Fiacbras (Bkq52) - 87271096 - Auditoria de Pcpa - Rm

Embed Size (px)

Citation preview

PCPAPart Number:

RESULT:

1BKQ52

Guidelines

Date:

11-Sep-08NA

87271096 Odm:

Project:

Sprayer - Hood Supplier Name:Supplier Code:

FIACBRASSupplier Plant:

Part Hood - Fuel Tank Description:PROCESS VERIFICATION (VP) Mat'l Request: Availability:1 - DOCUMENTATION 2 - TOOLING / EQUIPMENT 3 - PROCESS

SQE: R. Mximo (vx822)PRE-SERIES (PS) Mat'l Request: Availability:5 - PRODUCT 4 - HUMAN RESOURCES QUALIFICATION / ONE & ORGANIZATION DAY PRODUCTION

Sumar (SP)### ###

RELEASE TO PROD. (DaP) Mat'l Request: Availability:6 - IMPLEMENTATION OF QUALITY 7 - IMPLEMENTATION OF QUALITY

CURRENT PRODUCTION Mat'l Request: Availability:8 - LOGISTIC 9 - CONTINUOUS IMPROVEMENT

Drawings A F-C

Die status (quality, capacity and timing)

Tier 2 approval

Have operators been Self-Qualification status properly trained?

Incoming Material Controls

Controls recording

Traceability

Lessons Learned

1Flow Chart

F-S

3

F

3

F

3Management involvement

F-S

2

F

3

F

4

F

4Identification

F

NV

B F

Equipment status (quality, capacity and timing) F-S

Tier 2 components approval

Integrative Tests Status

Production approval

Controls recording regarding Report Characteristics F

Improvement Activities for Tier 2 Suppliers

2

4

F

2

4Are the Resources dedicated to controls sufficient?

F-S-C

NV

F

3

1

4FIFO

F

NVWarranty

Process FMEA C F-S

Are clear operator Preservation conditions instructions available of dies machines and and updated for each equipments operation? F

Matchability and Benestare Status

Process Controls and Tests

Control instruments management

1

3s)

F

3

3If more than one shift, does information get passed across shifts? F

F-S-C

NV

F

2

F

2Re-works

4Appropriate handling and packaging

F

4Periodic ReQualification

Process Control Plan (machines/dies/equipment D F-S

Ordinary and Preventive Maintenance

Process Capability (Ppk, Cpk & Cmk)

One Day Production

Outgoing Quality

1

F

3

F-S

NV

2

F-S

NV

F

2SQE Audit

F

4

F

3

NVQuality and Environmental certifications F

E

IMDS (Mgt. of use limitation Is the Special for dangerous or Maintenance effective? forbidden substances)

Restart of production

Environment, Health and Safety (EHS)

Strengthened PreLaunch Control Plan

Non-conforming products management

Appropriate process flow

NA

F

3

F

3

2

NV

F-S

NV

3REMARKS & REMARKS & OBSERVATIONS OBSERVATIONS

F

3

4

na - Not Applicable nv - Not ValuatedSupplier Resp.: Name

1 - JOB STOPPER

4 - Planned 2 - JOB STOPPER 5 - Implemented 3 - 2nd Level Issue Activity according Risk Activity to ProjectProgr. Mgr.Name Sign. SQE: Name Sign.

ATTACHED DOCUMENT

Sign.

SQM: Name

Sign.

BACK TO PCPA FORM PCPA FORM AUDITOR REMARKS (SQE)

Positive Points:* Abertura e receptividade por parte da Empresa e colaboradores; * Esforo em atender as solicitaes e necessidades dos clientes; * Transparncia.

Improvement Points: * Necessidade de melhorias nas reas de inspeo de produto acabado; * Necessidade de melhorias em sua documentao tcnica: PFMEA, Fluxo de Processo, Planos de Controle; * Necessidade de melhorias na gesto do Controle de Processo.

QUESTION

RANKING

OBSERVATION The supplier should be in possession of drawings that reflect some form of customer approval; i.e. Design Engineers signature, approved design change order, etc.

AUDIT EVIDENCES

CORRECTIVE ACTION

RESPONSIBLE

DATE6-Oct-08

STATUS

Rodrigo A.F. 1) O fornecedor no possuia cpia da norma 1/2)Solicitado cpia; DWGB105/09 (ou FIAT 01455/13) que determina 3) Correo do desenho e envio a CNH Salgado (Suporte as tolerncias para Synthetic Resin para aprovao (solicitao de CD) Tcnico Components; Fiacbras)

J6-Oct-08

1A

1

2) O fornecedor no possuia cpia da norma The supplier should demonstrate that the que estabalece o MS515 - Tupe III - Grade A, technical documentation (Drawings, Technical que estabelece as caractersticas fsicoSpecs., Standards and Norms) for the part, qumicas da fibra-de-vidro; product or component under examination shall be updated and available, whether the part 3) A pea fornecida atualmente no is produced internally or purchased from representa 100% o desenho. Foram includos external sources. os insertos FC-DI-537 (substitui o 311717), FC-DI-582-1, FC-DI-582-2 e FC-DI-598 sem a devida aprovao da Eng. CNH; The drawings elaborated by the supplier should show the adequate tolerances. The drawings elaborated by the supplier should show the link between the customers standards.

Rodrigo A.F. Salgado (Suporte Tcnico Fiacbras)

J06/11/2008Dependendo aprovao CNH do Eng. LUIZ GROPPO Dpto. engenharia Piracicaba

Rodrigo A.F. Salgado (Suporte Tcnico Fiacbras)

K J K

1B 1C

2 1

The suppliers manufacturing facility should O fornecedor no possui Fluxo de Processo have available a Process Flow Diagram. formalizado. The supplier should have available an O fornecedor no possui FMEAs de Processo acceptable PFMEA, witj acceptable RPNs, formalizados. consistent with DFMEA, Process Flow and that includes CNH important characteristics (CNH1 and CNH2).

- Concluir fluxo de processo; - Treinar Colaboradores; - Implantar.

Atlio (CQ)

9-Oct-08

Sidelice (SGQ)/ 31/01/2009 - Agendamento de treianemnto FMEA para a Finalizar at equipe; - Atlio (CQ) - 09/02/09 Elaborao e implantao de Procedimentos; - realizao e implantao do FMEA.

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

1D

1

The supplier should have an available O fornecedor no possui Planos de Controle Process Control Plan. formalizados. An acceptable Process Control Plan should have: * numbers and controls match PFMEA and Process Flow Chart; * includes CNH important characteristics (CNH1 and CNH2); * recalls suitable frequencies and sampling sizes; * include incoming, throughout the process to labelling and shipping.

