Upload
others
View
13
Download
0
Embed Size (px)
Citation preview
FINAL
AIR QUALITY ASSESSMENT
OF THE McCORMICK PIT
Prepared for:
Harrington McAvan Limited
6882 14th
Avenue
Markham, Ontario
L6B 1A8
Prepared by:
SENES Consultants Limited
121 Granton Drive, Unit 12
Richmond Hill, Ontario
L4B 3N4
February 2013
AIR QUALITY ASSESSMENT
OF THE McCORMICK PIT
Prepared for:
Harrington McAvan Limited
6882 14th
Avenue
Markham, Ontario
L6B 1A8
Prepared by:
SENES Consultants Limited
121 Granton Drive, Unit 12
Richmond Hill, Ontario
L4B 3N4
____________________________ _____________________________
Prepared by: Reviewed by:
Chris Marson, P.Eng. Abby Salb, P.Eng.
Senior Environmental Engineer Senior Environmental Engineer
February 2013
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 E-1 SENES Consultants Limited
EXECUTIVE SUMMARY
Atmospheric dispersion modelling was undertaken to determine the maximum impact of the
proposed McCormick Pit on ambient particulate matter concentrations in the area. The
AERMOD model was used to simulate the emissions of all significant sources of particulate
matter at the facility, in combination with emissions from surrounding public roads. The two
phases (Phase C and Phase D) that could most significantly affect the sensitive receptors in the
vicinity of the proposed pit were analyzed, which were based on high activity levels occurring
near sensitive receptor locations. The estimated emissions from each phase will be quite similar,
but due to the fact that the extraction pit location varies between phases, it was necessary to
model the two phases separately to properly assess the maximum impact on all of the sensitive
receptors. The maximum 24-hour and annual average dust concentrations in three size ranges
(TSP, PM10, and PM2.5) were evaluated specifically at the eight sensitive receptors located closest
to the boundary of the proposed site.
The analysis showed that even using a conservative emission scenario (i.e., an overestimate), the
applicable standards for TSP and PM2.5 were not predicted to be exceeded during site operations
at any of the nearby sensitive receptors. Exceedances of these criteria were limited to a small
area along the north edge of the property boundary.
The MOE 24 hour average Interim Guideline for PM10 was predicted to be exceeded at up to 5 of
the nearby sensitive receptors. Receptor R5, which is closest to the property boundary, was
modelled to exceed this guideline approximately 5 times per year.
Both the 30 day and annual criteria for dustfall are met at all receptors. A marginal exceedance
is predicted at the maximum location for both time averaging periods.
Due to the conservative modelling approach used in this study, and the presence of vegetation
and berms around the site, the maximum concentrations will likely be lower than predicted.
The analysis was conducted considering a reasonable level of mitigation, including efficient dust
control (e.g., watering) of unpaved roads and excavation areas as appropriate. Good dust
management practices will ensure that any effect associated with material handling and
transportation of materials is minimized. These practices are outlined in the Best Management
Plan (BMP).
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 i SENES Consultants Limited
TABLE OF CONTENTS
Page No.
EXECUTIVE SUMMARY ......................................................................................................... E-1
1.0 INTRODUCTION ........................................................................................................... 1-1
1.1 Air Quality Criteria .............................................................................................. 1-2
1.2 Dustfall Criteria ................................................................................................... 1-3
1.3 Other Criteria Air Contaminants .......................................................................... 1-4
2.0 BACKGROUND CONCENTRATIONS ........................................................................ 2-1
2.1 Air Concentrations ............................................................................................... 2-1
2.2 Dustfall Concentrations ....................................................................................... 2-2
3.0 DISPERSION MODELLING PARAMETERS .............................................................. 3-1
3.1 INTRODUCTION ............................................................................................... 3-1
3.2 Meteorology ......................................................................................................... 3-5
3.2.1 Wind ......................................................................................................... 3-5
3.2.2 Atmospheric Stability and Mixing Heights ............................................. 3-7
3.3 Modelling Terrain and Grid ................................................................................. 3-8
3.4 Particle Fallout ................................................................................................... 3-11
3.5 SOURCES OF PARTICULATE MATTER ...................................................... 3-12
3.5.1 On-site Emissions .................................................................................. 3-15
3.5.2 Local Area (Off-Site) Traffic Emissions ............................................... 3-17
4.0 MODELLING RESULTS ............................................................................................... 4-1
4.1 Total Suspended Particulate (TSP) ...................................................................... 4-1
4.2 Particulate Matter Less Than 10 Microns (PM10) .............................................. 4-11
4.3 Particulate Matter Less Than 2.5 Microns (PM2.5) ............................................ 4-14
4.4 Dustfall Deposition ............................................................................................ 4-15
4.5 Perspective on Fugitive Dust and Air Dispersion Modelling ............................ 4-17
5.0 CONCLUSIONS AND RECOMMENDATIONS .......................................................... 5-1
5.1 Conclusions .......................................................................................................... 5-1
5.2 Recommendations ................................................................................................ 5-1
6.0 REFERENCES ................................................................................................................ 6-1
APPENDIX A – DETAILED EMISSIONS TABLES
APPENDIX B – PROPOSED BEST MANAGEMENT PLAN FOR FUGITIVE DUST
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 ii SENES Consultants Limited
LIST OF TABLES
Page No.
Table 1.1 – Particulate Matter Ambient Air Quality Assessment Criteria .................................. 1-3
Table 1.2 – Dustfall Ambient Air Quality Assessment Criteria .................................................. 1-4
Table 2.1 – Particulate Matter Measurements from the Point Petre Station ................................ 2-1
Table 2.2 – Particulate Matter Measurements from the Tiverton Station .................................... 2-2
Table 2.3 – Selected Background Concentrations for TSP, PM10 and PM2.5 .............................. 2-2
Table 3.1 – Operating Phases at McCormick Pit ......................................................................... 3-3
Table 3.2 – Site Activity Timings ................................................................................................ 3-4
Table 3.3 – TSP Particle Size Distribution used for Dust Deposition Calculations .................. 3-12
Table 3.4 – Monthly Site Activity Levels .................................................................................. 3-13
Table 3.5 – Summary of Emission Sources Used in Dispersion Model .................................... 3-14
Table 4.1 – Modelled and Cumulative Maximum 24 Hour TSP Concentrations (µg/m3) .......... 4-2
Table 4.2 – Modelled and Cumulative Annual TSP Concentrations (µg/m3) ............................. 4-2
Table 4.3 – Phase C and Phase D Cumulative Exceedances in 5 Years of 24 hr TSP AAQC .... 4-7
Table 4.4 – Modelled and Cumulative Maximum 24 Hour PM10 Concentrations (µg/m3) ....... 4-12
Table 4.5 –Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline ................... 4-12
Table 4.6 – Modelled and Cumulative Maximum 24 Hour PM2.5 Concentrations (µg/m3) ...... 4-15
Table 4.7 – Maximum 30 Day Modelled and Cumulative Deposition (g/m2/30days) .............. 4-16
Table 4.8 – Maximum Annual Modelled and Cumulative Deposition (g/m2/yr) ...................... 4-16
Table A.1 – Emission Calculations ..................................................................................................1
Table A.2 – Emission Calculations ..................................................................................................2
Table A.3 – Emission Calculations ..................................................................................................2
Table A.4 – Emission Calculations ..................................................................................................2
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 iii SENES Consultants Limited
LIST OF FIGURES
Page No.
Figure 3.1 – Phase C of McCormick Pit Development ............................................................... 3-2
Figure 3.2 – Phase D of McCormick Pit Development ............................................................... 3-4
Figure 3.3 – Wind Rose (1996-2000) .......................................................................................... 3-6
Figure 3.4 – Wind Speed Class Frequency Distribution (1996-2000) ........................................ 3-7
Figure 3.5 – Terrain Data ............................................................................................................. 3-8
Figure 3.6 – Modelling Receptor Grid ....................................................................................... 3-10
Figure 3.7 – Model Discrete Receptors ..................................................................................... 3-11
Figure 3.8 – Modelled Emission Sources .................................................................................. 3-18
Figure 4.1 – Base Case Maximum 24 hr TSP Incremental Concentration (µg/m3) .................... 4-3
Figure 4.2 – Maximum 24 hr TSP Concentration with Distance from Road .............................. 4-4
Figure 4.3 – Phase C Maximum 24 hr TSP Incremental Concentration (µg/m3) ........................ 4-5
Figure 4.4 – Phase D Maximum 24 hr TSP Incremental Concentration (µg/m3) ........................ 4-6
Figure 4.5 – Maximum 24 hr TSP Cumulative Concentration with Distance North from
Maximum Location .............................................................................................................. 4-7
Figure 4.6 – Phase C Cumulative Exceedances in 5 Years of 24 hr TSP AAQC ....................... 4-8
Figure 4.7 – Phase D Cumulative Exceedances in 5 Years of 24 hr TSP AAQC ....................... 4-9
Figure 4.8 – Phase C Annual TSP Incremental Concentration (µg/m3) .................................... 4-10
Figure 4.9 – Phase D Annual TSP Incremental Concentration (µg/m3) .................................... 4-11
Figure 4.10 – Phase C Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline . 4-13
Figure 4.11 – Phase D Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline 4-14
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 1-1 SENES Consultants Limited
1.0 INTRODUCTION
SENES Consultants Limited (SENES) was retained by Harrington McAvan on behalf of
Blueland Farms Ltd. to assess the potential dust impacts of a proposed sand and gravel extraction
operation near Caledon, Ontario. The site is proposed to be located on the west side of Heart
Lake Road, approximately 500 metres north of Escarpment Side Road. The site surrounding
area is relatively flat towards the north and rolling terrain to the south. An existing aggregate pit
(Caledon Sand and Gravel) is located to the west of the site. The remainder of the lands
surrounding the site are rural residential.
SENES developed an emissions inventory for particulate matter, based on a maximum annual
extraction limit of 1,500,000 tonnes/year of gravel and related product. Particulate matter (PM)
is a term used for both solid and liquid particles of small size in the atmosphere. Primary PM is
directly emitted to the atmosphere, and secondary PM is chemically formed from other
pollutants. Particulate matter varies considerably in size. Total Suspended Particulate (TSP)
describes all particles with aerodynamic diameters less than 44 µm; PM10 describes all particles
with aerodynamic diameters less than 10 µm; and PM2.5 describes all particles with aerodynamic
diameters less than 2.5 µm. The larger diameter fraction of PM is commonly made up of crustal
material (for inland locations) and can be emitted to the atmosphere by erosion by the wind, or
disturbance of soil due to anthropogenic activity. The smaller diameter fraction of PM is most
often attributed to combustion sources. Whereas larger particulate matter tends to be deposited
relatively close to the source(s) of emission, fine particulate matter can stay airborne for days and
can be transported significant distances from the source(s). Currently, there is a provincial
ambient air quality criterion specified for TSP, but not for PM10 or PM2.5. There is however, a
(federal) Canada-Wide Standard for PM2.5, and an Ontario Ministry of the Environment (MOE)
interim guideline for PM10.
The objective of the dust impact assessment is to conservatively predict the highest levels of
airborne particulates (dust) that are likely to result from the added industrial activity at the
proposed McCormick Pit. The predicted air quality impacts were compared to relevant criteria
and guidelines, as discussed above. The potential impact of particulate matter emissions on air
quality in the vicinity of the operation was evaluated using dispersion modelling to determine
maximum predicted ambient air concentrations of total suspended particulate matter (TSP),
inhalable particulate matter (PM10), and respirable particulate matter (PM2.5). The modelling
analysis focussed on potential impacts in the vicinity of nearby residential properties, since these
will be most sensitive to any dust emissions originating from the proposed operation.
