Upload
hansini-manisha-deena
View
17
Download
0
Embed Size (px)
DESCRIPTION
economics for distillation
Citation preview
ECONOMICS: SUMMARY OF EQUIPMENT PURCHASE COST
Equipments MUR (Rs)
Cane preparation and milling
Cane carriers 883,380
Bagasse carrier 559,469
Cane Knives 1,995,676
Tongaat Shredder 672000
Tramp Iron Separator 30,950
3 roller mills 21, 634,399
Juice clarification unit
Heater 1 2,753,582
Heater 2 2, 414,493
Cooler 906,550
Flash Tank 496,360
Clarifier 5,098,500
Rotary drum filter 6,165,965
Milk of Lime Tank 204,673
Liming Tank 116,635
Juice Mixer/Blender 247,200
MEE 4 effects 37,684,325
Barometric Condenser 92 700
Fermentation unit
Absorption Tower 3,090,000
Scrubber column packing 1,409,000
Centrifuges (x2) 983,276
Fermentation Tanks (x5) 32, 059,223
Heat exchangers (x5) 8,114,243
Holding Tank 6,358,340
Pre-Fermentor 1,552,931
Pumps (x7) 4,099,275
Distillation unit
Rectifying column 543,060
Stripping column 543,060
Reboiler 3,508,660
Pre-heater 1,086,639
Condenser 1,258,300
Dehydration unit
U-tube preheater 2,771,029
Bayonet vaporizer 993,491
Bayonet condenser 665,732
Molecular sieves 558,817
Vacuum pump 815,944
Adsorption towers (x2) 3,176,848
Storage tanks (x5) 56,954,365
EQUIPMENT PURCHASE COST
(EPC)
193,249,332
ECONOMICS: CALCULATING TOTAL CAPITAL INVESTMENT
Parameter Range Factor
chosen
Price (Rs) Justification
DIRECT COSTS
Purchase equipment
(f1)
- - - 193,249,332 -
Installation (f2) EPC (x) 0.25-0.55 0.25 48312332.98 Includes structural supports and installation
Instrumentation &
control (f3)
EPC (x) 0.06-0.30 0.30 57974799.58 Intensive control throughout the plant
Piping (f4) EPC(x) 0.10-0.80 0.45
86962199.37 Average value taken
Electrical (f5) EPC(x) 0.10-0.40 0.10 19324933.19 Sinnot (1999) reports the contribution of this element
as 10% of the EPC
Building, process &
auxiliary (f6)
EPC(x) 0.10-0.70 0.22 42514853.02 Peters and Timmerhaus (1991) reports the
contribution of this element as 22% of the EPC for a new plant at an existing
site.
Service facilities
and yard
improvement (f7)
EPC (x) 0.10-1.0 0.10 19324933.19 A new plant requires these services but a minimum is
taken so as priority is given to other more important services.
Land (f8) EPC (x) 0.04-0.08 0.08 15459946.55 Land will be fully required for setting of the plant.
TOTAL DIRECT COST = (f1 + f2 + f3 +f4 + f5 + f6 + f7)483,123,329.82
INDIRECT COSTS
Engineering and supervision (f9)
DC (x) 0.05-0.30 0.30 144936998.9 Maximum expertise is necessary since it is a new
plant.
Construction and contractor’s fee
(f10)
DC (x) 0.06-0.30 0.18 86962199.37 An average is taken as a better estimate.
Contingency (f11) FCI (x) 0.05-0.15 0.1 0.1 FCI A proper average safety margin is deemed
necessary.
