Course Overview Prerequisites

Bus635 and/or EMB 510 Requirements and Grading

1 Paper (40%) One Midterm Examination (20%) Final Examination (40%)

Class Materials Web-page: http://fkk.weebly.com

Office: NAC 751 Office hours: Tuesday, 5pm-6:30 pm

2

Page 3: FIN 650: Project Appraisal Lecture 1 Introduction

Activity Schedule: FIN650Class Date Exams Paper

1 24 May

2 31 May

3 7 June

4 14 June

5 21 June Guest Lecturer Lab class

6 28 June Guest Lecturer Lab class

7 5 July Mid 1

8 12 July

9 19 July

10 26 July

11 9 Aug

12 16 Aug Guest Lecturer Paper

13 13 Aug-23 Aug.

Final

Page 4: FIN 650: Project Appraisal Lecture 1 Introduction

Project Appraisal Nature of project appraisalGiven the limitation of resources, choices must be made among the competing uses, and project appraisal is one method of evaluating alternatives in a convenient and comprehensive fashionProject appraisal assesses the benefits and cost of a project and reduces them to a common yardstick. If benefits exceed costs, the project is acceptable; if not the project should be rejected Society’s objective

Growth: to increase total national incomeEquity: to improve the distribution of national income

Projects should be assessed in relation to their net contribution to both of these objectives

Page 5: FIN 650: Project Appraisal Lecture 1 Introduction

Project and Program Appraisal

Project and program sometimes used interchangeablyProject: Jamuna Bridge Project, Square PharmaceuticalsProgram: Literacy Program

Analysis by whom?Private

Investor Lender

Government agency Public-private partnership

Donor agency

Tools for analysis will varyPrivate investor-capital budgetingGovernment/donor agency- cost benefit analysis

Page 6: FIN 650: Project Appraisal Lecture 1 Introduction

CBA and Capital Budgeting

Cost-Benefit Analysis

Cost benefit analysis is a program/project

assessment method that quantifies in monetary

terms the value, net social benefits, of all

program /project consequences for all members of

the society Capital Budgeting

Is the process of evaluating and selecting long-term

investments consistent with the firm’s goal of

owner wealth maximization

Page 7: FIN 650: Project Appraisal Lecture 1 Introduction

Major Steps in CBA Specify the set of alternative projects Decide whose benefits and costs counts(standing) Catalogue the impacts and select measurement

indicators (units) Predict the impacts quantitatively over the life of the

project Monetize (attach dollar/taka values to) all impacts Discount benefits and costs to obtain present values Compute the NPV of each alternative Perform sensitivity analysis Make a recommendation based on the NPV and

sensitivity analysis

7

Page 8: FIN 650: Project Appraisal Lecture 1 Introduction

Capital Budgeting Capital budgeting is primarily concerned with

sizeable investments inlong-term assets. Tangible: property, plant or equipment Intangible: R&D, Patents or trademarks

Different from recurring expenditure in two aspects: Projects are significantly large Long-lived projects with their benefits or cash

flows spreading over many years. Capital budgeting decisions have significant

impact on firm’s performance and they are critical to the firms success or failure

Page 9: FIN 650: Project Appraisal Lecture 1 Introduction

Capital Budgeting Capital budgeting is one of the most

significant financial activity of the firm.

Capital budgeting determines the core activities of the firm over a long term future.

Capital budgeting decisions must be made carefully and rationally.

Page 10: FIN 650: Project Appraisal Lecture 1 Introduction

Capital Budgeting Within the Firm

The Position of Capital Budgeting

Capital Budgeting

L o n g T e rm A sse ts S h o rt T e rm A sse ts

Investm ent D ecison

D e b t/E qu ity M ix

Financing D ecis ion

D iv id en d P a yo ut R a tio

D ividend D ecis ion

Financial Goa l of the F irm :W ealth Maxim isation

Page 11: FIN 650: Project Appraisal Lecture 1 Introduction

Examples of “Long Term Assets”

• Real Estates• Aircrafts, Ships• Forest• Plant and Machineries

Page 12: FIN 650: Project Appraisal Lecture 1 Introduction

Aspects of Capital Budgeting

Capital Budgeting involves: Committing significant resources. Planning for the long term: 5 to 50 years. Decision making by senior management. Forecasting long term cash flows. Estimating long term discount rates. Analyzing risk.