The U.S. EPA AERMOD regulatory short range air dispersion model which is an approved
model under the Ontario Ministry of the Environment (MOE) O.Reg. 419/05 (Local Air Quality)
was used with the projected emissions to predict ambient particulate matter concentrations, as
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 1-2 SENES Consultants Limited
well as dustfall, in the area surrounding the site. AERMOD is a steady-state plume model that
incorporates air dispersion based on planetary boundary layer turbulence structure and scaling
concepts, including treatment of both surface and elevated sources, and both simple and complex
terrain. It includes the capability to model emissions originating from open pit sources.
1.1 AIR QUALITY CRITERIA
1.1.1 Total Suspended Particulate (TSP)
Total Suspended Particulate (TSP) is often used to characterize air quality near a dust source.
TSP is typically measured with a high-volume (Hi-Vol) sampler over 24-hours and consists of
particles less than 44 µm in diameter. An annual average is typically calculated as the geometric
mean of these samples measured every six days.
The Ontario Ministry of the Environment (MOE) Standards Development Branch released
Ambient Air Quality Criteria (AAQC) in April 2012 (PIBS #6570e01). The AAQC for TSP is
120 µg/m3 averaged over 24-hours, and the annual geometric mean of the 24-hour samples is
60 µg/m3.
The ambient TSP standards and criteria were set to prevent a reduction in visibility. Particles
suspended in the atmosphere reduce visibility or the visual range by reducing the contrast
between an object being viewed and its background. This reduction is a result of particles
scattering or absorbing light coming from both the object and its background, and from particles
scattering light into the line of sight [Robinson, 1977]. Particles with a radius of 0.1 to 1.0 µm
are most effective at reducing visibility. In a rural area where particulate levels are on the order
of 30 µg/m3, the visibility would be about 40 km. At 150 µg/m
3, the range would be reduced to
about 8 km [Robinson, 1977]. The MOE 24-hour criterion of 120 µg/m3 is based on a visual
range of about 10 km.
1.1.2 Fine Particulate Matter (PM10 and PM2.5)
Many studies over the past few years have indicated that fine particulate matter (PM10 and PM2.5)
in the air is associated with various adverse health effects in people who already have
compromised respiratory systems such as asthma, chronic pneumonia and cardiovascular
problems. However, the available studies have not been able to link the adverse health effects in
such people to any one component of the pollution mix. PM10 is a mixture of chemically and
physically diverse dusts and droplets, and some of these components may be important in
determining the effects of PM10 on health.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 1-3 SENES Consultants Limited
Particulate Matter less than 2.5 µm – PM2.5 is known as respirable particulate as “respirable”
since the particles are generally small enough to be drawn in and deposited into the deepest
portions of the lungs. Anthropogenic sources, such as combustion of fossil fuels, tend to be the
largest contributor to PM2.5 levels in the environment.
The MOE has in Interim Guideline for PM10 of 50 µg/m3 based on a 24 hour average. In the
MOE AAQC document footnote 8 presents an ambient air quality guide for decision making for
PM2.5 of 30 µg/m3 based on a 24 hour average (based on Federal target). Table 1.1 presents the
particulate matter ambient air quality assessment criteria used in this study.
Table 1.1 – Particulate Matter Ambient Air Quality Assessment Criteria
Pollutant Averaging Period Source Air Quality Standard
(µg/m3)
TSP 24-hour AAQC 120
Annual AAQC 60
PM10 24-hour Ontario Interim Guideline 50
PM2.5 24-hour Guide for decision making 30* Note: * 98th percentile averaged over 3 years
1.2 DUSTFALL CRITERIA
Dustfall, or dust deposition, involves the settling of particles from the air due to gravitational
force. It is a total amount of dust, inclusive of all particle categories. Dustfall or dust deposition
includes those particles of sufficient weight to settle from the air by gravity. These particles are
generally larger than 20 µm in diameter. TSP deposition generally provides a good estimate of
total dustfall. The AAQC for dustfall is 7.0 g/m2/30 days for an averaging period of one month
and 4.6 g/m2/30 days for an averaging period of 1 year.
In developing an Ambient Air Quality Criterion for dustfall, the MOE used soiling data (i.e.
surface build-up of dust) from various Ontario towns between 1951 and 1955, which indicated
areas of relatively low soiling (11 – 15 g/m2/30 days), relatively moderate soiling (17-24 g/m
2/
30 days) and relatively heavy soiling (26-34 g/m2/30 days) (WHO, 1961).
Table 1.2 presents the dustfall ambient air quality assessment criteria used for this study.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 1-4 SENES Consultants Limited
Table 1.2 – Dustfall Ambient Air Quality Assessment Criteria
Pollutant Averaging Period Source Air Quality Standard
(g/m2)
Dustfall 30 Day AAQC 7
Annual AAQC 4.6
1.3 OTHER CRITERIA AIR CONTAMINANTS
Criteria Air Contaminants (CACs) including nitrogen oxides, sulphur oxides and carbon
monoxide are common pollutants released into the air by activities such as the combustion of
fossil fuels.
Nitrogen dioxide (NO2) is a reddish brown, highly reactive gas that is formed in the ambient air
through the oxidation of nitric oxide (NO). Nitrogen oxides (NOx), the term used to describe the
sum of NO, NO2 and other oxides of nitrogen play a major role in the formation of ozone.
Sulphur dioxide (SO2) is a colourless gas that smells like burnt matches. It can be oxidized to
sulphur trioxide, which in the presence of water vapour, is readily transformed to sulphuric acid
mist. SO2 can be oxidized to form acid aerosols, and is a precursor of particulate sulphates,
which are one of the main components of respirable particulates in the atmosphere (MOE, 2002).
Carbon monoxide (CO) is a colourless, odourless gas, formed when carbon in fuel is not burned
completely. It is a component of motor vehicle exhaust, which contributes about 60 percent of
all CO emissions nationwide. High concentrations of CO generally occur in areas with heavy
traffic congestion.
There are some minor sources of CACs at the proposed McCormick pit. These sources include
mobile equipment such as haul trucks and front end loaders, as well as stationary equipment such
as diesel generators. These sources are not expected to be significant contributors to
concentrations of these contaminants at nearby residential locations, due to the proximity of local
public roads (which are larger sources of these contaminants). The site is also subject to Ontario
Regulation 419/05 and as such will apply for an Environmental Compliance Approval from the
MOE. This will require that the site comply with MOE Point of Impingement standards for all
significant contaminants. As such, CACs were not included in the dispersion modelling
assessment at this time.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 2-1 SENES Consultants Limited
2.0 BACKGROUND CONCENTRATIONS
Existing air quality in the area surrounding the proposed McCormick Pit, is a combination of
emissions from sources in the area (other pits and traffic) plus a component that flows into the
area from other areas (Toronto, the USA, etc.). When a modelling assessment is completed all of
these other “background” sources must be included in order to get an accurate representation of
the air quality after the proposed McCormick Pit is in operation. Existing dust sources such as
traffic along Heart Lake Road are expected to contribute to background dust concentrations in
the area. To account directly for some of the background levels of dust, existing traffic data
developed by Sernas Transtech in April 2012 for future conditions (i.e. 2020), was used and
input into the air dispersion model. This is representative of the expected level of traffic that will
occur along Heart Lake Road once the pit is operational. In addition, historical rural background
concentrations for TSP, PM10 and PM2.5 were added to model-predicted concentrations to
capture the upwind portions of background. Consequently, the concentrations presented in this
report include potential effects from the background dust sources in the area as well as other
upwind sources.
2.1 AIR CONCENTRATIONS
The proposed McCormick Pit site will be in a rural location, therefore TSP, PM10 and PM2.5
monitoring data from a representative rural MOE air quality station would best represent the
background air quality. However, in recent years the MOE have been focusing their attention on
the monitoring of the PM2.5 size fraction only, and as such recent TSP background monitoring
data is unavailable. Data from the now-retired Point Petre MOE station were considered for
developing background concentrations as both PM2.5 and PM10 data was measured. Table 2.1
below presents latest five years of 90th
percentile 24-hour measurements for PM10 and PM2.5.
TSP concentrations were estimated by multiplying the PM10 measurements by a factor of 2. The
90th
percentile values are values that will only be exceeded 10% of the time under adverse
meteorological conditions.
Table 2.1 – Particulate Matter Measurements from the Point Petre Station
Year 90
th Percentile
PM2.5 (µg/m3)
90th
Percentile
PM10 (µg/m3)
90th
Percentile
TSP1 (µg/m
3)
Annual Average
TSP1 (µg/m
3)
2000 9 13 27 16
2001 10 15 30 17
2002 10 15 30 17
2003 11 15 30 18
2004 14 19 38 19
Average 11 16 31 17 Note: 1 TSP estimated by multiplying PM10 by 2
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 2-2 SENES Consultants Limited
As a verification that the Point Petre station data is still valid, the most recent five years of
90th
percentile data from the rural MOE Tiverton air quality station was gathered and compared.
The Tiverton station collects only the PM2.5 size fraction. Table 2.2 shows that the data from the
Point Petre station is still valid as it compares well with the most recent data from the Tiverton
station.
Table 2.2 – Particulate Matter Measurements from the Tiverton Station
Year 90th
Percentile PM2.5 (µg/m3)
2007 14
2008 13
2009 9
2010 12
2011 11
Average 12
As can be seen in Tables 2.1 and 2.2, the recent monitoring data indicates that the 90th
percentile
PM2.5 concentration is in the range of 11 – 12 µg/m3 at rural stations. The PM2.5 background
concentration used in previous assessments was 12.5 µg/m3. This indicates that the data used
previously is still valid. Historical measurements across Ontario show that PM10 is
approximately 50% of TSP. Similarly, PM2.5 measurements have historically been observed to
be 50% of PM10 measurements. As such, the background concentrations used in this assessment
were based on historical measurements of TSP and assumed PM10 and PM2.5 concentrations.
These are shown in Table 2.3 below.
Table 2.3 – Selected Background Concentrations for TSP, PM10 and PM2.5
Averaging Time Contaminant Background Concentration (µg/m
3)
TSP PM10 PM2.5
24-hour 50 25 12.5
Annual 30 n/a n/a
2.2 DUSTFALL CONCENTRATIONS
A measured background dust deposition rate was not available. However, a background value
may be estimated from a 30 day average TSP air concentration combined with an assumed
particle settling velocity. The annual TSP concentration of 30 µg/m3 presented in Table 2.3 was
used as a surrogate for the 30 day average concentration. The background deposition rate was
estimated using a settling velocity of 4 cm/s. This was added to the model predicted monthly
and annual average deposition rates.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 2-3 SENES Consultants Limited
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-1 SENES Consultants Limited
3.0 DISPERSION MODELLING PARAMETERS
3.1 INTRODUCTION
SENES used the ‘Operations Plan, Phases B-G Number 02-48’ (dated February 2013) provided
by Harrington McAvan Ltd. to obtain the details on the planned phases needed for dispersion
modelling. The Plan included the locations of the Plant Site, where processing will occur, the
on-site haul road and the adjacent public arterial Heart Lake Road. Additional information was
provided through personal communication with Harrington McAvan staff.
An emission inventory was developed for each particulate matter size fraction (TSP, PM10, and
PM2.5) and modelled separately with AERMOD using a variable spaced receptor grid as defined
in O.Reg. 419/05. An additional grid of receptors was added along the Heart Lake Road.
Nearby residences were added as ‘discrete’ receptors.
At the proposed McCormick Pit location, the water table is located at +/-405.0 - 411.0m above
sea level, which is approximately 8 to 20m below the existing grade (depending on location
within the property). The planned maximum depth of extraction is approximately 384m above
sea level. Therefore, a considerable amount of gravel will be extracted from beneath the water
table. Removal and processing of gravel when it is wet results in negligible dust emissions in
comparison to removal and processing of gravel above the water table. Therefore, material
handling emissions were only considered for phases in which above water extraction occurred
and emissions were conservatively estimated assuming total extraction and processing above the
water table. However, emissions resulting from equipment operation (i.e. tailpipe/exhaust)
during below water extraction were considered.
