulation and storm water
managementLow maintenance costs and no irrigation required after fully
establishedGreater range of design
Suitable for retrofit projects Usually accessibleLower Capital Costs Greater variety of human usesEasier to replace Greater biodiversity potential
Green Roof Advantages
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 50
success, Sika Sarnafil’s products have migrated to the United States and their waterproofing system was selected to protect Chicago’s City Hall.
Figure 27. below visually displays all of the components of the Sarnafil green roof system. The system includes a waterproofing membrane, a drainage layer, a root barrier, an insulation layer, a filter fabric, growth media, and vegetation. The individual components of this particular system are defined below and the product data for each of the components can be found in Appendix C.
Figure 27: Extensive Green Roof Components (Sika Sarnafil)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 51
Sarnafil Waterproofing Membrane (Sarnafil G476):
The G476 waterproofing membrane is specially compounded for sub‐grade environments of constant dampness, high alkalinity, exposure to plant roots, fungi, and bacterial organisms, as well as varying levels of hydrostatic pressure including pounded water conditions. The membrane is highly dimensionally stable and fastened together at the seams with the use of heat welds.
Sarnafelt NWP Separation Layer:
Sarnafelt NWP separation layer is compatible with all Sarnafil membranes, and is typically used in Sika Sarnafil Waterproofing Systems. The Sarnafelt NWP separation layer acts as a barrier between the Sika Sarnafil waterproofing membrane and extruded polystyrene insulations which are un‐faced. In addition, installation of the NWP separation layer significantly increases the puncture resistance of the waterproofing assembly when installed between the waterproofing membrane and the protection layers.
Sarnatherm XPS Insulation
Sarnatherm XPS is a rigid extruded polystyrene insulation board. The insulation board is installed over the Sika Sarnafil waterproofing membrane. Also, the boards are available in tapered configurations to enhance drainage.
Sarnafil Drainage Panel (Panel 980):
The Panel 980 is a prefabricated panel designed for enhancing the performance of the Sika Sarnafil waterproofing system. The panels channel water away from the waterproofing relieving hydrostatic pressure build up. The multidimensional core provides a uniform flow path for water to escape. The interlocking and overlapping dimple and flange assembly capability ensure low continuity across panels. However, this component is not compatible with electronic leak detection systems.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 52
Growth Media:
The growth media will be approximately four inches in depth. The soil will need to be lightweight and are comprised of both inorganic and organic materials. The inorganic material will make up roughly 75% of the soil and consist mainly of expanded slate and crushed clay, while the organic material will make up the remaining 25% of the soil and consist mostly of humus and topsoil.
This type of soil will be able to support the growth of small flower and native grasses, both of which will require no additional irrigation to sustain life.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 53
Green Roof Structural Analysis
If Marymount University were to replace their current white TPO roofing system will a Sika Sarnafil Extensive green roof system, the roof structure will require to be reanalyzed. This is necessary to ensure that the structure is capable of withstanding the additional loads that are introduced by a green roof.
In order to begin this structural analysis, the loads associated with each of the components that make up the green roof system were required to be calculated. This was done for both the Academic and Residential Facilities due to their differing structural characteristics. The load calculations are shown for the Residential and Academic Facilities in Figures 28. and Figure 29., respectively.
Figure 28: Load Tabulation ‐ Residential Facility
Figure 29: Load Tabulation ‐ Academic Facility
Mark Density Total (lbs.) Total (psi)Growth Media 85.00 327618.33 28.333Separation Layer 0.03 38.54 0.003Drainage Pannel 60.00 115630.00 10.000XPS Insulation 1.80 6937.80 0.600Waterproofing Membrane 0.14 1618.82 0.140
40
TOTAL DEAD LOAD ‐ Residential Facility Green RoofArea (sf.) Area Comparison11563.00 0.3311563.00 1.0011563.00 0.17
TOTAL11563.00 1.0011563.00 0.33
Mark Density Total (lbs.) Total (psi)Growth Media 85.00 478720.00 28.333Separation Layer 0.03 56.32 0.003Drainage Pannel 60.00 168960.00 10.000XPS Insulation 1.80 10036.22 0.594Waterproofing Membrane 0.14 2365.44 0.140
40
TOTAL DEAD LOAD ‐ Academic Facility Green RoofArea (sf.) Area Comparison16896.00 0.3316896.00 1.00
TOTAL16896.00 1.00
16896.00 0.1716896.00 0.33
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 54
Currently, the roof structure for the entire facility consists of post‐tensioned, cast‐in‐place, structural slabs that are supported by reinforced concrete columns. The design criterion for each of the facilities is outlined below:
Academic Facility
Slab Thickness = 9” Live Loads = 30 PSF Snow Load = 20 PSF f’c = 5000 psi
Residential Facility
Slab Thickness = 7” Live Loads = 30 PSF Snow Load = 20 PSF f’c = 5000 psi
After all of the initial design specifications have been identified, the effects of the newly introduced loads of a green roof needed to be analyzed.
In order to begin the process of evaluating a two‐way post‐tensioned structure, a guide titled, “Time Saving Design Aid”, provided by the Portland Cement Association was utilized. All of the calculations follow methods presented in ACI 318‐05 and comply with IBC 2003. This is imperative as the entire Marymount University 26th Street Project was designed according to this edition of the International Building Code.
Now that the newly introduced loads from the green roof have been established, the remaining design criterion is listed below.
Loads:
• Framing Dead Load = self‐weight
• Superimposed Dead Load = 40 psf (Green Roof)
• Live Load = 30 psf ( Section 1607.0, 2003 IBC)
• Snow Load = 20 psf
• 2 hour fire‐rating
Materials:
• Concrete: Normal weight 150 pcf f’c = 5,000 psi
f’ci= 3,000 psi
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 55
• Rebar: fy = 60,000 psi
• PT: Un‐bonded Tendons ½” φ, 7‐wire strands, A = 0.153 in2 fpu = 270 ksi Estimated pre‐stress losses = 15 ksi (ACI 18.6) fse = 0.7*(270 ksi) – 15 ksi = 174 ksi (ACI 18.5.1) Peff = A*fse = (0.153 in
2)*(174 ksi) = 26.6 kips/tendon
Structural Redesign
All of the appropriate calculations associated with this analysis can be found in Appendix D. The results of these calculations determined that the 9” post‐tensioned roof slab for the Academic Facility was capable of withstanding the new introduced loads. However, the results also proved that the roof slab for the Residential Facility was inadequate and required a full redesign. This redesign involved increasing the thickness of the post‐tension roof slab, altering the steel reinforcing sizes and layout, and increasing the number of tendons within a typical bay. Figure 30. displays a typical bay and the corresponding reinforcing bar sizing and layout.
Figure 30: Typical Bay Size and Reinforcing Layout
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 56
In addition to altering the rebar sizing and layout, the thickness of the roof slab was also increased from 7” to 8”. Increasing thickness will ultimately require additional concrete in both the roof slab and all of the columns that span from the third level to the underside of the roof slab. The columns on this level needed to be extended by an extra inch in order to ensure that the floor to ceiling height remained consistent. The original design specifications have the elevation of the Roof Level set at 456.67’, while the elevation of the 3rd Level is set at 446.67’. This provides a floor‐to‐floor height of exactly 10’‐0”.
To ensure that the plenum space remains fully intact, the roof will be required to be raised by one inch. This will raise the elevation to 446.75’, which falls below limits set by the International Building Code, as well as the local code authorities. According to section 504.2 of the International Building Code, the building is permitted to have a total height of 160’‐0”, plus an additional 20’‐0” due to the fact that the building is fully sprinklered. However, Arlington County, the local code authority, has implemented a set of use conditions on the university, of which limits the total building height to 45’‐0”. Currently, the extents of the roof rise to an elevation that is 44’‐6” above the finished grade. That being said, extending the columns and raising the roof of the Residential Facility by one inch will ensure that the new building height still remains within the permissible limits set by the local code authorities.
Green Roof Mechanical Analysis
One of the major benefits of a green roof system is that it is capable of significantly improving the building’s energy efficiency. Their ability to reduce the overall heat transfer through the building’s envelope makes this possible. If the heat transfer can be reduced, the heating and cooling loads induced on the building can be reduced accordingly. In order to create a basis for comparison, the heat transfer through the existing roof was first calculated using the following equation:
∆
The first step of this analysis involves calculating the thermal transmittance (U Value) for the existing white TPO roof. The associated calculations can be seen in Figure 31.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 57
Figure 31: TPO Thermal Properties
The thermal properties for the green roof system are much more difficult to calculate due to their dynamic properties. The thermal performance will be consistently fluctuating with changes in both moisture content and temperature. As a solution to this problem, a study that was performed was performed at the National Research Center in Toronto, Canada was utilized as a reference. The study was set up to compare the thermal properties of a conventional roofing system to that of a green roof system. The findings of this two year study determined that a green roof is capable of reducing heat gain and heat loss by a total of 95% and 26%, respectively.
Figure 32: Yearly Heat Flux
Thickness (L)Total R‐Value U ‐ Value
in. °F*ft2*h/Btu Btu/°F*ft2*h
1 Outside Air Film ‐ 0.17 5.8822 TPO Membrane 0.06" 0.05 20.0003 Extruded Polystyrene Insulation 4" 20.00 0.0504 Concrete Slab 7" 0.70 1.4295 Inside Air Film ‐ 0.61 1.639
21.530 0.046
White TPO Roof Thermal Properties
Total
MaterialLayer
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 58
When calculating the data that can be found in Figure 32., conservative values for both heat gain and heat loss were utilized. A 70% reduction in heat gain and a 20% reduction in heat loss were utilized to perform the appropriate calculations.
Through the research at the National Research Center in Toronto, Canada, it was concluded that green roofs provide the best thermal performance in the warmer, summer months. This is at a time when the building is constantly being cooled to keep the building’s occupants at a comfortable temperature.
After evaluating the values in Figure 32., it was determined that the greatest energy savings will occur in July. The impacts of a green roof allow the average heat flux to drop by approximately 2 BTU/sq. ft. of roof area for the month of July.
Existing TPO Roof System: ∆
0.046°
11,550 16,900 77.5 ° 70 °
9,815
Extensive Green Roof System:
9,815 1 0.70
2,945
Total Savings:
9,815 2,945 /12,000
0.5725
Yearly Energy Savings:
28,450 1.9
24 365
473,521,800
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 59
Yearly Cost Savings:
$
, , $ .
,
(*Seasonal Energy Efficiency Ratio of 14 is required for an Energy Star rating.)
$ ,
LEED Analysis
Marymount University has opted to incorporate sustainable features into the 26th St Project. The project is striving to achieve a LEED® Certified rating and was designed according to LEED NCv2.2. Some of the major the major sustainable features of this project are listed below.
On‐site bicycle racks for residents and university employees Preferred parking for carpools, vanpools, and Zip Cars All plumbing fixtures will be “Low‐Flow” and consume 21% less water Building envelope, lighting, power, and HVAC systems have been designed according to ASHREA 90.1‐2004
CFC‐based refrigerants will not be utilized in the HVAC systems All building occupants will have access to on‐site storage receptacles for recyclable materials
At least 10% of products used during construction will contain recycled material At least 10% of the materials used during construction will be regionally located (extracted, processed & manufactured)
All paints, adhesives, sealants, and carpets have been specified to be low‐emitting
If Marymount University were to incorporate an extensive green roof into the design of their new facilities, they would eligible to potentially achieve a Silver Rating. Additional credits can be earned in each of the following categories;
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 60
Figure 33: Potential Credits Generated by a Green Roof
In total, a green roof is capable of generating a potential of twenty‐five LEED points. In combination will all of the other sustainable features that have been incorporated into the design of the facilities at Marymount University, the total project score would be 33. This would put the 26th Street Project at the lower limits of a LEED Silver rating, with 13 total points still possible. A completed LEED Scorecard can be found within Appendix F.
Credit Category Comment Direct Indirect
Credit 5.1Reduce Site Disturbance: Protect or Restore Open Spaces
Green roof with native or adapted vegetation will cover a minimum of 50% of the open space of the site.
X
Credit 6.1Stormwater Management: Rate and Quantity
Green roofs can reduce or eliminate the rate and quantity of storm water discharged from the site through direct absorption and storage of excess water.
X
Credit 7.2 Heat Island Effect: Roof50% of the total roof area will be covered by green roof
X
Credit 1.2Water Efficient Landscaping: No Potable Use or No Irrigation
All potable water will be eliminated for irrigation of the green roof and all associated landscape features.