Page 13: FIN 650: Project Appraisal Lecture 1 Introduction

Aspects of Capital Budgeting

Capital Budgeting:

• Emphasizes the firm’s goal of wealth maximization, which is expressed as maximizing an investment’s Net Present Value

• Requires calculation of a project’s relevant cash flows

Page 14: FIN 650: Project Appraisal Lecture 1 Introduction

Aspects of Capital Budgeting

Capital Budgeting Uses:• Sophisticated forecasting techniques:-

• Time series analysis by the application of simple and multiple regression, and moving averages

•Qualitative forecasting by the application of various techniques, such as the Delphi method

Page 15: FIN 650: Project Appraisal Lecture 1 Introduction

Aspects of Capital Budgeting

Capital Budgeting requires:

Application of time value of money formulae.

Application of NPV analysis to forecasted cash flows.

Risk Analysis – Risk Adjusted Discount Rate(RADR) and Certainty Equivalent

Application of Sensitivity and Break Even analyses to analyze risk.

Page 16: FIN 650: Project Appraisal Lecture 1 Introduction

Aspects of Capital Budgeting

•Application of Simulation and Monte Carlo Analysis as extra risk analysis.•Application of long term forecasting and risk analysis to projects with very long lives.•Application of optimization techniques to projects which have constrained resources.•Development and application of generic and specific financial models•Application of cash flow forecasting, and NPV analysis to all aspects of property investment projects.•Application of NPV analysis under the additional risks associated with international investments

Page 17: FIN 650: Project Appraisal Lecture 1 Introduction

Shareholder Wealth Maximization and NPV

• The shareholder wealth maximization goal requires that management should endeavor to maximize net present value (NPV) of expected future cash flows to the shareholders of the firm. •NPV represents discounted sum of the expected net cash flows.

•Cash outflows: capital outlays•Cash inflows: proceeds from sales

• Net cash flows are determined by subtracting a given period’s cash outflows from that period’s cash inflows.

Page 18: FIN 650: Project Appraisal Lecture 1 Introduction

Shareholder Wealth Maximization and NPV

•The discount rate takes into account the timing and risk of the future cash flows resulting from the investment.

•The longer it takes to receive a cash flow, the lower the present value to the investor.•The greater the risk associated with receiving a future cash flow, the lower the value investors place on that cash flow.

•Shareholder wealth depends on magnitude, timing and risk associated with the cash flows expected to be received in future by the shareholders

Page 19: FIN 650: Project Appraisal Lecture 1 Introduction

19

Class Exercise

Project Alpha requires an initial capital outlay of Tk. 45,000 and will have net cash inflows of Tk. 15,000, Tk. 20,000 and Tk. 30,000 at the end of years 1,2, and 3 respectively. The discount rate is 8% per annum.

How much project Alpha will add to the firm’s value?

Page 20: FIN 650: Project Appraisal Lecture 1 Introduction

20

Classification of Investment Projects An independent project is one the acceptance

or rejection of which does not directly eliminate other projects from consideration or affect likelihood of their selection

Mutually exclusive projects- cannot be pursued simultaneously-the acceptance of one prevents the acceptance of the alternative proposal

A contingent project is one the acceptance or rejection of which is dependent on the decision to accept or reject one or more other projects Complementary projects, pharmacy and doctor’s clinic Substitute projects, Thai or Chinese restaurant

Page 21: FIN 650: Project Appraisal Lecture 1 Introduction

21

The Capital Budgeting Process

Corporate goal Strategic planning Identification of investment opportunities Preliminary screening of projects Financial appraisal of projects Qualitative factors in project evaluation The accept/reject decision Project implementation and monitoring Post-implementation audit

Page 22: FIN 650: Project Appraisal Lecture 1 Introduction

22

The Capital Budgeting Process` Corporate goal

Strategic Planning

Investment opportunities

Preliminary Screening

Financial Appraisal

Qualitative factors, Judgments

Accept/Reject Decision on the projectAccept

Reject

Implementation

Monitoring

Post implementation audit

Page 23: FIN 650: Project Appraisal Lecture 1 Introduction

23

Why Cash Flows? Cash flows, and not accounting

estimates, are used in project analysis because: They measure actual economic wealth. They occur at identifiable time points. They have identifiable directional flow:

inflow and outflow. They are free of accounting definitional

problems.