During the lifetime of the undertaking, the working face will be located in different regions of
the site. However, the permanent plant site and the haul road, between the permanent plant site
and Heart Lake Road, will remain fixed in one location. Figure 3.1 provides a visualization of
the McCormick Pit, showing the extraction areas. Berms will be constructed along the northwest
and northeast fence lines to reduce adverse noise and visual impacts (Figure 3.1). The berms
will be a minimum of 3m in height (berms vary in height). Of the residential dwellings near the
McCormick Pit, R5 has the greatest potential to experience elevated dust levels due to pit
operations. The berm and existing trees and shrubs surrounding R5 will act to reduce horizontal
dust transport from the Pit area.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-2 SENES Consultants Limited
Figure 3.1 – Phase C of McCormick Pit Development
During the lifetime of the Pit, there will be seven different phases of operation. During Phases E
through G, progressive rehabilitation of processed areas will occur in addition to extraction. A
basic description of each operating phase is provided in Table 3.1.
R5
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-3 SENES Consultants Limited
Table 3.1 – Operating Phases at McCormick Pit
Operating
Phase Description of Activities
A
Removal of overburden in Area 1, preparation of the permanent plant site,
construction of berm along NW fence line and along Heart Lake Road adjacent to
the archaeological site. Begin above water extraction in Area 1. Establish
processing plant and stockpiling area.
B
Removal of overburden in Area 2. Above water extraction in Area 1 and Area 2,
below water extraction in Area 1. Construction of berm along Heart Lake Road
adjacent to R5 property line. Progressive rehabilitation of side slopes and
shorelines in Area 1.
C
Removal of overburden in Area 3. Complete construction of acoustical berm
along Heart Lake Road and the acoustical berm along the east perimeter of Area 3
and Area 4. Above water extraction in Area 3, continue below water extraction in
Area 1, complete above water extraction in Area 2. Continue progressive
rehabilitation of Area 1
D
Begin removal of overburden in Area 4. Begin below water extraction in Area 3.
Complete below water extraction in Area 2. Begin above water extraction in
Area 4. Begin progressive rehabilitation of side slopes and shoreline in Area 2
and Area 3.
E
Complete below water extraction in Area 3. Continue above and below water
extraction in Area 4. Complete rehabilitation in Area 3. Begin progressive
rehabilitation in Area 4.
F Complete below water extraction for Area 4. Complete rehabilitation of Area 4.
Continue rehabilitation of Area 1 and Area 2.
G Complete all remaining rehabilitation for entire site. Note: Shaded Phases were modelled
Phases C and D were chosen to be modelled as they are the operating scenarios that potentially
will result in the highest particulate concentrations at each of the nearby sensitive receptors (due
to the proximity of the activities to these receptors). The processing plant will be permanently
located in Area 1 and the haul road (between the plant site and Heart Lake Road) will be located
in Area 1 and Area 2. Figure 3.1 (presented earlier) shows the layout for Phase C and Figure 3.2
shows the layout for Phase D. All other phases are expected to result in equivalent or lower
ground-level dust concentrations due to locations of emission sources and/or below water
extraction. The rehabilitation process is progressive throughout most phases of the project and
emissions at any point in time will be low in comparison to other on-going activities. As such
these emissions were not considered for modelling.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-4 SENES Consultants Limited
Figure 3.2 – Phase D of McCormick Pit Development
Table 3.2 shows the planned hours of operation for the McCormick Pit.
Table 3.2 – Site Activity Timings
Activity Timing
Weekdays Saturdays
Site Preparation and Rehabilitation 07:00 – 19:00 h 07:00 – 15:00 h
Excavation and Processing 07:00 – 19:00 h
Shipping 07:00 – 19:00 h 06:00 – 15:00 h
R5
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-5 SENES Consultants Limited
3.2 METEOROLOGY
The AERMOD model accepts hourly meteorological data records to define the conditions for
plume rise, transport and dispersion. The model estimates the concentration or deposition value
for each source-receptor combination, for each hour of input meteorology, and calculates
short-term averages, such as one-hour, eight-hour and 24-hour averages. The hourly averages
can also be combined into longer averages (1-month, seasonal, annual or period).
MOE prepared, AERMOD-ready Regional meteorological files applicable to the Caledon area
with “crops” land use/surface characteristics were used in this assessment. These files are
available for download from the MOE website at
http://www.ene.gov.on.ca/environment/en/industry/standards/industrial_air_emissions/air_polluti
on/STDPROD_084107.html and are based on 5 years of surface data from the Toronto Pearson
International Airport and upper air data from the National Weather Service station at Buffalo,
N.Y. The MOE prepares these data sets to ensure that meteorological data used for air
dispersion modelling assessments in Ontario is processed correctly and consistently.
3.2.1 Wind
Wind is the primary driver that carries air pollutants away from a source towards a receptor. The
direction and speed of the wind dictates the location and distance from the source that a pollutant
may travel, and the receptors that may be impacted. Higher wind speeds disperse gases and
particulates throughout the atmosphere more effectively and as a result, concentrations generally
decrease with increasing wind speed due to dilution. However, high wind speed conditions can
lead to increased wind erosion and re-suspension of surface-based dust sources. Low wind
speeds or no winds can lead to very high pollutant concentrations at ground level. Wind speed
also induces mechanical turbulence (which affects dispersion) as a result of flows around
obstacles on the surface (topography, buildings, etc.). The amount of mechanical turbulence
created depends on the roughness of the surface and the wind speed.
Figure 3.3 presents the wind rose that shows the frequency of the direction that winds blow from
for the 5 years of hourly meteorological data used in this assessment. It shows that predominant
wind directions are from the west to north.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-6 SENES Consultants Limited
Figure 3.3 – Wind Rose (1996-2000)
Figure 3.4 presents the wind speed class frequency distribution for the meteorological data used
for modelling. It shows that the predominant wind speed is in the range 3.6-5.7 m/s.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-7 SENES Consultants Limited
Figure 3.4 – Wind Speed Class Frequency Distribution (1996-2000)
3.2.2 Atmospheric Stability and Mixing Heights
Atmospheric stability is tied to vertical temperature structure, and is a measure of the amount of
vertical motion in the atmosphere, and hence its ability to mix pollutants. A stable atmosphere
has little vertical motion (is less turbulent) and cannot disperse pollutants as well as a more
turbulent, unstable atmosphere. The AERMOD model uses a series of calculated parameters to
describe the stability of the atmosphere in a continuous manner which is different than previous
models (such as the Industrial Source Complex [ISC] model) which used a series of 6 classes of
stability. In Ontario, the atmosphere is defined as having neutral stability approximately 70% of
the time. Stable conditions, which exist in Ontario about 25% of the time, can produce higher
concentrations of contaminants because of reduced turbulent mixing.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-8 SENES Consultants Limited
3.3 MODELLING TERRAIN AND GRID
The AERMOD model can take advantage of terrain information with heights being applied to all
receptors and sources. MOE prepared terrain data is used in the modelling and is presented as
Figure 3.5. It can be seen that the land elevation rises gently from the southeast to the northwest
with the Niagara Escarpment forming a distinct ridge across the modelling domain.
Figure 3.5 – Terrain Data
The AERMOD model calculates output at a series of receptors entered into the model. A
variable spaced grid was used in the assessment as specified in MOE O.Reg. 419/05 and the
MOE Air Dispersion Modelling Guidelines for Ontario. The grid spacing from middle of site is
as follows:
0-200 m 20 m
200-500 m 50 m
500-1000 m 100 m
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-9 SENES Consultants Limited
1000-2000 m 200 m
2000-5000 m 500 m
An additional series of grid points were added beside Heart Lake Road to assess the effect of
emissions due to vehicle travel. Since the modelled concentrations drop quickly from the edge
of the road, it is important to have a series of equally spaced receptors along the road or
modelling artefacts are introduced. Receptors were placed at the following distances from the
edge of the road:
50 m;
100 m, and;
150 m.
All of the variable spaced receptors that fell within the property boundary or within the right of
way of the road were removed. Figure 3.6 graphically shows the receptor grid used.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-10 SENES Consultants Limited
Figure 3.6 – Modelling Receptor Grid
A further set of discrete receptors that were labelled the same as in the noise assessment of this
pit were added to represent the location of nearby residences so that results could be presented in
tabular format. These are shown in Figure 3.7 below.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-11 SENES Consultants Limited
Figure 3.7 – Model Discrete Receptors
3.4 PARTICLE FALLOUT
Dust deposition resulting from the pit activities and traffic was also predicted using the
AERMOD model and the TSP particle size distribution shown in Table 3.5.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-12 SENES Consultants Limited
Table 3.3 – TSP Particle Size Distribution used for Dust Deposition Calculations
Particulate Matter
Class Particle Density Parameter Diameter Mass Fraction
TSP 2.0
1.6 0.181
3.9 0.112
7.8 0.205
12.7 0.205
17.2 0.097
22.1 0.10
27.4 0.10
3.5 SOURCES OF PARTICULATE MATTER
All significant sources of particulate matter were characterized and included in the emission
inventories for the gravel pit. Most of the emissions are fugitive in nature. Fugitive dust
involves the suspension of dust by material or machinery movement, or erosion by wind. The
source emissions are based on seasonal daily maximum extraction rates and include those due to
operating machinery and conveyor transfers/drops, road-based emissions due to the movement of
shipping trucks on-site, and particulate emissions due to exhaust from internal combustion
engines. Windblown dust due to the erosion of exposed surfaces was also determined and
included in the total emissions.
Since the pit does not operate during the late fall/winter/early spring, emissions were estimated
on a monthly basis, over the period of May - October. For each source, the months with the
highest activity (based on projected shipping and production) and therefore highest emission
rate, was used to determine an average hourly emission rate, which was then applied over all
daily operating hours over the entire period. The monthly activity rates (expressed in percent of
peak activity) are shown in Table 3.3 below.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-13 SENES Consultants Limited
Table 3.4 – Monthly Site Activity Levels
Month Percent of Peak Activity Level (%)
January 0
February 0
March 0
April 0
May 62.5
June 100
July 100
August 100
September 100
October 62.5
November 0
December 0
Operations will not occur at the proposed pit during the winter months due to freezing
conditions, and thus the activity level factor was set to zero. The operating hours assumed for
modelling purposes were shown earlier in Table 3.2. A summary of the individual sources
included in the dispersion modelling analysis is provided in Table 3.4. Specific individual
parameters used in the dispersion model are detailed in Tables A.1, A.2 and A.3 and can be
found in Appendix A.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-14 SENES Consultants Limited
Table 3.5 – Summary of Emission Sources Used in Dispersion Model
Activity Emission Factor Equation Units Reference Comments
Loader Travel on Unpaved Roads E24hr = 281.9 x k x (s/12)a x (W/3)b
Eannual =281.9 x k x (s/12)0.8 x (W/3)0.4 x ((365-P)/365) g/VKT
AP-42 13.2.2,
November 2006 Unpaved Roads, Permanent Plant Area
Haul Road Truck Travel on Paved Roads E24hr = k x (sL)0.91 x (W)1.02
Eannual = [k x (sL)0.91 x (W)1.02 ]x (1-P/4N) g/VKT
AP-42 13.2.1,
January 2011
Paved Haul roads
Background traffic + Product trucks on Heart Lake
Road
Paved Road, traffic counts provided by
Sernas Transtech
Scraping & Dozing
ETSP = 2.6 x (s)1.2 x (M)-1.3
EPM10 = 0.75 x 0.45 x (s)1.5 x (M)-1.4
EPM2.5 = 0.105 x 2.6 x (s)1.2 x (M)-1.3
kg/hr AP-42 Table 11.9-2,
October 1998
removes overburden – technically can be
considered a construction activity,
however emissions considered for this
study
Secondary Crushing (Controlled) TSP = 0.0006, PM10 = 0.00027 PM2.5 = 0.00005 kg/tonne AP-42, Table 11.19.2-1,
August 2004 2 at Permanent Plant, controlled
Washing/size classifying Wet - negligible emissions 1 at Permanent Plant
Screening (Controlled) TSP = 0.0011, PM10 = 0.00038 PM2.5 = 0.000025 kg/tonne AP-42, Table 11.19.2-1,
August 2004 2 at Permanent Plant, controlled
Material Drops to conveyor E = k x (0.0016) x (U/2.2)1.3 x (M/2)-1.4 kg/tonne AP-42 13.2.4, 1995 Material Drops to conveyor at working
face. Based on maximum extraction rate,
applied at actual hourly windspeed
Material Drops loading Crusher E = k x (0.0016) x (U/2.2)1.3 x (M/2)-1.4 kg/tonne AP-42 13.2.4, 1995
Material Drops loading off-site haul trucks E = k x (0.0016) x (U/2.2)1.3 x (M/2)-1.4 kg/tonne AP-42 13.2.4, 1995
Wind Erosion - Storage (Surge) Piles E = 1.9*s/1.5 kg/ha/day U.S. EPA Only applied when wind speed
> 5.4 m/s at anemometer height.