X
Credit 2.0 Innovation Wastewater TechnologiesThe green roof will serve as an on‐site wastewater treatment media.
X
Credit 3.1 Water Use Reduction: 20% ReductionOne credit can be earned if potable water is reduced by 20%.
X
Credit 1.0Optimize Energy Performance: 28% New, 21% Existing
A green roof can contribute to enhanced energy performance of the building. Credits earned are based on % of reduction of energy costs. The total reduction of must equal 28% in order to achieve the 4 credits
X
Credit 4.1 Recycled Content
Most of the materials that make‐up the green roof contain recycled content. Materials with recycled content must constitute 5% to 10% of the total materials used.
X
Credit 5.1 Regional Materials10% of all building materials, based on total cost, must be produced with a 500 mile radius of the project location.
X
Credit 1.1Innovation in Design: Green Roof Design
Green roofs allow the designer to be innovative in the total building design.
X
Innovation & Design Process
Energy and Atmosphere
LEED & Green Roofs
Sustainable Sites
Water Efficiency
Materials and Resources
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 61
Cost & Schedule Impacts
In order to accurately determine the cost impacts of an intensive green roof system, cost data was obtained from the manufacturer, Sika Sarnafil. It was determined that the total cost of an extensive green roof system for a project of this size will have an installed cost of roughly $20.00/SF. The estimated cost that is shown in Figure 34. does not include additional costs associated with maintenance or up keeping of the green roof. However, this should be minimal and generally limited to routine seasonal maintenance.
Figure 34: Extensive Green Roof $/SF
The green roof redesign would cover approximately 16,900 square feet of the Academic Facility and roughly 11,550 square feet of the Residential Facility. Areas that are not affected by this redesign include stair towers, elevator shafts, and any other space that is being occupied by mechanical equipment.
A complete cost comparison of the two separate roofing systems can be found in Figure 35.
Figure 35: Cost Comparison ‐ Roofing Systems
In addition to the cost increase of the green roof materials, the costs of the structure also saw an increase. This increase in cost was a result of the additional labor and materials that were required to accommodate the new introduced loads of the green roof. The increase in material totals is outline below.
Component Cost/SFGreen Roof System (Membrane, Drainage Fabric, Filter Fabric, Growth Media)
$12.00
Installation Costs $8.00TOTAL $20.00
Sika Sarnafil Extensive Green Roof System
Roofing System Cost Comparison Sq. Feet $/SF Total CostExisting White TPO Roofing System 28,450 $11.00 $312,950.00Extensive Green Roof system 28,450 $20.00 $569,000.00
Roofing System Cost Comparison
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 62
An additional 36 cubic yards of concrete was required, this is roughly equivalent to a 0.25% increase.
An additional 15 tons of steel reinforcing bar was required, this is approximately a 2.0% increase.
The formwork totals netted an increase of 190 square feet of materials.
After all of the individual quantities were established from the structural drawings, RSMeans CostWorks software was utilized as a source for cost data. All of the data that was taken from RSMeans was appropriately adjusted for both location and time.
The estimated cost for the entire structural system came to $8,529,185. This includes the additional structural requirements that were required by introducing a green roof. This is equivalent to 20% of the total project cost. A detailed breakdown of material quantities and cost data can be found in Figure 37. Please refer to Appendix E for a detailed quantity take‐offs.
Also, the newly estimated value of $8,529,185 is only $140,000 greater than the originally estimated price for the structure. This results in a new building cost per square foot of $31.94, which is equivalent in a $0.52 increase. A complete cost comparison can be seen in Figure 36.
Description Total Cost Cost/SF% of Project
CostRSMeans + Quantity Take‐offs 8,389,288.31$ 31.42$ 20%Structure with Green Roof 8,529,185.33$ 31.94$ 20%
Green Roof Cost Comparison
Figure 36: Green Roof Structural Impacts
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 63
Figure 37: Total Cost for the Structural System
Description Quantity Unit Bare Material Bare LaborBare
EquipmentBare Total Total O &P Final O & P
Columns 67 Tons 1,550.00$ 950.00$ ‐$ 2,500.00$ 3,250.00$ 217,750.00$ Beams/Girders 32 Tons 1,550.00$ 890.00$ ‐$ 2,440.00$ 3,150.00$ 99,369.13$ Elevated Slabs 450 Tons 1,650.00$ 490.00$ ‐$ 2,140.00$ 2,605.00$ 1,172,250.00$ Spread Footings 186 Tons 1,400.00$ 395.00$ ‐$ 1,795.00$ 2,175.00$ 404,550.00$ Foundation/Shear Walls 183 Tons 1,475.00$ 1,340.00$ ‐$ 2,815.00$ 3,265.00$ 439,200.00$ Expoxy Coated Rebar 129 Tons 2,340.00$ $475.00 ‐$ 2,815.00$ 3,265.00$ 421,185.00$
2,754,304.13$
Beams/Girders (5000 psi) 347 CY 110.00$ 55.00$ 26.50$ 191.50$ 249.00$ 86,403.00$ Columns (5000 psi) 574 CY 110.00$ 61.50$ 30.00$ 201.50$ 262.00$ 150,388.00$ Elevated Slabs (5000 psi) 7193 CY 106.00$ 22.50$ 10.90$ 139.40$ 182.00$ 1,309,126.00$ Spread Footings (5000 psi) 737 CY 110.00$ 55.00$ 26.50$ 191.50$ 249.00$ 183,513.00$ Mat Foundations (5000 psi) 2410 CY 110.00$ 8.20$ 3.99$ 122.19$ 159.00$ 383,190.00$ Foundation/Shear Walls (4000 psi) 2196 CY 106.00$ 27.50$ 13.30$ 146.80$ 191.00$ 419,436.00$ Slab on Grade (4000 psi) 776 CY 106.00$ 55.00$ 26.50$ 187.50$ 244.00$ 189,344.00$
2,721,400.00$
Columns 39267 SFCA 0.15$ 0.79$ 5.65$ 6.44$ 9.62$ 377,748.54$ Elevated Slabs 265675 SFCA 0.09$ 1.55$ 3.43$ 4.98$ 7.01$ 1,862,384.34$ Foundation/Shear Walls 81144 SFCA 0.12$ 0.78$ 4.73$ 5.51$ 8.21$ 666,189.27$ Beams/Girders 14461 SFCA 0.12$ 0.90$ 4.73$ 5.63$ 8.34$ 120,608.34$ Mat Foundations 2944 SFCA 0.14$ 0.70$ 5.35$ 6.05$ 9.02$ 26,550.71$
3,053,481.20$
8,529,185.33$
FORMWORK
FORMWORK TOTAL
GRAND TOTAL
Total Cost for the Structural System (Green Roof)
REBAR
REBAR TOTALCONCRETE
CONCRETE TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 64
It can be seen in the proposed schedule below, that altering the roofing system will add seven days to the existing roof schedule. The total duration for this set of activities has been lengthened; however the overall construction schedule is not affected. In both scenarios, the Building Dry Milestone remains consistent. This is extremely important, as all of the interior finishes are depending on the achievement of this milestone.
Figure 38: Green Roof Schedule Impacts
Life Cycle Cost Analysis
As mentioned previously, the roofs of both facilities at Marymount University are specified to have white TPO roofing membranes. Through the literature provided by the manufacturer of this particular roofing membrane, it has been determined that the warranty period is 15 years. The warranty is limited because the roofing membrane will be fully‐adhered, thus unprotected from elements such as ultraviolet radiation and high wind speeds for extended periods of time.
Assuming that the university was to have incorporated a green roof into the design of their new facilities, they would have seen an increase in the durability of their roof’s waterproofing membrane. This is due to the fact that the growth media is capable of protecting the membrane from ultraviolet radiation, extreme winds, and temperature fluctuations, keeping it from prematurely degrading.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 65
The life cycle cost analysis in Figure 39. was performed to compare these two systems. The analysis includes initial costs, replacement costs, routine maintenance costs, and energy savings. The calculation of the energy savings was determined through a building enclosure study that can be found within the Mechanical Analysis.
Figure 39: Life Cycle Cost Analysis
From Figure 39., it can be seen that the green roof has a much higher initial cost associated with it. This is because the system is $9.00/SF greater than the currently specified system and requires additional structural requirements that total $140,000. However, around year 15, when the warranty period for the TPO roofing membrane expires, the roof will most likely need to be completely replaced. The spike at year 15 can be explained by the additional costs that are associated with replacing the entire roofing system. This is not the case with a green roof, as it is much more durable, lasting upwards of 50 years.
For the university to completely capitalize on their initial investment, they will have to wait approximately 30 years. This is not out of the question, as they look to utilize this building for decades to come.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 66
Conclusions & Recommendations
Through the completion of this analysis topic, it has been determined that implementing a green roof into the design of Marymount University 26th Street Project is viable alternative to a white, TPO Roofing system. An extensive green roof system does carry higher initial costs, but its durability proves to be a critical factor.
If Marymount University were to incorporate this change into the design of their roofing system, they would potentially see a $2,700 reduction in energy costs, yearly. Additionally, through a life cycle cost analysis comparing the two systems proved that the university would begin to see a return on their investment around year 30.
Financial incentives are not the only benefits that would be seen if the university opted for an extensive green roof. A green roof would provide a visual showcase that proves to faculty, students, university personnel, and community members that they are committed to improving the sustainability of their new facilities. Currently, the Marymount University 26th Street Project is slated to achieve a rating of LEED Certified. However, through the addition of an extensive green roof, they could easily achieve a rating of LEED Silver.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 67
8.0 Master of Architectural Engineering Requirement
Knowledge gained in 500‐Level Architectural Engineering classes has been displayed through the incorporation and design of a green roof in Analysis III. The addition of a green roof has proven to increase the building’s sustainability and significantly improve the thermal performance of the building’s envelope. The topic of sustainability was the main theme of AE 597D: Sustainable Building Construction, while AE 542: Building Enclosure Science and Design provided adequate knowledge involving building envelope systems, both of which are highly involved in the design of a green roof.
AE 597D: Sustainable Building Construction provided an understanding of sustainability concepts and green design principles as applied in the building construction industry. Through the completion of this course, the appropriate vocabulary and skills regarding sustainable methods of construction were developed. This course also provide an in‐depth background of the LEED rating system, which allowed the building’s current LEED Rating to be reanalyzed due to the sustainable impacts that are associated with a Green Roof.
AE 542: Building Enclosure Science and Design provided the knowledge regarding issues involving the building enclosures, science, and design.
The building enclosure: nature, importance, loadings Science: control of heat, moisture, air, hydrothermal analysis Design: walls, windows, roofs joints
This course is in the process of completion; however the topics of heat transfer and roofing systems have been covered thoroughly enough to select, design, and analyze the thermal characteristics of a green roof system.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 68
9.0 Final Conclusions Through the completion of the Marymount University 26th Street Project, the university feels strongly that the project should be completed on time and under budget. Additionally, the university has made it clear that they wish to utilize these facilities for decades to come. These factors alone provided opportunities to perform critical industry research, investigate value engineering ideas, provide constructability reviews, and look for ways to reduce the schedule. Through the completion of the analysis on Short Interval Production Scheduling, it has been determined that the Academic Facility at Marymount University would be a prime candidate for this scheduling technique, as it involves a series of repetitive activities. Throughout the completion of these activities, the contractors would be capable of maximizing their rates of production, while avoiding any sacrifices in quality. Additional factors that would have benefited the entire Project Team involve a schedule reduction of approximately ten working that generate a savings of $70,000 in general conditions costs. This would not only provide a savings to the owner, but it would also ensure that the project is turned over on time.
The conclusion of the analysis involving MEP Coordination Methods reinforces the fact that 3D MEP Coordination is becoming increasingly popular within the construction industry. The General Contractor, James G. Davis, has acknowledged this trend with the development of a new position within their organization. Once properly educated, Integrated Construction Engineers (ICEs), are supplied with the proper knowledge to successfully manage the 3D MEP Coordination process. Overall, it can be concluded that the Project Team, as well as the university, would have benefited significantly from this newly created role and the utilization of 3D MEP Coordination.