- Concluir planos de controle; - Revisar fluxograma de novo produto FC.DC-15 incluindo plano de controle;

Atlio (CQ)/ Sidelice (SGQ)

9-Oct-08

J

1E 2A

NA 3

IMDS

IMDS no um requisito CNH.

NAAtlio (CQ) - Ao em andamento (revalidao dos gabaritos com recuperao e tratamento de proteo superficial e gernciamento atravs de planilha de controle e aprovao peridicas) 31-Dec-08

The supplier should manage the die status in O fornecedor deve gerenciar a vida til de terms of (building and try-out) timing and seus moldes e gabaritos, realizando functionality. manutenes peridicas e try-outs dos mesmos. The supplier should manage the environment where are stored the dies, with particular attention to the conditions of humidity, protection, lubrication and identification.

J06/10/2009 Finalizar 12/02/09

2C

3

O fornecedor no apresenta uma rea Com a concluso das instalaes da ampliao Henrique destinada para o armazenamento de do prdio (em andamento), ser construido um (Diretoria Comercial) / ferramentais e gabaritos, ficando os mesmos galpo maior para melhor armazenamento dos Claudio alocados na rea de produo. ferramentais e gabaritos. (DiretoriaIndustrialI)

K J

The supplier should manage the preventive or O fornecedor deve melhorar a gesto das predictive maintenance plan for all manutenes preventivas das mquinas de production equipment directly connected with spray-up, de modo a determinar frequncias the product (including machine tooling). de manuteno, itens padro a serem verificados e a gesto peas de reposio. The supplier should have spare parts ready for those machines/tools that may cause stopping of production. Estas manutenes devem ser registradas e avaliadas.

2D

3

Devido a durabilidade muito variada dos componentes iinternos das mquinas de SpryUp, manutenes preventivas peridicas completas se tornam invivel para a Fiacbras, no entanto, realizado atualmente, a limpeza, verificao e troca de componentes com probabilidade de desgastes constantes, para isso temos um estoque mnimo desses componentes, faltando no entanto um controle formal (registro da manuteno); - Ser elaborado planilha de estoque mnimo de componentes para reposio e implantao de planilha de controle das manutenes.

Sidelice (SGQ)/ 15-Nov-08 Manuel (Laminalo)

Sidelice (SGQ)/ 15-Nov-08 Manuel (Laminalo)

J

2E

3

The supplier should have a trained maintenance team (internal or external) available for intervention also in case of emergency during all working time. Special maintenance interventions must be recorded.

As manutenes corretivas das mquinas de spray-up devem ser registradas e avaliadas de modo a re-alimentar as manutenes preventivas.

Idem 2D 3

JAtlio (CQ/ Sidelice (SGQ) 15/11/2008 Depende CNH (desenhos item 1A1-3)

3A

3

The supplier should have an approved Utilizao de sub-fornecedores sem a devida - Realizar e implantar PPAP (Denesfer); supplier list exist for all components aprovao (DENESFER no homologado). - Rever sistemtica FC.PR-04 needed for the assembled part (commodity or (Procedimento de aquisio) technology) Adicionalmente, recomendada a reviso da OBS: Agendar treinamento PAPP sistemtica de avaliao via IQF e IFF. para suprimentos e qualidade para o 1 trimestre de 2009

K

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

3B

2

Atlio (CQ)/ The supplier should have a sitematic process No foram encontradas evidncias de - Solicitao de anlise dimensional e to qualify purchased product/material prior formalizao de anlise e aprovao dos certificados de Qualidade ao fornecedor; - sidelice (SGQ) to its being used in its production line. insertos FC-DI-537 (substitui o 311717), FC- Verificao e Aprovaao da analise pela The management of modified DI-582-1, FC-DI-582-2 e FC-DI-598 quanto: Fiacbras; material/components should be guaranteed. * Anlise Dimensional; Envio para aprovao CNH e; * Certificados de Qualidade de Matria- Formalizao do procedimento Prima; atravez da adio no procedimento FC.PR-04 * Certificados de Qualidade do Acabamento (Aquisio). Superficial.

15/11/2008 depende CNH (desenhos item 1A1-3)

K

3C

3

The supplier shoud provide in the A IT Aplicao de GEL COAT (Rev03 workstations clear operator instructions and 03/10/07) estabelece a necessidade de parameter set-up instructions according to aplicao de 03 camadas de gel, entretanto the needs and method of production. Such os operadores aplicam 02 camadas. documents shall be easily identifiable for the various steps related to the usage (e.g. classification, colours, pictures/sketches/drawings, etc.) to avoid any possible mistake.

- Revisar FC.IT-010 mantendo especificado apenas a espessura final do gel; - Providnciar medidor de espessura de gel e deixar no posto de trabalho; - Orientar (treinar) operador;

Sidelice (SGQ)/ 15-Nov-08 Vincius (Compras)

J

Process Capability (Ppk, Cpk & Cmk)

NA No foi eveidenciada a existncia de uma sistemtica para a realizao de estudos de capabilidade. O fornecedor deve avaliar a viabilidade e exteno da realizao destes estudos. Vale a pena destacar que os itens produzidos so confeccionados em moldes/gabaritos o que, quando com processos controlados adequadamente, pode ser considerado como uma inspeo 100%.

3D

NV

The supplier should have, according to requirements, instructions concerning equipment management in case of production changes or re-starts (set-up).

3E

3

1) Foi detectado peas em estgios avanados - Diminuir quantidade de peas por Ordem de Natanael (PCP) de processo (laminao, rebarbao, Produo para dinamizar o giro da mesma; acabamento) com a Ordem de Produo na etapa - Auxiliar de de laminao, sem as aprovaes PCP, contrada para a funo a um ms, est formalizadas; auxilido PCP para agilizar a elaborao e emisso das OP's evitando assim a falta da 2) A Ordem de Produo 2150 (03/09/08) mesma nos postos de trabalho. solicita a confeco de 03 unidades. Na realizao da auditoria, j haviam sido entregues para a CNH 02 unidades, entretando a OP ainda estava incompleta. O fornecedor deve gerar o controle de OP parciais.

9-Oct-08

J

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

The supplier should have a record of training courses completed, as well as a skills matrix chart identifying the versatility of the employees shall be available. This matrix shall be consistent with the days of work and number of shifts per day.

4A

3

The responsibility for the management/updating of the versatility matrix shall be defined.