TOTAL INDIRECT COST = (f9 + f10 + f11 ) 231899198.3+ 0.1 FCI
Fixed capital investment (FCI) = Direct cost + Indirect cost
FCI = (483,123,329.82 + 231,899,198.3 + 0.1 FCI)
Hence, FCI = Rs 794,469,475.7
Working capital (WC) = 0.15 TCI
Total capital investment = FCI + WC
TCI = Rs 794,469,475.7 + 0.15 TCI
Hence, TCI = Rs 934,669,971.4
ECONOMICS: CALCULATING TOTAL PRODUCT COST
Total product cost = manufacturing cost + General Expenses
MANUFACTURING COST
Manufacturing cost = Direct Production cost + fixed charges + plant overheads
1. DIRECTION PRODUCTION COST
Raw materials
Price of raw materials: The price of sugarcane was fixed at 1700 Indian rupees per tonne of
sugarcane (N.Deshmukh, TNN, 2013) (
http://articles.timesofindia.indiatimes.com/2012-07-23/pune/32803260_1_sugarcane-farmers-sugar-
factories-raghunath-patil)
Converting Indian currency to Mauritian currency and obtaining: 1 tonne of sugarcane = Rs 1190
Amount of sugarcane used = 103.102 tonnes/h
Total amount = 103.102 * 24 * 150 = 371,167.2 tonnes
371,167.2 tonnes of sugarcane = Rs 445,536,000
Operating labour and direct supervisory and clerical labour
Product capacity = 167 tons/day
Operating labour = 85 (from the graph; the graph chosen in this section as that in case
multiple small units for increasing capacity).
Number of operating days = 150
Annual operating labour requirement = 85*5*150 = 63750 hours
Considering 9 working hours per employee,
Total number of employees required per day = 63750150∗9
= 47.22 = 48
Figure 1: Labour requirement for chemical process industries
(Source: Plant design and economics for chemical engineers, Peters M.S and Timmerhaus K.D)
The technical team in charge of the operation of the BioEPP will comprise of:
The General Manager
Operations Manager
Process Manager
Maintenance Manager
Shift supervisors and Operators
The salary were taken from PRB 2012-2013
Occupation Quantity Salary per person/Rs Justification
OPERATING LABOUR
General Manager 1 102,000 Responsible for all business operations of the ethanol plant including product operations,
purchasing, marketing and personnel.
Operation Manager 1 48 600Responsible for optimizing plant runtime as well as downtime while ensuring a quality end product.
Process Manager 1 48 600 Work with department managers and supervisors in operations,
maintenance, logistics, environmental, health, safety and
quality
Maintenance Manager 1 44 100 In charge of coordinating and supporting plant maintenance performance personnel and
contractors to achieve efficient and safe completion of the workload.
Senior electrical engineer
1 26 250
New plant, therefore one of each category is enough.
Electrical engineer 1 18 900
Chief technician 1 16 500 Decision making during shut down or major technical problems
Supervisor 2 14 300 Supervising daily operations including ethanol storage, loading,
inventory control measures and safety compliance and sanitation.
Laboratory attendant 1 10 250Run multiple tests in accordance
to the standard operation procedures and in accordance with the frequency established
by the Process Manager.
Driver 2 10 000For emergencies and running odd
jobs on working premises.
Watchman 2 9 000Assuring plant security
Store attendant 1 8 500
Keep track of equipment and chemicals.
General Worker 3 7 400 Ensure proper up-keeping of the working premises.
DIRECT SUPERVISORY AND CLERICAL LABOUR
Senior Technician 5 16500
One major technician per unit
Technician 10 15800 1 technician per unit per shift
Foreman 5 15380 Extensive supervision required for floor work
Chef de quarts 5 20000 Verify all the controls and instrumentations regarding the plant. Take necessary steps in
case of cropping up of technical problems.
Plumbers and pipe fitters
4 102503 fitters per shift
Account clerk 1 11250To record all the transactions
TOTAL 48 882 150
Total salary = (412 500 + 469650) = Rs 882 150 [for 48 staff working 9 hrs/day during 1 month]
Cost of labour per hour = 882 150 / (48 x 30 x 9) = Rs 68.08
Annual labour cost = 68.08 x 63750 = Rs 4,339,280
Utilities
Since the plant is self-sufficient in terms of steam and electricity produced by the
cogeneration plant for partly internal consumption, utilities cost (10-15% of TPC) is
taken as 15 % of the total product cost.
Utilities cost = 0.15 * TPC
Maintenance and repairs
Maintenance is a planned programme in any process plant in order to keep all the
equipment in a good working condition. The maintenance cost includes cost for material
tools and supervision and can be in the range of 2-10% of the fixed capital investment
(FCI).