Wind Erosion - Unvegetated Areas E = 1.9*s/1.5 kg/ha/day U.S. EPA Only applied when wind speed
> 5.4 m/s at anemometer height.
Tailpipe Emissions (excavators and loaders) E10 = 0.189
g/hp-hr U.S. EPA non-road, 2011,
Tier 1
Excavator and 1 dragline at working face
feeding conveyor,
2 loaders at plant (dozers)
(dragline)
E10 = 0.252
E10 = 0.337
Tailpipe Emissions (diesel generators for crushers,
screeners and conveyors) E10 = 0.193 g/hp-hr
U.S. EPA non-road, 2011,
Tier 1
2 generators at
permanent plant
Notes: AP-42 is a U.S. EPA compilation of air contaminant emissions due to various activities. See http://www.epa.gov/ttn/chief/ap42/index.html.
EPA non-road is a compilation of (industrial) emissions from non-road activities. See above site.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-15 SENES Consultants Limited
3.5.1 On-site Emissions
In order to be conservative, a maximum emission scenario was developed to capture expected
worst-case maximum daily particulate emissions from the proposed McCormick pit. The
maximum operating scenario was based upon a maximum daily extraction rate of
10,500 tonnes/day and an hourly maximum extraction rate of 875 tonnes/hour during the summer
months. This scenario also incorporated an estimated maximum daily shipping rate of 480
trucks per day. The modelling assumed that these conditions occurred during every operational
hour throughout the months of June through September. During the months of May and
October, the activity levels were assumed to be at 62.5% of the peak levels to account for lower
product demands during these months. These assumptions highlight the conservative nature of
the assessment, as the facility is unlikely to experience maximum levels of operation on a
continuous basis.
Shipping was conservatively assumed to occur 5-days per week and part of the day on Saturdays.
Production was assumed to occur 5-days per week.
On-Site Road Dust Emissions
Silt content and fleet average vehicle weight are the most important parameters needed for
estimating fugitive roadway emissions in the Pit. The entire length of the site haul road (between
plant site and Heart Lake Road) will be paved and SENES assumed that the silt loading on the
on-site paved Haul Road was 27 g/m2, which is based on the mean total silt loading listed in
AP-42 Table 13.2.1-3 [U.S. EPA 2011] for roads at sand and gravel processing facilities. The silt
content on the unpaved routes travelled by the loaders around the processing plant (i.e. from
conveyor to stockpile, stockpile to shipping truck, etc.) was conservatively assumed to be 7.1%,
which is the mean silt content from AP-42 Table 13.2.2-1 for sand and gravel processing
material storage areas. The loaders onsite were assumed to be Caterpillar 980G front end loaders
[Caterpillar2000] having an operating weight of 29.5 tonnes and a load capacity of 21 tonnes.
Material was assumed to be transferred off-site by 21 tonne shipping trucks having a load
capacity of 39 tonnes. Raw materials were assumed to be transferred from active pits to the
permanent processing area by conveyor. While precipitation acts as a natural dust control,
modelling was undertaken excluding this effect to determine the worst case situation. As such,
annual emissions and their resulting concentrations will be overstated.
On-Site Tailpipe Emissions
Tailpipe emissions for industrial machinery and heavy-duty vehicles were included in the
fugitive emissions from the McCormick Pit. Appropriate emission factors were obtained for
each vehicle type or piece of machinery from the U.S. EPA [U.S. EPA non-Road 2010]. For
roadworthy vehicles, the emissions estimates are proportional to the total vehicle kilometres
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-16 SENES Consultants Limited
travelled per day, which were calculated from the maximum daily number of loads shipped and
the on-site road lengths. For loaders, the maximum daily extraction rate and vehicle capacity
were used to calculate the total number of kilometres the trucks would cover in a day. For the
diesel generators, the emission estimates are proportional to the generator capacities.
Material Handling and Processing Emissions
Fugitive dust emissions resulting from material handling, primarily from material drops onto
conveyors and off of vehicles and equipment, have been estimated using U.S. EPA emission
factors [U.S. EPA 2006] in conjunction with maximum hourly extraction rates. These emissions
are based on the hourly wind speed (i.e. the higher the wind speed, the higher the emissions).
The WSPEED variable emission option was used in the AERMOD model to simulate differing
levels of emissions at the different wind speeds, specified under this option.
The particulate emissions resulting from the screeners and crushers were estimated using
U.S. EPA emission factors [U.S. EPA 2006] in conjunction with the maximum hourly extraction
rate. The moisture content of the raw material extracted from similar pits in the area is typically
greater than 4%. When the moisture content is greater than 2.5%, “controlled” emission factors
may be used to estimate the emissions from screening and handling operations, since less dust is
generated from damp materials. Thus, “controlled” emission factors were used for to estimate
emissions from the primary and secondary screeners. “Controlled” AP-42 emission factor were
also used to estimate emissions from the primary crusher and secondary crushers, assuming that
a water spray1 will be used in conjunction with all crushing operations.
Wind Erosion
Wind eroded dust is typically an event-driven emission, whereby particles are not suspended
unless a sufficient wind speed is reached. As a result, wind dependent emissions were calculated
and modelled based on actual hourly wind speeds. As mentioned previously, an emission factor
equation for continuously active piles and unvegetated areas was used2. In this assessment, the
WSPEED variable emissions function was used to limit wind erosion from storage piles and
unvegetated disturbed areas to wind speeds greater than 5.4 m/s (at 10 m anemometer height).
At speeds less than 5.4 m/s it was assumed there would be no emissions caused by wind erosion.
This value of threshold wind velocity corresponds to the ground level wind speed at which wind
erosion and particulate suspension would occur for overburden type material, which is a
conservative estimate for this site, since most exposed areas would contain processed materials
1 Material moisture content has no effect on crushing emissions, since it is the spray action of a water spray which
knocks out the dust. Thus a controlled EF can only be used if a crusher is equipped with a water spray. 2 “Continuously active” piles and areas means that areas available for wind erosion are all freshly exposed, and
contain erodible particulate (e.g. surface is not crusted).
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-17 SENES Consultants Limited
(crushed and/or washed aggregate which have a reduced fines content), or a mixture of sand and
gravel.
3.5.2 Local Area (Off-Site) Traffic Emissions
Public Roadway Emissions
The only public road in the immediate vicinity of the McCormick Pit is the Heart Lake Road,
which runs adjacent to the northeast boundary of the Pit. All haul traffic leaving the Pit will turn
left (northwest) and continue along this road. Traffic volumes were obtained from existing
traffic data developed by Sernas Transtech in April 2012 for year 2020. Estimated shipping
traffic resulting from the proposed McCormick pit was added to the existing traffic, to estimate
the total emissions resulting from vehicle traffic on Heart Lake Road during future operations of
the proposed McCormick pit.
For Heart Lake Road, a default silt loading value of 0.2 g/m2 from AP-42 was used based on the
AADT counts from the Sernas Transtech Traffic Report. The AP-42 emission equation also
requires an average vehicle weight, which was estimated to be 26 tons including site traffic,
resulting in a calculated overall emission rate of 20.8 g TSP/vehicle kilometre travelled.
Based on the peak AM and PM traffic counts provided to SENES in the Traffic Report a
typically rural hourly profile was incorporated into the emissions estimates, with two peaks in
traffic flow per day.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 3-18 SENES Consultants Limited
Figure 3.8 – Modelled Emission Sources
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-1 SENES Consultants Limited
4.0 MODELLING RESULTS
A total of nine air dispersion modelling runs were conducted to predict maximum 24-hour and
annual ground-level concentrations at both sensitive receptor locations and gridded receptor
locations. Results are presented graphically as isopleths over entire modelling domain and in
tabular format at nearby model receptors presented in Figure 3.7. It should be noted that for the
24 hour average concentrations, these are the maximum modelled concentrations that occur only
once in the 5 years (1,825 days) of meteorological data used. For the tabular results, all cells that
are over the applicable criteria are shaded grey.
4.1 TOTAL SUSPENDED PARTICULATE (TSP)
24 hour TSP Concentrations
Table 4.1 presents the maximum predicted 24-hour average TSP concentrations at modelled
discrete receptors for both phases assessed based on the five years of MOE meteorological data
used. Table 4.2 presents similar results for annual concentrations.
It can be seen that including regional background and concentrations due to traffic along Heart
Lake Road the 24-hour MOE AAQC for TSP of 120 µg/m3 and the annual MOE AAQC for TSP
of 60 µg/m3
are both met at all discrete receptors except for a slight exceedance of the 24 hour
average MOE AAQC during Phase C at R5 which is essentially surrounded by the facility.
However, it should be noted that the modelling does not consider the effect of the 5 m high berm
that will be constructed around this receptor. As such, the maximum concentration is likely to be
lower in actuality. The annual TSP incremental concentrations at all of the discrete receptors are
only a small fraction of the current existing background.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-2 SENES Consultants Limited
Table 4.1 – Modelled and Cumulative Maximum 24 Hour TSP Concentrations (µg/m3)
Receptor Regional
Background
Future
Conditions -
Heart Lake
Road with
Regional
Background
Phase C Phase D
Facility
with Heart
Lake Road
Cumulative
Facility
with Heart
Lake Rd
Cumulative
R1
50
51 45 95 54 104
R2 51 31 81 31 81
R3 51 38 88 18 68
R5 52 78 128 61 111
R6 51 35 85 25 75
R7 51 17 67 18 68
R10 50 25 75 28 78
R14 50 13 63 12 62
Max 53 189 239 207 257 Note: MOE TSP 24 hour AAQC = 120 µg/m3
Table 4.2 – Modelled and Cumulative Annual TSP Concentrations (µg/m3)
Receptor
Regional
Background
(annual)
Future
Conditions -
Heart Lake
Road with
Regional
Background
Phase C Phase D
Facility
with Heart
Lake Rd
Cumulative
Facility
with Heart
Lake Rd
Cumulative
R1
30
30 2.7 33 2.5 33
R2 30 1.4 31 1.3 31
R3 30 2.0 32 1.7 32
R5 30 9.2 39 7.2 37
R6 30 2.0 32 1.7 32
R7 30 1.6 32 1.6 32
R10 30 1.4 31 1.5 32
R14 30 0.5 30 0.5 30
Max 30 21 51 21 51 Note: MOE TSP Annual AAQC = 60 µg/m3
However, Table 4.1 and Table 4.2 show that at the maximum modelled location the MOE
criteria for both the 24 hour average and annual average are exceeded. To demonstrate the
spatial distribution of the area of elevated maximum concentration several isopleths were
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-3 SENES Consultants Limited
prepared. The isopleths for TSP are presented in this report. The concentration isopleths for
PM10 and PM2.5 are very similar in shape and were not reproduced in this report.