Page 24: FIN 650: Project Appraisal Lecture 1 Introduction

24

The Meaning of RELEVANT Cash Flows.

A relevant cash flow is one which will change as a direct result of the decision about a project.

A relevant cash flow is one which will occur in the future. A cash flow incurred in the past is irrelevant. It is sunk.

A relevant cash flow is the difference in the firm’s cash flows with the project, and without the project.

Page 25: FIN 650: Project Appraisal Lecture 1 Introduction

25

Cash Flows: A Rose by Any Other Name Is Just as Sweet.

Relevant cash flows are also known as:-Marginal cash flows. Incremental cash flows. Changing cash flows.Project cash flows.

Page 26: FIN 650: Project Appraisal Lecture 1 Introduction

26

Categories of Cash Flows Project cash flows may be separated into

two categories: Capital cash flows

The initial investment Outflows, purchasing assets and initial working capital

Additional middle-way investments such as upgrades and increases in working capital investments

Terminal cash flows Inflows, proceeds from sale, salvage value of the asset net

of tax, recovery of remaining working capital Outflows, cost of asset disposal, environmental

rehabilitation, redundancy payment to employees Operating cash flows: cash inflows from sales,

cash outflows for marketing and advertising, payments for wages, utilities, raw materials

Page 27: FIN 650: Project Appraisal Lecture 1 Introduction

27

Essentials in Cash Flow Identification Principle of the stand-alone project

Evaluation of the proposed project purely on its own merits, in isolation from any other activities or the projects of the firm

Indirect of synergistic effects Negative effects, new model of car, lower sales of

existing model, must be deducted from future cash flows Positive effects, pharmacy adjacent to doctor’s clinic,

favorable impact on clinics cash flows to be added to pharmacy project’s cash flows

Opportunity cost principle: the most valuable alternative that is given up if the proposed investment project is undertaken Use of existing resources, space, building, rental value,

market value

Page 28: FIN 650: Project Appraisal Lecture 1 Introduction

28

Essentials in Cash Flow Identification Sunk cost, is an amount spent in the past in

relation to the project, but which cannot now be recovered or offset by the current decision Past consulting expenses

Overhead costs Utilities, executive salaries With or without the project, incremental costs to be

included Treatment of working capital

Current assets (inventories, accounts receivables) minus current liabilities (accounts, wages payable)

Increases in working capital is treated as cash outflows even though there is no actual cash outflow, opportunity cost

Capital flows, not operational flows, it is a fund

Page 29: FIN 650: Project Appraisal Lecture 1 Introduction

29

Essentials in Cash Flow Identification

After-tax cash flows Must be accounted for as a cash outflow, not

based on net cash flow but on taxable income Treatment of depreciation

Is not a cash flow In project appraisal, what is relevant is not the

accounting depreciation but tax allowable depreciation to measure the tax effect

Investment allowance, enhances NPV Financing flows, excluded. double

counting, included in the discount rate

Page 30: FIN 650: Project Appraisal Lecture 1 Introduction

30

Essentials in Cash Flow Identification Within-year timing of cash flows

Occurs at various points of time in a year Standard practice is to assume that capital expenditure

occur at the beginning of the year and all other cash flows occur at the end of the year

Points in cash flow timing is are set at the end of each year. An initial outlay of Tk. 50,000 at the start of year 1will be timed as occurring at the end of year zero.

