Project Charter
Our goals are to take an existing database center, and move/upgrade it to a newer building. We are trying to get bigger because we regrew out of our original size.
We want to use better equipment so we can get a bigger customer base. This is part of a larger project.
Estimated Budget
Estimated Labor $0
Estimated Materials $10,000
Estimated Contractors $0
Estimated Equipment and Facilities $75,000
Estimated Travel $1,000
Total Estimated Cost $86,000
Business Needs• We are doing this project due to our customer’s demand for
server space and an option of playing a variety of games on our platforms.
• The upgrade will add new servers capable of hosting multiple gaming servers at once.
• This will be a financial gain for the owner as well as a better gaming experience for the owner.
• Word of mouth promotion will help the revenue for the owner as well.
• This will be a financial gain for the owner as well as a better gaming experience for the owner.
Milestones • We are acquiring the building first, on 11/6/2015. • We will spec out and order equipment on 11/9/2015 and on
11/9/2015 we are setting up a date for our metro Ethernet. • we are getting the equipment needed on 11/13/2015. • We start wiring up the servers on 11/14/2015 and we are getting the
installation of metro Ethernet. • On 11/18/2015 we will be doing a stress test on the servers to make
sure they work well with high volume • A beta testing invite to our customers will be on 11/20/15 to 11/22/15. • On 11/25/15 we are doing an editing and reviewing/bug repair to our
servers. • 12/07/2015 is the launch date of our servers.