Figure 4.1 was prepared to show the effect of the existing traffic along Heart Lake Road on the
existing 24 hour average TSP concentrations. This graphic shows the effect of TSP generated by
traffic along the road drops off quickly with distance and the maximum modelled concentration
(2.6 µg/m3) is very small in comparison to the assumed regional concentration of 50 µg/m
3. All
figures showing isopleths show the maximum modelled concentration that occurs once in the
5 years of meteorological data used in the model. These concentrations cannot occur at the same
time everywhere. For example, for receptors to the east of a source can only be influenced by
the source when the wind is blowing from the west.
Figure 4.1 – Base Case Maximum 24 hr TSP Incremental Concentration (µg/m3)
Note: Regional TSP 24 hour background = 50 µg/m3
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-4 SENES Consultants Limited
To demonstrate how quickly TSP concentrations drop off with distance maximum 24 hour
average concentrations were plotted along a line at right angles from the edge of Heart Lake
Road and presented as Figure 4.2. The graphic shows that after 100 m the maximum TSP
concentrations due to the road drops to about half of the maximum value.
Figure 4.2 – Maximum 24 hr TSP Concentration with Distance from Road
Figure 4.3 and Figure 4.4 present the maximum 24 hour average TSP incremental concentrations
isopleths for Phase C and Phase D, respectively. These isopleths include the effect of the facility
and the traffic along Heart Lake Road but do not include the regional background of 50 µg/m3.
Therefore, the 70 µg/m3 isopleth (70 + 50 = 120 µg/m
3) can be used to show the area where the
24-hour AAQC for TSP would be exceeded. It can be seen that the highest concentrations are
occurring along the north boundary of the site near where the processing plant and haul road to
gate are located. As with the concentrations due to the road traffic, the maximum 24 hour
concentrations due to the operations on site drop off quickly with distance as they are both are
low level emission sources (as opposed to stack sources). As is seen in the figures, only a
relatively small area would be above the MOE 24 hour TSP AAQC of 120 µg/m3.
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
0 100 200 300 400 500 600 700 800
Fra
cti
on
of
Co
ncen
tra
tio
n a
t E
dg
e
Distance from Edge of Road (m)
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-5 SENES Consultants Limited
Figure 4.3 – Phase C Maximum 24 hr TSP Incremental Concentration (µg/m3)
Note: Regional TSP 24 hour background = 50 µg/m3
70 µg/m3 isopleth represents areas above the AAQC of 120 µg/m3 including background
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-6 SENES Consultants Limited
Figure 4.4 – Phase D Maximum 24 hr TSP Incremental Concentration (µg/m3)
Note: Regional TSP 24 hour background = 50 µg/m3
70 µg/m3 isopleth represents areas above the AAQC of 120 µg/m3 including background
Figure 4.5 shows how quickly cumulative TSP concentrations drop off with distance maximum
24 hour average concentrations were plotted along a line north at right angles to the north
property boundary of the site. The graphic shows that after 200 m the maximum cumulative TSP
concentrations drop down to the MOE AAQC levels.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-7 SENES Consultants Limited
Figure 4.5 – Maximum 24 hr TSP Cumulative Concentration with Distance North from
Maximum Location
To help put the potential exceedances in perspective, the number of exceedances of the 24 hour
TSP AAQC were counted and are presented in Table 4.3. This table shows that despite over
100 predicted exceedances just north of the permanent plant site, there are no predicted
exceedances at any of the nearby receptors.
Table 4.3 – Phase C and Phase D Cumulative Exceedances in 5 Years of 24 hr TSP AAQC
Receptor Phase C Phase D
R1 0 0
R2 0 0
R3 0 0
R5 0 0
R6 0 0
R7 0 0
R10 0 0
R14 0 0
Max 114 118
Although the number of exceedances at the maximum location appears high, this is the total
number of predicted exceedances in a 5-year period. Figure 4.6 presents isopleths of cumulative
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
0 100 200 300 400 500 600 700 800
Fra
cti
on
of
MO
E 2
4 h
r
TS
P A
AQ
C
Distance from Property Line (m)
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-8 SENES Consultants Limited
exceedances of the MOE 24hr TSP AAQC (including background) for Phase C. It can be seen
that potential exceedances are restricted to a very small area just along the north edge of the
property boundary near the location of the permanent plant and the internal haul route. A similar
pattern for Phase D is shown in Figure 4.7.
Figure 4.6 – Phase C Cumulative Exceedances in 5 Years of 24 hr TSP AAQC
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-9 SENES Consultants Limited
Figure 4.7 – Phase D Cumulative Exceedances in 5 Years of 24 hr TSP AAQC
Annual TSP Concentrations
Figure 4.8 and Figure 4.9 present the increment annual TSP concentrations for Phase C and
Phase D, respectively. These figures better represent the overall impact of the facility. It can be
seen in comparison to the existing regional annual TSP concentration the incremental effect of
the pit operation is relatively small on an annual basis.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-10 SENES Consultants Limited
Figure 4.8 – Phase C Annual TSP Incremental Concentration (µg/m3)
Note: Regional TSP annual background = 30 µg/m3
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-11 SENES Consultants Limited
Figure 4.9 – Phase D Annual TSP Incremental Concentration (µg/m3)
Note: Regional TSP annual background = 30 µg/m3
When the estimated annual TSP background concentrations of 30 µg/m3 is added to the modelled
results presented in Figure 4.8 and Figure 4.9, no exceedances of the annual TSP AAQC were
predicted.
4.2 PARTICULATE MATTER LESS THAN 10 MICRONS (PM10)
Table 4.4 presents the maximum predicted 24-hour average PM10 concentrations at modelled
discrete receptors for both phases assessed based on the five years of MOE meteorological data
used. With the inclusion of the existing regional PM10 concentrations, the modelled maximum
24 hour PM10 concentrations are predicted to be above the MOE Interim Guideline of 50 µg/m3
at many of the receptors. However, as discussed previously, the assessment used very
conservative assumptions (i.e. maximum activity levels during all hours of operation during
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-12 SENES Consultants Limited
summer months). The predicted maximum concentrations shown in Table 4.4 are the highest
concentrations that are predicted to occur in 5 years. These maxima generally occur along the
northern property boundary of the site and not at residential locations.
Table 4.4 – Modelled and Cumulative Maximum 24 Hour PM10 Concentrations (µg/m3)
Receptor Regional
Background
Regional
with Heart
Lake Road
Phase C Phase D
Facility
with Local
Background
Cumulative
Facility
with Local
Background
Cumulative
R1
25
25 41 66 45 70
R2 25 30 55 30 55
R3 25 33 58 31 56
R5 25 55 80 46 71
R6 25 30 55 25 50
R7 25 15 40 15 40
R10 25 20 45 23 48
R14 25 10 35 9 34
Max 26 151 176 158 183 Note: MOE 24 hour Interim Guideline = 50 µg/m3
Table 4.5 presents the number of times that the criterion is exceeded at each of the discrete
receptors and at the location of the maximum concentration for Phases C and D. The maximum
location occurs right at the property boundary. It can be seen that the most impacted residential
receptor is R5 which under Phase C is predicted to have 28 days in 5 years above the MOE PM10
Interim Guideline. This is only an average of 5 days per year above this interim guideline
criterion, including background.
Table 4.5 –Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline
Receptor Phase C Phase D
R1 5 7
R2 1 1
R3 1 1
R5 28 14
R6 3 1
R7 0 0
R10 0 0
R14 0 0
Max 416 401
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-13 SENES Consultants Limited
Figure 4.10 graphically shows the cumulative exceedances in 5 years of the 24 hour PM10
Interim Guideline for Phase C. It shows that the number of predicted exceedances drops off very
quickly with distance from the site. Figure 4.11 presents the same data for Phase D with similar
patterns.
Figure 4.10 – Phase C Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-14 SENES Consultants Limited
Figure 4.11 – Phase D Cumulative Exceedances in 5 Years of 24 hr PM10 Interim Guideline
4.3 PARTICULATE MATTER LESS THAN 2.5 MICRONS (PM2.5)
Table 4.6 presents the maximum predicted 24-hour average PM2.5 concentrations at modelled
discrete receptors for both phases assessed based on five years of MOE meteorological data
used. With the inclusion of the existing regional PM2.5 concentrations, the modelled maximum
24 hour PM2.5 concentrations are below the MOE Guideline of 30 µg/m3 at all of the receptors.
The Canada Wide Standard is based on the 98th
percentile of all daily averages for a year and
averaged over 3 years. As a surrogate of this type of calculation, the maximum 24 hour average
concentration was determined and the model was rerun for that year only and the 98th
percentile
(8th
highest) concentration at the maximum location was determined. Table 4.6 shows that at the
maximum location the Canada Wide Standard is only marginally exceeded. The PM2.5 24 hour
criterion will be met at all residential receptors including existing background.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-15 SENES Consultants Limited
Table 4.6 – Modelled and Cumulative Maximum 24 Hour PM2.5 Concentrations (µg/m3)
Receptor Regional
Background
Regional
with Heart
Lake Road
Phase C Phase D
Facility
with Local
Background
Cumulative
Facility
with Local
Background
Cumulative
R1
12.5
13 10 23 10 23
R2 13 9 21 8 21
R3 13 10 22 8 21
R5 13 14 26 11 24
R6 13 10 22 8 20
R7 13 5 17 4 17
R10 13 6 18 6 18
R14 13 2 15 2 15
Max 13 38 51 34 47
Max 8th
13 19 32 19 31 Note: MOE 24 hour Assessment Value = 30 µg/m3
4.4 DUSTFALL DEPOSITION
Table 4.7 presents the maximum predicted 30 day dustfall deposition rates modelled at the
discrete receptors for both phases assessed based on the five years of MOE meteorological data
used. It can be seen that with the inclusion of the estimate of the existing regional dustfall rates,
the modelled maximum monthly dustfall rates are below the MOE Assessment criteria of
7 g/m2/30days at all of the receptors and is only marginally exceeded at the maximum location.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-16 SENES Consultants Limited
Table 4.7 – Maximum 30 Day Modelled and Cumulative Deposition (g/m2/30days)
Receptor Regional
Background
Regional
with Heart
Lake Road
Phase C Phase D
Facility
with Local
Background
Cumulative
Facility
with Local
Background
Cumulative
R1
3.1
3.1 0.5 3.6 0.4 3.5
R2 3.1 0.2 3.3 0.2 3.3
R3 3.1 0.3 3.4 0.3 3.4
R5 3.1 2.4 5.5 1.6 4.7
R6 3.1 0.6 3.7 0.5 3.6
R7 3.1 0.3 3.4 0.4 3.5
R10 3.1 0.2 3.3 0.2 3.3
R14 3.1 0.1 3.2 0.1 3.2
Max 3.1 4.0 7.1 4.1 7.2 Note: MOE Dustfall monthly AAQC = 7g/m2/30days
Table 4.8 shows that only at the maximum location is the annual MOE criteria of
4.6 g/m2/30days marginally exceeded when the estimated regional background deposition rate is
included.