Through the completion of the research that was performed in the green roof analysis, it has been determined that an extensive green roof will provide the university with a roofing system that is more energy efficient and much more durable. The green roof would carry higher initial costs, but through a life cycle cost analysis, the cost was proven to be offset by its durability. Additionally, the university would reinforce their public commitment to sustainability, as their LEED rating would increase from Certified to Silver.
Over the completion of these three analysis topics, it has been determined that the results have the potential to increase efficiencies in multiple aspects of the project. In all, the university will be provided with more efficient and predictable project schedule, a more efficient method of MEP Coordination, and a more efficient roofing system. When combined, all three analysis topics have the ability to present the university with a high quality product that they can occupy for years to come.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 69
10.0 Resources
(2009, August). Retrieved August 26, 2009, from Official Site of Arlington County Virginia: http://www.arlingtonva.us
Behr, R. A. (2010). Building Enlcosure Science and Design. State College.
Kibert, C. J. (2008). Sustaniable Construction. Hooken: John Wiley & Sons, Inc. .
Marymount University. (2009, August). Marymount University‐26th St Project. Retrieved August 26, 2009, from http://www.marymount.edu/26thstreetproject/
National Institute of Building Sciences. (2010). Extensive Green Roofs. Retrieved March 1, 2010, from Whole Building Design Guide: http://www.wbdg.org/resources/greenroofs.php
Portland Cement Association. (2010). Time Saving Design Aids. Two‐Way Post‐Tensioned Design .
PSU Computer Integrated Construction. (2006). Penn State CIC Program. Retrieved March 22, 2010, from Computer Integrated Construction: http://www.engr.psu.edu/ae/cic/
RSMeans. (2010). Online Cost Estimating. Retrieved February 12, 2010, from RSMeans CostWorks: http://meanscostworks.com/
Sika Sarnafil. (2010). Green Roof Design Guide.
Sika Sarnafil. (2006). Green Roof Systems. Retrieved March 1, 2010, from Sika Sarnafil: http://www.sarnafilus.com/index/roofing/systems_rs/roofing‐sarnafil/green_roof_rs.htm
Stein, B., Reynolds, J. S., Grondzik, W. T., & Kwok, A. G. (2006). Mechanical and Electrical Equipment for Buildings. Hoboken, New Jersey: John Wiley and Sons.
SurveyMonkey. (2010). Free Online Survey Software & Questionnaire Tool. Retrieved March 1, 2010, from SurveyMonkey: http://www.surveymonkey.com/
U.S. Department of Energy. (2010). Department of Energy. Retrieved March 1, 2010, from http://www.energy.gov/
U.S. Green Building Council. (2010). USGBC: U.S. Green Building Council. Retrieved March 1, 2010, from http://www.usgbc.org/
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 70
Appendix A: Critical Path Method Finish Schedule
ID Task Name Duration Start Finish
1 G3 LEVEL 66 days Thu 1/28/10 Thu 4/29/102 Frame Walls 10 days Thu 1/28/10 Wed 2/10/103 Rough-In MEP 11 days Thu 2/11/10 Thu 2/25/104 In Wall QC 8 days Fri 2/26/10 Tue 3/9/105 Building Dry Milestone 0 days Fri 2/19/10 Fri 2/19/106 Hang/Tape/Finish GWB 10 days Wed 3/10/10 Tue 3/23/107 Prime Walls 3 days Wed 3/24/10 Fri 3/26/108 Point-Up Drywall 3 days Mon 3/29/10 Wed 3/31/109 Paint Final Coat 5 days Thu 4/1/10 Wed 4/7/10
10 Install Ceramic Tile 4 days Thu 4/8/10 Tue 4/13/1011 Install Plumbing Fixtures 3 days Wed 4/14/10 Fri 4/16/1012 Install Millwork & Countertops 4 days Mon 4/19/10 Thu 4/22/1013 Install VCT & Carpet 5 days Fri 4/23/10 Thu 4/29/1014 G2 Level 66 days Thu 2/11/10 Thu 5/13/1015 Frame Walls 10 days Thu 2/11/10 Wed 2/24/1016 Rough-In MEP 11 days Thu 2/25/10 Thu 3/11/1017 In Wall QC 8 days Fri 3/12/10 Tue 3/23/1018 Hang/Tape/Finish GWB 10 days Wed 3/24/10 Tue 4/6/1019 Prime Walls 3 days Wed 4/7/10 Fri 4/9/1020 Point-Up Drywall 3 days Mon 4/12/10 Wed 4/14/1021 Paint Final Coat 5 days Thu 4/15/10 Wed 4/21/1022 Install Ceramic Tile 4 days Thu 4/22/10 Tue 4/27/1023 Install Plumbing Fixtures 3 days Wed 4/28/10 Fri 4/30/1024 Install Millwork & Countertops 4 days Mon 5/3/10 Thu 5/6/1025 Install VCT & Carpet 5 days Fri 5/7/10 Thu 5/13/1026 G1 Level 66 days Thu 2/25/10 Thu 5/27/1027 Frame Walls 10 days Thu 2/25/10 Wed 3/10/1028 Rough-In MEP 11 days Thu 3/11/10 Thu 3/25/1029 In Wall QC 8 days Fri 3/26/10 Tue 4/6/1030 Hang/Tape/Finish GWB 10 days Wed 4/7/10 Tue 4/20/1031 Prime Walls 3 days Wed 4/21/10 Fri 4/23/1032 Point-Up Drywall 3 days Mon 4/26/10 Wed 4/28/1033 Paint Final Coat 5 days Thu 4/29/10 Wed 5/5/1034 Install Ceramic Tile 4 days Thu 5/6/10 Tue 5/11/1035 Install Plumbing Fixtures 3 days Wed 5/12/10 Fri 5/14/1036 Install Millwork & Countertops 4 days Mon 5/17/10 Thu 5/20/1037 Install VCT & Carpet 5 days Fri 5/21/10 Thu 5/27/1038 Level 1 66 days Thu 3/11/10 Thu 6/10/1039 Frame Walls 10 days Thu 3/11/10 Wed 3/24/1040 Rough-In MEP 11 days Thu 3/25/10 Thu 4/8/1041 In Wall QC 8 days Fri 4/9/10 Tue 4/20/1042 Hang/Tape/Finish GWB 10 days Wed 4/21/10 Tue 5/4/1043 Prime Walls 3 days Wed 5/5/10 Fri 5/7/1044 Point-Up Drywall 3 days Mon 5/10/10 Wed 5/12/1045 Paint Final Coat 5 days Thu 5/13/10 Wed 5/19/1046 Install Ceramic Tile 4 days Thu 5/20/10 Tue 5/25/1047 Install Plumbing Fixtures 3 days Wed 5/26/10 Fri 5/28/1048 Install Millwork & Countertops 4 days Mon 5/31/10 Thu 6/3/1049 Install VCT & Carpet 5 days Fri 6/4/10 Thu 6/10/1050 Level 2 90 days Thu 3/25/10 Wed 7/28/1051 Frame Walls 14 days Thu 3/25/10 Tue 4/13/1052 Rough-In MEP 15 days Wed 4/14/10 Tue 5/4/1053 In Wall QC 11 days Wed 5/5/10 Wed 5/19/1054 Hang/Tape/Finish GWB 14 days Thu 5/20/10 Tue 6/8/1055 Prime Walls 4 days Wed 6/9/10 Mon 6/14/1056 Point-Up Drywall 4 days Tue 6/15/10 Fri 6/18/1057 Paint Final Coat 7 days Mon 6/21/10 Tue 6/29/1058 Install Ceramic Tile 6 days Wed 6/30/10 Wed 7/7/1059 Install Plumbing Fixtures 4 days Thu 7/8/10 Tue 7/13/1060 Install Millwork & Countertops 6 days Wed 7/14/10 Wed 7/21/1061 Install VCT & Carpet 5 days Thu 7/22/10 Wed 7/28/1062 Level 3 90 days Wed 4/14/10 Tue 8/17/1063 Frame Walls 14 days Wed 4/14/10 Mon 5/3/1064 Rough-In MEP 15 days Tue 5/4/10 Mon 5/24/1065 In Wall QC 11 days Tue 5/25/10 Tue 6/8/1066 Hang/Tape/Finish GWB 14 days Wed 6/9/10 Mon 6/28/1067 Prime Walls 4 days Tue 6/29/10 Fri 7/2/1068 Point-Up Drywall 4 days Mon 7/5/10 Thu 7/8/1069 Paint Final Coat 7 days Fri 7/9/10 Mon 7/19/1070 Install Ceramic Tile 6 days Tue 7/20/10 Tue 7/27/1071 Install Plumbing Fixtures 4 days Wed 7/28/10 Mon 8/2/1072 Install Millwork & Countertops 6 days Tue 8/3/10 Tue 8/10/1073 Install VCT & Carpet 5 days Wed 8/11/10 Tue 8/17/10
2/19
1/17 1/24 1/31 2/7 2/14 2/21 2/28 3/7 3/14 3/21 3/28 4/4 4/11 4/18 4/25 5/2 5/9 5/16 5/23 5/30 6/6 6/13 6/20 6/27 7/4 7/11 7/18 7/25 8/1 8/8 8/15 8/22February March April May June July August
Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline
Marymount UniversityDetailed Finish Schedule
Page 1
Project: Davis Finish ScheduleDate: Tue 3/16/10
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 72
Appendix B: MEP Coordination Survey
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 73
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 74
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 75
Appendix C: Sika Sarnafil Product Data
Product Data Sheet Edition: 5/2009Version no.: 0006
Drainage Panel 980
Overview: Drainage Panel 980 is a high quality prefabricated composite panel designed to provide continuous free flow of water in applications with soil overburden such as green roofs, landscaped plazas and planters. The drainage panel has a three dimensional high impact polymeric core and woven geotextile fabric that provides better filtration of small soil particles. Water passes freely into the drain core, where it is gravity fed to the drain or to discharge.
Composition: Panel 980 is composed of a high impact resistant polymeric core and wo-ven geotextile fabric. The panel is available in rolls 4 ft wide and 50 ft long (1.2 m x 15.2 m).
Features: Panel 980 is a prefabricated panel designed for enhancing the performance of the Sika Sarnafil waterproofing system. The panel channels water away from the waterproofing relieving hydrostatic pressure build up. The multidimensional core provides a uniform flow path for water to escape. The interlocking and overlapping dimple and flange assembly capability ensures flow continuity across panels. It is not compatible with electronic leak detection systems.
Packaging: Panel 980 is packaged individually in polyethylene bags weighing 45 lbs (20.4 kg) each.
Installation: Panel 980 is installed by an authorized Sika Sarnafil Waterproofing Applica-tor. The drainage panel is loosely laid over the completed waterproofing system. Panels are interlocked or snapped together to form one continu-ous layer of material. Consult with Sika Sarnafil Extensive and Intensive Green Roof Waterproofing Specifications for further information.
Availability: Panel 980 is available directly from Sika Sarnafil Authorized Applicators when used within a Sika Sarnafil Waterproofing System. Contact Sika Sar-nafil or visit our website www.sikacorp.com for further information.
Warranty: As a Sika Sarnafil-supplied accessory, Drainage Panel 980 is included in Sika Sarnafil’s Standard or System Warranty.
Technical: Sika Sarnafil provides technical support. Technical staff is available to advise applicators as to the proper installation method.
Technical Data (as manufactured): ASTM Core Test Method Value Compressive Strength D 1621 21,000 psf (1,005 kN/m2)Thickness D 5199 0.40 in (10.2 mm)Flow D 4716 21 gpm/ft2 W (260 lpm/m2 W)FabricFlow D 4491 95 gpm/ft2 (3,866 lpm/m2)Puncture D 4833 130 lbs (0.58 kN)Apparent Opening Size D 4751 80 US Sieve (EOS) (0.18 mm)Grab Tensile D 4632 205 lbs (0.92 kN)
Drainage Panel 980 requires no maintenance.Maintenance:
Information contained herein is offered solely for the customer’s consideration, inves-tigation and verification. Determination of suitability for use is the sole responsibility of the user.