O fornecedor possui uma Matriz de 1/2) Nova avaliao da matriz observando as Sidelic (SGQ) Competecncias (2Sem/08), entretanto a falhas citadas (incluso do auxiliar de mesma est desatualizada: inspeo, incluso dos supervisores na 1) Foi detectado que um dos colaboradores matriz de fabricao para suprir atividades designados para a avaliao e liberao de onde no h colaborador aptos a treinar; itens acabados no estava listado na matriz. 3) 2) Existem atividades onde no existem Disponibilizar matrizes atualizadas nas colaboradores aptos para o reas de trabalho; treinamento/multiplicao; 4) Atualizar matriz com as competcias dos 3) As matrizes no esto disponibilizadas lideres/ supervisores. nas reas de trabalho; 4) As matrizes no apresentam as competncias dos lderes/supervisores das reas.

15-Nov-08

J

4C

3

The supplier should provide an adequate A rea destinada a inspeo final dos itens - Est sendo providnciado iluminao number of resources involved in the process, necessita de iluminao diferenciada apropriada para rea de inspeo; ensuring the coverage of all working shifts. (avaliao de cor) e que no seja contaminada pela poeira proveniente do processo de acabamento. Adicionalmente, recomendada a instalao de uma cabine de luz para avaliao de padres de cor. The supplier should have an effective communication, particularly across shifts, dept's., etc., that problems info quickly reach the correct personnel. O fornecedor no possui formalizada a transmisso de informaes entre turnos Em fase de teste planilha de comunicao entre os turnos; semndo aprovada, a mesma ser implantada e inclusa no procedimento FC.DC-06 (Controle de Produo).

Claudio/ Henrique (Diretoria)

6-Dec-08

JNatanael (PCP)/ 31-Oct-08 Sidelice (SGQ)

4D

2

J6-Dec-08

4E

2

Claudio/ The supplier should demonstrate a cleaning Em virtude das caractersitcas do processo Baseado em 18 anos de experiencia na plan of workplaces in order to maintain the atual, seu do fluxo fsico e instalaes, as fabricao de produtos com fibra de vidro, Henrique (Diretoria) right level according to product reas de produo apresentam um grande sem nunca ter constatado contaminao que criticality. There shall be taken in account potencial de contaminao durante as fases: comprometesse a qualidade do laminado ou on working cycles a time dedicated to clean * Laminao; perda de processo, a Fiacbras no v the workstation. * Aplicao de Gel-Coat e Pintura; necessidade de mudanas nesse aspecto; no * Inspeo Final. entanto, a Empresa se encontra em fase de ampliao (construo), o que pode ter Adicionalmente, as reas de laminao causado algum impacto negativo durante a possuem pisos revestidos de areia, o que auditoria. pode vir a contaminar as mantas/resina Com a concluso das instaes e mudana do durante a laminao (ver 6C). processo de laminao para o novo galpo, esses processos vo ficar livres do p, que possa estar vindo do setor de acabamento.

J

Self-Qualification status

5A

2

O fornecedor no avaliou os seguintes - Reviso dos desenhos; tpicos durante o desenvolvimento do item: - Solicitao do CD a CNH. * Cotas de simetria 518 mm e 583 mm no foram medidas; * O molde desenvolvido no foi elaborado com base no modelo 3D e sim em amostra; * No apresentou o dimensional dos insertos.

Rodrigo A.F. Salgado (Suporte Tcnico Fiacbras)

06/11/2008Dependendo aprovao CNH do Eng. LUIZ GROPPO Dpto. engenharia Piracicaba

K

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

5C 5D 5E 6A

NV NV NV 3

Matchability and Benestare Status One Day Production Strengthened Pre-Launch Control Plan The supplier and the sub-suppliers should have a procedure to manage purchased material/raw material with significant characteristics assigned, including the recording and filing of inspection results.

Item de produo corrente em alterao de reviso de desenho. Item de produo corrente em alterao de reviso de desenho. Item de produo corrente em alterao de reviso de desenho. Foi detectado durante a auditoria a utilizao de resina isoftlica no liberada. Resina ARAZYN AZ110#00, lote 4333#00, NF 28729. "- Treinar e alertar Colaboradores quanto as Elias (Logistica)/ identificaes de liberao para uso; Sidelice (SGQ) Colocar placa de alerta sobre o lote a ser liberado "NO APANHAR; AGUARDAR LIBERAO"31-Oct-08

J J6-Dec-08

6B

3

Ver observaes do tpico 3E. The supplier should have defined and implemented controls on the first part produced in case of re-start of production, after any modification, or change of manufacturing process. The supplier should have process and machine 1) O processo de laminao no assegura o parameters defined according to how is controle de contaminao das camadas de prescribed into specs, norms, drawings both manta/resina aplicadas. Durante a auditoria customer and supplier (temperature, foi evidenciado que pedaos de manta que pressure, voltage, current, load, capacity, caiam no cho de areia eram colocados torque, etc.)? diretamente na pea em laminao;

Idem 3E

6C

2

1) Idem a 4E 2; Os Colaboradores do setor de Cleide / Manuel (laminao) laminao sero orientados a ter mais cuidado no manuseio do material. 2) Aquisio de 3 caixas de madeira (pint-las por dentro com tinta preta)para armazenagem dos padres de cores SGQ, Pintura e embalagem. 2) A gesto dos padres de cor deve ser 3)Os gabaritos esto sendo revalidados melhorada. Foi detectado durante a auditoria (conforme item 2 A3)e paralelamente, os Vincius The supplier should demonstrated that the O (Compras)/ Jos method of recording data are be verify as a guarda de padres na rea de pintura sem o projetos sero formalizados. ou Leomir item descrito no item 3 ser formalizado suitable for the checks being performed and devido cuidado de preservao. conforme o prazo de ao, os demais seguiro (Produo) any control limits utilized should be 3) No foram evidenciados projetos formais paralelo ao prazo do item 2 A3. reasonable. dos gabaritos de montagem (adeso de Rodrigo A.F. 4)Em Out of control conditions or special causes insertos) do item 87271096, o que vem Salgado of variation should be clearly identified, dificultar o controle/manuteno dos mesmos. anlise a viabilidade do estudo e das (Suporte necessidades (treinamentos, planilhas, etc.) Tcnico documented and linked to a robust corrective 4) O fornecedor dever confeccionar um Fiacbras) action support system that is responsive to quadro com os principais defeitos the operator. encontrados em seu processo de pintura (Arranhes, gotejamento, casca de laranja) de modo a servir de apoio a seu pessoal de inspeo. Atlio (CQ)/ The supplier should use a system for the sidelice (SGQ) easy identification of conforming products already produced (lot breaker, control charts, etc).