Table 4.8 – Maximum Annual Modelled and Cumulative Deposition (g/m2/yr)
Receptor Regional
Background
Regional
with Heart
Lake Road
Phase C Phase D
Facility
with Local
Background
Cumulative
Facility
with Local
Background
Cumulative
R1
3.1
3.1 0.2 3.3 0.2 3.3
R2 3.1 0.1 3.2 0.1 3.2
R3 3.1 0.1 3.2 0.1 3.2
R5 3.1 0.8 3.9 0.6 3.7
R6 3.1 0.2 3.3 0.1 3.2
R7 3.1 0.1 3.2 0.1 3.2
R10 3.1 0.1 3.2 0.1 3.2
R14 3.1 0.0 3.1 0.0 3.1
Max 3.1 1.6 4.7 1.7 4.8 Note: MOE Dustfall Annual AAQC = 4.6g/m2/30days
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 4-17 SENES Consultants Limited
4.5 PERSPECTIVE ON FUGITIVE DUST AND AIR DISPERSION MODELLING
In summary, the dispersion modelling results indicate that the maximum expected activity at the
proposed McCormick Pit during any of the two phases assessed will not result in any
exceedances of the relevant Provincial or Federal standards for TSP, or PM2.5 at any of the eight
nearby discrete residential receptor locations. The PM10 criterion was predicted to be exceeded
at some of the residential locations, but this was shown to be limited to a maximum of 28 times
in 5 years (or approximately 5 times per year). There were some predicted concentrations that
exceed the applicable standards, for TSP, PM10, and PM2.5 at small non-sensitive areas
off-property, primarily along the northern property boundary of the site, which is in close
proximity to the processing plant. However, due to the conservative nature of the assessment,
the model predicted concentrations are expected to be greater than those that will likely occur in
reality.
A comprehensive review of fugitive dust and air dispersion modelling was conducted in 1998
involving a panel of experts including several members of the U.S. EPA [Watson and Chow,
2000]. One of the statements the panel made was to indicate that suspendable particles are not
necessarily transportable particles, and that the majority (60-90%) of suspended TSP and PM10
remains within one to two metres above the ground. As a result, deposition to the ground or
impaction to a vertical structure occurs within a few minutes of suspension.
Although the development of a vegetated barrier (berm and trees) along the east and north
property boundary would likely have a significant impact on ambient dust concentrations beyond
the property fenceline, models such as ISC currently are not able to parameterize such a feature.
Indeed, one of the suggestions from the workshop mentioned above was to account for the fact
that (AP-42) road emission factors can over estimate effective emissions from these sources. In
addition, the workshop concluded that
“there is insufficient accounting for deposition losses and horizontal impaction in
dispersion models”
Since up to 90% of the horizontal flux of suspended dust will remain within 2 m of the ground, it
is probable that most of this amount will be prevented from being transported up and over a
berm, particularly if there is sufficient vegetation to act as an impaction source.
As a result, SENES proposes that the required berms surrounding the property on the east and
north sides be adequately vegetated with species of varying heights to act as an impaction source.
This is expected to significantly reduce the transport of fugitive dust from the pit area, and has
been incorporated into the study recommendations, and the proposed Dust Management Plan
(DMP) for the site, which is presented in Appendix B.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 5-1 SENES Consultants Limited
5.0 CONCLUSIONS AND RECOMMENDATIONS
5.1 CONCLUSIONS
AERMOD air dispersion modelling was undertaken following MOE dispersion modelling
guidelines for two phases of the pit operation that were anticipated to have the maximum impact
of the nearby sensitive receptors. The modelling represented the maximum operation during the
operating months of May to October. It is not possible to model the mitigating impacts of berms,
trees and bushes as the site is progressively rehabilitated. As a result, the actual impacts from
this pit are expected to be lower than modelled.
The analysis illustrated that even considering a very conservative emissions scenario (e.g. a
likely overestimate of emissions), the potential for significant impacts at nearby receptors has
been minimized. The predicted maximum 24 hour average cumulative TSP and PM2.5
concentrations, as well as dustfall are below the MOE AAQC at all residential receptors. There
are some marginal exceedances of these criteria at non-residential locations limited to a small
area along the north edge of the property boundary. No exceedances of the annual average TSP
criterion were predicted to occur.
The MOE 24 hour average Interim Guideline for PM10 was predicted to be exceeded at up to 5 of
the nearby sensitive receptors. The model results indicated that the concentrations at
Receptor R5 could exceed this guideline approximately 5 times per year. This residential
receptor is the most impacted sensitive receptor, as it is located immediately adjacent to the
property line. This is not surprising, given that the PM10 Interim guideline is more stringent than
those for either TSP or PM2.5. However, the frequency of occurrence of these exceedances is
predicted to be relatively low, and as such should not pose a significant problem.
5.2 RECOMMENDATIONS
The analysis was conducted considering a reasonable level of mitigation, including efficient dust
control (e.g., watering) of unpaved roads and excavation areas as appropriate. The intent is to
ensure that only limited amounts of dust are carried out of the site. In addition, good dust
management practices will ensure that any effect associated with material handling and
transportation of materials is minimized. These practices are outlined in the Best Management
Plan (BMP) that is presented in Appendix B.
In order to ensure that the conclusions of this study remain valid, the following recommendations
are made:
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 5-2 SENES Consultants Limited
dust mitigation activities on site shall meet or exceed those used in this assessment,
particularly for the site main entrance road, which shall be paved or hard surfaced with
recycled asphalt product;
any on-site roads that are paved to reduce dust emissions shall be kept clean and free of
dust through water flushing, as appropriate;
vehicle speeds on all on-site haul roads shall remain at 20 km/h or less.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 6-1 SENES Consultants Limited
6.0 REFERENCES
Aercoustics Engineering Ltd. 2013. The Potential Impact of Noise from Aggregate Extraction &
Processing at the Proposed McCormick Pit. February.
Canadian Council of Ministers of the Environment (CCME) 2000. Canada-Wide Standards for
Particulate Matter (PM) and Ozone. Endorsed by CCME Council of Ministers, June
5-6, Quebec City, 10 pp.
Caterpillar Inc. 2000. Caterpillar Performance Handbook.
Ministry of Environment (MOE) 2009. Air Dispersion Modelling Guideline for Ontario.
Version 2.0. March.
Ministry of the Environment (MOE) 2009. Ontario Regulation 419/05 – Air Pollution – Local
Air Quality – amended
Ontario Ministry of Environment (MOE) 2012. Ontario’s Ambient Air Quality Criteria
(PIBS#6570e01) Standards Development Branch.
Robinson, E. 1977. Air Pollution (3rd
Edition), Vol. 2, A.C. Stein (Ed.).
Sernas Transtech 2012. Traffic Impact Study Update: Proposed McCormick Gravel Pit, Town of
Caledon, Ontario.
United Stated Environmental Protection Agency (U.S. EPA) 2010. Exhaust and Crankcase
Emission Factors for Nonroad Engine Modelling – Compression – Ignition. .
United States Environmental Protection Agency 2006. Compilation of Air Pollutant Emission
Factors AP-42, Fifth Edition, Volume I: Stationary Point and Area Sources. S-13.2.1,
S-13.2.2, S-13.2.4. November.
Watson, J.G., and J.C. Chow 2000. Reconciling Urban Fugitive Dust Emissions Inventory and
Ambient Source Contribution Estimates: Summary of Current Knowledge and Needed
Research. Desert Research Institute, DRI Document No. 6110.4F, May, 2000.
World Health Organization (WHO) 1961. Air Pollution. Monograph Series #46. pp, 124-128.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 SENES Consultants Limited
APPENDIX A
DETAILED EMISSIONS TABLES
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 A-1 SENES Consultants Limited
Table A.1 – Emission Calculations
On-Site Road TrafficK (g/VKT)
PM30
K (g/VKT)
PM10
K (g/VKT)
PM2.5
sL
(g/m2)W (tons) a for TSP a for PM10,2.5 b for TSP
b for
PM10,2.5p (days/yr) TSP (g/VKT)
PM10
(g/VKT)
PM2.5
(g/VKT)
Total # Passes
per day
Road
Length
(km)
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Heart Lake Road North - including site traffic - paved road 3.23 0.62 0.15 0.2 26.10 0.65 1.5 21 3.99 0.97 1690 1.978 0.805 0.15 0.037
Heart Lake Road South - no site traffic - paved road 3.23 0.62 0.15 0.2 4.11 0.65 1.5 3.2 0.61 0.15 730 1.058 0.028 0.005 0.0013
Heart Lake Road North - existing traffic only - paved road 3.23 0.62 0.15 0.2 4.11 0.65 1.5 3.2 0.61 0.15 730 1.978 0.053 0.010 0.0024
On site Haul Road (assumed all in pit) - paved road 3.23 0.62 0.15 8.2 42.82 0.65 0.90 1.5 0.45 1012 194.22 46.99 960 0.400 8.30 1.59 0.386
On-Site Non-Road TrafficK (g/VKT)
PM30
K (g/VKT)
PM10
K (g/VKT)
PM2.5
s % W (tons)a for
TSP*b for TSP M (%) p (days/yr) Units TSP (g/VKT)
PM10
(g/VKT)
PM2.5
(g/VKT)
Total # Trips
per hr
Length
(km/hr)
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Loader - Permanent Plant to Shipping Truck AND PLANT 1381.31 422.85 42.285 7.1 44 0.7 0.45 4.8 g/VKT 3205 883 88 84 3.3 2.98 5.27 0.53
Loader - Permanent Plant to Shipping Truck w/ precip. 1381.31 422.85 42.285 7.1 44 0.7 0.45 4.8 145.5 g/VKT 1927 531 53 84 3.3 1.79 3.17 0.32
Bulldozer - Removes overburden s % M (%) p (days/yr) Units TSP (kg/hr) PM10
(kg/hr)
PM2.5
(kg/hr)
% of Operating
Hours Active
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Bulldozer - Removes overburden 7.1 4.8 kg/hr 3.54 0.71 0.37 50.00% 0.49 0.10 0.05
Material Handling - non-wind dependentK
PM30
K
PM10
K
PM2.5
a b M (%) U (m/s) TSP (kg/tonne)PM10
(kg/tonne)
PM2.5
(kg/tonne)
Tonnes Loaded
per Hour
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Excavator - working face - drop onto conveyor 0.74 0.35 0.053 1.3 -1.4 4.8 1.54 0.00022 0.00010 0.00002 875 0.053 0.025 0.0038
Conveyor Transfer Points 0.00007 0.00002 0.00001 875 0.017 0.006 0.0016
Conveyor Drop - onto surge pile 0.74 0.35 0.053 1.3 -1.4 4.8 1.54 0.00022 0.00010 0.00002 875 0.053 0.025 0.0038
Loader - Loading material into screener 0.74 0.35 0.053 1.3 -1.4 4.8 1.54 0.00022 0.00010 0.00002 875 0.053 0.025 0.0038
Loader - Loading from pile to truck 0.74 0.35 0.053 1.3 -1.4 4.8 1.54 0.00022 0.00010 0.00002 875 0.053 0.025 0.0038
Crushing & ScreeningK (g/VKT)
PM30
K (g/VKT)
PM10
K (g/VKT)
PM2.5
a b M (%) U (m/s) TSP (kg/tonne)PM10
(kg/tonne)
PM2.5
(kg/tonne)
Tonnes Loaded
per Hour
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Primary Crusher Controlled 0.00060 0.00027 0.00005 875 0.1458 0.0656 0.01215
Primary Screener Controlled 0.0011 0.00037 0.000025 875 0.2674 0.0899 0.00608
Secondary Crusher - controlled 0.00060 0.00027 0.00005 438 0.0729 0.0328 0.00608
Secondary Screener - Controlled 0.0011 0.00037 0.000025 438 0.13 0.05 0.003
Tailpipe Emissions(g/hp-hr)
PM30
(g/hp-hr)
PM10
(g/hp-hr)
PM2.5TAF
SPM Adj
g/hp.hr
BSFC
(lb/hp.hr)
Power Rating
(hp)
Average
Speed
(km/h)
Road Length
(km)
Total # Passes
per day
Hours of
Operation per
Day
TSP (g/VKT) PM10 (g/VKT)PM2.5
(g/VKT)
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Heart Lake Road - including site traffic - paved road 1.9775 1690 24 0.0328 0.0328 0.0162 1.27E-03 1.27E-03 6.28E-04
Heart Lake Road - existing traffic only - paved road 1.9775 730 24 0.0159 0.0159 0.0076 2.66E-04 2.66E-04 1.27E-04
On site Haul Road (assumed all in pit) - unpaved road 0.40 960 13 0.04558 0.04558 0.0231 3.74E-04 3.74E-04 1.89E-04
Excavators- Working Face 0.189 0.189 0.189 1.23 0.058 1.01 316 NA NA NA 12.00 0.0166 0.0166 0.0166
Loader - Loading material into crusher 0.189 0.189 0.189 1.23 0.058 1.01 316 NA NA NA 12.00 0.0166 0.0166 0.0166
Dozer - removing overburden 0.252 0.252 0.252 1.23 0.058 1.01 230 NA NA NA 6.00 0.0161 0.0161 0.0161
Dragline at working face 0.337 0.337 0.337 1.97 0.058 1.01 316 NA NA NA 12.00 0.0296 0.0296 0.0296
Loader - Loading from pile to truck 0.189 0.189 0.189 1.23 0.058 1.01 316 NA NA NA 12.00 0.0166 0.0166 0.0166
Diesel Generator - Permanent Plant (Wash Ponds) 0.193 0.193 0.193 1 0.021 0.367 600 NA NA NA 12.00 0.0322 0.0322 0.0322
Diesel Generator - Crusher (Permanent Plant) 0.193 0.193 0.193 1 0.021 0.367 600 NA NA NA 12.00 0.0322 0.0322 0.0322
Wind Erosion - non wind dependentK
PM30
K
PM10
K
PM2.5s % f % Disturbed area (ha)
TSP Adh.