Corporate OfficeSika SarnafilA Division of Sika Corporation100 Dan RoadCanton, MA 02021
Tel.: (781) 828-5400 1-800-451-2504Fax: (781) 828-5365Web: www.sikacorp.com Email: [email protected]
Canada OfficeSika Sarnafil A Business Unit of Sika Canada6820 Davand Drive Mississauga, ON L5T 1J5
Tel.: (905) 670-2222 1-800-268-0479Fax: (905) 670-5278Web: www.sika.ca
Disclaimer: The information, and, in particular, the recommendation relating to the application and end-use of Sika Sarnafil products, are given in good faith based on Sika Sarnafil’s current knowledge and experience of the products when properly stored, handled and applied under normal conditions in accordance with Sika Sarnafil recommendations. In practice, the differences in materials, substrates and actual site conditions are such that no war-ranty in respect of merchantability of fitness for a particular purpose, nor any liability arising out of any legal relationship whatsoever, may be inferred from this information. The user of the product must determine the product’s suitability for the intended application and purpose. Sika Sarnafil reserves the right to change the properties of its products. The proprietary rights of third parties must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be supplied on request.
Product Data Sheet Edition: 8/2009Version no.: 0006
Sarnafelt NWPSeparation Layer
Overview: Sarnafelt NWP separation layer is a high quality geotextile fabric of non-wo-ven polypropylene. Sarnafelt NWP separation layer is installed between the waterproofing membrane and the extruded polystyrene (XPS) insulation. It can also be used between the waterproofing membrane and protection layers. It is intended to act as separation between products and also to increase the puncture resistance of the waterproofing assembly.
Composition: The Sarnafelt NWP separation layer is a 9 oz/yd2 (305 g/m2) geotextile fabric composed of 100% recycled polypropylene fibers tightly knit together. The tight needle punch produces a fabric which is highly resistant to punc-ture. The polypropylene is naturally resistant to most chemicals, and is particularly resistant to high alkaline exposure. It is available in a roll 90 in (2.3 m) wide and 135 ft (41.1 m) long.
Features: Sarnafelt NWP separation layer is compatible with all Sarnafil membranes, and is typically used in Sika Sarnafil Waterproofing Systems. Consult with these specifications. The Sarnafelt NWP separation layer acts as a barrier between the Sika Sarnafil waterproofing membrane and extruded polysty-rene insulations which are unfaced. In addition, installation of the NWP separation layer significantly increases the puncture resistance of the wa-terproofing assembly when installed between the waterproofing membrane and the protection layers.
Packaging: The NWP separation layer rolls are wrapped in a protective film and weigh 75 lbs (34 kg).
Installation: Sarnafelt NWP separation layer is installed by an authorized Sika Sarnafil Waterproofing Applicator. The NWP separation layer is typically loose-laid and lapped 4 in (102 mm) over the previous roll.
Availability: Sarnafelt NWP separation layer is available directly from Sika Sarnafil Authorized Applicators when used within a Sika Sarnafil Waterproofing System. Contact Sika Sarnafil or visit our website www.sikacorp.com for further information.
Warranty: As a Sika Sarnafil-supplied accessory, Sarnafelt NWP is included in Sika Sarnafil’s Standard or System Warranty..
Technical: Sika Sarnafil provides technical support. Technical staff is available to advise applicators as to the proper installation method.
Maintenance: Sarnafelt NWP requires no maintenance.
Technical Data (as manufactured): ASTM Typical PhysicalParameters Test Method PropertiesWeight D 3776 9 oz/yd2 (305 g/m2)Fiber Type 100% recycled polypropylene nonwoven, needle punchedThickness D 1777 0.160 in (4.1 mm)Burst Strength D 3786 315 lbs (1400 N)Tensile Strength D 5034 70 M.D./140 C.M.D.
Recycled Content Up to 90% Post-Consumer/Up to 20% Post-Industrial
Corporate OfficeSika SarnafilA Division of Sika Corporation100 Dan RoadCanton, MA 02021
Tel.: (781) 828-5400 1-800-451-2504Fax: (781) 828-5365Web: www.sikacorp.com Email: [email protected]
Canada OfficeSika Sarnafil A Business Unit of Sika Canada6820 Davand Drive Mississauga, ON L5T 1J5
Tel.: (905) 670-2222 1-800-268-0479Fax: (905) 670-5278Web: www.sika.ca
Disclaimer: The information, and, in particular, the recommendation relating to the application and end-use of Sika Sarnafil products, are given in good faith based on Sika Sarnafil’s current knowledge and experience of the products when properly stored, handled and applied under normal conditions in accordance with Sika Sarnafil recommendations. In practice, the differences in materials, substrates and actual site conditions are such that no war-ranty in respect of merchantability of fitness for a particular purpose, nor any liability arising out of any legal relationship whatsoever, may be inferred from this information. The user of the product must determine the product’s suitability for the intended application and purpose. Sika Sarnafil reserves the right to change the properties of its products. The proprietary rights of third parties must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be supplied on request.
Product Data Sheet Edition: 5/2009Version no.: 0006
Sarnafil® G476 Waterproofing Membrane
Overview: Sarnafil G476 waterproofing membrane is a heat-weldable thermoplastic waterproofing and flashing membrane formulated with an integral fiberglass mat carrier sheet for dimensional stability.
G476 is used in horizontal applications receiving overburden such as plaza decks, green roofs, planters, balconies, terraces and split slab applica-tions. G476 membrane and flashings must be covered and can not be left permanently exposed.
G476 waterproofing membrane is produced in a variety of lengths and a width of 6.56 ft (2 m).
Composition: G476 is a high quality product containing PVC resin, pigments, stabilizers, biocide and fiberglass carrier sheet. The standard color is orange and the underside is dark gray.
Features: G476 waterproofing membrane is specially compounded for sub-grade environments of constant dampness, high alkalinity, exposure to plant roots, fungi, and bacterial organisms, as well as varying levels of hydrostaticpressure including ponded water conditions. G476 is highly dimensionally stable.
The seams are heat welded providing the most secure seaming method available and will not deteriorate even in the presence of moisture, roots or under stress. G476 is available in 60 mil (1.5 mm), 80 mil (2.0 mm) and 96 mil (2.4 mm) thicknesses.
Packaging: G476 rolls are 6.56 ft (2 m) wide wrapped in a protective film and strapped to a wood pallet. Individual rolls weigh between 134-168 lbs (61-71 kg) depending on thickness and roll length.
Installation: G476 is installed by an authorized Sika Sarnafil Waterproofing Applicator. The membrane is used as the primary waterproofing sheet and concealed flashing membrane with Sika Sarnafil Waterproofing Systems and Green Roofs. Consult with these specifications and your local Sika Sarnafil repre-sentative.
Availability: Sarnafil G476 is available from an authorized Sika Sarnafil Waterproofing Applicator. Contact Sika Sarnafil or visit our website www.sikacorp.com for further information.
Technical: Sika Sarnafil provides technical support. Technical staff is available to advise applicators as to the proper installation method.
Technical Data (as manufactured): ASTM TypicalParameters Test Method Physical Properties Reinforcing Material -- FiberglassOverall Thickness(1), min. D638 (see note 1)Tensile Strength, min., psi (MPa) D638 1600 (11.1)Elongation at Break, min. D638 240% M.D. 240% C.M.D.Seam Strength(2), min., D638 90 (% of tensile strength)Retention of Properties D3045 -- After Heat Aging Tensile Strength, min., D638 95 (% of original) Elongation, min., D638 95 (% of original)Tearing Resistance, min., lbf (N) D1004 21.3 (94.7)Low Temperature Bend, D2136 Pass -40°F (-40°C)Linear Dimensional Change D1204 0.002%Weight Change After D570 2.0% Immersion in WaterStatic Puncture Resistance, D5602 Pass 56 lbf (250 N)Dynamic Puncture Resistance, D5635 Pass 117.7 ft-pdl (5 J)
(1)Typical Physical Properties data is applicable for 0.048 in. (1.2 mm) membrane thickness and greater. (2)Failure occurs through membrane rupture not seam failure.
Corporate OfficeSika SarnafilA Division of Sika Corporation100 Dan RoadCanton, MA 02021
Tel.: (781) 828-5400 1-800-451-2504Fax: (781) 828-5365Web: www.sikacorp.com Email: [email protected]
Canada OfficeSika Sarnafil A Business Unit of Sika Canada6820 Davand Drive Mississauga, ON L5T 1J5
Tel.: (905) 670-2222 1-800-268-0479Fax: (905) 670-5278Web: www.sika.ca
Disclaimer: The information, and, in particular, the recommendation relating to the application and end-use of Sika Sarnafil products, are given in good faith based on Sika Sarnafil’s current knowledge and experience of the products when properly stored, handled and applied under normal conditions in accordance with Sika Sarnafil recommendations. In practice, the differences in materials, substrates and actual site conditions are such that no war-ranty in respect of merchantability of fitness for a particular purpose, nor any liability arising out of any legal relationship whatsoever, may be inferred from this information. The user of the product must determine the product’s suitability for the intended application and purpose. Sika Sarnafil reserves the right to change the properties of its products. The proprietary rights of third parties must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be supplied on request.
Sarnafil G476 requires no maintenance. Although the membrane is typi-cally not easily accessible, regular standard maintenance of plaza decks and green roofs should include regular inspection of drains and termination sealants at least twice per year and after each storm.
Maintenance:
Upon successful completion of the waterproofing system application, a SikaSarnafil warranty may be available. Consult with your Sika SarnafilRegional Office for further information.
Warranty:
Product Data Sheet Edition: 5/2009Version no.: 0004
Sarnatherm XPS Insulation
Overview: Sarnatherm XPS is a rigid extruded polystyrene insulation board.Sarnatherm XPS is installed either under or over the Sika Sarnafil water-proofing membrane depending on the waterproofing system design.Always place a separation layer such as Sarnafelt NWP between the Sar-natherm XPS and the warterproofing membrane.
Composition: The core of Sarnatherm XPS is extruded polystyrene closed-cell foam. The core has continuous skin surfaces on the face and back surfaces. Sarnatherm XPS is available in various sizes depending upon the thermal resistance requirements and application.
Features: Sarnatherm XPS is also available in tapered configurations to enhance drainage.
Packaging: Sarnatherm XPS is provided in labeled bundles that are wrapped in a pro-tective polyethylene film. The amount of Sarnatherm per bundle varies with board thickness.
Installation: Sarnatherm XPS is typically loose-laid on the substrate or over the water-proofing membrane. Overburden is utilized to hold the insulation in place. During installation in hot, sunny weather, protect the insulation with a white covering to prevent excessive heat build-up and potential warping of the insulation boards.
Availability: Sarnatherm XPS is available directly from Sika Sarnafil Authorized Applica-tors when used within a Sika Sarnafil Roofing or Waterproofing System. Contact Sika Sarnafil or visit our website www.sikacorp.com for further
Warranty: As a Sika Sarnafil-supplied accessory, Sarnatherm XPS is included in Sika Sarnafil’s Standard or System Warranty.
Maintenance: Sarnatherm XPS requires no maintenance. Areas of frequent traffic may require protection from damage.
Technical: Sika Sarnafil provides technical support. Technical staff is available toadvise applicators as to the proper installation method.
Technical Data (as manufactured): Thermal Values Nominal Thickness R-Value C-Value 1.0 inch (25 mm) 5.0 0.200 1.5 inch (38 mm) 7.5 0.133 2.0 inch (51 mm) 10.0 0.100 2.5 inch (64 mm) 12.5 0.080 3.0 inch (76 mm) 15.0 0.067 4.0 inch (102 mm) 20.0 0.050 (not all available thicknesses are listed)
(1) Properties shown are representative values for 1in (25 mm) thick material based upon most recent product quality audit data. (2) Value at yield or 5% whichever occurs first. (3) Water vapor permeance varies with product type and thickness. Values are based on the desiccant method and they apply to insulation 1 in (25 mm) or greater in thickness (4) This numerical flame spread rating is not intended to reflect hazards presented by this or any other material under actual fire conditions.