J15-Nov-08

J06/11/2008Dependendo aprovao CNH do Eng. LUIZ GROPPO Dpto. engenharia Piracicaba

K

15-Jan-09

J15/01/2009 finalizar 09/02/09

6D 6E

2 NV

The supplier should have and apply an adequate Product Audit Plan: * Results of previous audits shall be available; * Reaction plan if defective parts are discovered shall be available. SQE Audit

No foi evidenciada a realizao de auditorias sistemticas de produtos e processos.

Ser feito planejamento para realizao de Atlio (CQ) auditorias de produtos com incio a apartir de jan/09.

K

Tpico no avaliado durante a realizao da auditoria.

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

7B

1

The supplier should provide, perform and No foram evidenciados os registros de record controls directly to the product for processo referentes ao controle/avaliao parts with Saferty/Report Characteristics das caractersticas CNH1 ([>). and/or subject to homologation, in order to ascertain conformity of the related characteristics.

- Identificar processos crticos atravs do Sidelice (SGQ)/ 15-Nov-08 Atlio (CQ ) desenho; - Incluir na Ficha de Processo de realizao do produto.

J

The supplier should have available Master Parts to confirm inspection and error proofing devices.

1) Idem ao item 6C. 1) A gesto dos padres de cor deve ser melhorada. Foi detectado durante a auditoria a guarda de padres na rea de pintura sem o devido cuidado de preservao.

Jem andamento finalizar at 09/02/09

7C

2

2) Para inspees visuais, como cor e acabamento, o fornecedor deve realizar The supplier should have a gauge calibration estudos de R&R de modo a verificar a system, including calibration frequency and confiabilidade de suas avaliaes. recording of relevant results.

KAtlio (CQ) Vincius (Compras)/ 15-Nov-08

7E

3

The supplier should identify (via signs/documents, well delimited areas, better if enclosed or adequate containers) Non-conforming parts.

O fornecedor deve aprimorar a identificao Cercar rea de Segregao de Produtos No de peas suspeitas e/ou no-conformes. A Conformes com corrente. utilizao de reas/barreiras fsicas em adio a utilizao de cartes de identificao deve ser considerada. O fornecedor deve acionar a logsica CNH - Solcitao de analise de viabilidade de para a anlise de viabilidade da utilizao aprovao de racks retornvis junto a de embalagens/racks retornveis. CNH;F50 - Aguardando aprovao CNH. As caixas de papelo utilizadas atualmente no asseguram a integridade do item durante o transporte.

J06/11/2008 depende fornecimento CNH

The supplier should identify the packaging according to standards agreed with the customer (packaging specifications).

Sidelice (SGQ)

8D

3

K6-Dec-08

The supplier should have the technical documentation to be used in the workstations. This documentation should be easily accessible without disrupting the working activity.

8E

2

recomendado que o fornecedor re-avalie o Considerando a fase de ampliao da empresa Henrique (Diretoria fluxo de processo atual e suas isntalaes e o fato de muitos processos serem Comercial) / fsicas de forma a assegurar a qualidade dos provisrios, no momento, a nica ao Claudio itens fornecidos. O controle de contaminao possvel orientar os colaboradores quanto (Diretoria IndustrialI) (por poeira/areia), durante o processo de a cuidados de manuseio. Aps trmino da laminao e pintura deve ser garantido. ampliao, o prprio layout com as novas disposies dos processos, permitir extio Estes cuidados devem ser considerados no do p nos setores de laminao e pintura de somente nas instalaes futuras (em gel. construo) como nas instalaes atuais.

J

9A 9B 9D

NV NV NV

Lessons Learned

Tpico no avaliado durante a realizao da auditoria.

Improvement Activities for Tier 2 Suppliers Tpico no avaliado durante a realizao da auditoria. Periodic Re-Qualification Tpico no avaliado durante a realizao da auditoria.

Supplier Responsible_____________________ (Name and signature)

SQE_____________________ (Name and signature)

BACK TO PCPA FORM

Contact ListAttendees [Y/N]

NAMEHenrique Ferraz Cludio Ferraz Atlio Sidelice Mata

COMPANYFIACBRAS FIACBRAS FIACBRAS FIACBRAS

DEPARTMENTGerncia Produo Qualidade SGQ

TELEPHONE NUMBER019 3803-1301 019 3803-1306 019 3803-1307 019 3803-1305

FAX NUMBER

E-MAIL

Y Y Y Y

019 3803-1309 [email protected] 019 3803-1309 [email protected] 019 3803-1309 [email protected] 019 3803-1309 [email protected]

PCPA GUIDELINES

1 DOCUMENTATION 1A Drawings Supplier must be in possession of drawings that reflect the change level of the part being produced. The drawings must reflect some form of customer approval; i.e. Design Engineers signature, approved design Supplier must be able to show that the customer approved drawing agrees with the part being shipped.

The technical documentation (Drawings, Technical Specs., Standards and Norms) for the part, product or com and available, whether the part is produced internally or purchased from external sources.

The correct management of documents shall be shown. The auditor shall verify the existence of a list with all are updated to avoid the retention and use of obsolete drawings.

Tolerances must be shown on the drawing. The link between the customers standards shall be shown; e.g. through a tree chart. Geometric Dimensioning and Tolerancing (GD&T) must relate back to data. Key Product Characteristics (KPC's) must be identified for characteristics that are critical to variation in the pa on the car (Note: it is not necessary that all parts have KPC's; the customers product engineering group is resp KPC's).

If the technical documentation supplied by the customer does not indicate the existence of significant characte minimum the supplier should select characteristics that affect close tolerances, fit, function, finish, reliabil process parameters and/or characteristics that affect the successive/final process.

1B Flow Chart

The Process Flow Diagram must be available at the suppliers manufacturing facility. The Process Flow Diagram must begin at the material receiving area and continue through the entire proces and Product storage areas. Any rework or repair operations must be shown on the Diagram and indicate the flow of material back into the repaired or reworked material back to the normal process where production test equipments must re-check and

Gauging and Inspection areas must be shown in the process, whether they are on the production line or off-l result in scrapping the parts, this should be identified on the chart.

1C Process FMEA

Is there a PFMEA available and is it acceptable? Are RPNs acceptable, is it consistent with DFMEA, n KPC's/PQC's/KCC's? Any evidence that it is a living document?

PCPA GUIDELINES

Corrective actions to product/process shall be used to update FMEA's and Control Plans. Since many product failures can be the result of problems in the manufacturing process, the supplier must use developing the PFMEA (e.g. PFMEA severity related to DFMEA severity).

The supplier must be able to describe how critical design characteristics that impact part performance were con

Process/Product FMEA shall be available for review by the customer. Verify that the Process FMEA was generated by a cross-functional team and follows the elements of the Pr occurrence and detection appearing consistent with available quality performance data.