Inflation and consistent treatment of cash flows and discount rates Nominal returns, incorporating the inflationary effect is

preferred over cash flow forecasts in real terms, excluding the inflationary effects

Fisher effect Consistency, cash flow in nominal terms- use nominal

discount rate; cash flow in real terms- use real discount rate

Page 31: FIN 650: Project Appraisal Lecture 1 Introduction

31

Project Cash Flows: Yes and No.

YES:- these are relevant cash flows: Incremental future sales revenue.

Incremental initial outlay. Incremental future salvage value. Incremental working capital outlay. Incremental future taxes.

Page 32: FIN 650: Project Appraisal Lecture 1 Introduction

32

Project Cash Flows: Yes and No.

NO:- these are not relevant cash flows:

Changed future depreciation. Reallocated overhead costs. Adjusted future accounting profit. The cost of unused idle capacity. Outlays incurred in the past.

Page 33: FIN 650: Project Appraisal Lecture 1 Introduction

33

Cash Flows and Depreciation: Always a Problem.

Depreciation is NOT a cash flow. Depreciation is simply the accounting

amortization of an initial capital cost. Depreciation amounts are only

accounting journal entries. Depreciation is measured in project

analysis only because it reduces taxes.

Page 34: FIN 650: Project Appraisal Lecture 1 Introduction

34

Other Cash Flow Issues. Tax payable: if the project changes tax

liabilities, those changed taxes are a flow of the project.

Investment allowance: if a taxing authority offers this ‘extra depreciation’ concession, then its tax savings are included.

Financing flows: interest paid on debt, and dividends paid on equity, are NOT cash flows of the project.

Page 35: FIN 650: Project Appraisal Lecture 1 Introduction

35

Other Cash Flow Issues. In property investment, ‘property’ cash

flows may be distinguished from ‘equity’ cash flows.

In project analysis, cash inflows are timed as at the end of a year, and capital outlays are timed as at the start of a year.

Forecast inflated cash flows must be discounted at the nominal discount rate, not the real discount rate.

Page 36: FIN 650: Project Appraisal Lecture 1 Introduction

36

Using Cash Flows

All relevant project cash flows are set out in a table.The cash flow table usually reads across in End of Years, starting at EOY 0 (now) and ending at the project’s last year. The cash flow table usually reads down in cash flow elements, resulting in a Net Annual Cash Flow. This flow will have a positive or negative sign.

Page 37: FIN 650: Project Appraisal Lecture 1 Introduction

37

Delta Project Cash Flows Project start date 2001 Capital outlay in year 1 is $ 1 million; year 3 is

$0.5 million Economic life 8 years Working capital Y0-2000; Y1-2500; Y2-3100; Y3-

3600; Y4-4000; Y5-4300;Y6-4500; Y7-3000, Y8-0. Salvage value in Y8: $16,000 Depreciation on initial investment is 12.5% p.a.

upgrade depreciates @$100,000 for years 4-8. Sales forecasts After tax salvage value Accounting income Workbook 2.1

Page 38: FIN 650: Project Appraisal Lecture 1 Introduction

38

Asset expansion project cash flows

Initial investment Initial investment in plants and working capital

Net operating cash flows Add back depreciation Exclude depreciation from costs Add tax shield of depreciation (tax rate x

depreciation) Terminal cash flows

Proceeds from sale of assets minus taxes on sale of an assets plus recovery of working capital

Page 39: FIN 650: Project Appraisal Lecture 1 Introduction

39

Asset replacement project cash flows Initial investment

Initial investment in plants and working capital minus proceeds from sale of old asset plus taxes on sale of old assets

Incremental operating cash flows Operating cash flow of new assets minus

operating cash flow of old assets Terminal cash flow

Proceeds from sale of new asset- proceeds from sale of old asset - taxes on sale of old assets- taxes on sale of an assets-taxes on sale of old assets plus recovery of working capital

Page 40: FIN 650: Project Appraisal Lecture 1 Introduction

40

Project Cash Flows: Summary

Only future, incremental, cash flows are Relevant. Relevant Cash Flows are entered into a yearly cash flow table. Net Annual Cash Flows are discounted to give the project’s Net Present Value.