Available data
FCI = Rs 794,469,475.70
% chosen = 2
Hence cost associated with maintenance and repair = 0.002 FCI = Rs 15,889,390
Operating supplies
Name Use Quantity
(Unit/day)
Price/Unit Cost/Yr
Lime For Juice Treatment 1903 kg $110/ton 31,400
Activated dry yeast Source for
fermentation
0.5 kg $2000/ton $ 150
Sulphuric Acid
(98%)
pH control 100 L $250/metric ton $6900
Di Ammonium
phosphate
Nutrient for yeast
propagation
80 Kg $800/metric ton $9600
Phosphoric acid Nutrient for yeast
propagation
30 L $800/ metric ton $ 6800
Magnesium sulphate Nutrient for yeast
propagation
0.25 kg $100/metric ton $3.75
Caustic soda For cleaning and pH
control
100 Kg $400/ton $6 000
TOTAL $ 60,854
In addition, corrosion inhibitors will be needed to prevent corrosion in storage tanks as well as
the use for gasoline for denaturation.
Gasoline
The gasoline price in Mauritius is found to be 51.30 MUR/L
Finding the required amount of gasoline:
1 day = 2.5173 m3
150 days = 378 m3 = 378, 000 L
Cost of gasoline = 51.30 MUR * 378000 L
= 19,391,400 MUR
Corrosion inhibitor
According to ChemWorld.com based in USA, the cost of corrosion inhibitor is as follows:
Quantity/ gallons Cost/ USD
55 709.99
30 549.99
15 399.99
5 149.99
Finding the amount of corrosion inhibitor required:
1 day = 2.27 * 10-3 m3
150 days = 34.05 m3 = 340.5 L
1 US gallon = 3.7854 L
Number of gallons needed = 340.5
3.7854 = 90 gallons
Since corrosion inhibitor is sold in 55/30/15/5 gallons by the company, 3 * 30 gallons are selected to be bought.
30 gallons = 549.99 USD
Cost of corrosion inhibitor = 3 * 549.99
= 1650 USD
= 51,402 MUR
Total cost for operating supplies = Rs (1,880,389 + 19,391,400 + 51,402)
= Rs 21,323,191
Laboratory charges
Laboratory charges are taken normally as 10-20% of the operating labour cost, thus;
Laboratory charges = 0.20 x operating labour
= 0.20 x Rs 4,339,280
= Rs 867,856
Patents and royalties
This item is taken as 6% of the Total Product Cost (TPC)
2. FIXED CHARGES
Depreciation
The straight line method is used to calculate the overall depreciation of the equipment. The fixed %
factor is then evaluated by the double declining method. The depreciation of the equipment over the
whole service life is calculated using the declining balance method. However, the yearly depreciation
of building is taken as a % of the building value.
a. Equipment depreciation
Straight line method (TimmerHaus, 1991),
d = V−Vs
n
Where
d = annual depreciation / USD
V = original value of total equipment / USD
Vs = salvage value of total equipment / USD
n = number of service life / years
Available data:
V = 193,249,332
Vs = 25 million rupees (Local sugar factory)
n = 30 (BP Biofuels 2012, Brazil)
d = Rs 5,608,312
Double declining balance method (TimmerHaus, 1991),
f = 2 x dv
Where
f = fixed % factor
f = 0.0580 (3 s.f)
Declining balance method (TimmerHaus, 1991),
Vs = V (1-f)n
= Rs 32,184,375
For year 1; vs = Rs 1,072,813
b. Building depreciation
Available data:
Building Cost = 42514853.02
% chosen = 2.5
Depreciation on building = 0.025x Building cost = Rs 1,062,871
Total depreciation = 1,062,871 + 1,072,813
= Rs 2,135,684
Local taxes
Since the location of the property is meant to be in the northern part of Mauritius, taxes
are lower as compared to more developed and highly populated areas, thus a factor of 2%
of the FCI can be used.