Activities on RPN reduction should be visible and following an ongoing process. A preliminary analysis on the manufacturing, activities and controls means has to be conducted (using ass knowledge of successive processes, knowledge of how the product is used, etc.). At a minimum the supplie close tolerances, fit, function, finish, reliability, durability, and/or are affected by process parameters and/or ch process.

For Family PFMEA you need to have a periodic reviewed document that shows evidence of PFMEA evaluation

All the activities that cause a cost increase for non-quality (rejects, reworks, additional controls, etc.) shall be m

Actions aimed to restore initial/optimal conditions shall be planned/implemented and there shall be evident the e

1D Process Control Plan

Is there a Process Control Plan (PCP) available? Is it acceptable (numbers and controls match PFMEA and Process Flow Chart, includes KPC's/PQC's/KCC's sizes, includes latest EWO/ODM)? Did the supplier use the right mechanics to create the PCP (ref. Fiat Standard 9.01102 and ISO TS 16949)?

PCP must include incoming, throughout the process to labelling and shipping. During the launch period there shall be an Early Production PCP (strengthened Plan). There shall be an organized structure to guarantee the updating of the control methods/conditions with the evol Any significant characteristic shall be designated by appropriate symbols throughout the whole documentation.

The classification of product characteristics shall be indicated on each Control Plan or Operating Instruction specifications and/or preventive analysis performed on the product when requested (FMEA, DOE, etc.).

The management on PCP of Safety/Report Characteristics and/or Homologation Characteristics shall comply w

Control plans and/or Inspection Instructions, compliant with updated drawings, safety and significant character purchased parts. Documentation used to conduct inspections (cycles, drawings, instructions, etc.) shall be available at each work Review the CONTENT of the PCP.

PCPA GUIDELINES

The adequacy of the contents of PCP or written instructions (characteristic, control frequency, sample size, me etc.) shall be ensured. For Family PFMEA you need to have a periodic reviewed document that shows evidence of PCP review for pot Ensure that the Process FMEA was utilized in compilation of the PCP with emphasis placed on KCC's / KPC's.

Seek evidence that control plan is a living document subject to regular review. Process/machine parameters subject to significant alterations over time (e.g. temperatures, times, speed monitored, automatically or manually, with respect to set tolerances.

Check the evidence of controls related to highest RPN's. The control frequencies, size and methodological criteria shall be defined. It is necessary to take into acc functionality of the product as defined by preliminary analysis (e.g. FMEA) and the stability of the process gene

1E IMDS (Management of use limitation for dangerous or forbidden substances)

Supplier shall have the reference set of rules where are written the use limitation (Fiat Cap. 9.01102 Fiat Ca recalled in those set of rules. Supplier must have sent the use limitation to its Suppliers. Supplier must have asked its Suppliers for the involved applications and must retain copy of the documentation

Supplier shall have copy of the documentation requested by Fiat Auto. Supplier shall have answered the requests of Fiat Auto in the expected time and shall retain copy of the sent do If specific materials/components need adjustment due to a substance elimination, Supplier shall carry out compliance with obligations and shall manage the traceability of components before and after modification.

Supplier shall quickly communicate to Fiat Auto the adjustment in progress through the sending of updated involved Part Numbers. Does Supplier insetred all data related to Fiat PN's of its own supplying into IMDS (International Material Data S

Supplier shall have the reference set of rules specific for IMDS (Fiat Cap. 9.01107). Supplier must be registered to site www.mdsystem.com. Supplier shall be aware of the presence of an Help Desk and a reference person in Fiat Auto as an help for the

Supplier shall have involved its own suppliers for the insertion of their data and shall retain the related documen Supplier shall be structured in order to guarantee the MDS insertion for all Fiat PN's within the Benestare control for those arrived by tier 2 Suppliers. Supplier shall update the MDS every time a significant variation of total weight of the product (>10%) occurs or (also regarding surface treatments) through an automatic change of modification level into the IMDS.

Supplier is responsible of all data inserted in its own MDS, also those related to materials/components of Tier 2

PCPA GUIDELINES

2 TOOLING / EQUIPMENT 2A Die status (quality, capacity and timing) The auditor shall verify die status in terms of (building and try-out) timing and functionality. The auditor shall verify the number of cavities and the consistency of life time with the estimated needs. The auditor shall verify the implementation of all requirements contained into the tooling sign off. 2B Equipment status (quality, capacity and timing) The auditor shall verify tooling status in terms of (building) timing and functionality. The auditor shall verify the presence of all necessary equipments to make definitive the process. 2C Preservation conditions of dies machines and equipments

The auditor shall verify the environment where are stored the dies, with particular attention to the conditi identification. Do the conditions guarantee the functionality through time? 2D Ordinary and Preventive Maintenance (machines/dies/equipments)

There shall be a programmed, preventive or predictive maintenance plan for all production equipment dire machine tooling). This plan shall be complied with, and all interventions performed shall be recorded in a logbook (ordina included). The records shall be analyzed to identify any weakness in the equipment and/or in the maintenance plan. There shall be spare parts ready for those machines/tools that may cause stopping of production. Customer owned tooling, gauges, etc., must be permanently identified and included in the maintenance plan.

2E Is the Special Maintenance effective?

There shall be a trained maintenance team, internal or external, available for intervention also in case of emerg Special maintenance interventions must be recorded.

3 PROCESS 3A Tier 2 approval Does an approved supplier list exist for all components needed for the assembled part?

PCPA GUIDELINES

Is there a list of qualified suppliers for each commodity or technology? Are there been any changes on the supplier list agreed during the APQP or the Part Approval? There shall be a systematically updated list indicating one or more qualified suppliers for each specific drawing,

There should be some methods to assess the adequacy of Tier 2 supplier performances. For critical supplier there should be a flexibility to switch production between PPAP approved/benestariati supp

3B Tier 2 components approval

How does the supplier qualify purchased product/material prior to its being used for the product being aud completion and validity of the controls performed or certified; if obtained from multiple moulds, dies, or multi-c mould, die, cavity).

Is the management of modified material/components guaranteed? Before starting production, the sub-supplier shall receive part approval on samples submitted to the supplie production tooling under normal production conditions. Part approval must ensure that the samples produce drawing, technical specifications, and are compatible with the customers processes and use on the final pro moulds, dies or multi-cavity equipment, each mould/die/cavity shall be identified in a permanent way on the pa each of them, in order to carry out separate dimensional controls.

The separate sampling is also required for parts of the same size but different characteristics (colour, hardness

If the approval is granted via deviation, this shall be temporary and shall indicate the quantity and/or the valid tim

Deviation on characteristics that may affect the fit or functionality of the component shall be authorized in writin When applicable, the auditor shall verify the existence of any master samples. The auditor shall verify the conformity of the part to the technical specifications. 3C Are clear operator instructions available and updated for each operation?