Page 41: FIN 650: Project Appraisal Lecture 1 Introduction

41

Overarching principles: We only need to estimate cash flows

that change as a result of accepting the project (incremental cash flows).

The amount of, and the timing of the cash flow must be estimated, not the

accounting profit/loss by ordinary accounting methods.

Project Cash Flows: Summary

Page 42: FIN 650: Project Appraisal Lecture 1 Introduction

42

There are generally three kinds of cash flows that can be affected by a capital budgeting project:

1) Initial period cash flow2) Operating cash flow3) Terminal year cash flow

Project Cash Flows: Summary

Page 43: FIN 650: Project Appraisal Lecture 1 Introduction

43

Since taxes are cash flows, we must include taxes in our cash flow estimates. All estimated cash

flows should be after-tax cash flow

estimates!

Page 44: FIN 650: Project Appraisal Lecture 1 Introduction

44

Cash flow type #1: Initial period cash flows

These are simply any cash flows that occur in the initial period of the project’s life (period 0).

For example, assume that a new investment project would require spending $20 million for new capital machines, plus $3 million for additions to working capital (increases in cash balances, inventory, and accounts receivable).

The initial period cash flow = -$20 + -$3= -$23 million.

Page 45: FIN 650: Project Appraisal Lecture 1 Introduction

45

Cash flow type #2: Operating cash flow

Accounting income for a period could be a measure of cash flow, except that depreciation (an expense, but not a cash flow) was subtracted in calculating it.

Operating cash flow equalsNet Income + Depreciation

Page 46: FIN 650: Project Appraisal Lecture 1 Introduction

46

Operating cash flow will be affected whenever a revenue or expense is changed on the income statement. For example, operating cash flow is

increased/decreased if a project results in increased/decreased sales revenues.

Operating cash flow is decreased/increased if a project results in increased/decreased expense of some kind.

Operating cash flow

Page 47: FIN 650: Project Appraisal Lecture 1 Introduction

47

Continuing with the example project:

Assume the business currently has sales of $95 million and cash operating expenses of $65 million, plus $15 million of depreciation

expense. Assume the tax rate = 30%. Net income = ($95 - $65 - $15) x (1 - .3)

= $10.5 million. Operating cash flow = Net income +

depreciation = $10.5 + $15 = $25.5 million per year.

Page 48: FIN 650: Project Appraisal Lecture 1 Introduction

48

Assume that accepting the new investment project would increase the business sales by $10 million, and increase the operating costs by $4 million, plus increase depreciation expense by $2 million. What is the incremental operating cash flow for the project?

Class exercise

Page 49: FIN 650: Project Appraisal Lecture 1 Introduction

49

Operating cash flow with the new project = ($105 - $69 - $17) x (1-.3) + $17 = $30.3 million. The incremental operating cash flow

for the project equals the change in cash flows from before accepting the project to after accepting it = $30.3 - $25.5 = $4.8 million per year. (Assume these benefits continue the same each year for 10 years.)

Answer

Page 50: FIN 650: Project Appraisal Lecture 1 Introduction

50

It is usually easiest to compute this incremental cash flow by just using the incremental numbers themselves. Thus, The relevant incremental operating cash flow

for the example project =+ Inc. in sales revenue ……… $10 million - Inc. in op. costs (expenses) ….. 4 million - Inc. in depreciation expense … 2 million = Inc. in EBT …………………. 4 million - Inc. in taxes (@ 30%) …..…... 1.2 million = Inc. in EAT …………….….. 2.8 million + Inc. in depreciation expense … 2 million = Inc. in operating cash flow ….. $ 4.8 million

An alternative way

Page 51: FIN 650: Project Appraisal Lecture 1 Introduction

51

Notice that this method of calculating the incremental operating cash flow requires you to simply identify every item in the company’s income statement that changes, and then to calculate the change in net income that results. Finally, the operating cash flow equals the change in net income plus the change in depreciation.