ASTM Property(1) Test Method 400 600 1000 Thermal Resistance, per in (25 mm), @ 75°F (24°C) mean temp., ft².h.°F/Btu C 518, C177 5.0 (.88) 5.0 (.88) 5.0 (.88) (m².°C/W), R-value (RSI), min. Compressive Strength, psi (kPa), min. (2) D 1621 40 (275) 60 (415) 100 (690) Flexural Strength, psi (kPa), min. C 203 60 (480) 75 (585) 100 (585) Water Absorption, % by volume, max. C 272 0.1 0.1 0.1 Water Vapor Permeance,perms (ng/Pa.s.m²) (3) E 96 0.8 (35) 0.8 (35) 0.8 (35) Maximum Use Temperature, °F (°C) -- 165 (74) 165 (74) 165 (74) Coefficient of Linear Thermal Expansion, D 696 3.5 x 10-5 3.5 x 10-5 3.5 x 10-5
in/in.°F (mm/m.°C) (6.3 x 10-2) (6.3 x 10-2) (6.3 x 10-2) Flame Spread(4) E 84 5 5 5 Smoke Developed E 84 165 165 165 Complies with ASTM C 578, Type -- VI VII V Complies with CAN/ULC S701, Type -- 4 4 4
Corporate OfficeSika SarnafilA Division of Sika Corporation100 Dan RoadCanton, MA 02021
Tel.: (781) 828-5400 1-800-451-2504Fax: (781) 828-5365Web: www.sikacorp.com Email: [email protected]
Canada OfficeSika Sarnafil A Business Unit of Sika Canada6820 Davand Drive Mississauga, ON L5T 1J5
Tel.: (905) 670-2222 1-800-268-0479Fax: (905) 670-5278Web: www.sika.ca
Disclaimer: The information, and, in particular, the recommendation relating to the application and end-use of Sika Sarnafil products, are given in good faith based on Sika Sarnafil’s current knowledge and experience of the products when properly stored, handled and applied under normal conditions in accordance with Sika Sarnafil recommendations. In practice, the differences in materials, substrates and actual site conditions are such that no war-ranty in respect of merchantability of fitness for a particular purpose, nor any liability arising out of any legal relationship whatsoever, may be inferred from this information. The user of the product must determine the product’s suitability for the intended application and purpose. Sika Sarnafil reserves the right to change the properties of its products. The proprietary rights of third parties must be observed. All orders are accepted subject to our current terms of sale and delivery. Users must always refer to the most recent issue of the local Product Data Sheet for the product concerned, copies of which will be supplied on request.
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 84
Appendix D: Structural Hand Calculations
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 85
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 86
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 87
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 88
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 89
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 90
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 91
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 92
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 93
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 94
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 95
Appendix E: Detailed Structural System Estimate
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 96
Mark Length (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYF80 8.00 8.00 2.67 170.67 2.00 341.33 12.64F85 8.50 8.50 2.67 192.67 4.00 770.67 28.54F90 9.00 9.00 2.83 229.50 9.00 2065.50 76.50F95 9.50 9.50 3.00 270.75 3.00 812.25 30.08F100 10.00 10.00 3.17 316.67 8.00 2533.33 93.83F105 10.50 10.50 3.33 367.50 9.00 3307.50 122.50F110 11.00 11.00 3.50 423.50 2.00 847.00 31.37F115 11.50 11.50 3.50 462.88 1.00 462.88 17.14
412.61
Mark Length (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYCF01 27.00 12.00 3.67 1188.00 4.00 4752.00 176.00CF03 16.00 13.00 4.00 832.00 1.00 832.00 30.81CF04 14.50 11.00 3.50 558.25 2.00 1116.50 41.35CF05 12.50 8.00 2.17 216.67 1.00 216.67 8.02CF06 18.00 9.00 2.83 459.00 4.00 1836.00 68.00
324.19
Mark Length (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CY‐ 132.00 4.00 1.50 792.00 1.00 792.00 29.33‐ 31.00 2.00 1.00 62.00 1.00 62.00 2.30‐ 129.00 3.00 1.50 580.50 1.00 580.50 21.50‐ 162.00 1.50 1.50 364.50 1.00 364.50 13.50
66.63
Mark Depth (ft.) Volume (cu. Ft.) Quantity Total Total CY24" 2.00 516.00 1.00 516.00 19.1134" 2.83 1691.87 1.00 1691.87 62.6642" 3.50 1184.26 1.00 1184.26 43.8654" 4.50 61655.63 1.00 61655.63 2283.54
2409.18
TOTAL
TOTAL
TOTAL
TOTAL
258
Square Foundations (Concrete)
Combined Foundations (Concrete)
Grade Beams (Concrete)
Mat Foundations (Concrete)Area (sf)
597.13338.3613701.25
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 97
Mark Height (ft.) Lenght (ft.) Width (ft.) Volume (cu. Ft.) Quantity Total Total CY101 9.00 2.00 1.33 23.94 6.00 143.64 5.32102 9.00 2.00 1.33 23.94 6.00 143.64 5.32103 9.00 2.00 1.33 23.94 6.00 143.64 5.32104 9.00 2.00 1.33 23.94 6.00 143.64 5.32105 9.00 2.00 1.33 23.94 6.00 143.64 5.32106 9.00 2.00 1.33 23.94 6.00 143.64 5.32107 9.00 2.00 1.33 23.94 6.00 143.64 5.32108 9.00 2.00 1.33 23.94 6.00 143.64 5.32109 9.00 2.00 1.33 23.94 6.00 143.64 5.32110 9.00 2.33 1.17 24.50 3.00 73.50 2.72111 9.00 2.00 1.33 23.94 6.00 143.64 5.32112 9.00 2.00 1.33 23.94 6.00 143.64 5.32113 9.00 2.00 1.33 23.94 6.00 143.64 5.32114 9.00 2.00 1.33 23.94 6.00 143.64 5.32115 9.00 2.00 1.33 23.94 6.00 143.64 5.32117 9.00 2.00 1.33 23.94 6.00 143.64 5.32118 9.00 2.00 1.33 23.94 6.00 143.64 5.32119 9.00 2.00 1.33 23.94 6.00 143.64 5.32120 9.00 2.00 1.33 23.94 6.00 143.64 5.32121 9.00 2.00 1.33 23.94 6.00 143.64 5.32122 9.00 2.00 1.33 23.94 6.00 143.64 5.32123 9.00 2.00 1.00 18.00 3.00 54.00 2.00124 9.00 2.00 1.33 23.94 6.00 143.64 5.32125 9.00 2.00 1.33 23.94 6.00 143.64 5.32126 9.00 2.33 1.17 24.50 6.00 147.00 5.44127 9.00 2.33 1.17 24.50 6.00 147.00 5.44128 9.00 2.33 1.17 24.50 6.00 147.00 5.44129 9.00 2.33 1.17 24.50 6.00 147.00 5.44130 9.00 2.00 1.33 23.94 6.00 143.64 5.32131 9.00 2.33 1.17 24.53 6.00 147.21 5.45132 9.00 2.33 1.17 24.53 6.00 147.21 5.45133 9.00 2.33 1.17 24.53 6.00 147.21 5.45134 9.00 2.00 1.33 23.94 6.00 143.64 5.32135 9.00 2.00 1.33 23.94 6.00 143.64 5.32136 9.00 2.00 1.33 23.94 6.00 143.64 5.32137 9.00 2.00 1.33 23.94 6.00 143.64 5.32138 9.00 2.33 1.17 24.53 6.00 147.21 5.45139 9.00 2.33 1.17 24.53 6.00 147.21 5.45140 9.00 2.33 1.17 24.53 6.00 147.21 5.45141 9.00 2.33 1.17 24.53 6.00 147.21 5.45142 9.00 2.33 1.17 24.53 6.00 147.21 5.45143 9.00 2.33 1.17 24.53 6.00 147.21 5.45144 9.00 2.33 1.17 24.53 6.00 147.21 5.45145 9.00 2.33 1.17 24.53 6.00 147.21 5.45146 9.00 2.33 1.17 24.53 6.00 147.21 5.45147 9.00 2.33 1.17 24.53 6.00 147.21 5.45148 9.00 2.33 1.17 24.53 6.00 147.21 5.45149 9.00 2.33 1.17 24.53 6.00 147.21 5.45150 9.00 2.00 1.33 23.94 6.00 143.64 5.32
257.24
Residential Columns (Concrete)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 98
Mark Height (ft.) Lenght (ft.) Width (ft.) Volume (cu. Ft.) Quantity Total Total CY101 9.083 2.00 1.33 24.16 1.00 24.16 0.89102 9.083 2.00 1.33 24.16 1.00 24.16 0.89103 9.083 2.00 1.33 24.16 1.00 24.16 0.89104 9.083 2.00 1.33 24.16 1.00 24.16 0.89105 9.083 2.00 1.33 24.16 1.00 24.16 0.89106 9.083 2.00 1.33 24.16 1.00 24.16 0.89107 9.083 2.00 1.33 24.16 1.00 24.16 0.89108 9.083 2.00 1.33 24.16 1.00 24.16 0.89109 9.083 2.00 1.33 24.16 1.00 24.16 0.89110 9.083 2.33 1.17 24.73 1.00 24.73 0.92111 9.083 2.00 1.33 24.16 1.00 24.16 0.89112 9.083 2.00 1.33 24.16 1.00 24.16 0.89113 9.083 2.00 1.33 24.16 1.00 24.16 0.89114 9.083 2.00 1.33 24.16 1.00 24.16 0.89115 9.083 2.00 1.33 24.16 1.00 24.16 0.89117 9.083 2.00 1.33 24.16 1.00 24.16 0.89118 9.083 2.00 1.33 24.16 1.00 24.16 0.89119 9.083 2.00 1.33 24.16 1.00 24.16 0.89120 9.083 2.00 1.33 24.16 1.00 24.16 0.89121 9.083 2.00 1.33 24.16 1.00 24.16 0.89122 9.083 2.00 1.33 24.16 1.00 24.16 0.89123 9.083 2.00 1.00 18.17 1.00 18.17 0.67124 9.083 2.00 1.33 24.16 1.00 24.16 0.89125 9.083 2.00 1.33 24.16 1.00 24.16 0.89126 9.083 2.33 1.17 24.73 1.00 24.73 0.92127 9.083 2.33 1.17 24.73 1.00 24.73 0.92128 9.083 2.33 1.17 24.73 1.00 24.73 0.92129 9.083 2.33 1.17 24.73 1.00 24.73 0.92130 9.083 2.00 1.33 24.16 1.00 24.16 0.89131 9.083 2.33 1.17 24.76 1.00 24.76 0.92132 9.083 2.33 1.17 24.76 1.00 24.76 0.92133 9.083 2.33 1.17 24.76 1.00 24.76 0.92134 9.083 2.00 1.33 24.16 1.00 24.16 0.89135 9.083 2.00 1.33 24.16 1.00 24.16 0.89136 9.083 2.00 1.33 24.16 1.00 24.16 0.89137 9.083 2.00 1.33 24.16 1.00 24.16 0.89138 9.083 2.33 1.17 24.76 1.00 24.76 0.92139 9.083 2.33 1.17 24.76 1.00 24.76 0.92140 9.083 2.33 1.17 24.76 1.00 24.76 0.92141 9.083 2.33 1.17 24.76 1.00 24.76 0.92142 9.083 2.33 1.17 24.76 1.00 24.76 0.92143 9.083 2.33 1.17 24.76 1.00 24.76 0.92144 9.083 2.33 1.17 24.76 1.00 24.76 0.92145 9.083 2.33 1.17 24.76 1.00 24.76 0.92146 9.083 2.33 1.17 24.76 1.00 24.76 0.92147 9.083 2.33 1.17 24.76 1.00 24.76 0.92148 9.083 2.33 1.17 24.76 1.00 24.76 0.92149 9.083 2.33 1.17 24.76 1.00 24.76 0.92150 9.083 2.00 1.33 24.16 1.00 24.16 0.89