Local taxes = 0.020 * FCI
= 0.020 * Rs 794,469,475.70
= Rs 15,889,389
Insurance
Insurance rates depend on the type of process being carried out in the manufacturing
operation and on the extent of available protection facilities. On an annual basis, these
rates amount to about 1 percent of the fixed-capital investment (FCI).
FCI = Rs 794,469,475.70
% chosen = 1
Hence cost associated with maintenance and repair = 0.001 FCI = Rs 7,944,695
Rent
This item is taken as 10% of the cost of building cost
Given building cost = Rs 42,514,853
Cost for rent = 0.1 x 42514853 = Rs 4,251,485
3. PLANT OVERHEAD
Plant overhead is taken as 1 % of the total product cost (TPC)
GENERAL EXPENSES
1. ADMINISTRATIVE COSTS
Administrative costs = 0.15 [supervision costs + maintenance costs + operating labour]
(P.Jeetah, 2012)
= 0.15 [132,713,887.2 + 14,549,374.3 + 4,339,280]
= Rs 22, 740, 381
2. DISTRIBUTION AND SELLING COSTS
Usually amounts to 1-20% of the total product cost. (TPC). Percentage chosen = 1 %
Hence, distribution and selling costs = (0.01 TPC )
3. RESEARCH AND DEVELOPMENT COSTS
Cost for this item is taken as 5 % of the Total Product Cost (TPC)
Calculating Total Product Cost (TPC)
Manufacturing cost = Direct Production cost + fixed charges + plant overheads
= Rs 518,176,970 + 0.22 TPC
Total product cost = manufacturing cost + General Expenses
TPC = (Rs 518,176,970 + 0.22 TPC) + (Rs 24,774,850 + 0.06 TPC)
Solving for TPC, we have:
Total Product Cost (TPC) = Rs 754,099,750
Calculating the total revenue
UNIT TOTAL (RS)
Ethanol (Rs/L) 38.00 997,500,000
Carbon Dioxide (Rs/ton) 2291.25 19,590,187.50
Total income 1,017,090,188
Total income = Rs 1,017,090,188
Gross earnings = Total income – Total product cost
= (1,017,090,188- 754,099,750)
= Rs 262,990,437
Net earnings = Gross earning – tax paid
Whereby excise tax = 15% (MRA)
Net earnings = Rs [262,990,437 – (0.15 x 262,990,437) ] = Rs 223,541,871
Calculating Simple Payback Period
With constant revenue of Rs 223,541,871:
Simple payback period = TotalCapital Investment
Net earning=934,669,971
223,541,871=4.18
Simple payback is found to be 4.18 years.
PROFITABILITY FACTORS
Turnover ratio
The asset turnover ratio is a measure of how efficiently a company's assets generate revenue.
For production to be profitable, turnover ratio ≥ 1.
Turnover ratio = Annual Sales
¿Capital Investment
= 1017090188794469475.7
= 1.28
Thus production is said to be still profitable, increasing the chances of investing in it.
Finding internal rate of return, IRR
Total profit alone cannot be used as a determining factor for profitability (Dr D.Surroop, 2013),
another important profitability factor is the internal rate of return (IRR) which helps to compare
the time span taken to recover all investments. IRR is given by the following formula:
IRR = Net earning costs
TotalCapital Investment
To find the net earnings, the tax paid on earnings should be deducted from the gross earnings:
Net earnings = Gross earnings – excise tax
Whereby excise tax = 15% (MRA)
Net earning cost = 262990437 – (0.15 * 262990437)
= 223541871.5 MUR
Total Capital Investment (TCI) = 934669972 MUR
IRR = 2235418712934669972
= 0.239
A higher rate of return indicates less time will be taken to recover initial investments in the
project.
Net Present Value, NPV analysis
NPV is a calculation that compares the amount invested today to the present value of the future
cash receipt from the investment. If NPV<0; project should not go ahead, NPV=0; all
investments are recovered over service life and if NPV>0; project is profitable.