Operating cash flow

Page 52: FIN 650: Project Appraisal Lecture 1 Introduction

52

Cash flow type #3: Terminal year cash flows

These cash flows consist of any residual values (salvage values) recovered from the project at the end of its useful life.

For our example, assume that at the end of the project’s life, the machines could be sold to net $100,000 after taxes, and that the working capital ($3 million) is recovered in full.

Thus, the terminal year cash flow (year 10) for the project = $3.1 million.

Page 53: FIN 650: Project Appraisal Lecture 1 Introduction

53

The complete cash flows for the example project are:Periods:

0 1-10 10 - $23 + $ 4.8 + $ 3.1Assume that the cost of capital for the project equals 10%, the NPV is calculated to be $7.69 million.

Total cash flows

Page 54: FIN 650: Project Appraisal Lecture 1 Introduction

54

Since the NPV > 0 we know the project is a good one.

We could alternatively have made the decision using the IRR method. IRR of the project can be calculated to be 17%. Since this is > the 10% cost of capital, the project should be accepted.

We could also have (alternatively) made the decision using the PI method. PI = 1.33, which is > 1.00.

What to do with the project?

Page 55: FIN 650: Project Appraisal Lecture 1 Introduction

55

Consider another example:

Assume the Widget Company is considering an investment to replace a production machine with a more efficient one.

Assume the new machine costs $100,000, and the old machine has a book value of $15,000 and a current salvage value of $25,000.

Assume the tax rate is 30%. What are the relevant cash flows for the project

analysis, and should the replacement be accepted?

Class Exercise 2

Page 56: FIN 650: Project Appraisal Lecture 1 Introduction

56

First, determine the initial period cash flows:

The $100,000 purchase price of the new machine is an immediate cash outflow.

The $25,000 salvage value of the old asset would be an immediate cash inflow.

Taxes on the gain from sale of the old asset is also an immediate cash outflow. Taxes = 30% x (SV-BV) = .3 x (25,000-15,000) = $3,000.

Initial period cash flows

Page 57: FIN 650: Project Appraisal Lecture 1 Introduction

57

The total initial period (period 0) incremental cash flows for the replacement project are:

-$100,000 + $25,000 - $3,000 = -$78,000.

Initial period cash flows

Page 58: FIN 650: Project Appraisal Lecture 1 Introduction

58

Next, we calculate the operating cash flows: Assume the new machine would reduce

operating costs by $35,000 per year for the next 8 years, compared to using the old machine. Depreciation expense would also increase by $12,500 per year for 8 years.

Net income will increase by ($35,000 - 12,500) x (1-.3) = $15,750.

Op. CF = Net Income + Depreciation = $15,750 + $12,500 = $28,250 per year, for 8 years.

Note that this is an annuity of benefits.

Operating cash flows

Page 59: FIN 650: Project Appraisal Lecture 1 Introduction

59

Assume that both the old machine and the new one would be fully depreciated after 8 years. With the new machine, sale in year 8 for

$5,000 => taxable gain on the sale equal to the salvage value minus the book value = ($5,000 – 0) = $5,000. Tax on this gain = $5,000 x .3 = $1,500.

With the old machine, sale in year 8 for $500 => taxable gain on the sale equal to the salvage value minus the book value = ($500 – 0) = $500.Tax on this gain = $500 x .3 = $150.

Calculation of Taxes

Page 60: FIN 650: Project Appraisal Lecture 1 Introduction

60

Altogether, then, the total terminal year cash flow equals

= incremental salvage value of $4,500 - incremental taxes of $1,350

= $4,500 - $1,350 = $3,150. This cash flow in year 8 is in addition

to the regular $28,250 operating cash flow of that year (already computed).

Terminal year cash flows

Page 61: FIN 650: Project Appraisal Lecture 1 Introduction

61

Important: While in general, any cash flow affected

by a project is relevant, we do not include any cash flows that are financing costs.

For example, we do not include interest expense or lease payments.

The reason for this is that all financial cash flows are implicitly included in the cost of capital used to find NPV (or used to compare to IRR). To include the

financial cash flows and then discount them to PV would be to double count their impact.