44.06
Residential Columns (Concrete)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 99
Mark Height (ft.) Lenght (ft.) Width (ft.) Volume (cu. Ft.) Quantity Total Total CY201 9.00 2.00 1.33 23.94 4.00 95.76 3.55202 9.00 2.00 1.33 23.94 4.00 95.76 3.55203 9.00 2.00 1.33 23.94 7.00 167.58 6.21204 9.00 2.00 1.33 23.94 7.00 167.58 6.21205 9.00 2.00 1.33 23.94 7.00 167.58 6.21206 9.00 2.00 1.33 23.94 4.00 95.76 3.55207 9.00 2.00 1.33 23.94 4.00 95.76 3.55208 9.00 2.00 1.33 23.94 7.00 167.58 6.21209 9.00 2.00 1.33 23.94 7.00 167.58 6.21210 9.00 2.00 1.33 23.94 7.00 167.58 6.21211 9.00 2.00 1.33 23.94 7.00 167.58 6.21212 9.00 2.00 1.33 23.94 7.00 167.58 6.21213 9.00 2.00 1.33 23.94 7.00 167.58 6.21214 9.00 2.00 1.33 23.94 7.00 167.58 6.21215 9.00 2.00 1.33 23.94 7.00 167.58 6.21216 9.00 2.00 1.33 23.94 7.00 167.58 6.21217 9.00 2.00 1.33 23.94 7.00 167.58 6.21218 9.00 2.00 1.33 23.94 7.00 167.58 6.21219 9.00 2.00 1.33 23.94 3.00 71.82 2.66219 9.00 28.26 4.00 113.04 4.19220 9.00 2.00 1.33 23.94 7.00 167.58 6.21221 9.00 2.00 1.33 23.94 7.00 167.58 6.21222 9.00 2.00 1.33 23.94 7.00 167.58 6.21223 9.00 2.00 1.33 23.94 4.00 95.76 3.55224 9.00 2.00 1.33 23.94 7.00 167.58 6.21225 9.00 2.00 1.33 23.94 7.00 167.58 6.21226 9.00 2.00 1.33 23.94 7.00 167.58 6.21227 9.00 2.00 1.33 23.94 7.00 167.58 6.21228 9.00 2.33 1.17 24.53 7.00 171.74 6.36229 9.00 2.00 1.33 23.94 7.00 167.58 6.21230 9.00 2.00 1.33 23.94 7.00 167.58 6.21231 9.00 2.00 1.33 23.94 7.00 167.58 6.21232 9.00 2.00 1.33 23.94 4.00 95.76 3.55233 9.00 2.00 1.33 23.94 7.00 167.58 6.21234 9.00 2.00 1.33 23.94 4.00 95.76 3.55235 9.00 2.33 1.17 24.53 7.00 171.74 6.36236 9.00 2.33 1.17 24.53 7.00 171.74 6.36237 9.00 2.33 1.17 24.53 6.00 147.21 5.45238 9.00 2.33 1.17 24.53 6.00 147.21 5.45239 9.00 2.33 1.17 24.53 6.00 147.21 5.45240 9.00 2.33 1.17 24.53 7.00 171.74 6.36241 9.00 2.33 1.17 24.53 7.00 171.74 6.36242 9.00 2.00 1.33 23.94 4.00 95.76 3.55243 9.00 1.50 1.50 20.25 4.00 81.00 3.00244 9.00 1.50 1.50 20.25 4.00 81.00 3.00245 9.00 1.50 1.50 20.25 4.00 81.00 3.00246 9.00 1.50 1.50 20.25 4.00 81.00 3.00247 9.00 2.00 1.33 23.94 3.00 71.82 2.66248 9.00 2.00 1.33 23.94 4.00 95.76 3.55249 9.00 2.00 1.33 23.94 4.00 95.76 3.55250 9.00 2.00 1.00 18.00 3.00 54.00 2.00251 9.00 2.00 1.00 18.00 3.00 54.00 2.00252 9.00 2.00 1.00 18.00 3.00 54.00 2.00253 9.00 2.00 1.00 18.00 3.00 54.00 2.00254 9.00 2.00 1.33 23.94 4.00 95.76 3.55
271.85TOTAL
Academic Columns (Concrete)
2.00
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 100
Mark Lenght (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYB101 19.00 0.83 1.33 21.06 6.00 126.35 4.68B102 18.00 0.83 1.67 25.05 4.00 100.20 3.71B103 20.00 1.67 1.17 38.89 1.00 38.89 1.44B104 14.00 1.67 1.17 27.22 1.00 27.22 1.01B105 22.00 1.67 1.17 42.78 1.00 42.78 1.58B106 22.00 1.67 1.17 42.78 1.00 42.78 1.58B107 20.00 1.67 1.17 38.89 1.00 38.89 1.44B108 20.00 1.67 1.17 38.89 1.00 38.89 1.44B109 22.00 2.00 2.17 95.33 1.00 95.33 3.53B110 20.00 2.00 1.50 60.00 1.00 60.00 2.22B111 20.00 2.00 1.50 60.00 1.00 60.00 2.22B112 28.00 1.00 1.00 28.00 20.00 560.00 20.74B113 23.00 1.00 5.58 128.42 1.00 128.42 4.76
50.36
Mark Lenght (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYB201 19.50 0.83 1.33 21.67 8.00 173.33 6.42B202 25.00 1.67 1.21 50.35 1.00 50.35 1.86B203 18.00 1.67 1.21 36.25 1.00 36.25 1.34B204 24.00 1.67 1.21 48.33 1.00 48.33 1.79B205 22.00 1.67 1.21 44.31 1.00 44.31 1.64B206 14.00 1.67 1.21 28.19 1.00 28.19 1.04B207 41.00 4.00 1.13 184.50 3.00 553.50 20.50B216 18.00 4.00 2.17 156.00 1.00 156.00 5.78B220 13.00 0.83 1.33 14.44 12.00 173.33 6.42B221 12.00 0.83 1.50 15.00 12.00 180.00 6.67B222 24.00 1.00 1.50 36.00 3.00 108.00 4.00B223 26.00 1.00 1.50 39.00 14.00 546.00 20.22B224 14.00 0.83 1.50 17.50 6.00 105.00 3.89B225 16.00 1.00 2.00 32.00 2.00 64.00 2.37B226 27.00 2.00 1.00 54.00 6.00 324.00 12.00B227 85.00 2.00 1.00 170.00 3.00 510.00 18.89B228 13.00 0.83 1.00 10.83 4.00 43.33 1.60B229 20.00 0.83 1.33 22.22 2.00 44.44 1.65B230 16.00 1.33 1.33 28.44 3.00 85.33 3.16B231 19.50 1.00 2.92 56.88 3.00 170.63 6.32B233 14.00 1.00 1.50 21.00 3.00 63.00 2.33
129.90
TOTAL
TOTAL
Residential Beams (Concrete)
Academic Beams (Concrete)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 101
Mark Depth (ft.) Volume (cu. Ft.) QuantityMud Mat 0.17 7480.49 1.00G4 Park 0.33 13465.67 1.00G3 Park 0.67 22748.03 1.00G3 Res. 0.67 7772.00 1.00G2 Park 0.67 23111.60 1.00G2 Res. 0.58 6505.33 1.00G1 Park 0.67 23073.12 1.00G1 Res. 0.58 6585.83 1.00Acad. 1 0.75 12377.25 1.00Res. 1 0.58 6844.74 1.00Plaza 1 1.00 12200.00 1.00Acad. 2 0.75 13429.62 1.00Res. 2 0.58 6845.42 1.00Acad. 3 0.75 13428.19 1.00Res. 3 0.58 6845.42 1.00
Roof Res. 0.67 7708.67 1.00Roof Acad. 0.67 11264.00 1.00
40397.00 498.7334122.04 842.5211658.00 287.85
Structural Slabs (Concrete)Area (sf) Total CY44882.95 277.06
243.9216503.00 458.4211733.84 253.51
34667.40 855.9911152.00 240.9434609.68 854.56
16896.00 417.19TOTAL 7469.83
17904.25 497.3411735.00 253.5311563.00 285.51
12200.00 451.8517906.16 497.3911735.00 253.53
11290.00
Mark Height (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYSW1 76.00 27.50 1.00 2090.00 1.00 2090.00 77.41SW2 76.00 18.00 1.00 1242.00 1.00 1242.00 46.00SW3 76.00 18.00 1.00 1168.50 1.00 1168.50 43.28SW4 76.00 9.50 1.00 722.00 1.00 722.00 26.74SW5 77.00 19.50 1.00 1501.50 1.00 1501.50 55.61SW6 77.00 9.25 1.00 712.25 1.00 712.25 26.38SW7 77.00 9.25 1.00 712.25 1.00 712.25 26.38SW8 85.00 9.00 1.00 765.00 1.00 765.00 28.33SW9 85.00 19.50 1.00 1657.50 1.00 1657.50 61.39SW11 65.00 27.50 0.67 1081.67 1.00 1081.67 40.06SW12 85.00 9.00 1.00 765.00 1.00 765.00 28.33SW13 40.00 18.00 1.00 720.00 14.00 10080.00 373.33
833.25TOTAL
Shear Walls (Concrete)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 102
Mark Lenght (ft.) Width (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CYB210 42.00 5.00 2.50 525.00 1.00 525.00 19.44B211 29.00 3.00 2.00 174.00 1.00 174.00 6.44B212 29.00 3.00 2.00 174.00 1.00 174.00 6.44B213 22.00 3.00 2.00 132.00 1.00 132.00 4.89B214 40.00 5.00 2.67 533.33 1.00 533.33 19.75B215 30.00 4.00 2.17 260.00 2.00 520.00 19.26B217 36.00 4.00 2.17 312.00 1.00 312.00 11.56B218 36.00 4.00 2.17 312.00 1.00 312.00 11.56
99.35
Mark LF (ft.) Height (ft.) Depth (ft.) Volume (cu. Ft.) Quantity Total Total CY0'‐8" 58.00 18.00 0.67 696.00 1.00 696.00 25.780'‐10" 130.50 24.00 0.83 2610.00 1.00 2610.00 96.671'‐0" 635.92 9.00 1.00 5723.25 4.00 22893.00 847.891'‐4" 289.33 9.00 1.33 3472.00 4.00 13888.00 514.37
1362.26
TOTAL
Foundation Walls (Concrete)
PT Transfer Beams (Concrete)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 103
Mark Qty. L (ft.) W (ft.) EW Bar EW qty. EW (lbs/lf) NS Bar NS qty. NS (lbs/lf) Wt. (lbs.) Total (tons)F80 2.00 8.00 8.00 #8 8.00 2.67 #8 8.00 2.67 341.76 0.34F85 4.00 8.50 8.50 #8 9.00 2.67 #8 9.00 2.67 408.51 0.82F90 9.00 9.00 9.00 #9 8.00 3.40 #9 8.00 3.40 489.60 2.20F95 3.00 9.50 9.50 #9 11.00 3.40 #9 11.00 3.40 710.60 1.07F100 8.00 10.00 10.00 #9 11.00 3.40 #9 11.00 3.40 748.00 2.99F105 9.00 10.50 10.50 #9 11.00 3.40 #9 11.00 3.40 785.40 3.53F110 2.00 11.00 11.00 #10 9.00 4.30 #10 9.00 4.30 851.99 0.85F115 1.00 11.50 11.50 #10 10.00 4.30 #10 10.00 4.30 989.69 0.49
12.30
Squae Foundations (Rebar)
TOTAL
Mark Qty. L (ft.) W (ft.) Bot. S. Bot. S. qty. Bot. S. (lbs./lf) Bot. L. Bot. L. qty. Bot. L. (lbs./lf) Top L. Top L. qty. Top L. (lbs./lf) Total (tons)CF01 4.00 26.50 11.50 #10 34.00 4.30 #10 16.00 4.30 #10 16.00 4.30 10.66CF03 1.00 15.50 12.50 #10 16.00 4.30 #10 14.00 4.30 #10 14.00 4.30 1.36CF04 2.00 14.00 10.50 #9 16.00 3.40 #9 12.00 3.40 #9 12.00 3.40 1.71CF05 1.00 12.00 6.00 #8 14.00 2.67 #8 8.00 2.67 #8 8.00 2.67 0.37CF06 4.00 17.50 8.50 #9 18.00 3.40 #9 8.00 3.40 #9 8.00 3.40 2.94
17.05TOTAL
Combined Foundations (Rebar)
Mark L (ft.) W (ft.) T & B T &B Qty. T & B (lbs/lf) Stir. Stir. (lf) Stir. (lbs/lf) Wt. (lbs) Total (tons)‐ 132.00 4.00 #5 5.00 1.04 #6 3.50 1.50 1382.30 0.69‐ 31.00 2.00 #5 3.00 1.04 97.00 0.05‐ 129.00 3.00 #9 5.00 3.40 #3 7.00 0.38 2532.53 1.27‐ 162.00 1.50 #8 6.00 2.67 #3 5.00 0.37 2892.51 1.45
3.45
Mark L (ft.) W (ft.) L Bar L Qty L (lbs/lf) W Bar W Qty. W (lbs/lf) Qty. (T&B) Total (tons)24" 21.50 12.00 #10 12.00 4.30 #10 21.00 4.30 2.00 2.19