(kg/ha/day)
PM10
(kg/ha/day)
PM2.5
(kg/ha/day)
Uncontrolled TSP
(g/s)
Uncontrolled PM10
(g/s)
Uncontrolled PM2.5
(g/s)
Wind Erosion - Stockpile before Processing Plant (Surgepile) 1.00 0.50 0.075 3.58 50 2.87 2.27 1.13 0.17 0.0753 0.0377 0.0056
Wind Erosion - Unwashed Final Stockpile 1.00 0.50 0.075 5.99 50 1.44 3.79 1.90 0.28 0.0630 0.0315 0.0047
Wind Erosion - Stockpile at working face 1.00 0.50 0.075 3.58 75 0.72 3.40 1.70 0.26 0.0282 0.0141 0.0021
Wind Erosion - Unvegetated Area - Permanent Plant 1.00 0.50 0.075 7.1 75 2.25 6.75 3.37 0.51 0.1759 0.0879 0.0132
Wind Erosion - Unvegetated Area - Area 2 1.00 0.50 0.075 7.1 50 1.77 4.50 2.25 0.34 0.0919 0.0460 0.0069
Wind Erosion - Unvegetated Area - Area 3 -Phase C 1.00 0.50 0.075 7.1 50 1.10 4.50 2.25 0.34 0.0575 0.0287 0.0043
Wind Erosion - Unvegetated Area - Area 3 -Phase D 1.00 0.50 0.075 7.1 50 2.21 4.50 2.25 0.34 0.1149 0.0575 0.0086
Wind Erosion - Unvegetated Area - Area 4 1.00 0.50 0.075 7.1 50 1.19 4.50 2.25 0.34 0.0621 0.0310 0.0047
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 A-2 SENES Consultants Limited
Table A.2 – Emission Calculations Table A.3 – Emission Calculations
Table A.4 – Emission Calculations
PP Sources
Controlled
TSP
(g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s)
AREA3 Sources Controlled
TSP (g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s)
On-Site Road Traffic Materials Handling: non-wind dependent portion
On site Haul Road (assumed 1/3rd all in pit) - paved road 0.14 0.0266 0.0064 Excavator - working face - drop onto conveyor 0.0528 0.0250 0.0038
On site Haul Road (assumed 1/3rd all in pit) - paved road w/ precip 0.12 0.0239 0.0058 Conveyor Transfer Points 0.0170 0.0056 0.0016
On-Site Non-Road Traffic Dozer / Scraping
2 Loaders - Permanent Plant (truck loading AND plant loading) 0.30 0.5272 0.0527 Bulldozer - Removes overburden 0.4911 0.0981 0.0516
2 Loaders - Permanent Plant to Shipping Truck AND Plant w/ precip. - controlled0.18 0.3171 0.0317 Tailpipe Emissions
Materials Handling: non-wind dependent portion Excavators- Working Face 0.0166 0.0166 0.0166
Conveyor Transfer Point 0.0170 0.0056 0.0016 Dozer - removing overburden 0.0161 0.0161 0.0161
Conveyor Drop onto Surge Pile 0.0528 0.0250 0.0038 Wind Erosion: non-wind dependent portion
Loader - Loading material into crusher 0.0528 0.0250 0.0038 Wind Erosion - Stockpile at working face 0.02824 0.01412 0.00212
Loader - Loading from pile to truck 0.0528 0.0250 0.0038 Wind Erosion - Unvegetated Area - Area 3 -Phase C 0.05745 0.02873 0.00431
Crushing & Screening
Primary Crusher Controlled 0.1458 0.0656 0.0122
Primary Screener Controlled 0.2674 0.0899 0.0061
Secondary Crusher - controlled 0.0729 0.0328 0.0061
Secondary Screener - Controlled 0.1338 0.0450 0.0030 Permanent Plant Production & Shipping Emissions (g/s) 1.2270 0.9026 0.1595
Tailpipe Emissions PP Annual Production & Shipping Emissions (g/s) 1.0946
On site Haul Road (assumed 1/3 all in pit) - unpaved road 0.00012 0.00012 0.00006
Loader - Loading material into crusher 0.0166 0.0166 0.0166 PP Wind Erosion Emissions (g/s) 0.3142 0.1571 0.0236
Loader - Loading from pile to truck 0.0166 0.0166 0.0166
Diesel Generator - Permanent Plant (Wash Ponds) 0.0322 0.0322 0.0322 Area2 Production Emissions (g/s) 0.0855 0.0576 0.0364
Diesel Generator - Crusher (Permanent Plant) 0.0322 0.0322 0.0322
Wind Erosion: non-wind dependent portion Area2 Wind Erosion Emissions (g/s) 0.1202 0.0601 0.0090
Wind Erosion - Stockpile before Processing Plant (Surgepile) 0.07532 0.03766 0.00565
Wind Erosion - Unwashed Final Stockpile 0.06301 0.03150 0.00473 Area3 Wind Erosion Emissions (g/s) 0.0575 0.0287 0.0043
Wind Erosion - Unvegetated Area - Permanent Plant 0.17589 0.08794 0.01319
Scraping/Dozing Source
AREA2 Sources
Controlled
TSP
(g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s) Dozer working near Pit3 (g/s) 0.1755 0.0805 0.0129
On-Site Road Traffic
On site Haul Road (assumed 2/3rd all in pit) - paved road 0.28 0.05 0.01
Emission
Factor
Seasonal
Multiplier
Tailpipe Emissions Bulldozing
On site Haul Road (assumed 2/3 all in pit) - unpaved road 0.00025 0.00025 0.00013 Winter 0.00
Dragline at working face 0.02960 0.02960 0.02960 Spring 1.00
Wind Erosion: non-wind dependent portion Summer 0.00
Wind Erosion - Unvegetated Area - Area 2 0.09193 0.04597 0.00689 Fall 0.00
1.00
0.67
0.00
Season
Production & Shipping
0.67
PP Sources
Controlled
TSP
(g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s)
AREA 4 Sources Controlled
TSP (g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s)
On-Site Road Traffic Materials Handling: non-wind dependent portion
On site Haul Road (assumed 1/3rd all in pit) - paved road 0.14 0.0266 0.0064 Excavator - working face - drop onto conveyor 0.0528 0.0250 0.0038
On site Haul Road (assumed 1/3rd all in pit) - paved road w/ precip 0.12 0.0239 0.0058 Conveyor Transfer Points 0.0170 0.0056 0.0016
On-Site Non-Road Traffic Dozer / Scraping
2 Loaders - Permanent Plant (truck loading AND plant loading) 0.30 0.5272 0.0527 Bulldozer - Removes overburden 0.4911 0.0981 0.0516
2 Loaders - Permanent Plant to Shipping Truck AND Plant w/ precip. - controlled0.18 0.3171 0.0317 Tailpipe Emissions
Materials Handling: non-wind dependent portion Excavators- Working Face 0.0166 0.0166 0.0166
Conveyor Transfer Point 0.0170 0.0056 0.0016 Dozer - removing overburden 0.0161 0.0161 0.0161
Conveyor Drop onto Surge Pile 0.0528 0.0250 0.0038 Wind Erosion: non-wind dependent portion
Loader - Loading material into crusher 0.0528 0.0250 0.0038 Wind Erosion - Stockpile at working face 0.02824 0.01412 0.00212
Loader - Loading from pile to truck 0.0528 0.0250 0.0038 Wind Erosion - Unvegetated Area - Area 4 0.06209 0.03104 0.00466
Crushing & Screening
Primary Crusher Controlled 0.1458 0.0656 0.0122
Primary Screener Controlled 0.2674 0.0899 0.0061
Secondary Crusher - controlled 0.0729 0.0328 0.0061
Secondary Screener - Controlled 0.1338 0.0450 0.0030 Permanent Plant Production & Shipping Emissions (g/s) 1.2270 0.9026 0.1595
Tailpipe Emissions PP Annual Production & Shipping Emissions (g/s) 1.0946
On site Haul Road (assumed 1/3 all in pit) - unpaved road 0.00012 0.00012 0.00006
Loader - Loading material into crusher 0.0166 0.0166 0.0166 PP Wind Erosion Emissions (g/s) 0.3142 0.1571 0.0236
Loader - Loading from pile to truck 0.0166 0.0166 0.0166
Diesel Generator - Permanent Plant (Wash Ponds) 0.0322 0.0322 0.0322 Area2 Production Emissions (g/s) 0.0855 0.0576 0.0364
Diesel Generator - Crusher (Permanent Plant) 0.0322 0.0322 0.0322
Wind Erosion: non-wind dependent portion Area2 Wind Erosion Emissions (g/s) 0.1202 0.0601 0.0090
Wind Erosion - Stockpile before Processing Plant (Surgepile) 0.07532 0.03766 0.00565
Wind Erosion - Unwashed Final Stockpile 0.06301 0.03150 0.00473 Area3 Wind Erosion Emissions (g/s) 0.0575 0.0287 0.0043
Wind Erosion - Unvegetated Area - Permanent Plant 0.17589 0.08794 0.01319
Scraping/Dozing Source
AREA2 Sources
Controlled
TSP
(g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s) Dozer working near Pit3 (g/s) 0.1755 0.0805 0.0129
On-Site Road Traffic
On site Haul Road (assumed 2/3rd all in pit) - paved road 0.28 0.05 0.01
Emission
Factor
Seasonal
Multiplier
Tailpipe Emissions Bulldozing
On site Haul Road (assumed 2/3 all in pit) - unpaved road 0.00025 0.00025 0.00013 Winter 0.00
Spring 1.00
AREA3 Sources
Controlled
TSP
(g/s)
Controlled
PM10
(g/s)
Controlled
PM2.5
(g/s) Summer 0.00
Tailpipe Emissions Fall 0.00
Dragline at working face 0.02960 0.02960 0.02960
Wind Erosion: non-wind dependent portion
Wind Erosion - Unvegetated Area - Area 3 -Phase D 0.11490 0.05745 0.00862
0.67
Season
Production & Shipping
0.00
0.67
1.00
Dispersion Modelling Source Source Type
TS
P (
g/s
)
PM
10
(g
/s)
PM
2.5
(g
/s)
Heart Lake Road (North) - Current Volume (HLRDNORTH) 0.0527 0.0101 0.0024
Heart Lake Road (North) - All Phases Volume (HLRDNORTH) 0.8047 0.1545 0.0374
Heart Lake Road (South) - Current + All Phases Volume (HLRDSOUTH) 0.0282 0.0054 0.0013
Phase C - PP - Processing (A) OpenPit (OPITPLNTA) 1.1536 0.8849 0.1841
Phase C - PP - Material Handling - Wind Dependant (B) OpenPit (OPITPLNTB) 0.1755 0.0805 0.0129
Phase C - PP - Wind Erosion (C) OpenPit (OPITPLNTC) 0.3142 0.1571 0.0236
Phase C - Area 2 - Processing (A) OpenPit (OPIT2A) 0.3066 0.0830 0.0426
Phase C - Area 2 - Wind Erosion (C) OpenPit (OPIT2C) 0.0919 0.0460 0.0069
Phase C - Area 3 - Processing (A) OpenPit (OPIT3A) 0.5238 0.1307 0.0842
Phase C - Area 3 - Material Handling (B) OpenPit (OPIT3B) 0.0698 0.0306 0.0054
Phase C - Area 3 - Wind Erosion (C) OpenPit (OPIT3C) 0.0857 0.0428 0.0064
Phase D - PP - Processing (A) OpenPit (OPITPLNTA) 1.1536 0.8849 0.1841
Phase D - PP - Material Handling - Wind Dependant (B) OpenPit (OPITPLNTB) 0.1755 0.0805 0.0129
Phase D - PP - Wind Erosion (C) OpenPit (OPITPLNTC) 0.3142 0.1571 0.0236
Phase D - Area 2 - Processing (ROAD) (A) OpenPit (OPIT2A) 0.2770 0.0534 0.0130
Phase D - Area 3 - Processing (A) OpenPit (OPIT3A) 0.0296 0.0296 0.0296
Phase D - Area 3 - Wind Erosion (C) OpenPit (OPIT3C) 0.1149 0.0575 0.0086
Phase D - Area 4 - Processing (A) OpenPit (OPIT4A) 0.5238 0.1307 0.0842
Phase D - Area 4 - Material Handling (B) OpenPit (OPIT4B) 0.0698 0.0306 0.0054
Phase D - Area 4 - Wind Erosion (C) OpenPit (OPIT4C) 0.0903 0.0452 0.0068
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 SENES Consultants Limited
APPENDIX B
PROPOSED BEST MANAGEMENT PLAN
FOR FUGITIVE DUST
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 B-1 SENES Consultants Limited
B.0 BEST MANAGEMENT PLAN
The following presents potential sources of fugitive dust at the McCormick Pit as well as actions
to control and mitigate these sources.