Workstations shall be provided with clear operator instructions and parameter set-up instructions according to the planning and development of these instructions, special attention should be given to operations where in easily identifiable for the various steps related to the usage (e.g. classification, colours, pictures/sketches/drawi

The auditor shall verify the knowledge and the application of procedures and job instructions by the operators. The auditor walk the line having the CP and cross-checking the control instructions. Review the adequacy of Visual Controls. 3D Process Capability (Ppk, Cpk & Cmk)

PCPA GUIDELINES

For all important measurable characteristics the process capability indexes must be calculated: Cm and Cmk Cpk for ongoing process capability. It is necessary to consider the process specific characteristics (e.g. presen characteristics under examination (e.g. unilateral, bilateral limits) when defining the statistical model to be used

Acceptable values shall meet customer requests for Cm, Cmk, Cp, Cpk, short and long term (ref. Fiat Norm 9.0

If the process should result not capable, 100% product inspection must be performed. Additionally, the proces a more capable process must be developed.

Capability must be determined under the normal production conditions (e.g. machine or equipment installed in t

Process capability must be monitored over time to guarantee its ongoing stability. This must be done using ade at fixed intervals by the same initial method.

Machine capability must be re-calculated when there are any modifications to the product or process, major m the machine is moved. All the above data, as well as any corrective actions implemented as a result of the elimination of special ca relevant forms. In the event the results of process capability are less than the objective, it shall be provided for: - reviewing periodic data processing and re-calculating control limits; - reviewing sampling frequencies; - increasing inspections accordingly; - availability and traceability of actions recorded in a logbook; - determination of the effectiveness of actions. When the type of process utilized does not permit to operate at the objective/required capability, it is useless t be replaced with a more robust 100% control. Reference documentation shall be updated accordingly. The auditor shall request all values of Ppk, Cpk and Cmk and shall verify if they meets specifications. If it is ne the data directly taken from the process.

3E Restart of production

There shall also be, according to requirements, instructions concerning equipment management in case of prod

Whenever necessary parameter values shall be recorded at the start of production; these should be analyzed t

4 HUMAN RESOURCES & ORGANIZATION 4A Have operators been properly trained?

PCPA GUIDELINES

Personnel shall be qualified to carry out the assigned tasks (use of equipment, compliance with work instruc and identification, consequences of non-conformities to product and the company caused by activities not pro and/or machine failures) and the management/setting of new equipment/machines.

Further qualifications shall take place after training. Training plans shall be commensurate to the importance of the characteristics controlled. The personnel shall be trained on the product, critical points in general and in particular on the difficulties whic (particular attention to be given to Safety/Report characteristics). A record of training courses completed, a versatility of the employees shall be available. This matrix shall be consistent with the days of work and numbe

A periodic updating of training plan shall be defined. The responsibility for the management/updating of the versatility matrix shall be defined. The auditor shall verify the effective distribution of training courses to operators. 4B Management involvement Is Management involved in quality issues? Are Action Plans made within the timing shared with the customer? Is responsibility for implementation assigned and do people understand their responsibility? 4C Are the Resources dedicated to controls sufficient? Is the number of resources involved in the process adequate? Is coverage of all working shifts guaranteed? 4D If more than one shift, does information get passed across shifts?

Seek evidence that effective well defined lines of communication are in place, particularly across shifts, dept's correct personnel. 4E Environment, Health and Safety (EHS)

There shall be a cleannes plan of workplaces in order to maintain the right level according to product criticity. cycles a time dedicated to clean the workstation.

Supplier shall demonstrate - where it is applicable - to have either the Fire Prevention License or, for plants out Is the Supplier certified or have a planning to meet ISO 14001 certification?

5 PRODUCT QUALIFICATION / ONE DAY PRODUCTION 5A Self-Qualification status

PCPA GUIDELINES

Has been the Self-Qualification procedure completed? Are the test results positive? Has been the test reports shared with the customer? If not, are clear the recovery actions related to the underlined anomaly? 5B Integrative Tests Status Has been the samples for integrative tests delivered? Are the test results positive? If not, are clear the recovery actions related to the underlined anomaly? 5C Matchability and Benestare Status Has been the samples for matchability and Benestare tests delivered? Are the test results positive? If not, are clear the recovery actions related to the underlined anomaly? 5D One Day Production

Has been the productive capacity process verified? Is the productive capacity sufficient to meet the customer requests? Does the verified productive capacity include the amount for spare parts and possible production increases req of time? 5E Strengthened Pre-Launch Control Plan

The auditor shall verify the existence of the Strengthened Pre-Launch Control Plan, characterized by the pres frequencies and/or sampling sizes higher than usual and by the presence of a final control station off line for the

This station shall be in adequate conditions for the right functioning (lighted place, necessary equipment availab

The auditor shall verify the adequacy of the Strengthened Pre-Launch Control Plan, for example checking correspond more severe controls or checking if all most important characteristics (Key, Critical, ...) have been ta

The auditor shall verify that the responsible for execution of the Plan have been identified and he correctly certi

6 IMPLEMENTATION OF QUALITY 6A Incoming Material Controls

PCPA GUIDELINES

For purchased material/raw material with significant characteristics assigned, what is the sub-suppliers processes (i.e. control plan), including the recording and filing of inspection results? When it is necessary effective controls, using an adequate sampling plan, shall be exercised both in the Incoming Inspection are prevent/block the use of non-conforming parts or raw material.

The control plan used shall be available and the related results of inspections and tests shall be accessible on r

The methodologies for retaining the performed/certified quality checks shall be defined. All components must be approved with customer requirements. When applicable, it must be verified the existence of deposited reference samples. If there is a computerized system to manage incoming products, sampling plans and acceptance/reject crit method in case the system were not operational.

Control plans shall be developed and used (characteristics, frequencies, sample sizes), assuring the approp characteristics, in order to allow periodic re-examination, data processing and acceptance criteria evolution.

Sub-suppliers may operate in self-certification status if they at least have quality system certification requirem quality performances suitable to the importance/product quality goals.

Procedures shall be defined for suspension/re-establishment of the self-certification status when non-conformit Results of inspections and tests shall always be available and promptly sent to the customer if required.