Mark T & B (EW) T & B (EW) Qty T & B (EW) (lbs/lf) Wt. (lbs.) Mult. Total (tons.)34" #10 40.00 4.30 1,721.20 5.97 5.1442" #10 40.00 4.30 1,721.20 3.38 2.9154" #11 40.00 5.31 2,125.20 137.01 145.59
155.83
TOTAL
TOTAL
Grade Beams (Rebar)
Mat Foundations (Rebar)
Mat Foundations (Rebar)
597.13338.36
13,701.25
Area Comparison100.00100.00100.00
Area (sf.)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 104
Mark T & B (EW) T & B (EW) Qty T & B (EW) (lbs/lf) Wt. (lbs.) Mult. Total (tons.)SW1 #6 40.00 1.50 600.80 20.90 6.28SW2 #6 40.00 1.50 600.80 12.42 3.73SW3 #6 40.00 1.50 600.80 11.69 3.51SW4 #6 40.00 1.50 600.80 7.22 2.17SW5 #6 40.00 1.50 600.80 15.02 4.51SW6 #6 40.00 1.50 600.80 7.12 2.14SW7 #6 40.00 1.50 600.80 7.12 2.14SW8 #4/#5 40.00 0.86 342.20 7.65 1.31SW9 #4/#5 40.00 0.86 342.20 16.58 2.84SW11 #4/#5 40.00 0.86 342.20 17.88 3.06SW12 #4/#5 40.00 0.86 342.20 7.65 1.31SW13 #5/#6 40.00 1.27 509.00 100.80 25.65
58.64
Area (sf.) Area Comparison2090.00
1501.50712.25712.25765.00
722.00
Shear Walls (Rebar)
100.00100.00100.00100.00100.00
100.00100.00100.00100.00
TOTAL
765.0010080.00
1657.501787.50
1242.001168.50
100.00100.00100.00
Mark L (ft.) Qty. Bar Wt. (lbs./lf) Bars Stir. Stir. (lf) Stir. (lbs/lf)Wt. (lbs.) Total (tons)4 Bars 9.00 140.00 #9 3.40 4.00 #3 5.50 0.38 19741.68 9.876 Bars 9.00 170.00 #9 3.40 6.00 #3 5.50 0.38 34376.04 17.198 Bars 9.00 17.00 #10 4.30 8.00 #3 5.50 0.38 5583.28 2.7910 Bars 9.00 3.00 #10 4.30 10.00 #3 5.50 0.38 1217.65 0.6112 Bars 9.00 7.00 #11 5.31 12.00 #4 5.50 0.67 4248.09 2.12
32.58
Mark L (ft.) Qty. Bar Wt. (lbs./lf) Bars Stir. Stir. (lf) Stir. (lbs/lf)Wt. (lbs.) Total (tons)4 Bars 9.00 140.00 #9 3.40 4.00 #3 5.50 0.38 19741.68 9.876 Bars 9.00 108.00 #9 3.40 6.00 #3 5.50 0.38 21838.90 10.928 Bars 9.00 32.00 #10 4.30 8.00 #3 5.50 0.38 10509.70 5.2510 Bars 9.00 12.00 #10 4.30 10.00 #3 5.50 0.38 4870.58 2.4412 Bars 9.00 18.00 #11 5.31 12.00 #4 5.50 0.67 10923.66 5.46
33.94
Residential Columns (Rebar)
TOTAL
Academic Columns (Rebar)
TOTAL
Mark L (ft.) Qty. T Bar Top (lbs./lf) Bars Bot. Bar Bot (lbs./lf) Bars Stirrup (lbs) Total (tons)B101 19.00 6.00 #7 2.04 2.00 #8 2.67 2.00 3.38 0.73B102 18.00 4.00 #8 2.67 2.00 #9 3.40 2.00 3.38 0.56B103 20.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.22B104 14.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.16B105 22.00 1.00 #8 2.67 4.00 #10 4.30 4.00 3.38 0.34B106 22.00 1.00 #9 3.40 4.00 #10 4.30 4.00 3.38 0.38B107 20.00 1.00 #8 2.67 2.00 #10 4.30 5.00 3.38 0.30B108 20.00 1.00 #8 2.67 2.00 #10 4.30 5.00 3.38 0.30B109 22.00 1.00 #9 3.40 4.00 #10 4.30 6.00 3.38 0.47B110 20.00 1.00 #9 3.40 4.00 #10 4.30 6.00 3.38 0.43B111 20.00 1.00 #9 3.40 4.00 #10 4.30 6.00 3.38 0.43B112 28.00 20.00 #7 2.04 2.00 #7 2.04 2.00 3.38 3.24B113 23.00 1.00 #9 3.40 2.00 #10 4.30 2.00 3.38 0.22
7.77TOTAL
Residential Beams (Rebar)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 105
Mark L (ft.) Qty. T Bar Top (lbs./lf) Bars Bot. Bar Bot (lbs./lf) Bars Stirrup (lbs/lf) Total (tons)B201 19.50 8.00 #7 2.44 2.00 #8 2.67 2.00 3.38 1.06B202 25.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.28B203 18.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.20B204 24.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.27B205 22.00 1.00 #8 2.67 2.00 #9 3.40 4.00 3.38 0.25B206 14.00 1.00 #8 2.67 2.00 #9 3.40 2.00 3.38 0.11B207 41.00 3.00 #7 2.44 4.00 #7 2.44 4.00 3.38 1.41B216 18.00 1.00 #9 3.40 6.00 #11 5.31 10.00 3.38 0.69B220 13.00 12.00 #8 2.67 2.00 #8 2.67 2.00 3.38 1.10B221 12.00 12.00 #8 2.67 2.00 #8 2.67 2.00 3.38 1.01B222 24.00 3.00 #8 2.67 2.00 #8 2.67 2.00 3.38 0.51B223 26.00 14.00 #8 2.67 2.00 #8 2.67 2.00 3.38 2.56B224 14.00 6.00 #8 2.67 2.00 #8 2.67 2.00 3.38 0.59B225 16.00 2.00 #8 2.67 2.00 #8 2.67 2.00 3.38 0.23B226 27.00 6.00 #8 2.67 2.00 #8 2.67 2.00 3.38 1.14B227 85.00 3.00 #8 2.67 2.00 #8 2.67 2.00 3.38 1.79B228 13.00 4.00 #8 2.67 2.00 #8 2.67 2.00 3.38 0.37B229 20.00 2.00 #7 2.44 2.00 #8 2.67 2.00 3.38 0.27B230 16.00 3.00 #8 2.67 2.00 #9 3.40 2.00 3.38 0.37B231 19.50 3.00 #9 3.40 3.00 #10 4.30 3.00 3.38 0.77B233 14.00 3.00 #8 2.67 2.00 #8 2.67 2.00 3.38 0.30
15.27
Mark L (ft.) Qty. T Bar Top (lbs./lf) Bars Bot. Bar Bot (lbs./lf) Bars Stirrup (lbs/lf) Total (tons)B210 42.00 1.00 #8 2.67 8.00 #8 2.67 8.00 3.56 0.97B211 29.00 1.00 #8 2.67 4.00 #8 2.67 4.00 3.56 0.36B212 29.00 1.00 #8 2.67 4.00 #8 2.67 4.00 3.56 0.36B213 22.00 1.00 #8 2.67 4.00 #8 2.67 4.00 3.56 0.27B214 40.00 1.00 #8 2.67 8.00 #8 2.67 8.00 3.56 0.93B215 30.00 2.00 #8 2.67 6.00 #8 2.67 6.00 3.56 1.07B217 36.00 1.00 #8 2.67 4.00 #8 2.67 6.00 3.56 0.54B218 36.00 1.00 #8 2.67 4.00 #8 2.67 6.00 3.56 0.54
5.05
Mark T & B (EW) T & B (EW) Qty T & B (EW) (lbs/lf) Wt. (lbs.) Mult. Total (tons.)0'‐8" #4/#5 30.00 0.79 237.53 10.44 1.240'‐10" #4/#6 20.00 1.09 217.00 31.32 3.401'‐0" #4/#7/#8/#8 40.00 2.02 807.20 228.93 92.401'‐4" #5/#6 40.00 1.27 509.00 104.16 26.51
123.54TOTAL
22893.0010416.00
100.00100.00100.00100.00
Foundation Walls (Rebar)Area (sf.) Area Comparison1044.003132.00
Academic Beams (Rebar)
TOTAL
PT Transfer Beams (Rebar)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 106
Mark T & B (EW) T & B (EW) Qty T & B (EW) (lbs/lf) Wt. (lbs.) Mult. Total (tons.)G4 Park ‐ ‐ ‐ ‐ ‐ ‐G3 Park* #5 24.00 1.04 250.32 341.22 42.71G3 Res. #5 24.00 1.04 250.32 116.58 14.59G2 Park* #5 24.00 1.04 250.32 346.67 43.39G2 Res. #4/#5 34.00 0.79 269.20 111.52 15.01G1 Park* #5 24.00 1.04 250.32 346.10 43.32G1 Res. #4/#5 34.00 0.79 269.20 112.90 15.20Acad. 1 #5 48.00 1.04 500.64 165.03 41.31Res. 1 #4/#5 34.00 0.79 269.20 117.34 15.79Plaza 1 #6 48.00 1.50 720.96 122.00 43.98Acad. 2 #5 48.00 1.04 500.64 179.06 44.82Res. 2 #4/#5 34.00 0.79 269.20 117.35 15.80Acad. 3 #5 48.00 1.04 500.64 179.04 44.82Res. 3 #4/#5 34.00 0.79 269.20 117.35 15.80
Roof Res. #5 36.00 1.04 375.48 115.63 21.71Roof Acad. #5 36.00 1.04 375.48 168.96 31.72
449.95
11152.00 100.0034609.68 100.0011290.00 100.0016503.00 100.00
Structural Slabs (Rebar)Area (sf.) Area Comparison40397.00 100.0034122.04 100.0011658.00 100.00
11735.00 100.0011563.00 100.0016896.00 100.00
*epoxy coated Rebar TOTAL
11733.84 100.0012200.00 100.0017906.16 100.0011735.00 100.0017904.25 100.00
34667.40 100.00
Mark LF Depth (ft.) Area (sf)24" 67.00 2.00 134.0034" 97.25 2.83 275.5442" 73.00 3.50 255.5154" 506.33 4.50 2278.49
2943.54
Mark LF Height (ft.) Area (sf)SW1 24.00 76.00 1824.00SW2 24.00 76.00 1824.00SW3 24.00 76.00 1824.00SW4 21.33 76.00 1621.31SW5 24.25 77.00 1867.25SW6 24.25 77.00 1867.25SW7 24.25 77.00 1867.25SW8 24.25 85.00 2061.25SW9 24.25 85.00 2061.25SW11 24.25 85.00 2061.25SW12 17.83 85.00 1515.83SW13 476.00 40.00 19040.00
39434.64
Mat Foundations (Formwork)
TOTAL
Shear Walls (Formwork)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 107
Mark Surface Area Depth (ft.) Quantity Area (sf)B101 68.59 1.33 6.00 411.54B102 77.90 1.67 4.00 311.61B103 83.89 1.17 1.00 83.89B104 59.89 1.17 1.00 59.89B105 91.89 1.17 1.00 91.89B106 91.89 1.17 1.00 91.89B107 83.89 1.17 1.00 83.89B108 83.89 1.17 1.00 83.89B109 148.00 2.17 1.00 148.00B110 106.00 1.50 1.00 106.00B111 106.00 1.50 1.00 106.00B112 86.00 1.00 20.00 1720.00B113 291.00 5.58 1.00 291.00
3589.49
Mark Surface Area Depth (ft.) Quantity Area (sf)B201 70.47 1.33 8.00 563.78B202 106.11 1.21 1.00 106.11B203 77.53 1.21 1.00 77.53B204 102.03 1.21 1.00 102.03B205 93.86 1.21 1.00 93.86B206 61.19 1.21 1.00 61.19B207 265.25 1.13 3.00 795.75B216 167.33 2.17 1.00 167.33B220 47.72 1.33 12.00 572.67B221 48.50 1.50 12.00 582.00B222 99.00 1.50 3.00 297.00B223 107.00 1.50 14.00 1498.00B224 56.17 1.50 6.00 337.00B225 84.00 2.00 2.00 168.00B226 112.00 1.00 6.00 672.00B227 344.00 1.00 3.00 1032.00B228 38.50 1.00 4.00 154.00B229 72.22 1.33 2.00 144.44B230 67.56 1.33 3.00 202.67B231 139.08 2.92 3.00 417.25B233 59.00 1.50 3.00 177.00
8221.61
Residential Beams(Formwork)
TOTAL
Academic Beams(Formwork)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 108