B.1 POTENTIAL SOURCES OF FUGITIVE DUST
Due to the nature of activities at a sand and gravel operation, there are several on-site sources at
the McCormick Pit that could potentially contribute to fugitive dust emissions. These are as
follows:
Truck travel on site entrance road
Loader travel on unpaved haul routes
material processing and handling (conveying, loading, crushing and screening of
aggregate)
stockpiling (raw and processed materials)
The fugitive dust generated by these sources and activities arises from processing or pulverizing
crustal materials, and thus generally does not have significant amounts of other contaminants
associated with it. Also, a significant portion of the fugitive dust from these sources is in the
coarse fraction which tends to result in nuisance effects; only a small fraction of the dust is in the
respirable range, which is of most concern from a health perspective.
In many instances, fugitive dust emissions are dependent on the wind speed at any given time as
well as the activity rates. Thus the amount of effort necessary to control such emissions is
greater during windy conditions in comparison to calm conditions.
B.2 REQUIRED CONTROL ACTIONS
In general, most approaches for controlling fugitive dust involve the application of water to
prevent the fugitive emissions from being generated. Depending on the source, there are other
measures that are used to remove the source of the dust, and/or reduce the impact of the
emissions when they occur. These are discussed in the following sections.
B.2.1 Application of Water to the Site Entrance Road and Internal Haul Route
As required by the Ministry of Natural Resources (MNR), water and/or calcium chloride will be
applied to the site entrance road and internal haul/loader routes to mitigate fugitive dust. In the
assessment, sufficient water was assumed to be applied to achieve a control efficiency of 90% on
all unpaved site roads travelled by non-road equipment (loaders, rock trucks, etc) and by product
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 B-2 SENES Consultants Limited
trucks that will be used to ship finished materials off site. These levels of control are reasonably
achievable, and necessary to prevent excessive off-site emissions.
In order to achieve the level of control that is required to meet the assumptions that were used in
the completion of this study, the following elements should be included this Best Management
Plan:
all unpaved roads should be watered at a sufficient frequency to control dust generation
due to vehicle travel;
vehicle speeds on unpaved haul roads should remain at 20 km/h or less;
the site entrance road and roads leading to Heart Lake Road should be hard surfaced to
reduce dust emissions and prevent track-out;
a site water truck should be equipped with both drip/spray bars to water unpaved roads,
and;
any on-site paved roads should be cleaned periodically using high pressure flushing with
a canon spray and/or vacuum sweeping (as practicable) to prevent mud track out onto
Heart Lake Road and reduce dust generation.
An operational watering scheme that is based on the activity levels and meteorological
conditions should be developed and followed by trained site personnel, to ensure that watering is
completed frequently enough to adequately control fugitive dust emissions. For the purpose of
illustration, the following scheme is included as an example of the type of system that could be
developed at the McCormick Pit.
B.2.1.1 Example Operational Watering Scheme
Internal haul routes (both within the pit and at grade) will be treated with water as necessary for
dust control. The capability for main internal haul truck watering will provide for up to 2 passes
per hour with a minimum 7,200 L water truck, as needed to achieve the recommended dust
control efficiency.
For operational purposes, a scheme based on the type of day (hot/dry/windy, warm/overcast,
cool/overcast, rainy) that prescribes the recommended watering frequency based on the number
of truck passes and the length of road, is suggested, as presented below:
During very hot, dry and sunny conditions (typical of July or August) or windy days (i.e.
greater than 20 km/h), sufficient water will be applied to all in-pit roads, that is
equivalent to approximately one load of water (7200 L) every hour, depending on the
traffic level;
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 B-3 SENES Consultants Limited
During moderately warm, dry conditions (late spring & fall), sufficient water will be
applied to in-pit unpaved roads at that is equivalent to approximately one load of water
(7200 L) applied to all site roads, every two hours, depending on the traffic level;
During wet or rainy periods, the roads generally will not be watered.
The scheme presented above should be adjusted as conditions dictate. For example, roads will
definitely be watered regardless of the “rules” if there is visible, or blowing dust.
B.2.2 Application of Water to Material Handling and Processing
In addition to road watering, material processing equipment will be equipped with water sprays
to reduce the generation of fugitive dust. The assessment was completed assuming that
secondary crushers and beyond, as well as all screening equipment will have these controls. The
assessment assumed that no controls will be used on material drops from loaders, excavators and
stackers. However, should problems with fugitive dust arise, installation of spray bars on
conveyor transfer points and stackers will be considered.
B.2.3 Application of Water to Material Storage Piles
Depending on the amount of “fines” present in the material, windblown dust from material
storage piles can occur. The assessment was completed assuming that wind erosion will only
occur above a threshold windspeed of 10 m/s at anemometer height, which generally corresponds
to a wind speed of approximately 5 m/s at mid-pile height. In addition, it was conservatively
assumed that no controls will be specifically employed to control this source. Should emissions
from storage piles become a problem, the piles will be sprayed with water or another approved
dust suppressant on a daily basis to reduce windblown dust.
B.2.4 Record Keeping
A daily log of water applications and other dust control procedures and observations should be
kept at the site to demonstrate, if necessary, that dust control actions are being taken.
B.2.5 Control of On-site Contractors
On-site contractors will be required to meet the same requirements as set out in this Best
Management Plan at all times that they are on-site.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 B-4 SENES Consultants Limited
B.3 CONSIDERATIONS FOR IMPROVED CONTROL
In addition to the procedures outlined above, SENES offers these following optional
considerations to further reduce the potential for off-site dust emissions:
Apply calcium chloride or other chemical dust suppressants annually or semi-annually, if
permitted by the ARA license; and
Ensure that the site perimeter berms and surrounding area be sufficiently vegetated.
o Several rows. of coniferous and/or deciduous trees and medium sized shrubs
should be sufficient to achieve the necessary reductions. Planting shrubs together
with trees is desirable, as shrubs quickly fill-in areas, giving time for trees to
reach mature sizes. If possible, it is preferable to place some plants with an
approximate 2 m mature height on or near the top of the berms. Trees that will be
large at maturity (e.g. ~ 2m taller than the height of the berm) can be planted at
the base of the berms, if necessary, on the non-pit side.
o It is important to note that as trees and shrubs grow, some will become tall, while
others will remain short; some will spread, while others will remain columnar.
The mature plant characteristics of the selected species should be examined to
determine the appropriate plant spacing and placement, such that a good screen is
produced once all plants reach their ultimate height and spread.
o The plantings should contain a mix of coniferous and deciduous species, such that
some screening potential remains after the leaves have fallen off of the deciduous
plants.
B.4 ENVIRONMENTAL COMPLAINT DOCUMENTATION AND RESPONSE PROCEDURE
SENES recommends that a complaint documentation and response procedure be established for
the McCormick Pit, such that standardized procedures are followed in the event that a complaint
is made by a member of the public. The documentation should include the date and time of the
complaint, the nature of the problem, and whether any follow-up action was taken. The
complaint information should be maintained in an on-site log that is available for review by the
MOE, if requested.
A sample form is included on the following page.
Dust Impact Assessment of the McCormick Pit
350526 - FINAL – February 2013 B-5 SENES Consultants Limited
RECORD OF ENVIRONMENTAL COMPLAINT AND RESPONSE
1. Location: __________________________________________________________ 2. Date and Time Complaint Received: _____________________________________ 3. Name of Complainant: ________________________________________________
Address: ___________________________________________________________ Telephone Number: __________________________________________________
4. Form of Complaint and Summary: Visit:[ ] Telephone Call:[ ] Letter:[ ] Attach Copy Other _____________________________________________________________ 5. Complaint Referred to Technical Services: No [ ] Yes [ ] and provide details: ___________________________________________________________________ 6. Contact Made With Government Official(s): No [ ] Yes [ ] If Yes, Complete and Attach Record of Government Environmental Official Contact Form --
Yes [ ]
7. Details Concerning Investigation Made by Company Concerning Complaint:
_____________________________________________________________________________________________________________________________________
8. Response to Complainant:
Letter [ ] Date _______________________ Attach copy of letter to this form. Telephone Call [ ] Date ____________________ Time _____________________ Summary of Telephone Call: _____________________________________________________________________________________________________________________________________
9. Follow-up Action Required and/or Taken by Company: None [ ] Details: ___________________________________________________________________________
___________________________________________________________________________
________________________________________________________________________
10. Filed Original Form in the Plant Environmental Manual: Yes [ ] Date ______________________ __________________________________ Employee Signature, Name & Position