A specific symbol showing the self-certification status shall appear on the material shipping documents, produc

Audits on incoming lots shall be done randomly and statistical evaluation of the results shall be made in ord indicators. A structure able to intervene on the sub-supplier shall be operating, in terms of: - process auditing for each new product/process; - analysis and sharing of control plans in case a product is new and/or has been modified. There shall be adequate procedures for the management of any modification concerning the product, proces shall be shown through a correct management of product/component modifications. Any product produced before a modification shall be considered as non-conforming unless otherwise provided

6B Production approval

Controls on the first part produced shall be defined and implemented in case of re-start of production, after a process. Conformity to specification shall be guaranteed through: - part approval by appointed personnel with specific approval instructions. The instructions shall be available, co

- OK to produce given by suitable responsible after verification of conformity to specifications of the first parts re - availability of the related documentation concerning parts (charts, instructions, etc.);

PCPA GUIDELINES

- availability of production tools, control and handling equipment; - when applicable, availability at working station of approved master sample part. 6C Process Controls and Tests The supplier shall have a procedure for the detection and immediate action on the process, when process drift

Have been process and machine parameters defined according to how is prescribed into specs, norm (temperature, pressure, voltage, current, load, capacity, torque, etc.)?

Check that process control limits are not confused with tolerances. Control limits have to show continuous improvement process in place. The method of recording data should be verified as suitable for the checks being performed and any control control conditions or special causes of variation should be clearly identified, documented and linked to a rob responsive to the operator.

The supplier shall use a system for the easy identification of conforming products already produced (lot breaker

The supplier shall have procedure to inspect parts back to the last in-control point/part, when a non-conformity There shall be defined and applied rules for the management of major non-conformities including: - identification of the non-conformity; - root cause analyses; - interim and long term corrective actions; - verification of effectiveness; - extension of improvements to similar processes. Corrective actions to the process shall be used to update FMEA's and control plans. The auditor shall verify at least the management of a corrective action subsequent to a non-conformity.

6D Outgoing Quality There shall exist and be applied an adequate Product Audit Plan: - results of previous audits shall be available; - reaction plan if defective parts are discovered shall be available. 6E SQE Audit In the Incoming Material Area select a sample from previously accepted/approved lots and inspect it.

In the Manufacture Area, the auditor shall require parts to be selected from different machines and different inspections, checking the consistency of the results with the previous recorded inspections, and comparing conformity, the results shall be investigated to determine the root cause. The auditor shall verify that the raw material being used is the same as approved by the customer.

PCPA GUIDELINES

During the examination of the complete sequence of operations, audits/inspections shall be performed by the a selected from a minimum of three machines/processes and audit them relevant to selected characteristics.

At the auditors option, check 15 pieces from each of the three machine/processes to demonstrate process con

In the Shipping Area select samples from previously accepted/approved lots that are ready to be shipped characteristics. During the Product Audit, did the inspection personnel show to be adequately trained? Are the inspection methods performed in a way that is consistent and adequate with the inspection requiremen Are the results of the audit conforming?

7 IMPLEMENTATION OF QUALITY 7A Controls recording Conditions and responsibilities shall be defined for the recording and filing of inspection and test results. Procedures for storing the documents in suitable places shall be defined and applied. 7B Controls recording regarding Report/Safety Characteristics

For parts with Saferty/Report Characteristics and/or subject to homologation, controls directly to the product sh order to ascertain conformity of the related characteristics. These controls joins those normally provided on pr of these characteristics and that shall be recorded as per the Fiat Standard 9.01120 "Report Characteristics".

The formalization of these controls shall be on the PCP, both on the step in which the characteristic is generate annex thar resume these controls. This document shall be handed to the SQE. In this formalization shall also be made clear controls performed on characteristics realized at Tier 2 plants.

7C Control instruments management

There shall be a sufficient quantity of inspection and test equipment to carry out the necessary controls (person Are boundary samples available to operators and in use? Do all gauges have operator instructions attached and clearly visible? Are Master Parts available to confirm inspection and error proofing devices? Gauges and measure equipment shall be of adequate measuring class commensurate to the requirements of characteristics.

PCPA GUIDELINES

Availability, suitability, identification, efficiency, correct storage of gauges, test equipment and reference sample

The supplier shall have a written, and properly applied, procedure to audit the capability of the gauges for: stability. The consistency between capability of the gauges and tolerances shall be audited. There shall be a gauge calibration system, including calibration frequency and recording of relevant results.

Gauge identification, calibration status and expiration date (via calibration stickers, colour code, etc.) shall be e

The criteria adopted to guarantee the continuance of required inspections and tests during the gauge calibrat the instrument is sent to external laboratories).

There shall be gauge history cards containing start-up date, interventions of calibration, as found condition, ma

There shall be gauge blocks and/or reference samples for gauge calibration; traceable to the national standard

The appropriateness of the accuracy level of gauge blocks and/or samples required for a correct calibration samples, etc.). Reaction rules shall be defined in the event that any gauge is found out of calibration. Identification and segregation of any non-conforming, not capable gauge shall be ensured. Referability, metrological traceability and calibration expiration date shall be shown. A boundary sample and acceptance standards shall be available and used for inspection of parts having appea shall be developed by either the customer or the supplier.

The boundary sample shall be, when applicable, in each inspection/control station. The identification and recording of the modifications on the boundary samples shall be recorded on specific cha

There shall be evidence of referability and traceability of the master samples. Storage, handling conditions and preservation of the boundary samples shall be defined. There shall also be, according to requirements, instructions concerning gauge management in case of producti

Gauges shall be provided with clear operator instructions, and parameter set-up instructions according to the n planning and development of these instructions, special attention should be given to operations where inspec identifiable for the various steps related to the usage (classification, colours, pictures/sketches/drawings, etc.) t

The master sample shall be, when applicable, in each inspection/control station. The identification and recording of the intervention actions shall be recorded on specific charts. There shall be evidence of referability and traceability of the master samples. Storage, handling conditions, and preservation of the master samples shall be defined. The auditor shall verify the effectiveness of mistake proofing by simulating one or more non-conformities.

Reference samples used to verify the operating condition of gauges and inspection/test equipment shall be ava Reference samples shall be used according to the frequencies set out in the Control Plans.

PCPA GUIDELINES

Error proof (objective) 100% control requires that the detection and rejection of parts are performed in an a down, or goes out of calibration, the parts shall be selected as "non-conforming" (positivity ofconsensus).

7D Re-works

Written instructions shall be developed for reworking, repair or touch-up of non-conforming parts. The instruct equipment, the material to be used, and the methods of identification and control of the reworked products.

The reworked/repaired products, when applicable, shall be clearly identified and traceable. The reworked/repaired products shall be reinserted into the principal flow at the point previous to where the n checked with the same gauges or test equipment that discovered the non-conformity.

7E Non-conforming products management

Non-conforming parts shall be adequately identified via signs/documents and properly segregated (well delim containers). There shall be defined rules for the management of non-conforming products and relevant responsibilities:

- identification; - segregation; - re-work/repair; - re-check; - reject or scrap; - deviations. When a non-conformity is discovered, the relevant management procedure shall be correctly applied (segregat the causes, corrections on processes, control of effectiveness of corrective actions).