Finding NPV
NPV = Present value - Initial Investment
= ∑i=1
i=n
P V n - Co
Whereby P V n = Cn* 1
(1+r )n
Co = initial investment (TCI)
Cn = net cash flow at year n
r = rate of return
n = service life
Whereby n is assumed to be 10 years for a bio-ethanol plant (Technical and Economic Feasibility of Production of Ethanol from Sugarcane by L.A.M Van Der Wielen et al, 2005)
The discounted flows at an IRR of 0.239 are as shown below:
Year Annual revenue (MUR) PV (MUR)1 262990437 212231696.4
2 262990437 171269698.9
3 262990437 138213614
4 262990437 111537552.9
5 262990437 90010132.43
6 262990437 72637633.98
7 262990437 58618132.5
8 262990437 47304479.37
9 262990437 38174429.54
10 262990437 30806534.39
∑i=1
i=n
P V n-
970803904.5
Co= 934669972 MUR
NPV = ∑i=1
i=n
P V n - Co
= 970803904.5 – 934669972
= + 36,133,934 MUR
NPV being positive indicates the profitability of the investments in the bio-ethanol plant.
Finding IRR when NPV = 0 to know break-even point:
Year
Annual revenue
(MUR)
PV
IRR= 0.100
PV
IRR= 0.150
PV
IRR= 0.200
PV
IRR= 0.239
PV
IRR = 0.300
PV
IRR= 0.400
1262990437 239082215.5
228687336.
5 219158697.5
212231696.
4 202300336.2 187850312.1
2262990437 217347468.6
198858553.
5 182632247.9
171269698.
9 155615643.2 134178794.4
3262990437 197588607.8
172920481.
3 152193539.9 138213614 119704340.9 95841995.99
4262990437 179626007.1
150365635.
9 126827949.9
111537552.
9 92080262.25 68458568.57
5262990437 163296370.1
130752726.
9 105689958.3
90010132.4
3 70830970.96 48898977.55
6262990437 148451245.5
113698023.
4 88074965.24
72637633.9
8 54485362.28 34927841.11
7262990437 134955677.8
98867846.4
2 73395804.37 58618132.5 41911817.14 24948457.93
8262990437 122686979.8
85972040.3
6 61163170.31
47304479.3
7 32239859.34 17820327.09
9262990437 111533618
74758295.9
7 50969308.59
38174429.5
4 24799891.8 12728805.07
10262990437 101394198.2
65007213.8
8 42474423.82
30806534.3
9 19076839.84 9092003.62
∑i=1
i=n
P V n-
1615962388 1319888154 1102580066
970803904.
5 813045323.9 634746083.5
TCI -934669972 934669972 934669972 934669972 934669972 934669972
681292416.9
385218182.
7 167910094.5
36133933.0
7 -121624647.5 -299923888
Since IRR lies between the +NPV and –NPV, finding IRR when NPV = 0;
When NPV = 36133933.07, IRR = 0.239
When NPV = -121624647.5, IRR = 0.300
Finding IRR when NPV = 0,
IRR = (0.3−0.239 )(0−36133933.07)(−121624647.5−36133933.07)
+ 0.239
= 0.253
Discounted payback period
One of the main disadvantages of the simple payback period is that it ignores the time value of
money. To counter this limitation, an alternative method known as the discounted payback
period can be followed. In discounted payback period we have to calculate the present value of
each cash inflow taking the start of the first period as zero point.
Initial Investment = Total Capital Investment
= Rs 934669,971
Taking Rate, K = 0.1
Discounting Factor = (1+k )−n
Where n = number of years
Year Cash Inflow/ Rs
Discounting Factor
(Rate = 0.1 %)
Discounted Cash Flow/ Rs
Cumulative Discounted
Cash flow/ Rs
0 -934669971.4 1 -934669971.4 -934669971.4
1 223541871.5 0.909090909 203219883.1 -731450088.3
2 223541871.5 0.826446281 184745348.3 -546704740
3 223541871.5 0.751314801 167950316.6 -378754423.3
4 223541871.5 0.683013455 152682106 -226072317.3
5 223541871.5 0.620921323 138801914.6 -87270402.69
6 223541871.5 0.56447393 126183558.7 38913156.02
Discounted payback period = 5 + ( 87270402.69126183558.7 ) = 5.69 years