Mark LF Height (ft.) Quantity Area (sf)101 6.66 9.083 7.00 423.45102 6.66 9.083 7.00 423.45103 6.66 9.083 7.00 423.45104 6.66 9.083 7.00 423.45105 6.66 9.083 7.00 423.45106 6.66 9.083 7.00 423.45107 6.66 9.083 7.00 423.45108 6.66 9.083 7.00 423.45109 6.66 9.083 7.00 423.45110 7.00 9.083 4.00 254.32111 6.66 9.083 7.00 423.45112 6.66 9.083 7.00 423.45113 6.66 9.083 7.00 423.45114 6.66 9.083 7.00 423.45115 6.66 9.083 7.00 423.45117 6.66 9.083 7.00 423.45118 6.66 9.083 7.00 423.45119 6.66 9.083 7.00 423.45120 6.66 9.083 7.00 423.45121 6.66 9.083 7.00 423.45122 6.66 9.083 7.00 423.45123 6.00 9.083 4.00 217.99124 6.66 9.083 7.00 423.45125 6.66 9.083 7.00 423.45126 7.00 9.083 7.00 445.07127 7.00 9.083 7.00 445.07128 7.00 9.083 7.00 445.07129 7.00 9.083 7.00 445.07130 6.66 9.083 7.00 423.45131 7.00 9.083 7.00 445.07132 7.00 9.083 7.00 445.07133 7.00 9.083 7.00 445.07134 6.66 9.083 7.00 423.45135 6.66 9.083 7.00 423.45136 6.66 9.083 7.00 423.45137 6.66 9.083 7.00 423.45138 7.00 9.083 7.00 445.07139 7.00 9.083 7.00 445.07140 7.00 9.083 7.00 445.07141 7.00 9.083 7.00 445.07142 7.00 9.083 7.00 445.07143 7.00 9.083 7.00 445.07144 7.00 9.083 7.00 445.07145 7.00 9.083 7.00 445.07146 7.00 9.083 7.00 445.07147 7.00 9.083 7.00 445.07148 7.00 9.083 7.00 445.07149 7.00 9.083 7.00 445.07150 6.66 9.083 7.00 423.45
20785.17
Residential Columns (Formwork)
TOTAL
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 109
Mark LF Height (ft.) Quantity Area (sf)201 6.66 9.00 4.00 239.76202 6.66 9.00 4.00 239.76203 6.66 9.00 7.00 419.58204 6.66 9.00 7.00 419.58205 6.66 9.00 7.00 419.58206 6.66 9.00 4.00 239.76207 6.66 9.00 4.00 239.76208 6.66 9.00 7.00 419.58209 6.66 9.00 7.00 419.58210 6.66 9.00 7.00 419.58211 6.66 9.00 7.00 419.58212 6.66 9.00 7.00 419.58213 6.66 9.00 7.00 419.58214 6.66 9.00 7.00 419.58215 6.66 9.00 7.00 419.58216 6.66 9.00 7.00 419.58217 6.66 9.00 7.00 419.58218 6.66 9.00 7.00 419.58219 6.66 9.00 3.00 179.82219 4.00 9.00 4.00 144.00220 6.66 9.00 7.00 419.58221 6.66 9.00 7.00 419.58222 6.66 9.00 7.00 419.58223 6.66 9.00 4.00 239.76224 6.66 9.00 7.00 419.58225 6.66 9.00 7.00 419.58226 6.66 9.00 7.00 419.58227 6.66 9.00 7.00 419.58228 7.00 9.00 7.00 441.00229 6.66 9.00 7.00 419.58230 6.66 9.00 7.00 419.58231 6.66 9.00 7.00 419.58232 6.66 9.00 4.00 239.76233 6.66 9.00 7.00 419.58234 6.66 9.00 4.00 239.76235 7.00 9.00 7.00 441.00236 7.00 9.00 7.00 441.00237 7.00 9.00 6.00 378.00238 7.00 9.00 6.00 378.00239 7.00 9.00 6.00 378.00240 7.00 9.00 7.00 441.00241 7.00 9.00 7.00 441.00242 6.66 9.00 4.00 239.76243 6.00 9.00 4.00 216.00244 6.00 9.00 4.00 216.00245 6.00 9.00 4.00 216.00246 6.00 9.00 4.00 216.00247 6.66 9.00 3.00 179.82248 6.66 9.00 4.00 239.76249 6.66 9.00 4.00 239.76250 6.00 9.00 3.00 162.00251 6.00 9.00 3.00 162.00252 6.00 9.00 3.00 162.00253 6.00 9.00 3.00 162.00254 6.66 9.00 4.00 239.76
18481.50TOTAL
Academic Columns (Formwork)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 110
Mark LF Height (ft.) Area (sf)0'‐8" 116.00 18.00 2088.000'‐10" 263.00 24.00 6312.001'‐0" 635.92 36.00 22893.001'‐4" 289.33 36.00 10416.00
41709.00
Foundation Walls(Formwork)
TOTAL
Mark Surface Area Depth (ft.) Quantity Area (sf)B210 445.00 2.50 1.00 445.00B211 215.00 2.00 1.00 215.00B212 215.00 2.00 1.00 215.00B213 166.00 2.00 1.00 166.00B214 440.00 2.67 1.00 440.00B215 267.33 2.17 2.00 534.67B217 317.33 2.17 1.00 317.33B218 317.33 2.17 1.00 317.33
2650.33TOTAL
PT Transfer Beams (Formwork)
Benjamin Mahoney Marymount University 26th St Project Construction Management Arlington, VA Consultant: Mr. Faust Final Report: 4/7/2010
Page | 111
Appendix F: LEED NCv2.2 Credit Scorecard
LEED for New Construction v 2.2 Registered Project Checklist
Last Modified: May 2008 1 of 4
Project Name:
Project Address:
Project Totals (Pre-Certification Estimates) 69 PointsYes ? No
Certified: 26-32 points Silver: 33-38 points Gold: 39-51 points Platinum: 52-69 points
Sustainable Sites 14 PointsYes ? No
Yes Prereq 1
Credit 1
Credit 2
Credit 3
Credit 4.1
Credit 4.2
Credit 4.3
Credit 4.4
Credit 5.1
Credit 5.2
Credit 6.1
Credit 6.2
Credit 7.1
Credit 7.2
Credit 8
Alternative Transportation, Low-Emitting & Fuel Efficient Vehicles 1
1
1
1
1
1
Required
1
1
1
1
1
1
1
1
Construction Activity Pollution Prevention
Site Selection
Development Density & Community Connectivity
Brownfield Redevelopment
Alternative Transportation, Public Transportation
Alternative Transportation, Bicycle Storage & Changing Rooms
Alternative Transportation, Parking Capacity
Site Development, Protect or Restore Habitat
Site Development, Maximize Open Space
Stormwater Design, Quantity Control
Stormwater Design, Quality Control
Heat Island Effect, Non-Roof
Heat Island Effect, Roof
Light Pollution Reduction
Water Efficiency 5 PointsYes ? No
Credit 1.1
Credit 1.2
Credit 2
Credit 3.1
Credit 3.2 1
1
1
1
1Water Efficient Landscaping, Reduce by 50%
Water Efficient Landscaping, No Potable Use or No Irrigation
Innovative Wastewater Technologies
Water Use Reduction, 20% Reduction
Water Use Reduction, 30% Reduction
Marymount University 26th Street Project
4763 Old Dominion Drive, Arlington, VA 22201
33 13 23
SILVER
10 1 3
1
1
1
1
1
1
1
1
1
1
1
1
1
1
3 2
1
1
1
1
1
LEED for New Construction v 2.2 Registered Project Checklist
Last Modified: May 2008 2 of 4
Energy & Atmosphere 17 PointsYes ? No
Yes Prereq 1
Credit 1
Credit 2
Credit 3
Credit 4
Credit 5
Credit 6 Green Power 1
1
1
1
1 to 3
1 to 10
RequiredFundamental Commissioning of the Building Energy Systems
Optimize Energy Performance
On-Site Renewable Energy
Enhanced Commissioning
Enhanced Refrigerant Management
Measurement & Verification
Yes Prereq 1 RequiredMinimum Energy Performance
Yes Prereq 1 RequiredFundamental Refrigerant Management
*Note for EAc1: All LEED for New Construction projects registered after June 26, 2007 are required to achieve at least two (2) points.
10.5% New Buildings / 3.5% Existing Building Renovations
14% New Buildings / 7% Existing Building Renovations
17.5% New Buildings / 10.5% Existing Building Renovations
21% New Buildings / 14% Existing Building Renovations
24.5% New Buildings / 17.5% Existing Building Renovations
28% New Buildings / 21% Existing Building Renovations
31.5% New Buildings / 24.5% Existing Building Renovations
35% New Buildings / 28% Existing Building Renovations
38.5% New Buildings / 31.5% Existing Building Renovations
42% New Buildings / 35% Existing Building Renovations
1
2
3
4
5
6
7
8
9
10
2.5% Renewable Energy
7.5% Renewable Energy
12.5% Renewable Energy 3
2
1Credit 2.1
Credit 2.2
Credit 2.3
Credit 1.1
Credit 1.2
Credit 1.3
Credit 1.4
Credit 1.5
Credit 1.6
Credit 1.7
Credit 1.8
Credit 1.9
Credit 1.10
3 5 9
2
3
1
1
1
1
4 4
-->
LEED for New Construction v 2.2 Registered Project Checklist
Last Modified: May 2008 3 of 4
Materials & Resources 13 PointsYes ? No
Yes Prereq 1
Credit 1.1
Credit 1.2
Credit 1.3
Credit 2.1
Credit 2.2
Credit 3.1
Credit 3.2
Credit 4.1
Credit 4.2
Credit 5.1
Credit 5.2
Credit 6
Credit 7
Materials Reuse, 5% 1
1
1
1
1
1
Required
1
1
1
1
1
1
1
Storage & Collection of Recyclables
Building Reuse, Maintain 75% of Existing Walls, Floors & Roof
Building Reuse, Maintain 95% of Existing Walls, Floors & Roof
Building Reuse, Maintain 50% of Interior Non-Structural Elements
Construction Waste Management, Divert 50% from Disposal
Construction Waste Management, Divert 75% from Disposal
Materials Reuse, 10%
Recycled Content, 10% (post-consumer + 1/2 pre-consumer)
Recycled Content, 20% (post-consumer + 1/2 pre-consumer)
Regional Materials, 10% Extracted, Processed & Manufactured
Regional Materials, 20% Extracted, Processed & Manufactured
Rapidly Renewable Materials
Certified Wood
Indoor Environmental Quality 15 PointsYes ? No
Yes Prereq 1
Credit 1
Credit 2
Credit 3.1
Credit 3.2
Credit 4.1
Credit 4.2
Credit 4.3
Credit 4.4
Credit 5
Credit 6.1
Credit 6.2
Credit 7.1
Credit 7.2
Credit 8.1
Low-Emitting Materials, Paints & Coatings 1
1
1
1
1
1
Required
1
1
1
1
1
1
1
1
Minimum IAQ Performance
Outdoor Air Delivery Monitoring
Increased Ventilation
Construction IAQ Management Plan, During Construction
Construction IAQ Management Plan, Before Occupancy
Low-Emitting Materials, Adhesives & Sealants
Low-Emitting Materials, Carpet Systems
Low-Emitting Materials, Composite Wood & Agrifiber Products
Indoor Chemical & Pollutant Source Control
Controllability of Systems, Lighting
Controllability of Systems, Thermal Comfort
Thermal Comfort, Design
Thermal Comfort, Verification
Daylight & Views, Daylight 75% of Spaces
Yes Prereq 2 RequiredEnvironmental Tobacco Smoke (ETS) Control
Credit 8.2 1Daylight & Views, Views for 90% of Spaces
3 3 7
1
1
1
1
1
1
1
1
1
1
1
1
1
9 2 4
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
LEED for New Construction v 2.2 Registered Project Checklist
Last Modified: May 2008 4 of 4
Innovation & Design Process 5 PointsYes ? No
Credit 1.1
Credit 1.2
Credit 1.3
Credit 1.4
Credit 2 1
1
1
1
1
LEED® Accredited Professional
Innovation in Design:
Innovation in Design:
Innovation in Design:
Innovation in Design:
5
1
1
1
1
1
Provide Specific Title
Provide Specific Title
Provide Specific Title
Provide Specific Title