8 LOGISTIC 8A Traceability Traceability shall be guaranteed for safety components and/or for components subject to specific regulation.

When the components have characteristics classified as Safety/Report or subject to homologation, it sha inspections and tests according to what is agreed with the customer and according to what is required by variou Norm 9.01102).

There shall be a traceability link between the packaging label and the product, lot, packing list, quantity, revis controls used both in internal and external processes.

Lot traceability to the raw material and/or sub-supplier components shall be maintained when required by contr

PCPA GUIDELINES

There shall be a clear identification of the batches assigned to Quality Department inspections/checks.

When it is required, on the finished product shall be reported the Supplier's alphanumeric code, with proper mo 07611. Materials stored in stock shall be rapidly identifiable by means of documentation reporting codes and lot numbe

There shall be adequate procedures for the management of any modification concerning the product, proces shall be shown through a correct management of product/component modifications. Any product produced before a modification shall be considered as non-conforming unless otherwise provided

8B Identification

The identification tag/label shall be visible for materials in stock. All semi-finished and/or finished products shall be positively identified (e.g. part number, lot code, quantity) a respect to the different phases of the manufacturing cycle (operations completed). The application and appropriateness of the provisions to visualize the inspection status (e.g. color coded tags) - product waiting to be inspected; - product inspected and accepted; - product waiting for a decision; - non-conforming product; - waste product (scrap) (segregation/identification in order to avoid any re-insertion into the process). The rejected product area, where the non-conforming material is stored waiting for its final destination, must personnel. Identification conditions shall be commensurate to the risk and type of process. Identification may be related to every single piece, to the container or the work cell, and shall enable to concerning inspections, gauges/test equipment, operator, date, team, etc.

Identification shall be clear, even after the partial use of the lot. Consistency between identification and traceability requirements shall be guaranteed in particular for products w

Each box, container, packaging, etc. shall be identified. Periodic controls shall be carried out to ascert correspond. Non-conforming products shall be identified and segregated in the relevant areas. Product identification/marking shall comply with the customers specifications and has to be written, in cas assembly, if they are available loose on the spare parts market. The auditor shall ensure all packaging is properly identified. 8C FIFO There shall be a system guaranteeing FIFO throughout the process flow.

PCPA GUIDELINES

Is the expiration date for perishable products managed? Product lots shall be sent to the following operation in an organized manner (FIFO, identification of destination If there is an Information Retrieval System, in the event of a failure, FIFO shall be managed by means of an eq

8D Appropriate handling and packaging

Product storage areas at each workstation shall be commensurate to requirements. Packaging used shall be designed to assure, even in the case of repackaging, the integrity of the single compo Packaging shall be identified according to standards agreed with the customer (packaging specifications). Operating instructions shall be defined in case of damaged packaging.

During unloading, staging and storage operations, environmental conditions shall be such as to protect the inte Handling, transport and containing means (forklifts, transpallets, etc.) shall be efficient and operated under safe

Storage shall be done on pallets, shelves, etc.; these shall be suitable and in good conditions: cleaning, mainte piling to ensure safety and product integrity. Storage/stockpiling areas shall be sufficiently sized to contain the material, located in a logical way with re protect the product, with easy access and safe handling. The supplier shall not use customer containers/packaging for internal handling.

8E Appropriate process flow

The technical documentation to be used in the workstations shall be easily accessible without disrupting the wo Material flow shall be designed to avoid missing of operations or mix of parts with similar products.

Equipment for production of lots/work orders not currently under production shall be properly identified a management of components/products being manufactured. Review the actual manufacturing area against the Process Flowchart, general layout and process control p Receiving to Dispatch. The workplace should be configured as per the general layout and be provided with adequate space, lighting, e

Locations should be designated and, where necessary, secured for the storage of gauges, scrap, reworked par

Provisions should also be made for display of Process Control Plans, Standard Operation Sheets, Work Instruc etc.

9 CONTINUOUS IMPROVEMENT 9A Lessons Learned

PCPA GUIDELINES

Are the issues found on current product managed and analyzed? Are the relevant corrective actions implement

9B Improvement Activities for Tier 2 Suppliers

Does an improvement plan related to tier 2 suppliers exist, in order to improve the quality of their product/proce

9C Warranty

Are developed analysis/prevention system that allow to prevent and avoid any claim from field? Are managed and analyzed the data related to problems detected in field? Are the samples returned from field analyzed (SITRA cards etc.)? Are Corrective Actions related to those analysis implemented? Does a system for collecting and stratification of data exist (QT, TESIS, SITRA, etc.)? Are the qualified tier 2 suppliers involved in the above mentioned activities going back up the processes an activities transferred to the new products in development?

9D Periodic Re-Qualification

Periodic process reviews and/or audit shall be performed in order to assure the maintenance over ti qualification/approval of the process. A periodic re-qualification of the supplied system, assembly or component shall be planned, with frequencies sh

In case there is not a specific request by the customer, the supplier shall arrange a plan by itself with frequency

The re-qualification process shall include all the necessary tests for the self qualification of the system, asse C.C.Q. (Certificate of Quality and Conformity). They are the tests that are written into the shared Self Qualificat

9E Quality and Environmental certifications

The auditor shall require to supplier copy of its Quality System Certificate and Environmental Management C equivalent).

ONE PAGE REPORT N ___Project: Part Description: Part Number: Prod. Family: Date: Sprayer - Hood Hood - Fuel Tank 87271096 9/11/2008 ODM: Supplier Name: Supplier Code: Manufact. Plant: SQE:

Supplier QualityFIACBRAS BKQ52 Sumar (SP) R. Mximo (vx822)

Abstract up to 3 arguments in order of severity:

1 3 5

BACK TO PCPA FORM

Argument:

(Program Review 1, 2, 3, etc., PCPA 1, 2, 3 etc., OK to samples or batches for Process Verification, Pre-series, etc.)

Problem / Root cause:

Containment / Corrective Actions: (Insert responsible and date)

Timings: 1st Try out: 1st Part: Interim: Self-qualification:PROCESS VERIFICATION (VP)

CW 12 Sampling for Benestare: CW 14 Sampling for Integr. Tests: CW15 Batch VP, Pre-Serie: CW 27 PRE-SERIES (PS) SQE Coord. Buyer E&D RELEASE TO PROD. (DaP) Project Coord. Sviluppo Supplier CURRENT PRODUCTION SQM Piattaforma

CW 22 CW 21 CW 15

Distribution: SQD QPL